Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
EEEIIIAAA///EEEMMMPPP RRReeepppooorrrttt
“““RRReeevvviiisssiiiooonnn &&& Expansion of GroupHousing Project”””
At
Sector-70, Village- mujheriFaridabad, Haryana.
For
M/s Pivotal Infrastructure Pvt. Ltd.
Prepared ByGRASS ROOTS RESEARCH & CREATION INDIA (P) LTD.
(An ISO 9001:2008 Certified Co.: Accredited by QCI / NABET: Approved by MoEF,GoI)
F-374-375, Sector-63, Noida, U.P.Ph.: 0120- 4044630, Telefax: 0120- 2406519
Email: [email protected], [email protected]: http://www.grc-india.com
GRC INDIA TRAINING & ANALYTICAL LABORATORY(Recognized by NABL & MoEF, GoI)
A unit of GRC India
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 1
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 1
CHAPTER-1
INTRODUCTION
1.1 PREAMBLE
Early identification and characterization of critical environmental impacts allow the public
and the government to form a view about the environmental acceptability of a developmental
project and what conditions should apply to mitigate or reduce those risks and impacts.
EIA is a technical exercise, to establish baseline environmental conditions to predict
environmental impact assess their significance and provide recommendations for their
mitigation. The impact assessment covers both construction and operation phase of the
development. The report covers areas such as noise, air quality, ecology, water quality &
hydrology, local architecture, landscape & visual character, sustainability and socio-
economic. The report describes how the project has been improved through the EIA process.
This report has been prepared as per the EIA Notification, 2006 & amendments, EIA
Guidance Manual for Building Construction Township and Area Development projects as
guiding documents.
1.2 GENERAL INFORMATION ON PROJECT
“Royal Heritage” Revision & Expansion of Group Housing Project is to be developed by M/s
Pivotal Infrastructure Pvt. Ltd. The project is located at Village Mujheri, Sector 70,
Faridabad, Haryana has already received Environmental clearance from MoEF (Ref No.21-
1079/2007 -1A 111 Dated : 27 May 2008) for the site admeasuring 82,232.12 sq.m (20.3199
acres) & built up area 1,44,351.0 sq.m EC letter has been attached as Annexure I and the
satisfactory repot from the MoEF is attached as Annexure II. The project though under
development has undergone an increment for better efficiency reason, increased built up area
to 1,79,297.91 sq.m which seeks consideration for EC. The Project is designed as a self-
sufficient residential establishment, wherein infrastructure facilities such as road network,
water supply, electric supply, emergency power supply, and communication facilities are
proposed. Further, the project proponent has made provisions for waste collection and
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 1
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 2
disposal and Sullage treatment to ensure that the project is environment friendly. Social
facilities as Community, commercial area and schools are also planned to provide the
residents with a good quality of life. The project proponent also proposes to arrange for
safety, maintenance and security of the residents.
1.3 ENVIRONMENTAL CLEARANCE PROCESS
As per EIA Notification, 2006 & its amendments, all building construction and area
development Projects covering an area of 50 ha and/ or built up area greater than 1, 50,000 sq
m. are designated as 8(b) projects and are required to obtain prior environmental clearance
from respective State Environmental Impact Assessment Authority (SEIAA). The application
for environmental clearance shall comprise submission of Form 1, Form 1A, and Conceptual
Plan along with ToR. The EIA/EMP report shall be based on ToR conveyed to the applicants
by SEAC. The following appraisal of the project to the satisfaction of the State Expert
Appraisal Committee (SEAC), environmental clearance shall be granted by SEIAA (State
Environment Impact Assessment Authority), Haryana.
Since, the total area of site for which EC is required is estimated to be 82,232.12 m2(20.3199
acres) and built up area 1,79,297.91 m2, the project attracts the provisions of the EIA
Notification, 2006 and requires EIA/EMP study to obtain Environmental Clearance from the
SEIAA, Haryana.
As per the requirement of EIA notification, M/s Pivotal Infrastructure Pvt. Ltd. had submitted
the application to State Level Environment Impact Assessment Authority (SEIAA) Haryana
and the ToR was approved from State Level Expert Appraisal Committee (SEAC) Haryana in
79th
meeting dated 9.4.13 vide Letter No. HR/SEAC/426/74 dated 16.4.13 for carrying out the
Environmental Impact Assessment study copy of the same is enclosed as Annexure III. The
detail environment data has been done at the study area including the project site during the
period from March 2013-May 2013 (pre monsoon period of the year 2013) based on ToR
approved by SEAC. The Compliance status to the ToR is enclosed as Annexure VIII with
EIA/EMP Report. The Undertaking to the effect that the prescribed ToR and data/information
in EIA/EMP report is factually correct, given in Annexure IV. The present EIA/EMP Report
has been prepared as per approved ToR by SEAC, Haryana.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 1
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 3
1.4 VALIDITY OF ENVIRONMENTAL CLEARANCE
As per the provisions of the EIA Notification, 2006 and its amendments, the prior
environmental clearance granted is valid for a period of five years. This may be
extended by a maximum of five years, provided an application is made to the
regulatory authority within the validity period with updated Form 1, Form 1A,
Conceptual Plan and Environmental Impact Assessment Report (EIA/EMP Report)
1.5 POST ENVIRONMENTAL CLEARANCE MONITORING
For Category B Project irrespective of its clearance from SEIAA. The project proponent
shall prominently advertise in the newspaper indicating that the project had been
accorded EC and the details of MoEF website where it is displayed.
It shall be mandatory for the project management to submit half-yearly compliance
report in respect of the stipulated prior environmental clearance terms and condition in
hard and soft copies to the regulatory authorities concerned on 1st June and 1
st December
of each calendar year.
All such compliance report submitted by the project management shall be public
documents. Copies of the same shall be given to any person on application to the
concerned regulatory authority.
1.6 TRANSFERABILITY OF ENVIRONMENTAL CLEARANCE
A prior environmental clearance granted for a specific project or activity to an applicant
may be transferred during its validity to another legal person entitled to undertake the
project or activity on application by the transferor or the transferee with a written “no
objection” by the transferor, to, and by the regulatory authority concerned, on the same
terms and conditions under which the prior environmental clearance was initially
granted, and for the same validity period.
1.7 GENERIC STRUCTURE OF ENVIRONMENT IMPACT ASSESSMENT
The environmental impact assessment has been carried out to assess the impact of the
project on various environmental components. The methodologies and findings of the
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 1
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 4
study are detailed in the EIA/ EMP Report along with other relevant information under
the different chapter headings as under:
Introduction- provides background information about the project and the developers
along with the legal environmental requirements of the project. The scope and EIA
methodology adopted in preparation of EIA report have also been described in this
chapter.
Project Description–briefly discusses the project features while elaborating on
components bearing environmental consequences.
Description of the Environment – discusses the environmental setting of the project
area based on primary and secondary data collection.
Anticipated Environmental Impacts & Mitigation Measures – predicts the
environmental impacts of the various components of the project during construction and
operation phases to highlight concern areas requiring mitigation measures. Accordingly,
it also suggests controls and mitigation measures to offset/ minimize the adverse impact
while optimizing the positive benefits from the project.
Analysis of Alternatives (Technology and site) – explores the alternative sites and
plans that have been considered for the project and evaluates the different scenarios in
the environmental context.
Environmental Monitoring Programme – outlines a monitoring programme for the
different environmental components during the construction and operation phase for
evaluation of the environmental status of the area due to the project proponent.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 1
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 5
Additional Studies – discusses any study that has been carried out for the purpose of
better understanding of the environmental impacts of the project. It also highlights any
pertinent findings from the study that will aid decision-making.
Project Benefits – brings out the positive impacts from the project.
Environmental Management Plan – organizes the suggested mitigation measures to
aid implementation through formulation of performance indicators, reporting structure
and pronounced implementation periods.
Summary & Conclusion – summaries the important report findings and concludes on
the environmental sustainability of the project.
Disclosure of Consultants engaged – gives the names of the technical team involved in
the report preparation along with accreditation of consultant from the quality council of
India.
1.8 PROJECT PROPONENT
The M/s Pivotal Infrastructure Pvt. Ltd. group is a major player of the real estate
Industry. The Group follows the basic values of professional services by providing
specified quality with rich/ value based specification, planned delivery coupled with
customer care and comfort level. Innovative design of the project not only provides the
highest quality of life to its residents, but also encourages a society that is both sensitive
and responsible towards the environment.
The contact details for Pivotal Infrastructure Pvt. Ltd. are as follows:
1.8.1 Name and the Contact address
Registered Office Address
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 1
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 6
Naresh Kr Chawla
DGM (Finance)
M/s Pivotal Infrastructure Pvt. Ltd
Pivotal Infrastructure Pvt Ltd.
309, 3rd
Floor, JMD Pacific Square
Sector 15, Part II,
Gurgaon, Haryana
1.9 BRIEF DESCRIPTION OF PROJECT
1.9.1 Land Description
The project is to be developed over an area of 82,232.12 m2
(20.3199 Acres) and the
total Built up Area is 1, 79,297.91 m2
along with other necessary facilities to support a
population of 9,853 persons.
There is neither any litigation (s) pending against the project and/or any directions or
order passed by any court of law/any statutory authority against the project that can be
detailed out. All reputed and accredited consultants are involved in the project providing
their inputs and expertise altogether required for a proper and authentic Environmental
Impact Assessment study.
Land has been allotted for Group Housing Colony project purpose under License No. 33
of 2010 dated 20.4.10 and License No 78 of 2009 dated 3.12.09 issued by Town and
Country Planning Department, Haryana. The license is enclosed as Annexure V and site
comes under Residential area as per Faridabad Master plan 2021.
Table 1.1 Basic Project details
S. No. Item Details
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 1
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 7
S. No. Item Details
1 Name of the project Revision & Expansion of Group Housing Colony
2. Location Village Mujheri, Sector 70, Faridabad, Haryana
3. Plot/survey/Khasra no. The plot khasra no. are given in License No. 78 of 2009 and
33 of 2010 is enclosed refer Annexure-V.
4. Village Mujheri
5. Tehsil Ballabgarh
6. District Faridabad
Site Description
“Royal Heritage” Revision & Expansion of Group Housing Project is located at Village
Mujheri, Sector 70, Faridabad, Haryana. The project site is well connected through sector
roads. The Nearest Highway is NH – 2 which is 3.5 km; W from project site. The nearest
railway station is Ballabgarh Railway Station, about 3.93 km; WNW from the project site.
The nearest airport is Safdarjung Airport, New Delhi; about 30.77 km, NNW from the project
site.
Need For the Project
The project activities must co-exist in harmony with its surrounding environment, to reduce
the environmental impact, which is likely to arise during various project activities. To
safeguard the environment from adverse effects of developmental activities, the MoEF has
issued some regulations. As per the notification dated 14.09.06 of MoEF, GoI; Environmental
Clearance is mandatory for any construction projects with built-up area of more than 20,000
Sq m.
1.10 DESCRIPTION OF REGULATIONS AND STANDARDS
a) The Urban Area Act, 1975 and Rules, 1976
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 1
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 8
b) Controlled area Act 1963 and Rules, 1965
c) The Water (Prevention and Control of Pollution) Act, 1974
d) The Water (Prevention and Control of Pollution) Cess Act, 1977
e) Indian Forest Act, 1980
f) The Air (Prevention and Control of Pollution) Act, 1981
g) The Municipal Solid Wastes (Management and Handling) Rules, 2000
h) NBC, 2005
i) Hazardous Wastes (Management, Handling & Trans boundary Movement) Rules,
2008 amended in 2010
j) E-waste (Management & Handling) Rules, 2011
k) EIA notification, 2006 and its amendments
l) No Objection Certificate from HSPCB
1.11 APPLICABLE LEGAL REQUIREMENTS
Under the Environment Impact Assessment Notification, 2006 and its Amendments the
project will obtain environment clearance. The project shall abide by all applicable provisions
of the Environment Protection Act, 1986 and rules formed there under. As per the Air
Pollution (Prevention and Control) Act, 1981, Water Pollution (Prevention and Control) Act,
1974, and Hazardous Wastes (Management, and Handling) Rules, 1989 the project shall
obtain No Objection Certificate from Haryana Pollution Control Board and continue to obtain
yearly Consent for Operation from the same during the operation period.
1.12 NEED OF THE EIA STUDY
The project activities must co-exist in harmony with its surrounding environment to
reduce the environmental impacts, which is likely to arise during various project
activities. To safeguard the environment from adverse effects of developmental
activities, the MoEF has issued some regulations. As per the notification dated 14.09.06
of MoEF, GoI, and Environmental Clearance is mandatory for any construction projects
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 1
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 9
with built-up area of more than 20,000 Sq. m and Environment Impact Assessment
Report is mandatory for the project having built up area of more than 1, 50,000 Sqm.
Since the built-up area of the present project is 1, 79297.91 m2, hence, an Environment
Impact Assessment study is applicable.
The study would facilitate M/s Pivotal Infrastructure Pvt. Ltd. to obtain Environmental
Clearance (EC) from SEIAA, Haryana.
1.13 SCOPE OF STUDY
The scope of the study is:-
Compilation of baseline environmental and social scenario of the study area within
a radius of 2 km around the project site based on field studies covering one season
(except monsoon) i.e. 1st March -to 31
st May 2013 and secondary data collection;
Identification, prediction and evaluation of potential environmental impacts
expected during the construction and operation phase of the project;
Preparation of mitigation measures, Environmental Management Plan (EMP) and
Monitoring Programmed for implementation of suggested mitigation measures.
1.14 STUDY METHODOLOGY
The approach followed by Grass Roots Research & Creation India Pvt. Ltd. in conducting the
EIA study is according to the applicable regulatory framework. The main stages followed are
described below:
Stage -I
Review of design and operational information of the Project through Project
Report and identification of sources of major potential impacts.
Stage -II
An initial review of the project site and status of the physical environment
around the project site vicinity;
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 1
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 10
Understanding regarding project design and operation as well as macro
environmental aspects. The major issues needed to be addressed with due care
were identified and monitoring plan for the environmental baseline was
prepared;
Baseline environmental assessment was conducted within the study area of 10
km radius around the project site;
Intense monitoring and primary field data collection of environmental
components viz. Ambient Air Quality, Water (Ground water) use and its
Quality, Soil Quality, Noise Level, Traffic Volume etc.;
Survey study was carried out in the study area to assess the status of flora &
fauna and socio-economic profile of the study area; and
Information was also collected through Primary and Secondary sources like
Department of Census, Local and City Offices, National Institutions (Survey of
India, National Information Centre etc.), District Head Quarters and other
Government Offices etc. as well relevant Published Literatures.
Stage –III
Compilation of the Environmental Baseline of the Study Area.
Stage -IV
Assessment of Environmental Impacts by predicting the scale and extent of
changes associated with the project and their subsequent effects on the
environment against the environmental baseline condition, and evaluating the
significance of such impacts against accepted criteria.
Stage -V
Identification and preparation of measures to mitigate significant impacts
(evaluated from the impact prediction process) by proposing applicable
alternatives and control measures; and
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 1
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 11
Finally, development of appropriate Environmental Management and
Monitoring Plan to audit and ensure that the mitigation measures are in place
and effective.
1.15 EIA METHODOLOGY
The project may have impact on the physical, biological and socio economic attributes
of surrounding environment. In assessing the environmental impact, collection, collation
and interpretation of baseline data is of prime importance.
The objective of EIA is to predict and address potential environmental problems/
concerns at an early stage of project planning and design. EIA/ EMP assists in the
decision making process by identifying the key impacts/ issues as a results of the
activities and formulating mitigation measures, leading to an improvement in
environmental quality.
In order to achieve these objectives, the following procedures have been adopted for the
study:-
Collection, collation and analysis of regional and local environmental status for
various environmental attributes (like topography, geology, ambient air quality,
meteorology, water quality, noise level, soil characteristics and land use, transport,
settlement status and socio economic aspects etc.)
Identification of environmental impacts.
Evaluation of impacts leading to preparation of environmental management and
monitoring plan.
This report is based on scientific principles and professional judgment with resultant
subjective interpretation. Professional judgments expressed herein are based on the
available data and information.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 12
CHAPTER-2
PROJECT DESCRIPTION
2.1 INTRODUCTION
“Royal Heritage” Revision & Expansion of Group Housing Project is to be developed
by the M/s Pivotal Infrastructure Pvt Ltd., considering the nature of activities to be
conducted and the various aspects of the project to be developed, our efforts in the
approach for the planning of various systems, shall include. The main objectives of
the project are as under:
To enhance the surrounding with greenery, landscaping and recommended
aesthetics.
Basis of population has been considered as per NBC guidelines.
Domestic water required per head per day shall be as per national building code
2005, Table-1, part 9, P-19 plumbing services.
There shall be enough safe, clean and potable domestic water on a continuous
basis to every user.
Efficient disposal from toilets/Wet areas.
Reliable fire fighting system.
To plan the systems in such a way as to minimize the energy requirements.
To make the system efficient and cost effective.
To have proper operation and maintenance system, which could be controlled
centrally and efficiently
To create minimum nuisance and disturbance to the environment.
This chapter briefly discusses the project features while elaborating on component bearing
environmental consequences.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 13
2.2 PROJECT LOCATION AND SITE SURROUNDINGS
2.2.1 Location & Connectivity features
“Royal Heritage” Revision & Expansion of Group Housing Project is located at Village
Mujheri, Sector 70, Faridabad, Haryana. The Geographical Co-ordinates of the project site
are - 28°20'16"N 77°21'9"E.
Connectivity
Project site is well connected through sector roads. The Nearest Highway is NH – 2 which is
3.5 km; W from project site. The nearest railway station is Ballabgarh Railway Station, about
3.93 km; WNW from the project site. The nearest airport is Safdarjung Airport, New Delhi;
about 30.77 km, NNW from the project site
2.3 ESTIMATED PROJECT COST
The total estimated cost of the “Royal Heritage” Revision & Expansion of Group Housing
Project is Approx. Rs 314 crores which includes the cost of the land as well as the
developmental cost.
2.4 BRIEF PROJECT FEATURES
The Plot Area for “Royal Heritage” Revision & Expansion of Group Housing Project is
82,232.12 m2 (20.3199 acres) and the total Build up Area is 1, 79,297.91 m
2. The detailed
Area Statement is provided below in Table 2.1 under License No. 33 of 2010 dated 20.4.10
and License No 78 of 2009 dated 3.12.09 issued by Town and Country Planning Department,
Haryana.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 14
Table 1: Area Statement
Sr.
No.
Particulars Area in
accorded EC
(m2)
Constructed
Area (m2)
Revision &
Expansion in EC
accorded Area (m2)
Total (m2)
1. Total Plot Area 82,232.12
2. Net Plot area as per zoning
Plan
79,686.52
3. Permissible Ground
coverage (@35 % of the net
plot area)
27,890.28
4. Proposed Ground Coverage 10,300 10,300 + 3517.64 13,817.64
5. Permissible FAR (@ 175%
of net plot area)
1,39,451.42
6. Proposed FAR 1,43,841.00 67,163.99 - 4584.85 1,39,256.15
Residential FAR 1,40,300.00 67,163.99 - 3072.4 1,37,227.60
Commercial FAR 3,541 - - 3146.65 394.35
Community FAR - - + 1634.20 1,634.20
7. Utility area 510 - - 510 -
8. Stilt area 7,786.66 6,000.00 + 131.71 7,918.37
9. Basement area 32,563.67 24,000.00 - 2,875.67 29,688.00
10. Primary school plot area
- - + 4,255.14
4,255.14
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 15
Built up area + 1,214.56 1,214.56
11. Nursery school 1 plot area
Built up area
- - + 2,839.88
+ 658.08
2,839.88
658.08
12. Nursery school 2 plot area
Built up area
- - + 1,418.13
+ 562.75
1,418.13
562.75
13. Built Up Area 1,44,351.00* 97,163.99 + 34946.91 1,79,297.91**
14. Landscape area 19020.22 19,020.22 + 5,636.61 24656.832
*Built-up Area for the Accorded EC = Proposed FAR + Service area
**Built-up Area for total = Proposed FAR + Basement area + Stilt area + Primary school + Nursery school 1 + Nursery school 2
built up area
Minus (-) showing the revision in area and (+) plus showing the expansion in area.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 17
Table2: Built – up Area for total (Revision & Expansion) Project
S.No. Description Type Area (in m2)
A. Residential FAR 1,37,227.60
1. Tower 1 3 BHK DUPLEX 7,938.875
2. Tower 2 3 BHK DUPLEX 7,938.875
3. Tower 3 3B+2T 5,760.103
4. Tower 4 3BHK 6,196.457
5. Tower 5 2BHK 4,960.122
6. Tower 6 2BHK+STUDY 4,142.549
7. Tower 7 2 BHK 5,127.667
8. Tower 8 2BHK+STUDY 3,110.216
2BHK
9. Tower 9 2BHK+STUDY 4,998.506
10. Tower 10 2BHK+STUDY 4,998.506
11. Tower 11 2BHK+STUDY 4,998.506
12. Tower 12 3BHK 10,360.344
2BHK+STUDY+ SR
ROOM
13. Tower 13 3 BHK 10,551.332
2BH+STUDY
14 Tower 14 2BHK+SQ 5,906.927
15 Tower 15 3 BHK 10,312.729
2BHK+STUDY+SR
16. Tower 16 2BHK+STUDY 4,992.673
17. Tower 17 2BHK 1,4477.756
18 Tower 18 2BHK 1,4477.756
19. Tower 19 EWS
1BHK 2,988.853
20. Tower 20 1BHK 2,988.853
B. Commercial FAR 394.358
C. Community FAR 1,634.2
D. Stilt Floor Area
Ground Floor
Ist Floor
7,918.36
6,161.92
1,756.499
E. Basement Area
Basement I
Basement II
29,688.00
14,844.00
14,844.00
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 18
F. Nursery School Built
up area
Nursery School 1
Nursery school 2
1,220.83
658.08
562.75
G. Primary School built
up area
1,214.56
Total Built-up Area (A + B + C + D + E + F + G) 1,79,297.91
2.5 POPULATION DETAILS
Total Population of Revision & Expansion of Group Housing project (fixed + floating) is
envisaged to be 9,853 persons. The residential block will have a total of 7,847 persons
(including General DU, General DU with SQ & EWS population) and the floating population
is estimated to be 1,101 persons. Total Number of Main dwelling units for (revision and
expansion) project is 1411 units and 250 units shall be allotted for the EWS. The detailed
population distribution is given below in table 3 along with comparative of obtained EC.
Table 3: Population Distribution total (Revision & Expansion) Project
Description Values in
applied EC
Revision In
applied area Expansion
Total
(Revision &
Expansion)
Fixed population
General DU (@ 5
persons/DU)
5040
(1008 DU)
5040
(1008 DU)
1285
(257 DU)
6325
(1265 D)
General DU with SQ
(@7 persons/DU) -
- 1022
(146 DU)
1022
(146 DU)
EWS
453 (151 DU)
(@ 3
persons/DU
453 (151 DU)
(@ 3
persons/DU
47 (99 DU) 500 (250 DU)
(@ 2 persons/DU
Total Fixed Population 5493 5493 2354 7847
Staff @5% of General
DU Population -
- 316 316
Visitors @ 10% of Fixed
Population -
- 785 785
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 19
Community
(@1person/10 m2
of
FAR)
Staff (@10% of
community
population)
Visitors (@90% of
community
population)
-
-
-
-
163
16
147
163
16
147
Commercial Area
(@1person/10 m2
of
FAR)
Staff (@10% of
commercial
population)
Visitors (@90% of
commercial
population)
787
-
-
132
13
119
-
-
-
132
13
119
Educational (Nursery +
Primary School)
@1person./4 sq mt of
buildable area
Staff
Visitors
Students
- -
-
-
-
610
31
61
518
610
31
61
518
Grand Total 6280 5625 4228 9853
2.6 POWER REQUIREMENT
The power supply shall be supplied by Dakshin Haryana Bijli Vitran Nigam. The Maximum
Demand load for the Revision & Expansion of Group Housing Project will be approx. 11453
KVA.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 20
SI. No. Description Values in accorded
EC
Total (Revision & Expansion)
1 Total power
requirement 8500 kVA 11453 kVA
Details of D.G Sets
There is provision of 4 no. of DG sets of 1500 kVA and 1 no. of DG sets of 750 kVA
capacity for power back up for the Revision & Expansion of Group Housing Project. The DG
sets will be equipped with acoustic enclosure to minimize noise generation and adequate
stack height for proper dispersion.
SI. No. Description Values in
applied EC
Total (Revision &
Expansion)
1 Power back-up 2x 750 kVA 4 x 1500 kVA & 1 x 750 kVA
2.7 PARKING
Parking Required for Total (Revision & Expansion) project
As per MoEF norms:
For residential facilities = 1 ECS/100 m2 proposed FAR
= 137227.6/100 =1372.276 or 1,372 ECS
For convenient shopping = 1 ECS/50 m2 FAR
= 394.358/50 = 8 ECS
For community = 1 ECS/50 m2 FAR
= 1634.02/50 = 33 ECS
For Educational Facilities = 1 ECS/50 m2 FAR
= 2435.39/50 = 49 ECS
Total parking required as per MoEF norms = 1372+8+33+49 = 1,462 ECS
As per Haryana Bye laws:
For Residential: 1.5 ECS @ 1411 main D.U = 2,116.5 ECS
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 21
For EWS: 5% of parking = 106 ECS
Total Parking required as per Haryana Bye laws = 2,223 ECS
Proposed Parking:
Area proposed for Open parking = 16125 m2
Area required for 1 ECS of open parking = 25 m²
Parking Proposed for open parking = 16125 /25 = 645 ECS
Area Proposed for parking under shade on ground floor = 2,250.00 m2
Area required for 1 ECS of open parking under shade = 25 m²
Parking proposed under shade on ground floor = 2,250.00/25 = 90 ECS
Area proposed for Stilt parking at Ground Floor = 6,030.16 m2
Area required for 1 ECS of Stilt parking = 30 m²
Parking proposed for Stilt parking at Ground Floor = 6,030.30/30 = 201 ECS
Area proposed for Stilt parking at First Floor = 1,756.44 m2
Area required for 1 ECS of Stilt parking = 30 m²
Parking proposed for Stilt parking at first floor = 1756.44/30 = 58 ECS
Area proposed for stack parking in Basement Level – I = 14,675.13 m2
Area required for 1 ECS of Basement parking = 35 m²
Parking proposed in basement Level – I = 419 x 2 = 838 ECS (MLCP)
Area proposed for stack parking in Basement Level – II = 14,691.87 m2
Area required for 1 ECS of Basement parking = 35 m²
Parking proposed in basement Level – II = 419 x 2 = 838 ECS (MLCP)
Total Parking Proposed in Open + Stilt + Basement = 645 + 90 + 201 + 58 + 838 + 838
= 2670 ECS
Parking proposed is 20% more than parking required as per MoEF norms/Haryana
Bye laws.
The Parking and Traffic Circulation plan is attached as Annexure VI.
2.8 WATER SUPPLY AND SEWAGE TREATMENT PLAN
2.8.1 Water Requirement and supply
The total water requirement of the Revision & Expansion of Group Housing Project is
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 22
approx. 1324 KLD out of which total domestic water requirement is 1116 KLD The total
fresh water requirement is approx. 831 KLD (which is 781 KLD i.e. 70% of the domestic
water demand plus 50 KLD for swimming pool). The water will be supplied by the Local
Authority. The daily water requirement and Sullage generation calculation is given below in
Table 4 along with comparative of Obtained EC.
Table 4: Total Water Demand of total (Revision & Expansion) Project
S. No.
Description
Values in Applied
EC
Total (Revision and
Expansion)
in KLD
1 Total Water Requirement 878 1,324
2 Total Domestic Water Requirement 754 1,116
3 Sullage Generated 648 960
4 STP capacity 780 1,200
Table 5: Calculations of Daily Water Demand for Existing (Accorded EC) project
SI.
