Upload
duongdang
View
222
Download
2
Embed Size (px)
Citation preview
12/19/2011
1
The Construction Specifications Institute
Audio Sessions
Session 7
SITE VISITS, OBSERVATION, AND INSPECTION
Construction Contract Administration
Education ProgramCertified Construction Contract Administrator (CCCA)
Preparatory Course2011
1www.csinet.org
This presentation is protected by US and International copyright laws. Reproduction, distribution, display and use of this presentation without written permission of the speaker and The Construction Specifications Institute is prohibited.
© The Construction Specifications Institute 2011
The Construction Specifications Institute is a Registered Provider with The AmericanInstitute of Architects Continuing Education Systems. Credit earned on completion ofthis program will be reported to CES Records for AIA members. Certificates ofCompletion for non-AIA members available on request.
This program is registered with the AIA/CES for continuing professional education.As such, it does not include content that may be deemed or construed to be anapproval or endorsement by the AIA of any material of construction or any method ormanner of handling, using, distributing, or dealing in any material or product.Questions related to specific materials, methods, and services will be addressed atthe conclusion of this presentation.
AIA
2
12/19/2011
2
The Construction Specifications Institute
Learning Objectives• To understand the difference between observations and
inspections
• To explain – A/E’s responsibilities for observations and inspections
– Contractor’s responsibilities for inspections
• To understand the importance of keeping the Owner informed
• To gain an insight into the limitations of authority of the Owner, A/E, and Contractor
• To introduce the responsibilities for defective and nonconforming work
• To explore the importance of record keeping and reporting
• To describe the procedures for maintaining field record documents
3
The Construction Specifications Institute
Session OutlineSTUDY GUIDE: Subject Matter Area No. 7 10%
SITE VISITS, OBSERVATION, AND INSPECTION
4
A. Construction Observation and Inspections
B. Contract Requirements and A/E Responsibilities1. A/E site visits
a. Role and frequencyb. Scheduling
2. Limitations of responsibility3. More extensive site
representation4. A/E inspections
a. Number and purposeb. Punch listsc. Requirements of Contractor
C. Owner Responsibilities1. Special inspections2. Owner observations
D. Contractor Responsibilities1. Contractor’s supervision2. Contractor inspection3. Contractor’s punch list
E. Working Relationship1. Team concept2. Conduct at the project site3. Project site safety4. Accidents5. Tolerances and clearances
Continued on following slide
12/19/2011
3
The Construction Specifications Institute
Session OutlineSTUDY GUIDE: Subject Matter Area No. 7
SITE VISITS, OBSERVATION, AND INSPECTION
5
F. Defective and Nonconforming Work1. A/E’s authority for rejecting work2. Owner’s decisions on defective
work3. Stopping the work
G. Delivery, Storage, and Protection of Products
Continued from previous slide
H. Record Keeping and Reporting1. Field observation reports2. Use of photographs and video3. Use of forms and log forms4. Filing and retrieval of
documentation
I. Project Record Documents
The Construction Specifications Institute 6
SITE VISITS, OBSERVATION, AND INSPECTION
STUDY GUIDE AREA NO. 7
12/19/2011
4
The Construction Specifications Institute
Construction Observationsand Inspections
STUDY GUIDE: Submit Matter Area No. 7 - A.
