56
Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652 Fort Polk, Louisiana Solicitation No. W9126G20U0025 Bldg 3003 Section 01 10 00.01 Page 1 Section 01 10 00.01 BUILDING 3003 SCOPE OF WORK Table of Contents Part 1 General Part 2 Design Part 3 Civil/Site Engineering Part 4 Architectural Part 5 Mechanical Engineering Part 6 Electrical Engineering Part 7 Structural Engineering Part 8 Fire Protection Engineering Part 1: General This project is the design/build renovation of Tactical Equipment Maintenance Facility (TEMF) 3003. The bid schedule identifies the various items of work as being part of the base bid or options. 1.1 Description of Work This project shall include the design and construction renovations for TEMF 3003, to include roof replacement, exterior wall panel replacement, exterior and interior renovations and improvements, joint sealing for the hardstand area, and additional POV parking areas. The Contractor shall perform a thorough inspection of the TEMF and site prior to submitting a proposal. The Contractor shall be responsible for verifying all conditions, loadings, and dimensions, as stated in this document. Due to statutory limitations for the funding provided for this project, new construction, new features of work, and/or new amenities are restricted to those specifically identified in this summary of work or on the Appendix B drawings. 1.2 Phasing / Sequencing of Work TEMF 3003 is currently occupied. The government will cease operations throughout the interior of the building during construction. The contractor shall relocate all furniture, fixtures, and equipment to a temporary storage facility provided by the contractor. At the end of construction, the contractor shall return all items to their current location. Hardstand areas to be completed in four (4) phases, with 25% of hardstand areas to be vacated at a time.

Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 1

Section 01 10 00.01

BUILDING 3003

SCOPE OF WORK

Table of Contents

Part 1 General Part 2 Design Part 3 Civil/Site Engineering Part 4 Architectural Part 5 Mechanical Engineering Part 6 Electrical Engineering Part 7 Structural Engineering Part 8 Fire Protection Engineering

Part 1: General

This project is the design/build renovation of Tactical Equipment Maintenance Facility (TEMF) 3003. The bid schedule identifies the various items of work as being part of the base bid or options.

1.1 Description of Work

This project shall include the design and construction renovations for TEMF 3003, to include roof replacement, exterior wall panel replacement, exterior and interior renovations and improvements, joint sealing for the hardstand area, and additional POV parking areas.

The Contractor shall perform a thorough inspection of the TEMF and site prior to submitting a proposal. The Contractor shall be responsible for verifying all conditions, loadings, and dimensions, as stated in this document.

Due to statutory limitations for the funding provided for this project, new construction, new features of work, and/or new amenities are restricted to those specifically identified in this summary of work or on the Appendix B drawings.

1.2 Phasing / Sequencing of Work

TEMF 3003 is currently occupied. The government will cease operations throughout the interior of the building during construction. The contractor shall relocate all furniture, fixtures, and equipment to a temporary storage facility provided by the contractor. At the end of construction, the contractor shall return all items to their current location. Hardstand areas to be completed in four (4) phases, with 25% of hardstand areas to be vacated at a time.

Page 2: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 2

Resealing the joints and restriping work shall be sequenced and coordinated with the customer to allow a minimum of 50% of the hardstand to remain in use while this work is being performed. 25% of hardstand area to be for contractor laydown area. Provide temporary fencing or secure building nightly.

Part 2 Design

2.1 DESIGN REQUIREMENTS

The project shall be designed and constructed in accordance with the military criteria in conjunction with industry-standard criteria, materials, and efficient practices. The latest version of building codes shall be used as design guides provided there are no conflicts with the above requirements. In the event that a conflict exists between standards, the military standards take precedence. The building design and the materials selected shall be high quality, durable, easily maintained and meet the specifications. The Contractor shall be responsible for the professional quality, code compliance, technical accuracy and coordination of all designs, drawings, specifications and other documents or publications upon which the design and construction are based.

2.2 INDUSTRY CRITERIA

Applicable design and construction criteria references are listed in Table 1 below and shall be taken from the most current references as of the date of issue of the contract. This list is not intended to include all criteria that may apply or to restrict design and construction to only those references listed. See also Paragraph 2.3 for additional facility-specific applicable criteria.

Table 1: Industry Criteria Air Conditioning and Refrigeration Institute (ARI)

ARI 445 550/590

Room Air-Induction Units Water chilling packages using the vapor compression cycle

ARI 880 890

Air Terminals Air diffusers

ARI 1060

Air to Air Heat Exchangers for Energy Recovery Ventilation Heat Equipment.

Air Movement and Control Association (AMCA)

AMCA 210

Laboratory Methods of Testing Fans for Rating

American Architectural Manufacturers Association (AAMA)

Page 3: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 3

AAMA 605

Voluntary Specification Performance Requirements and Test Procedures for High Performance Organic Coatings on Aluminum Extrusions and Panels

AAMA 607.1

Voluntary Guide Specifications and Inspection Methods for Clear Anodic Finishes for Architectural Aluminum

AAMA 611 Voluntary Specification for Anodized Architectural Aluminum

AAMA 1503

Voluntary Test Method for Thermal Transmittance and Condensation Resistance of Windows, Doors, and Glazed Wall Sections

American Bearing Manufacturers Association (AFBMA)

AFBMA Std. 9

Load Ratings and Fatigue Life for Ball Bearings

AFBMA Std. 11

Load Ratings and Fatigue Life for Roller Bearings

American Boiler Manufacturers Association (ABMA)

ABMA ISEI

Industry Standards and Engineering Information

American Concrete Institute

ACI 318-14

Building Code Requirements for Structural Concrete

ACI SP-66

ACI Detailing Manual.

ACI 301-16

Specifications for Structural Concrete

TMS 402/602-16

Building Code Requirements and Specifications for Masonry Structures

Architectural Barriers Act (ABA)

ABA Accessibility Standards for DOD Facilities

(ABA Standards)

American Institute of Steel Construction (AISC)

AISC 325-17

Manual of Steel Construction (latest version)

AISC 360-16

Specification for Structural Steel Buildings

Page 4: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 4

American National Standards Institute 11 (ANSI)

ANSI Z21.45 Flexible Connectors of Other Than All-Metal Construction for Gas Appliances

ANSI/IEEE C2 National Electrical Safety Code

ANSI/AF&PA NDS National Design Specification for Wood Construction

American Society of Civil Engineers (ASCE)

ASCE 7-16 Minimum Design Loads for Buildings and Other Structures

ASCE 37 Design and Construction of Sanitary and Storm Sewers, Manuals and Reports on Engineering Practice [sanitary sewer and storm drain design criteria]

American Society of Heating, Refrigerating and Air Conditioning Engineers (ASHRAE)

ASHRAE 90.1 Energy Standard for Buildings Except Low-Rise Residential Buildings

• HVAC design and energy modeling must be inaccordance with ASHRAE 90.1-2010

• Continuous air barrier inspection and testing mustbe in accordance with the requirements ofASHRAE 90.1 2013, “Continuous Air Barrier” withthe following exceptions: Maintenance bays andsimilar areas that are not fully air conditioned shallbe inspected only. Per UFC 3-101-01.

• Lighting design must be in accordance withASHRAE 90.1-2016

ASHRAE 189.1-2014 Standard for the Design of High-Performance Green Buildings Except Low-Rise Residential Buildings

ASHRAE Guideline 1 The HVAC Commissioning Process

ASHRAE Hdbk-IP Handbook

Fundamentals I-P Edition

ASHRAE Standard 15- (AM-0004)>2013 2016 <(AM-0004)

Safety Standard for Refrigeration Systems

ASHRAE Standard 62.1 – -(AM-0004)>2010 2016 <(AM-0004)

Ventilation for Acceptable Indoor Air Quality

American Society of Mechanical Engineers International (ASME)

<(AM-0004) (AM-0004)>

<(AM-0004) (AM-0004)>

Page 5: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 5

ASME BPVC SEC VII Boiler and Pressure Vessel Code: Section VII Recommended Guidelines for the Care of Power Boilers

American Water Works Association (AWWA)

Standards [standards for water line materials and construction]

American Welding Society

AWS D1.1/D1.1M -15 with Errata’s

Structural Welding Code – Steel

AWS D1.3/D1.3M-18 Structural Welding Code – Sheet Steel

Architectural Woodwork Institute (AWI)

AWI Quality Standards

Associated Air Balance Council (AABC)

AABC MN-1 National Standards for Testing and Balancing Heating, Ventilating, and Air Conditioning Systems

AABC Associated Air Balance Council Testing and Balance Procedures

Builders Hardware Manufacturers Association (BHMA)

ANSI/BHMA A156 Series American National Standards for Builders Hardware

Building Industry Consulting Service International

Telecommunications Distribution Methods Manual (TDMM)

Customer-Owned Outside Plant Design Manual (CO-OSP)

Code of Federal Regulations (CFR)

10 CFR 430 Energy Conservation Program for Consumer Products

Consumer Electronics Association

CEA 709.1B Control Network Protocol Specification

CEA 709.3 Free-Topology Twisted-Pair Channel Specification

Page 6: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 6

CEA 852

Tunneling Component Network Protocols Over Internet Protocol Channels

Crane Manufacturers Association of America (CMAA)

CMAA 70-15

Specification for Top Running Bridge and Gantry Type Multiple Girder Electric Overhead Traveling Cranes

CMAA 74-15 Specifications for Single Girder Cranes

Electronic Industries Association (EIA)

EIA/TIA 568-B

Commercial Building Telecommunications Cabling Standards

ANSI/EIA/TIA 569-B

Commercial Building Standard for Telecommunications Pathways and Spaces

J-STD EIA/TIA 607

Commercial Building Grounding and Bonding Requirements for Telecommunications

Federal Highway Administration (FHWA)

FHWA-NHI-01-021

Hydraulic Engineering Circular No. 22, Third Edition, URBAN DRAINAGE DESIGN MANUAL and U.S. Weather Bureau Technical Paper No. 40, dated May 1961

Government Safety Requirements

UFGS 01 35 26

Government Safety Requirements

EM 385-1-1 (2014)

Safety and Health Requirements Manual

Illuminating Engineering Society of North America (IESNA)

IESNA Lighting Handbook

Reference and Application

Institute of Electrical and Electronics Engineers Inc. (IEEE)

Standard for Use of the International System of Units (SI): the Modern Metric System

International Code Council (ICC)

Page 7: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 7

IBC-2018

International Building Code 2018

Note: All references in the International Building Code to the International Electrical Code shall be considered to be references to NFPA 70.

All references in the International Building Code to the International Fuel Gas Code shall be considered to be references to NFPA 54 and NFPA 58.

All references in the International Building Code to the International Fire Code shall be considered to be references to Unified Facilities Criteria (UFC) 3-600- 01.

IMC

International Mechanical Code

IPC

International Plumbing Code

IEC

Energy Conservation Code (IEC) – Deleted DEC 2007- Refer to Paragraph 5.3.2, ENERGY CONSERVATION requirements.

IGC

International Gas Code - not applicable. Follow NFPA 54, National Fuel Gas Code and NFPA 58, Liquified Petroleum Gas Code.

International Organization for Standardization (ISO)

ISO 6781:1983

Qualitative detection of thermal irregularities in building envelopes – infrared method

Metal Building Manufacturers Association (MBMA)

MBSM -18

Metal Building Systems Manual

Midwest Insulation Contractors Association (MICA)

National Commercial and Industrial Insulation Standards Manual

National Association of Corrosion Engineers International (NACE)

NACE RP0169

Control of External Corrosion on Underground or Submerged Metallic Piping Systems

NACE RP0185

Extruded, Polyolefin Resin Coating Systems with Adhesives for Underground or Submerged Pipe

Page 8: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 8

NACE RP0285 Corrosion Control of Underground Storage Tank Systems by Cathodic Protection

NACE RP0286 Electrical Isolation of Catholically Protected Pipelines

National Electrical Manufacturers Association (NEMA)

National Environmental Balancing Bureau (NEBB)

Procedural Standards Procedural Standards for Testing Adjusting Balancing of Environmental Systems

National Fire Protection Association (NFPA)

NFPA 10 - 2018 Standard for Portable Fire Extinguishers

NFPA 13 - 2019 Installation of Sprinkler Systems

NFPA 20 - 2019 Standard for the Installation of Stationary Pumps for Fire Protection.

NFPA 24 - 2019 Standard for the Installation of Private Fire Service Mains and Their Appurtenances [underground fire protection system design]

NFPA 30 - 2018 Flammable and Combustible Liquids Code

NFPA 30A - 2018 Code for Motor Fuel Dispensing Facilities and Repair Garages

NFPA 54 - 2018 National Fuel Gas Code

NFPA 70 - 2020 National Electrical Code

NFPA 72 - 2019 National Fire Alarm Code

NFPA 80 - 2019 Standard for Fire Doors and Fire Windows

NFPA 90a - 2018 Installation of Air Conditioning and Ventilating Systems

NFPA 101 - 2018 Life Safety Code

NFPA 291 - 2019 Recommended Practice for Fire Flow Testing and Marking of Hydrants

NFPA 400 - 2019 Hazardous Materials Code

Page 9: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 9

National Roofing Contractor’s Association (NRCA)

Roofing and Waterproofing Manual

Plumbing and Drainage Institute (PDI)

PDI WH201

Water Hammer Arrestors

Rainfall Frequency Atlas

US Atlas- NOAA

Rainfall frequency Atlas of the United States for Durations from 30 minutes to 24 hours, and return periods from 1 to 100 years.

Sheet Metal and Air Conditioning Contractor’s National Association (SMACNA)

SMACNA HVAC Duct Construction Standards

HVAC Duct Construction Standards - Metal and Flexible

SMACNA Architectural Manual

Architectural Sheet Metal Manual

SMACNA HVAC TAB

HVAC Systems - Testing, Adjusting and Balancing

State/Local Regulations

State Department of Transportation Standard Specifications for Highway and Bridge Construction, latest edition.

