47
Sellwood Replacement Bridge Perched Box Caisson Design & Construction …a cofferdam alternative

Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Embed Size (px)

Citation preview

Page 1: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Sellwood Replacement Bridge Perched Box Caisson

Design & Construction

…a cofferdam alternative

Page 2: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Sellwood Replacement Bridge

Page 3: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Project Information

• Location: Portland, Oregon• Budget: $307.5 Million• Three span steel deck arch (Design by TYLin)• Contractor: Slayden/Sundt, A Joint Venture

Page 4: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Perched Box CaissonElevated cofferdam constructed above water thenlowered down using hydraulic jacks. A voided baseslab sleeves over foundation shafts as the box issubmerged and secured using anchoring collars toseal and resist vertical forces.

Page 5: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Why?

Page 6: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Key Constraints

• Alluvial gravel with numerous cobbles and boulders up to 5 feet in diameter

• Long sheet pile length • Scour up to 65 feet (CH2M Hill estimate)• Stay-in-place falsework not to exceed 35ft2

relative to stream flow • In-water work restricted to July 1st - Oct 31st

Page 7: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Design Development

Page 8: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Buried Pier - Option 1 Typical Cofferdam

Constructability Limitations• 90ft sheet piles driven into

cobbles & boulders. • In-water work

NOT CONSTRUCTIBLE Conclusion:

Page 9: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Elevated Pier - Option 2A Above Grade Seal

Constructability Limitations• Abandoned concrete seal

exceeds permit allowance• Removal of concrete seal

not reasonable.

NOT ALLOWEDConclusion:

Page 10: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Elevated Pier - Option 2BCofferdam with Shored Pier

Constructability Limitations• Piles driveability issues. • Limited removal access of

heavy falsework shoring. • Mid depth concrete seal

could negatively influence the structural behavior of the permanent foundations (i.e. Seismic Response)

NOT RECOMMENDED Conclusion:

Page 11: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Elevated Pier - Option 2CPerched Box Caisson

Constructability Limitations• Fabrication Intensive• Requires “Birds Mouth”

Forms

SELECTED OPTIONConclusion:

Area ≤ 35ft2

Page 12: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Construction Sequence

1,2,3,4,5

Page 13: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Drive Pile

Use pile template when driving

Page 14: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Construct Drilling Reaction Frame

Page 15: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Install Drilled Shafts

Pile to support oscillator lateral and vertical extraction forces

Page 16: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Disassemble Reaction Frame

Use steel crossbeams to form Box Caisson base slab

Page 17: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Pour Elevated Base Slab

Page 18: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Construct Wales, Walls & Topping Slab

Page 19: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Construct Bird Mouth Forms

Page 20: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Construct Jack-Down Frame

Reuse steel beams from drilling reaction frame

Page 21: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Lower Assembly (Jack-down)

Total Weight = 1,016,000 lbs

Page 22: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Install Tie-down Collars

Anchor tie-down collars and seal to shaft casing

Page 23: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Dewater, Remove Frame, Cut-off Casing

Resist buoyant uplift force

Page 24: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Pour Bottom Lift of Pier

Support pier concrete weight

Page 25: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Pour Upper Pier and Angel Wings

Page 26: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Disassemble Walls, Slab to Remain

Page 27: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Analysis & Design

1+1=2

Page 28: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Analysis & Design Steps

• LUSAS 3D Finite Element Analysis Software• Check loading for:

– Oscillator drilling forces– Base slab pour– Jack-down distribution– Bouyant uplift – Pier concrete weight

Page 29: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Voided Slab Design

Page 30: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Construction Photos

Page 31: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Inside Box Prior to Jack-down

Page 32: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Tie-Down Collar

Design

Fabrication

Page 33: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

…or Flying Saucer

Page 34: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Aerial View

Page 35: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Elevated Position

Page 36: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Jack-down Frame

High Tension Rods

(8) Cylinder Jacks

Page 37: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

EFCO Pier Forms

Page 38: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

High Water

Page 39: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Completed Pier

Page 40: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Time-Lapse Video

November 2013 – February 2014

Page 41: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts
Page 42: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Contractor Feedback

Page 43: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Construction Benefits

• Quantities saved:

• Reduced environmental liability • Easy access for materials

Structure Steel Concrete Dredging

Traditional Cofferdam 1,170 Tons 6,130 yd3 13,100 yd3

Perched Box Caisson 390 Tons 380 yd3 0 yd3

Savings 780 Tons 5,750 yd3 13,100 yd3

Page 44: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Additional Benefits

• Easier permitting with lower total pile count. Reused 3800LF temporary pile.

• No tremie concrete = no contaminated water. Dewater directly back into river.

• Construction schedule not limited to in-water work restrictions.

Page 45: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Challenges and Lessons Learned

• Synchronizing jacks to maintain slab tolerance during Jack-down was difficult.

• Creating a water-tight seal at the sheet to concrete interface was costly and time consuming.

• Joints at birds mouth forms to sheet pile are difficult to achieve water-tightness.

Page 46: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Suggestions for Improvements

• Negotiate larger allowable stay-in-place falsework• Avoid birds mouth forms when possible• Improve sealing methods prior to jack-down• Improve control during jack-down• Increase pumping rate during dewatering• Modify tie-down collar to reduce underwater

construction• More robust pile for shaft drilling

Page 47: Sellwood Replacement Bridge Perched Box Caisson · Elevated cofferdam constructed above water then lowered down using hydraulic jacks. A voided base slab sleeves over foundation shafts

Questions?