Upload
lammien
View
215
Download
0
Embed Size (px)
Citation preview
SESSION D “TAKT TIME and LOGISTICS”:
PROCESS and MILESTONE PLANNING
& SYSTEMATIC COMPLETIONGeometry and Function / Experiences and Next Steps
Hans Thomas Holm
Head of Project Life Science
Statsbygg, Oslo, Norway
@ Linked In
Page 2
FROM: TO:
ACADEMY of ART and DESIGN LIFE SCIENCEin BERGEN (KHiB), 2013-2017 in OSLO, 2018-2024
EXPERIENCES, WHAT WE DID & NEXT STEPS &
LESSONS LEARNED IMPROVING FURTHER
Rev: 09.May.2018
Page 3
Rev: 09.May.2018
ACADEMY of ART and DESIGNin BERGEN (KHiB), 2013-2017
EXPERIENCES, WHAT WE DID &
LESSONS LEARNED
About Academy of Art and Design:
- All works completed by May 1.st 2017
- 1 100 000 000 NOK (incl. VAT, 2017)
Construction Project
- 14 800 sqm
- Passive house
- 11x Design Bid Build
Just ahead of time
Just below budget
On quality
Page 4
Rev: 09.May.2018
ACADEMY of ART and DESIGNin BERGEN (KHiB), 2013-2017
Lean Strategy
Lean Process Planning
Lean Design
Systematic Completion
Lean Construction
Takt Planning & 14-10-6-4-1
BIM
Main Success Factor:
Geometry and Function Takted together
Page 5
Rev: 09.May.2018
ACADEMY of ART and DESIGNin BERGEN (KHiB), 2013-2017
MAIN PROCESS PLAN MANAGEMENT
(aka Milestone Planning)
Defining Main Processes
Defining Milestones (Keypoints)
Identifying Dependencies
Identifying Constraints
Page 6
Rev: 09.May.2018
ACADEMY of ART and DESIGNin BERGEN (KHiB), 2013-2017
LEAN DESIGN
Defining Milestones (Keypoints)
Splitting up in many small pieces
Defining Topics
Defining Topic Owners
Identifying Dependencies
Identifying Constraints
Page 7
Rev: 09.May.2018
ACADEMY of ART and DESIGNin BERGEN (KHiB), 2013-2017
TAKT PLANNING
& «14-10-6-4-1»
7 conditions for a sound activity
Page 8
Rev: 09.May.2018
ACADEMY of ART and DESIGNin BERGEN (KHiB), 2013-2017
SYSTEMATIC COMPLETION
(Takt Planned)
Page 9
Rev: 09.May.2018
ACADEMY of ART and DESIGNin BERGEN (KHiB), 2013-2017
KHiB BOOKLETS #1-5
#4 Lean Design (in progress)
#5 BIM@KHiB (in progress) All free pdf available
Page 10
Rev: 09.May.2018
Page 11
Rev: 09.May.2018
LIFE SCIENCEin OSLO, 2018-2024
NEXT STEPS &
IMPROVING FURTHER
About Life Science:
- Highly advanced multi research facility
- Planned completed by Dec 1.st 2024
- 5 670 000 000 NOK (incl. VAT, 2018)
Construction Project
- Approx. 70 000 sqm
- «Footprint» 17 000 sqm
- 3-5 Design Build contracts (TBD)
- 1 140 000 000 NOK (incl. VAT, 2018)
User Equipment
Objectives:
Lean Extreme / Process Planning / Takt /
Systematic Completion / Logistics / BIM
Page 12
Rev: 09.May.2018
LIFE SCIENCEin OSLO, 2018-2024
IMPROVING FURTHER
SYNERGY:
CONSTRUCTION («GEOMETRY»)
SYSTEMATIC COMPLETION («FUNCTION»)
USER EQUIPMENT («THINGS»)
DIGITALSTRATEGY
LEANSTRATEGY
LOGISTICSSTRATEGY
SYSTEMATICCOMPLETION
STRATEGYAs Built
MaintenanceOperations
BIMJan. 2018 Dec. 2024
Involving subcontractors and suppliers much earlier.Taking ‘7 conditions for a sound activity’ further.
