Services II AC system

Embed Size (px)

Citation preview

  • 8/7/2019 Services II AC system

    1/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    Department of Building Economics i

    Acknowledgement

    We are having a long list of individuals to whom we should convey our acknowledgement. We express

    our indebtedness to each individual for giving us a great support to finish our course work successfully

    and specially Mr. Wickramasooriya for helping us in many ways to find information.

    It is our foremost duty to pay our gratitude to the Department of Building Economics, University of

    Moratuwa, and all the lecturers in the department of Building economics and the staff. Special thank goes

    to our Services II Lecturer Mr. Patrick Weerasinghe, Project Work Lecturers, Ms. Nilupa Udawatta and

    Ms. Nilushi Abesinghe for their valuable advices and guidance towards the successful completion of our

    course work. In addition, our special thanks go to the staff of laboratory of Department of Building

    Economics and staff of Library of University of Moratuwa.

  • 8/7/2019 Services II AC system

    2/23

  • 8/7/2019 Services II AC system

    3/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    Department of Building Economics iii

    Table of Figures

    Figure 2.1: Classifications of AC Systems ................................ ................................ ............................... 3Figure 2.2: Central Air Conditioning Systems ................................ ................................ .......................... 3Figure 2.5: Window Air Conditioner ................................ ................................ ................................ ........ 4Figure 2.4: Split Air Conditioner ................................ ................................ ................................ .............. 4Figure 2.3: Packaged Air Conditioner ................................ ................................ ................................ ...... 4Figure 2.6: Fan Coil Units ................................ ................................ ................................ ........................ 4Figure 3.1: Selected Building ................................ ................................ ................................ ................... 6

  • 8/7/2019 Services II AC system

    4/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    Department of Building Economics 1

    1.0 Introduction

    Air conditioning means the full mechanical control of the internal environment to maintain the specified

    and required condition of a building. The objectives of the air conditioning are to provide a thermally

    comfortable temperature, humidity, air cleanliness and freshness for the uses of the building. The air

    conditioning differs from mechanical ventilation, which includes the moving air by means of fans, air

    filtration, heating, humidification, by the incorporation of refrigeration. However, air conditioning

    requires six main functions, cooling, heating, air circulation, air cleaning, humidification and

    dehumidification. So air conditioning can be defined as the simultaneous control of temperature, humidity

    and air motion. Temperature, relative humidity, air motion, air filtration, indoor air quality and noise are

    the main parameters controlled and maintained by an air conditioning system.

    The air conditioning system basically has four interconnected components: compressor, condenser,

    thermostatic expansion valve and evaporator. Compressor is known as the heart of the refrigeration

    system which takes the refrigerant vapour at a low temperature and low pressure from the evaporator,

    raises it to a higher temperature and pressure and forces it into the condenser. Condenser liquidifies the

    refrigerant vapour while thermostatic expansion valve throttles the high pressure liquid to the evaporator.

    Then the refrigerant in the evaporator absorbs heat from the conditioned space and sends back to

    compressor.

    Nowadays as the population rises, the number of buildings for residential, commercial, industrial and

    other needs is increasing making the limited land available scarce. Though the high rise buildings are one

    of the best solutions to provide more area for the population, prevailing wind pressure may preclude the

    opening of the windows to provide the necessary ventilation and occupied areas cannot be satisfactorily

    supplied with enough fresh air by natural ventilation. Also heat gains occurring within the building, from

    people, lights, electrical, catering and mechanical equipment, external air pollution, the need to air seal

    the buildings in order to limit noise penetration and close control of internal atmosphere required to

    manufacturing of pharmaceuticals, electronics, paper and cotton products have emphasized the need and

    requirement of a proper air conditioning system to buildings.

    There are various types of air conditioning systems like central air conditioning system, room air

    conditioning system and fan coil units which are briefly discussed in next chapter. So when designing a

    suitable air conditioning system, factors like available space, sound level, friction loss, installation cost

    and life cycle cost, heat and leakage loss and gain, requirement of the client, aesthetic appearance, size of

    the internal space in which the temperature should be controlled, function or the purpose of the building,

    number of occupants and the degree of changing the amount of occupants of the building, availability,

    existing resources and technology, amount of vibration, environmental conditions and weather conditions,

    electrical appliances and computers, expected life of the system should be thoroughly considered to select

    the most appropriate and cost effective system for the selected building.

