59
Section 2 Procedures and Tests -Plant- Job Guide – Concrete Paving Plant Monitor Contact Report – Paving Contractor Mix Designs JMF Concrete Aggregate Worksheet JMF Moving Average Summary JMF Adjustment Worksheet Well Graded Aggregate Incentive -#200 Wash Coarse Aggregate Quality Incentives Worksheets WC Ratio Calculation Worksheet WC Ratio Incentive Concrete Ingredient Summary Sample Cards -Field- Job Guide – Concrete Paving Inspector Air Content Worksheet Concrete Test Beam Data Probing, Coring, Texture Report and MIT-SCAN T2 Troubleshooting (IMCP Manual) Operation of MIT SCAN T2 Device

Section 2 - Procedures and tests

Embed Size (px)

Citation preview

Page 1: Section 2 - Procedures and tests

Section 2

Procedures and Tests

-Plant- Job Guide – Concrete Paving Plant Monitor

Contact Report – Paving Contractor Mix Designs

JMF Concrete Aggregate Worksheet JMF Moving Average Summary

JMF Adjustment Worksheet Well Graded Aggregate Incentive

-#200 Wash Coarse Aggregate Quality Incentives Worksheets

WC Ratio Calculation Worksheet WC Ratio Incentive

Concrete Ingredient Summary Sample Cards

-Field-

Job Guide – Concrete Paving Inspector Air Content Worksheet

Concrete Test Beam Data Probing, Coring, Texture Report and MIT-SCAN T2

Troubleshooting (IMCP Manual) Operation of MIT SCAN T2 Device

Page 2: Section 2 - Procedures and tests

2

Page 3: Section 2 - Procedures and tests

JOB GUIDE CONCRETE PAVING PLANT MONITOR 1. Review the Contract and Plans:

• Become familiar with applicable specifications based upon the size of the project and delivery method of concrete.

• Review incentives and disincentives available. • Check Schedule of Materials Control for testing rates and sample sizes. • Attend the pre-construction meeting if possible.

2. Preliminary Testing and Mix Design Requirements:

• Verify the Contractor’s aggregate sources and make sure preliminary testing if required has been done well in advance of the project start date.

• Make sure the Contractor submits mix designs and gradations/job mix formulas (JMF) to the Concrete Engineering Unit for review and approval a minimum of 21 days prior to initial placement of mix design.

3. Become familiar with concrete batching and mixing equipment and the duties of the Contractor. • Obtain the Contractor’s organizational chart listing names, phone numbers and emails of

individuals responsible for mix design, process control administration and inspection. • Inspect batch trucks for compliance with specifications

4. Complete a Concrete Paving Contact Report (Form 2164): • Review the Contractor’s concrete paving combination plant-lab office for compliance. • Verify whether the Contractor has an electronic means of communication (email) • Check that scales and water meter are calibrated • Obtain pre-production coarse aggregate samples for quality testing in accordance with

the Schedule of Materials Control. Fill out Aggregate Sample I.D. cards completely and include with lab samples.

• Verify cement, fly ash, and admixtures are on the Certified/Approved Products list. • Obtain cement, fly ash, and admixtures samples from the Contractor per the Schedule of

Materials Control. Provide sampling containers and witness sampling when possible. • Include cementitious invoices when submitting samples to the laboratory for testing. • Fill out lab sample I.D. cards completely and enclose them with cement, fly ash, and

admixture samples. 5. During Concrete Production:

• Monitor stockpiling and loading of delivered aggregates. • Observe scale operation and loading of trucks at a minimum of 2 hour intervals

throughout the day. • Check field hoppers for contamination. If contaminated, have Contractor empty storage

and weigh hoppers and re-charge. • Review mix designs and ensure the Contractor is using correct mix design weights. • Check that batch weights are adjusted in accordance with current moisture tests. • Ensure compliance with minimum and maximum mixing times.

Page 4: Section 2 - Procedures and tests

6. Complete Concrete Ingredient Summary Daily:

• Collect a production summary in an electronic format of the daily total concrete produced and daily total ingredient quantities (aggregate, cementitious and water) including the percent overrun/underrun.

• Collect final project total quantities for concrete produced and ingredients in an electronic format including the percent overrun/underrun.

• Verify daily and final quantities are within tolerances as required by the Specifications. 7. Perform Moisture Tests and Water Content Verification Testing (Microwave Oven):

• Verify contractor performs start-up moisture tests. • Take additional moistures whenever moisture appearance of delivered aggregate seems

to vary or batch water deviates greatly from previous loads. • Use Concrete W/C Ratio Calculation Worksheet to determine moisture contents, batch

ticket, w/c ratios, unit weight, microwave oven w/c ratios, charting and w/c ratio. incentive/disincentives.

• Review water/cementitious ratio results for compliance with project specifications and verify with microwave oven testing.

8. Aggregate Gradation Testing:

• Review Contract and Contractor Mix Design to determine gradation testing requirements.

• Use Well-graded Concrete Aggregate Worksheet to calculate gradations in the field. • Verify Contractor is using Well-graded Concrete Aggregate Worksheet for gradations

test, charting and well-graded incentives. • Review Contractor’s tests for compliance and compare to the Agency test results (split

samples). • If submitting gradation samples to the lab, fill out Aggregate Sample I.D. cards

completely including the JMF number found on the Contractor mix design and the QC Gradation results. Identify “QA Gradation” on ID card.

• Determine if Contractor is eligible for well-graded aggregate incentives. Review the Contractor’s Well-Graded Aggregate Summary Worksheet.

9. % Passing 75 µm (#200) Sieve:

• Perform all percent passing the #200 (75 µm) sieve at the Contractor’s plant site. • Verify Contractor washed all fine aggregate gradations to determine the percent passing

the #200 (75 µm) sieve. • Use Well-graded Concrete Aggregate Worksheet to calculate the percent passing the

#200 (75 µm) sieve in the field. • Review the Contractor’s percent passing the #200 (75 µm) sieve for the coarse

aggregate results to determine compliance or if additional testing is required and compare to Agency results.

10. Aggregate Quality Sampling:

• Fill out Aggregate Sample I.D. cards completely and record the Contractor and Agency -#200 (75 µm) test results.

• Identify Quality samples with a “Q” including the specification reference (Spec 3126 for sand and 3137.2D3 for coarse aggregate) on ID card.

• Identify the Quality Companion samples with a “Q”.

Page 5: Section 2 - Procedures and tests

11. Coarse Aggregate Quality Sampling:

• If coarse aggregate quality incentive/disincentive applies, determine when random samples will be taken in accordance with the Schedule of Materials Control using the Coarse Aggregate Quality Incentive/Disincentive Worksheet.

• Fill out Aggregate Sample I.D. cards completely and enclose with lab samples. Identify Incentive samples with “I/D” on ID card.

12. Alkali Silica Reactivity (ASR) Sampling: • Obtain samples of cement, supplementary cementitious materials (fly ash or slag) and

sand in accordance with the Schedule of Materials Control. • Fill out the Sample I.D. card completely and enclose with lab samples. Identify ASR

sample with “Project Specific ASR Testing” on ID card.

13. Contractor Records and Charts: • Obtain the Contractor’s on-site QC records and charts on a daily basis or otherwise

directed by the Engineer. • Review the Contractor’s on-site QC records and charts for accuracy and completeness. • Obtain batch tickets on a daily basis or otherwise directed by the Engineer.

14. Maintain a daily diary:

• Includes hours of production, equipment, weather, concrete air content test results conducted at the plant, air temperatures, concrete yardage totals, and problems or unique circumstances encountered.

15. Documention of test results:

• Record all calculated w/c ratio test results and mix design data along with all field results on the Weekly Concrete Report (MnDOT Form 2448).

• Contractor field test results can be entered on a separate form and submitted with the Weekly Concrete Report.

16. Submit the following to the MnDOT Concrete Engineering Unit: • Contact Report • Weekly Concrete Reports – Form 2448 • W/C Ratio Incentive Calculation Worksheets • Well-graded Aggregate Incentive Worksheets • Quality Incentive/Disincentive Worksheets

References: MnDOT Specification 2301, 2461, 3126, 3137, Special Provisions, Schedule of Materials Control and MnDOT Concrete Manual.

Page 6: Section 2 - Procedures and tests

1

TP-2164 (1/3/2017)

Minnesota Department of Transportation

Contact Report - PavingOwner's Name:

Plant/Unit #:

Set Up Location:

Plant Superintendent:

Lab Equpment Calibrations - Date of seive calibration:

Scale and/or Meter Calibrations - Date of scale/meter calibration:

Batch Ticket - A computerized ticket that includes all MnDOT Specifications and supporting information.

