Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries 1 S.No. Clause No. Pg. No. Clause as per RFP Query Clarification/Response ISPAT Corporation Pvt. Ltd 1 2.2 10&11 Eligibility Criteria: 2.2.2 To be eligible for evaluation of its Proposal, the Applicant shall fulfil the following: (A) Technical Capacity: The Applicant shall have, over the past 10(Ten) years preceding the PDD, undertaken a minimum of 2 (Two) Eligible Assignments as specified in Clause 2.2.2 (B). (B) Eligible Assignments: For the purposes of determining Conditions of Eligibility and for the evaluating the Proposals under this RFP, the following projects shall be deemed as eligible assignments (the “Eligible Assignments”). Experience of Detailed Master Planning and Infrastructure Planning of Industrial Park / SEZ /Industrial Estate projects of 2000 Acres or above in a single project. As our team has an experience of projects involving industry planning & design, so we request you to modify the eligibility criteria and consider it for the preparation of master plan for Pharma City. RFP Clause holds good. 2 2.2.2 10 Eligible assignments 2.2.2 (B) Eligible Assignments: For the purposes of determining Conditions of Eligibility and for the evaluating the Proposals under this RFP, the following projects shall be deemed as eligible assignments (the “Eligible Assignments”} Experience of Detailed Master Planning and Infrastructure Planning of Industrial Park / SEZ /Industrial Estate projects of 2000 Acres or above in a single project. We would request you to consider eligible projects of 8 Sq. Km above. Also please clarify, whether the assignments should be Brownfield or Green field. The Clause shall be read as “Experience of Detailed Master Planning and Infrastructure Planning of Greenfield Industrial Park / SEZ /Industrial Estate projects of 2000 Acres or above in a single project”.

Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

  • Upload
    buidang

  • View
    225

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

1

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

ISPAT Corporation Pvt. Ltd

1 2.2 10&11 Eligibility Criteria:

2.2.2 To be eligible for evaluation of its Proposal,

the Applicant shall fulfil the following:

(A) Technical Capacity: The Applicant shall have,

over the past 10(Ten) years preceding the PDD,

undertaken a minimum of 2 (Two) Eligible

Assignments as specified in Clause 2.2.2 (B).

(B) Eligible Assignments: For the purposes of

determining Conditions of Eligibility and for the

evaluating the Proposals under this RFP, the

following projects shall be deemed as eligible

assignments (the “Eligible Assignments”).

Experience of Detailed Master Planning and

Infrastructure Planning of Industrial Park / SEZ

/Industrial Estate projects of 2000 Acres or above

in a single project.

As our team has an experience of projects

involving industry planning & design, so we request

you to modify the eligibility criteria and consider it

for the preparation of master plan for Pharma City.

RFP Clause holds good.

2 2.2.2 10 Eligible assignments

2.2.2

(B) Eligible Assignments: For the purposes of

determining Conditions of Eligibility and for the

evaluating the Proposals under this RFP, the

following projects shall be deemed as eligible

assignments (the “Eligible Assignments”}

Experience of Detailed Master Planning and

Infrastructure Planning of Industrial Park / SEZ

/Industrial Estate projects of 2000 Acres or above

in a single project.

We would request you to consider

eligible projects of 8 Sq. Km above. Also please

clarify, whether the assignments should be

Brownfield or Green field.

The Clause shall be read as

“Experience of Detailed Master Planning and

Infrastructure Planning of Greenfield

Industrial Park / SEZ /Industrial Estate

projects of 2000 Acres or above in a single

project”.

Page 2: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

2

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

3 2.1 9 Scope of Work

Detail Scope of Work described in Schedule – I:

Terms of Reference.

1) Please provide clarifications on the scope of

work, whether it is limited to designing part or

should also include good for

construction/detailed design submission.

2) In the RFP document, preparation of the

economic viability/financial studies for the

project is not mentioned, hence please clarify

that its already been prepared.

Scope includes detailed designs and GFC

drawings for execution (Please refer Clause

B(b), (c) & (d) of Pages47 -48 of RFP). Also

please refer response at S.No (12).

Not required.

4 1.8 7 Proposal Due Date (PDD) & Time

22-02-2016

15.00 HRS (IST)

As our Chinese partner will be officially unavailable,

due to their holidays from 3rd-17th Feb. Hence,

we would request you to extend the submission

deadline by at least 15 days from the given date i.e.

22.02.2016.

PDD extended upto 10.03.2016, 15.00 Hrs

(IST).

AECOM

5 2.1.1 9 Consortium member/s

The maximum number of members allowed in a

consortium is Two (2) including Lead member,

Consortium member / Associate.

We request you to kindly modify the same as “The

maximum number of members allowed in a

consortium is Three (3) including Lead member,

Consortium member / Associate.”

This will allow to have best of the experiences.

RFP Clause holds good.

6 2.2.2 B 10.11 Eligible Assignments

Experience of Detailed Master Planning and

Infrastructure Planning of Industrial Park / SEZ

/Industrial Estate projects of 2000 Acres or above

in a single project.

We request you to kindly modify the same as

“Experience of Detailed Master/Development

Planning and/or Infrastructure Planning of Industrial

Park / SEZ /Industrial Estate/Special Investment

Region projects of 2000 Acres or above in a single

project.”

RFP Clause holds good.

Page 3: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

3

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

7 2.2.2 C 11 Financial Capacity

The Applicant shall have an average annual

turnover of Rs. 20 crores during each of the last

three financial years preceding the PDD. The

revenues from the consulting/advisory services will

only be considered for evaluation. Turnover of

Associates/JVs will not be considered.

We request you to kindly modify the same as “The

Applicant shall have an average annual turnover of

Rs. 100 crores during each of the last three

financial years preceding the PDD. The revenues

from the consulting/advisory services will only be

considered for evaluation. Turnover of

Associates/JVs will not be considered. ”Since the

quantum and magnitude of the Project is big.

RFP Clause holds good.

8 2.14.2 f 21 Curriculum Vitae (CV)

The CVs have been recently signed and dated, by

the Applicant. Photocopy or unsigned /

countersigned CVs shall be rejected.

We request you to kindly allow Scanned Signature

of the Expert on his/her respective CV as most of

the Expert/s are located across the Geography.

Digital Sign is permitted with a counter

signature by the Authorised Person submitting

the Bid on behalf of the Consulting Firm.

9 3.1.2 2b 31 Scoring Criteria

Master planning experience in Eligible Projects

with pharma sector as a component with an area

over 500 acres.

We request you to kindly modify the same as

“Master planning experience in Eligible Projects

with industrial sector as a component with an area

over 500 acres.”

RFP Clause holds good.

10 3.1.2 3 31 Relevant Experience of the key personnel

Key Personnel having desired Educational

qualification and No. of years‟ experience shall be

considered. Each Key Personnel will be eligible for

marking (as below) only if each of them is existing

employee of the Applicant firm (Permanent

employee)

Request you to kindly waive off the Permanent

employee/s criteria. And if any Key Personnel

proposed is not a permanent employee of the

Applicant (including in case of a JV, of its members)

a self-declaration by the said key expert duly

countersigned by the authorized representative of

the bidder shall be submitted confirming his/her

availability for the assignment against the said

clause, should be accepted.

This has also been followed in other APIIC or

similar department contracts.

The following key personnel shall be

Permanent employee/s with the Applicant

(Sole Firm / Consortium Members).

Team Leader

Urban & Regional Planner

Infrastructure Planning Expert

Water Expert

Transportation Expert

Architect

However, in case of Consortium, the Team

Leader and Urban & Regional Planner must

be the Permanent employees of Lead

Member only.

11 3.1.2

B2

32 Key Personnel Evaluation Criteria

Experience of Special Assignment

Request you to kindly elaborate the meaning of

“Special Assignment”

It means eligible Projects having Pharma

Sector as component with an area of over 500

acres.