  • 8/7/2019 Services II AC system

    5/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    Department of Building Economics 2

    In this report, chapter one provides a brief and comprehensive details about the main types of air

    conditioning system. The chapter two of the report discusses about the project details and client

    requirements. The cooling load calculation, which is used to determine the appropriate air conditioning

    system to the building, is focused in chapter three. Then the options available for air conditioning the

    building are considered in chapter four. The justification and valid arguments for the selection ispresented in chapter five finally the report provides an estimate for the proposed air conditioning system

    and the layout plans as annexes.

  • 8/7/2019 Services II AC system

    6/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    Department of Building Economics 3

    2.0Types of A/C Systems

    Figure 2.1: Classifications of AC Systems

    2.1 Central air conditioning system

    The central air conditioning system is mostly used for cooling high rise buildings, offices, entire hotels,

    gyms, movie theatres, where it is very expensive initially as well in the long run to provide individualunits to each room for the whole building is to be air conditioned. The central air conditioning system is

    comprises of cooling towers, chillers, Air handling units, and air ducts to provide pathway to distributed

    cool air throughout the building. (Figure 2.2)

    Figure 2.2: Central Air Conditioning Systems

    Air ConditioningSystem

    Central A/CSystem

    oom A/CSystem

    WindowSystem

    Split System

    ackageSystem

    Fan Coilnit

  • 8/7/2019 Services II AC system

    7/23

  • 8/7/2019 Services II AC system

    8/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    Department of Building Economics 5

    3.0 Project Details and Client Requirements

    The two storied building situated in No. 29, Wipulasena Mawatha, Deans Road, Colombo 10 was selected

    to design an Air Conditioning system which has not been air conditioned yet. At the design stage, the

    owner, Wickramasooriya Opticians Ltd, has planned to use the total building for his company. But due to

    various reasons, after construction he wishes to use this first floor of the building as their main branch to

    provide better service to the customer and to lease the second floor to a Dental Centre for two years. The

    floor plans of the two storied building (Annexe 1 & 2) shows the internal partition work that has been put

    up by the owner in the first floor and second floor.

    After the discussing with the building owner, the following basic requirements for the air conditioning

    system were identified.

    y As the two stories have to function separately as two buildings, the client requires an airconditioning system which can be controlled at one place to provide constant temperature in the

    whole building.

    y As both Wickramasooriya Opticians Ltd and Dental Centre provide services to the customers inthe day time, client wish to have all the occupied areas with air conditioning service for day time

    use.

    y The selected air conditioning system should have the ability to automatically reduce the powerconsumption when the building is totally cooled down as the number of occupants of this building

    is not a fixed amount.

    y The owner initially leases out the second floor for two year period but wishes to have a durable airconditioning system that may generally meets the needs of Wickramasooriya Opticians Ltd or any

    other commercial organization that may occupy the second floor in the future.

    y However the owner has permanently put up timber partitions since he has first decided to use bothfloor to Wickramasooriya Opticians Ltd and wishes to have a constant temperature in the total

    building. So the tenants have to compensate their operational requirements with the building

    structure.

    y The owner wishes to have an added value to the building with an attractive and reliable airconditioning system.

    y The client requires having an air conditioning system which needs less space from the operationalspace of the building other than the ceiling void and roof top.

    y The system shall meet the above basic requirement with least capital cost and operational cost.

  • 8/7/2019 Services II AC system

    9/23

  • 8/7/2019 Services II AC system

    10/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    Department of Building Economics 7

    5.0 Selected air-conditioning system

    After considering the clients requirements and the options available to meet those requirements, it was

    decided that water cooling package air conditioning system would be appropriate. The following reasons

    are considered when selecting the package system as the ideal air-conditioning system to this building.

    y In the package air conditioning system all the major components like compressor, evaporator andother items are in one single box except the cooling tower, and it does not require separate large

    plant room to install all those items. Because of this reason the floor space for operation of the

    function of the building can be utilized well.