Technicians -

Cert#:

Cert#:

Cert#:

Cert#:

Agency Representative:

x Approved for concrete paving production on SP/SAP #:

Date:

Not approved for the following reason(s):

Re-inspected and approved on by

Certified by:

Bill Batcher

Leo Sands

[email protected]

MnDOT Certified Plant 1 Technician:

MnDOT Certified Plant 1 Technician:

MnDOT Certified Plant 1 Technician:

MnDOT Certified Plant 2 Technician:

A MnDOT Certified Concrete Plant Level 1 or 2 Technician, representing the Producer, signs the report certifying compliance with the Certified Ready Mix requirements and continual maintenance of the plant to assure that the plant can produce concrete meeting MnDOT Specifications.

2017

W123

St. Cloud

Phone#:

Phone#:

MnDOT

651-563-7634

Bill BatcherPlant Representative

5/1/14

After completing the Concrete Plant Contact Report, any procedural changes that cause non-compliance with this program may result in de-certification of the plant and cessation of further production of Department concrete as determined by the Concrete Engineer in accordance with 2461.3.F.4.h, "Decertification."

5/1/14

612-987-6543

Date:

Phone:

Email:

651-345-5645

Sandy Beaches 99118

Phone#:

8901-23

Email Contact Report and Certificate of Compliance to the Concrete Office at [email protected].

Whitey Walker 99663 Phone#:

Age

ncy

Insp

ectio

n

Agency:

Cell #:

Prior to the production of Agency concrete for a paving project, a Department Representative shall perform a thorough on-site inspection of the portable concrete plant with a MnDOT Certified Plant Level 1 or Level 2 Technician representing the Producer.

TUV Paving

651-343-6453

5/1/14

5/1/14

Page 7: Section 2 - Procedures and tests

2

W123 2017

Type of Mixer:

Type of Paving Plant: Make:Condition:

Single Drum Dual Drum xMax. mixer batch size yd3

Batching Equipment: Make:All Dump Trucks are equipped with vibrators (y/n):

Batch Ticket:

Computerized Batch Printout (y/n): y English/Metric Conversion (y/n): y

x Date x Target weight of materialsx State project number (SP) or (SAP) x Actual batched weights of materialsx Mix number x Temper waterx Time concrete was batched x Total water weightx Quantity of concrete in this loadx Running total of each type of concrete, each day for each projectx

Scale and Meter Information:

Plant Lab - Office (2301.3.B.3.a):

x Located within 100 yd from the batch plantx Plant lab and plant office separated and isolated by a wallx Plant lab floor area at least 144 sq.ftx Plant office floor area at least 80 sq.ftx One sturdily built workbench or countertop at least 30 in x 144 inx Shelf space of at least 8 ft x 8 inx Electronic scales of sufficient size to weigh the sample for all required materials testingx A four burner 30" standard stove top or stove and at least two additional electric burnersx Metal bowls of sufficient size to perform all required material testingx Water supply connected to the sink faucetx Two desksx At least four chairsx Telephone capable of providing emailx Printer with scanning and copying capabilitiesx Drinking water container or cooler with adequate supply of potable waterx Heating and cooling system capable of maintaining a uniform temperature between 72o and 85o Fx Adequate sample storage area to prevent contamination of the samplesx Detached portable toilet conveniently located

20 lb

1 gal 5/1/14

Digital

Digital

Digital

Digital

Aggregate

Seltic

Water Meter

Fly Ash

Slag

Water Scale

Seltic

10000 lb

Seltic

Seltic

5/1/14

5/1/14

300 gal

Labels identifying each material that correlates with the Contractor mix design, including cementitious and admixture abbreviations, and MnDOT 5 digit pit numbers

Material

20 lb

10000 lb

10000 lb

10000 lb

Cement 5/1/145 lb

Model:

5/1/14

SelticDigital

TypeDate of Scale and Meter CalibrationMake Capacity

y

Rex

5 lb

Graduation

1A

S

Plant and LabModel:

Seltic

Serviceable

Page 8: Section 2 - Procedures and tests

3

W123 2017

Cementitious Materials:

Automatic Cement Recorded (y/n)

Admixtures:

Does AEA bulk storage tank hold at least 300 gallons (y/n)

Aggregates:

Plant is feed by: y 4Number of working bins 4Are stockpiles separated (y/n) yHow many belts feed plant working bins 4Is turn head used (y/n) nAggregate sampled at: x

Water:

Source: Proportioned by:x City Water x Meter

Well Water ScaleOther-

Can water be heated with a boiler (y/n) n

Temperature gauge location:

3/4+

3/4-

Coarse Aggregate

Class

C

Dispensing Tube

Rock Island

17777

19999

18888

Salinger

Rock IslandC

Supplier Pit Location Pit Number

St. Cloud

St. Cloud

Deliver By

Freeport

Field Hoppers (y/n)

Belt

What?

How many?

18888

In Plant Storage (tons)

Water Reducer Adcon

Material

Ajax Dispensing Tube

WRXX

Type Supplier Product NameSampled at (dispensing tubes

recommended)

240

75

Auger

Auger

Capacity (tons)

Delivered to Hopper by (gravity,auger)

Graymatter 1

1

Material

Cement

Slag

Cement Mill/Power Plant # of Silos

A.E.A. Adcon

Fly Ash Asher

Materials

Pebble Beach

Specifications 3126/3137

St. Cloud3/8- C

Sand

Page 9: Section 2 - Procedures and tests

4

W123 2017

Equipment:

Mechanical Shakers, Screens and Sieves

Box Screens: Must have all screens listed below Calibrated on

x 2" (50mm) x 3/4" (19mm) x #4 (4.75mm)

x 1 1/2" (37.5mm) x 5/8" (16mm)* x Bottom Pan

x 1 1/4" (31.5mm)* x 1/2" (12.5mm) x Mechanical Shaker

x 1" (25mm) x 3/8" (9.5mm)

*Sieves Not RequiredNote: Additional fill-in sieves may be needed to be added to prevent overloading.

Brass Sieves: Must have all screens listed below Calibrated on

x 3/8" (9.5mm) x #30 (600um) x Bottom Pan

x #4 (4.75mm) x #50 (300um) x Mechanical Shaker

x #8 (2.36mm) x #100 (150um)

x #16 (1.18mm) x 2 - #200 (75um)

Are replacement sieves available within 24 hours if needed (y/n): y

Scales, Microwave Oven Equipment and Miscellaneous

Scales:

Minimum 15 kg Capacity(minimum 0.02 kg graduated interval)

Minimum 6000 g Capacity(minimum 0.1 g graduated interval)

Microwave Oven and Ancillary Equipment:

x Microwave Oven with turntable or wave deflection fan (900 Watt)

x Heat resistant glass pan ( approx. 9" x 9" x 2")

x Plain weave fiberglass cloth (10 oz/yd2 and 14 mils thick)

x Metal scraper and grinding pestle

Miscellaneous:

x 2" (50mm) Sample Splitter with 3 Pans

x 6 Electric Burners (minimum)

5/1/14

Note: Two #200 (75um) sieves are needed, one is for shaking the gradation and the second is for washing the sample during the final steps of the gradation process.

Equipment

x

x

Calibrated on

Calibrated on5/1/14

5/1/14Electronic Scale

Electronic Scale

Page 10: Section 2 - Procedures and tests

Minnesota Department of Transportation

Project Specific Mix Design (JMF)SP Number

Use for: Requested ByJob Specific Concrete using a JMF Company

Cement I/II 3.15 Paving Projects 3,500 CY or greater PhoneFly Ash F 2.50 High Performance Bridge EmailSlag AgencyContactOther CM Pit # Class SP.G. ABS. Agency PhoneAdmx#1 AEA 0.5-3 FA#1 19999 2.63 0.009 Agency EmailAdmx#2 A 0-5 FA#2 Plant NameAdmx#3 CA#1 18888 C 2.75 0.009 ContractorAdmx#4 CA#2 18888 C 2.69 0.013Color CA#3 17777 C 2.67 0.015

Estimated Batch Weights - Pounds (Dry)37 25 25 13

3A21-1 7.0 225 433 182 30 615 0.37 1101 778 761 393 27.0 154.3 1/2-3"3A41-1 7.0 249 433 182 30 615 0.40 1078 761 745 384 27.0 152.7 2-5"

Submit to: [email protected] Page 1

3/4

% F

ly

Ash

% S

lag

% O

ther

CM

WRXX

CA#1

W/C

Ra

tio

CA#2

CA#3

Slag

Name/Mill/PlantMnDOT

AbbreviationType/Class

ASCAMNGRSPMNGraymatter

Asher

Joe ContractorTUV Paving

[email protected]

8901-23

Volu

me

FA#1

FA#2

Mix

#

% A

ir

Slum

p Ra

nge

MnDOT Approval

Th. U

nit

Wt.

Fly

Ash

(1/2/17)

Sand

The Concrete Engineer reviews the Contractor's concrete mix design submittal and approves the materials and mix design based on compliance with the contract. Final approval for payment is based on satisfactory field placement and performance.