Sedimentation and Erosion Control Design Requirements

Environmental Control Requirements

Storm Water Management Requirements

American Water Design Guide

American Water Design Specifications and Standard Details

Louisiana Department of Health and Hospitals (LDHH)

Louisiana DOTD, Office of Highways

Louisiana Department of Environmental Quality

Steel Door Institute (SDI)

Page 10: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 10

ANSI A250.8/SDI 100 Standard Steel Doors and Frames

Uniform Federal Accessibility Guidelines (UFAS)

JTRC and Fort Polk Regulation 200-1 Environmental Quality

Installation Environmental Performance Requirements

Available at: https://home.army.mil/polk/application/files/8115/5248/8821/JRTC_and_FP_Reg_200-1.pdf

2.3 MILITARY CRITERIA

The project shall conform to the following criteria. Certain design impacts and features due to these criteria are noted for the benefit of the offeror. However, all requirements of the referenced criteria will be applicable, whether noted or not, unless otherwise specified herein. The current edition as of the date of the contract award is applicable. Dates listed below are current as of the date this RFP was submitted.

UFC 1-200-01, 8 October 2019, DoD Building Code General Building Requirements

UFC 1-200-02 – High Performance And Sustainable Building Requirements. Footnote 1 of Table 1-1 UFC 1-200-02 (Oct. 2019) indicates that the Project Delivery Team (PDT) can define the requirements relative to the scope of the project/work. The PDT has determined that the CMU exterior walls and the overhead coiling doors are not in the scope of work for sustainability energy analysis. Many overhead coiling doors are to be replaced with insulated doors as indicated below. The sustainability documentation will be reviewed by a third party commissioning agent rather than Third Party Certification.

UFC 3-101-01 – Architecture

UFC 3-301-01, 01 October 2019, Structural Engineering

UFC 3-401-01 – Mechanical Engineering

UFC 3-410-01 – Heating, Ventilating, And Air Conditioning Systems

UFC 3-410-02 – Direct Digital Control For HVAC And Other Building Control Systems

UFC 3-420-01 – Plumbing Systems

UFC 3-501-01 – Electrical Engineering

UFC 4-010-01, 12 December 2018, DoD Minimum Antiterrorism Standards for Buildings

Page 11: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 11

2.4

UFC 4-020-01, 11 September 2008, DoD Security Engineering Facilities Planning Manual

UFC 4-214-02, March 2015, Tactical Equipment Maintenance Facilities (TEMF) Standard Design, available at https://mrsi.erdc.dren.mil/cos/standard-designs

Tactical Equipment Maintenance Facilities (TEMF) Legacy Facilities Renovation Study, available at: https://mrsi.erdc.dren.mil/cos/standard-designs

Architectural and Engineering Instruction Manual, Southwest Division January 2003

Hydraulic Engineering Circular No. 22

I3A Installation Information Infrastructure

UFC 3-310-01 Design: Structural Load Data

UFC 3-210-10 Low Impact Development

UFC 3-230-17FA Drainage in Areas Other than Airfields

UFC 3-580-01 Telecommunications Bldg Cabling Systems Planning/Design

UFC 3-600-01, 8 August 2016, Change 4, 7 February 2020: Fire Protection Engineering for Facilities

UFC 4-010-01 DoD Minimum Antiterrorism Standards for Buildings (Dec 12 2018)

UFC 4-021-01, 9 April 2008, Change 1, January 2010: Design and O&M: Mass Notification Systems

Technical Guide for Installation Information Infrastructure Architecture (I3A)

DESIGN FEATURES

The design of architectural, interior, structural, mechanical, fire protection, electrical, environmental, civil, and other engineering features of the work shall be accomplished and reviewed and approved by engineers, architects, and interior designers registered to practice in their respective professional field. The Contractor shall comply with the requirements of the Louisiana Department of Environmental Quality (LDEQ), LDEQ General Permit No. LAR 200000. The Contractor is responsible for providing and maintaining the pollution prevention plan. The contractor shall be required to apply for Construction related storm

Page 12: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 12

water permits and pay the permitting fees. The contractor shall send a copy of the storm water application and proof of payment of the fee to the contracting officer, who will then forward to the installation’s environmental division (ENRMD). The contractor is required to send LDEQ a Notice of Termination of the storm water permit when construction activities are completed. A Notice of Termination shall not be filed until Final Stabilization is achieved.

Comply with JTRC and Fort Polk Regulation 200-1 Environmental Quality Installation Environmental Performance Requirements. Available at: https://home.army.mil/polk/application/files/8115/5248/8821/JRTC_and_FP_Reg _200-1.pdf Comply with “JRTC and FORT POLK – ENVIRONMENTAL SPECIFICATIONS FOR CONTRACTS As of 4 DEC 2019” in the Attachments of this package.

2.5 DESIGN UNITS

The designs shall be developed using the English inch-pound (I-P) system of units. This project includes inch-pound units of measurements. Submittals for Government approval or for information only shall cover the I-P products furnished for the project. The Contractor shall submit the required drawings and calculations in the same units used in the contract documents describing the product or requirement unless otherwise instructed or approved.

Part 3 Civil / Site Engineering

3.0. SITE PLANNING AND DESIGN GENERAL. See CS100 for the project location keymap.

3.0.1. EXISTING CONDITIONS. The site is located within the 3000 Building block. The 3000 Block is bound by Pennsylvania Avenue to the North, Texas Avenue to the East, Louisiana Avenue to the South, and Georgia Avenue to the West. The main access point is on Georgia Avenue. The building address is: 7229 Georgia Avenue, Fort Polk, LA 71459.

3.0.2. The Contractor’s work shall include, but not limited to: resealing joints in the existing hardstand, replacing sunken pavement, curb removal, restriping the existing hardstand, site grading, storm drainage, new asphalt POV parking lot, and all details necessary for construction. The project site shall be designed and constructed in accordance with the following criteria:

a. The Contractor shall be responsible for design and construction ofsite and facilities within the specific site responsibility areasdefined.

• The Contractor shall remove the existing striping on thehardstand around Building 3003 and restripe the hardstandwith white paint as the existing configuration shows. Thevehicle numbers on the hardstand shall be removed but not berepainted. The pavement markings shall comply with theinstallation requirements and the Manual on Uniform Traffic

Page 13: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 13

Control Devices.

• The Contractor shall remove, clean and replace all jointsaround the building perimeter. The perimeter of the building isapproximately 800 feet.

• The Contractor shall provide a new dumpster pad andenclosure for 3 dumpsters meeting design guidelines on theaccess drive outside the fence around the hardstand near thenew asphalt parking lot. New dumpster screens shall belocated per UFC 4- 010-01. Dumpster screening shall becompatible with the building it serves and shall be sized toaccommodate trash (front loading) dumpsters. Newlyconstructed dumpster pads shall not impede proper drainage.

• The Contractor shall replace any sidewalks damaged duringthe construction of this contract to its original or bettercondition. The Contractor shall provide sod for all graded anddisturbed areas.

• The Contractor shall provide a final Grading Plan. TheContractor shall ensure drainage away from the buildings andthat new surface inlets and curb inlets are properly sized forthe drainage directed to each inlet.

• See CLIN Options. The Contractor shall construct a newasphalt parking lot on the west side of Georgia Avenue at thelocation shown on sheet CS101. The parking lot shall beconstructed with curb and gutter and have proper drainageconnected to an existing drainage structure that complies withthe storm design requirements. The existing power poles in thevicinity of the new parking shall remain. The flexible pavementsection at a minimum shall be a minimum of two (2) 1.5”HMAC pavement lifts for a minimum total of 3” of HMAC, 7”base course with CBR=50 compacted to at least 100 percentof maximum laboratory density (ASTM D 1557), geotextilelayer, 6” drainage layer consisting of open graded gravelcompacted to at least 95 percent of maximum laboratorydensity (ASTM D 1557), geotextile layer, and 6” Raw Subgradecompacted to at least 90 percent of maximum laboratorydensity (ASTM D 1557). Drainage within drainage layer to befacilitated through underdrain piping or surface drainage(daylighting). Parking stalls for the new parking lot shall be 9ft. x 18 ft. Provide striping for the new parking lot and restripethe existing parking lot using the existing configuration. Thestriping work shall be sequenced to keep one parking lot inservice. The pavement markings shall comply with theinstallation requirements and the Manual on Uniform TrafficControl Devices.

Page 14: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 14

• The Contractor shall remove, clean and replace all joints in the hardstand around building 3003.

Specific work shall include, but not be limited to the following (see sheet CS101 for numbered scope item locations). Additionally, all work items noted as (American Water) will be designed and performed by private water supplier but shall be coordinated by the contractor with all other work activities. Coordination shall be through the Fort Polk DPW utility COR, and with American Water:

1. Construct 39 space asphalt POV parking lot 2. Remove and replace wash rack water spigots

3. Remove and repaint striping on hardstand

4. Remove, clean and seal all joints in hardstand, evaluate concrete

panels in hardstand and replace approximately 2% of concrete panels

5. Remove wash rack grates, clean trench drain and replace damaged

grates, repair hardstand (approximately 220 SY)

6. Adjust hydrant to grade (American Water)

7. Locate and adjust existing drainage inlet to grade

8. Construct concrete dumpster pad and enclosure for 3 dumpsters

9. Grease racks to be removed, hardstand to be repaired as needed

(approximately 200 SY)

10. Fuel concrete islands and bollards to be removed, hardstand repaired as needed (approximately 400 SY)

11. Remove and replace culvert

12. Cut and cap existing 1 1/2" diameter water service, abandon existing

service in place (American Water)

13. Remove and replace drainage inlet, inspect pipe and repair as needed, remove and replace concrete apron (approximately 80 SY)

b. The Contractor shall accept the site as is and be solely responsible all surveys required. Excess soil may not be wasted within the work area without the written approval of the Contracting Officer’s Representative (COR). All waste material shall be disposed of on post and coordinated with Directorate of Public Works (DPW).

Page 15: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 15

c. Construction trailer complex will not be allowed on the project site. Contractor lots are available for use during the period of performance of this project on a space-available basis. Refer to Section 01 35 12.00 44, Special Project Procedures for Fort Polk, for additional information.

d. All temporary utilities are the responsibility of the Contractor. The Contractor shall coordinate with the American Water Enterprise Military Services Group (AW) if temporary water is required.

e. The Contractor shall provide electronic design files (CADD/GIS) for the site as part of their design and construction responsibilities.

f. DESIGN SUBMITTAL: The Contractor’s site design shall include separate drawings to include, but not limited to Demolition Plan, Storm Drainage Plan, Grading Plan, Layout Plan, Utility Plan, Profiles. Complete design calculations shall be included in a design analysis for site development items such as storm drainage and storm drainage structures. See also Section 01 33 16.00 10, Design After Award.

g. The Contractor is responsible for obtaining all necessary permits required for construction. A digging permit shall be obtained before any excavation is begun. Digging permits at Fort Polk require several in-person visits of several hours each.

3.1. SITE ENGINEERING

3.1.1. BASE UTILITY INFORMATION AND DESIGN REQUIREMENTS

Water, Sanitary Sewer and Electric have Privatized Utility Providers (PUP) at Fort Polk. The PUPs own and operate the utilities up to the point of demarcation, and the individual projects are responsible for everything on the building side of the demark. The contractor shall coordinate though the Fort Polk DPW PUP Contracting Officer Representative (COR) for each utility. Coordinate during design and construction. All outages shall be coordinated well in advance of need or occurrence.

3.1.2. WATER DISTRIBUTION: The design and construction of water distribution piping shall be in accordance with UFC 3-230-01 for water distribution system criteria. The PUP is American Water. The demark for bidding purposes is the first valve inside the building. Verify during design.

3.1.3. SANITARY SEWER: There are no renovations to the sanitary sewer service lines required with this project. The Contractor shall repair or replace any existing utilities damaged during construction. The PUP is American Water. The demark for bidding purposes is the first cleanout closest to the building. Verify during design. There is no known sanitary sewer work in this project.

Page 16: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 16

3.1.4. STORM DRAINAGE SYSTEM: The design and construction of the storm drainage system shall be in accordance with UFC 3-230-17FA Drainage in Areas Other than Airfields, Federal Highway Administration Publication No. FHWA-NHI-01-021, Hydraulic Engineering Circular No. 22 Second Edition URBAN DRAINAGE DESIGN MANUAL, and U.S. Weather Bureau Technical Paper No. 40, dated May 1961, Rainfall Frequency Atlas of the United States for Durations from 30 minutes to 24 hours, and return periods from 1 to 100 years. Design of the storm drainage system shall incorporate the principles of Low Impact Development (LID), as detailed in UFC 3-210-10 DESIGN: LOW IMPACT DEVELOPMENT MANUAL. The Contractor has the option of using concrete pipe, corrugated steel pipe, corrugated aluminum alloy pipe, PVC or Corrugated PE pipe for the underground storm drain pipes, where applicable except that all pipe repair shall use pipe materials matching existing pipe. The Contractor is responsible for designing the storm drainage system to be as economical as possible, while taking into account the topography, drainage area, and outfall locations, as well as coordination with existing drainage systems, and existing and future underground utilities. During the construction of the facilities, the Contractor shall be responsible for the SWPPP for the entire construction site limits.

3.1.5. STORMWATER MANAGEMENT MEASURES: Install stormwater management measures that meet the requirements of Section 438 of the Energy Independence and Security Act of 2007. The Contractor's design shall maintain or restore, to the maximum extent technically feasible, the predevelopment hydrology of the site with regard to the temperature, rate, volume, and duration of flow in accordance with Section 438 of the Energy Independence and Security Act of 2007. Design of the stormwater management facilities shall be in accordance with the Environmental Protection Agency’s (EPA) Technical Guidance on Implementing the Stormwater Runoff Requirements for Federal Projects under Section 438 of the Energy Independence and Security Act, dated December 2009.