7
Construction Observations and Inspections
• Basic to quality control is that participants have certain responsibilities for making observations and inspections– Observe – Perceive, notice,
see
– Inspection – Examine carefully and crucially, especially for defects
• Distinction between observation and inspection is important
8
Construction Contract Administration Practice Guide: 6
12/19/2011
5
Owner-A/E Responsibilities• Standard Owner-Architect agreements and standard
Conditions of the Contracts typically stipulate A/E periodically visit construction site to– Ascertain progress and quality of work
– Inform Owner of
- Known deviations from contract documents - Defects and deficiencies observed in the Work
– Keep Owner informed of progress of the work
– Conduct inspections to determine dates of
• Substantial completion• Final completion
Construction Contract Administration Practice Guide: 6
9
Owner-Contractor Responsibilities• Standard Owner-Contractor agreements and standard
conditions of the contract typically stipulate Contractor to– Prior to bidding or commencing the work, visit site to
- Correlate conditions- Coordinate observations with contract documents- Report discrepancies to A/E
– Direct and supervise the work
– Control means, methods, and techniques
– Continually inspect the work to ensure each portion is ready to receive subsequent portions
– Arrange for inspections required by authorities having jurisdiction
Continued on following slide
10
Construction Contract Administration Practice Guide: 6
12/19/2011
6
Owner-Contractor ResponsibilitiesContinued from previous slide
– Required to inspect work to qualify for Substantial Completion
– Prepare comprehensive list (initial punch list) of items to be completed or corrected prior to final payment
11
Construction Contract Administration Practice Guide: 6
Owner Responsibilities
• Standard Owner-Contractor agreements and standard conditions of the contracts typically stipulate Owner to– Provide site information
- Physical characteristics- Legal limitations- Utility locations
– Provide other information or services to Contractor upon request
– Be responsible for the work
- By Owner- By other Contractors
12
Construction Contract Administration Practice Guide: 6
12/19/2011
7
Benefits of Teamwork• Timely communication between A/E and Contractor helps
avoid misunderstandings
• Good communications– Prevents small problems from escalating into claims
– Ensures accurate interpretations of contract documents
– Provides necessary information when it is needed
• Preconstruction and progress meetings helps establish– Good lines of communication
– Mutual understanding of project roles, responsibilities, and contractual relationships
Construction Contract Administration Practice Guide: 6
13
Benefits of Teamwork• Using following principles allows participants to focus on
project requirements rather than problems– Coordination
– Cooperation
– Communications
– Conformance
Construction Contract Administration Practice Guide: 6
14
12/19/2011
8
The Construction Specifications Institute
Contract Requirements and A/E Responsibilities
STUDY GUIDE: Submit Matter Area No. 7 - B.
15
1. A/E site visitsa. Role and frequencyb. Scheduling
2. Limitations of responsibility3. More extensive site representation4. A/E inspections
a. Number and purposeb. Punch listsc. Requirements of Contractor
A/E Site Visits• As previously stated, A/E typically required to visit the site
– At intervals appropriate to the stage of construction; not required to make exhaustive or continuous inspections
– To become generally familiar with progress and quality of the completed work
– To determine in general if work observed is being performed in accordance with contract documents
– Advise Owner of defects and deficiencies observed
• Periodic site observations help ensure– Coordination between design and construction
– Timely communication between A/E and Contractor
– Accurate interpretation of contract documents
– Conformance with contract documents
Construction Contract Administration Practice Guide: 6.2.1
16
12/19/2011
9
A/E Site Visits• Site visits at “intervals appropriate” require A/E to exercise
professional judgment in determining– Frequency
– Duration
• Beneficial for A/E to schedule more site visits during– Critical construction activities
– Early stages of construction
Construction Contract Administration Practice Guide: 6.2.1
17
• Use site visits to evaluate contractor’s application for payment
Limitations of Responsibility• Standard Owner-Architect agreements and standard
conditions of the contracts stipulate A/E not responsible for– Continuous inspection
– Construction means and methods
– Project site safety
– Contractor’s failure to perform
– Stopping work
– Coordinating work of contractor or subcontractors
Construction Contract Administration Practice Guide: 6.2.2
18
12/19/2011
10
More Extensive Site Representation• Occasions when Owner wants more extensive A/E
representation at project site, often in form of full-time project representation
• Purpose of full-time project representation– Assist A/E in providing more continuous observation of project
– “usually” not empowered to act in A/E’s behalf
• Use an add service to add to A/E contract.
• Duties and responsibilities of full-time project representation– Observes work progress and quality of work
– Monitoring construction progress schedule
– Reviewing contract documents request for interpretation and change
– Attending project meetings
Continued on following slideConstruction Contract Administration Practice Guide: 6.2.3
19
More Extensive Site RepresentationContinued from previous slide
– Observes tests
– Maintains records
– Keeps diary or logbook
– Assist with shop drawing review
– Review application for payment
– Review punch lists
– Assist with final inspection
– Review record documents periodically
– Review partial occupancies to minimize claims for damage
Construction Contract Administration Practice Guide: 6.2.3
20
12/19/2011
11
A/E Inspections• Standard Owner-A/E agreements typically stipulate only
two inspections
• Contractor prepares initial punch list
• Contractor notifies Owner and A/E that project is substantially complete
• A/E inspects work – Verifies initial punch list
– May add additional items to develop final punch list
• A/E establishes date of substantial completion
• Owner may occupy project for it’s intended use
Continued on following slide
Construction Contract Administration Practice Guide: 6.2.4
21
A/E InspectionsContinued from previous slide
• Contractor corrects items on final punch list
• A/E inspects work and verifies final punch list
• Final completion– Owner has made final payment to Contractor
– Contractor has accepted final payment
Construction Contract Administration Practice Guide: 6.2.4
22
12/19/2011
12
The Construction Specifications Institute
Owner ResponsibilitiesSTUDY GUIDE: Submit Matter Area No. 7 - C.