Wat

er

Cem

ent

SP.G / Dosage

%

Tern

ary

T.SandersSize

1 1/2

% Aggregate Proportion by Volume

JMF Number 14-004

[email protected]

TUV Batch PlantTUV Paving

Oth

er

CM

Comments:

Adcon

Adcon

Ajax

3/8

Tota

l CM

Page 11: Section 2 - Procedures and tests

Minnesota Department of Transportation (1/2/17)

Contractor Mix Design - Specialty Concrete (JMF)JMF

FA #1 FA #2 CA #1 CA #2 CA #3 TOTAL % WORKING TOTAL %Agg. Size Sand 1 1/2 3/4 3/8 PASSING RANGE RETAINED SPProp. % 37 25 25 13 100% LIMITS

2" 100.0 100.0 100.0 100.0 100 ± 5 95 100 01 1/2" 100.0 97.2 100.0 100.0 99 ± 5 94 100 1

1" 100.0 43.7 100.0 100.0 86 ± 5 81 91 133/4" 100.0 5.6 96.2 100.0 75 ± 5 70 80 111/2" 100.0 0.9 65.1 100.0 67 ± 5 62 72 83/8" 100.0 0.6 41.6 100.0 61 ± 5 56 66 6#4 100.0 0.4 4.6 70.0 47 ± 5 42 52 14#8 92.0 0.1 1.0 11.0 36 ± 4 32 40 11#16 75.0 0.1 1.0 4.0 29 ± 4 25 33 7#30 50.0 0.1 1.0 2.0 19 ± 4 15 23 10#50 20.0 0.1 1.0 2.0 8 ± 3 5 11 11#100 4.0 0.1 1.0 1.0 2 ± 2 0 4 6#200 0.8 0.1 0.4 0.7 0.5 < 1.6 0.0 1.6 2

Page 2

JMFWORKING

RANGE

14-004

8901-23

workability of the mix.

% Retained(#30 through #200)

29

28Greater than 15%,

Coarse Sand

Fine Sand

generally enhances

generally enhancescohesion of the mix.

Mix #

% Retained(#8 through #30)

Between 24-34%,

3A21-13A41-1

0

2

4

6

8

10

12

14

16

18

20

22

24

#200 #100 #50 #30 #16 #8 #4 3/8" 1/2" 3/4" 1" 1 1/2" 2"

% R

ETA

INED

SIEVE SIZE

Well-Graded Aggregate Optional Incentive - % Retained Gradation Band

Page 12: Section 2 - Procedures and tests

(1/2/2017)Minnesota Department of Transportation

S.P. Plant: Date: FA #1: 19999 FA #2:Engineer: Tester: Time: CA #1: 18888 CA #2: 18888 CA #3: 17777Lot #: Test #: JMF #:

Sieve Analysis of Coarse AggregateSample Wt. Sample Wt. Sample Wt.

Aggregate CA #1 CA #2 CA #3Fraction Mix Prop. Mix Prop. Mix Prop.Sieve SizesPass - Ret. Ind. Cum. Ind. Cum. Ind. Cum.2" - 1 1/2" 0.00 29.8 100 0.00 16.1 100 0.00 15.1 1001 1/2" - 1 1/4" 12.00 29.8 100 0.00 16.1 100 0.00 15.1 1001 1/4" - 1" 2.00 17.8 60 0.00 16.1 100 0.00 15.1 1001" - 3/4" 10.00 15.8 53 0.15 16.1 100 0.00 15.1 1003/4" - 5/8" 0.00 5.8 19 0.00 16.0 99 0.00 15.1 1005/8" - 1/2" 5.00 5.8 19 4.80 16.0 99 4.55 15.1 1001/2" - 3/8" 0.50 0.8 3 3.85 11.2 69 3.58 10.6 703/8" - #4 0.15 0.3 1 6.75 7.3 45 6.45 7.0 46#4 - Btm 0.15 0.2 1 0.55 0.6 3 0.56 0.6 4Check Total 29.80 16.10 15.14

Sieve Analysis of Fine Aggregate Percent Passing #200 Sieve TestSample Wt. Sample Wt. CA #1 CA #2 CA #3

Aggregate FA #1 FA #2 (A) Dry weight of original sample 5088.2 2516.4 2515.0Fraction Mix Prop. Mix Prop. (B) Dry weight of washed sample 5071.8 2509.4 2509.4Sieve Sizes (C) Loss by washing (A-B) 16.4 7.0 5.6Pass - Ret. Ind. Cum. Ind. Cum. (D) % Passing #200 (C/A)*100 0.3 0.3 0.21/2" - 3/8" 0.0 492.7 1003/8" - #4 15.0 492.7 100 FA #1 FA #2#4 - #6 0.0 477.7 97 (A) Dry weight of original sample 533.9*#6 - #8 10.0 477.7 97 (B) Dry weight of washed sample 527.2#8 - #16 145.0 467.7 95 (C) Loss by washing (A-B) 6.7#16 - #30 155.0 322.7 65 (D) % Passing #200 (C/A)*100 1.3#30 - #50 110.2 167.7 34#50 - #100 38.0 57.5 12 Additional Remarks or Comments#100 - #200 12.3 19.5 4*#200 - Btm 0.5 7.2 1.5Loss by Washing 6.7Check Total 492.7

Composite Gradation for Job Mix FormulaAggregate CA #1 CA #2 CA #3 FA #1 FA #2Fraction 1 1/2" 3/4" 3/8" SandMix Prop. 25% 25% 13% 37% Coarse Sand % Retained

2" 25 25 13 37 100 100 ± 5 95 100 0 (#8 through #30)1 1/2" 25 25 13 37 100 100 ± 5 95 100 0 24

1" 13 25 13 37 88 90 ± 5 85 95 123/4" 5 25 13 37 80 82 ± 5 77 87 81/2" 1 17 9 37 64 64 ± 5 59 69 16 Fine Sand % Retained3/8" 0 11 6 37 55 58 ± 5 53 63 9 (#30 through #200)#4 0 1 0 36 37 42 ± 5 37 47 18 23#8 35 35 35 ± 4 31 39 2

#16 24 24 27 ± 4 23 31 11#30 13 13 17 ± 4 13 21 11#50 4 4 6 ± 3 3 9 9#100 1 1 1 ± 2 0 3 3#200 0.1 0.1 0.0 0.5 0.7 0.4 ± 1.6% max 0.0 1.6 0.3

1

TUV PavingL.Bean

1 14-004

5/5/20148:30am

29.70 16.10

8901-23

Coarse Aggregate

Fine Aggregate

15.153/8"

% Pass

Total % Passing

Total % Retained

Comp. Grad. Req.

JMF JMF Working RangeWorking Range

JMF Concrete Aggregate WorksheetAggregate Sources (Pit #):

T.Sanders

% Pass % Pass

1 1/2"25% 25%

3/4"

492.5

Agency only - QC Test Number corresponding to this test:

% Pass

Weights (kg)

37%Sand

13%

± 0.10 kg of Sample Wt

Weights (kg) Weights (kg)

± 0.3% of Sample Wt ± 0.3% of Sample Wt

Weights (g) Weights (g)

± 0.10 kg of Sample Wt ± 0.10 kg of Sample Wt

Agency -#200 Result: 1 1/2" = 0.2, 3/4" = 0.3, 3/8" = 0.3

% Pass

Page 13: Section 2 - Procedures and tests

1

Minnesota Department of Transportation

JMF Moving Average SummaryPlant: SP:

Test #:

JMF #:

2" 100 100 100 95 100 100 100 100 95 100 100 100 100 95 100 100 100 100 100 95 100

1 1/2" 100 100 100 95 100 98 100 100 95 100 98 100 100 95 100 99 100 99 100 95 100