No. Description Occupancy
Demand
(lpcd)
Total Water
Requirement in KLD
1. Domestic Water
Requirement
(a) Residents 5,493 135 741.555
(b) Commercial Area 787 15 11.805 or 12
SUB TOTAL (a+b) 754 KLD
2.
Horticulture Water
Requirement
(4.7 Acres)
@ 25 KLD/
Acre 119
3. DG Cooling (2x750
kVA) 5
TOTAL WATER REQUIRMENT (1+2+3) 878 KLD
Table 6: Sullage Calculations for Existing (Accorded EC) project
Domestic Water Requirement 754 KLD
Fresh (70% of domestic) 528 KLD
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 23
Table 7: Calculations for Daily Water Demand for of total (Revision & Expansion)
Project
SI.
No.
Description Occupancy Demand
(lpcd)
Total Water
Requirement (in KLD)
1. Domestic Water
Requirement
(a) Residents
Staff (@ 5% of General
DU Population)
Visitors
(@ 10% of Fixed
population)
7,847
316
785
135
45
15
1,059.345
14.22
11.775
(b) Commercial Area
Staff
Visitors
132
13
119
45
15
0.585
1.785
(c) Community
Staff
Visitors
163
16
147
45
15
0.72
2.205
(d) Educational
Staff
Visitors
Students
610
31
61
518
45
15
45
1.395
0.915
23.31
Flushing (30% of domestic) 226 KLD
Sullage Generated
(80% fresh + 100% flushing)
422+226= 648 KLD
STP Capacity 780 KLD
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 24
SUB TOTAL (a+b+c+d) 1116.255 or 1,116 KLD
2. Horticulture (20672.514
m2)
@ 6 Lt/sq mt 124.035 or 124 KLD
3. HVAC (218 TR)¤ 13 Lt./hr/TR 34.008 or 34 KLD
4. Make up water for
Swimming Pool
50 KLD
TOTAL WATER REQUIRMENT (1+2+3+4) 1324 KLD
¤12 hours are considered for HVAC
Table 8: Sullage Calculations for of total (Revision & Expansion) Project
Domestic Water Requirement 1116 KLD
Fresh (@ 70% of domestic) + make up
water for swimming pool
781.2+50 = 831.2 or 831 KLD
Flushing (@ 30% of domestic) 335 KLD
Sullage Generated
(@ 80% fresh + 100% flushing)
625 + 335 = 960 KLD
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 25
Figure 1: Water Balance Diagram for Existing (Accorded EC) project
Recycled Water
FRESH WATER
(528 KLD)
(70% of Domestic water)
SULLAGE GENERATED
(648 KLD)
STP CAPACITY 780 KLD
@ 80%
@ 80 %
518 KLD
FLUSHING
(226 KLD)
(30% of Domestic water)
@ 100%
Sullage
waterwaterwat
erwaterwaterw
aterwaterwater
HORTICULTURE (119 KLD)
119 KLD
226 KLD
DG COOLING
(5 KLD)
ROAD WASHING,
RECREATION &
MICELLANEOUS
(60 KLD)
Nearby Construction
activities
108 KLD
5 KLD
60 KLD
108 KLD
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 26
Figure 2: Water Balance Diagram for total (Revision & Expansion) Project
sullage Treatment and Re-use
It is expected that the total Sullage generation from Revision & Expansion project will be 960
KLD which will be treated in a STP of capacity 1200 KLD generating 768 KLD of treated
water. The treated water will be used for flushing, Horticulture, HVAC & rest surplus water
will be used for Nearby Construction projects i.e. approx. 108 KLD for Existing (accorded
EC) project and approx. 275 KLD for total (Revision & Expansion) project.
2.8.2 Sewerage System
FRESH WATER
(781 KLD)
(70% of Domestic water)
SULLAGE GENERATED
(960 KLD)
STP CAPACITY 1200 KLD
HORTICULTURE
(124 KLD)
@ 80%
FLUSHING
(335 KLD)
(30% of Domestic water)
@ 100%
124 KLD
335 KLD
Fresh water
TOTAL FRESH WATER
(781.2+50 = 831.2 or 831 KLD
50
KLD
34 KLD
960 KLD
(@ 80 %
768 KLD)
HVAC
(34 KLD)
Make up water for Swimming
Pool
(50 KLD)
NEARBY CONSTRUCTION
PROJECTS
275 KLD
275 KLD
Recycled Water Sullage
waterwaterwat
erwaterwaterw
aterwaterwater
Fresh Water
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 27
An external sewage network shall collect the sewage from all units, and flow by gravity to
the sewage treatment plant.
Following are the benefits of providing the Sewage Treatment Plant in the present
circumstances:
Reduced net daily water requirements, source for Horticultural purposes by utilization
of the treated waste water.
Reduced dependence on the public utilities for water supply and sewerage systems.
Sludge generated from the Sewage Treatment Plant shall be rich in organic content
and an excellent fertilizer for horticultural purposes.
a. Wastewater Details
(a) Daily load : 960 KLD
(b) Duration of flow to STP : 24 hours
(c) Temperature : Maximum 32oC
(d) pH : 7 to 9.5
(e) Color : Mild
(f) T.S.S. (mg/l) : 250-400 mg/l
(g) BOD5 (mg/l) : 200-300 mg/l
(h) COD (mg/l) : 500-700 mg/l
b. Final discharge characteristics
(a) pH : 6.5 to 8.5
(b) B.O.D. : < 5 mg/l
(c) C.O.D. : < 25 mg/l
(d) Total Suspended Solids : < 10 mg/l
MBBR TECHNOLOGY
An MBBR (Moving Bed Biofilm Reactor) or adherent reactor biomass moving bed is a
biological treatment plant for the purification of waste water, i.e. exhaust, polluted. The
reactors, moving bed biomass adherent part of the family of adherent biomass systems, which
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 28
are displacing jobs to activated sludge treatment of wastewater polluted.
2.9 Mechanism:
The MBBR reactor type are formed by biological reactors in which microorganisms flourish
in their means of support dispersed and suspended in the wastewater being treated. The
biofilm that forms on these supports is a function of the organic load associated with the
incoming wastewater. Unlike other processes at fixed biomass film, the media in this case are
free to move and then do not maintain fixed or the mutual positions nor compared to the
reactor.
The growth of a biofilm on a support is the result of the interaction between biological
processes and transport processes of the substrates. In particular, the formation of biofilms is
mainly due to the growth of microbial cells and the production of extracellular polymers
(usually negligible the contribution of the mass in suspension, which takes hold of the
surface).
The development of the film thus varies depending on the composition of the waste and
transport processes, from the latter depends on the availability of substrates for the
microorganisms within the biofilm. The progressive thickening of the film, one part affects
the diffusion of organic substrates and oxygen, the other causes, according to the
hydrodynamic characteristics of the reactor, the partial detachment of the film from the
media, through the phenomenon that is usually referred to as "detachment of the film
naked. In particular this happens for several reasons: predation by organisms such as protozoa
or metazoa, shear-induced water flow tangential to the film, abrasion due to shock each other
they are subjected to media where the film is present (trials to bed mobile), or a spontaneous
collapse when posting deep zones of the biofilm are made limiting conditions of oxygen and
substrates.
The MBBR reactor can be made with or without recirculation of sludge from the secondary
settler. If recycling is not foreseen, the adherent biomass reactors are defined as pure, while in
the case where the sludge to be recycled is called hybrid reactors, biomass or biomass mixed
adherent (adherent + suspended).
The moving bed reactors consist of tanks in which are kept in motion supporting elements,
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 29
which can be made of different materials, and on which the biofilm develops. The movement
of the elements is guaranteed by the system of air injection or by mechanical mixers, this
guarantees the realization of complete mixing reactors, so it reduces the presence of dead
zones hydraulically and maximizes the available volume. The tanks are equipped with
appropriate grids to avoid dragging and release of elements from the reactor.
2.10 Features:
The main characteristics of the moving bed reactor can be summarized as follows:
Operate continuously, are not subject to clogging, due to their high degree of vacuum,
and therefore does not require backwashing;
Have limited losses, because you do not have the formation of preferential pathways
between the supports;
Have a good versatility in the operation: it is possible to vary the rate of fill (always)
and the ratio of sludge recirculation (hybrid reactor).
2.11 Advantages:
The MBBR technology benefits are:
Easy to use for upgrading activated sludge plants;
primary sedimentation is not necessary;
footprint smaller than that of activated sludge plant;
Limited losses.
2.12 Applications:
The main applications include the treatment of wastewater, both civil and industrial. The
MBBR systems are particularly effective for removing nitrogen and phosphorus and organic
carbon (COD).The processes that are established are used depending on the type patented, of
biological aerobic, anoxic or anaerobic.
The phases are:
Removal of organic matter: biological treatment, grinding and refining;
Nitrification: oxidation of organic compounds to nitrogen was carried out by
autotrophic bacteria reduced,
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 30
Denitrification: the removal of nitrogen compounds present in solution in the
form of NO3-and NO2-(produced by nitrification above) by denitrifying bacteria.
The MBBR technology developed are used in municipal intensive, extensive lagoon systems,
fish farms, food processing, paper mills and chemical plants.
In some cases, are flanked by wider dissemination systems to enhance the effect of treatment.
The MBBR technology is still not very widespread in Italy, while increasing applications
especially in Northern Europe is indicated for the adaptation of existing systems thanks to the
simplicity of implementation and management that characterizes it.
Figure 3: Schematic Diagram of STP
Sewer System
The alignment and slope of the sewer line will follow the road network, drains or natural
ground surface and will be connected to the trunk sewers. The discharge point will be a
treatment plant, a pumping station, a water course or an intercepting sewer. Pumping stations
would be provided at places where the natural slope of the terrain is insufficient to permit
gravity flow or the cost of excavation is uneconomical to do the same.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 31
2.13 RAINWATER HARVESTING
The storm water disposal system for the premises shall be self-sufficient to avoid any
collection/stagnation and flooding of water. The amount of storm water run-off depends upon
many factors such as intensity and duration of precipitation, characteristics of the tributary
area and the time required for such flow to reach the drains. The drains shall be located near
the carriage way along either side of the roads. Taking the advantage of road camber, the
rainfall run off from roads shall flow towards the drains. Storm water from various plots/shall
be connected to adjacent drain by a pipe through catch basins. Therefore, it has been
calculated to provide 20 rainwater harvesting pits at selected locations, which will catch the
maximum run-off from the area.
1) Since the existing topography is congenial to surface disposal, a network of storm
water pipe drains is planned adjacent to roads. All building roof water will be brought
down through rain water pipes.
2) Proposed storm water system consists of pipe drain, catch basins and seepage pits at
regular intervals for rain water harvesting and ground water recharging.
3) For basement parking, the rainwater from ramps will be collected in the basement
storm water storage tank. This water will be pumped out to the nearest external storm
water drain.
Rain water harvesting has been catered to and designed as per the guideline of CGWA. The
recharge pit of 3 m diameter and 3.5 m depth is constructed for recharging the water. At the
bottom of the recharge well, a filter media is provided to avoid choking of the recharge bore.
Design specifications of the rain water harvesting plan are as follows:
Catchments/roofs would be accessible for regular cleaning.
The roof will have smooth, hard and dense surface which is less likely to be damaged
allowing release of material into the water. Roof painting has been avoided since most
paints contain toxic substances and may peel off.
All gutter ends will be fitted with a wire mesh screen and a first flush device would be
installed. Most of the debris carried by the water from the rooftop like leaves, plastic
bags and paper pieces will get arrested by the mesh at the terrace outlet and to prevent
contamination by ensuring that the runoff from the first 10-20 minutes of rainfall is
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 32
flushed off.
No sewage or wastewater would be admitted into the system.
No wastewater from areas likely to have oil, grease, or other pollutants has been
connected to the system.
Rain Water Harvesting Pits
Table No 9: Total Rain Water Harvesting Pits of total (Revision & Expansion) Project
SI.
No.
Description Values in accorded EC Total
( Revision & Expansion)
1. Rainwater
harvesting pits 14 20
Table No 10: Rain Water Harvesting Pits in Existing (Accorded EC) project
Type of the
plot/built-up area
Area (in
sq mts)
Coefficient
of run-off
Peak rainfall
intensity during
one hour of
rainfall (in mts)
Rain water
harvesting
potential/hour (in
m3)
Roof-top area 10300 0.8 0.045 370.8
Paved Area (Total
area - sum of
rooftop area &
landscape area)
52911.9
0.7
0.045
1666.725
Green Area 19020.22 0.1 0.045 85.59
Considering 15 minutes retention time, total storm water load is = 530.779
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 33
Taking the radius as 4 m and effective depth as 3 m, volume of a RWH
pit ( π r2h/4) is =3.14 × 4 × 4 × 3/ 4 = 37.68
Hence no. of pits required in approx = Total storm water load considering 15
minutes retention time / Volume of a RWH pit = 14.08
Thus, total no. of pits to be provided is 14 pits.
The required nos. of pit calculation is given in the following Table: 11
Table No 11: Calculations for Storm water and Required Rainwater Harvesting Pits for
total (Revision & Expansion) Project
Type of the plot/built-up area Area (in
sq mts)
Coeffici
ent of
run-off
Peak
rainfall
intensit
y
during
one
hour of
rainfall
(in mts)
Rain water
harvesting
potential/hou
r (in m3)
Roof-top area 13,817.64 0.8 0.045 497.435
Paved Area (Total area - sum of
rooftop area & landscape area)
43,457.64 0.7 0.045 1,378.366
Green Area (Landscape area- water
body)
20672.514 0.1 0.045 93.02
Considering 15 minutes retention time, total storm water load is =
492.20
Taking the radius as 3 m and effective depth as 3.5 m, volume of a RWH pit (
π r2h/4) is =3.14 × 3 × 3 × 3.5/ 4 = 24.72
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 34
Hence no. of pits required in approx = Total storm water load considering 15
minutes retention time / Volume of a RWH pit = 19.911 or say 20
As 1 pit/acre is required so, total 20 rain water harvesting pits will be required for 20.31 acre
land.
Total of 20 Rain Water Harvesting pits are being proposed for artificial rain water recharge
within the project premises
Figure 4: Typical Rain Water Harvesting Pit Design
2.14 SOLID WASTE MANAGEMENT
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 35
Solid Waste
Construction
Waste
Construction waste,
Broken Bricks,
Waste Plaster
Empty Cement
Bags
Used in re-filling,
raising site level
Sold to agency for
recycling
Excavated Soil
Top soil conserved for landscaping,
balance used in re-
filling
Solid waste would be generated both during the construction as well as during the operation
phase. The solid waste expected to be generated during the construction phase will comprise
of excavated materials, used bags, bricks, concrete, MS rods, tiles, wood etc. The following
steps are to be followed for the management solid waste:
Construction yards are for storage of construction materials.
The excavated material such as topsoil and stones will be stacked for reuse during
later stages of construction
Excavated top soil will be stored in temporary constructed soil bank and will be
reused for landscaping of the Group housing project.
Remaining soil shall be utilized for refilling / road work / rising of site level at
locations/ selling to outside agency for construction of roads etc.
Figure 5: Solid Waste Management Scheme (Construction Phase)
During the operation phase, waste will comprise domestic as well as agricultural waste. The
solid waste generated from the project shall be mainly domestic waste and estimated quantity
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 36
of the waste shall be approx 4390 kg per day (@ 0.5 kg per capita per day for residents, @
0.15 kg per capita per day for the visitors, 0.25 kg per capita per day for the staff members
and landscape wastes @ 15 kg/acre/day).Following arrangements will be made at the site in
accordance to Municipal Solid Wastes (Management and Handling) Rules, 2000 and
amended Rules, 2008. E- Waste will be managed as per E-waste (Management & Handling)
rules, 2011.
Table 13: Solid Waste Generation for total (Revision & Expansion) project
SI. No. Description Values in accorded EC Total
(Revision & Expansion)
1 Solid waste 2315 kg/day 4390 kg/day
Table 14: Calculation of Solid Waste Generation for total (Revision & Expansion)
project
S. No. Category kg per capita per day Waste generated
(kg/day)
1. Residential
General DU
General DU with SQ
EWS
Staff
Visitors
6325 @ 0.5 kg/day
1022 @ 0.5 kg/day
500 @ 0.50 kg/day
316 @ 0.25 kg/day
3162.50
511.00
250
79
117.75
2. Commercial
Staff
Visitors
13 @ 0.25 kg/day
119 @ 0.15 kg/day
3.25
17.85
3. Community
Staff
Visitors
16 @ 0.25 kg/day
147@ 0.15 kg/day
4
22.05
4. Educational
Students
Staff
Visitors
518 @ 0.25 kg/day
31 @ 0.25 kg/day
61 @ 0.15 kg/day
129.5
7.75
9.15
5. Landscape waste 5.10 acres @ 15
kg/acre/day
76.5
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 37
TOTAL SOLID WASTE GENERATED 4390.3 kg/day or Say
4390 kg/day
(Source: For Waste Collection, Chapter 3, Table 3.6, Page no. 49, Central Public Health
& Environment Engineering Organization, Ministry of Urban Development, (Government
of India, May 2000))
Collection and Segregation of waste
1. A door to door collection system will be provided for collection of domestic waste
in colored bins from household units.
2. For commercial waste collection, adequate number of colored bins (Green and
Blue & dark grey bins– separate for Bio-degradable and Non Bio-degradable) are
to be provided at the strategic locations of the commercial area.
3. Litter bin will also be provided in open areas like parks etc.
Treatment of waste
Bio-Degradable wastes
1. Bio-degradable waste will be subjected to composting by the use of organic waste
converter and the compost will be used as manure.
2. STP sludge is to be used for horticultural purposes as manure.
3. Horticultural Waste is to be composted and will be used for gardening purposes.
Recyclable wastes
i. Grass Recycling – The cropped grass will be spread on the green area. It will act as
manure after decomposition.
ii. Recyclable wastes like paper, plastic, metals etc. will be sold off to recyclables.
Disposal
Recyclable and non-recyclable wastes will be disposed through Govt. approved agency.
Hence, the Municipal Solid Waste Management will be conducted as per the guidelines of
Municipal Solid Wastes (Management and Handling) Rules, 2000 and amended Rules, 2008.
A Solid waste management Scheme is depicted in the following figure for the residential
project.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 38
Figure 6: Solid Waste Management Scheme (Operation Phase)
Organic Waste Converter
A waste converter is a machine used for the treatment and recycling of solid and liquid refuse
material. A converter is a self-contained system capable of performing the following
functions: pasteurization of organic waste; sterilization of pathogenic or biohazard waste;
grinding and pulverization of refuse into unrecognizable output; trash compaction;
dehydration.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 39
Figure 7: Organic Waste Converter
Benefits of organic waste converter
1. Large quantity of solid waste is converted to fertilizer in a very short period
2. Fertilizers can be sold as compost to farmers, or used for gardening
3. Machine requires less space and the efficiency is high
4. Manpower and maintenance is very less
5. This is one of the latest techniques of managing solid waste
2.15 LANDSCAPE
Total green area plus tree plantation measures 24,656.832 m2 i.e. 7968.652 m
2 (32.31% of the
green area) for tree plantation; 8719.528 m2 (35.36 % of the green area) for Avenue
Plantation, 3984.326 m2 (
16.15% of the green area) for climber plants, herbs & shrubs,
3984.326 m2
(16.15% of the green area ) for water body. The breakup of green area is given
in Table 15 and list of trees to be planted is given below in Table 15
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 40
Table 15: List of Trees
S.No. Botanical name Local name
1. Cassia fistula Amaltas
2. Delonix regia Gulmohar
3. Bauhinia purpurea Kachnar
4. B. Variegata Kachnar
5. Lagerstroemia flosreginae Pride of India
6. Grevillea robusta Silk oak
7. Callistemon lanceolatum Bottle Brush
8. Anthocephalus cadamba Kadam
9. Polyalthia longifolia Ashok
10. Putranjiva roxburghii Putrajiv
11. Sterculea alata Coconut Buddha
12. Melia azadirachta Neem
13. Bassia Latifolia Mahua
14. Cassia javancia Pink Shower
15. Alstonia scholaris Devil Tree
16. Michelia champaca Champak
17. Terminalia arjuna Arjun
18. Ficus retusa Ficus
19. Saraca indica Ashoka
20. Casuarina Equisetifolia Ironwood
21. Salix alba White Willow
22. Dalbergia sissoo Shisham
23. Kigelia Pinnata Sausage tree
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 41
24. Poangamia glabra Karanja
25. Erythrina indica Pangaar
26. Maduca latifolia Madhu
27. Ficus infectoria Pilkhan
28. Cassia nodosa Roheda
ORNAMENTAL SHRUBS
29. Delonix pulcherima Chhota gulmohar
30. Plumeria alba Champa
31. Lagerstroemia indica Dhayti
32. Ervatamia divaricata Chandni
33. Nyctanthes arbor-tristis Harsinghar
34. Yellow Duranta Skyflower
35. Hibiscus hirusta Costa Flores
36. Cassia biflora Twin-flowered cassia
37. Nerium indicum Kaner
38. Cassia aungustifolia Senna
39. Cassia glauca Kalamona
(Source: Guidelines for developing Green Belts by CPCB, 2000)
2.16 MANPOWER REQUIREMENT
During the construction phase, a large number of professionals and workers will be engaged in
various related activities. An approximation of the manpower requirement for the project is
around 200-300 workers which include skilled, semiskilled and unskilled.
As a responsible corporate, the proponent shall comply with all applicable Acts related to
employees’ service and their welfare of the Government of India in terms of working hours,
basic amenities and welfare facilities such as given below:
Minimum Wages Act, 1948,
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 42
Contract Labour (Regulation & Abolition) Act, 1970,
Inter-State Migrant Workmen (Regulation of Employment & Conditions of Services)
Act,1979,
The Building and other Construction Workers (Regulation and Employment of
Service) Act, 1996,
The Building and other construction workers Welfare Cess Act, 1996.
All workers and technicians will be provided with clean drinking water, sheds for resting and
sanitary facilities as mobile toilets/ toilets connected to septic tanks. Camps shall also be
organized for health check up every six months. No child shall be employed in the process and
that the safe and hygienic working conditions will be provided for the workers both during
construction and operational phase of the project. First aid facilities will be maintained at
readily accessible place where necessary appliances including sterilized cotton, wool, etc shall
be available for the construction workers and safe drinking water and sanitary facilities
(mobile sulabh shauchalayas) will be provided during construction phase.
2.13 FIRE FIGHTING SYSTEM
The Revision & Expansion of Group Housing Project located at Village Mujheri, Sector 70,
Faridabad, Haryana. Following provisions are required according to National Building Code 2005 Table 23 and
generally according to occupancy:-
The fire fighting system has been designed considering the following codes, manual and
guidelines;
National Building Code of India (NBC);
Latest relevant NFPA codes, USA, in particular NFPA – 13, 14, 20 & 22;
IRI guidelines;
As per requirement of fire officer/local fire approving authorities; and
As per Indian Standard Code for Fire Protection (IS Codes)
Following items are envisaged for firefighting:
Fire-Water Connections
Firewater inlet and outlet connections shall be provided to the water storage tanks;
External main fire ring, having 150 mm diameter and hydrants @ 45 m3/s spacing
shall be provided. This external fire ring shall be separated from the Sprinkler Main
Systems;
All flow switches, test valves, drain pipes etc. shall be provided as per NFPA
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 43
guidelines on the sprinkler system;
All pump installation and arrangements shall be in accordance with IRI guidelines and
NFPA-20;
All pumps and accessories and electrical controllers shall be as per UL/FM lists,
tested, approved and certified; and
By-pass arrangements shall to be provided (150 mm Dia. Nominal bore) with NRV
and gate valve and bulk flow meter on the discharge header of each pump to check the
duties of pumps.
2.14 DETAILS OF CONSTRUCTION MATERIALS
List of building materials being used at site:
1. Coarse sand
2. Fine sand
3. Stone aggregate
4. Stone for masonry work
5. Cement
6. Reinforcement steel
7. Pipe scaffolding (cup lock system)
8. Bricks
9. CLC fly ash blocks
10. Crazy (white marble) in grey cement
11. P.V.C. conduit
12. MDS, MCBs
13. PVC overhead water tanks
14. 2 1/2'’ thick red colour paver tiles
15. PPR (ISI marked)
16. PVC waste water lines
17. S.W. sewer line up to main sewer
18. PVC rain water down take
19. Stainless steel sink in kitchen
20. Joinery hardware- ISI marked
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 2
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 44
2.14 MATERIALS USED FOR CONSTRUCTION & THEIR U VALUES
2.15 LIST OF MACHINERY USED DURING CONSTRUCTION
(i) Dumper
(ii) Concrete mixer with hopper
(iii) Excavator
(iv) Concrete Batching Plant
(v) Cranes
(vi) Road roller
(vii) Bulldozer
(viii) RMC Plant
(ix) Tower Cranes
(x) Hoist
(xi) Labor Lifts
(xii) Pile Boring Machines
(xiii) Concrete pressure pumps
(xiv) Mobile transit mixer
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 45
CHAPTER-3
DESCRIPTION OF ENVIRONMENT
3.1 INTRODUCTION
Information on the existing environmental status is essential for assessing the likely environmental
impacts of the project. In order to get an idea about the existing state of the environment, various
environmental attributes such as meteorology, air quality, water quality, soil quality, noise level,
ecology and socio-economic environment have been studied/ monitored.
3.2 STUDY PERIOD
Baseline environmental data generation for air, water, noise and soil quality monitoring around the
project site was conducted from 1st March 2013 to 31
st May 2013. Apart from field monitoring,
additional data was also collected from secondary sources like Irrigation Department, India
Meteorological Department (IMD), Central Ground Water Board, Geological Survey of India, State
Ground Water Department, State Pollution Control Board, Census of India and Local Forest
Department, Non -Governmental Agencies etc.
3.3 STUDY AREA
As per the Faridabad Master plan 2021 the site is earmarked for residential area having total Plot area
of 82,232.12 m2 (20.3199 acres). The probability of impacts from the Group Housing Project is
generally within 2 kms. However, field monitoring has been carried out beyond 2 km, in case of
presence of sensitive receptors. The study area comprises area with angular distance of 5 km
surrounding the project site. A 15 km radius around the project area has been considered for
secondary data collection.
3.4 BASELINE MONITORING OF ENVIRONMENTAL COMPONENTS
In order to get an idea about the existing state of the environment, various environmental attributes
such as meteorology, air quality, water quality, soil quality, noise level, ecology and socio-economic
environment have been studied/monitored.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 46
3.4.1 Meteorology
A meteorological station was set up at the project premises. Meteorological data was generated
during the March 2013 to May 2013.
The following parameters were recorded at hourly intervals continuously during monitoring period:
-Wind speed
-Air temperature
Table-3.1 gives summarized meteorological data for the monitoring period (March- May 2013).
Figure-3.1 gives the wind-rose diagram for the monitoring period.
Table 3.1: Meteorological Data for (March- May 2013)
Month Temperature (o
C) Wind Speed (m/s)
Min Max Average Min Max Average
March 10 34 23 0 8.2 2.82
April 0 40 11 0 7.7 2.44
May 22 46 35 0 12.9 2.82
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 47
Figure 8: The wind-rose diagram for three months 1st March 2013 to 31st May 2013
3.4.2 Air Environment
The prime objective of the baseline study with respect to ambient air quality is to establish the present
air quality and its conformity to National Ambient Air Quality Standards. This data has been further
used during impact assessment to predict the final air quality. This section describes the sampling
locations, frequency of sampling and methodology adopted for monitoring ambient air quality.
To quantify the impact of the project on the ambient air quality, it is necessary at first to evaluate the
existing ambient air quality of the area. The existing ambient air quality, in terms of Particulate Matter –
10 (PM10), Particulate Matter- 2.5 (PM2.5), Sulphur-dioxide (SO2), Oxides of Nitrogen (NO2), and
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 48
Carbon Monoxide (CO), has been measured through a planned field monitoring.