    y The package unit and the cooling tower will emit a large amount of sound compared to other airconditioning systems. But since both these equipments can be located in the roof top of the

    building, the disturbance by noise is minimised.

    y This has a unique feature to control the functioning of the system. Here as cooling zones in thebuilding cool down, air flow control dampers are closed, evaporator blowers are slowed down,

    and compressors is staged off and un-loaded. These features improve efficiency and reduce the

    power consumption of the unit.

    y Unlike the split systems and window systems, packaged system provides ability to maintain aconstant temperature in the whole building with the minimum use of energy. Though even the

    central air conditioning system can fulfil this requirement, that system is costlier and package

    system can provide same requirement with much lower installation and maintenance cost.

    y Though the owner has already built up timber partitions in the both floor, he has the ability toremove them when he needs to go for a different design. At this situation the package system has

    the flexibility, so that the owner gets the chance to adjust this system to the new design.

    The above reasons justify the selection of Packaged Air conditioning System as the most suitable A/C

    system for this building.

    When designing the installation of the packaged system to this building the following factors and analysis

    were taken into consideration.

    As the entrances to main occupied areas in both floor is somewhat near the middle of the width of the

    building, with two glazed windows in the either side of the main entrance it was decided to have two ductways dividing the floor in to two zones in both floors as shown in layout plans, to preserve the symmetry

    of the layout and to reduce the cross section of the air duct. In this way the wastage of cool air can be

    minimized.

    The ducts are designed to distribute throughout the building through the ceiling void which is not used for

    any other purpose. Supply air diffusers and return air diffusers would be located one from each in a room

    or more if the size of room is large or the required cooling load is high. As the cost would increase

  • 8/7/2019 Services II AC system

    11/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    Department of Building Economics 8

    immensely when the length of ducts increase, it was decided to use air ducts only for the supply air and

    for return air the normal ceiling void would be used without ducts.

    The Package Unit, which is the most important component of package air conditioning system, can be

    installed on the concrete slab of the roof of the building since it has a flat roof as shown in Figure 3.1.

    Also the cooling tower too can be installed on the roof slab since it has adequate space. However it

    creates cost of piping and pumping although it saves valuable land space which is allocated for vehicleparking.

  • 8/7/2019 Services II AC system

    12/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    Department of Building Economics 9

    6.0 Cooling Load Calculations

    6.1 Assumptions

    Item Exposure FactorWindow North 27

    East 52

    West 64

    South 32

    Walls North 03

    East 06

    West 07

    South 03

    Partitions 06

    Roof 11

    Ceiling 04

    Floor 05

    Electrical & Appliances 3.4

    People 465

    Computer 250

    y Artificial lighting inside the building is about 1.4W per ft 2.y The office provides approximate 20ft2 of working space per person.y Floor to floor height is 11.5fty The total building has the same constant temperature of 240C.y Assume that walls and windows have similar heat transfer.y As the whole building is under one constant temperature, the partitions were neglected.

    Sizes of Doors and Windows

    Type Size

    D1 5.00 x 7.00

    W1 21.17 x 9.00

    W2 28.50 x 9.00

    W3 30.67 x 9.00

    W4 55.08 x 9.00

  • 8/7/2019 Services II AC system

    13/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    Department of Building Economics 10

    6.2 First floor

    Floor area = 282ft x 184ft = 51888ft2

    Ceiling area = 282ft x 184ft = 51888ft2

    Nr of Occupancy = 250

    Electrical Appliances = 51888ft2

    x 1.4 = 72.64kW

    Nr of computers = 22

    West External Wall Qty Length(ft) Height(ft) Area(sq. ft.)

    Wall Area 1 184.00 11.50 2116.00

    Glass Area 2 21.17 9.00 381.06

    Net Wall Area

    North External Wall Qty Length(ft) Height(ft) Area(sq. ft.)

    Wall Area 1 282.00 11.50 3243.00

    Glass Area 2 28.50 9.00 513.00

    Net Wall Area

    East External Wall Qty Length(ft) Height(ft) Area(sq. ft.)

    Wall Area 1 184.00 11.50 2116.00

    Glass Area2

    1

    21.17

    30.67

    9.00

    9.00 657.09

    Net Wall Area

    South External Wall Qty Length(ft) Height(ft) Area(sq. ft.)