Page 13
Rev: 09.May.2018
LIFE SCIENCEin OSLO, 2018-2024
MAIN PROCESS PLAN MANAGEMENT
«LOD-1»
LLI
«LOD-2»
LLI
«LOD-3»
LLI
«LOD-4»
LLI
«LOD-5»
LLI
«LOD-6»
LLI«LOD-1» «LOD-2» «LOD-3» «LOD-4» «LOD-5» «LOD-6»
Pr-1 (Project Management)
Pr-2 (Quality Management)
Pr-3 (Design)
Pr-4 (Procurement)
Pr-5 (Construction)
Pr-6 (User Equipment)
Pr-7 (Systematic Completion)
Pr-8 (Public Permissions)
Pr-9 (Facility Management)
MANAGEMENT- & MAIN PROCESS PLAN w/ Keypoints
Design Construction
Infra/Demolition Foundations Structure Enveloping Completed Handover
LOD = Level of Development ~ Freeze Level for changes ~ Scope Check Points / LLI = Long Lead Items
(2 W Takt) (1 W Takt)
Roles
(LODs to be defined.)
Pr-10 (User Involvement)
Reverse Planning
Systematically
Page 14
Rev: 09.May.2018
LIFE SCIENCEin OSLO, 2018-2024
SYSTEMATIC COMPLETION
Likely more than 650 different systems.
An extremely complex building.
Page 15
Rev: 09.May.2018
LIFE SCIENCEin OSLO, 2018-2024
SYSTEMATIC COMPLETION as a PROCESS
FOUNDATIONS for SYSTEMATIC
COMPLETION
Functional specifications
- System by system
- Integrated
System Diagrams
Test Procedures
Integrated tests
System function
testsArea tests
TESTING
CONSTRUCTION
Full-scale test
User testsTabletest
DETAIL ENGINEERING
Project phase
Testing
Training Theoretical Inspection and testing Building Management System (BMS)
Verification of Screenshots (BMS) Verification of screenshots (BMS)
Hand over
BMS
Page 16
Rev: 09.May.2018
Complete Systems List
- Defined acceptance criteria
- Finished AND Accepted test
By using measureable milestones and
actively relate to the acceptance criteria can
one impose KPI’s adapted to the project.
LIFE SCIENCEin OSLO, 2018-2024
SYSTEMATIC COMPLETION as a PROCESS
Testing
Training
Foundations
TABLE TESTS:
- Theoretical talk through test
- All stakeholders attend
- All systems
- system by system, or
- in naturally associated groups
- Executed before ordering
Page 17
Rev: 09.May.2018
LIFE SCIENCEin OSLO, 2018-2024
CHALLENGES
- Creating a good and inspiring project mentality and culture
- Thinking and creating flow along all processes
- Efficient logistic systems for all products
- Integrating all digital systems
- Early involvement of subcontractors and suppliers
- Industrialising the construction site as much as possible
- Creating value in every step, reducing waste
- Influencing the industry enough to make it change
- Complete works on time with all systems working according to plan
Page 18
Rev: 09.May.2018
QUESTIONS?
THANKS!
Hans Thomas Holm / Statsbygg
Statsbygg 2007 –
The LEAN way at Statsbygg 2010 – #1 Domus Medica, #2 KHiB, #3 Life Science
Torino 2006 Olympic Winter Games 2004 – 2006 TOROC Transportation
Lillehammer 1994 Olympic Winter Games 1992 – 1994 LOOC Transportation
Various Project Management 1991 –
MSc Chalmers Technical University 1991
Karlsruhe Technische Hochschule 1987
Christian August / Halden 1982
5 languages
(* 1964)