To assess the ambient air quality level, 5 (five) monitoring stations were set up. Table-3.2 gives
location of the ambient air quality monitoring stations and attached as Annexure VII (a)
Table 3.2: Location of Ambient Air Quality Monitoring Stations
Locations Locations
Code
Direction Distance
AQ1 Village Mujheri E 0.4 km
AAQ2 Sector 71 ENE 1.1 km
AAQ3 Sector 68 SE 1.9 km
AAQ4 Sector 2 WSW 1.2 km
AAQ5 Project site - 0 km
3.4.2.1 Monitoring Schedule
Ambient air quality monitoring was carried out twice a week with a frequency of 24 hours for 12
weeks.
3.4.2.2 Methods of Sampling and Analysis
Fine particulate Sampler APM MFC550 was used for monitoring Particulate Matter (PM2.5 and
PM10); gaseous pollutants like SO2, and NO2 was collected by Gaseous Pollutant Sampler APM
433 and CO was monitored by Serinous 30 CO Analyser with NDIR detector.
3.4.2.3 Method for measurement of Particulate matter, SO2 & NO2
Method for measurement of Particulate Matter (PM10) in ambient air is done by Cyclonic Flow
Technique. Particles with aerodynamic diameter less than the cut-point of the inlet are collected by a
filter. Ambient air at the monitoring location is sucked through a cyclone. Coarse and non-reparable
dust is separated from the air stream by centrifugal forces acting on the solid particles and these
particles fall through the cyclone's conical hopper and get collected in the sampling cap placed at the
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 49
bottom. The fine dust (<10 microns) forming the particulate matter (PM10) passes the cyclone and is
retained on the filter paper The mass of these particles is determined by the difference in filter
weights prior to and after sampling. The concentration of PM10 in the designated size range is
calculated by dividing the weight gain of the filter by the volume of air sample. A tapping is
provided on the suction side of the blower to provide suction for sampling air through a set of
impinges for containing absorbing solutions for SO2 and NO2. Samples of gases are drawn at a flow
rate of 0.2 liters per minute. The APM MFC 550 is used for PM2.5. This system is a manual method
for sampling fine particles (PM2.5 fraction) and is based on Impact or designs standardized by
USEPA for ambient air quality monitoring.
PM2.5 & PM10 have been estimated by gravimetric method (IS- 5182 part XXIII 2006). Improved
West and Gake method (IS-5182 part-II, 2001 & reaffirmed 2006) has been adopted for estimation
of SO2 and Modified Jacobs-Hochheiser method (IS-5182 part-X, 2006) has been adopted for the
estimation of NO2.
3.4.2.4 Method for measurement of Carbon Monoxide – NDIR method
Instrument used: Ecotech Serinus 30 Carbon Monoxide
This analyzer is used to measure CO in ambient air, in the range of 0-200 ppm (220mg/m3) to a
sensitivity of 0.05 ppm 55µg/m3). The Serinus 30 combines the benefits of Microprocess control
with Non-Dispersive Infrared Spectrophotometery technology (IS-182 part X 1999, reaffirmed
2003). CO Concentration is automatically corrected for gas temperature and pressure changes.
3.4.2.5 Results and Discussions
The results of Air quality is summarized below in the tabular form. The results when compared
with National Ambient Air Quality Standards (NAAQS) of Central Pollution Control Board
(CPCB) for "Industrial, Residential, Rural and Other Areas" show that the average values of
ambient air quality parameters are well within the stipulated limit.
The results of ambient air quality monitoring are summarized in the Tables below:
Table 3.3 (a) Ambient Air Quality with respect to PM2.5
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 50
PM2.5 (µg/m3)
Location AAQ 1 AAQ 2 AAQ 3 AAQ 4 AAQ 5
Min 38.4 38.1 34.5 41.8 40.1
Max 62.8 54.5 50.4 66.4 64.3
Average 47.1 45.6 39.4 49.7 50.7
98 Percentile 61.7 53.3 49.6 65.8 63.1
The values of PM2.5 in study area are presented in Table 3.3 (a). The seasonal minimum, maximum,
average values and 98 percentile of PM 2.5 were observed 40.1 µg/m3, 64.3 µg /m
3, 50.7 µg/m
3 and 63.1
µg/m3 respectively at the project site. The seasonal minimum, maximum and average values ranged
between 38.1-41.8 µg/m3, 50.4-66.4 µg/m
3, 39.4-50.7 µg/m
3 & 49.6-65.8 µg/m
3 respectively in the
study area.
Table 3.3 (b) Ambient Air Quality with respects to PM10
PM10 (µg/m3)
Location AAQ 1 AAQ 2 AAQ 3 AAQ 4 AAQ 5
Min 81.1 80.3 78.9 85.4 82.2
Max 124.5 114.5 92.6 126.5 116.8
Average 97.6 94.0 84.8 102.3 100.1
98 Percentile 122.7 113.9 91.8 125.4 115.5
The values of PM10 in study area are presented in Table 3.3 (b). The seasonal minimum, maximum,
average values and 98 percentile of PM10 were observed 82.2 µg/m3, 116.8 µg /m
3, 100.1 µg/m
3 and
115.5 µg/m3 respectively at the project site. The seasonal minimum, maximum and average values
ranged between 78.9-85.4 µg/m3, 92.6-126.5 µg/m
3, 84.8-102.3 and 91.8-125.4 µg/m
3 respectively in
the study area.
Table 3.3 (c) Ambient Air Quality with respect to SO2
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 51
SO2 (µg/m3)
Location AAQ 1 AAQ 2 AAQ 3 AAQ 4 AAQ 5
Min 8.9 8.2 7.2 9.8 9.2
Max 15.6 14.8 12.4 15.5 14.5
Average 10.8 9.8 9.7 12.1 10.8
98 Percentile 15.6 13.7 11.9 14.9 13.7
The values of SO2 in study area are presented in Table 3.3 (c). The seasonal minimum, maximum,
average values and 98 percentile of SO2 were observed 9.2 µg/m3, 14.5 µg /m
3, 10.8 µg/m
3 and 13.7
µg/m3 respectively at the project site. The seasonal minimum, maximum and average values ranged
between 7.2-9.8 µg/m3, 12.4-15.6 µg/m
3 , 9.7-12.1 µg/m
3 & 11.9-15.6 µg/m
3 respectively in the study
area.
Table 3.3 (d) Ambient Air Quality with respects to NO2
NO2 (µg/m3)
Location AAQ 1 AAQ 2 AAQ 3 AAQ 4 AAQ 5
Min 22.8 22.6 19.5 26.9 23.2
Max 34.8 32.4 28.2 36.8 34.6
Average 27.0 26.5 23.9 30.8 27.3
98 Percentile 33.1 31.8 27.7 36.1 33.2
The values of NO2 in study area are presented in Table 3.3 (d). The seasonal minimum, maximum,
average values and 98 percentile of NO2 were observed 23.2 µg/m3, 34.6 µg /m
3, 27.3 µg/m
3 and 33.2
µg/m3 and respectively at the project site. The seasonal minimum, maximum and average values ranged
between 19.5-26.9 µg/m3, 28.2-36.8 µg/m
3, 23.9-30.8 and 27.7-36.1 µg/m
3 respectively in the study
area.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 52
Table 3.3 (e) Ambient Air Quality with respects to CO
CO (µg/m3)
Location AAQ 1 AAQ 2 AAQ 3 AAQ 4 AAQ 5
Min 830 800 740 870 820
Max 1280 1250 1190 1310 1210
Average 996 1031 943 1065 988
98 Percentile 1220 1236 1130 1278 1187
The values of CO in study area are presented in Table 3.3 (e). The seasonal minimum, maximum,
average values and 98 percentile of CO were observed 820 µg/m3, 1210 µg/m
3, 988 µg/m
3 and 1187
µg/m3
respectively at the project site. The seasonal minimum, maximum and average values ranged
between 740-870 µg/m3, 1190-1310 µg/m
3, 943-1065 µg/m
3 and 1130-1278 µg/m
3 respectively in the
study area.
3.4.3 Noise Levels
Noise is one of the most undesirable and unwanted by-products of our modern life style. It may not
seem as insidious or harmful as air and water pollutants but it affects human health and well-being and
can contribute to deterioration of human well-being in general and can cause neurological disturbances
and physiological damage to the hearing mechanism in particular. It is therefore, necessary to measure
both the quality as well as the quantity of noise in and around the site.
3.4.3.1 Methodology
The intensity of sound energy in the environment is measured in a logarithmic scale and is expressed
in a decibel, dB (A) scale. In a sophisticated type of sound level meter, an additional circuit (filters)
is provided, which modifies the received signal in such a way that it replicates the sound signal as
received by the human ear and the magnitude of sound level in this scale is denoted as dB (A). The
sound levels are expressed in dB (A) scale for the purpose of comparison of noise levels, which is
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 53
universally accepted by the international community.
Noise levels were measured using an Integrating sound level meter manufactured by Pulsar
Instruments Plc, Model NO. 91 (SL.No.B21625). It has an indicating mode of Lp and Leq. Keeping
the mode in Lp for few minutes and setting the corresponding range and the weighting network in
“A” weighting set the sound level meter was run for one hour time and Leq was measured at all
locations.
The day noise levels have been monitored during 6.00 am to 10.00 pm and night noise levels, during
10.00 pm to 6.00 am at all the 4 locations, which covers residential areas, commercial, industrial
areas, Silence area if available within 10 km radius of the study area.
3.4.3.2 Sampling Locations
A preliminary survey was undertaken to identify the major noise generating sources in the area. The
noise survey was conducted to assess the background noise levels in different zones. Gazettes
Notification (S.O. 123(E)) of MoEF dated February 14, 2000 on ambient air quality standards has
different noise levels for different zones viz. project site, industrial, commercial, and residential and
silence zones. Four sampling locations were selected for the sampling of noise levels. The sampling
locations are given in Table-3.4 below and also attached as Annexure VII (b).
Table 3.4 Noise Level Monitoring Stations in the study area
Location Code Locations Type of Area Direction Distance
NQ1 Village Mujheri Residential Zone __ __
NQ2 Anuradha Hospital Silence Zone WNW 3.2 km
NQ3 Innova Technology Industrial Zone NW 3.0 km
NQ4 SRS Bazar Commercial Zone NW 2.0 km
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 54
Ministry of Environment & Forests (MoEF) has notified the noise standards vide gazette notification
dated February 14, 2000 for different zones under the Environment Protection Act (1986). These
standards are given in Table-3.5.
Table 3.5 Ambient Quality Standards in respect of Noise
Area Code Category of Area Noise dB(A) Leq
Day time* Night time*
A Residential Zone 55 45
B Silence zone 50 40
C Industrial Zone 75 70
D Commercial Zone 65 55
Note:
1. Daytime is from 6.00am to 10.00 pm and Night time is from 10.00 pm to 6.00 am.
2. Silence zone is defined as area up to 100 meters around premises of hospitals,
educational institutions and courts. Use of vehicle hours, loud speakers and bursting of
crackers are banned in these zones.
3.4.3.3 Results and Discussion
The noise data compiled on noise levels in April 2013 is given in Table - 3.6. The ambient noise
level at the project site during the day was 57.8 dB (A) during night it is 48.6 dB (A). For maintaining
the noise level, plantation and traffic management during the operation phase are suggested.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 55
Table 3.6: Hourly Leq Noise Level in the study Area, (March to May 2013)
Royal Heritage village.-Mujheri Sec.70 Faridabad Haryana
Noise Quality data April 2013
S.No. Locations ZONE LIMIT (as per CPCB Guidelines),Leq RESULT (Leq)
DAY* NIGHT* DAY* NIGHT*
1 Village Mujheri Residential Zone 55 45 57.8 48.6
2 Anuradha Hospital Silence zone 50 40 55.4 44.8
3 Innova Technology Industrial Zone 75 70 69.2 59.9
4 SRS Bazar Commercial Zone 65 55 62.3 51.4
3.4.4 WATER ENVIRONMENT
3.4.4.1 Water Quality
Water quality assessment is one of the essential components of EIA study. Such assessment helps in
evaluating the existing health of water body and suggesting appropriate mitigation measures to minimize
the potential impact from development projects. Water quality of ground water has been studied in order
to assess proposed water-uses in construction, drinking, cooling and horticulture purpose.
The water quality at the site and other locations within the 10 km impact zone was monitored during
March to May 2013. The locations of the monitoring sites are given in Table 3.7 and the result of the
monitoring and analysis of ground water is presented in the Table 3.8 (a, b, c).
3.4.4.2 Sampling Frequency and Sampling Techniques
Parameters for analysis of water quality were selected based on the utility of the particular source of
water as per MoEF guidance. Hence quality of ground water was compared with IS: 10500: 1991
(Reaffirmed 1993 With Amendment NO -3 July 2010) for drinking purposes. As per the standard
practice, one sample from each station was taken each month in the study period. Sampling was done by
standard sampling technique as per the Standard Methods. Necessary precautions were taken for
preservation of samples. The sampling locations for ground water are given in Table-3.7 and is attached
as Annexure VII (c) .
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 56
Table 3.7: Location of Water Sampling Sites
Location No. Location Name Distance & Direction from
project site
GW – 1 Sector 2 WSW, 1.2 km
GW – 2 Village Mujheri E, 400 m
GW-3 Sector 71 ENE, 1.1 km
The water quality in the impact zone was assessed through physic- chemical and bacteriological
analysis of ground samples. The results have been compared with the drinking water quality
standards specified in IS: 10500.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 57
Royal Heritage vill.-Mujheri Sec.70 Faridabad Haryana
Ground Water Quality
March13
Parameter Unit
Limit (as per IS:10500:2012) GW 1 GW 2 GW 3
Desirable Limit
Permissible
Limit Sector2
Village
Mujheri Sec.71
Colour Hazen 5 15 <5 <5 <5
Odour - Agreeable Agreeable Agreeable Agreeable Agreeable
Taste - Agreeable Agreeable Agreeable Agreeable Agreeable
Turbidity NTU 1 5 <1 <1 <1
pH - 6.5-8.5
No
Relaxation 7.36 7.44 7.48
Total Hardness (as CaCO3) mg/l 200 600 293 328 253
Iron (as Fe) mg/l 0.3
No
Relaxation 0.08 0.09 0.11
Chlorides (as Cl) mg/l 250 1000 286 352 336
Fluoride (as F ) mg/l 1 1.5 0.4 0.6 0.6
TDS mg/l 500 2000 950 1210 1125
Calcium(as Ca2+) mg/l 75 200 62 68 60
Magnesium (as Mg2+) mg/l 30 100 33 38 25
Copper (as Cu) mg/l 0.05 1.5 <0.01 <0.01 <0.01
Manganese(as Mn) mg/l 0.1 0.3 0.03 0.04 0.05
Sulphate (as SO4) mg/l 200 400 61 76 65
Nitrate(as NO3) mg/l 45
No
Relaxation 7 6 9
Table 3.8 (a) Ground water quality in study area during March 2013
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 58
Phenolic Compounds (as
C6H5OH) mg/l 0.001 0.002 <0.001 <0.001 <0.001
Mercury (as Hg) mg/l 0.001
No
Relaxation <0.001 <0.001 <0.001
Cadmium (as Cd) mg/l 0.003
No
Relaxation <0.01 <0.01 <0.01
Selenium ( as Se ) mg/l 0.01
No
Relaxation <0.01 <0.01 <0.01
Arsenic (as As) mg/l 0.01 0.05 <0.01 <0.01 <0.01
Cyanide (as CN ) mg/l 0.05
No
Relaxation <0.01 <0.01 <0.01
Lead (as Pb) mg/l 0.01
No
Relaxation <0.01 <0.01 <0.01
Zinc (as Zn) mg/l 5 15 0.08 0.11 0.13
Anionic Detergent (as
MBAS) mg/l 0.2 1 <0.01 <0.01 <0.01
Chromium (as Cr6+) mg/l 0.05
No
Relaxation <0.01 <0.01 <0.01
Mineral oil mg/l 0.5
No
Relaxation <0.01 <0.01 <0.01
Alkalinity (as CaCO3) mg/l 200 600 275 371 342
Aluminum (as Al) mg/l 0.03 0.2 <0.02 <0.02 <0.02
Boron (as B) mg/l 0.5 1 0.1 0.3 0.2
Microbiological Parameter
Total Coliform MPN/100ml 10 , Max - ND(<2) ND(<2) ND(<2)
E.coli
E.coli
/100ml Absent - Absent Absent Absent
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 59
Royal Heritage vill.-Mujheri Sec.70 Faridabad Haryana
Ground Water Quality
April 13 Apr-12
S.No Parameter Unit
Limit (as per IS:10500:2012) GW 1 GW 2 GW 3
Desirable Limit
Permissible
Limit Sector2
Village
Mujheri Sec.71
1 Colour Hazen 5 15 <5 <5 <5
2 Odour - Agreeable Agreeable Agreeable Agreeable Agreeable
3 Taste - Agreeable Agreeable Agreeable Agreeable Agreeable
4 Turbidity NTU 1 5 <1 <1 <1
5 pH - 6.5-8.5
No
Relaxation 7.47 7.51 7.36
6 Total Hardness (as CaCO3) mg/l 200 600 318 340 274
7 Iron (as Fe) mg/l 0.3
No
Relaxation 0.07 0.11 0.08
8 Chlorides (as Cl) mg/l 250 1000 302 370 340
9 Fluoride (as F ) mg/l 1 1.5 0.6 0.7 0.6
10 TDS mg/l 500 2000 996 1225 1132
11 Calcium(as Ca2+) mg/l 75 200 60 67 58
12 Magnesium (as Mg2+) mg/l 30 100 40 41 31
13 Copper (as Cu) mg/l 0.05 1.5 <0.01 <0.01 <0.01
14 Manganese(as Mn) mg/l 0.1 0.3 0.04 0.05 0.06
15 Sulphate (as SO4) mg/l 200 400 64 72 70
Table 3.8 (b) Ground water quality in study area during April 2013
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 60
16 Nitrate(as NO3) mg/l 45
No
Relaxation 8 7 10
17
Phenolic Compounds (as
C6H5OH) mg/l 0.001 0.002 <0.001 <0.001 <0.001
18 Mercury (as Hg) mg/l 0.001
No
Relaxation <0.001 <0.001 <0.001
19 Cadmium (as Cd) mg/l 0.003
No
Relaxation <0.01 <0.01 <0.01
20 Selenium ( as Se ) mg/l 0.01
No
Relaxation <0.01 <0.01 <0.01
21 Arsenic (as As) mg/l 0.01 0.05 <0.01 <0.01 <0.01
22 Cyanide (as CN ) mg/l 0.05
No
Relaxation <0.01 <0.01 <0.01
23 Lead (as Pb) mg/l 0.01
No
Relaxation <0.01 <0.01 <0.01
24 Zinc (as Zn) mg/l 5 15 0.09 0.13 0.14
25
Anionic Detergent (as
MBAS) mg/l 0.2 1 <0.01 <0.01 <0.01
26 Chromium (as Cr6+) mg/l 0.05
No
Relaxation <0.01 <0.01 <0.01
27 Mineral oil mg/l 0.5
No
Relaxation <0.01 <0.01 <0.01
28 Alkalinity (as CaCO3) mg/l 200 600 288 355 332
29 Aluminum (as Al) mg/l 0.03 0.2 <0.02 <0.02 <0.02
30 Boron (as B) mg/l 0.5 1 0.3 0.2 0.3
Microbiological Parameter
1 Total Coliform MPN/100ml 10 , Max - ND(<2) ND(<2) ND(<2)
2 E.coli
E.coli
/100ml Absent - Absent Absent Absent
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 61
Table 3.8 (c) Ground water quality in study area during May 2013
Royal Heritage vill.-Mujheri Sec.70 Faridabad Haryana
Ground Water Quality
May13
Parameter Unit
Limit (as per
IS:10500:2012) GW 1 GW 2 GW 3
Desirable
Limit
Permissible
Limit Sector2
Village
Mujheri Sec.71
Colour Hazen 5 15 <5 <5 <5
Odour - Agreeable Agreeable Agreeable Agreeable Agreeable
Taste - Agreeable Agreeable Agreeable Agreeable Agreeable
Turbidity NTU 1 5 <1 <1 <1
pH - 6.5-8.5
No
Relaxation 7.56 7.58 7.32
Total Hardness (as CaCO3) mg/l 200 600 326 350 296
Iron (as Fe) mg/l 0.3
No
Relaxation 0.10 0.13 0.11
Chlorides (as Cl) mg/l 250 1000 324 362 352
Fluoride (as F ) mg/l 1 1.5 0.7 0.7 0.6
TDS mg/l 500 2000 1042 1218 1124
Calcium(as Ca2+) mg/l 75 200 62 65 55
Magnesium (as Mg2+) mg/l 30 100 41 45 38
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 62
Copper (as Cu) mg/l 0.05 1.5 <0.01 <0.01 <0.01
Manganese(as Mn) mg/l 0.1 0.3 0.05 0.04 0.05
Sulphate (as SO4) mg/l 200 400 60 75 70
Nitrate(as NO3) mg/l 45
No
Relaxation 6 6 9
Phenolic Compounds (as
C6H5OH) mg/l 0.001 0.002 <0.001 <0.001 <0.001
Mercury (as Hg) mg/l 0.001
No
Relaxation <0.001 <0.001 <0.001
Cadmium (as Cd) mg/l 0.003
No
Relaxation <0.01 <0.01 <0.01
Selenium ( as Se ) mg/l 0.01
No
Relaxation <0.01 <0.01 <0.01
Arsenic (as As) mg/l 0.01 0.05 <0.01 <0.01 <0.01
Cyanide (as CN ) mg/l 0.05
No
Relaxation <0.01 <0.01 <0.01
Lead (as Pb) mg/l 0.01
No
Relaxation <0.01 <0.01 <0.01
Zinc (as Zn) mg/l 5 15 0.11 0.14 0.12
Anionic Detergent (as
MBAS) mg/l 0.2 1 <0.01 <0.01 <0.01
Chromium (as Cr6+) mg/l 0.05
No
Relaxation <0.01 <0.01 <0.01
Mineral oil mg/l 0.5
No
Relaxation <0.01 <0.01 <0.01
Alkalinity (as CaCO3) mg/l 200 600 298 370 314
Aluminum (as Al) mg/l 0.03 0.2 <0.02 <0.02 <0.02
Boron (as B) mg/l 0.5 1 0.2 0.3 0.2
Microbiological Parameter
Total Coliform MPN/100ml 10 , Max - ND(<2) ND(<2) ND(<2)
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 63
E.coli
E.coli
/100ml Absent - Absent Absent Absent
pH has found to be in the range of 6.5 to 8.5 in ground water samples
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 63
Rainwater Harvesting:
It has been planned to provide recharge pits within the project premises. Rain water will be
harvested from roof tops and surface areas. The rain water harvesting scheme is given below:
Figure 9 : Rainwater Harvesting Scheme
It has become necessary to harvest the rain water as maximum as possible. The drainage system needs
to be planned with a view to incorporate rainwater harvesting principles.
a) System that collect direct roof runoff for storage and then reusing for various purposes.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 64
b) Systems that use in-field or adjoining surface catchments to collect run-off and then impounded
for irrigation, horticultural, recreational and domestic purposes, after treatment.
c) Systems that utilize the rainwater run-off from various surfaces including Terrace and Roads and
green areas etc. for re-charging of the underground aquifer, through various measures.
In this system, the catchment from roof/terrace areas is further segregated for direct
recharging of aquifer through filter media.
The catchments from surfaces of road/paved/park/lawns etc. is segregated and then taken
to underground, through de-silting chamber/oil and grease separator etc.
3.4.5 LAND ENVIRONMENT
Land is the most vital resource for sustenance of life and degradations of land due to
industrialization, urbanization and population growth is a matter of concern. Therefore, it is
necessary to establish the existing land use pattern to optimize the land use as well as minimize
degradation due to the developmental activities. Also it is necessary to the landform of the
project site and the quality of the soil as soil erosion further deteriorates the quality of the land.
Soil erosion can be prevented by following methods:
Planting vegetation which stabilizes the soil and prevent erosion.
Applying a layer of mulch to the soil top which stabilize the soil as well as to reduce he
storm water runoff.
Using Geo textiles which help in stabilizing soil.
3.4.5.1 Topography
The landform of the project site is a plain land with average elevation of about 99.5 m-100 m.
The land environment is described by land use / land cover of the study area within 10 km
radius and soil environment of the study area within 5 km radius.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 65
Natural Drainage:
There are two major rivers near the project site i.e. Yamuna River. River Yamuna lies within the study
area at a distance of approx. 11.33 E. The drainage map of the study area is attached as Annexure – VII
(d).
3.4.5.2 Land Use Description
The land use / land cover of the project site was done to identify the land use pattern and land cover
pattern of the study area. The study of land use in the area enables one to know about the land that
can be used for various development activities envisaged in post project scenario. It also enables to
envisage the scenario emerging due to the increase in demand for land with increase in population
and the impacts arising due to the interface with the various project activities.
Objectives of the Study
The objectives of the present study are:
To map the study area with respect to various land use/land cover change over the past 10 years.
To identify the sensitive areas within 10 km radius around the project site.
Methodology
The land use / land cover pattern has been established based on the analysis of the data received from
satellite imagery by making land use/land cover map with the help of GIS technique. References have
been taken from Survey of India. Also the data based on Census of India, 2001 was referred and land
use study was done within 10 km radius area with limited ground truth verifications. Ground and
ancillary information have been used to identify the sensitive places within 10 km radius of the project.
Land Use Pattern Classification and description
The classification of land use / land cover pattern of the study area is mainly dominated by the types -
agricultural land, water bodies, canals, settlements or cultural use, and etc. The agricultural land covers
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 66
the majority of the land which is about 71.48 % of the study area. The land use data are presented in
Table 3.9 and also highlighted with a pie chart at Figure 3.2. The Land use map is enclosed as
Annexure VII (e).
Table 3.9: Land use pattern of project area within 500 mtrs
LAND USE CLASS AREA (Ha)
Water bodies 60.23
Settlement 7448.62
Vegetation 216.35
Open Scrub 772.86
Open Land 846.72
Agriculture 23591.6
Forest 65.78
TOTAL 33001.62
Figure 10: Land Use Pattern of the Project Site within 10 Km
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 67
Topography:
Slope form: Contour plan shown that land is flat land with highest RL 100 m and Lowest RL
99.5 m. Project will not cause any change in natural slope.
Landform and Terrain analysis: According to the study of 10 km radius around the project in
topographical map of scale 1:50000, it was found that 71.48 % is Agriculture, 22.57 % is settlement,
2.34 % is Open Scrub, 0.65 % area is Vegetation, 2.56 % is Open land, 0.18 % is Water bodies &
0.199% forests Complete details are given in figure 3.3 above.
Soil:
Soil formation is influenced mainly by climate, geology, relief and other biotic interactions. To
assess the soil quality of the proposed area, following stations were selected. Soil profile and
quality was studied at 5 different locations.
The composite soil samples were collected from different location and were analyzed for
characterization. The locations of the monitoring sites are depicted in Table 3.10 (a) and the
results of the monitoring and analysis is presented in the Table 3.10 (c) and is attached as
Annexure VII (f).
Table 3.10(a): Soil Sample Collection Points
Location No. Sample collected from Direction Distance (Km)
SQ- 1 Project Site ___ ___
SQ- 2 Village Mujheri E 0.4 km
SQ- 3 Sector 71 ENE 1.1 km
SQ- 4 Sector 68 SE 1.9 km
SQ-5 Sector 2 WSW 1.2 km
3.4.5 Methodology
The soil samples were collected in the month of April 2013 from 5 locations as given in
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 68
above Table. At each of these locations 3 sub-locations were identified randomly from where
soil was collected from up to 30 cm below the surface. The final 5 samples represent
homogenously mixed soil from these 3 sub-locations for each location. The samples were
filled in polythene bags, labeled in the field with number and site name and sent to laboratory
for analysis. Table 3.10(b) gives the idea of the frequency and methodology of selection of
soil sampling stations and monitoring process.