3.1.6. NATURAL GAS: Natural gas service will NOT be modified. The demark for natural gas for bidding purposes is the building side of the meter. For bidding purposes, there are no changes to the natural gas service needed. Verify during design.

3.1.7. HARDSTAND REPAIR: The design and construction of hardstand repair and replacement shall conform to UFC 3-250-04 STANDARD PRACTICE FOR CONCRETE PAVEMENTS. Concrete joint types shall be consistent with original pavement design intent and adjacent joint types.

3.1.8. HARDSTAND JOINT SEALING: Hardstand joint sealing shall conform to UFC 3-250-08FA including joint cleaning and sealant replacement.

3.1.9. ELECTRICAL SERVICE: There are no changes to the electric service for

Page 17: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 17

bidding purposes. Verify during design. The PUP is Entergy, the power supply is considered reliable with outages totaling 124 minutes from Oct, 2017 through March 2020, therefore no generator is required for electric fire pumps. The demark for bidding purposes is the secondary side of the transformer, which is close to the building. If any work is indicated for light poles, for bidding purposes we believe they are fed from the building, so the electrical would be in this contract. Verify during design. The DPW PUP COR is Linda C. Howard, DPW O&M Division, Privatized Utilities COR, Ft. Polk, LA 71459, 337-531-1439, [email protected]

3.2. SITE STRUCTURES AND AMENITIES

3.2.1. LOUISIANA POLLUTANT DISCHARGE ELIMINATION SYSTEM (LPDES). The Contractor shall comply with the requirements of general permit number LAR200000. The Contractor is responsible for providing and maintaining his construction activity storm water pollution prevention plan (SWPPP).

3.2.2. FORCE PROTECTION. The Contractor shall adhere to the applicable levels of protection as specified in UFC 4-010-01 to the extent required for the renovations being made to this facility.

Part 4 Architectural

4.1 General Description

See bid schedule for list of bid options. Unless listed as “Bid Option”, the base bid work shall include renovations to existing buildings as follows:

(a) Existing interior and exterior finishes shall be replaced as indicatedin drawings with durable, easily maintainable materials that areaesthetically similar to an industrial office environment.

(b) New finishes and 50% of interior doors and 100% of exteriorswing doors and hardware will be replaced throughout the building.Hardware on remaining doors shall be adjusted and 50% replaced. TheDB DOR will inventory the doors and will provide recommendations tothe COR for review. The worst/most important doors are to be selectedfor replacement.

(c) The contractor shall provide utility connections to appliances andequipment indicated to be Government Furnished, Government Installed(GFGI).

(d) The existing metal roof shall be replaced with a new StandingSeam Metal Roof System (SSMRS) with a minimum SolarReflectance Index (SRI) of 39. Roof system shall include all trims,gutters, downspouts, curbs, fascias, soffits and required accessories.

(e) Existing exterior metal wall panels shall be replaced compatible

Page 18: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 18

with SSMRS and painted to match base standard color. CLIN OPTION: Existing exterior metal wall panels shall be replaced with an insulated sandwich panel compatible with SSMRS, instead of field applied insulation.

(f) Administration and open areas shall be renovated as follows:

(1) All metal panel partitions, including metal liner panels installed on the interior face of exterior walls, shall be removed and replaced with gypsum wallboard partitions on metal studs. All drywall exposed to high traffic areas like corridors and staging areas shall be impact resistant. All drywall located in damp areas shall be mold resistant and water-resistant. All areas to receive tile shall be tile backer cementitious board.

(2) Approximately 50% of interior personnel doors shall be removed and replaced with new doors. Door removal and installation shall include frames, hardware and any accessories. See drawings for additional information.

(3) All suspended acoustical tile (ACT) ceilings shall be replaced with 2’ x 2’ suspended ACT system complete with all lighting fixtures, fire protection, HVAC & Communication ceiling-mounted equipment. Other indicated areas shall have suspended gypsum board ceiling systems.

(4) New floor finishes shall be installed at all office areas latrine and interior rooms. All floor finishes to be polished concrete, except latrine and the Comm room or enclosure.

(5) New plumbing fixtures and accessories shall be installed at all restroom areas as indicated in drawings.

(6) New High-Density Polyethylene HDPE, Class A fire rated toilet partitions shall be provided, with full height stainless steel hinges and stainless steel hardware.

4.2 Demolition

4.2.1 TEMF Building 3003

4.2.1.1 Interior

(a) Admin Areas: Remove all ceiling, and floor finishes, doors as applicable, frames, and hardware, as indicated. Remove all metal liner panels on the interior side of the exterior walls. See other sections of this document for the demolition of electrical, mechanical items. Prepare all surfaces to receive new appliances, fixtures, doors and frames as required.

Page 19: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 19

(b) The Contractor shall remove all furniture, to a conditioned storagespace provided by the contractor. Near the end of the project thecontractor shall return all furniture to its original location. The contractorshall coordinate with the user any existing equipment to be re-used sothat it may be protected in place or temporarily removed or stored inconditioned storage space provided by the contractor. The Contractor isresponsible for moving of any remaining excess furniture and shalldispose of or store in conditioned space provided by the contractor. Anydamaged furniture or equipment to be protected-in-place or stored duringconstruction shall be repaired or replaced with an item that has the samesize, function and appearance at the contractor’s expense.

4.2.1.2 Exterior

(a) Remove all metal wall panels, downspouts, personnel doors &door frames (unless noted otherwise), including all hardware andaccessories from Bldg. 3003. Coordinate removal or protection of otherexisting wall-mounted equipment with appropriate discipline.

(b) Remove all existing metal roof system from Building 3003,including trim, gutters, fascias, ridge vents, skylights, roof underlayments,insulation and insulation retainers, as applicable. Coordinate all roofpenetrations with appropriate discipline and prepare the structure toreceive a new roof system as required.

(c) Existing exterior overhead doors: Contractor shall repair and/orreplace all damaged doors and door frames from Bldg. 3003 as required.See notes on drawings for an approximate count of doors to be completelyreplaced vs. repair/motorization work. Overhead doors shall includeframes, guides, motors, controls, manual chain override, safety stop, andany other attachment needed to make it a fully functional motorized doorwith electrical push button operation.

(d) Repair/replace cast iron downspout boots. Refer to drawings.Currently the cast iron boots discharge into an undergroundstorm drain, and this condition is to remain. Flush (hydro jet)storm lines.

4.2.1.3 Environmental Surveys and Abatement

The Record of Environmental Consideration (REC) for the building is provided in Appendix D. In addition to the materials identified in the REC, the Contractor shall assume for bidding purposes that asbestos-containing materials and/or lead are present in the following materials: all pipes; the ceiling texture throughout the building; floor mastic and VCT; paint on the door frames, stair railings, and bollards; caulking in the exterior control/expansion joints; caulking around windows and doors; telecommunications copper building service splices (lead splices). The

(AM-0004)>

<(AM-0004)

Page 20: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 20

Contractor shall perform an environmental survey of the building after award to determine actual abatement requirements. If the Contractor’s environmental survey and the REC both indicate that abatement of a particular material is not necessary, a modification will be issued to delete the unnecessary abatement.

4.3 New Work

The new work will be applicable to building 3003 except as indicated herein.

4.3.1 Functional/Operational Requirements

The plans in Appendix B show the intended functional layout of Building 3003.

4.3.1.2 Accessibility Requirements

Able-bodied soldiers occupy TEMF facilities; therefore, the Architectural Barriers Act (ABA) requirements do not apply to TEMF facilities.

4.3.1.3 Repair and Maintenance Bays

(a) Pressure-wash all floors, provide new finishes as indicated and paint all exposed structural steel frame. Prepare steel structure as required to install new exterior metal wall panels.

(b) The restroom areas shall receive new tile floors and walls. All bathrooms are to receive full height tile on walls. Provide a minimum 6 foot high wall tile wainscot in janitor closets. Ceramic floor tile size shall be a minimum of 12 inches by 12 inches, except when trimmed at borders. All substrate for wall tile shall be ½ inch minimum thickness cementitious backer boards. Restrooms shall receive new wash fountains or lavatories (see drawings). All countertops shall be a composite material, minimum ¾ inch (2 cm) thick throughout the material, unless specified otherwise, and be abrasion-resistant. All edges shall be beveled or radiused. All faucets and tub/shower valves shall use the same interchangeable, ceramic cartridge and be single handed. Balancing valves shall have an adjustable flow control.

(c) Refer to structural, mechanical & electrical chapters for additional requirements in Repair Bays. (d) Central bench tops to be removed.

(e) Provide new concrete-filled steel pipe bollards around unprotected permanent mechanical equipment located around the perimeter of the building.

Page 21: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 21

(f) All interior bays shall be cleaned, patched and repaired where needed. CMU walls shall be painted with semi-gloss paint. See Fort Polk Standard Color Schedule at the end of this section.

(g) Provide new doors and hardware as indicated in drawings in Appendix B.

(h) Provide new wall and floor finishes in all areas. Paint walls. All floor finishes to be polished concrete, except latrine and the Comm room or enclosure.

4.3.1.4 Administrative Areas

(a) New gypsum wallboard (GWB) partitions on metal studs shall be provided throughout in lieu of existing metal panel wall system. Provide batt insulation for sound attenuation. Impact resistant GWB shall be used on heavy use public areas like corridors, stairs, storage and staging areas (mezzanines). This applies to the admin rooms on the mezzanines. For bidding purposes assume the same door and wall configuration as shown. Provide architectural design services and meet with COR and user groups to determine if a different interior wall layout should be considered.

(b) Provide and install new suspended ACT or gypsum ceiling system as indicated in drawings in Appendix B.

(c) Provide new doors and hardware as indicated in drawings in Appendix B.

(d) Provide new wall and floor finishes in all areas. Paint walls. All floor finishes to be polished concrete, except latrine and the Comm room or enclosure.

4.3.1.5 Fire Extinguisher Cabinets and Fire Extinguishers

Furnish and install fire extinguisher cabinets (FEC) and fire extinguishers as required by applicable codes and criteria. Fire extinguishers shall be a minimum of 15 lbs Type ABC. Fire extinguisher cabinets mounted on fire-rated walls or partitions shall be appropriately rated for that wall. Similarly, any other equipment, panel, accessory or wall mounted item shall not diminish or compromise the fire rating of rated walls. If any item called to be recessed on the wall is not available as a fire-rated assembly, or a rated assembly cannot be constructed around it, the item shall be surface mounted on the wall.

4.3.2 Hardware 4.3.2.1 Emergency Key Box

Provide a non-destructive emergency access system with the following

Page 22: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 22

features:

• Rapid Entry System

• Knox-Box 3200 series w/ tamper switch (connected to fire alarmsystem)

• Exterior dimension: Recessed mount- 7” H x 7” W x 3 ¼” D

• Lock UL Listed. Double-action rotating tumblers and Hardenedsteel pins accessed by a biased cut key.

• Finished Pre-treated – Zinc-phosphate to Federal Standard TTC490 Type II

• Final Coating – weather-resistant interior and Exterior TGICpolyester powder coat.

• Finish Color – Black

• P/N: 3200 Series KNOX-BOX (mfr’s. cat. ID)

• Manufacturers’ name: KNOX COMPANY

• Locate 1 Knox Box per building within plain sight, maximum 6’-0”above finished floor level near the fire sprinkler riser room/firedepartment connection.

4.3.2.2 Finish Hardware

Locksets for mechanical, electrical and communications rooms only shall be keyed to the existing Installation Master Keying System. Plastic cores are unacceptable. Provide closers for all exterior doors, all doors opening to corridors and as required by codes. Push pad rim exit devices shall be installed at all building egress doors. All hardware shall be stainless steel Grade 1. All lockset functions shall match existing except where a change of room function is required; in that case, the contractor shall install an appropriate lockset for that function in accordance with applicable codes. All exterior doors shall be fully weatherstopped with stainless steel retainers. All exterior door frame heads shall have an extruded aluminum rain drip extending at least 1.5 inches in front of the face of the door. The door bottom shall have a seal and extruded aluminum door rain drip. Thresholds shall have weatherstrip ADA waterstops.

4.3.2.3 Auxiliary Hardware

Provide wall or floor stops for all doors that do not have overhead holder/stops. Wall stops at drywall partitions are not allowed unless solid wood blocking is provided. Provide other hardware as necessary for a complete installation. All hardware shall be Grade 1.

4.3.2.4 Hardware for Fire Doors

Hardware for fire doors shall be installed in accordance with the requirements of applicable codes. Exit devices installed on fire doors shall have a visible label bearing the marking "Fire Exit Hardware." Other hardware installed on fire doors, such as locksets, closers, and hinges,

Page 23: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 23

shall have a visible label or stamp indicating that the hardware items have been approved by an approved testing agency for installation on fire-rated doors. Hardware for smoke-control door assemblies shall be installed in accordance with applicable codes. All hardware shall be stainless steel Grade 1.

4.3.3 Acoustical Requirements

4.3.3.1 Doors, Windows & Interior Partitions

Doors, windows and new interior partitions shall be designed to provide for attenuation of external noise sources such as airfields in accordance with applicable criteria, but no less than the following:

(a) New interior partitions, except in non-occupied areas – STC 49

(b) New interior doors and frames, except in non-occupied areas– STC 33.

4.3.3.2 Mechanical/Electrical Equipment

4.4

Sound conditions (and levels) for interior spaces, due to the operation of mechanical and electrical systems and devices, shall not exceed levels as recommended by ASHRAE handbook criteria. Provide acoustical treatment for drain lines and other utilities (HVAC) to prevent noise transmission into the office spaces. All motors and pumps shall be of a type that does not require field lubrication.

Exterior

The exterior envelope of Building 3003 shall meet or exceed performance requirements indicated in Chapter 5 Mechanical Engineering.

