DR JJ MAHLANGUHOD HEALTH :MPUMALANGA
SELECT COMMITTEE ON APPROPRIATIONS: HRP
HRP GRANT OBJECTIVES
Provision of funding to enable provinces to plan manage modernise rationalise and transform the infrastructure, health technology, monitoring and evaluation of hospitals in line with national policy.To transform hospital management and improve quality of care
1
MPUMALANGA HRP PROJECTS
•
3
PROJECT NAME PROJECT STATUS
Ermelo Hospital Partially complete
Themba Hospital Partially complete
Rob Ferreira Hospital Partially complete
BUDGET EXPENDITUREUP TO 30 JUNE 2010
EXPENDITURE UP TO 30 SEPT 2010
R331 657 000 R72 797 000 R166 247 274
100% 22% 50%
HOSPITAL REVITALISATION PROJECTS
2
CURRENT HOSPITAL PROJECTS
Name of Project
Project Description
Start date Anticipated / Actual Completion date
Progress to date & Comments
Ermelo HospitalConstruction of new OPD Casualty and Theatre
21-Nov-08 07-Jul-10
Main building is complete. Project is on retention pending approval of the adjustment of provisional sums by the Department of Health Practical completion was achieved on the 07-Jul-10.Variation order received after practical completion
Ermelo Hospital
Renovations to existing Intensive Care Unit(ICU), and Maternity Ward.(Phase 4)
21-Nov-08 30-Nov-10
Main building is outstanding of theatre lights and snag list. The gate-house is 48% complete. V'O for abnormal foundation is still outstanding.
Ermelo HospitalConstruction of a new Paediatric ward. (Phase 4)
21-Nov-08 30-Nov-10
Contractor on penalties for 30 days. Progress on staff parking is 55% complete. Air-conditioning commissioned. Poor workmanship applied vinyl sheeting on uneven floor.
Ermelo HospitalConstruction of a new Health Support Block.
21-Jan-09 07-Jul-10 Practical Completion was done on the 07-Jul-10.
3
CURRENT HOSPITAL PROJECTS CONT....
Name of Project Project Description Start date Completio
n date Progress to date & Comments
Ermelo Hospital Construction of new Medico Laboratory 21-Sep-07 02-Feb-10
The practical hand over was done on the 02-Feb-10. There is pending approval on the adjustment of the provisional sums. Fire certificate was submitted. Project is 100% complete. Variation order received after practical completion date
Themba Hospital Construction of Doctor's accommodations x 30 units 05-Jun-06 TBA
Contractor have been terminated due to poor performance. The department is in a process to appoint a new contractor w ho will complete the outstanding work. Progress was at 98%.
Themba Hospital Construction of Bambanani Clinic and garages 10-Nov-08 22-May-10 Project on retention. Workmanship very good
Themba Hospital Construction of CE Workshop and New General Ward. 22-Jan-09 30 –Nov-10
Contractor is failing to complete the works. Third warning letter have written to the contractor on the 23rd September 2010 and has been put on terms. Progress is at 98%.
Themba HospitalRenovations and Upgrading of Allied, Postnatal and chronic wards
26-Mar-09 30 –Nov-10
Two floors were handed over on the 18-02-10 and 13-07-10. Transformer room is complete and equipment is awaiting delivery on the 15th October 2010. Progress is at 79%. Main contractor not paying sub-contractors
4
Name of Project
Project Description Start date Completion date
Progress to date & Comments
Themba Hospital
New Medico Legal Laboratory 05-Jun-08 30-Jun-10 Project is on retention.
Themba Hospital
Renovations and Upgrading of Ophthalmic, Orthopedic, Female &, Male Surgical and Female & Male Medical Wards.
19-Mar-09 30-Dec-10
A handful of the Wards were completed prior handing over Sectional units by mid June 2010 to the Contractor for upgrading. The other units are still to be handed over to the contractor mid October 2010.Progress is 61%.
Themba Hospital
Renovations and Upgrading of ICU / High Care, Trauma unit, Casualty, CSSD, Theatre and Children's ward.
04-Mar-10 04-Mar-11
Progress is at 15%, delays have been caused by conflict in the re-scoping of work as design architects have duplicated bills of quantities between two projects and omitted roof replacement.
CURRENT HOSPITAL PROJECTS CONT....