Page 4: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

4

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

12 2.1 B ( c) 47 Detailed Engineering and Designs – Internal

Infrastructure

Wastewater Management System design

supported with wastewater conveyance system

drawings, line diagrams of proposed treatment

systems (ZLD based CETP and STP), drawings of

treatment plants

We request you to kindly modify the same, as

normally for WTP and STP, detailed design is

prepared by the EPC contractor only as the

Detailed design is vender specific depending on the

Particular Technology / treatment units by different

EPC/ DBO contractors. Preliminary design shall be

prepared by the Consultant but detailed design

should be prepared by the EPC Contractor only.

Detailed design of all civil components of

proposed CETP, WTP, STP shall be carried

out and supporting process flow diagrams,

detailed drawings, detailed specifications etc.

have to be provided.

The consultant is expected to study, analyse

and recommend the best suitable technology

for the above components along with costing

of electro mechanical items and their detailed

technical specifications from reputed suppliers

through atleast 3 quotations.

The consultant shall ensure that, there should

be no abnormal deviation in cost estimation

for execution.

The Authority will decide the model of

implementation of the above components in

due course of the project.

13 2.1 B ( c) 48 Solid Waste Management Solid Waste

Management System design for all categories of

solid waste – industrial and domestic solid waste.

Different management systems shall be designed

for hazardous…..

Please clarify: The identification of Landfill site is

pre-decided or has to be identified by the selected

consultant?

The consultant is expected to recommend

the same after conducting due analysis on

availability of similar facilities in the

surrounding region and their adequacy for

meeting the project requirements.

14 2.1 B ( c) 48 Technical Infrastructure Components

Technical Infrastructure Components

(Manufacturing support facilities such as..........

Please clarify the intent as Detailed Engineering for

PEB Structures like Gantry etc. are generally not in

the scope of the Consultant but is with the EPC

contractor. However the Consultant shall prepare

the Preliminary design and its specifications.

Detailed design of all civil components shall

be carried out.

Detailed engineering for support structures

like Gantry is limited to Preliminary design,

drawings and its specifications.

Page 5: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

5

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

15 2.1 B (d) 48 Preparation of Detailed Cost Estimates &

Technical Specifications

Carry out Rate Analysis and prepare detailed cost

estimates as per prevailing Standard Schedule of

Rates (SSR) and Standard data of GoTS.

We presume that client shall assist/provide the

consultant prevailing Standard Schedule of Rates

(SSR) and Standard data of GoTS.

The SSR and Standard data of GoTS are

available in public domain.

TSIIC will facilitate the same.

16 2.1 B (d) 48 Preparation of Detailed Cost Estimates &

Technical Specifications

Detailed technical specifications shall be prepared

and the consultant shall provide assistance to

client while preparation of tender Documents for

works.

We presume that Tender Preparation is not in the

Scope of Consultant.

The consultant shall provide all the necessary

inputs and assistance to client while preparing

the Tender Documents as per the Standard

Practices of Client and Project Requirements.

17 2.1 B (d) 48 Presentations & Meetings

The consultant shall attend meetings with Client,

Government, Stakeholders etc. and make

presentation(s).

Request you to kindly specify the No. of Meetings &

Presentations envisaged as it will help us to plan

our deliverables and commercials.

As and when necessary by the Client and

GoTS, the consultant team led by the Team

Leader shall attend meetings with Client,

Government, Stakeholders etc., and make

presentation(s).

18 2.2.4 49 Submission of Final Master Plan

Submission of Final Master Plan and Infrastructure

Plan Report (Stage -2 tasks & Outcomes) after

presentation to Client & Govt. of Telangana –

D+3.5

We request you to kindly increase the time by

another 3 Months as it is difficult to prepare the

Engineering Design of the envisaged infrastructure

components as per TOR. Moreover unless the

Conceptual Master plan is not approved the design

of the Infrastructure components cannot be started

else it may lead to redesigning of work and

subsequently impacting the effort and commercial

of the project.

The revised timelines are as below.

S.No

Details Time Duration (in Months)

1 Inception Report D*+0.25

2 Submission of Inception Report covering Stage 1 Tasks & outcomes

D+1.5

3 Submission of Draft Master Plan & Infrastructure Plan Report

D+2.5

4 Submission of Final Master Plan & Infrastructure Plan Report. (after presentation to client & GoTS)

D+3.0

Page 6: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

6

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

5 Submission of Draft Detailed Engineering Reports for External Infrastructure Linkages (as per Clause 2.1 B(b) &(d) of Schedule-1)

D+4.0

6 Submission of Final Detailed Engineering Reports for External Infrastructure Linkages (as per Clause 2.1 B(b) &(d) of Schedule-1)

D+4.5

7 Submission of Draft Detailed Engineering Reports for Internal Infrastructure (as per Clause 2.1 B(c) &(d) of Schedule-1)

D+5.0

8 Submission of Final Detailed Engineering Reports for Internal Infrastructure Linkages (as per Clause 2.1 B(c) &(d) of Schedule-1)

D+5.5

*D – Start date of assignment/date of signing of agreement/issue of LoA. Note: The Master Plan & Infrastructures component proposal shall be supported with 3D models, walkthroughs and films for better visualization of project components.

Page 7: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

7

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

19 2.3 50 Payment Schedule

S.No. Payment Milestones % of total Professional Fee

1 Inception Report Nil

2 Interim Report 10%

3 Submission of Draft Master Planning Report

30%

4 Approval on Draft Master Planning Report by TSIIC/ Govt of Telangana

10%

5 Submission of Final Master Planning Report

30%

6 Approval on Final Master Planning Report by TSIIC/ Govt. of Telangana

20%

S.No. Payment Milestones % of total

Profession

al Fee

1 Advance 10%

2 Inception Report 10%

3 Interim Report 10%

4 Submission of Draft Master Planning Report

40%

5 Approval on Draft Master Planning Report by TSIIC/ Govt of Telangana

5%

6 Submission of Final Master Planning Report

20%

7 Approval on Final Master Planning Report by TSIIC/ Govt. of Telangana

5%

The revised payment schedule is as below.

S.No Payment Milestones % of total

Professional

Fee

1 Mobilization Advance (on submission of Performance Security)

5%

2 Interim Report 10%

3 Submission of Draft Integrated Master Planning Report

15%

4 Submission and Approval of Final Integrated Master Planning Report TSIIC/ Govt of Telangana

5%

6 Submission of Draft Detailed Engineering Reports for External Infrastructure Linkages

15%

7 Submission and Approval of Final Detailed Engineering Reports for External Infrastructure Linkages by TSIIC/ Govt of Telangana

10%

8 Submission of Draft Detailed Engineering Reports for Internal Infrastructure

30%

9 Submission and Approval of Final Detailed Engineering Reports for Internal Infrastructure Linkages TSIIC/ Govt of Telangana

10%

Page 8: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

8

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

20 APPENDI

X-I –

FORM-7

101 Financial Capacity of the Applicant

Certificate from the Statutory Auditor

We request you to accept the Balance Sheets of

the Firm which are already Certified from the

Statutory Auditor and the APPENDIX-I – FORM-7

further can be certified by a C.A, since most of the

firms get their balance sheet audited by Statutory

Auditor and it‟s a cumbersome process to get it

Certified again.

Permitted.

21 1.8 7 Schedule of selection process

Proposal Due Date (PDD) & Time - 22-02-2016 at

15.00 HRS (IST)

We request you to kindly extend the Bid

Submission Date by next 4 weeks after the

response of Pre-Bid since the envisaged project/s

are vast and requires substantial time and input to

frame a competitive bid.

PDD extended upto 10.03.2016, 15.00 Hrs

(IST).

EGIS India

23 2.2.2 11 Eligible Assignments

Experience of Detailed Master Planning and

Infrastructure Planning of Industrial Park / SEZ

/Industrial Estate projects of 2000 Acres or above

in a single project.