Table 3.10 (b) Frequency and Methodology for Soil Sampling & Monitoring:
Particulars Details
Frequency Once during the Study Period
Methodology Grab samples of the topsoil were collected from 3 depths, at particular locations
and all samples are mixed to provide a representative sample for analysis. They
were stored in airtight. Polythene Bags and analyzed at the laboratory.
*Grab sample- a single sample or measurement taken at a specific time or over as a short period as
feasible.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 69
Table 3.10 (c): Soil Quality Data
Royal Heritage Vill-Mujheri Faridabad Sec-70 Haryana
Soil Quality Data April 2013
Project Site Vill.Mujheri Sec-71 Sec-68 Sec-2
S.No Parameter Unit SQ-1 SQ-2 SQ-3 SQ-4 SQ-5
1
Texture - Sandy Loam Loam Sandy Loam Sandy Clay Loam Sandy Loam
Sand % 68.6 51.3 60.3 56.9 64.5
Silt % 16.5 24.1 21.1 22.5 18.4
clay % 14.9 24.6 18.6 20.6 17.1
2 pH (1:2) - 7.86 8.06 7.68 8.12 7.86
3 Electrical Conductivity (1:2) µmhos/cm 254 523 371 438 387
4 Cation exchange capacity meq/100 gm 12.6 16.2 13.3 14.9 14.3
5 Exchangeable Potassium meq/100 gm 0.28 0.38 0.29 0.31 0.26
6 Exchangeable Sodium meq/100 gm 0.58 0.76 0.61 0.64 0.71
7 Exchangeable Calcium meq/100 gm 8.6 10.5 8.8 10.1 9.2
8 Exchangeable Magnesium meq/100 gm 3.1 4.6 3.6 3.8 4.1
9 Sodium Absorption Ratio - 0.76 0.87 0.77 0.77 0.87
10 Water Holding Capacity % 24.1 29.8 26.4 27.8 25.2
11 Porosity % 40.3 35.2 38.1 37.9 39.4
12 Permeability cm/hrs 2.3 1.7 2.0 2.1 2.2
13 Total kjehdahl Nitrogen % 0.024 0.046 0.034 0.041 0.032
14 Phosphorus(Olsen’s) mg/kg 5.3 8.3 6.5 7.4 5.8
15 Organic Matter % 0.28 0.35 0.31 0.34 0.30
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 70
Result:
Results are summarized in Table 3.10 (c); the result shows that texture of the core is Sandy Loam. The
results of buffer zone show that texture is sandy loam. pH ranges from 7.68– 8.12.
3.4.6 Biological Environment
3.4.6.1 Biological Environment
Literally environment stands for the totality of surrounding conditions. Animals and plants form
a vital part of this sum total. Flora and fauna of an area are inter-related to each other and have a
very crucial impact on human life. With changes in environmental conditions, structure, density
and composition of plants and animals undergo changes as well. The present study was carried
out in two separate headings for floral and faunal community. The aspects to be covered in the
study for the project are given in Table 3.11.
Table 3.11: Aspects to be covered in the study for the Project
Aspect of Environment Likely Impacts
A. Terrestrial Ecology Impacts on terrestrial flora and fauna
Impacts on wildlife
Impacts on socially/economically/genetically/
biologically important project species
B. Aquatic Ecology Impacts on aquatic fauna/flora
The relevant environmental impacts out of the entire gamut of issues outlined in the Table 3.15
were identified. For these impacts or aspects, environmental baseline data has been
collected from primary as well as secondary data sources. As a part of the study, detailed
field studies on various aspects were conducted. The baseline status has been ascertained for the
following aspects:
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 71
3.4.6.2 Biological Environment: Terrestrial Ecology/Aquatic Ecology
The information presented in this Chapter has been collected through field studies,
consultation with various government departments and collation of available literature
with various institutions and organizations. The summary of data collected from various sources
as a part of the EIA study is outlined in Table 3.12.
Table 3.12: Summary of data collected from various sources
Aspect Mode of data
collection
Parameters
monitored
Frequency Source(s)
Terrestrial
Ecology
Primary secondary and
field survey
Floral and Faunal
Inventory/
Importance
One
Season
(Summer)
Field studies,
Forest
Department and
literature review
Aquatic Ecology Primary and secondary Presence of
various
species/Importance
One
Season
(Summer)
Field studies,
Forest
Department and
literature review
A. Floral Community:
The study area was divided into two zones as given below;
i) Core Zone: within the project area.
ii) Buffer Zone: (A) 100 m radius around the project site.
(B) 10 km radius around the project site.
General Vegetation Pattern:
The prevailing vegetation cover over the area is mainly of tropical dry deciduous forest as per
the Champion and Seth (1968) “Classification of forest type of India”.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 72
i) Core Zone: There was no vegetation within the core zone. Only a few species of
Parthenium, Acacia nilotica and Cynodon dactylon were seen.
ii) Buffer Zone:
In 100 m radius around the project area:
The list of plants recorded in Buffer Zone (100 m Radius) is given in Table 3.15(a).The vegetative
community of the area is mainly under open scrub forest and because of urbanization area is usually
surrounded with planted varieties. The dominant species are Japanese maples (Acer palmatum),
Trident maples (Acer buergerianum), neem (Azadarachta indica), Gulmohar (Delonix regia.), Safeda
(Eucalyptus), Carrot grass (Parthenium sp.), etc. The prominent grass is Cynodon dactylon.
No threatened, rare, endangered or endemic species were observed during the survey in this
Buffer Zone (100m radius around the project area).
Table 3.13(a): List of Plants in Buffer Zone (100 m Radius)
S. No. Local Names Botanical Names
1. Neem Azadirachta indica
2. Safeda Eucalyptus
3. Dhatura Datura sp.
4. Amaltas Cassia fistula
5. Carrot grass Parthenium sp.
6. Gulmohar Delonix regia
7. Japanese maples Acer palmatum
8. Trident maples Acer buergerianum
In 10 km radius around the project site:
The list of plants recorded in Buffer Zone (10 km Radius) is given in Table 3.15(b). There is no
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 73
protected forest area in this zone. The vegetative community of the area is mainly under open scrub
forest and because of urbanization area is usually surrounded with planted varieties. The dominant
species are Neem (Azadirachta indica), Gulmohar (Delonix regia sp.), Safeda (Eucalyptus), Carrot
grass (Parthenium sp.), Amaltas (Cassia fistula), Dhatura (Datura sp.), Arandi (Ricinus communis),
Bougainvellia, Peepal (Ficus religiosa), shisham (Dalbergia sissoo), bottle blush (Callistemon
lanceolatus), etc. The prominent grass species is Cynodon dactylon.
Table 3.13(b): List of Plants in Buffer Zone (10 Km Radius)
S. No. Local Names Botanical Names
1. Neem Azadirachta indica
2. Safeda Eucalyptus
3. Dhatura Datura sp.
4. Arandi Ricinus communis
5. Peepal Ficus religiosa
6. Bougainvelia Bougainvelli
7. Bottle palm Beaucarnea recurvata
8. Amaltas Cassia fistula
9. Shisham Dalbergia sissoo
10. Bottle brush Callistemon lanceolatus
11. Carrot grass Parthenium sp.
12. Gulmohar Delonix regia
13. Oak Quercus sp
14. Japanese maples Acer palmatum
15. Trident maples Acer buergerianum
Agricultural land
The Irrigation facility is proper in the study area, thus chana , sarson, ragi, jowar and maize
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 74
are the main crops grown in the area. Other crops, which are grown, are Moong, Cajanus, Til,
etc. Where watering facility is available seasonal vegetables are also grown.
Waste land
Wasteland is commonly seen in the area, and is mostly covered with species like Lantana
spp, Ipomea spp, Calotropis procera, Cassia tora, Parthenium spp., Zizyphus spp., Argemone
spp. etc.
Grassland
Grassland in the study area is secondary in origin. The common species found
in the area are Euphorbia spp. Desmodium spp., Cynodon dactylon, Cyperus spp.,
Ipomoea spp. etc.
Vegetation in and around human settlement
Near villages the vegetation pattern changes from rest of the area. The common species
grown near villages are Mangifera indica, Madhuca indica, Sizygium cumini, Bambusa sp.,
Azadirachta indica, Delonix regia, Tamarinds indica, Eucalyptus spp. Ficus religiosa, etc.
Avenue trees and projection
The roadside along in the study area are projected with trees in single to double
rows. The common trees are Azadirachta indica, Syzigium cumini. Mangifera indica,
Delonix regia, Cassia fistula, Eucalyptus spp., Saraca asoca etc.
Agricultural crops
Land at some places is used for agriculture purpose. The main crops are maize, bajra,
Chana, Sarson, jowar, ragi, and vegetables. No threatened, rare, endangered or endemic
species were observed during the survey in Buffer Zone (10 km radius around the project
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 75
area).
B. Faunal Community:
A general faunal study was carried out for the core zone and buffer zone separately as given
below;
(i) Core Zone: There was no unique faunal community within the core zone of the project site
(ii) Buffer Zone:
In 100 m radius around the project site:
The species observed in Buffer zone (100 m around the project area) are given in Table 3.13(c).
No threatened, rare, endangered or endemic species were observed during the survey in Buffer
Zone (100 m radius around the project site).
Table 3.13(c): List of Species in Buffer Zone (100 m Radius)
Sl. No. Local Names Zoological Names
Amphibians
1. Toad Bufo sp
2. Frog Rana tigrina
Reptiles
3. Indian garden lizards Calotes versicolor
4. house lizards Hemidactylus sp.
Mammals
5. Indian palm squirrel Fumambulus pennanti
6. Cat Felis sp.
7. Dog Cuon sp
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 76
Sl. No. Local Names Zoological Names
8. Cow Bos sp.
9. Rat Rattus rattus
Aves
10. Crow Corves splendens
11. Sparrow Passer domesticus
12. Baya Ploceus philippinus
13. Parrot Psittacula krameri
In 10 km radius around the project area list of species observed in this buffer zone is given in
Table 3.13(d).
Table 3.13(d): List of Species in Buffer Zone (10 Km Radius)
S.No. Local Names Zoological Names
Amphibians
1. Toad Bufo sp.
2. Frog Rana tigrina
Reptiles
3. Indian garden lizards Calotes versicolor
4. House lizards Hemidactylus sp.
Mammals
5. Indian palm squirrel Fumambulus pennanti
6. Cat Felis sp.
7. Dog Cuon sp.
8. Cow Bos sp.
9. Horse Equs sp.
10. Rat Rattus rattus
Aves
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 77
S.No. Local Names Zoological Names
11. Crow Corves splendens
12. Sparrow Passer domesticus
13. Baya Ploceus philippinus
14. Parrot Psittacula krameri
15. Peafowl Pavo cristatus
16. Pigeon Columba livia
17. Egretta Egretta sp
18. Myna Acridotheres tristis
C. Protected Areas
There are no, Wildlife Sanctuary, National Park and/ or Biosphere Reserve within 10 km of the
study area.
D. Wild life and avifauna
Detailed survey was conducted to evaluate faunal composition of the study area (core and buffer
zone) within the project area. Primary data like faunal composition was recorded during site visit and
secondary data was collected from the Forest department to get the correct picture of the study area.
The major portion of the study consists of agricultural field and human settlements which support
wildlife habitat insignificantly.
The survey methods used for faunal assessment are:
The major part of the study area lies under agriculture field and human settlements which restricted
the wildlife habitat significantly. Most of the mammalian species reported in the study area are
common fox, and Indian hare. There is neither any wildlife sensitive area nor any corridor for the
movement of wildlife present in the study area. There are many small ponds present in the buffer
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 78
zone of study area which are the major attraction sites for avifauna. Common Maina, Kingfisher,
Spotted dove, Pintail and Pond Heron are some dominant bird species present in the study area.
There is no information regarding migratory movement of birds in the study area. As far as the
reptiles community was concerned, Krait and house lizard are reported from the study area.
Methodology
3.8.3 Aquatic life
The Phytoplankton in the lakes is basically dominated by filamentous forms. The dominant ones
are Chaetophora sp., Cladophora sp., Spirogyra sp. The Zooplanktons are basically dominated by
Crustaceans and Rotifers.
3.5 SOCIO ECONOMIC IMPACTASSESSMENT
3.5.1 Background
Background
i) In this part of the EIA report an attempt has been made to assess the Socio-Economic Impact
of the Group housing project at village Mujheri, sector 70, Faridabad, Haryana developed by
M/s. Pivotal Infrastructure Pvt. Ltd, Registered office at 309, 3rd
floor ,JMD Pacific Square
,sector 15 , Part II , Gurgaon , Haryana.
Socio-economic impact assessment of the study area of a project is pre requisite before the project is put
into implementation. The study area consists of the core area where the project is expected to come up
and a buffer area encircling the core area with a radius of certain distance from the periphery of the core
area. In the present township project the study area consists of core area and the buffer area encircling
the core area with a distance of two kilometers from the periphery of the core area. Socio-economic
impact assessment has been made mandatory by the Government of India and the same is applicable to
all types of venture namely real-estate development; construction of power plants, refineries, roadways,
railways, shipyards, airports, large industrial undertakings, Export Promotion Zones (EPZ), Special
Economic Zones (SEZ), mining of mineral ores; land filling etc. Socio-economic impact assessment is
a technique to get acquainted with social, cultural and economic conditions of stakeholders, which
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 79
includes individuals, groups, communities and organizations. The above assessment is made through a
socio-economic survey conducted by a team of experts that often consist of a demographer, statistician,
econometrician, social scientist, health expert and gender specialist. The scope of the socio-economic
study is as under.
a. To assess the prevailing socio-economic conditions in the study area
b. To analyze the possible impact of the project on the prevailing socio-economic environment
in the study area.
c. To analyze awareness and perception of the people about the project.
d. To suggest steps to annul the adverse effects of the project on the people in the area.
Besides the above base line data is collected from primary and secondary sources so that post
construction evaluation and impact assessment could be undertaken more effectively in order to obtain
realistic outcome.
The findings of the study are very crucial to the authority granting environment and other clearances to a
particular project, as it provides valuable information to them for arriving at a decision.
3.5.2 Approach & Methodology
A mixture of both quantitative and qualitative approach was adopted in the current socio-economic
study. Since the qualitative information is hypothetical in nature and cannot be analyzed directly they
were converted into numerical facts prior to data analysis. The study was conducted based on primary
and secondary data. The primary data was collected by organizing field survey. The questionnaires
formulated for collection of primary data contained both open and close ended questions. While primary
data was collected through a sample survey of selected households, the secondary data was collected
from the administrative records and published literatures.
3.5.3 Sample Survey of Households
Study Area
For all township projects the study area, also known as impact area has been defined as the sum total of
core and buffer area with a radius of two kilometers from the periphery of the project site. The study
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 80
area includes all the land marks both natural and manmade, falling therein. The entire study area of the
Group housing Project is falling in Faridabad, Sub-district and district, Haryana covering 2 villages
namely, Chandauli and Mujheri. The urban area covered is mainly Ballabhgarh. The Group housing
Project is located at Village- Mujheri , Faridabad, Haryana. In small patches of land vegetables grow in
abundance. The study area is the home of many IT and software companies. There is however
manufacturing unit at both the villages ,Mujheri and Chandauli for Electrical Goods. The entire study
area is fast getting urbanized
Sample Design
Two stage sampling design was adopted in the above study. The first stage units are localities in the
study area and the ultimate stage units are households in the selected localities.
3.5.4 Sampling unit
The households in selected localities are the ultimate sampling units. Primary data was collected from
the sample households through face to face interviews.
3.5.5 Respondents
The head of the selected household was treated as respondent for collection of information through face
to face interview. The respondents were of either sex. Further, it was ensured that he/she must be an
adult member of the selected household. However, where the head of the household was not present at
his/her dwelling unit or refused to participate in the interview, one of the remaining adult members of
the household ready to provide the information through face to face interview was treated as respondent.
3.5.6 Reference period
The reference period for the survey was last 365 days from the date of survey.
3.5.7 Selection of localities and number of households selected
For collection of information through household survey two villages were selected namely Mujheri is
located close to project site and Chandauli with the Urban area of Ballabhgarh located at the outer
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 81
periphery of the buffer area. These localities were selected from a list frame prepared in-house by GRC
India (P) Ltd. Due to non- availability of auxiliary information in the list frame these localities were
selected randomly. Number of households (ultimate stage units) selected in each village were 6
respectively.
3.5.8 Questionnaire
For collection of information GRC developed two structured questionnaire – (1) Village questionnaire
and (2) Household questionnaire. Both the questionnaires are divided into several blocks. Besides
identification particulars, the Household questionnaire had provision for collecting information on
following aspects:
(i) House structure
(ii) Socio-economic profile of the household
(iii) Details regarding BPL families
(iv) Household assets.
(v) Details of household members.
(vi) Availability of potable water and sanitation facilities
(vii) Storm water and solid waste/ garbage disposal facilities
(viii) Details about personal and hygiene facilities
(ix) Awareness level of the household regarding upcoming township project
(x) Respondent’s perception about the project.
The Village questionnaire carried questions on demographic particulars of the locality, infrastructure
and other facilities available in the area.
3.5.9 Conduct of field work
Immediately, after the completion of a short briefing the field work was taken up and the same was
completed in a week’s time. The team members visited each selected village and collected data from the
randomly selected households. In case of non-responses due to house-locked, household refused to
provide information or household shifted outside the locality alternate households were approached for
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 82
collection of information.
3.5.10 Findings of the survey
Demographic particulars of the study area based on decadal growth rate
As the entire study area has got completely urbanized an attempt has been made to estimate the
population of the study area by using the Census 2001. Accordingly, the estimated population of the
study area for has been worked out to 1,93,562 based on Census 2001.
Of the total population 34,783 (18 percent) belong to 0-6 age group. Again of this 18,923 (54 percent)
are male and the remaining 15,860 (46 percent) are female. The sex ratio of overall population of the
study area has been worked out to 852 females per 1000 males, which is slightly more than the district
average of 851 females per 1000 males and much less than the state average of 908 for utter Pradesh and
national average (provisional) of 940 females per 1000 males. The sex ratio of 0-6 age group has been
worked out to 838 females per 1000 males.
It has been estimated that 1,03,929 (54 percent) of the total population of the study area are literate. Of
this, 68,475 (66 percent) are males and the remaining 35,454 (34 percent) are females. The overall
literacy rate in the study area has been worked out to 65 percent. The literacy rate of male population is
around 80 percent and that of female is 48 percent, creating a gender gap of 31.6 percent.
A worker has been defined as a person who participates in a productive activity with or without
compensation, wages or profit and such participation may be physical and/or mental in nature. The field
survey has revealed that 79,967 (41 percent) the total population is gainfully employed. While male
workers constitute 63 percent of the total work force, the share of female workers is only 37 percent.
In the study area the workers engaged in various activities can be classified into agricultural workers,
industrial workers and other workers. Those who are engaged in ‘agriculture’ can be classified further as
cultivators and land less labour. In the study area the total number of workers engaged in ‘agriculture’ is
41,229 which is 22 percent of the total population. Of the total number of workers engaged in
agriculture nearly 68 percent are cultivators who own land and the remaining 32 percent are land less
agricultural labour who works in the farm owned by others. Further, 2 percent of the total workers in the
study area are engaged in household industries. The field survey has revealed that most of these
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 83
industrial units are Own Account Enterprises (OAE) with no hired worker.
Furthermore, about 78 percent of the total workers fall in the category of ‘other workers’. They are
mostly white collar workers, workers engaged in large scale industries, traders and petty shop owners,
etc.
3.5.11 Dwellings
Earlier, most of the dwelling units in the study area were Kachcha or semi-pucca houses. Due to rapid
urbanisation these kachcha /semi-pucca houses have replaced by palatial buildings, multi-storeyed flats,
residential houses, commercial buildings & offices, shopping malls etc. The Greater Noida authority is
giving much attention to promotion of green buildings that ensures economic use of energy and
conservation of water.
3.5.12 Amenities
Education Facilities
The area is rich in institutional education facilities. There are all types of schools including global
schools for education. Also there are colleges and universities and other institutions for higher
education. The Aryavir Bhalla Dev Public School is located at a distance of approximately 7.25 Km
NNW from the project site .
Medical Facilities
The study area is dotted with institutional medical facility. Most of them are private hospitals, clinics
and nursing homes. Most of the medical institutions operate 24x7 and many are of world class standard.
The Noble Hospital is located at a distance of 6.62 km in the NNW direction from the project site and
Fortis Escorts Hospital 7.40 km NNW from the project site.
3.5.13 Drinking water facilities
In the study area the main source of drinking water is tap water. In high rise buildings water is drawn
with the help of power full motors and submersible pumps. In multistoried buildings there are water
storages in which water is stored during fixed hours of the day and the same is available to the dwellers
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 84
all throughout the day. The area faces water shortage during dry season when water supply gets erratic.
The local government is emphasizing on setting up of rainwater harvesting structures for storing and
recharging of groundwater.
3.5.14 Supply of Electricity
All the settlements in the study area have been fully electrified. Power supply is available for all types of
uses namely domestic, agriculture and industrial. People in the study area consume power mostly for
domestic, commercial and industrial uses. Due to rapid urbanization the demand for power for
agricultural uses is fast declining. The demand for power is ever increasing due to increase in
population, trade and industries.
3.5.15 Transport and Communication
The Group Housing Project has been planned to be set up close to NH-2, which is approx. 3.5 km away
from project site towards West direction. The area is well connected by roads. The nearest railway
station is Ballabhgarh railway station.
3.5.16 Banking facilities
The study area is well served by banks and other financial institutions. Most of the commercial banks
including nationalized and private banks have opened their branches in the study area.
Impact of the project on existing land use
3.5.17 Impact on existing land use
As per Faridabad Master plan 2031 the project site is located in the land earmarked for residential
purposes. Accordingly, no change in the land use pattern is envisaged. It is anticipated that the
construction activities of the project will not have any adverse effect on the land use pattern of the study
area.
3.5.18 Acceleration in Urbanization
The project site is located near village Mujheri, in Faridabad , Haryana. It now forms part of the
Faridabad Municipal Authority. This indicates that urbanization of the area, where the residential
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 85
township is located has already started. It is expected that the project will further accelerate the ongoing
urbanization of the area.
The urbanization of the area is the positive impact of the residential Project. However, this has to be
undertaken more cautiously as it may cause negative impact on the socio-economic aspect of people
living in the area due to stress and strain on civic amenities. It is therefore suggested that for smooth
development of the area long term planning should be adopted and there should be adequate budgetary
provision for the purpose.
3.5.19 Availability of Residential Accommodation
The up-coming residential township has been planned to provide residential accommodation to
7847persons. Besides the above the project will also provide accommodation to about 785 visitors. This
is a positive impact of the project as it gives solution to housing problem to some extent.
3.5.20 Development of Slums
During the construction period the project may give birth to slums dwelt by the construction workers. It
may be ensured that growth of slums must be discouraged and people living in the slums may be shifted
as and when the construction of the residential township is over. It would be appropriate if separate
dwelling units are constructed for EWS.
3.5.21 Impact on population composition
Consequent to development of the above residential project there will be an increase in the overall
population of the study area. The increase in population will take place during the construction period as
well as during post construction period when large number of families will shift to the above township.
This will change the existing sex ratio of the study area. The increase in population during construction
period will be marginal and temporary.
3.5.22 Impact on Employment opportunities
The residential project will provide employment opportunities to the local people in terms of labor
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 86
during construction period. The number will vary according to pace of progress of construction and it
will vary between 50 and 300. During the operation period as many as 30 people will get direct
employment as staff of the Resident’s Association for maintenance and up-keeping of the entire
premises. They include service personnel namely guards, security personnel, gardeners, electricians,
plumber, sweepers, lift men etc. Besides the above the project will provide employment opportunities
to about 100 persons in the informal sector. These job opportunities will be for those who want to work
as delivery boys, washer men, maid servants, cooks, baby keepers, drivers, cleaners, vendors etc. There
is no dearth of skilled and unskilled manpower in Faridabad and its adjoining areas. Hence, it is
expected that all the employment opportunities will be made available to the local people. . Creation of
employment opportunities is a positive impact of the project on socio-economic aspects of people living
in the neighborhoods.
3.5.23 Impetus to Infrastructure development
The residential project will pave the way for various infrastructure developments that includes roads,
parks, play grounds, bus shelters etc. This is a positive impact, which will create further employment
opportunities for the local people.
3.5.24 Impact on Health facilities
The availability of cheap health facility in the study area is inadequate as there is no government health
facility for the workers in the area. For any medical assistance the local people are required to visit the
private hospitals or dispensaries or rush to district hospital. Hence, there is a dire need for augmentation
of cheap and efficient health services in the study area. The residential township project, when in
operation will increase the population of the area as also the need for institutional health facilities. It is
therefore suggested that a health center may be set up in the neighborhood of the residential township
project especially for the people working in the informal sector.
3.5.25 Awareness of the Project and people perception
The sample survey has revealed that 90 percent of the households living in the study area are un-aware
of the proposed residential town ship project as no construction activity has yet started. Only six percent
reported that they have heard about the project from their neighbors and friends. The remaining four
percent did not make any comment on it. Most of the people interviewed during the field survey
supported the project with the hope that it will create employment opportunities for the local people as
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 3
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 87
also provide permanent residential accommodation to those who are living in rented houses.
3.5.26 Corporate Social Responsibility
Corporate social responsibility (CSR) refers to responsibility of a company to ensure positive impact on
environment, consumers, employees, communities, stakeholders and all other members of the public
sphere. It is mandatory for all project proponents to undertake various socio-economic activities under
Corporate Social Responsibility (CSR), while executing development projects. M/s. Pivotal
Infrastructure Pvt. Ltd is expected to make contributions to society through social investment. The thrust
areas should be education, health, infrastructure, livelihood and plantation. These activities should be
identified based on the need based survey conducted by GRC India (P). It is ensured that the activities
selected for development are based on community needs and not individual needs. The activities
proposed to be undertaken are indicated below:
1. Bus shelter
2. Skill development for EWS.
3. Medical Facilities
4. Educational Assistance to girl child belongs to EWS.
5. Regular garbage clearance
6. Awareness programs on female education, HIV/AIDS etc.
3.5.27 Conclusion
The project does not call for any land acquisition and no change in the existing land use pattern. The
execution of the project will not disturb the people living in the area as there will be no blasting and
large scale digging. The project will generate employment opportunities for both skilled and unskilled
workers in the vicinity, which will produce multiple effects on the life and economy of the local people.
Thus from socio-economic point of view the project is beneficial to the people and can be executed with
no hesitation.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 89
CHAPTER-4
ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES
4.1 INTRODUCTION
This chapter discusses identification and appraisal of various environmental impacts due to the
“Royal Heritage” Revision & Expansion of Group Housing Project. Generally, the
environmental impacts can be categorized as either primary or secondary. The development,
construction and functional phase of the project comprise various activities, each of which may
have some impact on environmental parameter. Various impacts during the development,
construction and operation phase on the environmental parameters have been studied to estimate
the impact on environment.
“Royal Heritage” Revision & Expansion of Group Housing Project will be constructed and
developed gradually in the time span of 3 years (approx.). In development phase, basic
infrastructure facilities like internal road, sewerage system, storm water drainage, street lighting
etc. will be developed.
For proper evaluation and assessment of the environmental impacts due to development,
construction and functional phase of project understanding to the various activities associated
with the “Royal Heritage” Revision & Expansion of Group Housing Project is essential. Various
activities related to the project would be different, in terms of nature during the development,
construction and functional phase.
The impact identification and prediction process aims to:
Identify potential source or cause of impact through out the life of project.
Characterize the potential impacts affecting a target or receptor (physical, human and
socio-economic).
Assess the potential of changing likely-hood of impact through Environmental
Management Plan (EMP)
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 90
Prediction of the impacts due to the development, construction and functional activities
encompass the developmental processes to be undertaken during construction and
functional phases.