23
1. Special inspections2. Owner observations
Owner Responsibilities• Owner not required by standard documents to make site
observations
• In most instances, Owner relies on A/E for observations
• Some Owners have experienced staff to perform site related activities but only to supplement A/E
• Applicable codes may require Owner to provide– Special inspections
– Testing
• A/E may need to monitor testing and inspection services– To verify required activities are taking place in a timely manner
– To verify communications and reporting are taking place
Construction Contract Administration Practice Guide: 6.4
24
12/19/2011
13
Owner Responsibilities• Independent testing and inspection agencies
– Perform required testing and inspections on behalf of Owner
– Submit certifications of compliance with contract documents and governing codes to AHJ’s
• Special inspections include– Concrete and reinforcement
– Foundations
– Structural framing
– Earthwork, including excavation and fill
– Fireproofing
– Fire sprinklers and alarms
– Elevators
– Ch 17 in IBC
Construction Contract Administration Practice Guide: 6.4
25
Owner Responsibilities• Regarding Owner
observations– Owner may wish to perform
construction contract administration without assistance of A/E
– Certain Owners have expertise and personnel to perform construction contract administration
– A/E may not be responsible for construction contract administration except those required by state licensing law
Construction Contract Administration Practice Guide: 6.4
26
12/19/2011
14
The Construction Specifications Institute
Contractor ResponsibilitiesSTUDY GUIDE: Submit Matter Area No. 7 - D.
27
1. Contractor’s supervision2. Contractor inspection3. Contractor’s punch list
Contractor Responsibilities• Standard conditions of the contract typically stipulate Contractor
should perform the following as another opportunity for quality improvement– Visit the site and become familiar with existing conditions
– Carefully study and compare the contract documents with each other
– Report to A/E any conflicts, errors, ambiguities, or discrepancies discovered
• Contractor is responsible– For construction of the project in conformance with contract documents
– For supervision and direction of the construction
– For construction means, methods, techniques, sequences, and procedures
– For acts and omissions of companies working under Contractor
Construction Contract Administration Practice Guide: 6.3
28
12/19/2011
15
Contractor Responsibilities• Standard Owner-Contractor agreements typically stipulate
Contractor to– Make inspections
– Arrange for certain other inspections
– Inspect portions of work already completed to ensure they are ready for subsequent work
– Obtain necessary inspections required by AHJ’s
– Prepare initial punch list for substantial completion
• Contractor prepares initial punch list based on comprehensive inspection; A/E usually adds to Contractor’s list thus making the final punch list
Construction Contract Administration Practice Guide: 6.3
29
The Construction Specifications Institute
Working RelationshipSTUDY GUIDE: Submit Matter Area No. 7 - E.
30
1. Team concept2. Conduct at the project site3. Project site safety4. Accidents5. Tolerances and clearances
12/19/2011
16
Working Relationship• Good working relationships
– Primary focus on quality of construction
– Helps to resolve problems and conflicts quickly
• Team concept – Contract document interpretations by A/E (IDM) must be impartial
– Communications to subcontractors from A/E, Owner, and consultants should be directed through Contractor
– A/E should give instructions in writing and direct to Contractor’s project manager or superintendent who will direct construction personnel
– Oral communications should be documented in writing
Construction Contract Administration Practice Guide: 6.6
31
Conduct at the Project Site• Participants should exercise proper conduct at the site
– Maintaining professional demeanor
– Being polite and courteous
– Showing respect
– Following proper lines of communication
– Adhering to Contractor’s procedures for visitors
Construction Contract Administration Practice Guide: 6.7
32
• Participants should keep others appraised of relevant concerns, questions, and decisions
12/19/2011
17
Project Site Safety• Contractor is responsible
• Cannot be ignored by Owner and A/E, they– Are responsible for safety of their employees
– Should educate their personnel
– Should follow safety procedures established by Contractor
• A/E should not– Seek out hazardous conditions
– Review Contractor’s safety program
– Attend Contractor’s safety meetings
• If A/E notices condition that may not be safe– Should bring condition to attention of Contractor
– Notify Owner in writing
Construction Contract Administration Practice Guide: 6.8
33
Project Site Safety• Contractor is responsible for investigating accidents
• In case of imminent danger, measures need to be in place to– Save personnel first
– Save property second
• Once danger has passed, accident scene should not be disturbed until proper investigation has been completed
Construction Contract Administration Practice Guide: 6.8
34
12/19/2011
18
The Construction Specifications Institute
Defective and Nonconforming WorkSTUDY GUIDE: Submit Matter Area No. 7 - F.