Kindly consider experience in Urban Cities/ Area

along with other sectors.

Request you to consider as below:

Experience of Detailed Master Planning and

Infrastructure Planning of Industrial

park/SEZ/Industrial Estate Projects/Urban Area of

2000 Acres or above in single Project.

RFP Clause holds good.

24 2.2.2. E 11 Conditions of Eligibility for Key Personnel

Key Personnel Educational

Qualification

Urban and Regional

Planner cum Team

Leader

Masters in Urban

Planning

Conditions of Eligibility for Key Personnel

Key Personnel Educational

Qualification

Urban and Regional

Planner cum Team

Leader

Masters in Urban

Planning or Equivalent

The Revised Eligibility for Key Personnel is as

follows:

Team Leader: Masters in Engineering or

Planning.

Regional Planner: Masters in Urban

Planning.

Page 9: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

9

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

25 3.1.2 31 Evaluation of Technical Proposal

Key Personnel having desired Educational

qualification and No. of years‟ experience shall be

considered. Each Key Personnel will be eligible for

marking (as below) only if each of them is existing

employee of the Applicant firm (Permanent

employee) and meets the Minimum Specific

Experience for Eligibility stipulated in clause 2.2.2

(D).

It is understood that only existing employee of the

applicant firm (Permanent Employee) shall be

considered.

We request you to kindly relax this condition. Kindly

Confirm.

Please refer response at S.No (10).

26 2.1 A (a) 42 Scope of Work

The Consultant Team shall hold Stakeholder

Consultations (Client, Government, Industry

Associations, Concerned Departments etc.) to

understand – (i) Client‟s Vision for the Project, (ii)

Client Expectations, (iii) Industry Feedback on the

nature of project development, (iv) Department of

Industrial Policy & Promotion (DIPP)‟s,

Government of India Expectations from the project

under the National Investment & Manufacturing

Zone (NIMZ) Scheme and MAKE IN INDIA

Program, (v) Infrastructure Service Providers to

understand external linkage options etc.,

Kindly confirm if the cost to be incurred for the

Stakeholder consultations shall be borne by TSIIC

(Client) such as Venue, Logistics etc.

Please confirm.

In case the stakeholder consultations are

proposed to be held at TSIIC Head Quarters,

venue for the same will be facilitated by

Client.

All other consultations as deemed necessary

as stated in the scope of work shall be

conducted by the consultant. The financial

proposal is inclusive of all such consultations.

27 2.1 A

(c )

43 Preparation of Base Map

Base Map for the Project Site shall be prepared

showing the (i) Site boundary as obtained from the

Topographic Survey and co-related with the

Cadastral Maps of the Site, (ii) Existing settlements

in the vicinity and within the Site (if any), (iii)

Existing road network within and in the vicinity of

the Site, (iv) Existing physical features such as

water bodies, streams, hills/hillocks, rocky areas,

Forests etc., (v) Administrative boundaries of

Request Client to furnish data with respect to

Revenue Village Boundaries for villages falling

within the site and requesting to also furnish data

with respect to cadastral Data (from Remote

Sensing Application Centre).

Kindly Confirm.

Requesting the client to suggest an appropriate

scale for preparation of Base Map.

The consultant shall collect all necessary data

for preparation of comprehensive base map

for the project.

TSIIC may facilitate such data as per

availability.

The appropriate scale shall be decided by the

consultant keeping in view of project size and

Page 10: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

10

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

villages / Mandals / districts that fall within the Site,

(vi) Built up features such as temples/shrines etc.

its specific requirements.

28 2.1 A (d) 44 Regional Setting & Site Analysis

Review the existing landuse at the Site using the

aid of latest available landuse map procured from

Telangana State Remote Sensing Applications

Centre (TSRAC) and validated with the

reconnaissance surveys carried out by the

Consultant Team.

It is that the cost of procuring Landuse Map, if any,

shall be borne by the client?

The consultant shall procure the same at their

own cost.

29 2.3 50 Payment Schedule

Payment Milestone % of Total

Professional Fee

Inception Report Nil

We request you to release at least 10% of the

Professional Fee at the submission/Approval of

Inception Report.

Kindly confirm.

Please refer response at S.No (19).

30 4.4 71 Substitution of Key Personnel

The Authority expects all the Key Personnel

specified in the Proposal to be available during

implementation of the Agreement. The Authority

will not consider any substitution of Key Personnel

except under compelling circumstances beyond

the control of the Consultant and the concerned

Key Personnel. Such substitution shall be limited

to not more than two Key Personnel subject to

equally or better qualified and experienced

personnel being provided to the satisfaction of the

Authority.

Without prejudice to the foregoing, substitution of

one Key Personnel shall be permitted subject to

reduction of remuneration equal to 20% (twenty

per cent) of the total remuneration specified for the

Key Personnel who is proposed to be substituted.

Request you to relax this condition.

RFP Clause holds good.

Page 11: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

11

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

In case of a second substitution, such reduction

shall be equal to 50% (fifty per cent) of the total

remuneration specified for the Key Personnel who

is proposed to be substituted.

31 7.2.1 75 Liquidated Damages for error/variation

In case any error or variation is detected in the

reports submitted by the Consultant and such error

or variation is the result of negligence or lack of

due-diligence on the part of the Consultant, the

consequential damages thereof shall be quantified

by the Authority in a reasonable manner and

recovered from the Consultant by way of deemed

liquidated damages, subject to a maximum of 50%

(fifty per cent) of the Agreement Value.

Request you to relax this condition.

RFP Clause holds good.

32 7.2.2 75 Liquidated Damages for delay

In case of delay in completion of Services,

liquidated damages not exceeding an amount

equal to 0.2% (zero point two per cent) of the

Agreement Value per day, subject to a maximum

of 10% (ten per cent) of the Agreement Value will

be imposed and shall be recovered by

appropriation from the Performance Security or

otherwise. However, in case of delay due to

reasons beyond the control of the Consultant,

suitable extension of time shall be granted.

Request you to relax this condition.

RFP Clause holds good.

33 1.8 7 Schedule of selection process

Proposal Due Date (PDD) & Time - 22-02-2016 at

15.00 HRS (IST)

Request you to extend bid submission date by

2 weeks from the date of issue of clarifications.

Please refer response at S.No (4).

Page 12: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

12

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

34 Schedule

1

2.2

49 Deliverables

1 Inception Report D*+0.25

2 Submission of Inception

Report covering Stage 1

Tasks & outcomes

D+1.5

3 Submission of Draft Master

Plan & Infrastructure Plan

Report

D+3.0

4 Submission of Final Master

Plan & Infrastructure Plan

Report.

(after presentation to client &

GoTS)

D+3.5

The current Project duration is mentioned as

approximately 3.5 months. As the project scope

entails objectives such as:

1. Project Site Visit & Field Surveys

2. Preparation of comprehensive Base Map

3. Preparation of Detailed Site Master Plan

4. Trunk Infrastructure Planning & Design

5. Detailed Project Cost Estimates etc.

To adhere to the respective project deliverable

timeframe, the mentioned project duration of

3.5 months is too short. The major task includes

procurement of existing land use map from TSRAC,

conducting stakeholder consultations, undertaking

detailed surveys & site visits, preparation of Master

Plan with detailed Engineering & cost estimates etc;

which is impossible to complete within the said

project duration.

Hence we request you to kindly extend the project

duration to 9 months.

Kindly clarify & confirm.

Please refer response at S.No (18).

EDIFICE

35 1.8 7 Schedule of selection process

Proposal Due Date (PDD) & Time - 22-02-2016 at

15.00 HRS (IST)

Considering the magnitude in the RFP we request

you to please consider to postpone the PDD to

allow for proper documentation.

Please refer response at S.No (4).

Page 13: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

13

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

36 2.1.1 9 Consortium member/s

The maximum number of members allowed in a

consortium is Two (2) including Lead member,

Consortium member / Associate.