    Wall Area 1 343.34 11.50 3948.41

    Glass Area

    2

    1

    1

    50.08

    36.58

    22.90

    9.00

    9.00

    9.00 1436.70

    Net Wall Area

  • 8/7/2019 Services II AC system

    14/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    Department of Building Economics 11

    Item Exposure Quantity Factor BTU/hr

    Solar Gain Glass North 513.00 ft2 7.5 3847.50

    East 657.09 ft2

    16 10513.44

    West 381.06 ft2

    23 8764.38

    South 1436.70 ft2

    7.5 10775.25

    Transmission - Glass North 513.00 ft2

    27 13851.00

    East 657.09 ft2 52 34168.68

    West 381.06 ft2 64 24387.87

    South 1436.70 ft2

    32 45974.40

    Transmission - Walls

    North 2730.00 ft2

    03 8190.00

    East 1458.91 ft2

    06 8753.46

    West 1734.94 ft2 07 12144.58

    South 2511.74 ft2 03 7535.22

    Partitions - - ft2

    06 -

    Ceiling 51888.00 ft2

    04 97552.00

    Floor 51888.00 ft2

    05 59440.00

    Electrical & Appliances 7264.00 W 3.4 24697.60

    People 250 Nr 465 11250

    Computer 12 W 250 3000

    GrandT

    otal Heat 213040.43

    Total heat load of the First floor=213040.43 BTU/hr

    = (213040.43 x3.517)/12000

    = 62.48kW

    = 65kW

  • 8/7/2019 Services II AC system

    15/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    Department of Building Economics 12

    6.3 Second floor

    Floor area = 282ft x 184ft = 51888ft2

    Ceiling area = 282ft x 184ft = 51888ft2

    Nr of occupancy = 250

    Electrical Appliances = 51888ft2

    x 1.4 = 72.64kW

    Nr of computers = 22

    West External Wall Qty Length(ft) Height(ft) Area(sq. ft.)

    Wall Area 1 184 11.5 2116

    Glass Area 2 21.17 9 381.06

    Net Wall Area

    North External Wall Qty Length(ft) Height(ft) Area(sq. ft.)

    Wall Area 1 282 11.5 3243

    Glass Area 2 28.5 9 513

    Net Wall Area

    East External Wall Qty Length(ft) Height(ft) Area(sq. ft.)

    Wall Area 1 184 11.5 2116

    Glass Area2

    1

    21.17

    30.67

    9

    9 657.09

    Net Wall Area

    South External Wall Qty Length(ft) Height(ft) Area(sq. ft.)

    Wall Area 1 343.34 11.5 3948.41

    Glass Area

    2

    1

    1

    1

    55.08

    36.58

    22.90

    34.41

    9

    9

    9

    9 1836.54 Net Wall Area

  • 8/7/2019 Services II AC system

    16/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    Department of Building Economics 13

    Item Exposure Quantity Factor BTU/hr

    Solar Gain Glass North 513.00 ft2 7.5 3847.50

    East 657.09 ft2

    16 10513.44

    West 381.06 ft2

    23 8764.38

    South 1436.70 ft2

    7.5 10775.25

    Transmission - Glass North 513.00 ft2

    27 13851.00

    East 657.09 ft2 52 34168.68

    West 381.06 ft2 64 24387.87

    South 1436.70 ft2

    32 45974.40

    Transmission - Walls

    North 2730.00 ft2

    03 8190.00

    East 1458.91 ft2

    06 8753.46

    West 1734.94 ft2 07 12144.58

    South 2511.74 ft2 03 7535.22

    Partitions - - ft2

    06 -

    Ceiling 51888.00 ft2

    04 97552.00

    Floor 51888.00 ft2

    05 59440.00

    Electrical & Appliances 72640.00 W 3.4 24697.60

    People 2594 Nr 465 11250

    Computer 12 W 250 3000

    GrandT

    otal Heat 213040.43

    Total heat load of the Second floor =213040.43 BTU/hr

    = (213040.43 x3.517)/12000

    = 62.48kW

    = 65kW

    Total cooling load of the building = 2 x 213040.43 BTU/hr

    = 426080BTU/hr

  • 8/7/2019 Services II AC system

    17/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    Department of Building Economics 14

