50
IENG 578 Cost Estimation of a GE Blender using SEER‐DFM Team Leader: Lavanya Nyayapathi [email protected] Members: Sri Harsha Chintala [email protected] Vimala Goli [email protected] Bjorn Olof Jonsson [email protected] Navya Reddy Lenkala [email protected] 11/17/2008 Submitted to Dr. Robert Creese Department of Industrial and Management Systems Engineering West Virginia University, Morgantown

seer dfm student paper

  • Upload
    lelien

  • View
    220

  • Download
    0

Embed Size (px)

Citation preview

  

IENG 578

Cost Estimation of a GE Blender using SEER‐DFM 

Team Leader:  Lavanya Nyayapathi      [email protected] Members:        Sri Harsha Chintala        [email protected]                            Vimala Goli                     [email protected]                            Bjorn Olof Jonsson        [email protected]                            Navya Reddy Lenkala   [email protected]  

 

11/17/2008  

 

Submitted to 

Dr. Robert Creese 

   

Department of Industrial  and Management Systems Engineering    West Virginia University, Morgantown 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 2  

Abstract Seer‐DFM software was used to find the basic cost estimate of a GE blender.   A bottom’s up approach was used to breakdown the work elements into sub assemblies and hierarchy of modules. The software demands appropriate values for parameters like tool amortization, material yield, operators’ experience, etc.  The risk analysis is performed by changing the production quantities on the average system cost. 

The procedure adopted here  involves breaking down the blender  into 2 subassemblies. The weight of every element in the sub‐assembly was determined and its volume was estimated. This data is entered into the software to develop the estimate of costs. Once the data has been validated, the software will give  a basic  as well  as detailed  estimate of  the  cost of  the  blender  and of  all  its  elements.  The  risk analysis,  cost  analysis, production  cost,  labor  cost  for  individual  elements  and  sub  assemblies  is  also generated by the software. 

The cost that SEER‐DFM estimates for the blender is $11.34 for 50,000 production units. This cost varies as the production units’ change. It also varies with the country of manufacturing.  The GE‐Blender was made in China and hence the estimate in this report is made with China as the country of production and hence its labor rate at $16/hour.  

The conclusions and risk analysis gives a detailed estimate of the price of the blender at different production quantities in both USA and China.  

 

 

 

 

 

 

 

 

 

 

    

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 3  

Table of Contents Abstract ..................................................................................................................................................... 1 

1 Introduction ........................................................................................................................................... 4 

1.1 What is SEER‐DFM: ......................................................................................................................... 4 

1.2 Problem description: ....................................................................................................................... 4 

2 Procedure ............................................................................................................................................... 5 

2.1 General factors ................................................................................................................................ 7 

2.2 Model Hierarchy ............................................................................................................................. 7 

2.3 Lid .................................................................................................................................................... 8 

2.4 Ingredient cap ............................................................................................................................... 10 

2.5 Jar .................................................................................................................................................. 11 

2.6 Pitcher base ................................................................................................................................... 12 

2.7 Jar bottom/Blade holder ............................................................................................................... 13 

2.8 Cog Wheel ..................................................................................................................................... 14 

2.9 Blade ............................................................................................................................................. 15 

2.10 Body ............................................................................................................................................ 16 

2.11 Motor .......................................................................................................................................... 17 

2.12 User Interface Panel .................................................................................................................... 18 

2.13 Motor Control Board ................................................................................................................... 19 

3 Results .................................................................................................................................................. 21 

3.1 Graphs and Charts ......................................................................................................................... 22 

4 Conclusions and Risk Analysis .............................................................................................................. 25 

 

 

 

 

 

 

    

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 4  

1 Introduction This is a project trying to estimate the cost of an electrical blender using SEER‐DFM 

1.1 What is SEER­DFM: SEER  stands  for  System  Evaluation  and  Estimation  of  Resources.  It  is  a  family  of  programs  for  cost estimation made by Galorath, a software company. The family consists of: 

• SEER for Software 

• SEER for Hardware, Electronics & Systems 

• SEER for Manufacturing  

• SEER for IT 

This  project  has  used  SEER‐DFM which  has  been  replaced  by  SEER  for Manufacturing.  SEER‐DFM  is focused on giving the user tools to evaluate different manufacturing options and trough that analyze the best option. By modeling thru SEER‐DFM the user can evaluate more options at a much lower price than through test production series.  