We understand that the consortium shall not consist

of more than 2 members.

1. Please revert if there is any restriction on number

of specialised sub-consultants that be appointed by

Lead member or Associate of consortium.

2. Can such sub-consultants be part of the Key

personal list due to their expertise in the field

brought to the forum?

1. Sub-consultants appointment by the

consultant is permitted limiting to their

involvement in the project for conducting

field surveys (such as Topographical &

Geotechnical, Traffic surveys, Social

surveys as deemed to be etc.,). Such

appointment shall be with the prior

approval of Client.

2. Not Allowed. (Please refer Clause 2.14.6

of RFP).

37 2.2.2. E 11 Conditions of Eligibility for Key Personnel -

Urban and Regional Planner cum Team Leader We are planning to participate as a consortium with

international firm. This firm can provide us Team

Leader as per the qualifications mentioned. In Such

scenario:

1. Which Office shall be termed as Lead Member of

the Consortium?

2. Can an International Firm be a Lead Member?

Please refer clause 2.1.1 & 2.2.2(C) of RFP.

Yes. However, Lead Member of Consortium

shall meet the eligibility criteria set forth in the

RFP.

38 2. 30 30

Authentication from Indian Embassy

Each and every page of Foreign Document(s), i.e.

Document(s) created or originating from outside

the Republic of India, such as work experience

certificate(s), financial detail(s), Power Of

Attorney(s), Undertaking(s), documentary

evidence(s), qualifying document(s), etc. shall be

compulsorily authenticated/ embossed/ legalized

from the Indian Embassy/Indian High Commission

situated in the country from where such Foreign

Document(s) are created or are originating, before

Considering the paucity of timelines after the

clarifications of queries, can the documents from

international associate be sent by e-transmit and

printed here?

Not Considered.

Page 14: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

14

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

any such Foreign Document(s) are sent to India for

the purpose of applying towards this Project. Such

authentication/ embossment/ legalization from the

Indian Embassy/Indian High Commission shall

also apply to all such document(s) that are in a

language other than English, which shall be

compulsorily be required to be translated (as the

true translated copies of the original) by a duly

certified/ authorized /qualified Translator,

supported by the affidavit of the said Translator,

certifying the correctness of the English translation.

39 2. 20 49 Deliverables

The Timelines mentioned in the RFP are not

workable for this size of the project considering the

time required for site survey and soil investigation

itself and then the thorough planning period. We

request you to validate and suggest suitable

timelines.

Please refer response at S.No (18).

40

3.1.2.2

(c ) 31 Overall Turnover

If the participating lead member is an international

firm, can the financial turnover of the member of

consortium which is a local firm be considered for

evaluation?

No.

Please refer Clause 2.1.1 & 2.2.2 (C) of RFP.

41 3.5 67

Insurance to be taken out by the Consultant

The Consultant shall, for the duration of this

Agreement, take out and maintain, and shall cause

any Sub-Consultant to take out and maintain, at its

(or the Sub-Consultant‟s, as the case may be) own

cost, but on terms and conditions approved by the

Authority, insurance against the risks, and for the

coverages, as specified in the Agreement and in

accordance with good industry practice.

If the participating firm has existing insurance cover,

then does it need to take project specific insurance

in addition to this?

Not required.

However, it shall ensure the insurance

coverage for sub-consultant firms, if any.

ATKINS INDIA

Page 15: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

15

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

42 1.8 7

Schedule of selection process

Proposal Due Date (PDD) & Time - 22-02-2016 at

15.00 HRS (IST).

Considering the enormous efforts to pull together

for the bid and in order to submit robust techno-

commercial bid for the subject assignment, it is

requested to extend the current submission date

from 22nd February 2016 to 31st March 2016.

Kindly consider and confirm.

Please refer response at S.No (4).

43 2. 30 30

Authentication from Indian Embassy

Each and every page of Foreign Document(s), i.e.

Document(s) created or originating from outside

the Republic of India, such as work experience

certificate(s), financial detail(s), Power Of

Attorney(s), Undertaking(s), documentary

evidence(s), qualifying document(s), etc. shall be

compulsorily authenticated/ embossed/ legalized

from the Indian Embassy/Indian High Commission

situated in the country from where such Foreign

Document(s) are created or are originating, before

any such Foreign Document(s) are sent to India for

the purpose of applying towards this Project. Such

authentication/ embossment/ legalization from the

Indian Embassy/Indian High Commission shall

also apply to all such document(s) that are in a

language other than English, which shall be

compulsorily be required to be translated (as the

true translated copies of the original) by a duly

certified/ authorized /qualified Translator,

supported by the affidavit of the said Translator,

certifying the correctness of the English translation.

The Subject Note necessitates for „Legalised

Authentication of the Foreign Documents‟ by Indian

Embassy situated in the respective countries

through „Apostilles‟. However, the requirement is

quite unique and will require significant time and

special coordination to get it achieved. We are

bidding in India for considerable period and our

group experience is recognised by all the Key

Government/ Semi-government Clients in India.

Thus considering these aspects, we request you to

relax this clause from the RFP. Please confirm.

Not Considered.

44

General Query – Experience

Will the experience of the Group/ Parent/ fully

subsidiary Company‟s be accepted towards

„evaluation of Eligible Assignments‟? Please

confirm.

Not Considered.

Page 16: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

16

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

45 2.12 19

PREPARATION AND SUBMISSION OF

PROPOSAL

The Proposal with all accompanying documents

(the “Documents”) and all communications in

relation to or concerning the Selection Process

shall be in English language and strictly on the

forms provided in this RFP. No supporting

document or printed literature shall be submitted

with the Proposal unless specifically asked for and

in case any of these Documents is in another

language, it must be accompanied by an accurate

translation of all the relevant passages in English,

in which case, for all purposes of interpretation of

the Proposal, the translation in English shall

prevail.

The clause clearly specifies not to submit „support

documents/ printed literature‟ unless otherwise

specifically requested by the Client. Can the Client

confirm and inform that „such documents‟ also

include work Experience certificates obtained for

the Eligible assignments or otherwise.

The applicant shall submit support documents

(Project Completion Certificates) related to

Eligible Assignments.

46 General Query

In the event „work experience certificates‟ are

required to be submitted along with the proposal,

then –

If the consultant has carried out a project (as a sub

consultant) for the Group Company, in that event

will the certificate issued by the Group Company be

accepted as proof of experience? Please confirm.

The supporting project completion certificate

shall be in the name of the “Applicant”.

47 General Query – Approval

It is understood that TSIIC is the „single approval

authority „for the project deliverables. Also, if the

Client has arrived at „Approval Mechanism‟ of the

submitted deliverables?

Please confirm.

Approval Authority includes the Client (TSIIC)

and Government of Telangana (GoTS).

Page 17: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

17

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

48

Schedule

1 TOR,

2.1 A - (e)

44

Market Study and Demand Assessment

The Consultant shall carry out a Market Study to

understand the pharmaceutical market in the

region and in the hinterland, in the context of the

proposed Pharma NIMZ.

It is stated to conduct a Market Study and Demand

Assessment of the project area. Can you please

confirm, if there is any „pre-feasibility study‟

available for the project area.

Also, the scope requires to conduct Market Study,

but the Position of Market Analyst is not included in

the Key Personnel. Please confirm that the

Consultants are not expected to furnish this specific

CV.

No.

Market Study Expert is now included in the

Key Personnel List with the following

qualification and experience:

Educational

Qualification

MBA (Marketing)

Length of

Professional

Experience

(years)

10

Experience on

Eligible

Assignment

Should have

experience as a

Market Study Expert in

more than 2 eligible

assignments.

The revised list of Key personnel, Eligibility,

and scoring criteria for evaluation are

enclosed.