1" 88 89 90 85 95 87 89 90 85 95 84 89 90 85 95 89 89 87 90 85 95

3/4" 80 81 82 77 87 77 81 82 77 87 76 81 82 77 87 79 81 78 82 77 87

1/2" 64 64 64 59 69 63 64 64 59 69 63 64 64 59 69 62 64 63 64 59 69

3/8" 55 53 58 53 63 55 53 58 53 63 54 53 58 53 63 53 53 54 58 53 63

#4 37 33 42 37 47 39 35 42 37 47 39 35 42 37 47 39 35 39 42 37 47

#8 35 34 35 31 39 32 34 35 31 39 32 34 35 31 39 32 34 33 35 31 39

#16 24 25 27 23 31 25 25 27 23 31 25 25 27 23 31 25 25 25 27 23 31

#30 13 12 17 13 21 17 15 17 13 21 16 12 17 13 21 17 15 16 17 13 21

#50 4 2 6 3 9 5 2 6 3 9 5 2 6 3 9 5 2 5 6 3 9

#100 1 1 1 0 3 0 1 1 0 3 1 1 1 0 3 0 1 1 1 0 3

#200 0.7 0.6 0 0.0 1.6 0.2 0.5 0 0.0 1.6 0.3 0.5 0 0.0 1.6 0.2 0.4 0.4 0 0.0 1.6

Agen

cy

Verif

icat

ion

Resu

lts

Mov

ing

Aver

age

Tota

l %

Pass

ing

JMF

Wor

king

Ra

nge

Cont

ract

or

Resu

lts

Agen

cy

Verif

icat

ion

Resu

lts

Mov

ing

Aver

age

Tota

l %

Pass

ing

JMF

Wor

king

Ra

nge

Cont

ract

or

Resu

lts

JMF

Wor

king

Ra

nge

Cont

ract

or

Resu

lts

Agen

cy

Verif

icat

ion

Resu

lts

Mov

ing

Aver

age

Tota

l %

Pass

ing

JMF

Wor

king

Ra

nge

Siev

e

Cont

ract

or

Resu

lts

Agen

cy

Verif

icat

ion

Resu

lts

Mov

ing

Aver

age

Tota

l %

Pass

ing

14-004 14-004 14-004 14-004

1 2 3 4

TUV Paving 8901-23

1/12/2017

Remarks or Comments

Page 14: Section 2 - Procedures and tests

1

Minnesota Department of Transportation

0 ≤ 5 ≤ 16 ≤ 20 4 - 20 4 - 20 4 - 20 ≤ 12 ≤ 12 4 - 20 4 - 20 ≤ 10 ≤ 2 > 15 24-34

1 5/5/14 0 0 12 8 16 9 18 2 11 11 9 3 0 24 23

2 5/5/14 0 2 11 10 14 8 16 7 7 8 12 5 0 22 25

3 5/5/14 0 2 14 8 13 9 15 7 7 9 11 4 1 23 25

Lot 1 Average 0 1 12 9 14 9 16 5 8 9 11 4 0 23 24 $2.00 3,983 3980 $7,960.00

4 5/6/14 0 1 10 10 17 9 14 7 7 8 12 5 0 22 25

5 5/6/14 0 1 11 10 16 9 14 7 7 8 12 4 1 22 25

Lot 2 Average 0 1 10 10 16 9 14 7 7 8 12 4 0 22 25 $2.00 1,799 1791 $3,582.00

6 5/7/14 0 1 11 10 16 9 14 7 7 8 12 4 1 22 25

7 5/7/14 0 1 11 11 16 13 9 7 7 8 12 4 1 22 25

8 5/7/14 0 1 11 10 17 8 14 7 7 8 12 4 1 22 25

Lot 3 Average 0 1 11 10 16 10 12 7 7 8 12 4 1 22 25 $2.00 3,011 3010 $6,020.00

Lot Average

8901-23T.Sanders

8781$17,562.00

SP #:ENGINEER:TOTAL YD3:

TOTAL I/D ($):Well Graded Aggregate Incentives

3/8"

1

2

3

3/4"1" #50

#100

#200

Lot #

Test

#

Dat

e Te

sted

2"

1 1/

2"

#30

1/2" #4 #8 #16

< --

- Yar

dage

per

Lot

pro

duce

d at

the

plan

t.

Ince

ntiv

e

Tota

l CY

P

rodu

ced

for

Lot

Pay

Fac

tor

< --

- Yar

dage

per

Lot

pla

ced

in th

e fie

ld

dete

rmin

ed b

y th

e A

genc

y fie

ld p

erso

nal.

Th

e in

cent

ive

is d

eter

min

ed fr

om th

is

quan

tity.

Specification

Tota

l CY

M

easu

red

for

Lot

% R

etai

ned

(#8

to #

30)

% R

etai

ned

(#30

to #

200)

Page 15: Section 2 - Procedures and tests

Minnesota Department of Transportation

JMF Adjustment Worksheet

S.P. Number: Date:

Sp. Gravity:

Current Mix Design Information % Aggregate Proportion by Volume

37 25 25 13

2" 100.0 100.0 100.0 100.0 100 03A21-1 7.0 225 433 182 1101 778 761 393 1 1/2" 100.0 97.2 100.0 100.0 99 1

1" 100.0 43.7 100.0 100.0 86 133/4" 100.0 5.6 96.2 100.0 75 111/2" 100.0 0.9 65.1 100.0 67 83/8" 100.0 0.6 41.6 100.0 61 6#4 100.0 0.4 4.6 70.0 47 14#8 92.0 0.1 1.0 11.0 36 11

#16 75.0 0.1 1.0 4.0 29 7#30 50.0 0.1 1.0 2.0 19 10

Current JMF Number: #50 20.0 0.1 1.0 2.0 8 11#100 4.0 0.1 1.0 1.0 2 6#200 0.8 0.1 0.4 0.7 0.5 2

Aggregate Proportion Adjustment % Aggregate Proportion by Volume37 22 28 13

2" 100.0 100.0 100.0 100.0 100 03A21-1R 7.0 225 433 182 1101 685 852 393 1 1/2" 100.0 97.2 100.0 100.0 99 1

1" 100.0 43.7 100.0 100.0 88 113/4" 100.0 5.6 96.2 100.0 78 101/2" 100.0 0.9 65.1 100.0 68 103/8" 100.0 0.6 41.6 100.0 62 6#4 100.0 0.4 4.6 75.0 48 14#8 92.0 0.1 1.0 11.0 36 12

#16 75.0 0.1 1.0 4.0 29 7#30 50.0 0.1 1.0 2.0 19 10

New JMF Number: #50 20.0 0.1 1.0 2.0 8 11

#100 4.0 0.1 1.0 1.0 2 6#200 0.8 0.1 0.4 0.7 0.5 2

Page 1Submit to MnDOT Concrete Office for New JMF Number: [email protected]

Contractor Representative Agency Representative

L. Bean A.Tester

14-004

14-015

Seiv

e Si

zes

Seiv

e Si

zes

Aggregate Gradation Adjustment

Slag

Oth

er

CM FA#1

FA#2

CA#1

CA#2

CA#3

CA#3

Slag

FA#1

FA#2

CA#1

CA#2

Tota

l %

Pass

ing

Tota

l %

Reta

ined

FA#1

FA#2

CA#1

CA#2

FA#2

CA#1

CA#2

Mix

#

% A

ir

Wat

er

Cem

ent

Fly

Ash

Mix

#

% A

ir

Wat

er

Cem

ent

Fly

Ash

8901-23 5/6/14

CA#3FA#2 CA#1 CA#23.15 2.50 2.63 2.75

Cement

CA#3

Fly Ash Slag Other CM FA#12.69

Oth

er

CM FA#1

(1/31/17)

Tota

l %

Pass

ing

Tota

l %

Reta

ine

d

2.67

CA#3

Page 16: Section 2 - Procedures and tests

Minnesota Department of Transportation (1/31/17)

JMF Adjustment Worksheet

Make JMF adjustments in accordance with 2301.2.L.3.b, "JMF Adjustments."

Page 2

% Retained(#30 through #200)

29Between 24-34%,

workability of the mix.generally enhances

Coarse Sand

No. 100 [150 um] +/- 2

Sieve Size Allowable Adjustment, %> No. 4 [4.75 mm] +/- 5

No. 8 [2.36 mm] - No. 30 [600um] +/- 4

% Retained(#8 through #30)

29Greater than 15%,generally enhancescohesion of the mix.

Fine Sand

No. 50 [300 um] +/- 3

Allowable JMF Adjustment per 2301.2.L.3.b

0

2

4

6

8

10

12

14

16

18

20

22

24

#200 #100 #50 #30 #16 #8 #4 3/8" 1/2" 3/4" 1" 1 1/2" 2"

% R

ETA

INED

SIEVE SIZE

Adjusted Well-Graded Aggregate Optional Incentive - % Retained Gradation Band

Page 17: Section 2 - Procedures and tests
Page 18: Section 2 - Procedures and tests
Page 19: Section 2 - Procedures and tests

(2/2017)Minnesota Department of Transportation

Coarse Aggregate Quality Incentive/Disincentive

Lot

Quality Cubic Yards

Testing Location (Cubic

Yards)

1 0.71 994 994

2 0.53 742 2,142

3 0.58 812 3,612

4 0.29 406 4,606

5 0.30 420 6,020

6 0.77 1,078 8,078

7 0.01 14 8,414

8 0.76 1,064 10,864

9 0.81 1,134 12,334

10 0.71 994 13,594

SP Number: Engineer: T.Sanders8901-23

10

Total Project Cubic Yards

Cubic Yards Per Lot

14000

1400

NOTE: Click "Generate Random Numbers" to establish the testing location.

The macros must be enabled for the random numbers generator to work.

