360
SECTION 00410 SCHEDULE OF PAY ITEMS 1 INJECTION WELL FACILITIES – PHASE 3 October 6 th , 2020 SECTION 00410 SCHEDULE OF PAY ITEMS IMPORTANT: THE SCHEDULE OF PAY ITEMS MUST BE COMPLETED BY EACH BIDDER AND PROPERLY SUBMITTED THROUGH THE ELECTRONIC BID MANAGEMENT SYSTEM AS A .PDF. FAILURE TO COMPLETE THE SCHEDULE OF PAY ITEMS WILL RESULT IN AN INCOMPLETE AND NON-RESPONSIVE BID. IF A BIDDER OMITS A PRICE FOR ANY ITEM OR INCLUDES ANY OTHER QUANTITY OTHER THAN THE ONE INDICATED IN SECTION 00410, M1W WILL CORRECT THE ITEM QUANTITY AND RECALCULATE THE BID AMOUNT. BIDDERS MUST PROVIDE PRICING FOR EVERY LINE ITEM INCLUDED IN THE SCHEDULE OF PAY ITEMS. FAILURE TO DO SO WILL RENDER THE BID NONRESPONSIVE. Base Bid Schedule A: Non-Well Drilling Work Item Description Units Quantity Total 1 Worker Protection and Safety/Shoring Pursuant to CA Labor Code 6707 Safety systems and equipment for protection of workers in open trench construction. Lump Sum 1 $ 2 SWPPP and Traffic Control Implementation of SWPPP BMPs and Traffic Control Plan. Lump Sum 1 $ 3 Mobilization and Demobilization (Limited to 5% of Total Bid Price) Lump Sum 1 $ 4 Conveyance Pipelines & Site Work Construction of all underground conveyance pipelines (including fittings and appurtenances) and aggregate base surfacing for the access road Lump Sum 1 $ 5 All work at Well Site No. 1 Site improvements and structural support pads for Well Site No. 1; construction of mechanical, electrical, and instrumentation equipment for well DIW- 3. Lump Sum 1 $

SECTION 00410 SCHEDULE OF PAY ITEMS IMPORTANT: THE

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

SECTION 00410SCHEDULE OF PAY ITEMS

1 INJECTION WELL FACILITIES – PHASE 3 October 6th, 2020

SECTION 00410 SCHEDULE OF PAY ITEMS

IMPORTANT:

THE SCHEDULE OF PAY ITEMS MUST BE COMPLETED BY EACH BIDDER AND PROPERLY SUBMITTED THROUGH THE ELECTRONIC BID MANAGEMENT SYSTEM AS A .PDF. FAILURE TO COMPLETE THE SCHEDULE OF PAY ITEMS WILL RESULT IN AN INCOMPLETE AND NON-RESPONSIVE BID. IF A BIDDER OMITS A PRICE FOR ANY ITEM OR INCLUDES ANY OTHER QUANTITY OTHER THAN THE ONE INDICATED IN SECTION 00410, M1W WILL CORRECT THE ITEM QUANTITY AND RECALCULATE THE BID AMOUNT.

BIDDERS MUST PROVIDE PRICING FOR EVERY LINE ITEM INCLUDED IN THE SCHEDULE OF PAY ITEMS. FAILURE TO DO SO WILL RENDER THE BID NONRESPONSIVE.

Base Bid Schedule A: Non-Well Drilling Work

Item Description Units Quantity Total

1

Worker Protection and Safety/Shoring –Pursuant to CA Labor Code 6707

Safety systems and equipment for protection of workers in open trench construction.

LumpSum

1

$

2

SWPPP and Traffic Control Implementation of SWPPP BMPs and Traffic Control Plan.

LumpSum

1

$

3

Mobilization and Demobilization (Limited to 5% of Total Bid Price)

LumpSum 1 $

4

Conveyance Pipelines & Site Work Construction of all underground conveyance pipelines (including fittings and appurtenances) and aggregate base surfacing for the access road

LumpSum

1

$

5

All work at Well Site No. 1 Site improvements and structural support pads for Well Site No. 1; construction of mechanical, electrical, and instrumentation equipment for well DIW-3.

LumpSum

1

$

SECTION 00410SCHEDULE OF PAY ITEMS

2 INJECTION WELL FACILITIES – PHASE 3 October 6th, 2020

Item Description Units Quantity Total

6

All Work at Well Site No. 4, excluding the analyzer implementation Site improvements and structural support pads for Well Site No. 4; construction of mechanical, electrical, and instrumentation equipment for well DIW-4.

LumpSum

1

$

7

Analyzers Construction of chlorine analyzer station at Well Site No. 4, including instruments, electrical equipment, and piping.

LumpSum

1 $

8

All other work All required non-well drilling work not described in the preceding bid items (Nos. 1-7)

LumpSum

1

$

Total Bid Price Schedule A $

Schedule B: Deep Injection Well (DIW-3) Drilling Work

Item

Description

Units

UnitCost

(Dollars per Unit)

Quantity

Total

1 Mobilization and Demobilization Lump Sum

1 $

2 Drilling and Installation of 36-inch Diameter Permanent Conductor Casing

Vertical Feet

120

$

3 36-inch Diameter Mild Steel Conductor Casing Material

Vertical Feet

120

$

4 Installation of Conductor Sealing Materials Lump Sum

1

$

5 Conductor Sealing Materials Cubic Yards

27

$

6 Drilling 17.5-inch Diameter Pilot Borehole below Conductor Casing

Vertical Feet

870

$

7 Reaming 34-inch Diameter Well Borehole below Conductor Casing

Vertical Feet

855 $

8 Hauling and Offsite Disposal of Drilling Fluids

1000x Gallons

20 $

SECTION 00410SCHEDULE OF PAY ITEMS

3 INJECTION WELL FACILITIES – PHASE 3 October 6th, 2020

Item

Description

Units

UnitCost

(Dollars per Unit)

Quantity

Total

9 Geophysical Logging of Pilot Borehole

Vertical Feet

870 $

10 Installation of 24-inch Diameter Type 304 Stainless Steel Well Casing

Vertical Feet

735 $

11 24-inch Type 304 Stainless Steel Well Casing Material, adjusted for 140-feet of owner-supplied casing

Vertical Feet

595 $

12

Installation of 24-inch Diameter Type 316 Stainless Steel Wire-Wrapped Stainless Steel Well Screen