(AM-0004)> Continuous air barrier inspection and testing must be in accordance with the requirements of ASHRAE 90.1 2013, “Continuous Air Barrier” with the following exceptions: Maintenance bays and similar areas that are not fully air conditioned will be inspected only. Per UFC 3-101-01. Air Barrier testing is required for core spaces that are air-conditioned. <(AM-0004)

It is the intent of this project to mimic the architectural character of other TEMF projects recently completed at Fort Polk.

4.4.1 Exterior Wall Panels

Replace all existing metal wall panels. Factory finish all wall panels to match exterior colors at existing TEMF building 3802. All wall insulation shall be new.

Prepare existing wall framing and any additional new substrate to receive a new wall panel system. Add new sub-framing as required or re-configure the existing sub-frame as needed to comply with loading requirements and new panel geometry. New exterior wall panels shall be part of the overall

Page 24: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 24

building envelope and shall meet or exceed performance requirements indicated in Chapter 5 Mechanical Engineering. Add insulation if none exists at the metal siding and replace all existing insulation. All wall insulation shall be new. Metal panels shall be compatible with SSMRS and shall be similar in color and appearance to the new TEMF building 3802. See Fort Polk Standard Color Schedule at the end of this section.

New wall metal panel system base bid to be a composite system with batt insulation in the cavity between the metal panel and interior. CLIN Option: metal insulated sandwich panel system instead of field applied batt insulation. Provide joints, sealants, air/vapor barriers, trims and flashings around existing and new windows and where required to provide an energy-efficient envelope.

4.4.2 Exterior CMU Walls

Repair, patch or replace existing CMU that has more than a single hairline crack. All exposed surfaces, when painted, should appear in new condition. Remove old expansion joint material and replace it with new joint material. Provide a paintable penetrating waterproof sealant on all exterior CMU and mortar. Sealant shall comply with the following:

Water repellent solution shall be a clear, non-yellowing, deep-penetrating, VOC compliant solution. Material shall not stain or discolor and shall produce a mechanical and chemical interlocking bond with the substrate to the depth of the penetration. Provide one of the following:

• Silane, 20 Percent Solids or greater, Penetrating water repellent. A monomeric compound containing approximately 20 percent alkyltrialkoxysilanes with alcohol, mineral spirits, water, and other proprietary solvent carrier. Active alkylalkoxysilane content: ASTM D2369 20 percent by weight, plus or minus 1 percent. Average depth of penetration: Up to 3/8 inch depending on substrate. e. VOC content: Less than 350 grams per liter. f. Flash point, ASTM D3278.g. Specific gravity, at 25 degrees C 78 degrees F: 0.96 to 0.98.h. Density: .96 to .98 kilograms per liter .0 to 8.2 pounds per gallon. Water absorption test: ASTM C642 and ASTM E514/E514M. b. Moisture vapor transmission: ASTM D1653, 28.33 perms or 51.61 percent minimum compared to untreated surfaces. c. Scaling resistance: ASTM C672/C672M, non-air-entrained concrete, zero rating, no scaling, 100 cycles treated concrete. d. Resistance to chloride ion penetration: AASHTO T 259 and AASHTO T 260.e. Water penetration and leakage through masonry, ASTM E514/E514Mpercentage reduction of leakage: 97 percent minimum.f. Resistance to accelerated weathering, ASTM G154 testing 2,500 hours: No loss in repellency. g. Drying time under normal conditions: Four hours per 24 degrees C 75 degrees F

Page 25: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 25

• Siloxanes, Penetrating water repellent. Alkylalkoxysiloxanes that are oligomerous with alcohol, ethanol, mineral spirits, or water. a. Solids by weight: ASTM D2369, 7.5 to 16.0 percent. b. Volatile Organic Content (VOC) after blending: Less than 175 grams per liter. c. Density, activated: One kilogram per liter 8.4 pounds per gallon, plus or minus one percent. d. Flash point, ASTM D3278: Greater than 100 degrees C 212 degrees F. Dry time for recoat, if necessary: One to two hours depending on weather conditions. e. Penetration: 3/8 inch, depending on substrate. f. Water penetration and leakage through masonry, ASTM E514/E514M, percentage reduction of leakage: 97.0 percent minimum. g. Moisture vapor transmission, ASTM E96/E96M: 47.5 perms or 82 percent minimum compared to untreated sample. h. Resistance to accelerated weathering, ASTM G154. Testing 2,500 hours: No loss in repellency. i. Resistance to chloride ion penetration, AASHTO T 259 and AASHTO T 260. j. Scaling resistance, ASTM C672/C672M, non-air-entrained concrete: Zero rating, no scaling, 100 cycles treated concrete.

. Paint all CMU to match exterior colors at existing TEMF building 3802.

4.4.3 Exterior Doors and Frames

4.4.3.1 Exterior Doors

Exterior doors: Install new insulated, minimum Level 3, physical performance Level A, Model 2 flush metal doors on metal frames. Frames shall be 12-gauge, with continuously welded mitered corners and seamless face joints. Doors and frames shall be constructed of hot-dipped zinc-iron alloy-coated steel sheet, complying with ASTM A653, Commercial Steel, Type B, minimum A40 coating weight; factory primed. Fire-rated openings shall comply with applicable codes, and the requirements of the labeling authority. The door and frame installation shall comply with applicable codes and criteria.

4.4.4 Windows

Replace windows as indicated in the Appendix B drawings. Seal all existing windows to ensure a weathertight building. Provide any necessary trim, flashings, air/vapor barriers, sills, stools, rain drip or other accessories for a complete installation. Remove manual operation hardware on clerestory windows. Install new anodized aluminum windows conforming to AA-DAF-45 and AAMA 611, Architectural Class II, designation AA-M10-C22 color anodized with double pane, low solar emission glazing. The windows shall meet the requirements of UFC 4-010-01. Minimum ¼ inch tempered exterior pane ¼” laminated interior pane with increased glazing bite.

Page 26: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 26

Frame construction must be factory-assembled and factory sealed inner and outer aluminum completely separated from metal-to-metal contact. Join assembly by a continuous, concealed, low conductance divider housed in an interlocking extrusion of the inner frame. Metal fasteners, straps, or anchors will not bridge the connection between the inner and outer frame. Window units shall comply with the U.S. Department of Energy, Energy Star Window Program for the Southern Climate Zone. The condensation Resistance Factor shall be 60 for window and 71 for frame per AAMA 1503-98 Thermal Performance Test. Each window unit must bear the AAMA Label warranting that the product complies with AAMA/WDMA/CSA101/I.S.2/A440. Window glazing shall be tinted. Framing color shall be Dark Bronze.

4.4.5 Stairs

The existing interior stairs shall be reviewed for compliance with the existing building occupancy chapters of NFPA 101. The condition of the existing railings shall be inspected and either repaired or replaced. All treads shall meet the code requirements for non-slip surfaces. Provide new non-slip rubber stair treads Replace or repair all hand railings and stair guard railings.

4.4.6 Roofs

Prepare all surfaces to receive new roof. Install new contractor designed Standing Seam Metal Roofing System (SSMRS) over the entire building including a new 2’-0” minimum building eave on all sides. The SSMRS shall comply with UFC 3-600-01 for applicable fire rating. The SSMRS shall be a UL 580 Class 90 system, and shall meet all components and cladding wind resistance requirements defined in IBC-2018, and adopted in the UFCs. Trapezoidal seam profiles are not acceptable. The SSMRS shall be insulated in accordance with the requirements in the Mechanical section. Provide snow & ice shield underlayment compatible with SSMRS. The new roof system shall be designed to provide a minimum 2’-0” overhang around the entire building. The existing roof framing system shall also be retrofitted as required to support the new overhangs. The new roof assembly shall be integrated with the rest of the building to form a continuous envelope where applicable. overhangs. Designer shall ensure the building envelope is completely sealed to preclude passage of air & moisture into conditioned areas. All roof penetrations and connections in conditioned spaces shall be sealed to external environmental influences. The Contractor shall design and install new exterior gutters and downspouts for the new SSMRS to be connected to existing underground sewer system. Roof color shall match the color used at TEMF building 3802. See Fort Polk Standard Color Schedule at the end of this section. Gutters and downspouts shall match roof color. Roof finish shall have a minimum Solar Reflectance Index (SRI) of 39. The complete SSMRS assembly shall have a minimum 20-year no dollar limit (NDL) warranty.

Page 27: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 27

4.5 Interior Design

General: Provide sustainable materials and furnishings that are durable, mold-resistant, easily maintained and replaceable. Provide interior surfaces that are easy to clean and light in color.

4.5.1 Signage

At each area, provide one room number and changeable two-line message strip signage. Changeable message strip signs shall be of the same construction as standard room signs to include a clear sleeve that will accept a paper or plastic insert with identifying changeable text. The insert shall be prepared typeset message photographically enlarged to size and mounted on paper card stock.

Ensure room signage meets the Fort Polk standard. TM 5-807-10, JRTC Fort Polk Regulation 420-11 and UFC 3-120-01.

At all mechanical room doors, self-laminated vinyl signage, approximately 8 ½ inches by 11 inches, shall be provided, stating “No Asbestos Containing Insulation in This Building, (Date of Transfer).” Provide permanent signage(laser engraved, exterior rated) with detailed operating instructions for all fans, HVAC, exhaust, emergency stop, POL, and other installed equipment. Signage wording is to be approved by DPW before purchase and installation. Average sign size 9 inches by 12 inches. Provide one sign for each POL fluid, and one for each piece of equipment or control location

4.5.2 Bulletin Boards

Provide one bulletin board centrally located on the first floor of each Service Area. Bulletin board shall be 4’-0” high and 6’-0” wide. Bulletin boards shall have a header panel and shall have lockable, glazed doors.

4.5.3 Corner Guards

Provide surface mounted, high impact resistant, integral color, snap-on type resilient corner guards, extending from floor to ceiling for drywall partitions and column outside corners. Factory fabricated end closure caps shall be furnished for top and bottom of surface-mounted corner guards.

4.5.4 Casework

Provide cabinets complying with Architectural Woodwork Institute Quality

Page 28: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 28

Standards. Countertops shall have waterfall front edge and coved backsplash. Bathroom vanity countertop shall be minimum 3/4 inch thick solid surfacing material with waterfall front edge and coved backsplash.

4.5.5 Interior Doors and Frames:

(a) Hollow Metal Doors: Provide Hollow Metal doors and frames. Comply with applicable codes and criteria. Doors shall be minimum Level 2, physical performance Level B, Model 2; factory-primed.

(b) Hollow Steel Frames: Comply with ANSI A250.8/SDI 100. Frames shall be minimum Level 2, 16 gauge, with continuously welded mitered corners and seamless face joints; factory-primed.

(c) Fire-rated and Smoke Control Doors and Frames: Comply with applicable codes, criteria and requirements of labeling authority.

(d) STC ratings shall be of the sound classification required and shall include the entire door and frame assembly.

4.5.6 Window Treatment

Provide heavy-duty aluminum mini blinds with prefinished metal housings at all exterior windows. Uniformity of window covering color and material shall be maintained to the maximum extent possible throughout each building. Window stools shall be minimum ½ inch thick cast 100% acrylic polymer solid surfacing material. Uniformity of window covering color and material shall be maintained throughout each building.

4.5.7 Mold Mitigation

The Contractor shall provide details in the design analysis and design showing steps taken to eliminate mold growth in the facility. Where mold-resistant products are available, they shall be provided to the maximum extent possible.

4.5.8 Toilet Accessories

Furnish and install the items shown on drawings and all other toilet accessories necessary for a complete and usable facility. All toilet accessories shall be Type 304 stainless steel with satin finish unless specified otherwise.

4.6 Finishes

4.6.1 Paint

(a) All paints used shall be listed on the "Approved product list" of the

Page 29: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 29

Master Painters Institute (MPI). Application criteria shall be as recommended by Master Painters Institute (MPI) guide specifications for the substrate to be painted and the environmental conditions existing at the project site.

(b) Exterior surfaces, except factory pre-finished material or exterior surfaces receiving other finishes shall be painted a minimum of one prime coat and two finish coats. Paints having a lead content over 0.06 percent by weight of nonvolatile content are unacceptable. Paints containing zinc- chromate, strontium-chromate, mercury or mercury compounds, confirmed or suspected human carcinogens shall not be used on this project. Exterior paints and coating products shall be classified as containing low volatile organic compounds (VOCs) in accordance with MPI criteria. Application criteria shall be as recommended by MPI guide specifications. Provide an MPI Gloss Level 5 Finish (Semi-gloss), unless otherwise specified.

(c) Interior surfaces, except factory pre-finished material or interior

surfaces receiving other finishes shall be painted a minimum of one prime coat and two finish coats. Paints having a lead content over 0.06 percent by weight of nonvolatile content are unacceptable. Paints containing zinc- chromate, strontium-chromate, mercury or mercury compounds, confirmed or suspected human carcinogens shall not be used on this project. Interior paints and coating products shall contain a maximum level of 150 g/l (grams per liter) of volatile organic compounds (VOCs) for non-flat coatings and 50 g/l of VOCs for flat coatings. Provide an MPI Gloss Level 5 Finish (Semi-gloss) with a minimum perm rating of 10, such as Sherwin Williams ProMar 200 Zero VOC S/G or similar, in all areas.

4.6.2 Minimum Interior

(a) Provide higher quality finishes.

(b) Wall, ceiling and floor finishes shall conform to the requirements of the UFC 1-200-01, IBC, NFPA and UFC 3-600-01.

(c) When installing ceramic, porcelain or quarry tile on floors or walls, use a narrow grout line technique. Grout color selected shall not be light or white. Tile size shall be a minimum of 8” x 8”.

