2
Energy Conservation Project Update SEPTEMBER, 2011 QUESTIONS? Call us at (480) 350-8369 or email [email protected] www.tempe.gov/greenprograms Percent Complete by Building Percent Complete by Building by Energy Conservation Measure by Energy Conservation Measure Replacing Inefficient and Outdated Equipment is COOL… In 2010, Ameresco (formerly APS Energy Services) conducted an audit of 23 city facilities and identified ways to reduce energy consumption and utility costs. Through an energy performance agreement , city facilities will receive a variety of energy conservation upgrades over the next year, creating work for approximately 100 construction employees. Tempe received $930,000 in Energy Efficiency & Conservation Block Grant funds to partially cover program costs, which total $8.7 million, in addition to $373,000 in utility rebates. The remaining project costs will be financed through special low-interest bonds, which will be paid over 15 years through utility cost savings of $550,000 per year due to reduced power consumption. Project Details: Project Details: 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 525 City Office Building City Hall Courts/ Police Edna Vihel Center Tempe Performing Arts Center Escalante Muli-Gen Facility South Police Substation Lighting Controls Motors Water Chiller Plant Optimization Retro- Commissioning Rooftop Unit Replacement Split System Replacement DDC Web Platform Ameresco Southwest is in the process of replacing 129 individual air conditioning units for the City of Tempe. Systems include heat pumps and gas packs, which consist of both package units and split systems. Thirteen buildings were selected for the air conditioning portion of the efficiency upgrade project. The two facilities seeing the most activity in September were the Edna Vihel Center and Escalante Multi-Generation Facility. The Edna Vihel project is 70% complete and approximately 60% of the units at the Escalante Multi-Generation Facility have been replaced. Special thanks goes out to the Edna Vihel and Escalante Multi-Generation Facility onsite staff, as well as, the facilities group for their excellent support of the construction teams as they continue with this project. The total air conditioning project is scheduled to be completed December 30th, 2011.

SEPTEMBER, 2011 Energy Conservation Project Update

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Energy Conservation Project Update

S E P T E M B E R , 2 0 1 1

QUESTIONS? Call us at (480) 350-8369 or email [email protected] www.tempe.gov/greenprograms

Percent Complete by BuildingPercent Complete by Building by Energy Conservation Measureby Energy Conservation Measure

Replacing Inefficient and Outdated Equipment is COOL…

In 2010, Ameresco (formerly APS Energy Services) conducted an audit of 23 city facilities and identified ways to reduce energy consumption and utility costs. Through an energy performance agreement , city facilities will receive a variety of energy conservation upgrades over the next year, creating work for approximately 100 construction employees. Tempe received $930,000 in Energy Efficiency & Conservation Block Grant funds to partially cover program costs, which total $8.7 million, in addition to $373,000 in utility rebates. The remaining project costs will be financed through special low-interest bonds, which will be paid over 15 years through utility cost savings of $550,000 per year due to reduced power consumption.

Project Details:Project Details:

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

525 City Office

Building

City Hall

Courts/Police

Edna VihelCenter

Tempe PerformingArts Center

EscalanteMuli-Gen

Facility

South PoliceSubstation

Lighting Controls Motors Water Chiller Plant Optimization Retro- Commissioning Rooftop UnitReplacement

Split SystemReplacement

DDC Web Platform

Ameresco Southwest is in the process of replacing 129 individual air conditioning units for the City of Tempe. Systems include heat pumps and gas packs, which consist of both package units and split systems. Thirteen buildings were selected for the air conditioning portion of the efficiency upgrade project. The two facilities seeing the most activity in September were the Edna Vihel Center and Escalante Multi-Generation Facility. The Edna Vihel project is 70% complete and approximately 60% of the units at the Escalante Multi-Generation Facility have been replaced. Special thanks goes out to the Edna Vihel and Escalante Multi-Generation Facility onsite staff, as well as, the facilities group for their excellent support of the construction teams as they continue with this project. The total air conditioning project is scheduled to be completed December 30th, 2011.

QUESTIONS? Call us at (480) 350-8369 or email [email protected] www.tempe.gov/greenprograms

Energy Conservation Project Update: City Buildings

The thirteen buildings that will receiving efficient air conditioning unit replacements are as follows. This portion of the City-wide energy conservation project is scheduled to be completed December 30, 2011.

• Edna Vihel Center • Escalente Multi-Generation Facility • Fire Station #1 and Administration • Fire Station #3 • Fire Station #5

• Fire Training Facility • Hardy Yard Maintenance Facility • JG Martinez Waste Water Treatment Plant • Kyrene Water Reclamation Facility

• Priest Yard • South Police Substation • Tempe Diablo Stadium • Westside Multi-Generational Facility

Facility Lighting Controls Motors WaterChiller Plant

OptimizationRetro-

CommissioningRooftop Unit Replacement

Split System Replacement

Stadium Lighting

Computer Power Management

DDC Web Platform

Power Monitoring

525 City Office Building complete complete complete

City Hall complete complete complete • complete

Courts/Police complete complete • • • complete

Edna Vihel Center • complete complete

Tempe Performing Arts Center • complete complete

Escalante Multi-Gen Facility • • •

South Police Substation •

Fire Station #1 & Administration

Fire Station #3

Fire Station #4

Fire Station #5

Fire Station #6

Fire Training Facility

Hardy Yard Maintenance Facility

JG Martinez WTP

Kyrene Water Reclamation Facility

Priest Yard - All Buildings

Pyle Adult Rec Center

South Tempe WTP

Tempe Diablo Minor League Building

Tempe Diablo Stadium

Traffic Maint. Shop & Warehouse

Westside Multi-Gen Facility