  • TECHNICAL SUBMISSION PROJECT SPECIFICATION SECTION C PART 2 SECTION 3: GROUND INVESTIGATION

    IA 12/13 C 057 ST C2/S3/1 February 2013 Construction and Upgrade of Rayyan Road Project 7: Contract 1 West of New Rayyan R/A to East of Bani Hajer R/A

    PART 3 PITS AND TRENCHES 3.2 PITS AND TRENCHES GENERALLY 3.2.5 Backfilling and Restoration Add new paragraph 5 as follows: 5 Restored surfaces shall match the existing surface in both level and appearance.

  • TECHNICAL SUBMISSION PROJECT SPECIFICATION SECTION C PART 2 SECTION 3: GROUND INVESTIGATION

    IA 12/13 C 057 ST C2/S3/2 February 2013 Construction and Upgrade of Rayyan Road Project 7: Contract 1 West of New Rayyan R/A to East of Bani Hajer R/A

    PART 4 SOIL SAMPLING 4.4 GROUNDWATER SAMPLES Delete paragraph 1 and substitute with the following: 1 Groundwater samples shall be taken from each exploratory hole where groundwater

    is encountered. Where more than one groundwater level is found, each one shall be sampled separately. Where water has been previously added, the water shall be baled out before sampling so that only groundwater is present. The sample volume shall not be less than 0.25 litre.

    Where groundwater is to be sampled from rotary drilled holes using water flush the sample shall, where practicable, be taken at the start of the subsequent shift; the hole having been baled out at the end of the previous shaft. A sample of the flushing water shall be taken for analysis at the same time.

  • TECHNICAL SUBMISSION PROJECT SPECIFICATION SECTION C PART 2 SECTION 3: GROUND INVESTIGATION

    IA 12/13 C 057 ST C2/S3/3 February 2013 Construction and Upgrade of Rayyan Road Project 7: Contract 1 West of New Rayyan R/A to East of Bani Hajer R/A

    PART 5 IN-SITU TESTING, INSTRUMENTATION AND MONITORING 5.2 TESTING, INSTRUMENTATION AND MONITORING GENERALLY 5.2.2 Instrumentation and Monitoring Add new paragraph 7 as follows: 7 Previously constructed boreholes and piezometers within the Right of Way as well

    as those put down by the Contractor shall be suitably marked and protected for as long as practicable during the execution of the Works. The Engineers written agreement shall be obtained before any of these are destroyed. Any destroyed without prior agreement shall immediately be replaced by the Contractor. Regular monitoring of water levels in these piezometers and boreholes is to be conducted throughout the entire period of the Works. The regularity of the monitoring shall be to the written approval of the Engineer.

    5.3 TESTS 5.3.2 Tests in accordance with BS 5930 Add new paragraph 2 as follows: 2 For all in situ permeability testing the Contractor shall establish and record all

    relevant data relating to the history of boring the hole and the apparent natural groundwater level. He shall interpret the test results only once conditions at the time of test have become established by subsequent monitoring.

    END OF SECTION