Vertical Feet

225 $

13 24-inch Diameter Type 316 Wire-Wrapped Stainless Steel Well Screen Material

Vertical Feet

225 $

14 Installation and Materials for Sounding Tube and Screen/Casing Centralizers

Lump Sum

1 $

15 Installation of Artificial Filter Pack Vertical

Feet

345 $

16 Artificial Filter Pack Materials Cubic Yards

45 $

17 Artificial Filter Feed Pipe Installation and Materials

Lump Sum

1 $

18 Installation of Well Sealing Materials Lump Sum

1 $

19 Well Sealing Materials Cubic Yards

75 $

20 Well Development by Surging and/or Airlifting

Hours

100 $

21

Well Development by Overpumping Hours

160 $

22 Installation and Removal of Pumping Equipment for Development

Lump Sum

1 $

23 Variable Rate Pumping Test Hours

8 $

SECTION 00410SCHEDULE OF PAY ITEMS

4 INJECTION WELL FACILITIES – PHASE 3 October 6th, 2020

Item

Description

Units

UnitCost

(Dollars per Unit)

Quantity

Total

24 Constant Rate Pumping Test Hours

24 $

25 Spinner Log of DIW-3 during Constant Rate Pumping Test

Lump Sum

1 $

26 Well Disinfection Lump Sum

1 $

27 Video Log of DIW-3 Lump Sum

1 $

28 Well Destruction - In the event of unsuccessful borehole or failed well

Vertical Feet

990 $

29 Standby Time Hours

24 $

Total Bid Price Schedule B $

Schedule C: DIW-3 Final Well Commissioning Work

Item

Description

Units

UnitCost

(Dollars per Unit)

Quantity

Total

1 Mobilization Lump Sum 1 $

2

Remove Permanent Pump Assembly

Lump Sum 1 $

3 Bailing Lump Sum 1

$

4 Nylon Brushing Hourly 2

$

5 Bailing Lump Sum 1

$

6 Temporary Discharge, Storage, Conveyance, and Disposal

Lump Sum 1 $

7 Pre-Chemical Simultaneous Air-Lift Pumping/Swabbing

Hourly 12 $

8 Chemical Treatment Lump Sum 1

$

9

Dry-Swab with Single-Line Swab Tool Hourly 12

$

SECTION 00410SCHEDULE OF PAY ITEMS

5 INJECTION WELL FACILITIES – PHASE 3 October 6th, 2020

Item

Description

Units

UnitCost

(Dollars per Unit)

Quantity

Total

10 Post-Chemical Simultaneous Air-Lift Pumping/Swabbing

Hourly 23 $

11 Acid Neutralization Lump Sum 1

$

12 Bailing Lump Sum 1

$

13 Post-Rehab Video Survey Lump Sum 1

$

14 Well Disinfection Lump Sum 1

$

15 Re-Install Permanent Pump

Assembly Lump Sum 1 $

16 Chlorine Flushing Lump Sum 1 $

17 Demobilization Lump Sum 1

$

Total Bid Price Schedule C $ Schedule D: Deep Injection Well (DIW-4) Drilling Work

Item

Description

Units

UnitCost

(Dollars per Unit)

Quantity

Total

1 Mobilization and Demobilization Lump Sum

1 $

2 Drilling and Installation of 36-inch Diameter Permanent Conductor Casing

Vertical Feet

120

$

3 36-inch Diameter Mild Steel Conductor Casing Material

Vertical Feet

120

$

4 Installation of Conductor Sealing Materials Lump Sum

1

$

5 Conductor Sealing Materials Cubic Yards

27

$

SECTION 00410SCHEDULE OF PAY ITEMS

6 INJECTION WELL FACILITIES – PHASE 3 October 6th, 2020

Item

Description

Units

UnitCost

(Dollars per Unit)

Quantity

Total

6 Drilling 17.5-inch Diameter Pilot Borehole below Conductor Casing

Vertical Feet

485

$

7 Reaming 34-inch Diameter Well Borehole below Conductor Casing

Vertical Feet

475 $

8 Hauling and Offsite Disposal of Drilling Fluids

1000x Gallons

20 $

9 Geophysical Logging of Pilot Borehole

Vertical Feet

485 $

10 Installation of 24-inch Diameter Type 304 Stainless Steel Well Casing

Vertical Feet

445 $

11 24-inch Type 304 Stainless Steel Well Casing Material

Vertical Feet

445 $

12

Installation of 24-inch Diameter Type 316 Stainless Steel Wire-Wrapped Stainless Steel Well Screen

Vertical Feet

140 $

13 24-inch Diameter Type 316 Wire-Wrapped Stainless Steel Well Screen Material

Vertical Feet

140 $

14 Installation and Materials for Sounding Tube and Screen/Casing Centralizers

Lump Sum

1 $

15 Installation of Artificial Filter Pack Vertical

Feet

223 $

16 Artificial Filter Pack Materials Cubic Yards

30 $

17 Artificial Filter Feed Pipe Installation and Materials

Lump Sum

1 $

18 Installation of Well Sealing Materials Lump Sum

1 $

19 Well Sealing Materials Cubic Yards

40 $

20 Well Development by Surging and/or Airlifting

Hours

100 $

21

Well Development by Overpumping Hours

120 $

SECTION 00410SCHEDULE OF PAY ITEMS

7 INJECTION WELL FACILITIES – PHASE 3 October 6th, 2020

Item

Description

Units

UnitCost

(Dollars per Unit)

Quantity

Total

22 Installation and Removal of Pumping Equipment for Development

Lump Sum

1 $

23 Variable Rate Pumping Test Hours 8 $

24 Constant Rate Pumping Test Hours

24 $

25 Spinner Log of DIW-4 during Constant Rate Pumping Test

Lump Sum

1 $

26 Well Disinfection Lump Sum

1 $

27 Video Log of DIW-4 Lump Sum

1 $

28 Well Destruction - In the event of unsuccessful borehole or failed well

Vertical Feet

595 $

29 Standby Time Hours

24 $

Total Bid Price Schedule D $

Schedule E: DIW-4 Final Well Commissioning Work

Item

Description

Units

UnitCost

(Dollars per Unit)

Quantity

Total

1 Mobilization Lump Sum 1 $

2

Remove Permanent Pump Assembly

Lump Sum 1 $

3 Bailing Lump Sum 1

$

4 Nylon Brushing Hourly 2

$

5 Bailing Lump Sum 1

$

6 Temporary Discharge, Storage, Conveyance, and Disposal

Lump Sum 1 $

7 Pre-Chemical Simultaneous Air-Lift Pumping/Swabbing

Hourly 9 $

SECTION 00410SCHEDULE OF PAY ITEMS

8 INJECTION WELL FACILITIES – PHASE 3 October 6th, 2020

Item

Description

Units

UnitCost

(Dollars per Unit)