For each category of environmental receptor (such as, ambient air quality, water quality, soils,
land, etc,) the potential impacts of activities during development, construction and functional
phases have been identified. Pollution sources & its characteristics, the potential impacts and
magnitude of the impacts have been assessed and discussed in detail in following sub sections.
In each case, cognizance has been taken to mitigation measures inherited in the development &
construction and functional phase.
4.2 IMPACT MATRIX
Various activities from the “Royal Heritage” Revision & Expansion of Group Housing Project
are likely to have some impact on the environmental constituents during its construction as well
as operational phase. The impact assessment matrix given in Table 4.1 reveals the impact
associated with each activity of the project on various environmental parameters during
construction and function phase respectively before any mitigation measures are implemented.
To assess the severity of the impacts, they are categorized as follows:
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 91
Environmental
Parameters
Nature of Potential Impacts during Construction and Operation Phases
Local Regional Short
Term
Long
Term
Reversible Irreversible Adverse Beneficial No Impact Significant Insignificant
Topography
√ √ √ √
Drainage
√ √ √ √ √
Soil
√ √ √ √ √
Water
Resources
√ √ √ √ √
Water Quality
√ √ √ √ √
Land Use
√ √ √ √ √
Air Quality
√ √ √ √ √
Noise
√ √ √ √ √
Flora
√ √ √ √ √
Fauna
√ √ √ √ √
Employment
√ √ √ √ √
Aesthetic
√ √ √ √ √
Table 4.1: Impact Assessment Matrix of Project on environmental components
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 92
4.3 POLLUTION SOURCES
Pollutants generated in the “Royal Heritage” Revision & Expansion of Group Housing Project
during both the construction and functional phases are solid, liquid and gaseous in nature. Also
the generation of pollution could be continuous, periodic or accidental. Sources of pollutants and
their characteristics during the construction and functional phase are given below in Table 4.2.
Table 4.2: Pollutant Sources
SI. No. Activity /
Area Pollutant Sources Frequency
CONSTRUCTION PHASE
1. Site
preparation
and
construction
activities
Air emission-
SO2, & NO2.
Dust from
construction
activities and
excavation.
Particulates matter,
NO2 and CO from
vehicle exhaust
Temporary during
construction phase
only.
Bulk of the
emissions is
expected from
ground work and
leveling.
Earth/Solid waste
Solid waste from
construction
activity and
excavation.
Periodic.
Hazardous waste
generation such
as used oil and
paints.
From D.G. Sets and
painting of the
buildings.
Periodic and
temporary
Noise Noise generated
from construction
equipment and
machinery
Temporary lasting
the construction
phase.
2. Labour
Camps
Sullage Sullage generated
from temporary
labor camps on site.
Temporary-during
the initial
construction phase
Solid Waste Solid Waste
generated from
temporary labor
camps on site.
Temporary- during
the initial
construction phase
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 93
SI. No. Activity /
Area Pollutant Sources Frequency
OPERATIONAL PHASE
1. Vehicular
movement
Air emissions and
noise
Vehicle exhaust
emissions
Continuous/
periodic
2. Diesel
generators
Air emissions SO2, NO2, PM, CO
from fuel burning
Occasional- during
power failure
Noise Noise due to
running of
equipment
Occasional - during
power failure
Hazardous Waste Used Oil
Generation
Occasional- during
oil changes
3. Maintenance /
House-
keeping
Sullage Floor washing
Sewage
Continuous
Solid waste Residential,
Commercial and
garden wastes
Continuous
4. Vehicle
Parking
Oil spills Minor oil leaks
Parking space
Continuous
5. Storm water
drains
Rainwater Contamination
discharge from site-
mainly suspended
solids
During rainy
season
4.4 IMPACT IDENTIFICATION
The areas of environmental concerns for which the impacts and their predictions are taken
into consideration are mainly:
Air Environment
Water Environment
Noise Environment
Land Environment
Biological Environment
Socio economic Environment and
Aesthetics Environment
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 94
The impacts can be further categorized as positive impacts and negative impacts depending
upon their nature, potential and magnitude.
4.4.1 Environmental Aspects of Development & Construction Operations
Generation, storage and disposal of construction wastes;
Noise pollution due to plant, machinery, equipments and vehicle movement;
Air pollution due to plant, machinery, equipments and vehicle movement;
Generation and disposal of sullage;
Impact on ecology;
Consumption of resources such as water, electricity, and diesel.
Physical change in landscape due to earth work excavation and related activities.
Soil erosion caused due to loss of vegetation and other construction activities.
4.4.2 Environmental Aspects of Building Planning and Use
Impacts identified during operation of “Royal Heritage” Revision & Expansion of Group
Housing Project and their use includes major concerns such as:
Disposal of domestic (sewage) effluent generation
Disposal of solid wastes generated in the “Royal Heritage” Revision & Expansion of
Group Housing Project from house, commercial and horticulture
Increase in noise levels due to transport
Consumption of water and impact on water resources
Impact on traffic on the road
Storm water during rains
Management and maintenance project
Environmental aspects of the project are not just limited to impact of sources of pollution
but also relate to energy conservation, water conservation and other issues, which are
mentioned in Table 4.3.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 95
Table 4.3: Environment aspects of project other than source of Pollution
S.No. Area Aspect
I. Energy
conservation Solar Heating, Day Lighting, Design Natural Ventilation,
Thermal Transfer value of Building Material, Energy
Efficient Building Services and Equipment,
Public Area Lighting and
Exterior Lighting
II. Water
conservation Reuse of Recycled Water
Gardening Water sources
III. Internal Roads
and Accesses Pedestrian Access Ramps for Disabled persons Road painting
and Signage Speed Breakers
IV. Material Use Construction Materials Selection
Paint Selection
Use of Recycled Materials
Use of Timber
V. Aesthetics
during
functional Use
Clothes Drying Facilities
Visitors Parking
Playground for children
Service Roads for walking
Flower bed water disposal
Floor washing arrangements
Air conditioning arrangements
Standby Power Supply
Provision for Garden and Group housing
Maintenance Staff
VI. Facilities for
Building
complex
servants
Servant quarters
Rest Rooms with toilets for Security Persons.
4.5 ASSESSMENT OF ENVIRONMENTAL IMPACTS DURING DEVELOPMENT
AND CONSTRUCTION PHASE
4.5.1 Topography
Impact: Topography around the project is almost plain. Therefore, topography and
physiography of the area will not be affected during the construction and post construction
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 96
phase of the project. Hence, no significant impact is anticipated on the topography and
physiographic from the “Royal Heritage” Revision & Expansion of Group Housing Project
by M/s Pivotal Infrastructure Pvt. Ltd.
It is further proposed to maintain 30.94 % of the Net Planned area as green through
plantation of various local and aesthetic species to improve the vegetation covers of the
area.
Mitigation Measure: Since there is no significant impact on topography from the project,
no detailed mitigation measures are proposed. It is however proposed that apart from the
proposed plantation greens, turfing with local species will be carried out extensively.
4.5.2 Land Use Pattern
Impact: “Royal Heritage” Revision & Expansion of Group Housing Project will be
developed as per Faridabad Master plan 2021 which demarcates the project site as
residential zone. Hence, no significant impact is expected from the project which will be
constructed after obtaining all necessary permissions.
4.5.3 Land Environment
Impact: In, “Royal Heritage” Revision & Expansion of Group Housing Project, soil would
be excavated at project site for foundations of residential development. During the disposal
of redundant overburden, soil of filling area would be covered and lost permanently.
The soil excavated during construction will be first temporarily stored in an area earmarked
and then shall be used to fill up low lying area in and around the project site and rest of the
soil shall be transported by road to fill up low lying areas elsewhere. Proper drainage
system shall be provided to deal with the storm water in case of rain. The impact on soil
during construction phase will be marginal and reversible in the nature.
Mitigation: It is proposed to remove vegetative cover only from the specific site on which
construction is to take place and allowing minimal disturbance to the vegetation in adjacent
areas. Land clearing activities only confined to necessary areas. The top soil will be
stripped from constructional areas and stockpiled for later reuse in landscaping. The
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 97
number, frequency and area of movement of heavy machinery will also be restricted during
the night time.
4.5.4 Water Environment
4.5.4.1 Surface Water Quality
Impact: The primary concerns relating to surface water quality associated with
construction activities are pointed out below:
Runoff related to unpaved and excavated areas during the rain shower.
Sediments transported to runoff from the construction site.
Run off related to area where lubricant, fuel other materials are stored, used and disposed,
off.
Surface water quality may be affected with the discharge of the runoff from the project site.
The impact to the surface water bodies could arise from the increased soil erosion from
excavated site only causing increase in the suspended particles and turbidity of runoff water
from the site. However, this impact will be temporary in nature and would be observed in
first rain only and as soon as rain is over excavated soil at site would be stabilized.
Therefore, the surface water quality during rains will be impacted marginally for very short
duration.
Mitigation Measures: During the construction phase, surface water quality is likely to be
affected due to soil erosion during first rain and generation of wastewater mainly from
construction labour camp. However, this phenomenon will be temporary and restricted to
close vicinity of construction site. The impact on surface water quality can be minimized
by adopting following measures;
Excavation during dry season and proper management of excavated soils,
Clearing all debris from site as soon as construction is over.
By providing proper hutment and toilet facilities for construction labour,
Through the proper disposal of sullage generated at site.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 98
4.5.4.2 Ground water Quality
Impact: No hazardous chemical and material will be used in the development and
construction phase of “Royal Heritage” Revision & Expansion of Group Housing Project.
Only used DG set oil will be generated during operation phase. Debris and wastes
generated during this phase will be collected and disposed suitably. Therefore, possibility
of contamination of ground water will be negligible. Hence, no impact is anticipated on the
ground water quality during the construction phase.
Mitigation: A well planned solid waste management plan will be followed during the
construction phase including timely collection, segregation and disposal as per legal
requirements. Used oil will be kept in HDPE containers in a specified locations and will be
sold to Government approved vendors and that will be managed according to Hazardous
waste (Management & Handling) Rules, 1989.
4.5.4.3 Surface and Ground Water Hydrology
Surface Water Hydrology
Impact: The project site is outside any flood plain. Runoff during rains takes way to
natural drain and in storm water drains laid in the area. During construction phase, there is
no impact anticipated on the drainage pattern of the project area.
Mitigation Measures: Project proponent will ensure no interception on water runoff flow
routes and drainage pattern of the area throughout the construction of the project by
providing adequate water channel.
Ground Water Hydrology
Impact: In the area around the “Royal Heritage” Revision & Expansion of Group Housing
Project, Scare fresh water resources are present. Water requirement during construction
phase will vary depending upon construction activities and will be met by treated water
from private water tankers supply as per IS 456:2000. Water will be required for site
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 99
preparation activities dust settlement, consolidation, compaction and curing as well as
building construction and drinking water requirement. The requirement of construction
water will not put sudden pressure on the available ground water recourses of area.
Therefore, impact on ground water resources will be insignificant during construction of
project.
Mitigation Measures: Although no significant impact is anticipated on the groundwater
regime, it is proposed to carry out the following to further minimize the demand on
freshwater resources:
Curing water will be sprayed on concrete structures and free flow of water not allowed.
After liberal curing on the first day, all concrete structures will be painted with curing
chemical to save water to stop daily water curing hence save water.
Concrete structures will be covered with thick cloth/gunny bags and then water sprayed
on them to avoid water rebound and ensure sustained and complete curing.
Ponds will be made using cement and sand mortar to avoid water flowing away from the
flat surface while curing.
Water ponding will be done on all sunken slabs. This will also highlight the importance
of having an impervious formwork.
4.5.5 Air Environment
Emissions Source: The potential sources of air emissions during the construction and
development phase of the project will be as follows:
Dust from earth works (during site clearance and preparation);
Emissions from power generator at site;
Emissions from the operation of construction equipment and machines;
Fugitive emissions from vehicles running to site;
Fugitive emissions during the unloading of material at the site;
Fugitive emissions during mixing of cement with other building materials during
development and construction activities;
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 100
Air emissions other than dust arise from combustion of hydrocarbons. The pollutants of
concerns are NO2, SO2, CO, particulate etc.
Potential Impacts: Ambient air quality effects are normally assessed in relation to their
potential to cause;
Health deterioration and nuisance in local communities
Health deterioration amongst onsite workers
Assessment of the impacts from Dust Emissions: During the excavation of channels,
foundations, unloading of construction material, cement bags and mixing of cement with
other building materials such as brick and silica dust, wood dust, fugitive dust emissions
may be emitted at construction site. During construction, curtaining floors from all sides
will be done to prevent cement dust from becoming airborne. It may be noted that all the
emissions will be in the form of coarse particulate matter and settle down ultimately in
closed vicinity of construction site. Therefore, no significant impact is anticipated due to
dust emission during development and construction phase.
Assessment of the impact from Diesel Generators: Emissions from the D.G. Set during
construction phase may cause some localized impact on ambient air quality for short
duration, as it will be operated during power failure only. It may be noted that the D.G. Set
power will be used to operate construction equipment only if required. Adequate height of
stacks and acoustic erective will be provided to the D.G. Set as per guidelines of CPCB to
facilitate the dispersion of flue gases into the atmosphere.
Mitigation Measures: It is proposed to provide adequate dust control systems in the form
of installation of batch plants, and loose material handling in covered sheds. Dust
suppression system is also to be provided where necessary. Provision for treatment of DG
Flue Gas emissions in a scrubber will be considered. It is further proposed to cover
scaffolding, hosing down road surfaces and cleaning of vehicles especially during the dry
season. Avenue and curtain plantation on the internal roads and peripheral plantation
around the site will also be developed.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 101
4.5.6 Noise Environment
During the construction phase of project, noise will be generated from the various sources.
Some major sources of noise generation at project site are listed here under:
Generation of noise during movement of vehicles carrying materials and loading &
unloading activities.
Generation of noise from excavation machines, concrete mixer and other construction
machines,
Generation of noise during the operation of D.G. Sets
Generation of noise during concreting, hammering, etc.
All the above-mentioned sources of development and construction activities at “Royal
Heritage” Revision & Expansion of Group Housing Project would be intermittent and
experienced occasionally. It may also be noted that the most of the construction activities
would be carried out only during the daytime.
The expected noise levels from various activities are given hereunder:
From vehicles bringing materials to the site 70 dB (A)
D.G. Set 85 dB (A)
Excavation 80 dB (A)
Concrete Mixtures 80 dB (A)
Hammering 85 dB (A)
Resultant Noise Level:
The combined effect of above sources can be determined as per the following equation:
Lp (total) = 10 log (10(Lpl/10)
+ 10(Lp2/10)
+ 10(Lp3/10)
+……..) ……. (1)
Where: Lp1, Lp2 and Lp3 are noise pressure level at a point due to different sources in dB
(A). The resultant maximum noise level for the above sources as calculated using equation
(1) is 89.3 dB (A).
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 102
For an approximate estimation of dispersion of noise in the ambient air from the sources
point, a standard mathematical model for sound wave propagation is used. The sound level
generated by noise source decrease with increasing distance from the source due to wave
divergence. An additional decrease in sound pressure level from the source is expected due
to atmospheric effect or its interaction with objects in the transmission path.
For hemispherical sound wave propagation through homogenous loss of free medium,
noise levels at various locations can be calculated due to different sources using model
based on the first principles as per the following, equation:
Lr2 = Lr1 -20 log (r2) – 8 ………. (2)
Where: Lr2 and Lr1 – Sound Pressure Level (SPLs) at points located at sources and at
distance of r2 from the source respectively in dB (A).
Assuming no environmental attenuation factors, noise modeling has been done, which
shows that noise level will be mingle with baseline noise level with in short distance.
The noise produced during, development and construction phase will have temporary impacts on
the existing, ambient noise levels at project site but restricted to small distance (maximum up to
4.3 km) and only during daytime. Therefore, the impact of noise levels on surrounding area will
be insignificant during the development and construction phase.
Mitigation: To minimize impacts of noise generation from construction activities, the workers
will be provided with ear muffs and other protection devices. D.G. Sets with proper acoustic
enclosure for controlling noise would be installed and pollution under control certificate (PUC)
would be installed.
4.5.7 Terrestrial Ecology
Impact: There is no loss of forest land due to the construction of the “Royal Heritage” Revision
& Expansion of Group Housing Project. No tree felling is involved, as the site was a barren land
devoid of vegetation.
Birds and other domesticated biodiversity observed near the project site are common and already
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 103
adapted to thrive in human - colonized habitats. The project will not have any major negative
ecological impact. There is no forest near the project site and therefore there will be no effect on
the ecology of the area.
Mitigation Measures: However, it is to develop extensive green areas in the project site to
improve the aesthetics of the area which will also help in reduction of air pollution, noise
pollution and provide suitable habitat for local birds and animal species.
4.5.8 Economic Impacts
Impact: Relatively long-lived economic impacts of the development and construction phase are
likely to be experienced in local area for the duration of construction phase of 3 years as workers
make everyday purchases from local traders in near by areas. This is likely to give a short-lived
stimulus to the traders that may disappear as soon as the construction is complete. Noticeable,
flow-on economic impacts will be experienced in other sectors of economy as a result of
purchase of construction materials and the payment of wages and salaries to the personnel
engaged in the development and construction of “Royal Heritage” Revision & Expansion of
Group Housing Project. Once the development and construction of project will complete, there
will be some long-term positive impact on the economic structure of the area. People in the area
will get direct and indirect employment opportunities and other benefits from the residents of the
“Royal Heritage” Revision & Expansion of Group Housing Project. Therefore, overall positive
impact is anticipated on economy of the area due to development and construction activity of the
“Royal Heritage” Revision & Expansion of Group Housing Project.
4.5.9 Socio-Economic Impacts
During the development and construction of “Royal Heritage” Revision & Expansion of Group
Housing Project, about 150 to 200 skilled and semiskilled and unskilled workers per day will get
direct employment opportunity, which will have beneficial impact on the local people and
improve socio-economic conditions of the area.
4.5.10 Construction Camp
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 104
Impact: During the development and construction phase, most of the laborers will be from local
areas as “Royal Heritage” Revision & Expansion of Group Housing Project will be developed
gradually in the time span of about 3 years (approx). Therefore, laborer camps will be
constructed to accommodate the laborers at the project site. This may lead to sanitation problems
in the absence of adequate facilities.
Mitigation: Suitable measures will be taken at the construction camps to mitigate anticipated
impacts due to temporary accommodation of laborers such as provision of clean drinking water,
adequate toilet facilities, water and solid waste disposal system.
Other safety precautions to be maintained at work site including provision of PPEs, guarding of
dangerous machine parts, maintenance of equipments as hoists and lifts etc, and adequate
provision of different types of fire extinguishers will be made. All applicable rules and
regulations pertaining to workplace health and welfare of workers will be adhered to.
4.5.11 Solid Waste Management
Impact: The construction and demolition waste includes debris, concrete (often recycled and
reused at the site), steel and other metals, pallets, packaging and paper products, fluorescent
tubes, wood beams, joists, studs, baseboards, cabinets and cupboards, railings, brick, doors and
casings, interior windows, bathroom fixtures, light fixtures, ceiling grid and tile, furnishings,
replant trees, shrubs. All wastes generated during the construction phase shall be collected and
segregated for disposal as per the standard practice.
During the development and construction phase, some amount of debris, cuttings of construction
materials may be observed at construction site. However, the quantity of these waste materials
would be very small and limited up to the construction site only. There will be no contamination
due to this waste as it will be collected time to time during construction phase and disposed
accordingly.
Mitigation Measures: After due waste segregation, recyclable wastes will be sold off to scrap
dealers and vendors, while inert wastes will be disposed off through Govt. approved agency.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 105
Hazardous wastes will be disposed off as per the provisions of the Hazardous Wastes
(Management and Handling) Rules, 1989.
4.5.12 Crops and Cropping Pattern
The predominate farming system in Faridabad district is Agriculture integrated with Animal
Husbandry. The major cropping systems under the existing farming system are bajra- wheat,
bajra-mustard guar-wheat and guar-mustard. Buffalo is the main component under animal
husbandry. Wheat and Mustard are the main crops in rabi, and in kharif, bajra is the major crop.
4.5.13 Transport Linkage and Traffic
Impact: During development and construction phase, construction labour and construction
materials bringing vehicles will approach the project site. The project is well connected to
neighborhood, where public transport facility, like, buses and minibuses are easily available in
the area as transport linkage. During construction phase, some impact is anticipated on the
transport linkage of the area, however increase in traffic will not adversely affect the local traffic
pattern since the site is well connected by broad road and present traffic load on these road are
not significant. Also construction of various buildings will take place in phased manner, thus
reducing peak traffic load bringing labour and building material to the site.
Mitigation: Through careful planning, the movement of the heavy vehicles will be scheduled to
reduce load on existing traffic such that the peak hours are avoided. It shall also be ensured that
all the vehicles to the site will be provided with Parking space such that there is no waiting time
along the access roads.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 106
4.6 ASSESSMENT OF THE ENVIRONMENTAL IMPACTS DURING POST
CONSTRUCTION PHASE
4.6.1 Land Environment
Impact: During the operation phase of the project, the soil may get polluted/ contaminated from
littering of various kinds of wastes generated within the site such as food items, paper, wood
pieces, paints, pesticides, oil & grease etc. However, owing to the proposed solid waste
management system, no significant impact is anticipated.
Mitigation Measures: To ensure against any chances of soil pollution, it is imperative to
establish a well planned solid waste collection system covering all areas of the project site apart
from door to door for the residential units. An identified area shall be designated for storage and
segregation of the wastes which will be treated/ disposed as per their characteristics.
4.6.2 Water environment
4.6.2.1 Surface water hydrology
Impact: During the post construction phase, no water will be taken from surface water bodies in
the area. Further, adequate drainage will be provided at the project site to channelize the storm
water for rainwater harvesting.
The sewage effluents generated from the project will be collected through the sewer line network
provided in the project site for treatment in the Sewage Treatment Plant (STP), and the treated
sullage reused within the site thereafter. Therefore, impact on the surface water hydrology will
be insignificant during the post construction phase.
Mitigation: It is proposed to provide rainwater harvesting across the project site. The roof tops
of buildings will also be connected to the rainwater collection system. This will not only reduce
the pressure of storm water management system of the city but also recharge groundwater.
4.6.2.2 Ground water hydrology
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 107
Impact: During post construction phase, the total water requirement of the “Royal Heritage”
Revision & Expansion of Group Housing Project is approx. 1160 KLD out of which total
domestic water requirement is 928 KLD. The fresh water requirement is approx. 700 KLD
(which is 70% of the domestic water demand+ make up water for swimming pool). The water
will be supplied by Municipal Corporation of Faridabad. Therefore, no significant impact is
anticipated on ground water resources due to project.
Mitigation Measures: Treated water from the site will be recycled for landscaping and flushing.
HVAC cooling to further reduce demand on freshwater resources.
Water meters conforming to ISO standards should be installed at the inlet point of water uptake
and at the discharge point to monitor the daily water consumption. To further lower the water
consumption, options of Low flow flushing systems, sensor based fixtures, and tap aerators etc
will be explored will be explored in commercial area.
4.6.2.3 Surface Water Quality
Impact: The sewage effluents generated from the Revision & Expansion of Group Housing
Project will be collected through the sewer line network provided in project, and treated in
Sewage Treatment Plants (STP) of capacity 960 KLD. No discharges from the project site will
be made to any surface water body.
Mitigation Measures: As no significant impact is anticipated on the water bodies of the region,
no mitigation measures are suggested.
4.6.2.4 Ground Water Quality
Impact: The storm water from the site will be used for recharging groundwater resources after
adequate treatment of the storm water through oil and grease traps and filtration. The treated
water from the site is proposed to be used for landscaping, flushing & HVAC cooling
requirements only after adequate treatment in proposed Sewage Treatment plant. Hence, no
adverse impact is anticipated on the groundwater quality form the project.
Mitigation Measures: The project will be well maintained. Solid waste management practices
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 108
will be adopted and followed to prevent groundwater pollution through leaching.
4.6.3 Air Environment
AIR ENVIRONMENT
Prediction of Impacts
Vehicular emissions and DG sets emission will be major sources of air pollution from building
construction projects. During the post construction phase, cars, scooter/motorcycle will be owned
by the population of such project. Ground Level Concentration of pollutants (as added by the
project) will depend upon the following:
Emission of pollutants from additional traffic on the roads due to the project.
Meteorological conditions.
Emission sources from D.G. Sets.
PM, NO2, SO2 and CO will be the main pollutants of primary concern released from traffic
movement and DG sets. Assuming that under cross wind condition perpendicular to the road, the
dispersion of vehicular emissions would be confined within limited distance from the road and
concentration will decrease with the increase in distance from road. It was anticipated that the
contribution of vehicular emissions from the exhaust in ambient air quality will be marginal as
Pollution under Control (PUC) Certified vehicles and branded make operated vehicle with low
sulphur diesel will be used. Ground Level Concentration (GLC) of pollutants is found to be well
within the stipulated National Ambient Air Quality Standards due to traffic movement and
vehicles used inside the premises. DG sets will be main source of Air Pollution in the project.
CPCB/ MoEF approved USEPA dispersion model -ISCST3 was used for prediction of impacts
caused by DG sets. Stack & emission data was used as per design value provided by standard
make and stipulated standards. Other primary data used as input for model were hourly
meteorological data of Wind speed & direction, temperature, cloud amount and mixing height.
Mixing height used in the model was taken from secondary data source “Atlas of Hourly Mixing
Height Assimilative Capacity of Atmosphere in India published in 2008 by IMD, Delhi”. Hourly
meteorological monitored at site during study period data was compared with long term data
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 109
available from the nearest India Meteorological station or any other authorized source/Govt.
agencies.
In this project, 5 DG set of (4 x 1500+ 1 X 750 kVA) of total capacity 6750 kVA has been
proposed, for back up of electricity supply during power failure. This will cause emission of PM,
SO2, NO2 and CO in the Ambient Air Quality. In the project, D.G. sets will be used only during
power failure and low sulphur diesel will be used as fuel to minimize SO2 emission. Therefore,
incremental load in the ambient air environment will be found to be very low as given in the
report. An adequate stack height of D.G. sets will be provided as per the stipulated guidelines of
Central Pollution Control Board (CPCB)/ National Building Code Manual to facilitate proper
dispersion of pollutants and to minimize the impact on Ambient Air Quality under the influence
of local meteorology.
Meteorology - Hourly Meteorological data of wind speed & direction, temperature, cloud
amount and rainfall were monitored at site for 3 months for the dispersion model. Wind rose
(Figure - 4.1) was prepared in eight directions as per standards. It was observed that westerly
and northwesterly were prevalent wind during the study period. Average wind speed was 5.51
knots (2.755 m/s) and calm condition was 14.04% during March- May 2013
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 110
Figure 11 Wind rose - (1st March to 31
th May- 2013)
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 111
Table 4.5 Pollution Source Details
Note:-DG set will be operated during power failure for maximum 6-Hours.
Table 4.6: Meteorological data for the 24-hour average maximum predicted Concentration
under worst meteorological condition
Year Month Day HOURS Wind
Direction
(Degree)
Wind Speed
( m/s)
Temperature
(K )
2013 4 13 1 337.5 2.6 301
2013 4 13 2 270 0 301
2013 4 13 3 0 0 301
2013 4 13 4 0 0 301
2013 4 13 5 0 0 301
2013 4 13 6 0 0 303
2013 4 13 7 0 0 305
2013 4 13 8 270 1.5 307
2013 4 13 9 225 2.1 307
2013 4 13 10 270 0 308
2013 4 13 11 247.5 2.1 311
2013 4 13 12 270 2.6 313
2013 4 13 13 292.5 3.1 315
2013 4 13 14 292.5 2.6 317
2013 4 13 15 270 2.6 317
2013 4 13 16 270 2.1 317
Stac
k
No.