(d) Floors: carpet shall not be used as a floor finish on this project. Resilient flooring shall be manufacturer’s standard size tile and suitable for an industrial setting. Tiles shall be high performance, commercial-grade, abrasion-resistant, slip and stain resistant, durable, recyclable flooring (either made from recycled materials or able to be recycled), low maintenance, and shall not require polishing/waxing. Floor tiles may be homogeneous or heterogeneous and shall be a minimum 1/8 inch thick. Provide static dissipative tile in Comm rooms or enclosures.

Page 30: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 30

(e) See Fort Polk standard color schedule, which is attached to this section.

(f) Walls: For drywall partitions use impact resistant gypsum board in public heavy use areas such as corridors, staging areas and storage rooms. All gypsum board shall achieve a score of 10, the highest level of performance for mold resistance under the ASTM D 3273 test method and shall be transported, handled, stored and installed in accordance with the GYPSUM ASSOCIATION – “Guidelines for Prevention of Mold Growth on Gypsum Board (GA-238-03)." (g) Toilet partitions to be Class A flame spread, High Density Polyethylene (HDPE) with full height stainless steel hinges and all stainless steel hardware.

4.6.3 Overhead Coiling Doors

(a) Following conditioning survey and testing of all doors, replace in their entirety the doors noted on the drawings.

(b) Repair and motorize all roll-up doors.

(c) Install new pull cord overrides on all bay doors. Install ½” whip braid rope.

(d) Replace all existing electric switches for all doors.

4.6.4 Existing Bridge Cranes (a) Test and provide annual maintenance for cranes. Currently, the cranes are reported to be fully functional, verify at the start of construction, and at the end of construction. Verify load-bearing test for the crane.

(b) Test and install safety limits to avoid collisions with obstacles.

4.6.5 Insulation

(a) Roof insulation shall have a minimum value of R10 plus R-19 Filled Cavity.

(b) Wall insulation shall have a minimum of R-10 continuous insulation. If R-13 batt insulation is used, provide an additional R-5 continuous insulation.

(c) Insulation around new piping shall be new. All piping should be new, and no existing pipe insulation should remain.

(d) All new construction on administration rooms shall have R11 insulation installed.

(e) Depending on HVAC/energy efficiencies, higher values may be required to meet energy performance requirements.

Part 5 Mechanical Engineering 5.1 TEMF Renovation

Page 31: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 31

Mechanical design requirements

5.1.1 Demolition

(a) Recycle all demolished materials in accordance with the base recycling standards. Sheetmetal ductwork, metal piping, and air compressors (if removed) are included in the items required to be recycled. Deliver recycled materials to the base recycling station.

(b) Remove all of the HVAC systems (equipment, ductwork, piping, exhaust, abandoned equipment, equipment supports, thermostats, control wiring, etc…) in their entirety except for the underground portions of the vehicle exhaust ductwork

(c) Abandon the underground ductwork for the vehicle exhaust systems in place. Remove floor boxes for the exhaust hoses and grind the floor level with the surrounding floor area. Provide a concrete or welded cap that is flush with the floor at the floor box.

(d) Remove all plumbing fixtures.

(e) Remove all of plumbing domestic water systems, including the water heater, except for the underground piping and piping concealed in walls that are not being removed. The domestic water backflow preventer and the upstream water piping can remain in place. Provide caps that are flush with the floor/wall for the abandoned underground and concealed piping.

(f) Remove all of the above-ground sanitary waste and vent piping. Inspect the condition of the underground sanitary piping and report the condition to the Army Corps of Engineers. Replace floor drain grates and cleanout covers where floors are being refinished.

(g) Remove all of the above ground natural gas piping back to the gas service meter/regulator.

(h) Remove all compressed air piping back to the air compressor. The air compressor shall not be removed. Piping concealed in walls can remain.

(i) Abandon the underground waste oil collection system piping in the bays. Remove floor collection stations and grind the floor level with the surrounding floor area. Provide concrete or welded caps that are flush with the floor at the collection station.

5.1.2 Heating Ventilation Requirements

(a) Provide an HVAC system to serve rooms 103, 104, 107, 108, 109, 111, 130, 132, and 133. Outside air intakes shall be a minimum of 10 feet above grade. Include natural gas heating. All duct systems shall be galvanized sheetmetal. All interior ducts shall have exterior ductwrap insulation. All exterior ductwork shall have rigid insulation and

Page 32: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 32

an aluminum jacket (0.016” minimum). All exposed interior ductwork (including ductwork installed on mezzanines) shall have a 6 oz. canvas jacket with fire retardant lagging. No equipment will be permitted to be installed on the roof. Equipment must be ground mounted or installed in the Mechanical room. Humidity control options such as hot gas reheat and/or variable speed compressors and fans shall be used where available.

(b) Provide an HVAC system to serve rooms 200, 201, 201, 205, 205A,206, 207, 208, 209, and 211. Outside air intakes shall be a minimum of10 feet above grade. Include natural gas heating. All duct systems shallbe galvanized sheetmetal. All interior ducts shall have exterior ductwrapinsulation. All exterior ductwork shall have rigid insulation and analuminum jacket (0.016” minimum). All exposed interior ductwork(including ductwork installed on mezzanines) shall have a 6 oz. canvasjacket with fire retardant lagging. No equipment will be permitted to beinstalled on the roof. Equipment must be ground-mounted or installed inthe Mechanical room. Humidity control options such as hot gas reheatand/or variable speed compressors and fans shall be used whereavailable.

(c) Provide an HVAC system to serve rooms 117, 118, 124, 125, 212,213, 215, and 216. Outside air intakes shall be a minimum of 10 feetabove grade. Include natural gas heating. All duct systems shall begalvanized sheetmetal. All interior ducts shall have exterior ductwrapinsulation. All exterior ductwork shall have rigid insulation and analuminum jacket (0.016” minimum). All exposed interior ductwork(including ductwork installed on mezzanines) shall have a 6 oz. canvasjacket with fire retardant lagging. No equipment will be permitted to beinstalled on the roof. Equipment must be ground-mounted or installedabove the mezzanine. Humidity control options such as hot gas reheatand/or variable speed compressors and fans shall be used whereavailable.

(d) Each space shall be supplied with outside air in quantities meetingASHRAE 62-1, (AM-0004)> 2007 2016 Standard for Indoor Air Quality.If the outside air quantities are large enough to require a Dedicated Outside Air System (DOAS), the DOAS system shall comply with Ft. Polk dehumidification requirements of 48F maximum supply air dew point temperature. <(AM-0004)

(e) Provide continuous ventilation and exhaust in the Bays a rate of 1.5 cfm /sf. The continuous ventilation system(s) shall include a gas-fired make-up air handling unit(s) and sheetmetal distribution ductwork. The maximum temperature shall be ambient + 10 deg F in the summer(provide rooftop exhaust fans controlled by manual switches if required). The minimum space temperature shall be 55 deg F in the winter and shall be maintained by the continuous ventilation system without the assistance of radiant heaters. Provide gas-fired radiant heaters, 60,000 Btu/hr min, at each column adjacent to the Bay overhead doors (Min. Qty = 12) in bays that have a crane. Provide gas-fired radiant heaters,

Page 33: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 33

90,000 Btu/hr min, suspended from the roof in bays that do not have a crane (Min Qty = 22). Locate ceiling radiant heaters above work spaces (not above vehicle spaces). Each radiant heater shall be provided with a manual timer switch.

(f) Latrines and janitor’s closets shall be exhausted per code. Industrialstyle diffusers, registers, grilles, and exhaust fans with integral grilles shallbe used in the latrines.

(g) Condition the latrines with using the Office HVAC system. The supplyair volume shall be approximately equal to the exhaust air volume.Provide supplemental electric heaters.

(h) Utility Spaces shall be heated by gas unit heaters and ventilated bywall mounted, 2-speed fan/damper system for summer ventilation.

(i) The P.O.L. room shall be heated by electric unit heaters.

(j) Provide new vehicle exhaust systems with one fan per hose reel.(Min. Qty = 9). Locate adjacent to P.O.L. distribution stations. (AM-0004)>Comply with UFC 4-214-02. <(AM-0004)

(k) Provide dedicated exhaust systems for the battery charging areas. Thissystem shall run continuously. (AM-0004)> THE DOR shall determine the battery charging exhaust requirements during design and shall comply with UFC 3-520-05. For bidding, anticipate that there will be 10 lead acid batteries charging at one time (example battery = Hawker model HASP-FT) <(AM-0004)(l) Provide a dedicated exhaust system for the P.O.L. room. This system shall run continuously.

(m)Provide a mobile welding exhaust unit with carbon filtration andarticulating arm.

(n) Provide emergency shutdown button for all air moving equipment.Each button shall shut down all air moving equipment. The button must beseparate from panels with other buttons. Provide a non-lockable cover forbutton. Location of the button shall be determined during final detaileddesign.

(o) Provide JACE 8000 Vykon Niagra N4.3 (or latest) controller and serverplatform for connecting individual HVAC devices and systems. The JACEshall have licenses for all of the points and shall be provided with astandard warranty. Graphics shall be built at the JACE using Niagrastandard graphics. Tie the JACE to the base network fiber switch. Powerfor the JACE shall be hardwired (no cords or plugs). No UPS is requiredfor the JACE. Provide a complete list of control points for the system. At aminimum, include occupancy schedules, space and/or return airtemperature and humidity in each system, on/off status, and alarms.Honeywell Spyders with individual licenses shall be used for individuallycontrolled devices.

5.1.3 Petrroleum, Oil, and Lubrication (P.O.L.) distribution system

Page 34: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 34

(a) Install a new P.O.L distribution system for Bays. This includes allpiping, pumps, regulators, gages, etc… and hose reel connections andthe inspection pit. Hose reels include compressed air, anti-freeze, 10W oil,80W90 gear oil, Dexron/ATF, and grease. All POL tanks and storage shallbe in a dedicated fluid distribution room. Provide containment systemcapable of holding 55 gallon drums for each fluid.

(b) Provide a minimum of 9 distribution stations. Coordinate location ofdistribution stations so they do not interfere with the operation of theoverhead crane(s).

(c) Distribution points shall have containment systems.

5.1.4 Plumbing requirements

(a) Provide new low-flow water-efficient plumbing fixtures including dualflush water closets, low-flow urinals with manual flush valves, lavatoriesand sinks with low flow faucets, and 2.0 gpm stainless steel janitor’s closetsinks as shown on the architectural plans.

(b) On each maintenance bay interior wall, include one hose bibb and oneeyewash/safety shower (even if these are not shown on the architecturalplans). Provide a minimum of one frost proof wall hydrants on eachexterior wall. Provide one hose bibb in each latrine.

(c) Eyewash/safety showers shall be supplied with tempered water. Theeyewash/safety shower shall include an ASSE 1070 compliantthermostatic mixing valve. Instantaneous electric water heaters may beused to avoid the cost of long runs of hot water and hot water return piping.

(d) Provide new natural gas-fired water heater.

(e) Provide copper domestic hot water and hot water return piping systemswith a return pump. Insulate all piping and accessories.

(f) Provide new domestic copper cold water piping system. Insulate allpiping and accessories.

(g) Provide three new water coolers with integral bottle fillers.

(h) Provide new above ground cast-iron sanitary waste and vent piping.Connect to existing underground piping.

(i) Provide new natural gas piping system including all regulators requiredfor the connected appliances/equipment.

(j) Provide new natural gas usage monitor. Tie new monitor into baseutility monitoring system. Monitor shall be approved by Ft. Polk (ElsterAC630 Diaphram or Elster Raby Rotor Meters as required by the availablegas pressure).

(k) Provide new compressed air piping system and new refrigerated airdryer. Provide a minimum of two compressed air outlet per service bay.(AM-0004)> (10 scfm per outlet at 160 psig). <(AM-0004)

Page 35: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 35

5.1.5 Survey Existing Buildings

The contractor shall perform a thorough survey of the building to determine conditions and actual dimensions and capacities.

5.1.6 Develop Design Documents

Details of work proposed and equipment data shall be submitted for review and Government acceptance.

5.1.7 Construct

Construct in accordance with UFC criteria and industry-accepted design standards

5.1.8 Design Conditions

Outside Design Temperatures:

Summer (Equipment shall be sized for both conditions): a. 94.7F DB, 75.7F WB andb. 141 HR, 82F DB

Winter: 30.5F DB

Inside Design Temperatures: Mechanical Rooms

Summer: Maximum 10F> than outside ambient temperature. Winter: 55F DB

Office areas Summer: 78F DB, 50% RH Winter: 68F DB.

Occupant Densities Office/Admin: Use ASHRAE 62.1 Conference/Meeting: 20 people/room

5.1.9 Mechanical Calculation Requirements

Must meet all calculation requirements of section 01 33 16 as well as the following: a) Mechanical systems shall be selected based upon a Life Cycle Cost

Analysis performed by the contractor.

b) Mechanical calculations for outside air intake and exhaust systemsand HVAC calculations for balancing all HVAC systems includingsupply and exhaust to administration areas and bathrooms.

c) All plumbing calculations including water heater tank and HW pipe sizing.

5.2 Commissioning

<(AM-0004)

(AM-0004)>

Page 36: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

5.2.1 TESTING, ADJUSTING AND BALANCING.

Test and balance air using a firm certified for testing and balancing by the Associated Air Balance Council (AABC), National Environmental Balancing Bureau (NEBB), or the Testing Adjusting, and Balancing Bureau (TABB). Perform TAB in accordance with the requirements of the standard under which the TAB Firm's qualifications are approved, i.e., AABC MN-1, NEBB TABES, or SMACNA HVACTAB unless otherwise specified herein. All recommendations and suggested practices contained in the TAB Standard shall be considered mandatory. Use the provisions of the TAB Standard, including checklists, report forms, etc., as nearly as practicable to satisfy the Contract requirements. Use the TAB Standard for all aspects of TAB, including qualifications for the TAB Firm and Specialist and calibration of TAB instruments. Where the instrument manufacturer calibration recommendations are more stringent than those listed in the TAB Standard, adhere to the manufacturer's recommendations. All quality assurance provisions of the TAB Standard such as performance guarantees shall be part of this contract. For systems or system components not covered in the TAB Standard, the TAB Specialist shall develop TAB procedures. Where new procedures, requirements, etc., applicable to the Contract requirements have been published or adopted by the body responsible for the TAB Standard used (AABC, NEBB, or TABB), the requirements and recommendations contained in these procedures and requirements are mandatory.