Number of Lots (n)

3

5

10

3,500 - 7,500

Plan (cubic yards) of Concrete

7,501 - 10,000

25,001 - 50,000

50,001 + 20

15

Samples Per Fraction (n)

10,001 - 25,000

Page 20: Section 2 - Procedures and tests

3/24/2017

(2/2017)Minnesota Department of TransportationClass C - Coarse Aggregate Quality Incentive/Disincentive

S.P. Number: 8901-23 Engineer: T.Sanders

Aggregate Fraction 3/4+ Aggregate Fraction 3/4-Number of Samples (n) 10 Number of Samples (n) 10Number of Cubic Yards 14000 Number of Cubic Yards 14000

Lot # Lot #1 4.00 1 16.202 5.20 2 16.403 2.30 3 17.204 3.50 4 15.905 4.60 5 16.806 4.20 6 14.507 3.90 7 13.908 5.20 8 16.109 6.30 9 15.50

10 4.30 10 21.8011 1112 1213 1314 1415 1516 1617 1718 1819 1920 20

X = mean 4.35 X = mean 16.43s = standard deviation 1.08 s = standard deviation 2.13QI = quality index 5.72 QI = quality index 19.12I/D per Cubic Yard $1.00 I/D per Cubic Yard $0.50

I/D per Fraction $14,000.00 I/D per Fraction $7,000.00

% Carbonate % Carbonate

Total Incentive/Disincentive: $21,000.00

Page 21: Section 2 - Procedures and tests

(2/17/2017)

Minnesota Department of Transportation

Concrete W/C Ratio Calculation Worksheet

MIX DESIGN BATCH SIZE, (cy) 10 (A)

= 570 (B)

BATCH REPORT

FRACTIONWT OF SAMPLE + PAN (WET), (g)WT OF SAMPLE + PAN (DRY), (g)WT OF PAN, (g)TOTAL MOISTURE FACTORABSORPTION FACTORFREE MOISTURE FACTOR

TOTALDESIGN WT (OVEN DRY), (lb/cy)TOTAL MOISTURE, (lb/cy) = 71 (C)FREE MOISTURE, (lb/cy) = 40 (D)

= 31.18 (E)

WATER/CEMENT CALCULATION

TICKET # BATCH TEMPER FLY ASH/SLAG 198.3 (F)WATER WATER(GAL) (GAL) 165.2 (G)

23 196.8788 024 198.3193 0 226.2 (H)25 200.2401 026 199.5198 0 205.2 (I)27 197.599 028 197.1188 0 0.36 (J)29 195.9184 030 200.7203 0 236.4 (K)31 200.4802 032 196.2785 0

AVE. 198.3 0.0AVE. CM

UNIT WEIGHT TEST % PASSING #4 SIEVE

VOLUME OF UNIT WEIGHT BUCKET, VOL ft3 MASS OF SAMPLE RETAINED #4 SIEVE, WR4 941.1 gMASS OF UNIT WT. BUCKET, BWT lb MASS. OF SAMPLE PASSING #4 SIEVE, WP4 702.8 gMASS OF UNIT WT. BUCKET & CONCRETE, CBWT lb (WD - WR4) - WS

% PASSING #4, P4 42.8 %MASS OF CONCRETE, (CBWT - BWT), CWT lb WP4 / (WD-WS)

UNIT WT. OF CONCRETE, CWT / VOL, UW lb/cf % PASSING #4 FROM JMF, P4JMF 42.0 %

% PASSING #4 FROM TOTAL MIX, P4TM 51.0 %MICROWAVE OVEN TEST

MASS OF TRAY & CLOTH, WS gMASS OF TRAY, CLOTH & WET CONCRETE, WF g CORRECTION FACTOR, CF 1.17MASS OF PAN, CLOTH & DRY CONCRETE, WD g (100 - P4 / 100 - P4TM)

TOTAL MEASURED WATER CONTENT, WTM lb/cy ADJUSTED TOTAL WATER CONTENT, AWTM 246.3 lb/cy(WF - WD / WF - WS) x 27 x UW WTM X CF COMPARE TO (K)

ESTIMATED ABSORBED WATER CONTENT, WTA lb/cy ADJUSTED MIXING WATER CONTENT, AMW 215.1 lb/cySum of Absorbed Moistures (E) AWTM - WTA

ESTIMATED MIXING WATER CONTENT, MW lb/cy ADJUSTED W/C RATIO 0.38WTM - WTA ((AMW) / (AVE CM / A)) COMPARE TO (J)

x100[((∑ Agg. Design WT.) x (P4JMF/100))+ (AVE CM / A)][(∑ Agg. Design WT.) + (AVE CM / A)]

179.3

31.18

144.0

16851685

16851690

16901705 ( I / AVE. CM )

TOTAL WATER IN CONCRETE, (lb/cy)

TEST #1

TESTER

WATER, (lb/cy)

4020.5 1690.55711

402540154025

W/C RATIO

(( F x 8.33 ) / A )

(((AVE. CM * 0.40) - D)*A) / 8.33))

TOTAL MIX WATER USED, (lb/cy)

MAXIMUM BATCH WATER AVAILABLE, (GAL)

40254015 1700

S.P.

DATETIME

TICKET #LOT #

39704020

ENGINEER

CONTENT

DESIGN W/C

(lbs)

0.37

ABSORBED MOISTURE, (lb/cy)

CEMENTCONTENT

(lbs)

40101685

4045

8901-235/5/201410:00 AM

210.5

36

( D + G )

( E + I )

( AVE. BATCH WATER + AVE. TEMPER WATER )ACTUAL BATCH WATER USED, (lb/cy)

2912.4

1268.53006.5

16954055 1685

CEMENT, (lb/cy)FLY ASH, (lb/cy)SLAG, (lb/cy)

TOTAL AVERAGE BATCH WATER, (GAL)

27

1

T.SandersL.Bean

44.58.5

400213

0170

1 1/2"3009.3

12.25

0.25

541.30.0030.010-0.007

631

SAND694.7673.7179.70.0430.0100.033

12255340

2-4

6.31

3/4"-3144.53109.5432.20.0130.0100.003

1262164

12.62

CA #3

3001.1

FA #1 FA #2 CA #1 CA #2

3A21-1

TOTAL CEMENTITIOUS, (lb/cy)

Page 22: Section 2 - Procedures and tests

Page 1

(2/17/2017)Minnesota Department of Transportation

W/C Ratio Incentive Calculation

1 5/5/14 3A21-1 0.36

2 5/5/14 3A21-1 0.37

3 5/5/14 3A21-1 0.36

4 5/5/14 3A21-1 0.37

Lot # 1 Average: 0.36 3982.5 $3.00 3980 $11,940.00

5 5/6/14 3A21-1 0.34

6 5/6/14 3A21-1 0.36

Lot # 2 Average: 0.35 1798.5 $3.00 1791 $5,373.00

7 5/7/14 3A21-1 0.36

8 5/7/14 3A21-1 0.36

9 5/7/14 3A21-1 0.35

Lot # 3 Average: 0.36 3011 $3.00 3010 $9,030.00

Lot # Average:

3

LOT # TEST #DATE

TESTEDMIX

NUMBERW/C

RATIO (J)

TOTAL CY PRODUCED BY

LOT PAY FACTOR

TOTAL CY MEASURED

FOR LOTINCENTIVE/

DISINCENTIVE

1

< --

- Yar

dage

per

Lot

pro

duce

d at

the

plan

t.

< --

- Yar

dage

per

Lot

pla

ced

in th

e fie

ld

dete

rmin

ed b

y th

e Ag

ency

fiel

d pe

rson

al.

The

ince

ntiv

e/di

sinc

entiv

e is

det

erm

ined

fro

m th

is q

uant

ity.

2

7.5 yards wasted

0.368,781

$26,343.00

SP NUMBER:ENGINEER:

AVERAGE W/C RATIO:TOTAL CUBIC YARDS:

TOTAL INCENTIVE/DISINCENTIVE:

8901-23T.Sanders

REMARKS

Page 23: Section 2 - Procedures and tests

Page 1 3/24/2017

(1/2017)Minnesota Department of Transportation

Concrete Ingredient SummaryS.P.: 8901-23 Engineer: T.Sanders 8,784

Plant: TUV Batch Plant Inspector: L.Bean -0.42

Date Product Type Batched Quantity (lb) Required Quantity (lb) Daily Overrun/Underrrun (%)

Cummulative Overrun/Underrrun (%) Mix Type Batched Quantity (cubic

yards)

Cement 1,650,000.00 1,657,600.00 -0.46 -0.46 3A21-1 3983

Fly Ash/Slag 666,840.00 664,960.00 0.28 0.28

Water

FA#1 6,117,800.00 6,137,260.00 -0.32 -0.32

FA#2

FA#3

CA#1 3,677,040.00 3,709,800.00 -0.88 -0.88

CA#2 3,504,100.00 3,521,580.00 -0.50 -0.50

CA#3CA#4 Waste

Cement 672,380.00 675,200.00 -0.42 -0.45 3A21-1 1799

Fly Ash/Slag 270,900.00 270,080.00 0.30 0.29

Water

FA#1 2,462,000.00 2,470,400.00 -0.34 -0.32

FA#2

FA#3

CA#1 1,503,380.00 1,518,240.00 -0.98 -0.91

CA#2 1,448,480.00 1,456,120.00 -0.52 -0.50

CA#3CA#4 Waste 8

Cement 710,000.00 712,400.00 -0.34 -0.42 3A21-1 3010

Fly Ash/Slag 285,480.00 284,960.00 0.18 0.26

Water

FA#1 2,649,700.00 2,657,560.00 -0.30 -0.32

FA#2

FA#3

CA#1 1,640,940.00 1,657,180.00 -0.98 -0.93

CA#2 1,412,880.00 1,419,200.00 -0.45 -0.49

CA#3CA#4 Waste

Cement

Fly Ash/Slag

Water

FA#1

FA#2

FA#3

CA#1

CA#2

CA#3CA#4 Waste

Total Batched Quantity (cubic yards)Final Cement Overrun/Underrun (%)

5/5/14

5/5/14

5/7/14

Page 24: Section 2 - Procedures and tests
Page 25: Section 2 - Procedures and tests
Page 26: Section 2 - Procedures and tests

JOB GUIDE CONCRETE PAVING INSPECTION 1. Review Contract and Plans:

• Obtain plans and special provisions and study them in detail. • Attend the pre-construction meeting.