35
1. A/E’s authority for rejecting work2. Owner’s decisions on defective work3. Stopping the work
Defective and Nonconforming Work• Standard Conditions of the Contracts typically stipulate
– A/E has right to have work uncovered if it was concealed contrary to A/E’s written request
– A/E has authority to reject work that does not conform to contract documents, also identified as defective work
– Only Owner can accept nonconforming work
• Contractor is obligated to correct defective work
• A/E should – Verify that defective work has been corrected
– Verify that corrected work is proceeding according to contract documents
– Order additional testing or inspection of suspected work
Construction Contract Administration Practice Guide: 6.9
36
12/19/2011
19
Defective and Nonconforming Work• If additional testing or inspection is ordered by A/E
– If found to be nonconforming, Contractor pays
– If found to be in conformance, Owner pays
• If Contractor refuses to correct nonconforming work – Owner has right to correct work
– Cost deducted from contract sum by change order
Construction Contract Administration Practice Guide: 6.9
37
Defective and Nonconforming Work• Standard conditions of the
contracts typically stipulate– A/E does not have authority to
stop work
– Owner may order Contractor to stop work until reason for stoppage has been eliminated
– Contractor has right to stop work for non-payment
Construction Contract Administration Practice Guide: 6.9
38
12/19/2011
20
The Construction Specifications Institute
Delivery, Storage, and Protection of Products
STUDY GUIDE: Submit Matter Area No. 7 - G.
39
Delivery, Storage, and Protection of Products
• Contractor is responsible for following concerning products– Scheduling
– Receiving
– Inspecting
– Unloading
– Handling
– Protecting
– Storing
- Products can be stored on-site or off-site- Standard conditions of the contract typically stipulate site should
not be encumbered with products- On-site storage should be coordinated with construction sequence
Construction Contract Administration Practice Guide: 6.10
40
12/19/2011
21
Delivery, Storage, and Protection of Products
• Off-site storage – Usually in location mutually agreed upon – typically bonded warehouse
– A/E usually confirms
- Location
- Products are correct
- Correct quantity
- Secure
- Protected
- Clearly identified for project
– Covered by insurance
• A/E’s verifications typically completed before applications for payment are certified
Construction Contract Administration Practice Guide: 6.10
41
Delivery, Storage, and Protection of Products
• Requirements may vary depending on – Manufacturer’s requirements
– Industry standards
– Common sense
• Requirements for product protection typically stipulated in PART 1 – GENERAL of the respective specification
• Requirements for installed work protection typically stipulated in PART 3 – EXECUTION of the respective specification
• Manufacturer’s requirements should be followed to ensure– Products are not damaged
– Warranty provisions are not voided
Construction Contract Administration Practice Guide: 6.10
42
12/19/2011
22
The Construction Specifications Institute
Record Keeping and ReportingSTUDY GUIDE: Submit Matter Area No. 7 - H.