1.2 Problem description: This project aims to see how efficient SEER‐DFM is as an estimation tool for a commercial product. It is also an exercise in the use of a commercial cost estimation tool. 

 

Figure 1  GE Blender Model 169169 

• 14-speed blender • 600-watts • 48-oz jar • Pulse feature • Electric control panel • Jar and blade assembly are

dishwasher-safe

SEER‐DF 

2 ProceThe produwith a spimeans thablender w

Figure 2 Sch

The  prodquantity o50,000  unfactors fo

Each  comapproxim

Table 1 Com

S.No   1 2 3 4 5 6 7 8 9 10 

11 

M Model for 

edure uct chosen fonning blade mat the producwas dissemble

hematic estimat

uction  quantof every elemnits of  blendr the part ass

mponent  waating them as

mponent Weight

Compo Li

IngredieJa

PitcheJar bottom/b

Cog wBla

User intControl

Bo

Mo

a GE‐BLEND

or this projectmade to spin ct is electro‐med into compo

ting breakdown 

tity  of  the  bment in the asers.    Every  esembly contri

as  weighed s made from 

t and Volume m

onent  d ent cap ar r base blade holder  wheel de terface l board dy 

tor 

DER                  

t is a GE 14‐spby an electric

mechanic andonents in ord

structure 

lender  assemssembly is 50element was ibution were 

and  measurthe basic sha

measurements 

weight lb 0.29563990.04894263.43612480.09942850.09832620.00705480.0546746

0.1250.068

0.1764

1.875

                       

peed Blender c motor. The  incorporatesder to estimat

mbly  is  consi,000 units as considered  tgiven.  

red  for  dimapes. 

 

volume cubic feet0.00338260.00073270.01100830.00151680.00110929.913E‐050.00010953.39E‐054.238E‐050.0026906

0.074

                        

sold by Wal‐motor is cons several mante the cost.  A

dered  to  be every part isto  be  the  pa

ensions.  The

                       

Mart. It is bastrolled by a cnufacturing prAs shown in F

50,000  units required forart  of  assemb

e  volume  w

                  Pag

sically a largecircuit board. rocesses. Theigure 2. 

s.  The  produr the productibly  and  henc

was  estimate

ge 5 

e jar This e 

 

uction ion of ce  the 

ed  by 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 6  

 

Figure 3 Motor 

 

 

Figure 4 Lid, ingredient cap, pitcher base, Jar (Clockwise from left top) 

 

 Figure 5 Blade holder & blade, cog wheel, motor control board, user interface panel (Clockwise from left top) 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 7  

2.1 General factors • Production quantity:       50,000 units 

• All labor rates, including overhead:   $16/hour 

• Quantity per next higher assembly:   1 

• Production Experience varies depending on the type of the product and manufacturing process used. 

• Used part assembly contribution for each element. Method of assembly chosen as closest type. 

• Functional tests for moving and electrical parts when assembled. 

2.2 Model Hierarchy The work elements are divided  into 2 sub assemblies, the Jar Assembly and the Motor Assembly.   The Work Elements section  is work region within the window frame, which allows the user to describe the structure  of  the  hardware  or  the  Estimating  Breakdown  Structure.  The  work  element  structure  is described in Figure 6.  

 

Figure 6 Model Hierarchy 

 

 

 

 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 8  

 

 

 

2.3 Lid The  lid  was  identified  as  a  first  element  under  the  jar  assembly.  The  process  type  is Fold/Cast/Forge/Powder Metals.  The manufacturing  process  considered  in  this  case  is  the  injection molding. The material of  the casing was determined as Polyvinyl Chloride. The  finished weight of  the component is 0.29 pounds. The parameter inputs are as follows. 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 9  

 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 10  

2.4 Ingredient cap The  ingredient cap  is a part of  the  jar assembly. The process  type  is Fold/Cast/Forge/Powder Metals.  The material of the casing was determined as Acrylic. This part is considered to be manufactured by the injection molding process. The most likely number of cavities for the production quantity of 50,000 units was considered to be 10. The finished weight of the component is 0.048 pounds. The parameter inputs are as follows. 