    7.0 Estimate for the proposed system

    No DESCRIPTION UNIT QTY RATE AMOUNT

    01

    02

    Air Conditioning System

    Packaged Air Conditioning Units

    Supply, position and connection of water cooled

    packaged air conditioning units as specified and

    comply with the specifications. Rate shall

    include for all necessary flexible connections,

    fresh air supply connections and condenser water

    piping connections interlocking arrangement

    between flow switches and complete with globe

    valves, gate valves, flow switches, pressure

    gauges, thermometer tapping, flow control

    devices, condensate drain connections, airdistribution ducting connections, all necessary

    power and control cabling and wiring required

    for complete installation.

    MWCP70A Packaged UnitCooling capacity 480,000 Btu/h

    Air Flow Rate 10,800 m3/h

    Carried to summary on page 5

    Cooling Towers

    Supply, position and Connection of water

    cooling towers having a capacity to match the

    total heat rejection of the condensers connected

    to the cooling tower condenser, water flow rate

    of 22.1 l/s. temperature entering 37oC , leaving

    33oC connected and rated temperature shall be as

    specified in specifications. Power supply shall be

    4000 V / 3 phase / 50 Hz. Rate shall include

    gate values, flexible coupling, and for all

    necessary cut off devices connections to gate

    valves necessary interconnections of water pipes

    where required and shall be to working order.

    Carried to summary on page 4

    Nr

    Nr

    1

    1

    250,000.00

    125,000.00

    250,000.00

    250,000.00

    125,000.00

    125,000.00

    Page 1

  • 8/7/2019 Services II AC system

    18/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    Department of Building Economics 15

    No DESCRIPTION UNI

    T

    QTY RATE AMOUNT

    03

    04

    05

    06

    07

    Air Condition Diffusers

    12 x 12 neck size Supply air diffusers

    Carried to summary on page 4

    Air Condition Duct Work

    All air conditioning and ventilation duct work to befabricated with GI sheets and fabrication and

    installation should fully confirm to ASHEREstandards.

    All supply and return duct work shall be fully

    insulated with fibre glass insulation 25 mm thick 32kg/cum density. The thermal conductivity less than

    0.4 W/moC and the thickness of the Aluminium foil

    vapour barrier shall avoid any condensation.

    Rate of duct work shall include bends, tees, flexible

    connection, and sound attenuators, anti vibration

    mounts, air sealant, connecting flanges, turning

    vanes, splitters, supporters, access panels, and fire

    barriers.

    All duct supports shall be galvanized.

    Supply Air Duct

    50 x 12

    25 x 12

    20 x 12

    12 x 10

    Carried to summary on page 4

    Nr

    ft.

    ft.

    ft.

    ft.

    45

    450.00

    120.00

    80.00

    332.50

    2,500.00

    1,550.00

    860.00

    700.00

    600.00

    112,500.00

    112,500.00

    697500.00

    103200.00

    56000.00

    199500.00

    1,056,200.00

    Page 2

  • 8/7/2019 Services II AC system

    19/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    Department of Building Economics 16

    Page 3

    No DESCRIPTION UNIT QTY RATE AMOUNT

    16

    17

    18

    19

    20

    21

    Condenser Water Supply Pipes

    Condenser water supply pipes from Makeup tankto cooling tower

    1 dia. (provisional Qty)

    Condenser water supply pipes from cooling

    tower to Condenser Water pumps

    5 dia. Supply pipe (provisional Qty)

    Condenser water supply pipes to AC units

    3 dia. pipe

    2 dia. pipe

    Condenser water return pipes from AC units

    3 dia. pipe

    2 dia. pipe

    Carried to summary on page 4

    ft.

    ft.

    ft.

    ft.

    ft.

    ft.