Quantity

Total

8 Chemical Treatment Lump Sum 1 $

9

Dry-Swab with Single-Line Swab Tool Hourly 8

$

10

Post-Chemical Simultaneous Air-Lift Pumping/Swabbing

Hourly 17 $

11 Acid Neutralization Lump Sum 1

$

12 Bailing Lump Sum 1

$

13 Post-Rehab Video Survey Lump Sum 1

$

14 Well Disinfection Lump Sum 1

$

15 Re-Install Permanent Pump

Assembly Lump Sum 1 $

16 Chlorine Flushing Lump Sum 1 $

17 Demobilization Lump Sum 1

$

Total Bid Price Schedule E $ Total Bid Price (Sched A + Sched B+ Sched C + Sched D + Sched E): $

Total Bid Price Amount Written in Words:

END OF SCHEDULE OF PAY ITEMS

1668012*05 INJECTION WELL FACILITIES – PHASE 3

40 60 20 - 1 Control Strategies October 6th, 2020

SECTION 40 60 20

CONTROL STRATEGIES

CONTROL STRATEGY 1 TITLE: System Configuration

A. General: This strategy describes the configuration of the Programmable Logic Controllers (PLCs) and associated operator interface or human machine interface (HMI) for configuration of the Remote Input/Output unit (RIO) and local HMI at the new deep injection wells.

B. Programmable Logic Controller: There is an existing PLC located in the Electrical Building. The PLC provides control and monitoring of the deep injection wells and backwash pumps, control valves, vadose zone injection well, and monitoring wells. The hydraulically-actuated flow control valve at a DIW will be controlled by a vendor-furnished controller, and will be monitored by the system PLC in the Electrical Building. 1. Well RIO Configuration: A new RIO shall be located at the new deep injection well

site. Configuration of the Deep Injection Well RIO shall be provided under this contract. The RIO shall provide an interface for all control and monitoring of the equipment and field instruments at the Deep Injection Well site. This includes the well backwash pump, injection flow control valve, backflush control valve, main in-line control valve and instrumentation. The wells shall be controlled as described in Control Strategies 4 and 5. The I&C Subcontractor for this contract shall coordinate work with the Contractor for the Well Equipping facilities for programming, uploading ladder logic, testing and startup.

2. Radio communications: There is an existing radio next to the Electrical Building for remote communications to the Blackhorse Reservoir and the M1W SCADA system. The radios and antennas at the Electrical Building, Blackhorse Reservoir, and other repeater sites (SRDF, Reeside Pump Station) for SCADA communications are existing.

3. Communications to Well PLCs: The deep injection well will be provided with its own RIO to act as an extension of the PLC at the Electrical Building. The PLC at the Electrical Building shall communicate to the well RIOs via Ethernet through fiber optic cable. Fiber optic patch panels and fiber to Ethernet media converters at the RIOs at the wells shall be provided under this contract. Fiber optic cable shall be provided under this contract.

C. Field instruments and devices are connected as PLC Inputs. While some signals are not processed by the PLC for control, they shall be programmed for monitoring at the new HMIs and existing HMIs (both existing DIW sites and Electrical Building).

D. Local Operator Interface: The panel-mounted HMI at each PLC and RIO shall provide the functions listed below as a minimum. The HMI shall allow for control and monitoring of the facility. The HMI shall include, but not be limited to, indications of the functions listed below. Print outs of the HMI screens shall be submitted to the Engineer for review. 1. Indication of equipment status and total running hours. 2. Indication and logging of alarms. 3. Indication and totalization of flows. 4. Indication of process variables such as pressure, level and flows.

Control Strategies October 6th, 2020

40 60 20 - 2 1668012*05 INJECTION WELL FACILITIES,

PHASE 3

5. Adjustment of control settings such as time delay, pressure and level setpoints. 6. Display of alarms. 7. Display of real time and historical trends for pressure, level and flows (real time

history shall be mimicked at the Electrical Building PLC and HMI). 8. Control of equipment in “Hand” mode at the HMI.

E. Deep Well Local HMI Screens: The HMI screens shall be modeled based on the existing HMI for the existing injection well facilities. Provide an overall Main Menu to allow selection of screens. Provide an alarm window with each screen to allow the operator to view and acknowledge alarms. The following screens shall be provided as a minimum at the HMI: 1. Deep Injection Well RIO Panel:

a. System Overview b. Well Pump Screens: Provide a minimum of one screen for control and

monitoring of the associated well. Provide local HMI with screens for monitoring of the other existing wells. (For example, DIW-3 shall be provided with a screen to control and monitor DIW-3. It shall also be provided with screens for monitoring only of status, such as pump status, level, pressure, and flow at the other injection and monitoring wells.)

c. Percolation Basin Level d. Well Water Levels: Show well water level trends for last 12 months, last 4

months, last 30 days and last 7 days. Water level screen shall display water level elevation based on setpoint control elevation equal to the well discharge head control elevation in feet above mean sea level to the hundredth of a foot.

e. Setpoints: Screen to adjust setpoints for the associated well only. f. Alarm Summary/History g. Trends h. Indication, low flow alarm, low low flow alarm, instantaneous flow, flow

totalization, non-resettable totals, resettable total flows, current day flow, and previous day flows

i. Indication of equipment status and total running hours j. Display of alarms and alarm acknowledge system k. Display the 3R Valve Position

F. The HMI noted in the subsequent control strategies in this section shall refer to both the

local HMI and the SCADA HMI.

G. Existing Electrical Building: 1. Existing PCP-MGI PLC shall be modified to integrate the new well improvements. 2. The existing PCP-MGI HMI shall be updated to include the new deep injection wells. 3. Add to (E) HMI the motor Runtimes as described in Control Strategies 2 C. 4. Pull a power fail alarm signal from the SWGR power meter 52-1 and add to the (E)

HMI screen. Include the Loss of Normal Power as described in Control Strategy 2 D. 5. Add Flow Totalization for all Deep Injection Wells, new and two existing to the (E)

HMI screens. 6. Add all alarms associated with DIWs to the (E) HMI screens 7. Add the 3R valve position for all Deep Injection Wells to the (E) HMI screens 8. Add a new SWGR screen (existing MV switchgear) to (E) HMI to include all available

relay and power meter alarms, status, monitoring, and trending. Relays and Power Meters included GE SEJ21A, two SEL-351, two SEL-751A, and three SEL-735 power meters.