49 General Query – Data

Can you please inform whether the Client has

topography or contour map, geo reference map and

any other background studies/ reports available for

the project area? Will it be possible to view these

reports/ maps/ info prior to Proposal Submission?

Please confirm.

The consultant shall collect all such

necessary data through primary surveys for

the project.

Page 18: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

18

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

50

2.2 & 2.3

49 & 50

Deliverables & Payment Schedule

From the Scope of Work (specified under TOR) vis-

à-vis Deliverable schedule mentioned in the subject

reference, it is understood that the outlined

schedule for the assignment is very inadequate.

The topo surveys of 5000 acres of land and the

Market Demand Assessment Study will itself take a

time of 6 months. These are the two dependent

factors on which the Conceptual and Detailed

Master Plan will be based. Moreover the detailed

cost estimates and detailed drawings will require

significant time to produce meaningful quality

deliverable. Thus in the interest of „realistic project

timelines and the quality‟, we strongly recommend

following Schedule.

Please refer response at S.No (18) & (19).

S.N

o.

Payment Milestones % of total

Professional

Fee

1 Advance Payment 5%

2 Inception Report 5%

3 Interim Report 10%

4 Submission of Draft Master

Planning Report

30%

5 Approval on Draft Master

Planning Report by TSIIC/

Govt of Telangana

10%

6 Submission of Final Master

Planning Report

30%

7 Approval on Final Master

Planning Report by TSIIC/

Govt. of Telangana

10%

Page 19: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

19

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

51 General Query - GIS Are there any deliverables required in GIS

Platform? Please confirm.

Yes.

The comprehensive base map, detailed

master plan, infrastructure development plan

etc. shall be developed and submitted in GIS

platform also.

52 General Query – CAD Dwg

Please confirm the Scale of Detailed Drawings (for

Infra components) to be produced as the outcome

of the project.

The appropriate scale shall be decided by the

consultant keeping in view of project size and

its specific requirements.

53

Appendix

– I, form

14

108 Proposal for Sub-Consultant(s)

Is there any limit of work to be sub-contracted to the

Sub-Consultants? If yes, please elaborate the

details.

Will the experience/ CV of the sub-consultants will

accepted/ considered towards technical evaluation?

Please confirm.

Please refer response at S.No (36).

Not considered.

Yooshin Engineering Corporation, Korea.

54 1.8 7

Schedule of selection process

Proposal Due Date (PDD) & Time - 22-02-2016 at

15.00 HRS (IST)

As the project scope is complex and needed to be

carefully analyzed to understand the project's

specific feature and to derive the most suitable

approach and methodology, we would like to take

more time for the proposal preparation. We hope

your kind understanding on our efforts for proposal

preparations.

Your kind consideration of circumstances, we ask

for the extension of proposal submission due date

for four (4) weeks.

Please refer response at S.No (4).

Page 20: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

20

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

SWA Group, USA

55

General

Do you have an expected date the RFP will be

issued? Is there an expected date for the RFP to be

due?

RFP document is available at the Client‟s web

site as below.

http://tsiic.telangana.gov.in/tenders/

56

With our expertise in design and planning, we

typically partner with an engineering firm who

provides infrastructural support. We noticed that

many of the other shortlisted firms are engineering

firms that we have worked with on projects that are

similar to yours. Do you see this project as being

led by an engineer and/or are you open to us

partnering with an engineer on the shortlist? We

would also be happy to bring in another engineer

for the RFP if you would like to see a wider

proposal list.

Please refer response at S.No (55).

Intercontinental Consultants and Technocrats Pvt. Ltd.

57 2.2.2. E 11 Conditions of Eligibility for Key Personnel

It mentions that Key personnel (Team Leader,

Infrastructure planning expert, environment expert,

etc.) need to have experience of more than two (2)

eligible assignments i.e., project area be 2000

acres or more as per the RFP.

It is proposed that 'eligible assignments' with

different/varying project areas (covering project

areas less than 2000 acres also).

Please confirm.

Not Considered.

Page 21: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

21

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

58 2.11.3 19

Amendment of RFP

In order to afford the Applicants a reasonable time

for taking an amendment into account, or for any

other reason, the Authority may, in its sole

discretion, extend the PDD.

Considering the scope of the project, it is

requested, at least three (3) weeks time be given to

the consultants for preparation of the proposals

from date of issue of pre-bid clarifications i.e. the

date of submission may be extended till 15th March

2016

Please refer response at S.No (4).

59

Schedule

1

1.2.2

40

Land Details

The project is proposed in around 12,500 acres.

The Consultant shall prepare the Master Plan for

the first phase of the project with an area of 5000

acres (Phase 1). The identified location falls in

Kandukur and Yacharam Mandals of Ranga Reddy

District and Partly in Amangal Mandal of

Mahbubnagar District, as shown above.

We understand that boundary map of Phase -1 of

area 5000 acres will be made available by the

client.

Please clarify.

Will be provided to the selected consultant.

60

Schedule

1

2.1. A (a)

42

Site Visits, Data Collection and Stakeholder

Consultations

The Consultant Team shall hold Stakeholder

Consultations (Client, Government, Industry

Associations, Concerned Departments etc.) to

understand – (i) Client‟s Vision for the Project, (ii)

Client Expectations, (iii) Industry Feedback on the

nature of project development, (iv) Department of

Industrial Policy & Promotion (DIPP)‟s,

Government of India Expectations from the project

under the National Investment & Manufacturing

Zone (NIMZ) Scheme and MAKE IN INDIA

Program, (v) Infrastructure Service Providers to

understand external linkage options etc.,

We understand that the client will provide all

logistics for stakeholders' meetings including

venues, room space, refreshments, etc and the

consultant will provide only technical inputs; as and

when requires to be organized during the total

duration of the project.

Please Clarify.

Please refer response at S.No (26).

Page 22: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

22

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

61

Schedule

1

2.1. A

( c)

43

Preparation of Base Map

Base Map for the Project Site shall be prepared

showing the (i) Site boundary as obtained from the

Topographic Survey and co-related with the

Cadastral Maps of the Site, (ii) Existing settlements

in the vicinity and within the Site (if any), (iii)

Existing road network within and in the vicinity of

the Site, (iv) Existing physical features such as

water bodies, streams, hills/hillocks, rocky areas,

Forests etc., (v) Administrative boundaries of

villages / Mandals / districts that fall within the Site,

(vi) Built up features such as temples/shrines etc.

It mentions that preparation of base map will cover

existing settlements in the vicinity of the site. In

view of this, please elaborate the area to be

covered beyond the site of 'Pharma NIMZ'?

The base map shall show all the physical

features within the project site as well as

surrounding area covering Srisailam Highway,

Nagarjuna Sagar Highway and connecting

roads to the site from Outer Ring Road.

62

Schedule

1

2.1.A(c)

Topographic survey and its correlation with

Cadastral maps.

We understand that the cadastral maps of the site

are available with the client and shall be made

available to the consultant free of cost.

Please Clarify.

Please refer response at S.No (27).

63

Schedule

1

2.1. A (d)

44

Regional Setting & Site Analysis

Review the existing landuse at the Site using the

aid of latest available landuse map procured from

Telangana State Remote Sensing Applications

Centre (TSRAC) and validated with the

reconnaissance surveys carried out by the

Consultant Team

Following observations with respect to the

availability of latest Land Use Maps from TSRAC.

(a) It will be made available in Hard & Soft copies

with consultant by the Client at free of cost? Please

Confirm.

(b) What is the date of preparation, scale and total

area covered by this Land Use Map? Please

Clarify.

Please refer response at S.No (28).

Page 23: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

23

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

64

Schedule

1

2.1. A (e)

44

Market Study and Demand Assessment

The Consultant shall carry out a Market Study to

understand the pharmaceutical market in the

region and in the hinterland, in the context of the

proposed Pharma NIMZ

The 'Region' to conduct the Market Demand

Assessment Survey may be defined like whether it

is to be conducted at State Level? Please Clarify.