COMMISSIONING: Commission all HVAC systems and equipment, including controls, and all systems requiring commissioning, in accordance with ASHRAE 189.1. The Contracting Officer’s Representative will act as the Owner’s representative in performance of duties spelled out under OWNER in Annex A2 of ASHRAE 189.1. Compliance with 019100.5 - Total Building Commissiong in the RFP is also required. The intent is to provide limited commissioning to assure the proper installation and startup of the HVAC systems.

5.2.2 ENERGY CONSERVATION

AM-0004)> LEED silver design criteria will be required. No LEEDCertification or Registration is required. Silver Certification will be required. Energy model reports, using commercially available modeling software such as Trane TRACE, shall be submitted demonstrating that the renovated building will be 5% more energy efficient than a Baseline Building according to ASHRAE 90.1-2010. Energy performance calculations shall be performed in compliance with Appendix G of ASHRAE 90.1-2010. Energy input and output reports must be presented in a format equivalent to LEED Credit EAp2. <(AM-0004)

All new mechanical equipment is required to comply with the minimum requirements of ASHRAE 90.1-2010.

Bldg 3003 Section 01 10 00.01 Page 36

(AM-0004)>

<(AM-0004)

Page 37: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 37

The contractor shall purchase Energy Star or FEMP designated products. The term “Energy Star product” means a product that is rated for energy efficiency under an Energy Star program. The term “FEMP designated product” means a product that is designated under the Federal Energy Management Program of the Department of Energy as being among the highest 25 percent of equivalent products for energy efficiency. When selecting integral sized electric motors, choose NEMA PREMIUM type motors that conform to NEMA MG 1, minimum Class F insulation system. Motors with efficiencies lower than the NEMA PREMIUM standard may only be used in unique applications that require a high constant torque speed ratio (e.g., inverter duty or vector duty type motors that conform to NEMA MG 1, Part 30 or Part 31). All motors shall have a minimum 1.15 service factor.

Part 6 Electrical Engineering

6.1 Demolition

6.1.1 Recycle all demolished materials in accordance with the base recycling standards. Raceways, conduit, conductors, etc. Deliver recycled materials to the base recycling station.

6.1.2 Dispose of all existing light fixtures to be removed.

6.2 Lighting

6.2.1 General • New light fixtures shall be LED, UL Listed and Buy American Act

compliant to include components of light fixtures.

• Lighting design and lighting controls shall comply with therecommendations of the latest UFC 3-530-01 Interior and ExteriorLighting Systems and Controls, the Illuminating Engineering Society ofNorth America (IESNA) and the requirements of ASHRAE 90.1.

• Products must have been in satisfactory commercial or industrial usefor two years prior to bid opening. The two-year period must includeapplications of equipment and materials under similar circumstancesand of similar size. The product must have been on sale on thecommercial market through advertisements, manufacturers' catalogs,or brochures during the two-year period. Where two or more items ofthe same class of equipment are required, these items must beproducts of a single manufacturer; however, the component parts ofthe item need not be the products of the same manufacturer unlessstated in this section.

• Provide with UL damp label and UL wet label, as required.

• Refer to Appendix B for floor plans and Appendix E for existing lightingplan.

Page 38: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 38

• Provide normal and emergency lighting studies for each room andwork area in footcandles on 2’ by 2’ grid.

• Provide normal and emergency lighting studies for exterior infootcandles on 5’ by 5’ grid.

6.2.2 All Light Fixtures shall meet the following characteristics: • Minimum Luminaire Efficiency: 90 Lumens per Watt delivered

• Operating Temperature: -40 degrees F to +140 degrees F

• Harmonics: Comply with IEC 6100-3-2

• THD: less than 10%

• Power Factor: greater than 0.9 (100-277VAC)

• Color Rendering Index (CRI): Minimum of 80 (90CRI for Downlights)

• Correlated Color Temperature (CCT): 4000K (Cool White)

• Luminaires must have a minimum 5-year manufacturer's warranty.

• Luminaires must have a minimum L70 lumen maintenance value of50,000 hours as calculated by IES TM-21, with data obtained per IESLM-80 requirements.

• Luminaires must be tested to IES LM-79 and IES LM-80 standards.

• Luminaires must be listed with the DesignLights Consortium 'QualifiedProducts List' when falling into category of "General Application"luminaires, i.e. Interior Directional, Display Case, Troffer, LinearAmbient, or Low/High Bay. Requirements are shown in theDesignlights Consortium "Technical Requirements Table" athttps://data.energystar.gov/dataset/EPA-Recognized-Laboratories-ForLighting-Products/jgwf-7qrr.

• Provide Department of Energy 'Lighting Facts' label for each luminaire.

• Complete luminaires shall be in accordance with NFPA 70, NEMA, andUL listed and labeled.

• LED drivers to be field replaceable and shall be serviceable while thefixture is in its normally installed position, and shall not be mounted toremovable reflectors or wireway covers.

• Luminaires shall be entirely factory wired by the luminairemanufacturer in accordance with UL requirements and shall befurnished fully compatible with the project electrical wiring and controlssystem for smooth, continuous, dimming or on/off flicker-free operation.

• Service Bay light fixtures shall be UL classified for damp locations.

• Exterior building mounted light fixtures shall be UL classified for wetlocations.

6.2.3 All existing interior light fixtures and their associate lighting controls shall be removed and replaced with new.

Page 39: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 39

• Maintained illumination levels for interior spaces shall be in accordancewith Table 6.1.1 in footcandles (+/- 5% maintained).

• Maintained illumination levels in areas not included in the Table 6.1.1shall comply with recommendations of the latest UFC 3-530-01 Interiorand Exterior Lighting Systems and Controls, the latest IESNAHandbook and all of the latest IESNA Recommended Practices (RP).

• Office, Supply Rooms, Training Room and Conference Room Lighting:Interior ambient illumination shall provide a generally glare free, highquality lighting environment conforming to IESNA RP-1-04. Multi-purpose rooms, training rooms and conference rooms shall have adimmable LED lighting. Dimming ballasts shall be capable of dimmingto 1 percent.

• Illumination levels in maintenance pits shall be calculated based on nocontribution from the overhead ambient light fixtures.

• The fixture layout shall be coordinated with the traveling bridge cranerequirements.

• Provide occupancy sensors in accordance with UFC 3-530-01, 01 April2015, change 3, 01 June 2016 and ASHRAE 90.1 – 2016. ProvideLED lights with integral occupancy/daylight sensors where possible.

• Provide manufacturer’s computerized horizontal illumination levelsusing AGI32 or ElumTools (AM-0002)> Visual Lighting or DIALux<(AM-0002) software in footcandles at workplane (30" above finishedfloor), taken every two (2) feet in every interior room and area. Includeaverage maintained footcandle levels and maximum and minimumratio. Provide reports for normal lighting and emergency lighting tocomply with requirements.

Table 6.1.1: New Lighting and Lighting Control Chart

SPACE TYPE

Targ

et

Illu

min

ati

on

Level

(FC

)

Overr

ide w

all

co

ntr

oll

er

(sw

itch

)

Du

al

Tech

Occu

pan

cy

sen

so

r

Ph

oto

sen

so

r /

Dayli

gh

t

harv

esti

ng

(d

imm

ing

)

Man

ual

wa

ll s

wit

ch

Administration 30 X X X

Shop Control 50 X X X

Warehouse, Storage, and

Miscellaneous Rooms

20 X X X

Latrines, Showers and

Lockers

20 X X

Break, Training, 30 X X X

Page 40: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 40

and Conference

Repair and Maintenance

Areas

50 X X X

Weapons Storage and

COMSEC Vaults

50 X

Maintenance Pit 15 X X

Repair Shops (General Item, Compact Item,

Special Environment, Battery, etc)

50 X X X

Mechanical

Room

20 X

6.2.4 All existing exterior site and building mounted lighting fixtures, poles and

their associate lighting controls shall be removed and replaced with new.

Replace all poles and pole mounted fixtures with LED fixtures.

• Maintained illumination levels shall comply with recommendations ofthe latest IESNA Handbook and all of the latest IESNA RecommendedPractices (RP).

• Exterior site lighting shall be controlled by a photocell and astronomicaltime clock. Site lighting shall have separate lighting controls from thebuilding mounted lighting for independent scheduling. Exterior lightingbranch circuits shall be routed through mechanically held contactors.Provide two separate contactor cabinets. One for site lighting and onefor building mounted lighting. Provide with Hands-Off-Auto switches formaintenance.

• Illumination levels shall be 5 foot-candles within 10 feet of the baydoors for repair areas, maintenance areas and the canopies for AS-LMS, SATS and vans. Illumination levels shall be no less than 0.5foot-candles for parking areas.

• Replace existing. Concrete light pole bases to remain.

• Provide manufacturer’s computerized horizontal and verticalillumination levels using AGI32 or ElumTools AM-0003)> VisualLighting or DIALux <(AM-0003) software in footcandles, taken everyfive (5) feet at grade for the entire exterior site. Include averagemaintained footcandle levels and maximum and minimum ratio.Provide reports for normal and emergency to comply withrequirements.

6.2.5 All existing exit and battery backed-up emergency light fixtures shall be removed and replaced with new. • New exit signs and battery backed-up emergency light fixtures shall be

LED.

(AM-0003)>

<(AM-0003)

(AM-0004)>

(AM-<(AM-0004)

Page 41: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 41

• Locate exit signs and battery backed-up emergency light fixtures perNFPA-101 Life-Safety Code and NFPA 70 National Electrical Code.

• Exterior, service bays and unconditioned area emergency lighting andexit signs to have integral battery heaters for cold weather.

• Equip Emergency Lighting Unit (ELU) and Exit Signs with brown-outsensitive circuit to activate battery when input voltage falls belownormal levels. Equip ELU’s with two LED, type light sources,automatic power failure device, test switch, and pilot light, and fullyautomatic high/low trickle charger in a self-contained power pack.Battery must be sealed, maintenance free type, and must operateunattended for a period of not less than five years. Emergency runtime must be a minimum of 1 1/2 hours. LEDs must have a minimumrated life of 10 years.

6.2.6 Replace all existing building branch circuiting with new.

6.2.7 CLIN OPTION: Completely replace all exterior lighting branch circuiting serving pole mounted light fixtures. Contractor may re-use existing conduits wherever possible.

6.3 Power

6.3.1 Provide interior electrical wiring, fixtures, switches, outlets, and apparatus in accordance with applicable codes and standards. The electrical system shall conform to NFPA 70, UFC 3-501-01 and UFC 3-520-01. Power and lighting circuits shall be separate. New and replacement materials and components shall, as a minimum, meet the applicable requirements of ANSI, NEMA and UL publications.

Main Panel Boards, Secondary service laterals, Building Panelboards, and Panelboard feeders shall be new and sized in accordance with new electrical load calculations.

6.3.2 Provide electrical connections to all HVAC, Plumbing and Fire Protection equipment and devices.

6.3.3 Wiring: All wiring shall be in electrical metal conduits and shall be concealed except in the service bays. No conductors shall be smaller than No. 12 AWG, copper wires. Solid conductors for No. 10 AWG and No. 12 AWG. Stranded conductors for No. 8 AWG and larger. Wiring underground shall be in Schedule 40 PVC. Exposed conduits on the exterior of the building are prohibited. Provide a ground conductor for

<(AM-0004)

(AM-0004)>

(AM-

Page 42: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 42

each circuit; conduits shall not be used for grounding. Use of cable assemblies Types AC, MC, or MI and flat conductors are prohibited. Circuit breakers shall be bolt-on type. Series rated circuit breakers and fusible panelboards shall not be used.

6.3.4 Outlet Circuits: Lighting and convenience outlets shall be on separate circuits. Install GFI protected receptacles at all wet or damp locations and all receptacles in the shop maintenance bay areas. Location of outlets shall be as required by applicable codes and standards. Provide extra outlets for maintenance and service staffs in spaces such as corridors, hallways and other public spaces. All exterior outlets shall be on separate circuits, weather resistant and shall be GFI protected, and equipped with a metal, in-use cover to prevent accidental water infiltration into the devices.

6.3.5 Provide new duplex 120-volt receptacles in all offices, restrooms, tool area, janitor, mechanical, electrical and communications rooms spaced approximately every eight feet along the wall(s). Provide a quad receptacle under the telecommunications wall board in the communications room.

6.3.6 Provide new duplex 120-volt duplex GFCI receptacles approximately every twelve feet along welding bay, service bay, maintenance bay and repair bay walls.

6.3.7 Provide one (1) digital energy meter and required CT’s (sized for service) at each facility. Shark 200 or equal. Located CT’s on incoming service lateral. Turn over existing digital meters to base (owner).

6.3.8 Power shall be provided for all installed equipment, roll-up doors, devices and panels requiring power. All existing manual roll-up doors shall be converted to electrical. Size per NEC and equipment nameplate.

6.3.9 Replace all existing 20-amp receptacles with new receptacles, unless otherwise noted.

6.3.10 Replace all existing 20-amp receptacles with new GFCI receptacles in latrines, maintenance area, repair areas, welding bays and service bays.

6.3.11 Replace all existing 120-volt exterior 20-amp receptacles with new weather resistant (WR), GFCI receptacles with new.