5
Name of Project
Project DescriptionStart date
Completion date
Progress to date & Comments
Rob Ferreira: Phase 4A
Renovations of Existing Units and construction of cafeteria. Renovations of crèche, Laboratory, theatre, and ICU block. Renovations to specialist OPD and Rehabilitation unit. Renovation to x-ray department, Office block and wards 2,3,4&8
08-Dec-08
31-Dec-10
Progress is at 95%. Remainder of the theatres have been handed over on the 01-Oct-10. Specialist OPD, and Victim Empowerment unit will be handed over on 29 October 2010.
Rob Ferreira: Phase 4B
Rob Ferreira Hospital : Construction of a basement, short stay ,day & private wards, admin block and helipad.
19-Oct-09
31-Dec-10
Progress is at 50%. Currently busy with brickwork in between the floors. Windows on the Second floor have been installed. Delays were due to world cup and materials delivery.
Rob Ferreira: Phase 4C
Rob Ferreira Hospital Construction of OPD, Casualty and Pharmacy, upgrading of OPD & dental unit , Electrical upgrade, roads, storm water and sewer, roads, roof ,gutter, mechanical work, External work, landscaping, and demolition of double story building.
01-Nov-04
18-Dec-10
Project is complete, however there is minor works to be done. Existing four lifts still needs to be removed and replaced as part of the scope. Contractor busy with snag list on former phase 2 , water and sewer connection. Electrical upgrade done. Three generators have been installed. Progress is at 100%.
CURRENT HOSPITAL PROJECTS CONT....
6
PERFORMANCE AND MONITORINGSteering committees in place
oProvincialoLocal steering committee: Project–based link
Office structureoAppointments according to DORA
Site project managersoAll sites
Reports on monthly & quarterly basisoProvincial TreasuryoNational Department of Health
Joint sites visits with public worksProject management meetings monthly
7
COORDINATION HRP PROJECTSAll projects business cases and health briefs are approved by NDoH prior to implementation.Project implementation plans submitted and approved: AnnuallyProject manager’s forums attended and reporting done: Quarterly Submission of monthly, quarterly, and annual reports to NDoH and Provincial TreasuryImplementing agent is DPWRT and IDT (Rob Ferreira) Project list of phases with available budgets are forwarded to DPWRT
8
PERFORMANCE OF CONTRACTORS AND CONSULTANTS: Rob Ferreira Hospital
Phase :2 Termination of non performing contractors and consultants implemented at Rob Ferreira for the following reasons:
oWorkmanship and design inadequaciesoIrregular variation ordersoVery slow progressoThis project has since been implemented with phase 4 and is now complete
Phase 4: consultants and contractor progress very well, good workmanship, improved project management, but renovations very costly compared to new construction
9
PERFORMANCE OF CONTRACTORS AND
CONSULTANTS: Themba Hospital
Poor project management by principal agent approving extension of time to more than doubling the actual contract period and seriously impeding service deliveryPoor performance of consultants and contractors, poor supervision of projects and slow progress. Contractors and consultants have been served with noticesMain contractor not paying sub-contractors Design architects duplicating bills of quantities in different contracts.Designs not compliant to health norms and standardsScope inadequacies leading to variation orders
10
PERFORMANCE OF CONTRACTORS AND CONSULTANTS: Ermelo Hospital
The pharmacy is complete but has leaking roof. The principal agent is unwilling to instruct contractors to repair it even though the roof still under guarantee. This is affecting the life span of pharmaceuticalsVery large variation orders for OPD, casualty and medico-legal mortuary that were submitted after completion of the projects. These have not been budgeted for.
11
REPORTING AND COORDINATION BETWEEN DPWRT AND DoH
There is a collaborative interdepartmental approach between DoH and DPWRT implemented as follows:-
Joint DoH and DPWRT meetings are held monthlySite meetings held monthlyUnannounced site visits conducted: Ad HocReports and recommendations by DoH to DPWRT are forwarded
12
CAPACITY TO IMPLEMENT HRP
Revitalisation unit structure is implemented according to DORAIDIP appointed 1 October 2010 to provide technical assistanceCapacity challenges for the DoH
o Absence of Infrastructure manager. The post is readvertisedo Absence of resident engineers. Recruitment is in process
13
•
15
CHALLENGES
The challenges cited above have an impact on the following:Spending
oSlow moving project affect spendingPerformance and monitoring
oPoor performance of contractors and consultantsoPoor workmanship
Co-ordinationoWeak contract management by principal agent
Cost escalationsoIrregular variation orders
14
16