Date: March 8, 2016 Tutorial EKC 316 Separation Process Topic: Humidification/Dehumidification Problem 1: Moist warm air is to be cooled and dehumidified to a wet-bulb temperature of 30ºC using water of 25ºC in a dehumidification column. The air enters the tower with a dry-  bulb temperature of 85ºC and wet-bulb temperature of 45ºC at 4800 kg/m 2 h rate. The overall gas phase mass transfer coefficient is estimated to be 2150 kg/ m 3 h. The flow rate of water is 1.4 times the minimum. Calculate height of the tower. Azam T Sem II, 2015/2016

Separation Process Tutorial 1

Embed Size (px)

Citation preview

Page 1: Separation Process Tutorial 1

 

Date: March 8, 2016

Tutorial EKC 316 Separation Process

Topic: Humidification/Dehumidification

Problem 1:

Moist warm air is to be cooled and dehumidified to a wet-bulb temperature of 30ºC

using water of 25ºC in a dehumidification column. The air enters the tower with a dry-

 bulb temperature of 85ºC and wet-bulb temperature of 45ºC at 4800 kg/m 2h rate. The

overall gas phase mass transfer coefficient is estimated to be 2150 kg/ m3h. The flow

rate of water is 1.4 times the minimum. Calculate height of the tower.

Azam T Sem II, 2015/2016