6.3.12 Provide a new GFCI duplex receptacle for existing latrines/restrooms currently without a duplex receptacle. For latrines/restrooms already with a duplex receptacle(s) that aren’t GFCI rated, a new GFCI duplex receptacle shall replace the existing one(s).

6.3.13 Provide over-voltage and surge protective devices (SPD/TVSS) at all new and existing panelboards. <(AM-0004)

(AM-0004)>

(AM-

Page 43: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 43

6.3.14 Provide one (1) new dedicated 20-amp, GFCI receptacle at each new vending machine location. Provide a minimum of 2 per building.

6.3.15 Exhaust in latrines to be controlled with the lighting motion sensor. Exhaust fans shall run for an additional 20 minutes after lights are turned off.

6.3.16 Exhaust in latrines to be controlled with the lighting motion sensor.

6.3.17 ASLMS Container

The ASLMS Container is provided with the following: • Provide the following power provisions for ASLMS container: two

dedicated 20 ampere, 120 volt, single phase circuits with a specialreceptacle for each circuit. MS part number for special receptacle tobe provided is MS3451W16-10S.

6.3.18 SATS Container

Provide the following power and data provisions for SATS container: • Provide a 100 amp, 208 volt, 3-phase, 4-wire feeder to a weatherproof

100 amp, 240 volt disconnect switch within the cable’s reach of theSATS.

• Provide a pre-manufacturer cable, stock number 5995-01-435-8697.The cable is 50 foot long with a plug for the SATS receptacle at oneend and terminal connections on the other end. Connect the cable’sterminal ends to the disconnect switch. Provide a means to hang thecable.

• Provide a weatherproof RJ 45 (phone) and RJ 45 (LAN) outlet with theconduit and cables (Category 6) to the Communication Room andconnect per I3A requirements. Provide 50 feet of exterior cable withappropriate connectors on each end for each outlet. Provide a meansto hang the cables.

6.3.19 Repair and Maintenance Bays • Provide one (1) 30A, 208V single-phase power receptacle in each

Repair and Maintenance Bay. Provide dedicated branch circuit back topanelboard from each receptacle.

• Provide one (1) 30A, 208V three-phase power receptacle in eachRepair and Maintenance Bay. Provide dedicated branch circuit back topanelboard from each receptacle.

• Provide one (1) 50A, 208V three-phase power receptacle in eachRepair and Maintenance Bay. Provide dedicated branch circuit back topanelboard from each receptacle.

• Provide two (2) new GFCI duplex receptacles in each Repair andMaintenance Bay. Each shall be on a dedicated 20 amp branch circuitback to panelboard.

• All 120 VAC power connections in the Repair and Maintenance Bays

Page 44: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 44

shall be GFCI protected.

6.3.20 Service Bays • Provide one (1) 30A, 208V single-phase power receptacle in each

Service Bay Provide dedicated branch circuit back to panelboard fromeach receptacle.

• Provide one (1) 30A, 208V three-phase power receptacle in eachService Bay Provide dedicated branch circuit back to panelboard fromeach receptacle.

• Provide one (1) 50A, 208V three-phase power receptacle in eachService Bay Provide dedicated branch circuit back to panelboard fromeach receptacle.

• Provide two (2) new GFCI duplex receptacles in each Service Bay.Each shall be on a dedicated 20-amp branch circuit back to panelboard.

• All 120 VAC power connections in the Service Bays shall be GFCIprotected.

6.3.21 Welding Bays • Provide one (1) 30A, 208V single-phase power receptacle in each

Welding Bay. Provide dedicated branch circuit back to panelboard from

each receptacle.

• Provide one (1) 30A, 208V three-phase power receptacle in each

Welding Bay. Provide dedicated branch circuit back to panelboard from

each receptacle.

• Provide one (1) 50A, 208V three-phase power receptacle in each

Welding Bay. Provide dedicated branch circuit back to panelboard from

each receptacle.

• Provide two (2) new GFCI duplex receptacles in each Welding Bay.

Each shall be on a dedicated 20-amp branch circuit back to panelboard.

• All 120 VAC power connections in the Welding Bays shall be GFCI

protected.

6.3.22 Voltage drop will be limited to 5% per UFC 3-501-01 requirements. Size service and feeder conductors for a maximum voltage drop of 2% at the circuit's rate capacity. Size branch circuits for a maximum voltage drop of 3% at the circuit's rated capacity.

6.3.23 Provide 20-amp, 120-VAC duplex receptacles within 25 feet of mechanical equipment on the interior and exterior of buildings. For exterior receptacles, provide ground fault (GFCI), weather resistant (WR) receptacles with die-cast metal, in-use covers

6.3.24 Replace all existing building branch circuiting with new.

6.3.25 Provide an arc flash study for the building electrical distribution system.

Conduct a hazard analysis/arc flash hazard analysis whenever work on or near

<(AM-0004)

(AM-0004)>

(AM-

Page 45: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 45

energized parts greater than 50 volts is necessary, in accordance with NFPA 70E. Provide clear direction that contractor is to perform this analysis and provide appropriate arc flash labeling and floor marked boundaries.

6.3.26 Demarcation of the building electrical service shall be at the secondary of the existing utility service transformer. Required electrical outages to be coordinated with the Privatized Utility Provider (PUP) and the Fort Polk DPW PUP COR, see Part 3 Civil in this section. Sufficient time shall be given to DPW, PUP COR and PUP for any required outages or rework of the electrical service.

6.4 Telecommunications

6.4.1 Main Distribution Frame (MDF) shall be located in Comm Rm 205A

6.4.2 Telecommunication cabling shall be Category 6 for all voice and data connections.

6.4.3 Provide one (1) new combination Telephone/Data outlet for each workstation location in all Offices, Administration and Shop Control areas. This will require multiple combination Telephone/Data outlets in rooms with multiple desks/workstations. Provide a minimum of 20 combination telephone/data outlets.

6.4.4 Provide one (1) new Voice outlet in each Training Room.

6.4.5 Provide a minimum of 31 Data outlets in each Training Room. Evenly space data drops around each training room. No more than 4 data outlets jacks/drops per faceplate.

6.4.6 Provide one (1) new Data outlet in each Service Bay

6.4.7 Provide one (1) new Data outlet at each Repair and Maintenance Bay workstation.

6.4.8 Provide one (1) new Data outlet at each new copier location.

6.4.9 Provide Data outlets for HVAC equipment or other equipment, as required. Provide a minimum of 3.

6.4.10 Provide one (1) new Data outlet at each vending machine location. Provide a minimum of 2 per building.

6.4.11 Provide a wall mounted Telephone outlet at the door near MDF.

6.4.12 Provide 4’x8’x3/4” fire rated plywood on wall at MDF.

6.5 Commissioning

6.5.1 Commission all electrical systems and equipment, including lighting controls, and all systems requiring commissioning, in accordance with

(AM-0004)>

(AM- <(AM-0004)

Page 46: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 46

ASHRAE 189.1. The Contracting Officer’s Representative will act as the Owner’s representative in performance of duties spelled out under OWNER in Annex A2 of ASHRAE 189.1. Compliance with 019100.5 - Total Building Commissioning in the RFP is also required. The intent is to provide limited commissioning to assure the proper installation and start-up of the lighting and lighting controls.

6.6 Lightning Protection

6.6.1 Provide a lighting protection system.

6.7 Grounding

6.7.1 A ground busbar shall be provided in each service bay. A grounding point shall be provided in each repair and maintenance area. Equipment grounding shall be in accordance with the recommendations of MIL-HNBK-419A. This includes, but is not limited to, the earth electrode subsystem should exhibit a resistance to earth of 10 ohms or less and multiple ground rods should be interconnected using 1/0 AWG bare copper cable. Ground busbar to be copper, minimum 1/4 inch thick by 4 inches wide with four (2) rows of 9/32-inch holes spaced 1-1/8 inches apart. Minimum length of 18”

6.7.2 Systems shall conform to NFPA 70 National Electrical Code, local codes UFC-520-01 and the Technical Criteria for Installation Information Infrastructure Architecture (I3A).

6.8 Fire Pump

6.8.1 Provide dedicated feeder from utility transformer to Fire Pump Controller per NEC and UFC. Provide all required work for an operational Fire Pump including final terminations to the fire pump.

Part 7 Structural Engineering

7.1 General Structural Requirements

The Contractor's Structural Designer-of-Record (D.O.R.) shall ensure that the repairs, modifications, rehabilitations, and new construction meet all applicable design codes and criteria, including UFC. The D.O.R. shall identify load-carrying components which will require strengthening and provide a design fix which is compatible with the materials used in the building. The building and all design loads shall be safely supported during demolition and construction. Also a consideration is the effect of new dead loads, introduced to reinforce weak components, shall not negatively affect the structural performance of any other parts of the building. The primary code used for structural design shall be the International Building Code (IBC-2018) and the codes referenced therein, except where modified by UFC criteria which shall take precedence.

(AM-0004)>

(AM-

<(AM-0004)

Page 47: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 47

For any new work and the loads associated with it, the D.O.R. shall also be responsible for strengthening of existing components to meet all applicable requirements for all other design loads as defined in IBC-2018, such as gravity dead and live loads, wind loads and seismic loads. The Structural D.O.R. is responsible for the specification and design of connections and fasteners to structural and exterior wall components. Also included is support for architectural features, mechanical, and electrical equipment.

7.1.1 Miscellaneous

All overhead Architectural, Mechanical, Electrical, Plumbing, and Fire- Protection equipment weighing 31 pounds or greater shall be supported per UFC 4-010-01 Standards 15 and 19.

The existing slab-on-grade is a conventional reinforce ribbed mat slab (RRMS). At any new slab penetrations, the RRMS shall meet the minimum requirements per CESWD-ED-TS/G Design Criteria for Ribbed Mat Foundations, SWDED-G Criteria Letter dated April 1987.

7.1.2 Overhead Door Jambs

It was found that some of the existing overhead door jambs have deterioration at the bottom from floor elevation to approximately 2 ft up. The contractor shall visually inspect and repair or replace the deteriorated overhead door jambs as directed by the Structural D.O.R.

7.1.3 Structural Building Components

The following represents some of the items found in the building however, it is the Contractors responsibility to review all structural components and determine what items need to be repaired or replaced.

It was found that many of the metal building columns, base plates, and anchor bolts were maintained with protective paint to minimize moisture deterioration. The 2 columns at grid M-10 and M-11 appear to have been previously repaired by having the bottom 2 feet of the metal building column, base plate, and anchor bolts replaced. The four end of building columns along grid 1, the four end of building columns along grid P, and the two columns along grid N were found to have deterioration that appear to be due to condensation along the wall. These columns do not have protective paint like the other columns. There is rod x-bracing that connects to the base of the deteriorated columns along grid 1 and along grid P.

The contractor shall complete a prebid visual survey to identify any additional areas requiring repair or replacement. The contractor shall repair or replace deteriorated components in the areas listed above and

Page 48: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 48

areas discovered during prebid visual investigations.

After award, the Contractor shall continue to visually inspect all building components (column bases, anchor bolts, purlins, etc) and propose repair or replacement of any deteriorated or modified components as directed by the Structural D.O.R. Inspection shall continue throughout the construction period.

7.1.4 Structural Rod X-Bracing

It was found that some of the structural rod x-bracing for the walls and roofs are sagging and need tensioning. The Contractor shall tension the rod x-bracing as directed by the Structural D.O.R.

7.2 Roofs

The existing roof consists of metal panel system over blanket insulation attached to light gauge purlins. The Contractor is to attach a new structural standing seam roof to the existing purlins if an engineer has found the existing structure to be suitable and compatible to carry the required loads and configuration of the new roof. The new roof system shall include extending the eaves to provide overhangs around the building. The new roof framing design shall include this new geometry and loads. Refer to the Architectural section for the description of the required work for the roof.

The new roof system shall be designed based on the uplift loads for Fort Polk and also for any anticipated mechanical loads that may be placed on it. Follow the load requirements from the IBC-2018 for the design of the new roof framing system, also the design shall comply with a UL 580 class 90 listed assembly.

7.3 Cranes

The existing cranes consist of a 7.5-ton bridge crane and a 3-ton Jib crane. The Contractor shall inspect, report any required repair to the COR, provide annual maintenance, lubricate, load test, and certify. The bridge cranes are currently operational and certified, verify at the start of construction and the end of construction.

Part 8 Fire Protection Engineering

8.1 General Fire Protection and Life Safety Requirements

Standards and Codes. All fire protection and life safety features shall be in accordance with UFC 3-600-01 and the criteria referenced therein. Tactical Equipment Maintenance Facilities (TEMF) shall be classified as mission essential and shall be provided with complete sprinkler protection.

Page 49: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 49

8.1.1 Fire Protection and Life Safety Design Analysis:

A fire protection and life safety design analysis shall be provided for the project. The analysis shall be submitted with the Interim design submittal. The analysis shall include classification of occupancy (both per the IBC and NFPA 101); type of construction; height and area limitations (include calculations for allowable area increases); life safety provisions (exit travel distances, common path distances, dead end distances, exit unit width required and provided); building separation or exposure protection; specific compliance with NFPA codes and the IBC; requirements for fire-rated walls, doors, fire dampers, etc.; analysis of automatic suppression systems and protected areas; water supplies; fire alarm system, including connection to the base-wide system; fire detection system; fire extinguishers; interior finish ratings; and other pertinent fire protection data. The submittal shall include a life safety floor plan for the building in the project showing occupant loading, occupancy classifications and construction type, egress travel distances, exit capacities, areas with sprinkler protection, fire extinguisher locations, ratings of fire-resistive assemblies, and other data necessary to exhibit compliance with life safety code requirements.