DG set
Capacity
(kVA)
Stack & Flue details Pollutants Emission
Heig
ht
(m)
velocit
y
(m/s)
Temp
(C)
Diamete
r (m)
NO2
(g/s)
SO2
(g/s)
PM
(g/s)
CO
(g/s)
1. 6000 KVA
(4 x 1500)
103 25 682.9 0.49 2.14 0.42 0.35 0.70
2. 750 KVA
(1 x 750)
103 25 809.0 0.33 0.59 0.04 0.02 0.21
Total Emission of DG capacity – 6750 KVA 2.73
6 0.46 0.37 0.93
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 112
2013 4 13 17 270 2.1 317
2013 4 13 18 270 2.1 315
2013 4 13 19 292.5 2.1 315
2013 4 13 20 270 2.1 313
2013 4 13 21 270 2.6 311
2013 4 13 22 315 4.1 309
2013 4 13 23 337.5 3.6 308
2013 4 13 24 270 2.6 306
Spatial distribution of NO2 is shown in iso-pleth Figure 4.1. It was observed that GLC closed to
the proposed source will be not significant due to high stack attached with DG sets. 24-h
maximum incremental GLC was 1.9 µg/m3 occurred at the distance 900 m, East of the project
site.
Conclusion
Maximum Incremental GLC of NO2 was 1.9 µg/m3 due to DG sets in the proposed project. High
to moderate wind speed and stack height of 103 m facilitates dispersion at the distance of 900 m
East under the influence of local meteorology. Low GLC of pollutants was predicted due to high
Stack height of 103 m fitted with DG sets. Predicted GLC of all pollutants are given in Table 4.3
as below
Table 4.7 Predicted GLC of all pollutants
S.No. Pollutants Maximum
Incremental
GLC (µg/m3)
Distance of occurrence
1 NO2 1.9 900 m, East
2 SO2 0.32 900 m, East
3 PM 0.25 900 m, East
4 CO 0.64 900 m, East
Low incremental value was predicted from DG sets due to high stack height of 103 m. No
significant impact was envisaged due to proposed DG sets to be installed at site.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 113
Figure 12: Spatial distribution of 24-hours average NO2 maximum incremental GLC (1.9 µg/m
3) at 900 m East.
Moderate to high wind speed and stack height of 103 m facilitates dispersion at a distance of 900m,
east under the influence of local meteorology.
Mitigation Measures: The project proponent will develop a green belt inside the premises of the
project site and along the internal road, which will work as barrier for the movement of
Max Conc. of NO2 is 1.9 µg/m3 at 1300 m East from the project site
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 114
pollutants and help in pollution control.
4.6.4 Noise Environment
Impact: The main sources of noise from the project are running of D.G. Sets and vehicular
traffic. D.G. Sets will provide emergency electricity supply during power failure. This will be
intermittent and for short durations. The vehicles playing within the site will be mainly of the
residents and are hence not expected to cause unnecessary noise. Hence, during this phase, no
major impact on noise environment is anticipated.
Mitigation Measures: D.G. Sets will be fitted in acoustic enclosures to control the noise
generated within 25 dB (A) insertion loss or for meeting the ambient noise standard whichever is
on higher side as per E (P) Act, GSR 371 (E) and its amendments. Adequate personnel protective
equipment (PPE) will be provided to the personnel engaged in D.G. Set room. The traffic noise
will diminish within a short distance from the source of origin. Honking within the site will be
discouraged. Proposed rows of plantation will further restrict the noise on other side of the
plantation i.e. outside the boundary.
4.6.5 Terrestrial Ecology
Impact: The total green area of the project is 24,656.84 m2 that will be planted with local
species with aesthetic appeal that will attract local bird and insect species. As against the existing
barren stretch of land, the project will add to the greenery and beauty of the region.
Mitigation Measures: Various kinds of plantation such as curtain, avenue and ornamental
plantation and lawns will be started during the construction phase itself and maintained during
the operation phase. Open space and Parks will be fenced through the grasses and ornamental
plants. Local and low water demanding plants that will also be effective as sinks for various
pollutants and attract birds will be grown in the site that will contribute in positive to the local
ecology. The project does not fall under Aravalli Notification and does not have any forest land;
Socio-economic Impact
Impact: During operational phase of “Royal Heritage” Revision & Expansion of Group Housing
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 4
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 115
Project, more than 200 persons will get employment opportunities as staff for management,
maintenance and security. As an estimate, during post construction phase, more than 300 persons
will get marginal employment opportunities from the residents of “Royal Heritage” Revision &
Expansion of Group Housing Project who would work as domestic helpers. This will help in
improving the quality of life of economically weaker sections of the local area.
Mitigation Measures: To further improve the socio-economic conditions of the area, it may be
proposed to employ mainly local people as workers. Much of the maintenance arrangements may
also be made with local companies and purchase of new parts from the local market.
4.6.6 Transport Linkage and Traffic
Impact: The vehicle from the project will increase car and two wheeler traffic load along the
road during peak hours. However, since present load is lean, increase in traffic load may not lead
to traffic congestion problem.
Mitigation Measures: The road width is provided as much as it is proposed to balance the
number of traffic vehicles during the peak hour too. So there will be no traffic congestion
problem during the peak hours
4.6.7 Energy Resources
Impact: During the operation phase of the project, electric supply will be provided from
Dakshin Haryana Bijli Vitran Nigam. The connected load for the Plotted Colony Project will be
approx. 11,453 kVA. The proponents will make arrangements for meeting any electricity
shortage for the project. Therefore, energy resources of the region will not be affected
significantly.
Mitigation Measures: To promote energy conservation, it is proposed to provide the buildings
with low energy consuming fixtures maximize availability of natural light and make plans in
conformance to the sun’s path.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 5
Faridabad
M/s Pivotal Infrastructure Pvt. Ltd. Page 116
CHAPTER-5
ANALYSIS OF ALTERNATIVES
5.1 INTRODUCTION
This chapter discusses the assessment of various options that may be available for different
components of the project in terms of environmental suitability. Lately, there are a number of
options available for the use of building materials, means of energy conservation and methods of
transportation. The various applicable options are thus evaluated for their suitability to project
and environment.
5.2 BUILDING MATERIALS
The choice of building materials plays an important role in terms of energy efficiency of the
building. The manufacture of building materials should also be assessed to ensure the use of
environment friendly and recycled/ recyclable construction materials.
5.2.1 Wall
Conventionally, sun burnt clay bricks are cemented in the construction of walls. The strength of
these construction materials cannot be compromised which will otherwise pose a threat to the life
and property of the occupants. However, presently, materials with similar properties are easily
available that are made of waste products, thereby reducing the waste burden and conserving
natural resources. Thus, the project proposes the use of the following for walls:
Brick and block products with waste and recycled contents such as fly ash (15 to 35%),
blast furnace slag (20 to 25%), sewage sludge, waste wood fiber etc.
Fly ash based lightweight aerated concrete blocks – fly ash being a waste product of
thermal power plant poses the challenge of disposal. Hazardous in powder form, it is
rendered harmless when molded as bricks. Fly ash-based lightweight aerated concrete
blocks are manufactured for walling and roofing purposes by mixing fly ash, quick lime,
or cement and gypsum with a foaming agent like aluminum powder
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter -5
Faridabad.
.
M/s Pivotal Infrastructure Pvt. Ltd. Page 117
Fal-G products – are manufactured by use of two waste products being fly ash, calcite
gypsum (a byproduct of phosphogypsum or natural gypsum) along with lime.
Perforated bricks
Materials proposed for use in the wall openings such as doors and windows include:
Precast thin lintels, use of fibrocement-sunshade cum lintel etc.
Renewable timber
Steel manufactured from recycled content
Aluminum manufactured from verified recycled content
Saw dust based doors and window frames
Ferro cement shutters, PVC doors and windows, Rice husk boards, Natural fibre-
reinforced
Polymer composite door panels
The finishing for the openings will be by the use of Fly ash, Ceramic tiles, and Terrazzo
floors.
5.2.2 Roof
The conventional material used for roofing is RCC, as it is suitable for longer spans. The
constituents of RCC, i.e. cement, sand, aggregate and steel are energy intensive materials and
high embodied energy content.
Alternately, it is proposed to use lightweight synthetic aggregates such as fly ash based
aggregates, which is suitable for manufacture of brick, blocks, and is good substitute for clinker
and natural aggregates. When pre-cast/aerated cellular concrete walling blocks and roofing slabs
are used in multi- storied structures, they reduce the weight, resulting in a more economical
design. They have high rating to fire resistance and provide better insulation and thus improved
energy efficiency. These are manufactured by the aerated cellular concrete manufacturing
process.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter -5
Faridabad.
.
M/s Pivotal Infrastructure Pvt. Ltd. Page 118
5.2.3 Superstructure
Structural frame of building comprises of footing, columns, beams and lintels, over which the
envelope of building is supported. A variety of metals are used in buildings, but the major
building material used structurally is steel. Steel has a high-embodied energy and recyclable
content, as well as scrap value. Aluminum forms the second most common material used for
roofing sheets, window frames, and cladding systems, which has the highest recyclable content.
Hence, bulk of the metal needs for the building shall be met by steel and aluminum.
Problem with RCC. The choice of cement will be:
Ferro cement: The composite Ferro cement system is simple to construct and is made of
Ferro cement—a rich mortar reinforced with chicken or/and welded wire mesh.
Use of fly ash and/or blast furnace slag concrete: The amount of cement used in
concrete can be reduced by replacing a portion of the cement with coal fly ash (waste
material from coal burning power plants) and/or GGBF (ground granulated blast furnace)
slag in conventional mixes.
Recycled aggregates: Recycled aggregates include crushed concrete, brick, glass, or
other masonry waste can also be used in conventional mixes
Lightweight concrete: Aluminum powder when added to lime reacts and form hydrogen
bubbles, and a lightweight cementitious material is formed which could be used in
conventional mixes.
5.2.4 Roads and open spaces
Roads and open spaces consist of compound walls, grills, roads, sidewalks, parking lots, drains,
curbs, landscaped areas, street furniture, tree covers, and flowerbeds.
In line with environment friendly design it is proposed to provide:
Permeable paving- Permeable (porous) paving will be provided to control surface water
runoff by allowing storm water to infiltrate the soil and return to the ground water. The
traffic areas will however continue to be impermeable.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter -5
Faridabad.
.
M/s Pivotal Infrastructure Pvt. Ltd. Page 119
Gravel/crusher fines- Loose aggregate materials from masonry wastes will be used to
cover pedestrian surfaces.
Use of grass pavers on the road, parking and pedestrian areas to reduce the heat island
effect.
Use of steel in fencing, grills, tree covers, and benches and even in streetlights will be
replaced by bamboo in the parks and green landscaped areas.
5.3 NATURAL HAZARD PRONE AREAS
The project will be situated in earthquake risk prone area (Seismic zone- IV). Special attention is
thus given to the structural design of foundation, elements of masonry, timber, plain concrete,
reinforced concrete, pre-stressed concrete, and structural steel. All applicable guidelines will also
be followed in this regard to ensure safety of the building and its residents.
5.4 ENVIRONMENT FRIENDLY DEVELOPMENT
Without compromising on the safety and comfort of the occupants, care will be taken to achieve
an energy efficient, water conscious project the benefits of which will be enjoyed in monetary
terms by the residents and other intangible benefits will result for the society at large. This will
be achieved by:
a. Minimal disturbance to landscapes and site condition
The project aims to integrate the new development with the local existing surroundings. Efforts
are made to minimize on-site tree cutting by careful and detailed layout planning. Tree felling
shall be undertaken only after receiving requisite permissions and under strict supervision. The
original landscape of the site has also been integrated with the design of the group housing such
that there is no alteration of the site topography.
b. Resource Conservation and Environmental Friendly Building Materials
To reduce the ecological footprint of the development, use of recycled material for construction
and conserving natural resources is of primary importance. In this light, the use of recyclable
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter -5
Faridabad.
.
M/s Pivotal Infrastructure Pvt. Ltd. Page 120
building materials has been proposed for various building materials. It is also proposed to reuse
building components, minimization of construction wastes etc.
The project is also committed towards conservation of water. This includes use of treated
sullage, provision of low water flow fixtures and raising awareness on means of water
conservation.
c. Efficient use of Water and Water Recycling
The need for water conservation in the face of impending water crisis cannot be overemphasized.
The project will follow a three pronged management for water resource viz water resource
development, minimize use of water and recycle sullage generated within the site.
The water demand is proposed to be brought down by the use of water efficient fixtures,
implement best management practices for water in both group housing development and
horticultural activities. An important means for achieving this is spreading awareness to the
occupants for generating water conservation awareness.
To reduce the freshwater demand of the project, sullage from site will be treated in a STP and
recycled for landscaping, HVAC and flushing.
d. Use of Energy Efficient design and Eco-Friendly Equipment
The project will be designed such that there is optimal solar energy utilization, especially for
natural light availability. Shading will be provided on sides that will otherwise reduce the energy
efficiency of the building. Energy conservation will be one of the focuses during the planning,
development, construction and post construction stages.
Use of Renewable Energy
The electrical supply is largely dependent on thermal power plants that are largely responsible
for accelerating the phenomenon of global warming and consumption of limited natural
resources. It is of paramount importance to shift focus on other renewable sources of energy to
achieve sustainable development in the energy sector. The project area in Faridabad receives
adequate hours and intensity of sunlight for effective solar energy generation. Taking full
cognizance of the availability of natural sunlight and technology, the project proposes the use of
solar energy to reduce the power demand of the project.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter -5
Faridabad.
.
M/s Pivotal Infrastructure Pvt. Ltd. Page 121
Solar energy will be used for the purpose of heating of the water.
e. Indoor Air Quality for Human Safety and Comfort
To provide the occupants with a safe building is the primary responsibility of a developer. Indoor
pollution sources that release gases or particles into the air are the primary cause of indoor air
quality problems in homes. Inadequate ventilation can increase indoor pollutant levels by not
bringing in enough outdoor air to dilute emissions from indoor sources and by not carrying
indoor air pollutants out of the home. High temperature and humidity levels can also increase
concentrations of some pollutants. Likewise, it is proposed to use all user safe building materials
such as:
i. The buildings will be painted with low VOC, ammonia free paints.
ii. Asbestos will not be used.
iii. Adequate ventilation will be provided in each residential unit and floor.
iv. Adequate openings for sunlight to enter the building, thereby reducing chances of
microbial growth.
v. All building maintenance and cleaning materials will be kept in an isolated and well
ventilated room with restricted entry.
f. Effective Controls and Management Systems
It is proposed to establish a Management System that will comprise modern equipment’s as well
as an efficient team of maintenance staff.
i. All essential services such as water supply will be provided with power back up.
ii. A security system for the entire Group Housing project will be provided comprising
intercom facility, closed circuit camera to the entrance and round-the-clock manning.
iii. Separate entries and exits of residents from the guests are proposed. The staffs’ vehicles
will be provided with identification stickers while visitors’ vehicles will be monitored
through security guards at the entrances.
The project further proposes extensive green areas as avenues, parks and roadside plantations.
The plants not only serve various direct environmental facilities, but also have indirect positive
environmental impacts such as reduction in overall energy use in buildings. The balcony garden
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter -5
Faridabad.
.
M/s Pivotal Infrastructure Pvt. Ltd. Page 122
is a natural development of the balcony’s role as a link between interior and exterior
environments. Efforts will be made to cover walls with climbers, as feasible.
5.5 COMMUNITY ISSUES
Apart from the site occupants, all efforts will be made to ensure that the exiting neighborhood is
not adversely affected by the project.
While, the site will not act as a thoroughfare for vehicles, there shall be no restriction to
movement of on-foot visitors and cyclists.
5.6 ENERGY CONSERVATION
To achieve conservation of energy, appropriate design of a building is of paramount importance.
Accordingly, it is proposed to incorporate the guidelines of Energy conservation Building Code,
2007 for the structures of the Group Housing project.
The concept of passive solar design emphasizes architectural design approaches that minimize
building energy consumption by integrating conventional energy-efficient devices, such as
mechanical and electrical pumps, fans, lighting fixtures, and other equipment, with passive
design elements, such as building sitting, an efficient envelope, appropriate amounts of
fenestration, increased day lighting design, and thermal mass. The basic idea of passive solar
design is to allow day light, heat, and airflow into a building only when beneficial.
The project layout has been finalized after careful sitting consideration of various group housing
components to optimize availability of natural sunlight. Advanced Solar Passive Techniques are
employed to achieve energy efficiency.
Glazed windows are located to receive maximum sunlight in winter. To reduce
heat losses during the night these windows are often double-glazed and have
insulating curtains.
Thermal storage wall is placed between the glazing and habitable space to prevent
solar radiation from directly entering the living space.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter -5
Faridabad.
.
M/s Pivotal Infrastructure Pvt. Ltd. Page 123
Passive cooling systems i.e. cooling directly from evaporation, convection
radiation without using any intermediate electrical devices.
Provisions for use of desert cooler (Indirect evaporative cooling which comprises
water, evaporative pads, a fan and a pump).
Effective measures have been incorporated to minimize the energy consumption in following
manners
:
• Use of Solar photovoltaic systems for street lighting
• Use of Light Emitting Diodes (LED) for common area lighting.
• Maximum use of sunlight by providing bringing the daylight at a high location, filtering
the light and bouncing it off surrounding surfaces.
• All lighting systems (interiors, external building features such as facades, illuminated
roofs, architectural features, and building grounds) will be in conformance to the ECBC
Code.
5.7 TRANSPORTATION
A well planned road network is proposed within the project premises. Adequate parking will be
provided during construction phase to ensure that all heavy vehicles visiting the site are provided
parking space within the site. There shall be no parking on the access roads. The movement of
the vehicles will also be scheduled such that the peak hours are avoided.
In the operation phase, entry and exits will be from separate gates to minimize disturbance to the
approach roads to the project site. To avoid congestion of the approach roads, space will be
provided for vehicles waiting checking. Adequate parking is also proposed to ensure there is no
parking along the roads. Within the site, wide roads are proposed. To achieve the same, speed
humps will be provided.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 6
Faridabad.
M/s Pivotal Infrastructure Pvt. Ltd. Page 124
CHAPTER-6
ENVIRONMENTAL MONITORING PROGRAM
6.1 INTRODUCTION
The purpose of the monitoring programme is to ensure that the specified mitigative measures
defined in the EMP are complied with and leads to the desired benefits for the target area and its
population. To ensure the effective implementation of the EMP and gauge the efficiency of the
mitigative measures, monitoring shall be undertaken both during the construction and operation
period of the project.
6.2 PERFORMANCE INDICATORS (PIs)
The physical, biological and social components are of particular significance to the project is as
listed below:
Air quality
Water quality
Noise levels
Solid Waste Management
Replantation success / survival rate
Of these, the following are selected as the Performance Indicators (PIs) and shall be monitored,
since these are well known and comparative data series exist:
Air Quality
Noise levels
Water Quality
Flora
To ensure the effective implementation of the mitigation measures and environmental
management during construction and operation phase of project road, it is essential that an
effective Environmental Monitoring Plan be designed and followed as given in Table 6.1.
6.2.1 Ambient Air Quality (AAQ) Monitoring
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 6
Faridabad.
M/s Pivotal Infrastructure Pvt. Ltd. Page 125
Ambient air quality parameters recommended for monitoring during construction activities are
PM, CO, SO2, and NO2. Monitoring shall be carried out twice a week for one month in each
season during construction phase in accordance to the National Ambient Air Quantity Standards.
The method of analysis will be applied as recommended by SPCB/CPCB/MoEF guidelines.
Monitoring location will be finalized as per dispersion model results i.e. occurrence of maximum
GLC due to polluting source, wind pattern at the site and study of that area based on population
of human settlements The locations with the pollution parameters to be monitored are shown in
Environmental Monitoring Plan (Table 6.1).
6.2.2 Noise Level Monitoring
The measurements of noise levels will be carried out at all designated locations in accordance to
the ambient Noise Standards formulated by MoEF as given. Noise level will be monitored on
twenty-four hourly bases. Noise should be recorded at “A” weighted frequency using a slow time
response mode of the measuring instrument. The measurement location, duration and the noise
pollution parameters to be monitored are detailed in the Environmental Monitoring Plan (Table
6.1).
6.2.2.1 Success of Vegetation
To ensure the proper maintenance and monitoring of the proposed plantation activities, a regular
survey of the survival rate of the planted trees is being up to a period of 2 years from the start of
operation of the project.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 6
Faridabad.
M/s Pivotal Infrastructure Pvt. Ltd. Page 126
Table 6.1: Environmental Monitoring Plan
Environment
Component
Project stage Parameter Standards Location Duration / Frequency
Ground
Water
Quality
Construction
Phase
Drinking water parameters Drinking water standards
(IS 10500)
Project site
Village Mujheri
Sector 71
Sector 68
Sector 2
Quarterly
Operation
Phase
Drinking water parameters Drinking water standards
(IS 10500)
Project site
Once every year during the
dry season
Drinking
water
Construction
Phase
Drinking water parameters Drinking water standards
(IS 10500)
Supply water after
treatment
Quarterly
Operation
Phase
Drinking water parameters Drinking water standards
(IS 10500)
Supply water after
treatment
Treated
wastewater
Operation
Phase
pH, BOD, COD, TDS,
TSS, DO
General Standards for
discharge of effluents
Outlet of the Sewage
Treatment plant
Every three months during
the project life cycle.
Air Construction
Phase
PM, SO2, NO2, CO National Ambient Air
Quality Standards
Project site
Village Mujheri
Sector 71
Sector 68
Sector 2
Continuous 24-hourly, twice
a week for 12 weeks
Operation
Phase
PM, SO2, NO2, CO, National Ambient Air
Quality Standards
Project Site
Continuous 24-hourly, twice
a week for one month, once
in a year (summer).
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 6
Faridabad.
M/s Pivotal Infrastructure Pvt. Ltd. Page 127
Environment
Component
Project stage Parameter Standards Location Duration / Frequency
Noise Construction
Phase
Noise Level in dB (A) As per Ambient Noise
Standards
Village Mujheri
Anuradha Hospital
Innova Technology
SRS Bazar
One day hourly
measurement, quarterly
Operation
Phase
Noise Level in dB (A) As per Ambient Noise
Standards
Project site One day hourly
measurement, annual
Rainwater
harvesting
Operation
Phase
Inspection of stormwater
drains and rainwater
harvesting pits
Design parameters Project site Prior to monsoons
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 6
Faridabad.
M/s Pivotal Infrastructure Pvt. Ltd. Page 128
6.3 DATA MANAGEMENT
The monitoring shall be carried out through MoEF/ NABL approved laboratory. All
results shall be maintained at the project site and submitted to the SPCB as per the
reporting requirements in the Environmental Clearance.
6.4 REPORTING SCHEDULES
The environment management cell shall be responsible for timely conduct of the
monitoring activities. The results of the analysis shall be intimated to the project head. Any
anomaly in test results shall be investigated into and proper corrective actions shall be
undertaken.
A complaint register shall also be maintained to note any complaints from the staff and
visitors in the project or any other stakeholder. Corrective actions taken against the
complaints shall also be noted.
6.5 EMERGENCY
Alarming levels of pollutants in any of the monitored component may raise alarm in the
“Royal Heritage” Revision & Expansion of Group Housing Project. However, such
information should be made available to the residents/ occupants through notices. The latter
may also be consulted on necessary steps to be taken on an immediate and long term basis
to tide over the problem.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 7
Faridabad
M/s Pivotal Infrastructure Pvt. Ltd. Page 129
CHAPTER-7
ADDITIONAL STUDIES
7.1 INTRODUCTION
This chapter broadly looks at various aspects related to disaster management, resource
conservation.
7.2 RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN
“Royal Heritage” Revision & Expansion of Group Housing Project encompasses the lives
of a large number of people. It also involves installation of various structures and
machineries that meet the comfort and needs of its population but may also pose serious
threat to the occupants in case of an accident. It is thus considered necessary to carry out a
risk assessment and disaster management plan for the project.
7.2.1 Risk Hazard & its control measures
It is attempted to plan and construct the buildings following all safety norms. However, it is not
always possible to totally eliminate such eventualities and random failures of equipment or
human errors. An essential part of major hazard control has therefore, to be concerned with
mitigating the effects of such emergency and restoration of normalcy at the earliest. A detailed
table showing activities during construction and operation phase along with mitigation measures
are given in Table 7.1.
Table 7.1: Activities during construction and operation along with mitigation measures
HAZARDS ASSOCIATED WITH
ACTIVITIES
(During Construction & Operation)
CONTROL/MITIGATION MEASURES
Manual Handling
Strains and sprains - incorrect lifting - too
heavy loads -twisting - bending - repetitive
movement - body vibration.
Exercise/warm up - get help when needed
-control loads - rest breaks/no exhaustion -
no rapid movement/twisting/
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 7
Faridabad.
M/s Pivotal Infrastructure Pvt. Ltd. Page 130
bending/repetitive movement - good
housekeeping.
Falls - Slips - Trips
Falls on same level - falls to surfaces below
- poor housekeeping - slippery surfaces
uneven surfaces -poor access to work
areas climbing on and off plant -
unloading materials into excavations
wind - falling objects.
Housekeeping - tidy workplace - guardrails,
handholds, harnesses, hole cover, hoarding,
no slippery floors/trip hazards - clear/ safe
access to work areas - egress from work
areas - dust/water controlled - PPE.
Fire
Flammable liquids/Gases like LPG, Diesel
Storage area and combustible building
materials - poor housekeeping - grinding
sparks - open flames, absence of Fire
hydrant net work.
Combustible/flammable materials properly
stored/used - good housekeeping - fire
extinguishers made available & Fire hydrant
Network with reserve Fire water (As per
NFPA Code) - Emergency Plan in case of
Fire or collapse of structure.
Absence of Personal Protective
Equipment
Lack of adequate footwear - head protection -
hearing/eye protection - respiratory
protection - gloves -goggles.
Head/face - footwear - hearing/eye - skin –
respiratory protection provided - training -
maintenance.
Defective or wrong Hand Tools
Wrong tool - defective tool - struck by
flying debris - caught in or on - missing
guards - carbon monoxide - strains and
sprains - dust.
Right tool for the job - used properly - good
condition/ maintenance guards - isolation -
eye/face protection - flying debris
controlled.
Electricity
Electrocution - overhead/underground
services- any leads damaged or poorly
insulated - temporary repairs -no testing and
tagging - circuits overloaded - non use of
Leads good condition and earthed - no
temporary repairs - no exposed wires -
good insulation - no overloading - use of
protective devices - testing and tagging -no
overhead/ underground services
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 7
Faridabad.
M/s Pivotal Infrastructure Pvt. Ltd. Page 131
protective devices.
Scarf folding
Poor foundation - lack of ladder access
insufficient planking - lack of guardrails and
toe boards - insufficient ties or other means -
all scaffolds incorrectly braced or stabilized to
prevent overturning.
All scaffolds correctly braced and
stabilized - 3:1 height to base ratio - firm
foundation, plumb and level - ladder
access provided and used - proper platform
(3 planks/675 mm) - planks secured -
guardrails and toe boards - 900mm to
1100mm high, within 200mm of working
face, mid-rail.
Ladders
Carrying loads - not secured against
dislodgement -defective ladders - not
sufficient length - wrong positions -
incorrectly placed (angles, in access ways,
vehicle
movements
Secured against movement or footed -
ladders in good condition - regularly
inspected - extend 1m above platform - 4:1
angle - out of access ways, vehicle
movements - climbing - no carrying loads -
3 points of contact - no higher than 3rd
step
down - use for access only, not working
platforms.
Excavations
Trench collapse - material falling in undetected
underground services - falls - hazardous
atmosphere struck by traffic and mobile plant.
Soil stability known - no water
accumulation - existing services known -
material 600 mm from edge - clear of
suspended loads - hardhats/PPE - ladders -
public protection – atmospheric testing -
traffic controls - Emergency Plan.
Gas Cutting and Welding
Fire - welding flash, burns, fumes,
electrocution in wet conditions - flashback in
oxygen set, leaking cylinders, acetylene
cylinders lying down - poorly maintained
Welding flash and burns controlled with
PPE and shields -fumes controlled with
ventilation and PPE
(in good condition and properly positioned)
,Gas cylinders be kept upright & secured
position (properly tied) - combustible
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 7
Faridabad.