43
1. Field observation reports2. Use of photographs and video3. Use of forms and log forms4. Filing and retrieval of documentation
Record Keeping and Reporting• Documentation created by construction contract
administration– Effective for communication
– Good for historical record of construction stage activities
– Aids in future recollection
• Ongoing stream of information among participants
• Timely responses are crucial to successful completion with minimum of difficulties
• A/E maintains records of many items during construction– Field observation reports
– Correspondence
Continued on following slide
Construction Contract Administration Practice Guide: 6.12 and 6.12.1
44
12/19/2011
23
Record Keeping and ReportingContinued from previous slide
– Meeting minutes
– Communication reports
– Submittals
– Test reports
– Payment requests and certifications
– Schedules
– Request for interpretation, clarification, or information
– Proposal requests and change order requests
– Contract document modifications
Construction Contract Administration Practice Guide: 6.12 and 6.12.1
45
Field Observation Reports• A/E’s record of site visits consists of
– Site observations
– Communications
• Reports for benefit of A/E and may be used for communication between Owner and Contractor
• In addition to administrative aspects, field observation reports contain– Weather conditions
– Site conditions
Continued on following slide
Construction Contract Administration Practice Guide: 6.12.2
46
12/19/2011
24
Field Observation ReportsContinued from previous slide
– Remarks
- Status of project, work in progress, work completed
- Products delivered/stored on site
- Items discussed
- Deficiencies noted
- Contractor comments and queries
- Reports must be– Objective
– Factual
– Complete
Construction Contract Administration Practice Guide: 6.12.2
47
Field Observation Reports
Construction Contract Administration Practice Guide: 6.12.2 and Figure 6.3
48
12/19/2011
25
Field Observation Reports• Contains observations about work in progress
• Documents – Pertinent remarks offered
– Oral instructions given by any participants
• Helpful to inquire whether Contractor has any unreported claims
• Documentation of potential claims brings them to consciousness of participants so they can be quickly resolved
Construction Contract Administration Practice Guide: 6.12.2
49
Field Observation Reports• Should not include
– Extraneous information
– Supposition
– Hearsay
– Conjecture
– Other nonfactual judgments
• Should include if work is or is not in compliance with contract documents
• A/E informs Contractor of work rejected for nonconformance with contract documents
Construction Contract Administration Practice Guide: 6.12.2
50
12/19/2011
26
Use of Photographs and Video• Provides visual record of
construction
• May be required by specifications to show construction progress
• Valuable companion to field observation reports
• Can document nonconforming work
• Represents actual conditions which allows later analysis and review
Construction Contract Administration Practice Guide: 6.12.5
51
Use of Forms and Log Forms• Standard forms
– Speed up documentation and written communication processes
– Keeps participants informed and helps prevent problems
– Helps avoid misunderstandings
• Log Forms– Records status of various construction related documents
– Database can be searched for submittals in various ways, including those yet to be processed or even received
Construction Contract Administration Practice Guide: 6.12.6
52
12/19/2011
27
Filing and Retrieval of Documentation• A structured filing system
should be established
• Organized by – File folders
– Binders
– Electronically
• Documents filed separately, in sequence, with most recent on top
Construction Contract Administration Practice Guide: 6.12.7
53
Filing and Retrieval of Documentation
Construction Contract Administration Practice Guide: Figure 6.8
54
12/19/2011
28
The Construction Specifications Institute
Project Record DocumentsSTUDY GUIDE: Submit Matter Area No. 7 - I.
55
Project Record Documents• Standard conditions of the contract and Division 01
specifications typically stipulate Contractor should maintain documents that record actual constructed conditions
• Actual conditions of construction should be recorded concurrently with construction progress on drawings, such as– Measured depths of foundation elements
– Measured horizontal and vertical locations of underground utilities
– Measured locations of internal utilities concealed within construction
– Field changes of dimensions and details
– Details not in original contract documents
– Changes and modifications
– References to related shop drawings
Construction Contract Administration Practice Guide: 6.14
56
12/19/2011
29
Project Record Documents• Record set of project manual normally required to show
– Modifications
– Record of actual construction
– Manufacturers and product information of each product installed
– Other information not originally specified
Construction Contract Administration Practice Guide: 6.14
57
• Completed set of record documents submitted by Contractor to A/E during project closeout
• A/E transmits record documents to Owner
The Construction Specifications Institute
Review OutlineSTUDY GUIDE: Subject Matter Area No. 7
SITE VISITS, OBSERVATION, AND INSPECTION
58
A. Construction Observation and Inspections
B. Contract Requirements and A/E Responsibilities1. A/E site visits
a. Role and frequencyb. Scheduling
2. Limitations of responsibility3. More extensive site
representation4. A/E inspections
a. Number and purposeb. Punch listsc. Requirements of Contractor
C. Owner Responsibilities1. Special inspections2. Owner observations
D. Contractor Responsibilities1. Contractor’s supervision2. Contractor inspection3. Contractor’s punch list
E. Working Relationship1. Team concept2. Conduct at the project site3. Project site safety4. Accidents5. Tolerances and clearances
Continued on following slide
12/19/2011
30
The Construction Specifications Institute
Review OutlineSTUDY GUIDE: Subject Matter Area No. 7
SITE VISITS, OBSERVATION, AND INSPECTION
59
F. Defective and Nonconforming Work1. A/E’s authority for rejecting work2. Owner’s decisions on defective
work3. Stopping the work
G. Delivery, Storage, and Protection of Products
Continued from previous slide
H. Record Keeping and Reporting1. Field observation reports2. Use of photographs and video3. Use of forms and log forms4. Filing and retrieval of
documentation
I. Project Record Documents
Questions?
60