1668012*05 INJECTION WELL FACILITIES – PHASE 3

40 60 20 - 3 Control Strategies October 6th, 2020

H. Existing M1W RTP: 1. The central SCADA system including the (E) HMI’s and (E) workstations shall be

modified to integrate the new well improvements. 2. Historical trending shall be modified to integrate the new well improvements. 3. Pull a power fail alarm signal from the SWGR power meter 52-1 and add to the

SCADA system, (E) HMI’s and (E) workstations. Include the Loss of Normal Power as described in Control Strategy 2 D. on the SCADA screens.

4. Add to (E) HMI’s and (E) workstations the motor Runtimes as described in Control Strategies 2 C.

5. Add Flow Totalization for all Deep Injection Wells, new and two existing to the (E) HMI screens and (E) workstations.

6. Add all alarms associated with DIWs to the (E) HMI screens and (E) workstations. 7. Add the 3R valve position for all Deep Injection Wells to the (E) HMI screens and (e)

workstations 8. Add a new SWGR screen (existing MV switchgear) to (E) HMIs and (E) workstations

to include all available relay and power meter alarms, status, monitoring, and trending. Relays and Power Meters included GE SEJ21A syn relay, two SEL-351 relay, two SEL-751A relay, and three SEL-735 power meters.

I. Allen Bradley PlantPAX VFD block shall be added to the Electrical Building PLC. A HMI

screen shall be developed to show VFD status signals and maintenance requirements.

Control Strategies October 6th, 2020

40 60 20 - 4 1668012*05 INJECTION WELL FACILITIES,

PHASE 3

CONTROL STRATEGY 2

TITLE: General Equipment Interface

AREA: All

RELATED CONTROL STRATEGIES: All

A. General: This strategy describes typical interface logic of the PLC with final control elements such as pumps and other equipment. This applies to all control strategies in this section of the Specifications.

B. Description: The PLC shall monitor or determine the equipment's related inputs/outputs as follows: 1. Monitor whether equipment is in "Ready" mode before initiating or queuing

equipment for control. 2. If equipment is ready, the PLC shall activate a normally open discrete output "DO" to

start the equipment. 3. The PLC shall interrogate the circuit and monitor the input "RUN" discrete input. 4. If the "RUN" input is not activated within an adjustable time period of t = 0 -10

seconds, the PLC shall annunciate an equipment "Fail" condition on the operator interface panel.

5. The PLC shall also annunciate an equipment "Fail" on the operator interface panel if a separate discrete input signal is detected.

6. The "RUN" signal shall activate on elapsed time register in the operator interface to monitor the total run time of equipment.

C. Runtime: 1. Log the runtime of all pumps. 2. To determine Runtime, the PLC monitors a start or run contact such as from a

variable frequency drive or motor starter. 3. Monitor for and determine Runtimes even if the “Ready” signal is not activated.

D. Loss of Normal Power: 1. The PLC and RIO cabinets shall be provided with a relay and contact to indicate loss

of “normal” power (120V) to the PLC or RIO. This shall be monitored upstream of the UPS.

2. After loss of normal power, the PLC shall restart PLC controlled loads in steps. Stagger start loads in 5 second increments.

E. UPS Fail: The PLC or RIO shall monitor a UPS fail alarm. The alarm shall be display on the HMI.

F. High Temperature: The PLC shall monitor a thermostat in the DIW RIO enclosure, which provides an alarm for a field-adjustable high temperature condition in the room. The alarm shall be display on the HMI.

G. PLC Communications: The Well RIO shall generate a local communications fail alarm based on a timer that is reset to zero by the Electrical Building PLC upon every communication or periodic communication.

1668012*05 INJECTION WELL FACILITIES – PHASE 3

40 60 20 - 5 Control Strategies October 6th, 2020

H. Panel Intrusion Alarm: The RIO panel door switch shall be monitored by the PLC. Authorized personnel shall be provided with an override key (Operator input at the local HMI) to disarm a panel intrusion alarm generated by the door switch.

Control Strategies October 6th, 2020

40 60 20 - 6 1668012*05 INJECTION WELL FACILITIES,

PHASE 3

CONTROL STRATEGY 3

TITLE: Alarm System RELATED EQUIPMENT AND CONTROL STRATEGIES: All

A. General: This strategy describes the monitoring and display of alarm conditions. The alarm conditions can be 1) Discrete input and 2) Derived.

B. Description:

1. Discrete Input: Whenever a discrete input alarm is detected, the PLC shall annunciate an alarm after an adjustable delay of 0 - 5 seconds.

2. Derived Alarms: A derived alarm consists of monitoring of analog inputs and/or logic derivation within control strategies. The PLC monitors these events and produce alarms after an adjustable delay of 0 - 5 seconds. Setting of alarm setpoint shall be available on the operator interface.

3. Instrument Analog Signal out of range: The PLC shall monitor 4-20mA analog signals from instrumentation such as level and pressure transmitters and flowmeters that provide continuous process signal monitoring. The PLC shall annunciate an “invalid signal” or “out of range” alarm when the signal is above or below the calibrated instrument range.

C. Alarm Sequence: The PLC programs shall execute alarms as follows:

1. Upon the activation of an alarm, a flashing indication and alarm text message shall be displayed on the operator interface.

2. An “Alarm Acknowledge” button at the operator interface shall acknowledge the alarm and the alarm message shall stay steady.