M/s Pivotal Infrastructure Pvt. Ltd. Page 132
leads.
materials to be kept at secured place to
avoid fire & Fire Extinguishers to be kept in
fire prone area with training to people for its
use.
Noise
Unknown noise levels - known noise levels
over 85 decibels
Levels below 85 decibels - proper
protection.
Falling Material
Fall during carrying/Lifting materials-
dislodged tools and materials from overhead
work areas.
Materials to be secured – kept away from
edge - toe boards –Use of hard hats.
Craneage & Lifts
Display of carrying capacity i.e load (No. Of
person), incorrectly slung, defective lifting
equipment, unsecured loads, craning in close
proximity to building people and plant - falls -
falling materials.
Periodic testing by competent authority -
correctly slung/secured loads, lifting
equipment good condition - use of proper
hand signals - falls while unloading
controlled.
• Visitors Presence at site
Falls - struck by - dropped materials - roading
accidents -insufficient hoarding or fencing -
pedestrian access past site - mechanical plant
movement on and off site.
Sufficient hoarding - fencing and barricades
- safe pedestrian access past site traffic
management for loading and delivery -
construction separated from occupied areas
of projects.
7.2.2 Emergency Response Plan (ERP)
The overall objective of an Emergency Response Plan (ERP) is to make use of the combined
resources at the site and outside services to achieve the following:
1. To localize the emergency and if possible eliminate it;
2. To minimize the effects of the accident on people and property;
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 7
Faridabad.
M/s Pivotal Infrastructure Pvt. Ltd. Page 133
3. Effect the rescue and medical treatment of casualties;
4. Safeguard other people;
5. Evacuate people to safe areas;
6. Informing and collaborating with statutory authorities;
7. Initially contain and ultimately bring the incident under control;
8. Preserve relevant records and equipment for the subsequent enquiry into the cause and
circumstances of the emergency;
9. Investigating and taking steps to prevent reoccurrence
The ERP is therefore related to identification of sources from which hazards can arise and the
maximum credible loss scenario that can take place in the concerned area. The plan takes into
account the maximum credible loss scenario - actions that can successfully mitigate the effects of
losses/ emergency need to be well planned so that they would require less effort and resources to
control and terminate emergencies, should the same occur.
Main hazards identified for the project include hazards pertaining to fires in buildings and fire in
diesel storage areas, earthquake and LPG leakage and an ERP pertaining to these is described in
the following section.
7.3 RESPONSE IN CASE OF EARTHQUAKE
7.3.1 Response Procedures for Occupants
If indoors:
1. Take cover under a piece of heavy furniture or against an inside wall and hold on.
2. Stay inside: The most dangerous thing to do during the shaking of an earthquake is to try to
leave the building because objects can fall on you.
If outdoors:
Move into the open, away from buildings, streetlights, and utility wires. Once in the open, stay
there until the shaking stops.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 7
Faridabad.
M/s Pivotal Infrastructure Pvt. Ltd. Page 134
If in a moving vehicle:
Stop quickly and stay in the vehicle. Move to a clear area away from buildings, trees, overpasses,
or utility wires. Once the shaking has stopped, proceed with caution. Avoid bridges or ramps that
might have been damaged by the quake.
After the quake
After the quake be prepared for aftershocks.
Although smaller than the main shock, aftershocks cause additional damage and may bring
weakened structures down. Aftershocks can occur in the first hours, days, weeks, or even months
after the quake.
Help injured or trapped persons.
Give first aid where appropriate. Do not move seriously injured persons unless they are in
immediate danger of further injury. Call for help.
Remember to help those who may require special assistance--infants, the elderly, and people
with disabilities.
Stay out of damaged buildings.
Use the telephone only for emergency calls.
7.3.2 Response Procedure for Emergency Team
1. Formulate an Emergency Response Team for earthquake response.
2. Using the public address system, inform residents of response procedures discussed above.
3. Inform the necessary authorities for aid.
4. Ensure no person is stuck beneath any debris, in case of a structural failure.
5. Ensure that all occupants standing outside near the buildings are taken to open areas.
6. Ensure that the first aid ambulance and fire tender vehicles are summoned if necessary.
7. Inform the nearby hospitals if there are any injuries.
8. Check the utilities and storage tanks for any damage.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 7
Faridabad.
M/s Pivotal Infrastructure Pvt. Ltd. Page 135
7.4 RESPONSE FOR LPG LEAKAGE
The affected area should be evacuated and cordoned off immediately
Initiate an Emergency Response Team for LPG leakage.
Shut down the main valves in the gas bank.
Ensure that only concerned personnel are present in the affected area and all other personnel and
visitors are moved to the nearest assembly points.
Rescue trapped personnel, also check if any personnel are unconscious in the area and
immediately move them outside and provide first aid. Ambulance should be summoned to take
injured personnel to the nearest hospital.
Personnel in the nearby buildings to close all doors and windows to prevent entry of the leaked
gas.
Source of leakage to be traced and isolated from all the other areas. And if required use pedestal
fans to bring down the gas concentration.
In case of a fire follow the instructions in case of fire.
7.5 RESPONSE IN CASE OF FIRE
Required response during in the event of a fire should be described in signs located in the lobby.
On sighting a fire, it should be immediately informed to the environment manager giving the
exact location and type of fire in detail.
Initiate the Emergency Response Team for fires.
If the fire is small, engage in extinguishing the fire using the nearest fire extinguisher.
Guide the Emergency Response Team staff to the emergency assembly point.
The Emergency Response Team should immediately inform the nearest dispensary and security
force. If required a fire tender should be summoned.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 7
Faridabad.
M/s Pivotal Infrastructure Pvt. Ltd. Page 136
The response team should immediately move to the point of fire and take all necessary steps to
stop the fire. If the fire is not controllable and spreads then the manager in charge should inform
the district authorities and call for external help.
The Emergency Response Team will provide immediate relief to the injured residents at the
scene of incident. Any injured persons should be evacuated on priority to the dispensary or one
of the nearest hospitals based on their condition.
Instructions for occupants
Get out of buildings as quickly and as safely as possible.
Use the stairs to escape. When evacuating, stay low to the ground.
If possible, cover mouth with a cloth to avoid inhaling smoke and gases.
Close doors in each room after escaping to delay the spread of the fire.
If in a room with a closed door.
If smoke is pouring in around the bottom of the door or if it feels hot, keep the door closed.
Open a window to escape or for fresh air while awaiting rescue.
If there is no smoke at the bottom or top and the door is not hot, then open the door slowly.
If there is too much smoke or fire in the hall, slam the door shut.
Stay out of damaged buildings.
Check that all wiring and utilities are safe.
A state of the art fire fighting system is proposed for the project to prevent and control fire
outbreaks. The fire fighting system will consist of portable fire extinguishers, hose reel, wet riser,
yard hydrant, automatic sprinkler system, and manual fire alarm system. The Group Housing
colony will also be provided with automatic fire detection and alarm system.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 7
Faridabad.
M/s Pivotal Infrastructure Pvt. Ltd. Page 137
7.6 RESOURCE CONSERVATION
The project will lead to utilization of various natural resources. As an environmentally
responsible corporate, the developers endeavor to conserve these resources by judicious
management and recycling and strive to build up these resources where possible.
Water Resources: The project will not use groundwater resources during both the construction
and operation phases of the project. Given the national water scenario, where availability if fresh
water is fast dwindling use of the same cannot be emphasized. Following means are proposed to
be adopted for conservation of this life sustaining resource:
No withdrawal of groundwater: The project will be supplied during construction phase by
Private water tanker suppliers as per IS 456:2000 and in operational phase by Municipal
Corporation of Faridabad.
Reduced use of water: To further minimize the use of available freshwater, various low flow
fixtures may be provided such as Low flow flushing systems, waterless urinals, and tap aerators.
Awareness will also be spread amongst the residents on the following lines:
Timely detection and repair of all leakages;
Turning off tap while brushing teeth;
Use of mug rather than running water for shaving;
Avoiding/minimizing use of shower/bath tub in bathroom;
Turning off faucets while soaping and rinsing clothes;
Using automatic washing machine only when it is fully loaded;
Avoiding use of running water while hand-washing;
Avoiding use of running water for releasing ice tray ahead of time from freezer;
Turning off the main valve of water while going outdoor;
Avoiding use of hose for washing floors; Use of broom may be preferred;
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 7
Faridabad.
M/s Pivotal Infrastructure Pvt. Ltd. Page 138
Watering of lawn or garden during the coolest part of the day (early morning or
late evening, hours) when temperature and wind speed are lowest. This reduces
losses due to evaporation.
Planting of native and/or drought tolerant grasses, ground covers, shrubs and
trees. Once fully grown, they need not to be watered frequently.
Avoiding over watering of lawns. Good rains eliminate the need for watering for
more than a week.
Setting sprinklers to water the lawn or garden only, not the street or sidewalk;
Avoiding installation or use of ornamental water features unless they recycle the
water and avoiding running them during drought or hot weather;
Installation of high-pressure, low-volume nozzles on spray washers;
Replacement of high-volume hoses with high-pressure, low-volume cleaning
systems;
Equipping spring loaded shutoff nozzles on hoses;
Installation of float-controlled valve on the make-up line, closing filling line
during operation, provision of surge tanks for each system avoid overflow;
Washing vehicles less often, or using commercial car wash that recycles water;
Treatment and Recycling: The sullage generated from the sites will be treated in an on-site
Sewage Treatment Plant. This will enable the treated sullage to be used for flushing and
landscaping thereby reducing the requirement of freshwater for these purposes.
Construction materials: As it is an Revision & Expansion of Group Housing Project, the
project will require various kinds of natural construction materials such as sand, gravel etc. It is
proposed for prior estimation of required quantities of these materials and procurement only as
per requirement. This will also result in cost-efficiency. Excavated soil from the project site will
be used within the site to the extent feasible. Excess soil will be made available to the
construction sites, as per need.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter - 7
Faridabad.
M/s Pivotal Infrastructure Pvt. Ltd. Page 139
Energy: To conserve the energy resources, good practices will be followed during the
construction phase such as turning off lights and equipments when not in use, ensuring fuel
efficiency of motors and vehicles through proper maintenance and minimal work at night. The
principles of energy conservation will also be embedded in the buildings through use of energy
efficient fixtures, maximum availability of natural light and use of solar energy for street
lighting.
7.7 RESETTLEMENT AND REHABILITATION
The project will not result in displacement of any local population and hence, does not require a
resettlement and rehabilitation study.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 8
Faridabad
M/s Pivotal Infrastructure Pvt. Ltd. Page 140
CHAPTER-8
PROJECT BENEFITS
8.1 GENERAL
The project site is situated at Village Mujheri, Sector 70, Faridabad Haryana. The project will be
developed on a total area of 82,232.12 m2. The site is well connected to NH – 2, Ballabgarh
Railway Station and Safdarjung Airport. There are many educational institutions and colleges in
the nearby area around the project site.
The salient features of the project include:
Fire Fighting system as per NBC
Emergency Alarm System
Basement parking
Multi-tiered security
Advanced fire protection systems
Seamless telecommunication networks
Backup power supply
8.2 PHYSICAL INFRASTRUCTURE
“Royal Heritage” Revision & Expansion of Group Housing Project will help in meeting the
growing residential needs of people; it also provides state-of-the-art apartments and modern
terms of comfort and safety of its residential units. Care has been taken to provide the occupants
and visitors with necessary facilities as power, water supply, parking spaces, and broad roads
that are safe and secure.
8.3 SOCIAL INFRASTRUCTURE
An Revision & Expansion of Group Housing project of this scale sets in an overall development
of the region, maintenance of existing roads, power supply and water supply, since a large Group
Housing generally brings the focus of the development authorities in the locality.
8.4 ECONOMIC BENEFITS
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 8
Faridabad
M/s Pivotal Infrastructure Pvt. Ltd. Page 141
The project will entail positive impact on the local economy in a convenient way. The
construction phase of the project will engage a large number of construction workers, whether
skilled, semi-skilled or unskilled. The workers will also be ensured welfare facilities such as
drinking water, sheds for resting, medical aids, and aid in children’s education.
In meeting the day-to-day and recreational demands of the residents of the site, the region is also
likely to develop a number of shopping and amusement facilities, thereby, further stimulating the
local economy.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 142
CHAPTER-9
ENVIRONMENTAL MANAGEMENT PLAN
9.1 INTRODUCTION
Identification and prediction of impacts further needs to suggest the mitigate measures which
would play a vital role in prevention of environmental degradation during construction and
operational phase of the Group Housing Project. This leads to preparation of Environmental
Management Plan (EMP), therefore EMP forms an imperative part of EIA process.
The Environmental Management plan is a site specific plan developed to ensure that the project
is implemented in an environmentally sustainable manner where all contractors and
subcontractors, including consultants if any, understand the potential environmental risks arising
from the project and take appropriate actions to minimize those risks. EMP also ensures that the
project implementation is carried out in accordance with the planned design and by taking
appropriate mitigates actions to reduce adverse environmental impacts during project’s life cycle.
The project will create certain inevitable impacts, mainly during construction phase, although
within permissible limits as mentioned in Chapter 4 and can be reduced significantly with the
help of effective implementation of a well-designed EMP. The potential environmental impacts,
which need to be regulated, are mentioned below:
Air pollution due to the emission of particulate matter and gaseous pollutants from
operation of D.G Sets during power failure and vehicular movement;
Noise pollution due to various noise generating equipment as well as vehicular
movement;
Water resource management to ensure continuous water supply.
Sullage generation from sanitary/domestic activities; and
Generation of municipal solid wastes from residences, maintenance of roads, parks,
common areas including constructional, electrical and plumbing wastes.
Energy conservation methods.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd . Page 143
Maintenance of Building Management Systems and emergency aids.
To ensure better environment in & around the project site, effective EMP is developed
separately for construction and operational phase.
9.2 ENVIRONMENTAL MANAGEMENT STRATEGIES
Strategy for environmental management in construction work should be based on three-pronged
approach comprising of:
Pollution prevention.
Pollution control.
Protection of pollution recipients.
9.2.1 Topography and Physiographic
During the development, construction and post construction phase of the “Royal Heritage”
Revision & Expansion of Group Housing Project, no significant impact is anticipated on local or
regional topography and Physiographic, hence exhaustive management plan is not required. It is
however proposed to carry out extensive turfing with local species apart from proposed
plantations and greens.
9.2.2 Soil
9.2.2.1 Development & Construction Phase
During the construction phase, various kinds of wastes are generated that will be disposed in
varied ways. The following measures will be taken to prevent soil contamination at site and
ensure waste management:
Vegetation and top soil management:
Remove vegetative cover only from the specific site on which construction will take
place.
Plantation as proposed shall be started at the earliest.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd . Page 144
The top soil will be stripped from constructional areas and stockpiled for later reuse in
landscaping.
Promote use of organic fertilizers.
Construction of erosion prevention troughs, as deemed necessary.
To prevent the erosion of excavated loose soil produced as a result of excavation, site
preparation activities and excavation work would be undertaken during dry season after
monsoon is over.
Construction Debris:
Fuel and oil would be stored in cement lined storage yard and handled carefully to
prevent soil contamination through leakage or spillage.
All metal, paper, plastic wastes, debris and cuttings would be collected from site as soon
as particular construction activity is over.
During construction of flexible pavement, bitumen wastes will be collected (if any) and
disposed in environmentally sound manner.
The number, frequency and area of movement of heavy machinery will also be restricted.
Recycling of construction wastes into aggregates for use in the project site.
Used oil from DG Sets shall be stored in HDPE drums in isolated covered facility and
disposed off as per the Hazardous Wastes (Management Handling Trans boundary
movement rules 2008.)
Wastes from the labor camps will be collected and disposed as per the existing practices
in the site.
9.2.2.2 Post Construction Phase
To prevent soil contamination at site, the most important aspect is to manage the solid wastes
that will be generated during the operation phase. The Environmental Management Plan for the
solid waste focuses on three major components during the life cycle of the waste management
system i.e. collection, transportation, and treatment or disposal.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd . Page 145
Collection and segregation of wastes
Solid waste generated from project would be collected door to door and segregated into
decomposable, recyclable and inert wastes.
Decomposable wastes will be decomposed and converted to manure to be used for
horticulture.
Recyclable waste would be sold to vendors.
Inert waste which comprises a very small amount of the total solid waste generated
would be temporarily stored within the project premises.
Waste bins would be placed at the strategic locations such as inter section of internal
roads, parks, common places, etc.
To minimize littering and odors, waste will be stored in well-designed containers/ bins
that will be located at strategic locations to minimize disturbance in traffic flow.
Care would be taken such that the collection vehicles are well maintained and generate
minimum noise and emissions. During transportation of the waste, it will be covered to
avoid littering.
Transportation:
Only the non-recyclable and non-biodegradable waste will be transported to the Govt. approved
agency. The segregation, transportation and disposal of wastes will be done by the authorized
agency that will take care of the waste management of the project during the operational phase of
the project.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd . Page 146
Figure 13: Waste Management Flow Diagram
Disposal
With regards to the disposal/ treatment of waste, the management will take the services of the
authorized agency for waste management and disposal of the same on the project site during its
operational phase.
9.2.3 Hydrology
9.2.3.1 Surface water Hydrology
Development & Construction Phase
To ensure adequate passage of the storm water as per the regional drainage pattern, water
channels will be provided. It is also suggested to avoid excavation during monsoons. Chemicals
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd . Page 147
such as paints and varnishes and oil/ grease will be stored under covered and cemented areas.
Wash offs containing these chemicals will be drained into impervious trains for disposal as
hazardous wastes.
9.2.3.2 Ground water Hydrology
Development & Construction Phase
The water requirement during the construction period will be met by tertiary treated STP from
private water tanker suppliers as per IS 456: 2000. The following are also proposed to further
reduce the demand of freshwater:
Curing water will be sprayed on concrete structures and free flow of water not allowed.
After liberal curing on the first day, all concrete structures will be painted with curing
chemical to save water to stop daily water curing hence save water.
Concrete structures will be covered with thick cloth/gunny bags and then water sprayed
on them to avoid water rebound and ensure sustained and complete curing.
Pools will be made using cement and sand mortar to avoid water flowing away from the
flat surface while curing.
Water ponding will be done on all sunken slabs. This will also highlight the importance
of having an impervious formwork.
Post Construction Phase
It is proposed to conserve groundwater resources through the combined means of water resource
development, minimized water consumption and reuse of treated sullage to reduce freshwater
demand.
9.2.3.3 Water Resource Development
The storm water disposal system for the premises shall be self-sufficient to avoid any
collection/stagnation and flooding of water. The amount of storm water run-off depends upon
many factors such as intensity and duration of precipitation, characteristics of the tributary area
and the time required for such flow to reach the drains. The drains shall be located near the
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd . Page 148
carriage way along either side of the roads. Taking the advantage of road camber, the rainfall run
off from roads shall flow towards the drains.
9.2.4 Storm Water Drainage
The storm water disposal system for the premises shall be self-sufficient to avoid any
collection/ stagnation and flooding of water. Underground pipe drain will be connecting
to the drain along the service road outside the site. The system will be proposed after
studying the site conditions and considering the following factors:-
• The pattern of slopes of terrain of site.
• The existing conditions of site and surrounding.
• The final levels and patterns of different type of roads.
Minimal Water Consumption
To reduce the water consumption, awareness along the following lines will be spread amongst
the management and maintenance team:
Installation of water meters conforming to ISO standards at inlet and outlet point of
water supply.
To further lower the water consumption, options of Low flow flushing systems,
sensor based fixtures, and tap aerators etc will be explored.
Leak detection
Drip irrigation for shrubs and trees
Use of low-volume, low-angle sprinklers for lawn areas
The message of water conservation will be spread amongst the residents through awareness
campaigns and pamphlets. Following tips shall be provided to the residents for conserving water.
Timely detection and repair of all leakages;
Turning off tap while brushing teeth;
Use of mug rather than running water for shaving;
Avoiding/minimizing use of shower/bath tub in bathroom;
Turning off faucets while soaping and rinsing clothes;
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd . Page 149
Using automatic washing machine only when it is fully loaded;
Avoiding use of running water while hand-washing;
Avoiding use of running water for releasing ice tray ahead of time from freezer;
Turning off the main valve of water while going outdoor;
Avoiding use of hose for washing floors; Use of broom may be preferred;
Watering of lawn or garden during the coolest part of the day (early morning or late
evening, hours) when temperature and wind speed are lowest. This reduces losses
due to evaporation.
Planting of native and/or drought tolerant grasses, ground covers, shrubs and trees.
Once fully grown, they need not to be watered frequently.
Avoiding over watering of lawns. Good rains eliminate the need for watering for
more than a week.
Setting sprinklers to water the lawn or garden only, not the street or sidewalk;
Avoiding installation or use of ornamental water features unless they recycle the
water and avoiding running them during drought or hot weather;
Installation of high-pressure, low-volume nozzles on spray washers;
Replacement of high-volume hoses with high-pressure, low-volume cleaning
systems;
Equipping spring loaded shutoff nozzles on hoses;
Installation of float-controlled valve on the make-up line, closing filling line during
operation, provision of surge tanks for each system avoid overflow;
Washing vehicles less often, or using commercial car wash that recycles water.
Re-use of treated sullage
Treated sullage from the site will be recycled for landscaping, flushing and HVAC cooling to
further reduce demand on freshwater resources. This will be achieved by treating the sullage
from the site in a proposed Sewage Treatment Plant of capacity 960 KLD.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd . Page 150
The treated sullage conforming to standards for effluent discharge on land will be reused to meet
various non-potable and non-contact requirements of the Revision & Expansion of the Group
Housing Project.
9.2.3.4 Surface water Quality
Development & Construction Phase
To mitigate the impacts of soil erosion during first rain and generation of sullage from
construction labor camps, the following measures are proposed;
Excavation during dry season and proper management of excavated soils,
Clearing all debris from site as soon as construction is over,
Provision of proper hutment and toilet facilities for construction labor,
Proper disposal of sullage generated at site.
9.2.3.5 Ground water Quality
Development and Construction Phase
To ensure against any groundwater pollution through leaching of soil, solid waste management
plan ensuring timely collection of wastes will be followed. The collected wastes will be stored at
designated area and disposed as per the standard procedures in line with the statutory
requirements.
Post Construction Phase
The ground water pollution can arise from improper waste handling or by recharge of
groundwater through contaminated storm water. A well planned solid waste management as
discussed in chapter 2 is proposed for the operation phase that will ensure against any chances of
soil or groundwater pollution on this account.
Landscaping water enters the soil and finally the groundwater. It is thus of utmost importance
that only clean water is used for horticulture purposes. The water from the households will
contain significant amounts of detergent and soap that is undesirable for plants, soil and in
groundwater. Hence, it is proposed to treat sullage from the sites up to tertiary level, and be used
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd . Page 151
for landscaping only thereafter. Regular monitoring of treated sullage shall be carried out to
ensure that all parameters are within acceptable levels.
9.2.4 Air Quality
9.2.4.1 Development and Construction Phase
The construction phase for the Revision & Expansion of this Group Housing Project is about
3years (approx), causing only marginal impact on ambient air quality from constructional
activities, unloading of construction materials, cement, soil and vehicular movement etc. The
main pollutant of concern is PM 2.5 PM 10 (dust). Likewise, following mitigation measures will
be adopted during this phase to mitigate the impacts on ambient air:
Installation of batch plant at isolated place and providing cover shed around
plants.
Loading and unloading of cement and other material in covered shed.
Providing dust suppression system in unloading area (as per requirement).
Developing avenue and curtain plantation on the internal roads and peripheral
plantation around the site to protect the movement of dust and other pollutants.
Cover scaffolding, hosing down road surfaces and cleaning of vehicles.
On-Road- Inspection for black smoke generating machinery.
Vehicles having pollution under control certificate will be allowed to operate.
Use of covering sheets for trucks to prevent dust dispersion from the trucks.
Reducing the speed of a vehicle to 20 km/hr to reduce emissions on site.
All material storages will be adequately covered and contained.
Training to the workers to reduce idling time of machines that otherwise tends to
produce hydrocarbons ad carbon monoxide.
Best practices for maintenance and repair of all machineries and equipments.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd . Page 152
9.2.4.2 Post Construction Phase
During the post construction phase, following measures will be adopted for pollution control in
the Revision & Expansion of this Group Housing Project:
Adequate stack height for DG Sets
Traffic pollution management
Plantation development
DG Sets: The running of DG sets will result in emission of various pollutants. To achieve
adequate natural dispersion, adequate stack height will be provided as per guidelines of Central
Pollution Control Board (CPCB) for 4 x 1500 kVA and 1 no. of DG sets of 750 kVA
Traffic pollution management: Internal roads would be maintained in good conditions to
control the dust emissions. Awareness will be raised amongst the residents for use of low sulphur
fuel.
Plantation development: Vegetation is an effective means for controlling air pollution due its
dual action of acting as a barrier between the source of emission and receptors and also as a sink
for various pollutants. It is proposed to develop plantation of species effective in absorption of
expected pollutants at site, along the internal roads and on the periphery of the Group Housing
Project. Suggested species for plantation are:
Cassia fistula(Amaltas)
Delonixregia (Gulmohar)
Bauhinia purpurea (Kachnar)
Dalbergiasissoo (Shisham)
9.2.5 Noise Levels
9.2.5.1 Development and Construction Phase
During the construction phase, some noise will be generated through the operation of
construction machines, excavators, DG sets, etc. Following measures would be taken; into
consideration to mitigate the noise at construction site:
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd . Page 153
Use of well-maintained equipment fitted with silencers and providing noise
shields near the heavy construction operations
Acoustic enclosures would be provide to DG sets at the construction site,
Earmuff and other protection devices shall be provided to laborers working in
high noise generating machines.
High noise activities shall be carried out during daytime.
9.2.6 Post Construction Phase
The main sources of noise during this phase are the intermittent use of DG Sets and traffic. The
principles of noise emission control and screening are proposed for the two different scenarios of
noise generation.
9.2.6.1 Noise emission control
All the D.G. Sets will be provided with acoustic enclosures ensuring 25 dB (A) insertion loss or
for meeting the ambient noise standards whichever is higher as per CPCB norms. It will be
ensured that the manufacturer provides acoustic enclosures as an integral part with Diesel
Generator Sets.
Barriers:
Trees having thick and fleshy leaves with flexible petioles having capacity to withstand vibration
are suitable. Heavier branches and trunk of the trees also deflect or refract the sound waves. The
following species are proposed to be used in a greenbelt especially surrounding housing groups
and along the periphery of the project.
Antocephalous cadamba (Kadam)
Polyathia longifolia (Ashok)
Terminalia arjuna (Arjun)
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd . Page 154
9.2.7 Biological Environment
9.2.7.1 Development and construction phase
During the development, construction and post construction phase, no tree will be cut and
therefore no impact is anticipated on terrestrial ecology. Site clearing shall be carried out strictly
as per plan. Workers shall be advised against cutting, uprooting, coppicing of trees or small trees
present in and around the project site for cooking. Workers shall also be discouraged from
wandering in nearby areas with plantation or dense vegetation.
Further, shelter belt will be developed on the periphery and along the internal roads of project
site during the construction phase itself that will act as a curtain to restrict the movement of
pollutants from either side of the project and improve site aesthetics.
9.2.7.2 Post construction phase
During the post construction phase, shelter belt will be developed and maintained. Ornamental
plant species and grasses will be planted in open space within the premises. 30.94% of Net
Planned area is proposed to be maintained green in the project site.
9.2.8 Demographic and Socio-Economic Environment
9.2.8.1 Development and Construction Phase
During the development and construction phase of the Revision & Expansion of Group Housing
Project, more than 200 skilled, semiskilled and unskilled workers will get direct and indirect
employment opportunities which will have beneficial impact on the socio-economic conditions
of the area.
Following suggestions are given to strengthen the beneficial impacts on the socio-economical
environment.