Hyderabad region in particular and Telangana

State & Country Scenario in general.

65

Schedule

1

2.2

49

Deliverables

1 Inception Report D*+0.25

2 Submission of Inception Report covering Stage 1 Tasks & outcomes

D+1.5

3 Submission of Draft Master Plan & Infrastructure Plan Report

D+3.0

4 Submission of Final Master Plan & Infrastructure Plan Report.

(after presentation to client & GoTS)

D+3.5

We understand that the time taken by the client on

giving the consent, comment, milestones' shall be

considered in addition to the given time line of 3.5

months given in the RFP Document.

Please Clarify.

Please refer response at S.No (18) for revised

deliverables and timelines.

66 2.3 50

Payment Schedule

S.No. Payment Milestones % of total Professional Fee

1 Inception Report Nil

Interim Report 10%

3 Submission of Draft Master Planning Report

30%

4 Approval on Draft Master Planning Report

10%

It is suggested that a Mobilization Advance of 10%

may be given against Bank Guarantee of the same

amount and this amount may be adjusted against

the milestone of approval of final Master Plan

Report i.e. 10% (in place of 20%).

Please Clarify.

Please refer response at S.No (19).

Page 24: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

24

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

by TSIIC/ Govt of Telangana

5 Submission of Final Master Planning Report

30%

6 Approval on Final Master Planning Report by TSIIC/ Govt. of Telangana

20%

67 2.4 50 Consultancy Team

Considering the Scope of the Work, it is suggested

that the team may also include the following

positions:

1. Rail Expert

2. Solid Waste Management Expert

3. Power/Electricity Engineer

4. Geo-technical Expert

5. BoQ Expert.

The revised list of Key personnel and scoring

criteria for evaluation are enclosed.

Infrastructure Development Corporation (Karnataka) Limited

68 2.1.1 9

Scope of Proposal

The term Applicant (the “Applicant”) means the

Sole Firm or Lead Member, as the case may be.

For evaluation of eligibility criteria, request this to be

Changed as follows:

The term Applicant (the “Applicant”) means the Sole

Firm or the Consortium as the case may be.

The main reason for forming a Consortium would

be to bring together the synergies of two parties

possessing specific credentials/strengths which

would add more value to the services to be

provided, hence for evaluation of the credentials of

the Consortium, the combined strengths of both the

parties should ideally be considered.

Clause 2.2.2 (A) & (B): Shall be met by the

Sole Firm (or) Consortium as the case may

be.

Clause 2.2.2 (C): Shall be met by the Sole

Firm (Or) Lead Member of the Consortium as

the case may be.

Page 25: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

25

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

69 2.2.2 (B) 10

Eligible Assignments

Experience of Detailed Master Planning and

Infrastructure Planning of Industrial Park / SEZ

/Industrial Estate projects of 2000 Acres or above

in a single project

Request this to be altered as follows:

Experience of Detailed Master Planning/Conceptual

planning, feasibility assessment and Infrastructure

Planning of Industrial Park / SEZ /Industrial

Estate/Corridor projects of 2000 Acres or above in a

single project

Not considered.

70 2.2.2 (C) 11

Financial Capability

The Applicant shall have an average annual

turnover of Rs. 20 Crores during each of the last

three financial years preceding the PDD. The

revenues from the consulting/advisory services will

only be considered for evaluation. Turnover of

Associates/JVs will not be considered.

Request this criteria to be changed as follows:

The Applicant shall have an average annual

turnover of Rs. 10 Crores over the last three

financial years preceding the PDD. The revenues

from the consulting/advisory services will only be

considered for evaluation.

In case of a Consortium the sum total of the

individual turnovers of the members would be

considered for evaluation.

The reason for the above request is to allow a

better competition among firms since there are

consultancy firms with vast experience in similar

large sized projects but with lesser turnover

amounts.

Not Considered.

Please refer response at S.No (68).

71

Schedule

- 1

2.3

50

Payment Schedule

TSIIC shall make payment to the selected

consultant based on the following payment

schedule.

S.No. Payment Milestones % of total

Professional

Fee

1 Inception Report Nil

Incorporating the Mobilisation Fees. Request this to

be altered as follows:

Payment Schedule:

TSIIC shall make payment to the selected

consultant based on the following payment

schedule.

S.No. Payment Milestones % of total

Professional Fee

1 Inception Report 10%

Please refer response at S.No (19).

Page 26: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

26

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

Interim Report 10%

3 Submission of Draft

Master Planning Report

30%

4 Approval on Draft

Master Planning Report

by TSIIC/ Govt of

Telangana

10%

5 Submission of Final

Master Planning Report

30%

6 Approval on Final

Master Planning Report

by TSIIC/ Govt. of

Telangana

20%

2 Interim Report 10%

3 Submission of Draft

Master Planning Report

30%

4 Approval on Draft

Master Planning Report

by TSIIC/ Govt of

Telangana

10%

5 Submission of Final

Master Planning Report

30%

6 Approval on Final

Master Planning Report

by TSIIC/ Govt. of

Telangana

10%

72 3.4.4 67

Liability of consultant

This limitation of liability specified in Clause 3.4.3

shall not affect the Consultant‟s liability, if any, for

damage to Third Parties caused by the Consultant

or any person or firm acting on behalf of the

Consultant in carrying out the Services subject,

however, to a limit equal to 3 (three) times the

Agreement Value.

Request this to be changed as follows:

Liability of consultant:

This limitation of liability specified in Clause 3.4.3

shall not affect the Consultant‟s liability, if any, for

damage to Third Parties caused by the Consultant

or any person or firm acting on behalf of the

Consultant in carrying out the Services subject,

however, to a limit equal to the Agreement Value.

Revised to a limit equal to the Agreement

Value.

Page 27: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

27

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

73 3.5.1 (d) 68

Insurance to be taken out by the Consultant

Except in case of Third Party liabilities, the

insurance policies so procured shall mention the

Authority as the beneficiary of the Consultant and

the Consultant shall procure an undertaking from

the insurance company to this effect; provided that

in the event the Consultant has a general

insurance policy that covers the risks specified in

this Agreement and the amount of insurance cover

is equivalent to 3 (three) times the cover required

hereunder, such insurance policy may not mention

the Authority as the sole beneficiary of the

Consultant or require an undertaking to that effect.

Request this to be changed as follows:

Except in case of Third Party liabilities, the

insurance policies so procured shall mention the

Authority as the beneficiary of the Consultant and

the Consultant shall procure an undertaking from

the insurance company to this effect; provided that

in the event the Consultant has a general insurance

policy that covers the risks specified in this

Agreement and the amount of insurance cover is

equivalent to the cover required hereunder, such

insurance policy may not mention the Authority as

the sole beneficiary of the Consultant or require an

undertaking to that effect.

Considered.

74 3.5.2 68

The Parties agree that the risks and coverages

shall include but not be limited to the following:

(a) Third Party liability insurance as required under

Applicable Laws, with a minimum coverage of____

Request this to be clarified Third Party liability insurance as required

under Applicable Laws, with a minimum

coverage equivalent to the Agreement Value

75 4.4 74

Substitution of Key Personnel

The Authority expects all the Key Personnel

specified in the Proposal to be available during

implementation of the Agreement. The Authority

will not consider any substitution of Key Personnel

except under compelling circumstances beyond

the control of the Consultant and the concerned

Key Personnel. Such substitution shall be limited

to not more than two Key Personnel subject to

equally or better qualified and experienced

personnel being provided to the satisfaction of the

Authority. Without prejudice to the foregoing,

substitution of one Key Personnel shall be

permitted subject to reduction of remuneration

equal to 20% (twenty per cent) of the total

remuneration specified for the Key Personnel who

As any substitution of key personnel would be done

with another personnel with either equal or higher

qualification/experience, request the clause for

second substitution to be waived off.