3. An “Alarm Reset” button shall remove the alarm message.

1668012*05 INJECTION WELL FACILITIES – PHASE 3

40 60 20 - 7 Control Strategies October 6th, 2020

CONTROL STRATEGY 4 TITLE: Well Injection AREA: All SHEET: I-003, I-009, I-010 RELATED EQUIPMENT: Hydraulically-Actuated Flow Control Valves: FCV-300 Hydraulic Pump Units: HPU-300 Hydraulic Valve Controllers: LCP-301 Deep Well Injection Isolation Valves: MOV-320 Deep Well Backwash Isolation Valves: MOV-310 Well Level Transmitters: LT-301 Well Pressure Transmitters: PIT-302 Injection Flow Meters: FIT-304 Backwash Flow Meters: FIT-306 Hydraulically-Actuated Flow Control Valves: FCV-400 Hydraulic Pump Units: HPU-400 Hydraulic Valve Controllers: LCP-401 Deep Well Injection Isolation Valves: MOV-420 Deep Well Backwash Isolation Valves: MOV-410 Well Level Transmitters: LT-401 Well Pressure Transmitters: PIT-402 Injection Flow Meters: FIT-404 Backwash Flow Meters: FIT-406 Total Chlorine: AE/AIT-431 Total Chlorine: AE/AIT-433 pH/Temperature: AE/AIT-432 pH/Temperature: AE/AIT-434 A. General: The hydraulic flow control valve, controller, and pump unit at the deep injection

well have associated vendor-furnished packages, which are programmed to adjust to maintain a flow setpoint during injection/recharge. The hydraulic flow control valves operate independently of one another and are interlocked with their corresponding injection isolation valve such that they close prior to the initiation of a backwash operation at the respective well. Chlorine Analyzer Station has spare or backup instruments. An operator shall manually adjust the ball valves in order to select one analyzer over another. The analyzers will require periodic calibration in the field.

B. Monitoring and Alarms 1. Monitoring:- DIW-3

a. Deep Injection Well: Level: LI-301 Injection Flow: FI-304 Valve FCV-300 Position: MOV-300 Valve FCV-310 Position: MOV-310 Valve FCV-320 Position: MOV-320 Injection Pressure (at ground level): PI-302 Backwash Flow (to Percolation Basin): FI-306

Control Strategies October 6th, 2020

40 60 20 - 8 1668012*05 INJECTION WELL FACILITIES,

PHASE 3

Isolation Valve Local/Remote Status: HS-320B Isolation Valve Opened/Closed Status: ZIO/ZIC-320B

2. Monitoring: DIW-4: a. Deep Injection Well:

Level: LI-401 Injection Flow: FI-404 Valve FCV-400 Position: MOV-400 Valve FCV-410 Position: MOV-410

b. Chlorine Monitoring Station Total Chlorine: AIT-431 Total Chlorine: AIT-433 pH: AIT-432A Temp: AIT-432B pH: AIT-434A Temp: AIT-434B

3. Valve FCV-420 Position: MOV-420 Injection Pressure (at ground level): PI-402 Backwash Flow (to Percolation Basin): FI-406 Isolation Valve Local/Remote Status: HS-420B Isolation Valve Opened/Closed Status: ZIO/ZIC-420B

4. Alarms -DIW-3 a. Discrete Input:

Deep Injection Flow Control Valve Fail: YA-300 b. Derived:

Isolation Valve Fail (Fail to Open/Close): YA-310, -320 Low Injection Flow: FAL-304

c. Instrument Analog Signal Out of Range: Level: LA-301 Pressure: PA-302 Flow: FA-304/306

5. Alarms -DIW-4 a. Discrete Input:

Deep Injection Flow Control Valve Fail: YA-400 b. Derived:

Isolation Valve Fail (Fail to Open/Close): YA-410, -420 Low Injection Flow: FAL-404

c. Instrument Analog Signal Out of Range: Level: LA-401 Pressure: PA-402 Flow: FA-404/406

C. Injection Control (Deep Wells) 1. Local Manual*: At the injection isolation valve (HS-320B and HS-420B at valve actuator

in LOCAL) *also relies upon programming within the vendor-furnished flow control valve controller

2. Remote Manual*: At the HMI (HS-320B and HS-420B at valve actuator in REMOTE) *also relies upon programming within the vendor-furnished flow control valve controller

3. Automatic*: By the PLC (HS-320B and HS-420B at valve actuator in REMOTE) *also relies upon programming within the vendor-furnished flow control valve controller a. Flow Control: Ideal injection flow is maintained by vendor-furnished valve and

control system. The setpoint shall be adjustable via a secured override at the HMI. b. Injection flow is measured by a flow meter (FIT-304 and FIT-404). Low flow alarm

shall be triggered at an adjustable value (Operator setpoint).

1668012*05 INJECTION WELL FACILITIES – PHASE 3

40 60 20 - 9 Control Strategies October 6th, 2020

c. Injection pressure (at ground level) is measured by a pressure transmitter (PIT-302 and PIT-402). The flow control valve shall close at a configurable low pressure setpoint.

d. Well level is measured by a level transmitter (LT-301 and LT-401). The flow control valve shall close at a configurable high water level setpoint.

D. Interlocks: 1. Deep Well Injection Flow Control Valves: Shall close when the corresponding deep well

injection isolation valve closes.

Control Strategies October 6th, 2020

40 60 20 - 10 1668012*05 INJECTION WELL FACILITIES,

PHASE 3

CONTROL STRATEGY 5 TITLE: Deep Well Backwash Pump Control AREA: All SHEET: I-003, I-009, I-010 RELATED EQUIPMENT: Hydraulically-Actuated Flow Control Valves: FCV-300 Hydraulic Pump Units: HPU-300 Hydraulic Valve Controllers: LCP-301 Deep Well Injection Isolation Valves: MOV-320 Deep Well Backwash Isolation Valves: MOV-310 Well Level Transmitters: LT-301 Well Pressure Transmitters: PIT-302 Well High Pressure Switches: PSH-302 Backwash Flow Meters: FIT-306 Backwash Pumps High Vibration Switches: VT-301A, VT -301B Backwash Pumps High RTDs: TIT-301 Backwash Pumps VFD (Output Contactors): XI-300, YI-301 Hydraulically-Actuated Flow Control Valves: FCV-400 Hydraulic Pump Units: HPU-400 Hydraulic Valve Controllers: LCP-401 Deep Well Injection Isolation Valves: MOV-420 Deep Well Backwash Isolation Valves: MOV-410 Well Level Transmitters: LT-401 Well Pressure Transmitters: PIT-402 Well High Pressure Switches: PSH-402 Backwash Flow Meters: FIT-406 Backwash Pumps High Vibration Switches: VT-401A, VT -401B Backwash Pumps High RTDs: TIT-401 Backwash Pumps VFD (Output Contactors): XI-400, YI-401 A. General: The deep injection well shall be equipped with one deep well turbine pump and

motor for backwash operations. Backwashes will occur weekly on each deep injection well, with only one well backwashed at one time. One variable frequency drive (VFD) controls all backwash pumps. The VFD can accommodate up to four (4) full-voltage bypass contactors, one for each planned deep injection well. The deep well shall be equipped with an electrically actuated backwash isolation valve (flow to Percolation Basin), an electrically actuated injection isolation valve, and an in-line check valve assembly on each the injection piping and the backwash piping. 1. The injection isolation valve shall be open when the well is in injection mode (normally

open) and the backwash isolation valve shall be closed when the well is in injection mode (normally closed).