All the applicable guidelines under relevant acts and rules related to labor welfare and
safety shall be implemented during the construction work activities.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd . Page 155
Proper sanitary and drinking water facilities should be provided to workers living in the
construction camps within the project premises.
Workers will be provided with appropriate PPEs during work.
Guarding of dangerous machine parts, maintenance of equipments as hoists and lifts will
be ensured.
Adequate provision of different types of fire extinguishers will be made.
Construction Camps will be provided with clean and safe drinking water and toilet
facilities. Domestic refuse generated at the construction camps will be disposed off on a
regular basis. First Aid Medical facilities will also be provided for the construction
workers.
9.2.8.2 Post Construction Phase
The project envisages addressing the wider goal of environmental protection through a social
investment strategy for the communities around the project. The project seeks to increase the
benefits to the local population and contribute towards meeting community’s expectation of
benefits from the project.
Some of the concerns raised by local people relate directly to the project. Concerns and
aspirations not directly related to the project were also solicited so as to identify areas that could
be addressed through socially responsible initiatives and interventions. These were:
a) Demand for employment opportunities.
b) Infrastructure development
The proposed strategy envisages addressing the wider goal of sharing benefits with the local
community. The following activities would be undertaken.
Income Generation Opportunity for local community
The local people will be given preference, although they will be recruited on their individual
merit. Tender specification for post construction services will include favorable employment
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd . Page 156
opportunities towards the local population. The main principles of employment are outlined
below:
Employment strategy will provide for preferential employment during operation phase.
General recruitment procedures will be transparent, public and open to all.
Recruitment procedures will be publicized at locally prominent locations in advance.
There will be no discrimination on basis of gender, caste or other factors.
Contractors would be required to abide by the Indian labor laws regarding standards on
employee working conditions, minimum wages for workers, safety and welfare measures.
Following the appointment of the contractor, information on employment will be
available to the local community at the Panchayat office or other prominent places like
the school, frequently visited spots in the village etc. Information on the following
aspects would be provided- scale and duration of employment, type of available work and
demand projection.
Improved working conditions
The project would provide safe working conditions for the labor and other workers employed at
the facility during construction and operation phase. Conditions of employment should address
issues like minimum wages and medical care for the workers.
9.2.9 Vehicle Parking and Traffic Management
9.2.9.1 Development and Construction Phase
To ensure that the heavy vehicles transporting construction material to the site does not burden
the local traffic, it is proposed to:
Plan the movement of the heavy vehicles avoiding the peak hours (day time).
All the vehicles to the site will be provided with parking space such that there is no
waiting time along the access roads.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd . Page 157
9.2.9.2 Post Construction Phase
It is to be ensured that there will not be any sudden influx of vehicles from the Revision &
Expansion of Group Housing Project at the entrance to the project site from access road. The
available width will provide sufficient merging space for the vehicles while meeting the road.
Adequate provision has been made for car/vehicle parking within the plot. Besides, wide internal
road will also provide space for off street parking.
9.3 ENERGY CONSERVATION
The Project will be designed in such a way that natural light and air will be enhanced in the
residences. Houses at the Revision & Expansion of Group Housing Project will be energy
efficient through use of low energy consuming fixtures. Energy conservation will be achieved
through various means as given below.
Site Plan and building design:
Maximum utilization of solar light will be done
Public areas will be cooled by natural ventilation as opposed to air-conditioning
Maximize the use of natural lighting through design
The orientation of the buildings will be done in such a way that maximum daylight is
available
The water bodies and green areas will be spaced, so that a significant reduction in the
temperature can take place.
Energy saving:
Energy efficient lamps will be provided within the complex.
Constant monitoring of energy consumption and defining targets for energy conservation
Adjusting the settings and illumination levels to ensure minimum energy used for desired
comfort levels
Awareness:
Promoting resident awareness on energy conservation
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd . Page 158
Training staff on methods of energy conservation and to be vigilant to such opportunities
9.4 MANAGEMENT AND MAINTENANCE SYSTEM
Management and maintenance system is an important issue for the Group Housing Project.
During the construction phase M/s Pivotal Infrastructure Pvt Ltd. will take care for the
implementation of environmental management plan for the project. They will review the
effectiveness of implemented mitigation measures adopted by contractors and sub-contractors
from time to time. The houses will be provided with water sprinklers and fire alarms and there
will be provision of adequate number of fire extinguishers. Back up service will be provided for
all emergency equipments and machineries.
Post construction, management and maintenance of the internal services laid in Revision &
Expansion of Group Housing Project will be done by M/s Pivotal Infrastructure Pvt Ltd. and
subsequently the same shall be transferred to the local Municipality/designated authority.
9.4.1 Institutional Capacity Building
a. Reporting: For effective implementation of any system/ plan, a systematic reporting
system is essential. An Environmental Management Cell shall be set up for
implementation of the proposed Management Plan. Reporting of the results of all the
management and monitoring plan shall be submitted to the designated Project Head. The
reports shall be reviewed and parameters exceeding their limits should be identified and
the reason for the same investigated. Any requisite mitigation plan shall be taken up
accordingly.
The Environment Management Cell will be a permanent organizational set up charged
with the task of ensuring its effective implementation of mitigation measures and conduct
environmental monitoring. The major duties and responsibilities of Environmental
Management Cell shall be as given below:
To implement the environmental management plan
To assure regulatory compliance with all relevant rules and regulations
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd . Page 159
To ensure regular operation and maintenance of pollution control devices
To minimize environmental impact of operations as by strict adherence to the EMP
To initiate environmental monitoring as per approved schedule
b. Review and interpretation of monitored results and corrective measures in case
monitored results are above the specified limit.
c. Maintain documentation of good environmental practices and applicable environmental
laws for a ready reference
d. Maintain environmental related records
e. Coordination with regulatory agencies, external consultants, monitoring laboratories
f. Maintenance of log of public complaints and the action taken.
9.4.2 Hierarchical Structure of Environmental Management Cell
Normal activities of the EMP cell would be supervised by a dedicated person who will report to
the project Head.
9.4.3 Awareness and Training
Training and human resource development is an important link to achieve sustainable operation
of the facility and environment management. For successful functioning of the project, relevant
EMP would be communicated to residents and contractors.
Occupants must be made aware of the importance of waste segregation and disposal, water and
energy conservation. The awareness can be provided by periodic Integrated Society meetings.
They would be informed of their duties.
9.4.4 Environmental Audits and Corrective Action Plans
To assess whether the implemented EMP is adequate, periodic environmental audits will be
conducted by the project proponent’s Environmental division. These audits will be followed by
Correction Action Plan (CAP) to correct various issues identified during the audits.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd . Page 160
9.5 OVERALL MITIGATION MEASURES AND ENVIRONMENTAL
MANAGEMENT PLAN
Overall impact assessment of anticipated environmental impacts and mitigation measures &
environmental management plan to mitigate the potential impacts during the development &
construction and operation phase are summarized in Table 9.1.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 161
Table 9.1: Environmental Management Plan during construction and operation phases of the project.
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
1. Groundwater
Quality
Ground water
contamination
Construction Phase
Sullage generated
from Labor tents.
1. Modular STP/
Mobile
toilets
No significant
impact as majority
of laborers would
be locally deployed.
Operation Phase
Sewage treatment,
sludge disposal on
land.
Sewage will be
treated in Sewage
Treatment Plant.
Sludge will be used
for horticultural
purpose as manure.
No significant
negative impact on
ground water
quality envisaged.
In an unlikely event
of soil and ground
water
contamination,
remediation
measures shall be
implemented.
2. Groundwater
Quantity
Ground Water
Depletion
Construction Phase
Ground water will
not be used for
construction
activity.
Not Applicable
Not Applicable
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 162
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
Operation Phase
Water will be
supplied by
Municipal
Corporation of
Faridabad.
Recycling of treated
water to reduce
freshwater
requirement
Storm water
collection for Water
Harvesting.
Awareness
Campaign for
reduced water use by
occupants.
No significant
impact on ground
water quantity
envisaged.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 163
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
3. Air Quality
Dust
Emissions
Construction Phase
All heavy
construction
activities.
Dust suppression
through water
sprinkling using
water trucks,
handheld sprays and
automatic sprinkler
systems.
Vehicles
transporting loose
construction material
should be covered.
Contractors will be
advised to provide
dust masks for the
employed labor.
Not significant
because dust
generation will be
temporary and will
settle fast due to
dust suppression
techniques used.
Emissions of
PM, SO2, NO2
and CO
Construction Phase
Operation of
construction
equipment and
vehicles during site
development.
Rapid on site
construction
Improved
maintenance of
equipment’s.
Not significant
Regular monitoring
of emissions and
control measures to
reduce the emission
levels.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 164
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
Operation Phase
Power generation
through D.G. Set
Operation.
Emissions from
vehicular traffic.
Use of low Sulphur
diesel.
Stacks will be
provided of adequate
height as per CPCB
guideline.
Shelter belt to be
provided with
specified species to
help reduce PM
levels.
Not significant as
D.G. Set would be
used as power
back-up only.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 165
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
4. Noise
Environment
Noise
emissions
Construction Phase
Operation of
construction
equipment and
vehicles during site
development.
Equipments should
be fitted with
silencers, where
applicable and
maintained well.
Providing noise
shields near heavy
construction
operations.
Construction activity
will be limited
mostly to daytime
hours only.
Use of Personal
Protective
Equipment (PPE)
like earmuffs and
earplugs during
construction
activities.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 166
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
Operation Phase
Noise from
vehicular
movement.
Noise from D.G.
sets operation.
Peripheral
plantations.
Providing Acoustic
Enclosures on D.G.
Sets.
Not significant
Short-term
exposure within
permissible limit.
5. Land
Environment
Soil
contamination
Construction Phase
Disposal of
construction
debris.
Construction debris
will be collected and
suitably used on site
as per construction
waste management
plan.
Impact will be
local, as any waste
generated will be
reused for
construction
activities. Not
significant.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 167
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
Operation Phase
Generating
municipal solid
waste on land.
Handling of used
oil from D.G. Sets.
It is proposed that
solid waste
generated will be
managed as per
MSW rules 2000 and
amended 2002.
Collection,
segregation,
transportation and
disposal of wastes
will be done by
authorized agency.
Used oil generated
will be sold to
authorized recyclers
Not Significant
Negligible impact
6. Biological
Environment
(Flora and
Fauna)
Removal of
Flora and
Fauna on site.
Increase of
Green Cover
Construction Phase
Site development
during
construction.
Important species of
tress if any will be
identified and
marked and will be
merged with
landscape plan.
No negative impact
--
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 168
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
Operation Phase
Plantations along
the periphery of
the Group Housing
Project.
Plantations of
species that are
native to the area,
fast growing and
with good canopy
cover.
Beneficial impact
7. Socio -Economic
Environment
Population
displacement
and economic
impact
Construction Phase
No relocation is
involved.
Constructional
activities
Compensation has
been provided to the
land owners by
development
authority.
Employment for
laborers
No negative impact
Beneficial impact
--
Operation Phase
Site operation.
Project will provide
employment
opportunities.
Boost to local
market for increased
demand in goods of
daily need.
Beneficial impact
--
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 9
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 169
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
8. Traffic Pattern Increase of
Vehicular
traffic
Construction Phase
Heavy vehicular
movement during
construction.
Heavy vehicular
movement will be
restricted to daytime
only and adequate
parking facility will
be provided.
No negative impact
Operation Phase
Increased traffic
from the project.
Vehicular movement
will be regulated
inside the site
Adequate parking
space provided.
Moderate negative
impact
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 10
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 170
CHAPTER-10
SUMMARY AND CONCLUSION
10.1 PROJECT BACKGROUND
M/s Pivotal Infrastructure Pvt Ltd. intends to “Royal Heritage” Revise & Expand Group Housing
Project “Royal Heritage” at Village Mujheri, Sector 70, Faridabad, Haryana. The project though
under development has undergone an increment for better efficiency reason, The total plot area is
82,232.12 m2 (19.690 acres) & increased built up area to 1,79,297.91 sq.m.which seeks
consideration for EC.
As per EIA Notification, 2006 & its amendments for all Group Housing Projects and area
development projects covering an area of 50 ha and/ or built up area greater than 1, 50,000m2 are
designated as category 8 (b) projects and are required EIA/EMP Report to obtain prior
environmental clearance from respective State Environmental Impact Assessment Authority
(SEIAA). The project is thus categorised as 8(b) under Schedule of the Environmental Impact
Assessment Notification and requires Environmental Clearance from the State Environment
Impact Assessment Authority, Haryana since the built up area is 1,79,297.91 m2. So, EIA/EMP
study is required. The EIA/EMP study has been carried out by Grass Roots Research & Creation
India Pvt. Ltd.
For this study, the impact zone shall confine within an angular radius of 5 km from the project
boundary. For the purpose of certain environmental components, the radius has extended up to
10 km as well. The EIA is conducted to establish the baseline environmental setting in the study
area, assessment of potential impacts on different environmental components, design of
mitigation measures so as to keep impacts within acceptable limits and strengthen the positive
impacts.
The Executive Summary summarizes the findings of the EIA study to aid in decision making and
provides project related information and environmental impacts to non-technical sections of
society. The summary highlights the baseline environmental status, key environmental issues and
their likely impacts and also lists the major recommended mitigation measures to attenuate the
impacts.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 10
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 171
10.2 PROJECT SITE & CONNECTIVITY
The project is located at Village Mujheri, Sector 70, Faridabad, Haryana.The project site is
approx 3.5 km; W far from NH – 2. The nearest railway station is Ballabgarh Railway Station,
about 3.93 km; WNW of project site. The nearest airport is Safdarjung Airport which is approx.
30.77 km, NNW of the project site.
10.3 PROJECT FEATURES
The design population of the site is 9,853. Salient features of the project are:
Table 10.1: Salient Features of the project
S. No. Facility Value
1. Power Supply 11453 KVA
2. D.G. Set 5 DG sets of total capacity of 6750 kVA
(4 x 1500, 1 x 750)
3. Parking Required -2223 ECS
Proposed -2698 ECS
4. Water Supply Operational Phase: Municipal Corporation
of Faridabad
Construction Phase: Private water Tankers
5. Water Demand Fresh water-831 KLD
6. Sullage Generation 960 KLD
7. STP Capacity 1200 KLD
8. Solid waste generation 4401 kg/day
9. Manpower requirement 150-200 persons
The project will be implemented over a span of three years (approx) from the commencement of
construction.
10.4 ENVIRONMENTAL SETTING OF THE STUDY AREA
The baseline environmental status was assessed based on primary and secondary data collected
either through in-site field observation or obtained from agencies such as Irrigation Department,
India Meteorological Department (IMD), Central Ground Water Board, Geological Survey of
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 10
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 172
India, State Ground Water Department, State Pollution Control Board, Census of India and Local
Forest Department, Non -Governmental Agencies. The baseline status established from analysis
of secondary and primary data and predicted impacts are discussed below. The proposed
mitigation measures are also provided along with.
10.4.1 Land Environment
The land use pattern of the study area is mainly residential, agricultural and open & degraded
vegetation.
The construction phase of any construction project poses the threat of soil contamination and soil
erosion, mainly during the construction phase. Inadequate solid waste management may also
cause soil contamination during operation phase. The estimated waste generation during
operation phase is 4401 kg/day.
During construction phase, excavation related work will be avoided during the monsoons and
site clearing will be carried out for specific areas being developed. All wastes from site will be
regularly removed and disposed/ sold. An efficient solid waste management is proposed
comprising door-to-door waste collection, segregation of solid waste management facility within
the site, and their disposal. Solid waste will be disposed by sale of recyclable wastes to vendors.
10.4.2 Water environment
The project site is located at Village Mujheri, Sector 70, Faridabad, Haryana. The water
requirement during construction phase will be met by Private water Tankers suppliers, water as
per IS 456:2000. A combination of efficient water management to reduce water consumption,
reuse of treated wastewater to reduce freshwater demand and to replenish groundwater is
proposed to have a positive bearing on the water environment of the region.
Sewage Treatment Plant (STP) of capacity 1200 KLD for will be set up to treat waste water.
10.4.3 Air Environment
During construction phase, the major air pollutant of prime concern is PM2.5, PM10 as impacts of
other emissions such as SO2, NO2, and CO will not be significant because the nature of sources
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 10
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 173
is such that the emissions are distributed spatially as well as temporal. Monitored average PM2.5,
PM10 level exceeded NAAQS at all the five locations. The levels of PM 2.5, PM10, NO2, SO2 and
CO at all the five locations were within the standards prescribed by NAAQS at all the five
locations. Thus dust emissions from construction activities shall require comprehensive
mitigation measures and best construction practices.
Adequate stack heights will be proposed for D.G. Sets of 6750 kVA capacity (4 x 1500, 1 x 750)
above the ground to provide for sufficient dispersion of pollutants. Water sprinklers will be used
to suppress dust during construction. During the operation phase, green belt and green area
development is proposed to restrict and absorb air pollutants.
10.4.4 Noise Environment
Noise levels were observed at four locations within the study area. Levels of background noise
monitored in exceed the limits at 55 dB (A) and 45dB (A) for daytime and night time
respectively.
The noise emitted from heavy-duty construction equipments during construction period being
high shall require occupational preventive measures and temporary noise barriers for noise
attenuation. The construction period being about 3 year duration, will require significant
mitigation measures such as restricted loud noise activities to daytime, provision of PPEs and
acoustic enclosures for D.G. Sets.
In the operation phase, noise pollution will be checked through acoustic enclosures of DG Sets
and green belt plantation.
10.4.5 Biological environment
There is also no tree cutting involved in the project. Additionally, there will be avenue
plantations, Shelter belt and herbs. The proposed landscaping will include native species that will
attract local birds and insects, reduce pollution and improve aesthetics and micro-climate of the
region. Total green area (revision and expansion) of the project is 24,656.84 m2. Evergreen tall
and ornamental trees and ornamental shrubs have been proposed to be planted inside the
premises. Trees like Silver Oak, Ashoka, Palm tree, Gulmohar etc. and flowers have been
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 10
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 174
proposed to be planted inside the premises. Parks will also be developed in addition to this.
Break up of Green area is given below in Table 10.2
Table 10.2: Break up of Green Area
Type of Green Area Area (in m2)
Total Plantation Area @30.94% of net planned
area
24,656.832
water body @5% of net planned area 3,984.326
Avenue Plantation 35.36 % of the green area 8,719.528
Climber plants, lawns, parks, Herbs & Shrubs@
16.15% of the green area
3,984.326
Shelter [email protected]% of the green area 7,968.652
10.4.6 Socio-economic environment
The Group Housing Project does not call for any land acquisition and no change in the existing
land use pattern. The execution of the project will not disturb the people living in area as there
will be no blasting and large scale digging. The project will generate employment opportunities
for both skilled and unskilled workers in the vicinity, which will produce multiple effects on the
life and economy of the local people. Thus from socio-economic point of view the project is
beneficial to the people and can be executed with little hesitation.
10.4.7 Energy efficiency
The total energy demand of 11453 KVA. for the project will be met by Dakshin Haryana Bijli
Vitran Nigam. 4 DG sets of total capacity of 6750 kVA (4 x 1500 & 1 x 750) are proposed to
provide backup in case of power failure. Various provisions are made to reduce the energy
efficiency of the building, such as use of solar energy, provision of low energy fixtures, design
features to maximise sunlight and use of materials to improve energy efficiency.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 10
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 175
10.4.8 Others
Resource Conservation: A concerted effort is made towards resource conservation by way of
using recycled building materials, reduced water consumption and improving energy efficiency
of the building.
Indoor Air Quality: Special attention will be given to maintaining indoor air quality through
use of low VOC paints, provision of adequate ventilation, proper storage of chemical and
cleaning materials.
Safety:A network of manned security gates, security men, closed circuit TV and intercom
facilities are proposed to ensure safety of the occupant. The buildings will also be provided with
adequate fire tenders, fire alarms and water sprinklers.
10.5 ENVIRONMENTAL MANAGEMENT PLAN
Adequate environmental management measures will be incorporated during the entire planning,
construction and operating stages of the project to minimize any adverse environmental impact
and assure sustainable development of the area.
For the effective and consistent functioning of the campus, an Environmental Management
System (EMS) will be established at the site including an Environmental Management cell for
implementation of the EMP and monitoring plan, training and awareness, audits and
maintenance of records.
The total estimated cost of the Expansion of Group Housing Colony project is Approx. Rs 240
Crores which includes the cost of the land as well as the developmental cost.
Based on the environmental assessment, the associated potential adverse environmental impacts
can be mitigated to an acceptable level by adequate implementation of the measures as stated in
the EIA and the EMP. Some of the benefits from the project are:
Use of solar energy for street lighting
Provision of green walls and green terraces
Use of fly ash bricks.
Use of steel manufactured from recycled content.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 10
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 176
Provide permeable paving to control surface water runoff
Meet all requirements for buildings in moderate earthquake prone areas.
Extending educational and healthcare facilities to the local people.
Commitment to engaging local people and businessmen for maintenance and
repair work.
Hence, it may be concluded that the project will have significant positive economic and social
impact on the local community apart from meeting the housing needs of the occupants, without
bearing any significant adverse environmental impacts.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 10
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 177
Table 10.3: Summary matrix of predicted impacts and mitigation measures
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
1. Groundwater
Quality
Ground water
contamination
Construction Phase
Sullage generated
from Labor tents.
1. Modular STP/
Mobile
toilets
No significant
impact as majority
of laborers would
be locally deployed.
Operation Phase
Sewage treatment,
sludge disposal on
land.
Sewage will be
treated in Sewage
Treatment Plant.
Sludge will be used
for horticultural
purpose as manure.
No significant
negative impact on
ground water
quality envisaged.
In an unlikely event
of soil and ground
water
contamination,
remediation
measures shall be
implemented.
2. Groundwater
Quantity
Ground Water
Depletion
Construction Phase
Ground water will
not be used for
construction
activity.
Not Applicable
Not Applicable
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 10
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 178
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
Operation Phase
Water will be
supplied by
Municipal
Corporation of
Faridabad.
Recycling of treated
water to reduce
freshwater
requirement
Storm water
collection for Water
Harvesting.
Awareness
Campaign for
reduced water use by
occupants.
No significant
impact on ground
water quantity
envisaged.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 10
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 179
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
3. Air Quality
Dust
Emissions
Construction Phase
All heavy
construction
activities.
Dust suppression
through water
sprinkling using
water trucks,
handheld sprays and
automatic sprinkler
systems.
Vehicles
transporting loose
construction material
should be covered.
Contractors will be
advised to provide
dust masks for the
employed labor.
Not significant
because dust
generation will be
temporary and will
settle fast due to
dust suppression
techniques used.
Emissions of
PM, SO2, NO2
and CO
Construction Phase
Operation of
construction
equipment and
vehicles during site
development.
Rapid on site
construction
Improved
maintenance of
equipment’s.
Not significant
Regular monitoring
of emissions and
control measures to
reduce the emission
levels.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 10
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 180
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
Operation Phase
Power generation
through D.G. Set
Operation.
Emissions from
vehicular traffic.
Use of low Sulphur
diesel.
Stacks will be
provided of adequate
height as per CPCB
guideline.
Shelter belt to be
provided with
specified species to
help reduce PM
levels.
Not significant as
D.G. Set would be
used as power
back-up only.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 10
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 181
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
4. Noise
Environment
Noise
emissions
Construction Phase
Operation of
construction
equipment and
vehicles during site
development.
Equipments should
be fitted with
silencers, where
applicable and
maintained well.
Providing noise
shields near heavy
construction
operations.
Construction activity
will be limited
mostly to daytime
hours only.
Use of Personal
Protective
Equipment (PPE)
like earmuffs and
earplugs during
construction
activities.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 10
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 182
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
Operation Phase
Noise from
vehicular
movement.
Noise from D.G.
sets operation.
Peripheral
plantations.
Providing Acoustic
Enclosures on D.G.
Sets.
Not significant
Short-term
exposure within
permissible limit.
5. Land
Environment
Soil
contamination
Construction Phase
Disposal of
construction
debris.
Construction debris
will be collected and
suitably used on site
as per construction
waste management
plan.
Impact will be
local, as any waste
generated will be
reused for
construction
activities. Not
significant.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 10
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 183
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
Operation Phase
Generating
municipal solid
waste on land.
Handling of used
oil from D.G. Sets.
It is proposed that
solid waste
generated will be
managed as per
MSW rules 2000 and
amended 2002.
Collection,
segregation,
transportation and
disposal of wastes
will be done by
authorized agency.
Used oil generated
will be sold to
authorized recyclers
Not Significant
Negligible impact
6. Biological
Environment
(Flora and
Fauna)
Removal of
Flora and
Fauna on site.
Increase of
Green Cover
Construction Phase
Site development
during
construction.
Important species of
tress if any will be
identified and
marked and will be
merged with
landscape plan.
No negative impact
--
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 10
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 184
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
Operation Phase
Plantations along
the periphery of
the Group Housing
project.
Plantations of
species that are
native to the area,
fast growing and
with good canopy
cover.
Beneficial impact
7. Socio -Economic
Environment
Population
displacement
and economic
impact
Construction Phase
No relocation is
involved.
Constructional
activities
Compensation has
been provided to the
land owners by
development
authority.
Employment for
laborers
No negative impact
Beneficial impact
--
Operation Phase
Site operation.
Project will provide
employment
opportunities.
Boost to local
market for increased
demand in goods of
daily need.
Beneficial impact
--
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 10
Faridabad.
M/s Pivotal Infrastructure Pvt Ltd Page 185
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
8. Traffic Pattern Increase of
Vehicular
traffic
Construction Phase
Heavy vehicular
movement during
construction.
Heavy vehicular
movement will be
restricted to daytime
only and adequate
parking facility will
be provided.
No negative impact
Operation Phase
Increased traffic
from the project.
Vehicular movement
will be regulated
inside the site
Adequate parking
space provided.
Moderate negative
impact
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 11
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 186
CHAPTER-11
DISCLOSURE OF CONSULTANTS ENGAGED
Project Name: Expansion of Group Housing Colony
Name and address of
the Consultant
GRC, India (P) Ltd.
F-374,375, Sector: 63,
Noida, India
ISO 9001:2008 Certified,
QCI-NABET Accredited.
Base line data GRC, India Training and
Analytical Laboratory
Sector: 63, F- 374, 375,
Noida, India
NABL & MoEF Accredited
Laboratory.
A unit of GRC, India (P) Ltd.
Following Coordinators & Functional Area Experts are involved in EIA
EIA Coordinator Mr. K.D. Choudhury
FAE-WP Dr. P.R. Chaudhari
FAE-AP Mr. K.D. Choudhury
FAE-AQ Prof. B. Padmanabha Murty
FAE-LU Mr. P. Radhakrishnamoorthy
FAE-EB Dr. P.R. Chaudhari
FAE-NV Mr. K.D. Choudhury
FAE-SE Mr. K.N. Dutta
FAE-HG Prof. Tapan Majumdar
FAE-G Prof. Tapan Majumdar
FAE-S Dr. S.R. Maley
FAE-RH Dr. Ravindra Kode
FAE-SHW Mrs. Anasua Nag
11.1 ACCREDITION/ FROM QUALITY COUNCIL OF INDIA, QCI AND LIST
OF COORDINATORS
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 11
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 187
GR&C India Pvt. Ltd. has got accredition from QCI as per MoEF, GoI requirements.
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 11
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 188
Royal Heritage, EIA/EMP Report
Revision & Expansion of Group Housing Project,
At village Mujheri, Sector 70, Chapter 11
Faridabad
M/s Pivotal Infrastructure Pvt Ltd Page 189
The license no. 33/2010 issued by Town and Country Planning Department, Haryana foran area of 6.83125 acres for development of Group Housing Project was valid upto19.04.2014. It was submitted to esteem SEIAA, Haryana.
M/s Pivotal Infrastructure Pvt. Ltd. has already submitted application for revalidation ofthe license and acknowledgment is attached below: