SECTION 4 PROGRESS
Sector E3-1 : Line 3 Completed this Month and Line 1 in progress with Pipe Laying work , Rehabilitation
Works on Line 5 Completed This Month .
Sector E3-2 : Line 1 ,2 and 6 In-Progress with pipe laying Works
Sector E5 : On progress with only one replacement line 2 with Pipe Laying.
Sector E6 : lines 1 ,2 and 3 Completed and Handed Over to ADSSC this Month
Sector E8 : Line 2 and 4 In-Progress With Pipe Laying works .
Sector E10 : started This Month with Excavation Work On Line 12
Sector E14 : Started This Month with Line 2,9 and 22 with Excavation and pipe laying works and CCTV
work for Line 12,15 ,28 and 29 .
Sector E15 : Rehabilitation Work Completed 100 %
Sector E16 : Rehabilitation Work Completed 100 %
Sector E16-2 : Started this Month and CCTV Work for Rehabilitation works Completed for Lines 9 , 10
and 28 .
Sector E19: Proposed new line 5, 8 , 14 completed 100 % and Handed Over to ADSSC . Proposed New
Lines 6, 10 and are in progress with laying of pipe, installation of new manholes, backfilling, compaction
and testing.
Sector E19/01: Replacement line 32 is completed 100 % and Handed Over to ADSSC.
Sector W1: All Replacement lines are completed 100 % except reinstatement Works for some Lines .
Sector W2: All the Lines in This Sector Completed and handed Over to ADSSC This Month Except Line
No. 6 still in progress with Pipe Laying work
Sector W3 : Started This Month with Rehabilitation works .
Sector W4: Lines 8 and 9 Completed 100 % and lines 2, 3 , 4 ,5 , 6 And 10 in progress with laying of
pipe, backfilling ,compaction and testing
Sector W5: The All lines in This Sector completed and handed over.
Sector W6 : Started This Month and Line No : 11 , 12 & 13 Completed 100 % and Line 2 & 4 in-progress
Sector W7 : Started This Month with Lines 13,14 & 15 in progress with Lowering excavation
7/28/2019 Section 4 - Progress
2/5
Overall project progress as per the update of the Approved Programme is 15.42% compared to planned
54.72% as detailed in attachment S4-2.
The statuses of the Submittals are as follows:
SL No. SubmittalsTotal No. of
Submittals
Total No.
SubmittedApproved
1 Method of Statements 42 41 39
2 Material Submittal 25 25 25
3 Shop Drawings:
Typical Drawing
General Shop Drawings
23
150
23
81
23
664 Sub-Contractors Prequalification
Documents
5 5 5
7/28/2019 Section 4 - Progress
3/5
CRITICAL PATH ANALYSIS PROGRAMME
Longest path method of PERT (Project Evaluation Review Technique) is considered in identifying the
critical path of this project which can be directly extracted from the actual programme (sequence of
activities that reflects the actual situation). After updating with the actual datas gathered on site, critical
activities that lies on the Longest Path is reflected in Attachment S4-1.
7/28/2019 Section 4 - Progress
4/5
UPDATE OF THE APPROVED PROGRAMME
Updated programme was derived from the Approved Baseline Programme updated with the actual
datas such as percent complete of activities that are on progress with the actual starting dates and
finishing dates as applicable. Original sequence as per the approved baseline programme was kept
although several out of sequence activities actually happened. Attachment S4-2 reflects the updated
programme after applying the actual datas updated as of 25 January 2012.
7/28/2019 Section 4 - Progress
5/5
PLANNED v/s ACTUAL PROGRAMME
Planned vs Actual Programme can be seen in attachment S4-3. Actual Programme is updated with the of
the Approved Baseline Programme with the Actual dates based on progress Gathered from site , Cut-Off
date Considered is as of 25 January 2012 Planned overall progress to date using earned value is
supposed to be 54.72 % as per the Aprroved Baseline Programme, while the actual measured progress
as per the actual programme as of the cut-off date is equals to 15.42%.