2. In the “AUTO” control mode the backwash pump will be called to run based on a request from the PLC at the Electrical Building. Pump speed will be controlled using a true PID algorithm (proportional, integral, derivative, time constant and setpoint) to maintain a setpoint flow rate within an adjustable deadband setpoint.

B. Monitoring and Alarms

1. Monitoring:- DIW-3

1668012*05 INJECTION WELL FACILITIES – PHASE 3

40 60 20 - 11 Control Strategies October 6th, 2020

a. Deep Injection Wells: Backwash Pump Run Status: XI-300 Backwash Pump E-Stop Status: YI-301 Backwash Pump VFD Remote Status: HS-001A Backwash Pump VFD Speed Indication: SI-001 Level: LI-301 Backwash Pressure: PI-302 Valve FCV-300 Position: MOV-300 Valve FCV-310 Position: MOV-310 Valve FCV-320 Position: MOV-320 Backwash Flow (to Percolation Basin): FI-306 Injection Isolation Valve Local/Remote Status: HS-320B Injection Isolation Valve Opened/Closed Status: ZIO/ZIC-320B Backwash Isolation Valve Local/Remote Status: HS-310B Backwash Isolation Valve Opened/Closed Status: ZIO/ZIC-310B

b. Deep Monitoring Wells: Level: LI-305

c. Percolation Pond: Level: LI-151

d. Surge Tank: Differential Pressure: DPI-150

2. Monitoring:- DIW-4 a. Deep Injection Wells:

Backwash Pump Run Status: XI-400 Backwash Pump E-Stop Status: YI-401 Backwash Pump VFD Remote Status: HS-001A Backwash Pump VFD Speed Indication: SI-001 Level: LI-401 Backwash Pressure: PI-402 Valve FCV-400 Position: MOV-400 Valve FCV-410 Position: MOV-410 Valve FCV-420 Position: MOV-420 Backwash Flow (to Percolation Basin): FI-406 Injection Isolation Valve Local/Remote Status: HS-420B Injection Isolation Valve Opened/Closed Status: ZIO/ZIC-420B Backwash Isolation Valve Local/Remote Status: HS-410B Backwash Isolation Valve Opened/Closed Status: ZIO/ZIC-410B

b. Deep Monitoring Wells: Level: LI-405

c. Percolation Pond: Level: LI-151

d. Surge Tank: Differential Pressure: DPI-150

3. Alarms -DIW-3

a. Discrete Input: VFD Fail: YA-001 Pump E-Stop: YA-301 Pump High Bearing Vibration Shutdown: VAH-301A Pump High Shaft Vibration Shutdown: VAH-301B Pump High Temperature Shutdown: TAH-301 Pump High Discharge Pressure Shutdown: PAH-302B

Control Strategies October 6th, 2020

40 60 20 - 12 1668012*05 INJECTION WELL FACILITIES,

PHASE 3

Percolation Pond High Level Shutdown: LAH-151B Deep Injection Flow Control Valve Fail: YA-300 b. Derived: Well Low Level: LAL-301 Pump High Discharge Pressure Alarm: PAH-302A High/Low Flow: FAH/FAL-306 Percolation Pond High Level Alarm: LAH-151A Isolation Valve Fail (Fail to Open/Close): YA-310, -320 c. Instrument Analog Signal Out of Range: Level: LA-301 Pressure: PA-302, DPA-150 Flow: FA-306

4. Alarms - DIW-4 a. Discrete Input: VFD Fail: YA-001 Pump E-Stop: YA-401 Pump High Bearing Vibration Shutdown: VAH-401A Pump High Shaft Vibration Shutdown: VAH-401B Pump High Temperature Shutdown: TAH-401 Pump High Discharge Pressure Shutdown: PAH-402B Percolation Pond High Level Shutdown: LAH-151B Deep Injection Flow Control Valve Fail: YA-400 b. Derived: Well Low Level: LAL-401 Pump High Discharge Pressure Alarm: PAH-402A High/Low Flow: FAH/FAL-406 Percolation Pond High Level Alarm: LAH-151A Isolation Valve Fail (Fail to Open/Close): YA-410, -420 c. Instrument Analog Signal Out of Range: Level: LA-401 Pressure: PA-402, DPA-150 Flow: FA-406

C. Pump Control: The pump can be started in one of three ways: 1. Local Manual: At the VFD (LOR switch at VFD in LOCAL)

a. Speed shall be manually controlled at the VFD keypad. 2. Remote Manual: At the Electrical Building HMI, local well HMI, or SCADA HMI (LOR

switch at VFD in REMOTE) a. Placing the pump HOA switch on the HMI display in the HAND position initiates

the change from injection mode to backwash mode. b. After initiation of backwash mode is complete (isolation valves changed, as

described in paragraph D), the pump starts if the pump is permitted and not failed. c. Speed shall be controlled manually at the HMI (manual speed entry to sliding scale

bar) 3. Automatic: By the Electrical Building PLC (LOR switch at VFD in REMOTE)

a. Backwash pump starts when initiated by its weekly schedule. The backwash for each well shall run on a weekly schedule. The pump shall ramp up to a flow set point or an automated flow rate modulation based on well level as described in Paragraph E. The pump run time and schedule shall be configurable.

b. Speed shall be adjusted based on a PID loop to maintain the current setpoint. c. Control valve sequence shall be initiated upon pump call to run as described in

Paragraph D, below.

1668012*05 INJECTION WELL FACILITIES – PHASE 3

40 60 20 - 13 Control Strategies October 6th, 2020

D. Control Valve Sequence: Under backwash operations the backwash isolation valve shall

be fully opened and the injection isolation valve shall be fully closed before the backwash pump is called to start. The valves shall open and close based on the sequences below. 1. Valve sequencing: The injection flow control valve shall be called to close. After the

injection flow control valve is closed, the injection isolation valve shall be called to close. After the injection isolation valve is closed, the backwash isolation valve shall be called to open.

2. Pump start permissives: The backwash pump shall not start under the following conditions: a. The backwash isolation valve is not open (initiate a backwash valve alarm) b. The injection isolation valve or injection flow control valve is not closed (initiate an

injection valve alarm) c. One of the other backwash pumps is running. d. The well water level is below a configurable setpoint. e. The percolation basin water level is above a configurable setpoint. f. Pump has been started 3 times within the last hour.