2. Determine Random Numbers:

• Determine random numbers for testing locations using the Probing, Coring, Texture and MIT-SCAN T2 Report.

3. Become familiar with concrete paving equipment and paving operations.

• Check paving equipment for proper adjustment and compliance with specifications. • Understand the function of each piece of equipment. • Become familiar with paving sequence and review field controls for line and grade. • Verify string line is set sufficiently in advance to avoid delays. • Check vibration equipment and verify vibration monitors are operating correctly. • Verify that utility work and conduits are complete. Pre-locate utility fixtures to be

incorporated into the pavement.

4. Placement on Grade: • Check that the grade is in a moist condition ahead of the concrete placement. • Trucks hauling concrete are not allowed on the finished grade unless authorized by the

Engineer.

5. Placement on Asphalt: • Clean the milled surface by sweeping and patching, or as directed by the Engineer. • Maintain the asphalt surface in a moist condition and at a surface temperature not

greater than 120 °F [50 °C] before or during concrete placement. • Ensure the Contractor trucks don’t tear up the asphalt during turning movements.

6. Placement on Geotextile: • Clean the surface of the concrete prior to placing the geotextile fabric by power

sweeping and air blasting. • Ensure fabric is tight without excess wrinkles or folds. • Maintain the surface in a slightly damp, not saturated, condition before placing the

concrete. • Ensure the Contractor trucks don’t tear up the geotextile during turning movements.

7. Reinforcing Steel and Keyway Placement:

• Check size, spacing, and placement of reinforcing steel, and any other special reinforced panels.

• Verify proper reinforcement size, grade, lap ties, depth and spacing. • Check size and length of centerline steel and keyway tie steel. • Check if the required mechanical placer is placing it at the proper depth. • Assure location at proper elevation. • Make sure bars are the right size and length, and properly spaced. • Make sure keyway tie steel is not placed at a doweled joint.

Page 27: Section 2 - Procedures and tests

8. Dowel Basket Assemblies:

• Check proper size and type of dowel bar assembly. • Review Quality Control Plan for Anchoring Dowel Basket Assemblies. • Observe for approval the Contractor’s fastening method for dowel bar assemblies before

the beginning of concrete placement and each day prior to beginning paving. • Check dowel bar assemblies for proper placement to assure that they are parallel with

the base and centerline of road, properly supported and staked. • Make sure dowel baskets are securely anchored on the bottom rail using the correct

number of anchors. Refer to the Standard Plates for details. • If a bond breaker layer is used, make sure dowel baskets are securely fastened through

the bond breaker layer into the concrete below. • Check the placement of dowel assemblies at catch basins and manholes; keep joint at

least 3 ft (1 m) from structure. • Make sure an approved form release agent has been applied to dowel bars. • Confirm joint sawing locations are marked at the same location as the dowel baskets. • Mutually use the MIT-SCAN T2 device for locating dowel basket assemblies in the

plastic concrete.

9. When using forms: • Inspect pavement forms, as necessary, to ensure cleanliness and compliance with form

requirements. • Verify the forms are set to the alignment and grade shown on the plans for a distance

equal to at least 3 hours ahead of concrete placement. • If rain or cold weather occurs, ensure forms are removed and reset as necessary to

allow drainage.

10. Verify the Contractor’s prepared for inclement weather (rain or cold weather conditions). • Review the Contractor’s written cold weather protection plan.

11. During Concrete Placement: • Make sure concrete is placed within the time specification. • Check that no concrete is lost on the haul road or sticks in the truck after it dumps. • Stencil the stationing into the edge of the pavement every 500 ft (200 m) as directed by

the Engineer. • When placing concrete adjacent to in-place concrete pavement, protect the existing

transverse joints and the edges of the pavement. • Set manhole and catch basin frames or rings to the elevation shown on the plans during

the paving operations. 12. Monitor paving operation for continuous placement and consolidation of concrete.

• Make sure concrete is spread uniformly and ensure there is uniform strike-off. • Check to see that paver is not over or under loaded, and that concrete is “rolling” not

“sliding” in front of the screed. • Check if vibrating tubes are operating • Spot check vibration equipment daily and verify vibration monitors are operating

correctly. • Computerized vibration monitors are required on slipform pavers. Obtain an electronic

copy of all vibration monitor data from the Contractor at the end of the project.

Page 28: Section 2 - Procedures and tests

13. Concrete Appearance:

• Check that the concrete is maintained at a uniform consistency. • Monitor the surface and edge slump. • Make sure the tamping bar is properly adjusted so large aggregate is tucked below the

surface and not dragged.

14. Verify pavement dimensions: • Measure pavement width, thickness, crown, superelevation, edge slump, and joints

match to ensure it meets plan requirements. • Observe the Contractor’s probing operations.

15. Air Content and Slump Testing in accordance with the Schedule of Materials Control:

• Observe Contractor perform air content testing for slipform placement before and after consolidation.

• Perform air content testing for slipform placement before and after. • Observe Contractor perform air content and slump testing for fixed form placement. • Verify the air content and slump test results are within Specifications. • Record all test results on the Weekly Concrete Report (MnDOT Form 2448). Contractor

test results can be entered on a separate form and submitted with the Weekly Concrete Report.

16. Flexural Strength Testing (Beams):

• Observe Contractor make beams as required in the Schedule of Materials Control. • Contractor removes beams from boxes, cleans boxes, and reassembles boxes. • Agency cures and breaks beams. • Record beam break results on Concrete Test Beam Data (MnDOT Form 2162). • Verify minimum strength requirements for opening pavements to construction and to

general traffic. 17. Finishing and Texturing:

• Do not allow the Contractor to add water to the surface of the concrete to aid in finishing without the approval of the Engineer.

• Check surface using a 10 ft (3 m) straightedge to check for tolerance.

18. Ensure texturing is properly performed at appropriate time. • Check that the texture marks are uniform and parallel to centerline. • Provide random sand patch test locations to the Contractor. • Verify texture by observing Contractor sand patch testing. • Review the Contractor’s Concrete Texture results for compliance.

19. Headers:

• Construct construction headers, temporary headers, and permanent headers as shown on the plans and Standard Plates

• Do not allow incorporating any concrete accumulated in the grout box of the paver into the pavement. Construct all headers such that the concrete contained in the grout box is removed from the project.

• Use internal vibration to consolidate the concrete along header joints before final finishing.

Page 29: Section 2 - Procedures and tests

20. Curing:

• Verify an approved curing compound lot/batch is used by checking the Approved/Qualified Products list.

• Check application rate of curing compound for uniformity, yield, and timely placement. • Ensure compliance with cold weather protection requirements.

21. Sawing Joints:

• Check joint sawing operation. Check joint location adjustments at side streets, inlets, manholes, etc.

• Check appearance, depth, and width of sawed joints on a daily basis. No raveling and no random cracking should occur at the time of initial sawing.

• Widening of the joints shall not occur until the concrete is at least 24 hours old. 22. Sealing Joints:

• Verify joints are clean and dry before approving. • Do not allow traffic on the slab until the widened joints are sealed.

23. MIT-SCAN T2 Testing on the Hardened Concrete:

• Provide random testing locations to the Contractor. • Observe the Contractor scan the tie bar steel and dowel bar anchoring within 24 hours of

pavement placement as required in the Special Provisions. 24. Thickness (Cores) Verification:

• Observe the Contractor’s coring operation to verify authenticity. • Field measure concrete cores, record the results on the Field Coring Report and submit

cores to the MnDOT Laboratory for official measurement and testing.

25. Pavement Surface Smoothness: • Make sure the Inertial Profiler (IP) is certified and displaying the certification sticker on

the vehicle. Make sure IP operator is certified. See MnDOT Smoothness website for a list of the certified IP’s, required settings for individual certified IP’s, and certified operators.

• Observe all Contractor profiling, unless approved by the Engineer. • Review the Contractor’s printouts containing the IP’s settings, each segment’s left and

right IRI values, the signature of the operator and electronic ERD files submitted on the same day of the profiling.

• Review the Smoothness Assurance analysis for contract compliance. • Determine if grinding is needed or required. • Check the final Concrete Profile Summary reports for contract compliance.