    20

    120

    100

    100

    100

    100

    180.00

    1,520.00

    665.00

    400.00

    665.00

    400.00

    3,600.00

    182,400.00

    66,500.00

    40,000.00

    66,500.00

    40,000.00

    399,000.00

  • 8/7/2019 Services II AC system

    20/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    Department of Building Economics 17

    Page 4

    DESCRIPTION AMOUNT

    A

    B

    C

    D

    E

    Summary

    Packaged Air Conditioning Units

    Cooling Towers

    Air Condition Diffusers

    Air Condition Duct Work

    Condenser Water Supply Pipes

    Total

    250,000.00

    125,000.00

    112,500.00

    1,056,200.00

    399,000.00

    1,830,000.00

  • 8/7/2019 Services II AC system

    21/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    Department of Building Economics 18

    8.0 Conclusion

    With the development of the technology, people are in search of new methods to make their lives more

    and more comfortable. Commonly used one such advanced technological method is controlling the

    temperature of a building. This is accomplished by Heating, Ventilating and Air Conditioning (HVAC)

    system which consists of a group of components or equipment connected in series to control the

    environmental parameters.

    The process of Air Conditioning can be simply defined as the process of controlling the air temperature,

    relative humidity, ventilation, air movement and air cleanliness of a given space in order to provide the

    occupants with a comfortable indoor temperature. There are various types of air conditioning system like

    central system, room systems and fan coil units etc. These systems are installed in various buildings

    considering the requirements.

    The amount of heat generated in the building from various sources is one of the key factors that should be

    considered in designing the appropriate air conditioning system. In a tropical country like Sri Lanka, heat

    gained by the walls, roof and partitions, windows, people, electrical appliances is high due to the solar

    radiation. To maintain the comfort conditions inside the room the total heat generated inside the room per

    hour should be removed completely. For this other than the heat gain, factors like space, sound level,

    friction loss, installation cost and life cycle cost, requirement of the client, aesthetic appearance, size of

    the internal space in which the temperature should be controlled, function or the purpose of the building,

    number of occupants and the degree of changing the amount of occupants of the building should also be

    considered.

    There are alternative methods of cooling buildings other than full comfort air conditioning. These include

    night-time cooling, evaporative cooling, chilled beams and ceilings, hollow floor slabs with air and

    cooling air by subsoil or water. Some of these will use significantly less energy than conventional air

    conditioning.

    As well as providing comfortable condition in buildings, several problems associated with air

    conditioning systems are identified by the HVAC engineers. Most commons ones are Legionnaires

    Disease, Humidifier Fever and Sick Building Syndrome. In Legionnaires Disease, the bacteria thrive

    naturally in warm moist conditions found in swamps and get adapted to the artificial climate of air

    conditioned buildings. Abolition of cooling towers, replacement with air cooled condenser units or a strict

    maintenance routine would be the solutions for this disease. In Humidifier Fever, an allergy causes

    temporary discomfort with symptoms similar to influenza. For this problem biocidal treatment to the

    spray water is one solution while replacement with a steam injection humidifier would be another. Sick

    Building Syndrome reveals itself in a number, or combination of symptoms including headaches,

    lethargy, skin irritations, dry or running eyes, runny nose, throat inflammation and loss of concentration.

  • 8/7/2019 Services II AC system

    22/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    Department of Building Economics 19

    9.0 References

    2001.Building services component life manual. London: Blackwell Publishing Limited.

    Brumbaugh, J. E., 1986. Heating, ventilating and air conditioning library volume I. New York:

    Macmillan Publishing Company.

    Charles, H.B., 1959.Residential and commercial air conditioning. 2nd Ed. New York: McGraw Hill Book

    Company.

    Derek, J.C. and Brian, M.R., 1981.Air conditioning and ventilation of buildings . 2nd

    ed. London: William

    Clowes Limited.

    Jones, W.P., 1980.Air Conditioning Applications and Design. London: Edward Arnold (Publishers) Ltd.

    Jordan, R.C., 1956.Refrigeration and Air Conditioning. U.S.A :Prentice-Hall.

    Raymond, K.S., 1976.HVAC control systems. Canada: John Wiley & sons Limited.

  • 8/7/2019 Services II AC system

    23/23

    BE 2202 Services II Course Work Design of Air Conditioning System

    10.0 Annexes

    In the layout plans, indicates Diffuser, indicates 20 x 12 ducts and

    reprsents 12 x 10 ducts.