3. Initiate backwash mode: The VFD shall start at minimum speed and the backwash timer shall start (PLC timer, with secured override in the HMI). The PLC shall monitor the backwash pump RUN status. If no RUN condition is detected, the PLC shall initiate an alarm and backwash pump shutdown. The VFD shall maintain minimum speed until a stable flow is established.

4. Pump flow ramp-up (after pump call to run): Once stable flow is established at minimum speed, pump flow shall be increased to the flow setpoint, based on a configurable ramp-up flow schedule. At the desired flow set point, the pump speed shall be maintained based on PID loop control as described in paragraph E.

5. Pump call to stop: When the pump is called to stop, the pump speed shall be reduced until the pump is stopped (pump speed is 0%). The backwash isolation valve shall be closed. After the backwash isolation valve is fully closed, the injection isolation valve shall be called to open after an adjustable time delay. If the backwash isolation valve does not close or the injection isolation valve does not open, a valve alarm shall be initiated.

E. Backwash Pump Automatic Speed Control: The PLC shall adjust the speed of the

backwash pump using PID loop controls to maintain the current setpoint. Automatic speed control shall be based on a single flow setpoint for initial operation. Control setting shall be selectable at the HMI. 1. Flow setpoint control: The flow setpoint shall be preset in the HMI. The PLC shall

initiate a pump call to start. The PLC shall initiate the valve control sequence as described in paragraph D. The PLC shall adjust the pump speed using PID loop control to maintain the desired flow. The flow rate shall have an adjustable deadband setpoint. The flow shall be monitored by a flowmeter on the backwash to percolation basin pipeline.

2. Well level control: If, during the flow setpoint control backwash operation, the well level falls below a configurable setpoint, the backwash control shall change to an automated flow rate modulation. The PLC shall adjust the pump speed using PID loop control to maintain the desired well level. The well level shall have an adjustable deadband setpoint. The flow shall be monitored by a flowmeter at the pump discharge.

F. Backwash Pump Shutdown: The backwash pump shutdown sequence shall be initiated

when any of the conditions listed below occur during the pump startup sequence or during normal operations. The shutdown sequence shall start after an adjustable time delay.

Control Strategies October 6th, 2020

40 60 20 - 14 1668012*05 INJECTION WELL FACILITIES,

PHASE 3

1. VFD Fail (contact closure at VFD). On a VFD Fail condition, the PLC shall attempt to reset and restart the pump. The number of attempts shall be adjustable at the HMI. A VFD Fail alarm shall be initiated to alert the Operator of a VFD lockout.

2. Emergency Stop (pushbutton switch located at each well). On an E-stop condition, the PLC shall initiate control valve sequence as described in paragraph D. The pump shall not restart until the alarm is cleared at the VFD.

3. High pressure, as measured by the pressure transmitter on the main line. High pressure shutdown setpoint shall be adjustable at the HMI.

4. High pressure, as indicated by the pressure switch on the pump discharge. The pressure switch shall be hard-wired to the VFD for pump shutdown at the VFD. The PLC shall initiate control valve sequence as described in paragraph D when the pump is stopped.

5. Low flow, as measured by the flowmeter on the backwash line. Low flow shutdown setpoint shall be adjustable at the HMI. The backwash pump shall be restarted manually by operator input.

6. Low low well water level, as measured by the well level transmitter. Low low well water level shutdown setpoint shall be adjustable at the HMI. The backwash pump shall be restarted manually by operator input.

7. High high percolation basin water level, as measured by the percolation pond level transmitter. High high water level setpoint shall be adjustable at the HMI. The backwash pump shall be restarted manually by operator input.

8. High high percolation basin water level, as indicated by the percolation pond level switch (normally closed contact open at VFD). Percolation pond high high level shall be hard-wired to the VFD for shutdown at the VFD. The PLC shall initiate control valve sequence as described in paragraph D when the pump is stopped. The pump shall not restart until the alarm is cleared at the VFD.

9. Motor overtemperature (normally closed contact open at VFD). Motor overtemperature shall be hard-wired to the VFD for shutdown at the VFD. The PLC shall initiate control valve sequence as described in paragraph D when the pump is stopped. The pump shall not restart until the alarm is cleared at the VFD.

10. Motor high vibration (normally closed contact open at VFD). Motor high vibration shall be hard-wired to the VFD for shutdown at the VFD. The PLC shall initiate control valve sequence as described in paragraph D when the pump is stopped. The pump shall not restart until the alarm is cleared at the VFD.

11. Overload (normally closed contacts open at VFD). Motor overload shall be hard-wired to the VFD for shutdown at the VFD. The PLC shall initiate control valve sequence as described in paragraph D when the pump is stopped. The pump shall not restart until the alarm is cleared at the VFD.

G. Loss of Power: When a loss of power occurs during the pump startup sequence or

backwash operation, the PLC shall not call the pump to start (restart the pump). A pump fail alarm shall be indicated until the backwash isolation valve opens and the injection isolation valve closes. The pump fail alarm shall be cleared when the valves return to normal condition before a pump call to start. 1. Upon loss of power, the flow control valve shall fail in the closed position.

END OF CONTROL STRATEGIES

4

3

2

1

0

0

USE OF DOCUMENTS

25mm

SCALES

1"

CHECKED

DESIGNED

DRAWN

0

Kennedy/Jenks Consultants

DATE

SHEET

FILE NAME

JOB NO.

D E F G HA B C

IF THIS BAR IS NOT

DIMENSION SHOWN,

ADJUST SCALES

ACCORDINGLY.

THIS DOCUMENT, INCLUDING THE INCORPORATED

DESIGNS, IS AN INSTRUMENT OF SERVICE FOR THIS

PROJECT AND SHALL NOT BE USED FOR ANY OTHER

PROJECT WITHOUT THE WRITTEN AUTHORIZATION

OF KENNEDY/JENKS CONSULTANTS.