Not Considered.

Page 28: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

28

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

is proposed to be substituted. In case of a second

substitution, such reduction shall be equal to 50%

(fifty per cent) of the total remuneration specified

for the Key Personnel who is proposed to be

substituted.

76 7.1.1 74

Performance Security

The Authority shall retain by way of performance

security (the “Performance Security”), 10% (Ten

per cent) of all the amounts due and payable to the

Consultant, to be appropriated against breach of

this Agreement or for recovery of liquidated

damages as specified in Clause 7.2. The balance

remaining out of the Performance Security shall be

returned to the Consultant at the end of 3 (three)

months after the expiry of this Agreement pursuant

to Clause 2.4 hereof. For the avoidance of doubt,

the parties hereto expressly agree that in addition

to appropriation of the amounts withheld

hereunder, in the event of any default requiring the

appropriation of further amounts comprising the

Performance Security, the Authority may make

deductions from any subsequent payments due

and payable to the Consultant hereunder, as if it is

appropriating the Performance Security in

accordance with the provisions of this Agreement.

Request this to be changed as follows as per the

model documents for such services:

Performance Security:

The Authority shall retain by way of performance

security (the “Performance Security”), 5% (Five per

cent) of all the amounts due and payable to the

Consultant, to be appropriated against breach of

this Agreement or for recovery of liquidated

damages as specified in Clause 7.2.

Not Considered.

Page 29: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

29

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

77 7.2.2 75

Liquidated Damages for delay

In case of delay in completion of Services,

liquidated damages not exceeding an amount

equal to 0.2% (zero point two per cent) of the

Agreement Value per day, subject to a maximum

of 10% (ten per cent) of the Agreement Value will

be imposed and shall be recovered by

appropriation from the Performance Security or

otherwise. However, in case of delay due to

reasons beyond the control of the Consultant,

suitable extension of time shall be granted.

Request this to be changed as follows:

Liquidated Damages for delay

In case of delay in completion of Services,

liquidated damages not exceeding an amount equal

to 0.1% (zero point one per cent) of the Agreement

Value per day, subject to a maximum of 5 (Five per

cent) of the Agreement Value will be imposed and

shall be recovered by appropriation from the

Performance Security or otherwise. However, in

case of delay due to reasons beyond the control of

the Consultant, suitable extension of time shall be

granted.

Not Considered.

L&T Infra Engineers Pvt Ltd.

78

2.2.2. E

11

Conditions of Eligibility for Key Personnel

A. Urban and Regional Planner cum Team

Leader

The proposed project requires a Team Leader who

has an overall exposure of the entire project cycle

in infrastructure / industrial / SEZ projects

beginning from project concept, engineering

surveys, traffic and transportation, market study and

demand assessment, infrastructure demand,

engineering design, cost estimation, environmental

and social impact assessment studies including

seeking environmental clearance from Ministry of

Environment and Forests. In view of the above, we

request TSIIC to have a team leader with the above

experience for an efficient and quality deliverable.

Hence we request TSIIC split the Urban and

Regional Planner-cum-Team Leader in two

positions as requested below.

The revised list of Key personnel, their

Eligibility, and scoring criteria for evaluation

are enclosed.

Page 30: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

30

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

A. Team Leader - Post Graduate in any

discipline

-20 Years

2 Urban and Regional Planner - Bachelor / Post

graduation Urban planning /Regional Planning

-15 years

B. Sector Expert

The scope of work for the proposed requires a

Sector Expert who has large experience in carrying

out market studies and demand assessment for

industrial sectors. In this regard we request TSIIC to

allow Key personnel with MBA qualification to be

field as Sector Experts

C. Water Expert

We request TSIIC to consider key personnel having

Master in Science / Environment Management /

Environment Engineering eligible to be fielded as

water experts.

D. GIS Expert

We request TSIIC to allow personnel with M Tech

Remote Sensing and GIS to be field as GIS Expert

E. Individual / Retainer Consultants

The team composition requires a multiple sector

experts and hence TSIIC is requested to allow

including individual consultants for at least three

positions other than Team Leader.

Please refer response at S.No (10).

Page 31: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

31

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

79

Schedule

1

2.2

49

Deliverables

Government of Telangana has a vision to create a

Pharma City of international standards and position

Hyderabad as a Global Pharma Hub. Therefore

sufficient time has to be provided for developing a

master plan of international standards and carrying

out detailed engineering design of the offsite and

onsite infrastructure facilities. The timelines given in

the RFP are inadequate to provide a quality

deliverable. We suggest the following changes in

the timeline for consideration of TSIIC :

1 Inception Report D*+0.25

2 Submission of Inception

Report covering Stage

1 Tasks & outcomes

D+2.5

3 Submission of Draft

Master Plan &

Infrastructure Plan

Report

D+3.5

4 Submission of Final

Master Plan &

Infrastructure Plan

Report. (after

presentation to client &

GoTS)

Within 2 weeks from

the receipt of

suggestions from

TSIIC

5 Submission of Draft

Infrastructure Plan

Report

D + 5.5

6 Submission of Final

Infrastructure Plan

Report

Within 4 weeks from

the receipt of

suggestions from

TSIIC

Please refer response at S.No (18).

Page 32: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

32

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

CBRE South Asia Pvt. Ltd

80 2.1.4 9

Key Personnel:

Urban & Regional Planner/Team Leader

Infrastructure Planning Expert

Environmental Expert

Water/Waste Water Expert

Urban Design Expert

Transportation Expert

Sector Expert (Pharmaceuticals)

Architect

Landscape Expert

GIS Expert

As per the Terms of Reference (Schedule 1) Stage

1: Preparation of Conceptual Master Plan for Phase

1 of Pharma NIMZ involves Market Study and

Demand Assessment and this exercise will form the

basis for formulating the product mix which will form

the critical base for the master plan.

As observed from RFPs floated by other

government agencies, such an exercise would

require a Market/Real Estate Expert with suitable

experience in carrying out demand assessment

studies in similar projects. Considering the above,

we kindly request TSIIC that a key personnel

position for “Market/Real Estate Expert” with

suitable experience also be added to the list of key

personnel.

Please refer response at S.No (48).

81 2.2 50

Deliverables

Submission of Interim Report covering Stage-1

tasks & outcomes is Due in 1.5 months.

Considering the exhaustive scope detailed out and

since a sector specific market assessment has to

be carried out along with interactions with industry

groups, plot level space demands including demand

for allied infrastructure, socio-economic benefits

and potential for a proposed pharma university, we

request that the time line for the interim report be

extended to 3 Months.

Please refer response at S.No (18).

Voyants Solutions Pvt. Ltd.

Page 33: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

33

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

82 2.2.2 (E) 12

Condition of Eligibility for Key Personal

GIS Expert:

Graduate Engineer with professional qualification

in CAD & GIS. Should have experience as a GIS

expert for more than 2 projects.

We would like to request you that Kindly consider

Master Degree in Geoinformatic for GIS expert

instead of Graduation in Engineering. The Master

Degree in Geoinformatic is specialized master

degree for GIS and Remote Sensing work.

RFP Clause holds good.

83 3.1.2 31

Evaluation of Technical Proposal

2b)

Master planning experience in Eligible Projects

with pharma sector as a component with an area

over 500 acres

(One completed assignment shall carry five

marks each, upto a maximum of 10 (ten) Marks)

Kindly relax the sector specific criteria to “Master

planning experience in Eligible Projects with

pharma sector as a component with an area over

250 acres”.

RFP Clause holds good.

84 2.1 (B)

Stage 2 47

Preparation of Detailed Master Plan for Phase 1

of Pharma NIMZ

(B) Detailed Engineering and Designs –

External Linkages

The Consultant shall carry out detailed engineering

designs of all identified external linkages using

appropriate tools and methods duly adhering to the

relevant IS Codes, covering but not limited to the

following:

o External road links

o Rail spur line, if any

o Power feeder lines, sub stations and other power

linkage infrastructure

o Water sourcing, pumping, conveyance, storage

and treatment

o Storm water disposal

o And all other identified external links for the

Please give us the details of identified source of

Power, Water Supply, and storm water outfall from

the proposed site for external infrastructure design.

