23
Susitna Hydro Evaluation Project Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to presented to Alaska Energy Authority November 2008

Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

Susitna Hydro Evaluation Project

Seminar on the

Development of Large Hydroelectric Projects

with a Focus on the Susitna Project

presented topresented to

Alaska Energy Authority

November 2008

Page 2: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

Hydroelectric Equipment,

Hydrology, and Energy

ProductionProduction

Page 3: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

� Physics: water flow times gravity head

equals power, integrated over time

equals energy

� Static head is developed by dams, in

this case 885 feet at Watana and 647

Introduction

this case 885 feet at Watana and 647

feet at Devil Canyon

� River flow captured by dams routed to

turn turbines-generators to produce

1,880 MW of renewable power

� Power over time is energy, which

annually is 6,900,000 MWh Watana

3

Page 4: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

� Dams

� Powerhouses

� Hydroelectric machinery

• Turbines

• Generators

Energy Process

Water Collection

Dam

Susitna River

• Generators

• Controls

• Transformers

• Transmission

� Hydrology

� Energy production

Shaft Power

Turbine

Generator

Transmission

Conveyance

Transformers

Alaskan Homes4

Page 5: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

Water Flows Downhill

5

P = ηγQHP = Power

H = Hydraulic Head (ft)

Q = Flow Rate (cfs)

γ = Specific weight of water (62 lb/ft^3)

η = Overall efficiency of facility (90 Turbine Efficiency-95 Generator Efficiency)%

Page 6: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

Profile View: Watana and Devil Canyon Powerhouses

Transformer Gallery

Powerhouse

Generator

6

Surge Chamber

TurbinePenstock

Draft Tube

Page 7: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

Turbine-Generator

1. Water in spiral case

turns turbine runner.

2. Runner turns shaft.

3. Shaft turns generator

rotor.

4. The rotating magnetic

field due to the

7

field due to the

spinning rotor

induces electrical

current in the

stationary stator.

5. Electrical current

from the stator is sent

through a transformer

and then on to the

utility grid.

Page 8: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

1985 FERC ApplicationStaged Development Plan

Watana Stage 1

• Install 700-foot dam at Watana

• Four turbine generator units.

• Total capacity: 440 MW

8

Full Devil Canyon

• Install 646-foot thin arch concrete dam

• Four 170MW turbine generator units.

• Total Devil Canyon capacity: 1,200 MW

Watana Stage 2

• Raise Watana dam by 185 feet

• Install two 200-MW turbine generator units.

• Total project capacity both plants: 1,880 MW

Page 9: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

Turbines: Watana

� Turbine - vertical-shaft,

Francis type,

with spiral case

� 3,500 cfs flow, 719 feet

of head, 94 percent of head, 94 percent

turbine and 97 percent

generator efficiency

� Six turbines rated at

200 MW each equals

total 1,200 MW

9

Page 10: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

Turbines: Devil Canyon

� Vertical-shaft Francis

turbine with spiral casing

� 600 feet of head with 3,800

CFS flow rate

� Four turbines rated at � Four turbines rated at

170 MW each

� 680 MW total

10

Page 11: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

Generator Specifications

� Approximate dimensions

• 38-foot stator diameter

• 24-foot rotor diameter

• Rotor weight 385 tons

• Total weight 740 tons• Total weight 740 tons

11

Umbrella Type

Page 12: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

� Generator parameters

• Watana: 200-MW

max power

• Devil Canyon:

170-MW max power

Generator Specifications, continued

170-MW max power

• 15kV, 3-phase,

60 Hertz power

• 225 rpm

synchronous speed

12

Page 13: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

Transformers

� Devil Canyon - three single-

phase transformers per

generator: 15 KV and 70MVA

per phase

� Watana – three single-phase � Watana – three single-phase

transformers per pair of

generators: 15 KV and

150MVA per phase

� Maximum size limited by

150,000-lb load limit on Denali

Highway

� Transmission line voltage –

345 KV/1,300 KV Voltage13

Page 14: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

Susitna River Hydrology

� 19,400 square mile drainage

� Peak flow in June

� Frozen October to March

� Glacial-fed, rainfall and storage project

14

Drainage Area

Page 15: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

Susitna River Seasonal Flows

Flo

w R

ate

(cfs

)F

low

Rate

(cfs

)

15

Gold CreekUSGS Gauge

Page 16: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

Susitna Flow Duration Curve

Historical

Project

16

Page 17: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

Hydrology: Influences and Trends

� Glacial Influences

• Glaciers currently comprise from 5 to 25 percent of drainage areas contributing to the Susitna River (Water-Resources Investigations Report 01-4109)

• Glaciers act to store and delay the seasonal runoff

• Significant source of water during the summer seasonsummer season

� Preliminary Hydrological Review

• Flows range from 400 to 40,000 cfs for 100 percent to 1 percent

• Susitna Powerhouse turbine flow 14,400 to 21,000

17

Page 18: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

Original Energy Production Estimates

� Estimate Inputs: daily river flows; dam and water conveyances parameters; turbine, generator and transformer capacities and efficiencies; outages.

� Previous studies estimated 6,900GW hrs/yr (40 percent plant factor to theoretical 24 hour/365 day capacity)

18

Page 19: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

Modern Energy Modeling“CHEOPS”

� Daily calculation of generation based on reservoir,

stream-flow and powerhouse operating constraints.

� Proprietary software:

• Technical staff has the ability to modify code

• Simulates unusual operating conditions or constraints

such as cascading in-series dams such as Susitna

• Solutions for flow, head, capacity optimization and

environmental compliance.

19

Page 20: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

Model Inputs and Outputs

� Inputs:

• Daily flows

• Headwater, tailwater, and acre-feet storage

• Turbine generator capacities and efficiencies

• License operating constraints, such as downstream flows

� Outputs:� Outputs:

• Powerhouse discharge flow, head and power

• Weekday and weekend generation shape for demand periods

• Customizable output reporting detailed out in daily, weekly,

annual and average long term flow, head and energy output.

• Energy outputs used as inputs to financial models.

20

Page 21: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

Energy : CHEOPS Model

1,000

1,200

1,400

1,600

1,800

2,000

4840.00

4850.00

4860.00

4870.00

Annual Model Chart

200

400

600

800

4800.00

4810.00

4820.00

4830.00

Time (months)

KEY

Blue-Turbine Discharge

Red- Inflow to Project

Black/Green- Reservoir Elevation

21

Page 22: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

� The Susitna Project would generate

approximately 7 million MW hours per

Conclusions

approximately 7 million MW hours per

year

� Susitna would also provide Alaska

electric security and system stability

22

Page 23: Seminar on the Development of Large Hydroelectric Projects ... · Seminar on the Development of Large Hydroelectric Projects with a Focus on the Susitna Project presented to Alaska

Q&AQ&A

23