26. Maintain Agency Daily Diary:

• Includes hours of production, equipment, concrete temperatures, air content, slump reading, cylinder and beam data, stations paved, width, depth, yield, weather, air temperatures, and problems or unique circumstances encountered.

27. Document all field results along with calculated w/c ratio test results and mix design data on

the Weekly Concrete Report (MnDOT Form 2448) and submit to the Concrete Engineering Unit on a weekly basis. Contractor field test results can be entered on a separate form and submitted with the Weekly Concrete Report.

Page 30: Section 2 - Procedures and tests

28. Submit the following to the MnDOT Concrete Engineering Unit:

• Weekly Concrete Reports – Form 2448 • Concrete Test Beam Data – Form 2162 • Field Coring Reports • Field Probing Reports • Concrete Texture Reports • Concrete Profile Summary Worksheets • Change orders and Supplemental Agreements

Page 31: Section 2 - Procedures and tests

AIR CONTENT WORKSHEET/CHART (1/2017)

1

5/5/14 5/5/14 5/5/14 5/5/14 5/5/14 5/5/14 5/5/14 5/5/14 5/5/14 5/5/14 5/5/14 5/5/14 5/5/14 5/5/14

7:46am 8:30am 9:55am 12:50pm 12:55pm 1:00pm 1:05pm 1:10pm 1:15pm 1:20pm 2:00pm 3:13pm 4:01pm 5:25pm

279+45 280+80 299+01 309+00 309+10 309+15 309+20 309+22 309+25 309+29 315+56 328+34 340+12 355+34

67 67 68 68 67 67 66 66 67 67 68 66 67 67

6.4 6.5 5.8 5.3 5.4 5.4 6.5 6.6 6.7 6.7 6.8 6.7 6.8 6.8

8:40am 2:10pm

280+82 315+59

68 67

5.5 6.1

1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 0.7 0.7 0.7 0.7

5.5 4.8 4.3 4.4 4.4 5.5 5.6 5.7 5.7 6.1 6.0 6.1 6.1Additional Information or Comments

Air Loss Correction Factor [a-b]

% Air or Adjusted % Air After Consolidation

Date

Time

% Air Before Consolidation [a]

% Air After Consolidation [b]

Station

Concrete Temperature

Concrete Temperature

Station

SP Number: 8901-23 Engineer: T.Sanders Contractor: TUV Paving

Time

Tester: Joe Tester

6.4 6.5

5.8

5.3 5.4 5.4

6.5 6.6 6.7 6.7 6.8 6.7 6.8 6.8

5.5

4.8

4.3 4.4 4.4

5.5 5.6 5.7 5.7

6.1 6.0 6.1 6.1

2.0

3.0

4.0

5.0

6.0

7.0

8.0AI

R CO

NTE

NT

(%)

% Air Before Consolidation % Air After Consolidation/Adjusted % Air After Consolidation

Page 32: Section 2 - Procedures and tests

1

Minnesota Department of Transportation

Mix Age Ave. Mix MixProject No.: No. No. No.Date: 3A21 3 535Project Engineer: 3A41HE 3 465Inspector: 3A21 28 762Contractor: 3A41HE 28 660

1A 508+00 5/5/14 3A21 8/26/13 6.12 6.00 20 560 B 0.98 550 31B 508+00 5/5/14 3A21 9/20/13 6.10 6.00 20 815 B 0.98 800 281C 508+00 5/5/14 3A212A 548+30 5/6/14 3A21 8/27/13 6.10 6.00 20 415 B 0.98 410 32B 548+30 5/6/14 3A21 9/21/13 6.10 6.00 20 710 B 0.98 700 282C 548+30 5/6/14 3A213A 569+00 5/7/14 3A41HE 8/28/13 6.10 6.05 20 480 B 0.97 465 33B 569+00 5/7/14 3A41HE 9/22/13 6.10 6.00 20 670 B 0.98 660 283C 569+00 5/7/14 3A41HE4A 589+20 5/8/14 3A21 8/29/13 6.10 6.00 20 653 B 0.98 645 34B 589+20 5/8/14 3A21 9/23/13 6.10 5.90 20 770 B 1.02 785 284C 589+20 5/8/14 3A21

8901.236/25/14

T.SandersL.Bean

TUV Paving

Ave. Strength

Age (days)

NotesIdentication No. StationDate Made

Ave. Strength

Modulus of Rupture

(psi)

Age (days)

Age (days)

Total Test Load (psi)

Spiral

Concrete Test Beam DataTP 2162-06 (1/2017)

Mix No.Date

Tested

Ave. Width "B"

(in)

Ave. Depth "D"

(in)

Span Length (in)

Area Correction

Factor

Page 33: Section 2 - Procedures and tests

1

Last Revised (1/2017)Minnesota Department of Transportation

Data Entry Enter the Entire project prior to start!

S.P.: Engineer: Inspector:

Starting Core #: 1 Is this an overlay where the slope/crown correction is with concrete? No

EBEBEBEBWBWBWB

Joe Inspector

TH 10 1 Lane Left of Centerline 65+00 130+00 12 8.0

60+00 12 8.0

TH 10 Off Ramp 0+00 12+00 18 7.0TH 10 1 Lane Right of Centerline 65+00 130+00 12 8.0

TH 10 1 Lane Left of Centerline 60+00 65+00 12 10.0TH 10 1 Lane Left of Centerline 0+10 60+00 12 8.0

Paving Contractor:

Roadway Direction LaneBegin Station

(ft)End Station

(ft)

TUV PavingT.Sanders8901-23

TH 10 1 Lane Right of Centerline 60+00 65+00 12 10.0

Lane Width(ft)

Design Thickness Requirement (in)

TH 10 1 Lane Right of Centerline 10+00

Page 34: Section 2 - Procedures and tests

2

Last Revised (1/2017)

Minnesota Department of Transportation

Field Probing ReportS.P.:

Corrected

Probe # Offset

P29 4.7

P30 1.4

P31 1.6

P32 14.3

P17 6.7

P5 5.3

P18 7.3

P6 10.6

P19 9.6

P20 8.9

P7 5.0

P21 6.4

P8 7.7

P9 5.7

P22 5.7

P1 2.7

P3 8.0

P2 1.8

P4 7.7

P10 6.3

TUV Paving8901-23 Engineer: T.Sanders Contractor:

5/5/14

5/7/14

5/7/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

TH 10, WB, 1 Lane Left of Centerline

15+11

14+02

8.1

7.1

8.4

Probed

Date

5/7/14

5/5/14

5/5/14

5/5/14

5/7/14

8.3

8.1

8.2

7.0

7.0

7.0

7.0

8.0

8.0

8.0

ThicknessRequirement

(in)

7.2

7.1Height

8.0

8.0

8.0

8.0

4+46

Station

TH 10, EB, Off Ramp

TH 10, EB, Off Ramp 4+44

Name

1+81Station

29+14

TH 10, EB, 1 Lane Right of Centerline

TH 10, EB, Off Ramp

25+09

TH 10, EB, Off Ramp

TH 10, EB, 1 Lane Right of Centerline

Offset from

pavement edge

25+05

19+35

9+05

TH 10, WB, 1 Lane Left of Centerline

Corrected

TH 10, WB, 1 Lane Left of Centerline

TH 10, WB, 1 Lane Left of Centerline 38+50

39+89

46+45

7+45

TH 10, EB, 1 Lane Right of Centerline

TH 10, WB, 1 Lane Left of Centerline

TH 10, EB, 1 Lane Right of Centerline 8.274+49

51+94

TH 10, EB, 1 Lane Right of Centerline

TH 10, WB, 1 Lane Left of Centerline 60+75

TH 10, EB, 1 Lane Right of Centerline 60+55

45+28

TH 10, WB, 1 Lane Left of Centerline 55+63

TH 10, EB, 1 Lane Right of Centerline 62+92 62+98

TH 10, WB, 1 Lane Left of Centerline 63+69

TH 10, EB, 1 Lane Right of Centerline

8.0

10.0

10.0

10.0

10.0

8.5

8.5

6.8

7.9

8.1

8.2

8.2

5/5/14

5/5/14

5/5/14

5/5/14

10.1

8.5

10.5

10.3

38+55

8.0

8.0

8.0

8.0

Page 35: Section 2 - Procedures and tests

3

Last Revised (1/2017)

Minnesota Department of Transportation

Field Coring ReportS.P.:

Core # Offset Offset

C15 4.7 PVC P29 7 7 7.0

C16 9.6 QAC 7.2 7.0

C9 7.3 PVC P18 8 8.2 8.0

C10 6.4 QAC 5.3 8 8.0

C4 2.3 QAC 8.1 8.0

C3 7.7 PVC P8 8.1 8.1 8.0

C12 3.9 QAC 8.2 8.0

C1 2.7 PVC P1 9.7 8.3 10.0

C2 4.6 QAC 10.1 10.0

C5 6.3 PVC P10 8.2 8.2 8.0

C11 5.3 PVC P24 8.1 8.2 8.0

C6 4.2 QAC 7.9 8.0

C7 3.5 PVC P14 8 8.1 8.0

C13 7.5 PVC P27 8.1 8.1 8.0

C8 3.0 QAC 5.5 8.2 8.0

C14 5.5 QAC 8.3 8.0127+36

74+49

84+28

86+38

106+60

112+17

120+26

1+81

7+75

19+35

25+37

38+42

46+45

58+30

60+55

62+65

TH 10, EB, 1 Lane Right of Centerline

TH 10, WB, 1 Lane Left of Centerline

TH 10, EB, 1 Lane Right of Centerline

TH 10, WB, 1 Lane Left of Centerline

TH 10, WB, 1 Lane Left of Centerline

TH 10, EB, 1 Lane Right of Centerline

TH 10, EB, 1 Lane Right of Centerline

TH 10, EB, 1 Lane Right of Centerline

TH 10, WB, 1 Lane Left of Centerline

TH 10, EB, 1 Lane Right of Centerline

TH 10, EB, Off Ramp

TH 10, EB, Off Ramp

TH 10, WB, 1 Lane Left of Centerline

TH 10, WB, 1 Lane Left of Centerline

TH 10, EB, 1 Lane Right of Centerline

TH 10, EB, 1 Lane Right of Centerline

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

5/7/14

5/7/14

5/5/14

5/5/14

5/5/14

5/5/14

Date CoredStation

8901-23

QCP Probe Height

Field Height

Core Type

Corrected

StationName

Engineer: T.Sanders Contractor: TUV Paving Joe InspectorInspector:

Date Poured

((REQUIRED))

7+71

84+23

ThickReq.(in.)Probe #

Page 36: Section 2 - Procedures and tests

4

Last Revised (1/2017)

Minnesota Department of Transportation

Concrete Texture ReportS.P.: 67,963

13 X

14 X

15 X

1 X

16 X

2 X

3 X

17 X

18 X

4 X

19 X

5 X

20 X

6 X

7 X

21 X

22 X

8 X

23 X

9 X

8901-23 Engineer: T.Sanders Contractor: TUV Paving

Dia. 1 (mm) Dia. 2 (mm) Dia. 3 (mm)

CarpetVolume of Spheres

(mm3):Texture Type:

Dia. 4 (mm)

285TH 10, EB, Off Ramp 285 287

285

285

287

TH 10, EB, 1 Lane Right of Centerline 18+07 245

289TH 10, WB, 1 Lane Left of Centerline 278 278

248

278

245TH 10, WB, 1 Lane Left of

Centerline 19+02 285 285TH 10, EB, 1 Lane Right of

Centerline 25+83

278

285TH 10, EB, 1 Lane Right of Centerline 33+01 285 285 285

TH 10, WB, 1 Lane Left of Centerline 36+06 278

278

285TH 10, WB, 1 Lane Left of Centerline 38+35 285 285 285

TH 10, EB, 1 Lane Right of Centerline

278

285TH 10, WB, 1 Lane Left of Centerline 55+65 285 285 285

TH 10, EB, 1 Lane Right of Centerline 57+91 278

278

285TH 10, WB, 1 Lane Left of Centerline 58+12 285 285 285

TH 10, EB, 1 Lane Right of Centerline

278

285TH 10, EB, 1 Lane Right of Centerline 71+21 285 285 285

TH 10, WB, 1 Lane Left of Centerline 76+97 278

279

274TH 10, WB, 1 Lane Left of Centerline 83+53 274 274 274

TH 10, EB, 1 Lane Right of Centerline

285

278TH 10, WB, 1 Lane Left of Centerline 88+86 278 278 278

TH 10, EB, 1 Lane Right of Centerline 99+10 285

Ave. Macrotexture Depth (mm)Test # Station

Outside Wheel Path

(OWP)

6+19

10+02

10+43

Name

TH 10, EB, Off Ramp

245

285

285

278 278 278 278

285

285

278 278

46+99 278 278 278

278 278

68+47 278 278 278

278 278

86+57 279 279 279

285 285

1.06

1.06

1.10

1.43

1.07

1.12

1.07

1.12

1.07

1.12

1.07

1.12

1.07

1.12

1.07

1.12

1.15

1.11

1.12

1.07

Page 37: Section 2 - Procedures and tests

5

Last Revised (1/2017)

Minnesota Department of Transportation

MIT-SCAN T2 ReportS.P.:

Scan #

14.2

13.1

13.2

14.3

13.3

14.4

14.5

13.4

14.6

14.7

13.5

13.6

15.1

13.7

15.2

1.1

14.1

15.3

1.2

1.3

5/5/14

5/7/14

TH 10, WB, 1 Lane Left of Centerline

TH 10, EB, Off Ramp

TH 10, EB, Off Ramp

Station

0+33

0+56

2+20

8901-23 Engineer: T.Sanders Contractor: TUV Paving

Name Corrected Station

YTH 10, WB, 1 Lane Left of

Centerline 11+94 11+85 5/5/14 Y

YTH 10, EB, 1 Lane Right of

Centerline 10+66 5/5/14 Y

Y

TH 10, EB, Off Ramp 9+64 5/5/14 Y

Y

TH 10, EB, Off Ramp 8+15 5/5/14 Y

YTH 10, WB, 1 Lane Left of

Centerline 6+70 6+79 5/5/14 n - Basket was adjusted

Y

TH 10, EB, Off Ramp 5+43 5/5/14 Y

TH 10, WB, 1 Lane Left of Centerline 9+94 5/5/14

TH 10, EB, Off Ramp 11+01 5/5/14

TH 10, EB, Off Ramp

Comments

5/7/14

TH 10, EB, Off Ramp 3+51 3+64 5/5/14

TH 10, WB, 1 Lane Left of Centerline 4+03 5/5/14

TH 10, WB, 1 Lane Left of Centerline 5+61 5/5/14

YTH 10, WB, 1 Lane Left of

Centerline 3+63 5/5/14 Y

Y

Y

YTH 10, WB, 1 Lane Left of

Centerline 2+38 5/5/14 Y

Date Scanned

7+05 5/5/14

TH 10, WB, 1 Lane Left of Centerline 8+54 5/5/14

TH 10, EB, 1 Lane Right of Centerline 12+63 5/5/14

5/5/14 Y

YTH 10, EB, 1 Lane Right of

Centerline 12+90

Page 38: Section 2 - Procedures and tests
Page 39: Section 2 - Procedures and tests
Page 40: Section 2 - Procedures and tests
Page 41: Section 2 - Procedures and tests
Page 42: Section 2 - Procedures and tests
Page 43: Section 2 - Procedures and tests
Page 44: Section 2 - Procedures and tests
Page 45: Section 2 - Procedures and tests
Page 46: Section 2 - Procedures and tests
Page 47: Section 2 - Procedures and tests
Page 48: Section 2 - Procedures and tests
Page 49: Section 2 - Procedures and tests
Page 50: Section 2 - Procedures and tests
Page 51: Section 2 - Procedures and tests
Page 52: Section 2 - Procedures and tests
Page 53: Section 2 - Procedures and tests
Page 54: Section 2 - Procedures and tests

1

Operation of MIT SCAN T2 Device –

Locating Reinforcement Bars and Dowel Bar Baskets 1. Assemble the device by connecting the two parts together. Do not force the connection. Be

sure the device is fully charged.

Page 55: Section 2 - Procedures and tests

2

2. To turn on the device, press both the top and bottom buttons on the handle and release.

3. The Main Menu will appear on the LCD panel. Main menu consists of:

A - Search/Measurement B - Location Settings C - System D - Data Management E - Off F - Device Settings

Page 56: Section 2 - Procedures and tests

3

4. To locate reinforcement bars or dowel bar baskets, select A – Search/Measurement.

5. Press and hold the bottom button on the handle while moving the device over the targeted area.

Page 57: Section 2 - Procedures and tests

4

6. To locate the reinforcement bars or dowel bar basket immediately after the paver or when the concrete is in plastic form, hover the device over the concrete. The wheels of the device do not need to touch the concrete for this function to work.

7. To locate the reinforcement bars or dowel bar basket when the concrete is in hardened form, either hover or roll the device over the concrete.

Page 58: Section 2 - Procedures and tests

5

8. If the sensor head approaches reinforcement bar or dowel bar basket from the side, one bar will appear higher than the rest. The four bars shown on the LCD panel represent four sensors evenly spaced on the bottom of the device (sensor head).

Note the location of rebar in relation to sensor.

Page 59: Section 2 - Procedures and tests

6

9. If the sensor head approaches the reinforcement bar or dowel bar basket straight on, all four bars will appear highest and equal.

10. For questions or further information, please contact: Robert Golish Assistant Concrete Engineer MnDOT Office of Materials and Road Research 1400 Gervais Avenue Maplewood, MN 55109 Office: 651-366-5576 Cell: 651-216-0516 Email: [email protected]