Such details need to be assessed and

proposals to be made by the Consultant.

Page 34: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

34

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

Project

85

Schedule

1

2.2

49 Deliverables

We think the 3.5 months period is very less to carry

out stage 1 and stage 2. We are of the view the

time should be at least 12 weeks for stage 1 and 18

weeks for stage 2. Further we understand that the

time duration specified for each deliverable

excludes the time that will be taken for approval by

the client.

Please refer response at S.No (18).

86 2.2.3 12

Condition of Eligibility

The Applicant shall enclose with its Proposal,

certificate(s) from its Statutory Auditors stating its

annual turnover during each of the past three

financial years.

Kindly consider certificate from “Chartered

Accountant” stating annual turnover of last 3

Financial Years.

Please refer response the query at S.No (20).

86

General Queries

We understand that for the preparation of Master

Plan as mentioned in ToR, the required data is

available with respective authorities which will be

made available to the consultant free of cost by

client after the award of contract. Kindly confirm.

Please refer response at S.No (27) & (28).

87 Kindly let us know the details of data available for

the assignment.

88

Please provide the man months/manning schedule

for each expert. This will enable all the firms to bid

on a specific number of man-months. The final

man-months can be negotiated with the preferred

bidder before contract signing.

The Consultant shall assess the same based

on their specific experience in delivering this

kind of projects in a time bound manner.

89

We would also like to confirm that the permissions

from the other authorities or to get clearances from

other agencies are not in the scope of work of the

consultant.

The consultant scope includes coordination

with concerned departments/agencies while

obtaining the necessary

permissions/approvals.

Page 35: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

35

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

Aarvee Associates

90 2.2.2 10

Eligible Assignments

Experience of Detailed Master Planning and

Infrastructure Planning of Industrial Park / SEZ

/Industrial Estate projects of 2000 Acres or above

in a single project

Please consider Master Plans/ Preliminary

Design Reports for Industrial Areas/ Area

Development Plans with 1000 Acres.

RFP Clause holds good.

91 3.1.2 31

Evaluation of Technical Proposal

2) Relevant Experience of the Applicant

2a)

Master planning and Infrastructure planning for

Eligible Projects

5 (five) marks for each Eligible Assignment, up

to a maximum of Fifteen (15) marks.

2b)

Master planning experience in Eligible Projects

with pharma sector as a component with an area

over 500 acres

(One completed assignment shall carry five

marks each, up to a maximum of 10 (ten)

Marks)

2a)

5 (five) marks for each Eligible Assignment,

upto a maximum of Twenty (20) marks.

2b)

One completed assignment shall carry five (5)

marks

RFP Clause holds good.

92 3.1.2 31

Evaluation of Technical Proposal

2a)

Master planning and Infrastructure planning for

Eligible Projects

5 (five) marks for each Eligible Assignment,

upto a maximum of Fifteen (15) marks.

Master Planning experience in Eligible Projects with

Industrial Sector as a component with an area over

1000 acres.

Please consider 1 project in Industrial Sector

RFP Clause holds good.

Page 36: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Clarification / Response to Pre-Bid queries

36

S.No. Clause

No. Pg. No. Clause as per RFP Query

Clarification/Response

93 2.2.2 10 & 11 Conditions of Eligibility

Marks will be given for “Completed

Assignments” only for which project

completion certificates are submitted along

with the Technical Proposal.

94 2.1 42 Schedule -1: ToR

As per the IRC Codes/Guidelines, Traffic

surveys shall also be carried out for the

external road linkages to the project.

Sd/-

Vice Chairman & Managing Director

Page 37: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Annexure to Clarification / Response to Pre-Bid queries

1. Clause 2.2.2 (E) - Conditions of Eligibility for Key Personnel :

Each of the Key Personnel must fulfil the Conditions of Eligibility specified below:

S. No. Key Personnel Educational Qualification

Length of Professional Experience (years)

Experience on eligible assignment*

1 Team Leader Masters in Engineering / Planning

15 Should have leadership experience of more than 2 eligible assignments.

2 Urban and Regional Planner

Masters in Urban Planning

15 Should have experience of planning of large cities and industrial regions with allied infrastructure with experience in at least 2 eligible assignments.

3 Infrastructure Planning Expert

Masters in Infrastructure Planning / Engineering

10 Should have experience as an infrastructure expert for more than 2 eligible assignments.

4 Environment Expert Master in Environmental Science or Engineering or equivalent

10 Should have experience as an environmental expert for more than 2 eligible assignments.

5 Water Expert Masters in Engineering

(Hydraulics/ Water Resources Engineering)

10 Should have experience as a water expert for more than 2 eligible assignments.

6 Urban Design Expert Masters in Architecture/ Urban Design

10 Should have experience as an urban design expert for more than 2 eligible assignments.

Page 38: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Annexure to Clarification / Response to Pre-Bid queries

S. No. Key Personnel Educational Qualification

Length of Professional Experience (years)

Experience on eligible assignment*

7 Transportation Expert Masters in transport planning or equivalent

10 Should have experience as a transportation expert for more than 2 eligible assignments.

8 Sector Expert:

Pharmaceutical

Masters in Pharmaceutical Sciences or Equivalent

10 Should have experience of working on industrial area of pharma sector for at least 1 eligible assignment.

9 Architect Master / Bachelor of Architecture

07 Should have experience as an architect for more than 1 eligible assignments.

10 Landscape Architect Master / Bachelor of Architecture

07 Should have experience as a landscape architect for more than 1 eligible assignments.

11 GIS Expert Graduate Engineer with professional qualification in CAD & GIS.

07 Should have experience as an GIS expert for more than 2 projects.

12 Market Study Expert MBA (Marketing)

10 Should have experience as Market Study Expert in more than 2 eligible assignments.

2. Clause 3.1.2 - Evaluation of Technical Proposals

The scoring criteria to be used for evaluation shall be as follows:

Sr. No. Particulars Marks Criteria

3 Relevant Experience of the key personnel

50 Key Personnel having desired Educational qualification and No. of years’ experience shall be considered. Each Key Personnel will be eligible for marking (as below) only if they meet the Minimum Specific Experience for Eligibility stipulated in clause 2.2.2 (D).

Page 39: Selection of Consultant for preparation of Integrated ...tsiic.telangana.gov.in/wp-content/uploads/2016/02/RFP-Queries... · Selection of Consultant for preparation of Integrated

Selection of Consultant for preparation of Integrated Master Plan for Hyderabad Pharma NIMZ Annexure to Clarification / Response to Pre-Bid queries

Sr. No. Particulars Marks Criteria

3a. Team Leader 10 The CVs the staff members qualifying minimum criteria shall be evaluated as per following

A. General Qualification: (20%)

A1. Education (10%)

A2. Professional Experience (10%)

B. Adequacy for the Assignment: Project related (65%)

B1 Experience of Eligible Assignment (25%)

B2 Experience of Special Assignment (25%)

B3 Other relevant experience (10%)

B4 Overseas/ International experience (05%)

C. Familiarity with the region (05%)

C1 Experience of working in Telangana (03%)

C2. Knowledge of local language (02%)

D. Association with the firm (10%)

D1 Years of association (10%)

3b. Urban and Regional Planner

05

3c. Infrastructure Planning Expert

04

3d. Environment Expert 04

3e. Water Expert 04

3f. Urban Design Expert 03

3g. Transportation Expert 03

3h. Sector Expert 03

3i Architect 03

3j. Landscape Architect 03

3k. GIS Expert 03

3l. Civil Engineer 03

3m. Market Study Expert 02

Grand Total 100