8.1.2 Life Safety and Fire Protection Design Document Requirements:

All Design Documents, (i.e. Building Code/Life Safety Analysis, plans, specifications, and calculations) developed for the project must be prepared by, or under the supervision of the design/build contractor's Qualified Fire Protection Engineer (QFPE), the Fire Protection Designer of Record (FPDOR). The analysis shall also include a hazards assessment prepared by the FPDOR to identify, assess and properly document the locations and types of hazardous areas and materials within the facility. This narrative shall be accurate, at each design phase, to reflect the designer’s intent in the preparation of the rest of the design documentation, including the aforementioned drawings and specifications, to ensure that no conflicts exist.

8.1.3 Life Safety Improvements:

Specific building construction features to be provided as part of the project to address life safety code compliance issues are described in the architectural section. The configuration of the spaces will be arranged to meet a mixed special purpose industrial and business occupancies to minimize hazard separation requirements and reduce egress path modifications. Sealing penetrations between admin, storage, and industrial use spaces, and the replacement of required doors and hardware for the protection from hazards is anticipated. Existing mezzanine areas will be reduced through fencing or partitions to establish the maximum allowable mezzanine areas permitted by NFPA 101 as well as separate Normally Unoccupied Equipment Support Areas

Page 50: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 50

(NUESA) as defined in NFPA 101 for the existing building systems distribution and maintenance of the building systems equipment that occurs in the open spaces over the facility storage and admin rooms. Any existing combustible access ladders or stairs for the mezzanine or NUESA shall be replaced with a non-combustible fixed stair/ladder. A Petroleum-Oil-Lubricant (POL) Distribution Room, Battery Charging room, and Fire pump room meeting code required fire ratings for the separations are anticipated.

8.1.4 General Fire Protection System Requirements:

Provide working space around all equipment. Provide concrete pads under all equipment. Provide all required fittings, connections and accessories required for a complete and usable system. Install all equipment in accordance with the applicable criteria and the manufacturer's recommendations. Where the word "should" is used in the manufacturer's recommendations, substitute the word "must".

The Qualified Fire Protection Engineer (QFPE) shall prepare, or supervise the design, of the shop drawings and calculations. The QFPE must affix their professional engineering stamp with signature to the shop drawings, calculations and material data sheets, indicating approval prior to submitting the fire extinguishing system shop drawings to the DFPE. The QFPE must monitor the installation of the fire protection systems and certify in writing that the fire protection systems have been constructed and operate as intended in the design plans and specifications.

Installation drawings, shop drawings or working plans, calculations, other required pre-construction documentation and as-built drawings must be prepared by, or under the direct supervision of a National Institute for Certification in Engineering Technologies (NICET) engineering technician as specified below. NICET engineering technicians must hold a current certification as an engineering technician in the field of Fire Protection Engineering Technology with minimum Level III certification in the appropriate subfield.

Provide training for the systems consisting of two (2) one (1)-hour sessions to accommodate both shifts of the base fire department and allow for rescheduling for unforeseen fire department responses.

8.2 Fire Sprinkler System Requirements

All existing sprinkler piping, valves, air compressors, and associated equipment shall be demolished completely back to the entry point of the fire water service into the building.

Provide new sprinkler protection utilizing painted, schedule 40 steel piping throughout the facility. Wet pipe sprinkler systems shall be

Page 51: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 51

provided. All floors and all areas of the facilities shall be protected. The sprinkler system design shall be in accordance with UFC 3-600-01 and NFPA 13. The sprinkler hazard classifications shall be in accordance with UFC 3-600-01, NFPA 13, and other applicable criteria. Design densities, design areas and exterior hose streams shall be in accordance with UFC 3-600-01. The sprinkler systems shall be designed and all piping sized with computer generated hydraulic calculations. The exterior hose stream demand shall be included in the hydraulic calculations. A complete sprinkler system design, including sprinklers, branch lines, floor mains and risers, shall be shown on the drawings. The sprinkler system plans shall include node and pipe identification used in the hydraulic calculations. All sprinkler system drains, including main drains, test drains, and auxiliary drains, shall be routed to a 2’ x 2’ splash block at exterior grade. Systems shall have drain valves at the remote ends the main and branch lines capable of testing the system and allowing the system to be flushed. Battery room sprinklers will have their own area control valve assembly with isolation valve with tamper switch, check valve, flow switch, and test drain. The flow switch shall shunt trip the power to the battery charger.

The minimum pipe size for a gridded system shall be 1-1/4 inch. Water velocity in the piping shall not exceed 20 ft/s. Hangers shall be provided on arm-overs to drop nipples supplying pendent sprinklers when the arm-over exceeds 12 inches. Riser nipples or "sprigs" to upright sprinklers shall contain no fittings between the branch line tee and the reducing coupling at the sprinkler. Riser nipples exceeding 30 inches in length shall be individually supported. Grooved couplings, fittings and grooving tools shall be products of the same manufacturer. Pipes that must penetrate concrete or masonry walls or concrete floors shall be core-drilled and provided with pipe sleeves. Escutcheons shall be provided for pipe penetration of ceilings and walls. Escutcheons shall be securely fastened to the pipe at surfaces through which piping passes.

The contractor shall provide the price difference for the entire sprinkler system to be served by a dry sprinkler system that shall include a nitrogen generator. See CLIN option “Dry Pipe Fire Sprinkler System in lieu of wet pipe”.

8.2.1 Fire Water Supply

Preliminary Fire flow test data is provided in the Attachments. The FPDOR shall conduct a fire hydrant waterflow test to gather required information accordingly and submit it with the design analysis in the Interim Design Submittal and in the design documentation prepared for the fire suppression system(s). The FPDOR shall perform fire hydrant waterflow testing and shall report the results, along with accompanying calculations, in accordance with NFPA 291 and UFC 3-600-01.

8.2.2 Sprinkler Service Main and Riser:

Page 52: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 52

The existing sprinkler service lateral is a dedicated line from the distribution main. The existing sprinkler service lateral shall be provided with a new exterior post indicator. The sprinkler system shall include an indicating control valve for each sprinkler system riser, a flow switch reporting to the FACP, and an exterior alarm bell. All control valves shall be OS&Y gate type and shall be provided with tamper switches connected to the FACP.

Facilities with multiple floors shall be provided with floor control valves for each floor. The floor control valve assembly shall be in accordance with NFPA 13-2019 A.16.14.1(b). Provide a check valve in the assembly.

8.2.3 Fire Department Connection

A new, wall-mounted fire department connection shall be provided for the building sprinkler system. These shall be located to be directly accessible to the fire department.

8.2.4 Backflow Preventer:

The existing double check backflow preventer within the aboveground insulated hot box (unheated) shall be serviced or replaced if not working after maintenance. An exterior wall hydrant with 2-1/2” hose connections with piping from the riser that includes a supervised OS&Y valve shall be provided to allow testing of backflow preventer at design flow as required by NFPA 13. An OS&Y shut-off valve with tamper switch shall be installed in the fire service entry riser inside the building.

8.2.5 Fire Pump

A fire pump will be required in the bid for the building based on recent flow tests on hydrants near the site. The need for a fire pump installation shall be confirmed by the Contractor after project award based on new fire flow test data from the project site and fire protection system design requirements for the project. The fire pump installation shall comply with the requirements of UFC 3-600-01, NFPA 13 and NFPA 20. The Contractor shall submit a fire pump design analysis and drawings during the design.

8.3 Fire Alarm and Mass Notification System Requirements

All existing alarm system panels, notification appliances, and initiation devices shall be demolished.

A new combination of mass notification and fire alarm and detection system shall be provided for this facility. It shall comply with the requirements of UFC 3-600-01, UFC 4-010-01, UFC 4-021-01, ECB

Page 53: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 53

2018-17, and NFPA 72. Provide a complete, electrically supervised, addressable intelligent, manual and automatic, annunciated fire alarm and detection system throughout the facility. Provide a voice evacuation type system that also serves as a mass notification system. Provide integrated systems capable of notifying building occupants by means of tones, strobes, textural messaging, and prerecorded and live voice announcements.

Fort Polk has limited the installation of new systems to a list of specific system manufacturers in order to reduce training, maintenance, and reserve parts costs. Acceptable manufacturers are Silent Knight and Honeywell fire alarm and mass notification systems. Systems not listed above shall be considered on an individual basis. The new system shall be fully compatible with and integrated with the base central monitoring and reporting system. The existing Monaco reporting system may be reused, but the system must have sufficient power to operate the transmitter in a normal standby status for a minimum of 72 hours and be capable of transmitting alarms during that period.

Coordinate fire alarm system requirements with the Fire Department’s Representative during design. The annunciator panels and local operating consoles (LOC) shall be shall be designed in accordance with UFC 3-600-01 and UFC 4-021-01. The LOCs are to be stand-alone units and not physically integrated into the Combined Fire Alarm and Mass Notification Panel. Push button switch for ATFP air handling unit shutdown should not be integrated into the LOC.

Provide sealed, maintenance-free batteries as the source for emergency power. Battery capacity shall be in accordance with the UFC and applicable standards.

Provide back-up amplifiers for the combination fire alarm/mass notification systems. Each amplifier shall be constantly supervised for any condition that could render the amplifier inoperable at its maximum output. Failure of any component shall cause automatic transfer to a designated backup amplifier, illumination of a visual "amplifier trouble" indicator on the control panel, appropriate logging of the condition on the system. Amplifier outputs shall be not greater than 100 watts RMS output. Equip each system with separate inputs for the tone generator, digitalized voice driver and panel mounted microphone. Microphone inputs shall be of the low impedance, balanced line type. Both microphone and tone generator input shall be operational on any amplifier. The amplifiers shall have sufficient capacity to simultaneously drive all notification speakers at the maximum rating plus 50 percent spare capacity.

Intelligibility testing of the System shall be accomplished in accordance with NFPA 72 for Voice Evacuation Systems, IEC 60268-16, and ASA S3.2. Ensure that a CIS value greater than the required minimum value is provided in each area where building occupants typically could be found. The minimum required value for CIS is .8.

Page 54: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 54

8.3.1 Appliances, Devices and Circuits

All initiating devices shall be connected, non-proprietary Class A (formerly Style 6), to signal line circuits (SLC). All alarm appliances shall be connected to non-proprietary notification appliance circuits (NAC), Class A. A looped conduit system shall be provided so that if the conduit and all conductors within are severed at any point, all NAC and SLC shall remain functional. Circuit Pathway Survivability Level 1 shall be provided for all signaling line and notification appliance circuits.

Speakers shall have six different sound output levels and operate with audio line input levels of 70.7 VRMs and 25 VRMs, by means of selectable tap settings. Tap settings shall include taps of 1/8, 1/4, 1/2, 1, and 2 watt. Speakers shall incorporate a high efficiency speaker for maximum output at minimum power across a frequency range of 150 Hz to 10,000 Hz, and shall have a sealed back construction.

A supervised Post Indicator Valve is not required.

A supervised Knox Box is required to be located near the fire department connection.

Provide surface mounted, double-action manual pull stations. Breakglass manual fire alarm stations shall not be used.

Interlock AHU shutdown with any alarm condition.

All sprinkler system alarms and switches shall be electrically powered and supervised by the fire alarm system including the Fire Pump per UFC and NFPA requirements.

Notification appliances with a single, clear lens marked “Alert” are required.

Smoke detectors in addressable systems shall be photoelectric analog type, providing information that the control unit stores in memory, and uses to provide a history of detector stability, and notification at the control unit where sensitivity is outside its acceptable sensitivity range.

The LED textual displays shall be programmable and shall display the same content of the voice message being played. The signs shall meet NFPA 72 requirements along with the following requirements: provide a minimum of 4 inch high letters, be located in high traffic areas easily seen by building occupants, provide two lines of information for high priority messaging, minimum of 20 characters per line (40 total) displayed, 32K character memory, be wall or ceiling mounted with mounting brackets, and display date and time during non-emergency periods.

Page 55: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 55

For systems having circuits located outdoors, communications equipment shall be protected against surges induced on any signaling line circuit. Digital and analog inputs and outputs shall be protected against surges induced by sensor wiring installed outdoors.

8.3.2 Carbon Monoxide Detection System

Provide Carbon Monoxide Detection System integrated with building Fire Alarm and Mass Notification in accordance with UFC 3-600-01 and NFPA 72.

Page 56: Section 01 10 00.01 BUILDING 3003 SCOPE OF WORKdotconstructioninc.com/wp-content/uploads/2020/08/Rev... · 2020. 8. 26. · Polk Tactical Equipment Maintenance Facility (TEMF) Reno.-

Polk Tactical Equipment Maintenance Facility (TEMF) Reno.- Bldgs. 3003 & 4652

Fort Polk, Louisiana Solicitation No. W9126G20U0025

Bldg 3003 Section 01 10 00.01 Page 56

Fort Polk Standard Color Schedule

Tan/Beige Color Scheme

Interior Colors

Walls

Paint Sherman-Williams Oyster White SW7637 Sherman-Williams Antique White SW6119

Ceramic Wainscot American Olean 12x12 Tan-Brown 132734 Or Daltile – Urban Putty

Vinyl Base Cove Roppe Fawn P140

Ceramic Sanitary Base American Olean 12x12 Tan-Brown 132734 Or Daltile – Urban Putty

Ceramic Accent American Olean 6x6 White

Door Frame Sherman-Williams Balanced Beige SW7037

Flooring

Static Dissipative Tile Armstrong Marble Beige 51950

Ceramic Tile Milestone Stonefire 18 inch by 18 inch Beige 1093088 Or Equal

Polished Concrete International Polished Concrete Institute (IPCI) Sheen Level 4. Material and Installation shall be in accordance with ASTM D 523. Installer shall be IPCI Certified; workers shall be IPCI Certified Craftsmen.

Accessories

Restroom Partition American Sanitary Solid Plastic HDPE Bronze BZ01 Stainless Steel Hardware

Exterior Colors

Roof

Metal Tudor Brown Medium Bronze

Walls

Metal Valspar - Cool Country Wheat 454R1160

CMU Sherman-Williams Oak Creek SW7718

End of Section