M. Gilchriese Sector Status Module Loading Task Force Meeting November 25, 2004

Sector Status

Embed Size (px)

DESCRIPTION

Sector Status. Module Loading Task Force Meeting November 25, 2004. Sector Summary. 9005 – FE-I2 modules Used for qualification and extensively tested (system test) 9000 – FE-I3 bad modules Used for final tune-up of assembly process Assembly completed. Survey completed - OK - PowerPoint PPT Presentation

Citation preview

Page 1: Sector Status

M. Gilchriese

Sector Status

Module Loading Task Force Meeting

November 25, 2004

Page 2: Sector Status

M. Gilchriese2

Sector Summary• 9005 – FE-I2 modules

– Used for qualification and extensively tested (system test)• 9000 – FE-I3 bad modules

– Used for final tune-up of assembly process– Assembly completed. Survey completed - OK– Preliminary( room T) electrical test done - OK– Thermal imaging, thermal cycling and burn-in to be done– Back in system test for now

• 9006 – 1st production unit– Assembly and survey completed on September 24. OK. Thermal OK.– All testing complete. OK.

• 9007 – Assembly and survey completed September 30. OK. Thermal OK. – Need to redo digital test cold with improved grounding, otherwise done.

• 9008– Six modules loaded. Survey OK. Testing to start next week

• 9009– Assembly and survey completed on October 19. OK– Not yet tested.

• 9010– Four modules loaded, OK so far

Page 3: Sector Status

M. Gilchriese3

Status

• Qualification of second assembly station nearly complete. Survey comparisons with other station done, agreement within few microns.

• Expect to start using second station next week for 9011.• Slowly ramp up assembly rate. Limited by manpower and soon

module delivery rate. Can add manpower if module rate improves.

• Testing fully operational but keep making small improvements.• XTALK cut in discussion with Module Analysis czar• Will shortly start planning to replicate test system to allow

faster rate• Expect to have at least one disk worth, eight sectors, assembled

before Xmas break.

Page 4: Sector Status

M. Gilchriese4

Planning

0

50

100

150

200

250

300

350

400

450

6-Oct-03 14-Jan-04 23-Apr-04 1-Aug-04 9-Nov-04 17-Feb-05 28-May-05 5-Sep-05 14-Dec-05

Date

Modules

Bare Modules Planned

Bare Modules Actual

Tested Modules Planned

Tested Modules Actual

Sector Assembled Planned

Sector Assembled Actual

Sector Tested Planned

Sector Tested Actual

Disks Planned

Disks Actual