 

   

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 11  

2.5 Jar The jar is chosen to be added as a purchased part, this because SEER‐DFM is not supporting calculations for glass manufacturing. An assumption of the price was made using similar sized  jars available on the consumer market. The assumed price of the jar  is $2 since similar sized glass jars  in retail are available from $3. 

 

   

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 12  

2.6 Pitcher base The  Pitcher  base  is  made  of  ABS  ‐  Acrylonitrile  Butadiene  Styrene  and  is  identified  as Fold/Cast/Forge/Powder Metals  process  type.    An  injection molding  process was  considered  for  the manufacturing process. The most  likely number of cavities  for  the production quantity of 50000 units was considered to be 10. The finished weight of the pitcher base was determined as 0.99 pounds. 

 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 13  

2.7 Jar bottom/Blade holder The  jar bottom or  the blade holder  is made of polyetheylene  and  is manufactured with  an  injection molding process. The finished weight of the component is 0.125 pounds.  

   

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 14  

2.8 Cog Wheel The cog wheel  is made of nylon and the manufacturing process  is  identified as  injection molding. The finished weight of the component is 0.006875 pounds.  

 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 15  

2.9 Blade The blade set  is  introduced as a machining element. The radial mill, end mill and drilling process along with angled faces were considered in the machining process. The material of the blade is steel stainless steel. The finished weight of the product is 0.05 pounds.  

 

 

 

   

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 16  

2.10 Body                          The body  is determined as ABS and  its weight  is 1.25 pounds. The manufacturing process  is  injection molding. The body also includes the buttons and the base of the blender.  

 

 

   

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 17  

2.11 Motor The blender motor drives the blade. This  is  identified as a purchased part. An assumption of the price was made using similar sized motors available on the consumer market. The assumed price of the motor is $3. 

 

  

 

 

 

 

 

 

 

 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 18  

2.12 User Interface Panel To supply power and converting AC voltage to DC there is an electronic circuit (PC Board) incorporated in the assembly. The  length and width of the board  is determined as 3 and 4  inches respectively. The material  for  this  is  determined  as  Alumina‐Thin  film.    A Go/No Go  test  is  used  for  testing  the  user interface panel.  

 

 

 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 19  

2.13 Motor Control Board Motor control board has 20 odd components on it along with the resistors and capacitors. The material for this is determined to be Alumna‐Thin film. The length and width of the motor control board is 3 and 5 inches respectively. A Go/No Go test is used to test its functionality.  

 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 20  

 

 

 

 

   

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 21  

3 Results With  the blender produced  in China  and  an  assumed quantity of 50,000 units we  get  a unit  cost of $11.34. It represents the cost of designing, developing and manufacturing the blender in lots of 50,000 units. The detailed analysis of the blender cost is given in the below table.  

 

Figure 7 Detailed Analyses 

The detailed analyses of costs of blender at different production units can be found in the Appendix V. 

The total cost of every work element for 50,000 units produced in China is as follows. The quick estimate of every work element can be found in Appendix IV. 

Table 2 Total cost for 50,000 units. 

Total Cost for 50000 units 

Part  Cost ($) 

Blender  566,947.03 

Jar  130,531.47 

Lid  29,127.91 

Pitcher Blade  30,254.34 

Blade  16,461.32 

Cog Wheel  27,871.54 

Jar Bottom  32,352.90 

Ingredient Cap  27,402.98 

Body  106,267.01 

Motor Control Board  4,140.27 

Motor   151,184.64 

User Interface Panel  11,352.65 

SEER‐DF 

3.1 Grap

 Cost AlloThe SEER‐The Cost A

 

Figure 8 Cos

3.1.1 ProbThe chart 

risk analy

the  cost 

probabilit

value. Pro

Probabilit

M Model for 

hs and Char

ocation Chart‐DFM softwaAllocation Ch

st Allocation Ch

bability base depicts the p

sis for a prod

is  in  the  giv

ty  value of  sa

obability plot

ty risk chart o

a GE‐BLEND

rts 

t re gives the art for individ

art of 50,000 un

ed Risk Chartprobability of

duction quant

en  range  as 

ay 20% mean

ts  for each co

of individual e

DER                  

cost allocatiodual compon

nits‐China 

ts f change in pr

tity of 50,000

opposed  to 

ns  that  there

omponent ca

elements can 

                       

on graph for ents can be fo

rice of the Ble

0 units. It can 

the  90%  pro

e  is  a 80%  ch

an be obtaine

be seen in th

                        

50,000 units ound in the A

 

ender. The ch

be seen that

obability whe

hance of exce

ed by  running

he Appendix I

                       

of blender pAppendix I. 

art below sho

t for a probab

ere  cost  see

eeding  the  c

g  the SEER‐D

I.  

                  Pag

produced  in C

oes the proba

bility value of

ms  to  increa

orresponding

DFM software

ge 22 

China. 

ability 

f 10%, 

ase.  A 

g  cost 

e. The 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 23  

 

Figure 9 Probability Risk Chart 

3.1.2 Cost Sensitivity Chart 

Based on the production experience the cost for the individual component varies. As can be seen for the 

blade from the below chart, the cost varies as follows 

Table 3Cost Sensitivity of Blade 

Blade 

Range  Lowest  Likely  Mean  Highest 

Cost in Dollars  0.275  0.3  0.315  0.375 

 

 

Figure 10 Production Experience VS Cost 

SEER‐DF 

3.1.3 Cost

From the with the Rgreatest c

Figure 11 Co

The chart

From the 

item is the

Figure 12 Co

M Model for 

t Distribution

cost distribuRollup cost cocost items are

ost Distribution 

t below gives

chart the mo

e blade contr

omponent Cost 

a GE‐BLEND

 Chart 

tion chart of ontribution ane the purchas

Summary 

s  the contribu

ost expensive 

ributing only 0

Distribution 

DER                  

the blender nd the projecsed parts at $

ution of  the 

item is the E

0% to the tot

                       

the unit costct cost contrib2 for the jar a

individual co

Electric Motor

tal cost of the

                        

t of every wobution. As canand $3 for the

mponents  to

r (27% of the 

e blender. 

                       

rk element cn be seen in fe motor. 

 

o  the  total co

total cost). T

                  Pag

an be found figure 11 the s

ost of  the Ble

The least expe

 

ge 24 

along single 

ender. 

ensive 

 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 25  

4 Conclusions and Risk Analysis The cost  is dependent on  the production quantity and  the  labor  rate,  therefore estimates have been done for different amounts of units produced and at different labor rates. Calculations have been done for both China,  labor  rate $16/hour, and USA,  labor  rate $80/hour at different production quantities. The results are as follows. The detailed cost estimate for different production quantities is found in the Appendix III.  

Table 4 List of unit cost with production quantity and labor rate. 

Production Quantity 

Unit cost ($/unit) 

Country 

USA  CHINA 

10,000  30.23  25.28 

25,000  19.71  14.82 

50,000  16.22  11.34 

75,000  15.05  10.18 

100,000  14.47  9.6  

Table 5 Unit cost of every element with the units of production 

Components Units of Production  

10000  25,000  50,000  75,000  100,000 

Jar  2.61  2.61  2.61  2.61  2.61 

Lid  2.72  1.12  0.58  0.4  0.32 

Pitcher Blade  2.72  1.13  0.61  0.43  0.34 

Blade  0.35  0.33  0.33  0.33  0.33 

Cog Wheel  2.66  1.08  0.56  0.38  0.29 

Jar Bottom  2.81  1.19  0.65  0.47  0.38 

Ingredient Cap  2.65  1.07  0.55  0.37  0.28 

Body  4.88  2.81  2.13  1.9  1.78 

Motor Control Board  0.31  0.14  0.08  0.06  0.05 

Motor   3.02  3.02  3.02  3.02  3.02 

User Interface Panel  0.55  0.31  0.23  0.02  0.19 

Blender  25.28  14.82  11.34  10.18  9.6  

With a production quantity of 50,000 units SEER‐DFM estimates the unit cost of the blender to $11.34. This can be compared to the price of the blender at Wal‐Mart which  is $29.88.  If the assumption that the consumer price is roughly a third of the production cost is made the blenders actual production cost is assumed to be $9.96. This gives a difference between the estimate and the “real” value to be $1.38 or the estimate to be 113 % of the cost. 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 26  

The  reasons  for  the assumption of a market price  three  times  the production are many. The product needs packaging, shipping and handling  to  reach  the store. Every step  in  the hierarchy of distribution also involves and adds costs to the product. It is not only the store that shares the difference between production cost and consumer price. In this case, the blender  is bought at Wal‐Mart which are famous for low overheads and though negotiations with suppliers. This could mean that we are underestimating the production cost with a third of the consumer price. The production cost could as well be a bit higher. 

There are several ways to explain this difference, and it is due to many reasons. The following are some of many: 

• Real production cost unknown 

• Production quantity unknown 

• Production methods etc. unknown 

• Inputs in SEER‐DFM estimations 

• SEER as a model not perfect 

One  thing  that  can be  seen  is how heavy  the price  relies on  the production quantity.  If  the guessed “real” production cost is used as a target it can be seen that as you move towards more units produced the unit cost decreases and actually fall below $9.96. This can be shown in the following table. 

Table 6 Unit cost at different production quantities for China. 

Production Quantity Unit cost ($/unit) 

10,000  25.28 

25,000  14.82 

50,000  11.34 

75,000  10.18 

100,000  9.6  The following graph depicts the same information, but also with the cost for the higher labor rate, USA.  

SEER‐DF 

Figure 6 Un

As  can  beinvestmenthe same part of th

One way t

Table 7 Cos

  

Par

Blen

Li

Pitche

Bla

Cog W

Jar Bo

Ingredie

Bo

Motor Con

User Interf

Ja

Mo This  tablefactors cothe  largesincludes t

If the conare the ja

M Model for 

it cost plotted a

e  seen  the  unts required degree of aue unit cost pe

to see how th

ts of 50,000 uni

rts 

nder 

r Base 

ade 

Wheel 

ottom 

ent Cap 

dy 

ntrol Board 

face Panel 

ar 

otor 

e  shows  howontribution tost part of thethe labor and 

tribution of tr, motor, and

a GE‐BLEND

against producti

unit  cost  dropare more or utomation is aer unit since m

he costs are d

ts produced in C

  

Labor cost 

1.16 

0.01 

0.05 

0.28 

0.03 

0.04 

0.01 

0.05 

0.02 

0.02 

0.61 

0.09 

w  the  costs  ao the total cose material cotooling costs

the different d the body i.e

DER                  

ion quantity. 

ps with  an  inless the samassumed. So,more units ar

distributed is 

China for the dif

C

Material cost 6.7 

0.04 

0.03 

0.04 

0.002688 

0.06 

0.01 

1.39 

0.01 

0.13 

are  distributest of the prodst and of thes for the subc

parts are con. the main pla

                       

ncreased  proe no matter  the molds are sharing the

to look at the

fferent part divi

Cost per Part

Tooling cost 3.48 

0.53 

0.53 

0.01 

0.52 

0.54 

0.53 

0.69 

0.06 

0.08 

ed  between duct. As can be total cost aontractor del

nsidered it is astic casing. 

                        

oduction  quaof the amounnd other fixee investments

e costs for the

ided in to labor,

Labor cost % 

10.23 

0.09 

0.44 

2.47 

0.26 

0.35 

0.09 

0.44 

0.18 

0.18 

5.38 

0.79 

the  differentbe seen the ps well. This  islivering the p

seen that the

                       

 

ntity.  This  is nt of units prd investments. 

e consisting u

, material and to

  

Material Cost % 59.08 

0.35 

0.26 

0.35 

0.02 

0.53 

0.09 

12.26 

0.09 

1.15 

17.64 

26.46 

t  parts.  The purchased pars expected siarts. 

e three major

                  Pag

natural  sincroduced as lots become a 

units. 

ooling costs. 

  

Tooling C% 

30.69

4.67

4.67

0.09

4.59

4.76

4.67

6.08

0.53

0.71

0.00

0.00

percentage  irts contributeince that cos

r cost compo

ge 27 

ce  the ong as lesser 

Cost 

is  the e with t also 

nents 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 28  

Going back  to Table 4  the unit cost  is more  in USA compared  to China as  the  labor cost are higher  in USA. This  leads to a higher cost  for the product  if  it  is made  in the USA.  It  is  likely  that there  is more automation involved in USA production plants than in China which might contribute to a lower cost on high volume products i.e. if the product is to be produced in USA a higher automation level is required to get a competitive production cost. 

   

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 29  

APPENDIX I 

 

Figure 2 Blender Cost Allocation 

 

Figure 3 Jar Assembly Cost Allocation 

 

Figure 4 Jar Cost Allocation 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 30  

 

Figure 5 Lid Cost Allocation 

 

Figure 6 Pitcher Base Cost Allocation 

 

Figure 7 Blade Cost Allocation 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 31  

 

Figure 8 Cog Wheel Cost Allocation 

 

Figure 8 Jar Bottom Cost Allocation 

 

Figure 9 Ingredient Cap Cost Allocation 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 32  

 

Figure 10 Motor Assembly Cost Allocation 

 

Figure 10 Body Cost Allocation 

 

Figure 12 Motor Control Board Cost Allocation 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 33  

 

Figure 13 Motor Cost Allocation 

 

Figure 14 User Interface Panel Cost Allocation 

   

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 34  

APPENDIX II Figure 11 Cost Risk Chart of Jar 

 

Figure 12Cost Risk Chart of Lid 

 

Figure 13Cost Risk Chart of Pitcher Base 

 

Figure 14Cost Risk chart of Blade 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 35  

 

Figure 15 Cost Risk chart of Cog Wheel 

 

 

Figure 16 Cost Risk chart of Jar Bottom 

 

Figure 17  Cost Risk chart of Ingredient Cap 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 36  

 

Figure 18Cost Risk chart of  Body 

 

Figure 19Cost Risk chart of Motor Control Board 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 37  

 

Figure 20 User Interface panel 

 

Figure 21Cost Risk chart of Motor 

 

 

 

   

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 38  

 

 

 

 

 

 

 

 

 

 

APPENDIX III 

   

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 39  

 

 

 

Figure 1 Cost of 10,000 units China 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 40  

 

 Figure 2 Cost of 25,000 units China 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 41  

 

 Figure 3 Cost of 50,000 units China 

   

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 42  

 

 Figure4 Cost of 75,000 units China 

   

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 43  

 

 Figure 5 Cost of 100,000 units China 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 44  

 

 

 

APPENDIX IV 

 

Figure 22 GE Blender Quick Estimate 

 

Figure 23 Jar Assembly Quick Estimate 

 

Figure 24 Jar Quick Estimate 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 45  

 

Figure 25 Lid Quick Estimate 

 

Figure 26 Pitcher Base Quick Estimate 

 

Figure 27 Blade Quick Estimate 

 

Figure 28 Cog Wheel Quick Estimate 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 46  

 

Figure 29 Jar Bottom Quick Estimate 

 

Figure 30 Ingredient Cap Quick Estimate 

 

Figure 31 Motor Assembly Quick Estimate 

 

Figure 32 Body Quick Estimate 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 47  

 

Figure 33 Motor Control Board Quick Estimate 

 

Figure 34 Motor Quick Estimate 

 

Figure 35 User Interface Board Quick Estimate 

   

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 48  

APPENDIX V 

Detailed Analysis for 10,000 units manufactured in US 

 

Detailed Analysis for 25,000 units manufactured in US 

 

   

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 49  

Detailed Analysis for 50,000 units manufactured in US 

 

Detailed Analysis for 75,000 units manufactured in US 

 

 

Detailed Analysis for 100,000 units manufactured in US 

SEER‐DFM Model for a GE‐BLENDER                                                                                                          Page 50