NO. REVISION DATE BY

1668012.05

PURE WATER MONTEREY

GROUNDWATER REPLENISHMENT PROJECT

INJECTION WELL FACILITIES

PHASE 3

SEPTEMBER 2020

M:\K

JC

I\0

3-D

IW

-3

\D

ra

win

gs\1

66

80

12

05

-C

-0

01

.d

wg

9

/3

0/2

02

0 A

Ste

rb

en

z

(831) 883-4848Salinas, CA 93907-2348

3 Quail Run Circle, Suite 101

9/1/2020

CJM

CJM

AAS

1 ADDENDUM NO. 1 09/25/2020 AAS

2 ADDENDUM NO. 2 10/1/2020 AAS

SWPPP DETAILS 2

C-003

166801205-C-001.DWG

M:\K

JC

I\03-D

IW

-3\D

raw

in

gs\166801205-C

-001.d

wg

, C

003, 9/30/2020 10:32:07 A

M

NTS

TRANSMITTER

(LOCATED AT FLOW SENSOR)

120 VAC POWER

4-20 mA OUTPUT

NOTES:

1. FLOW TUBE TO BE 5 STRAIGHT PIPE DIAMETERS UPSTREAM AND

TWO PIPE DIAMETERS DOWNSTREAM.

2. PROVIDE GROUNDING RINGS AS REQUIRED.

3. 120VAC POWER TO TRANSMITTER AND 4-20 mA OUTPUT SIGNAL

SHALL BE ROUTED THROUGH SEPARATES JUNCTION BOXES.

TRANSMITTER INSTALLATION DETAIL

MAGNETIC FLOWMETER AND

1

-

NOTE:

1. SUPPORT PRESSURE GAUGE AND PRESSURE

SWITCH WITH UNISTRUT CHANNEL. - NOT SHOWN

2. PRESSURE INDICATE TRANSMIT SWITCH SIMILAR.

NTS

PRESSURE INSTRUMENT DETAIL2

-

NTS

WELL LEVEL DETAIL3

-

SIGNAL CONDUIT

LEVEL TRANSMITTER

TERMINATION

NEMA 4X, SS 304 JB

FITTINGS TO

PREVENT CABLE

SLIPPING AND 3/4"

LIQUID TIGHT

CONDUIT

REFER TO DETAIL 17

ON ELECTRICAL

SHEET E-003 FOR

SUPPORT AND

MOUNTING

MOTOR

TERMINATION

NEMA 4X,

SS 304 JB

FLEX

CONDUIT

SOUND TUBE

SEE MECHANICAL

SHEET M-004

DETAIL 1

INSTALL SUBMERSIBLE

LEVEL TRANSMITTER

IN SOUNDING TUBE

NOTES:

1. INSTALL JUNCTION BOXES

PER DETAIL 4 ON SHEET

E-002.

3/16

PRESSURE

TRANSMITTER

PRESSURE SWITCH

1" x 1/2" GALV STEEL BUSHING

1" NPT THREAD-O-LET

PIPE

1/2" PULSATION DAMPENER (TYP. OF 3)

1/2" TYPE 316 STAINLESS STEEL

BALL VALVE (TYP. OF 3)

4-20mA

OUTPUT

PRESSURE GAUGE

TYPE 316 STAINLESS

STEEL PIPE AND FITTING

GALV STEEL

DIELETRIC NIPPLE

4

3

2

1

0

0

USE OF DOCUMENTS

25mm

SCALES

1"

CHECKED

DESIGNED

DRAWN

0

DATE

SHEET

FILE NAME

JOB NO.

D E F G HA B C

IF THIS BAR IS NOT

DIMENSION SHOWN,

ADJUST SCALES

ACCORDINGLY.

THIS DOCUMENT, INCLUDING THE INCORPORATED

DESIGNS, IS AN INSTRUMENT OF SERVICE FOR THIS

PROJECT AND SHALL NOT BE USED FOR ANY OTHER

PROJECT WITHOUT THE WRITTEN AUTHORIZATION

OF KENNEDY/JENKS CONSULTANTS.

NO. REVISION DATE BY

1668012.05

PURE WATER MONTEREY

GROUNDWATER REPLENISHMENT PROJECT

INJECTION WELL FACILITIES

PHASE 3

SEPTEMBER 2020

9/4/20

SLS

JMO

JRM

1 ADDENDUM NO. 2 10/2/2020 JMO

INSTRUMENTATION

STANDARD DETAILS

I-002

1668012.05-I-002.dwg

pw

:\\kjce-pw

.bentley.com

:kjce-pw

\D

ocum

ents\C

lients\M

onterey R

egional W

ater P

ollution C

ontrol A

gency\P

rojects\D

IW

-3 F

acilities_1668012.05\10-D

esign\10.06-D

raw

ings\Instrum

entation\1668012.05-I-002.dw

g

No. E15453

Exp. 6/30/21

RE

G

I

S

T

E

R

E

D

P

R

O

FESS

IO

N

A

L

E

N

G

I

N

E

ER

S

T

A

T

E

O

F

CAL

I

F

O

R

N

I

A

E

L

E

C

T R

I

C

A

L

SA

N

D

Y

SC

H

U

L

E

R

1

1

AutoCAD SHX Text
CS06S
AutoCAD SHX Text
CS08S
AutoCAD SHX Text
CS06S
AutoCAD SHX Text
CS08S
AutoCAD SHX Text
CS06S
AutoCAD SHX Text
CS08S
AutoCAD SHX Text
CS06S
AutoCAD SHX Text
CS08S
AutoCAD SHX Text
CS06S
AutoCAD SHX Text
CS08S
AutoCAD SHX Text
CS06S
AutoCAD SHX Text
CS08S

M

HPU-300

P-300

FCV-300

DIW-3

DEEP INJECTION

WELL

(E)

RADIO

PCP-MGI

MOV-310

480V

PO

SIT

IO

N

LO

CA

L / R

EM

OT

E

OP

EN

/C

LO

SE

RIO

DIW 3

EXISTING VFD LOCATED IN

ELECTRICAL BUILDING

4160V

240V

001

SIK

SP

ENTRY

001

SI

%

001

YI

READY

001

YA

FAIL

001

HS

S/S

S/S

001

YY

001

SC

MOV-310

BW

CAV

4160V

FCV-310

FCV-320

ETHERNET

101

YI

PUMP 1

RUN

101

YI

201

YI

PUMP 2

RUN

201

YI

PW

001

YI

RUN

001

HS

100

YA

ESTOP

100

YA

480V

I-005

TO PERCOLATION

BASIN

I-005 / C

SUPPLY FROM

AWPF

M

120V

MOV-320

PW

PW

MOV-320

PO

SIT

IO

N

LO

CA

L / R

EM

OT

E

OP

EN

/C

LO

SE

480V

ET

HE

RN

ET

120V

480V

310A

HS

START/

STOP

310A

HS

310

ZT

VALVE

POSITION

310

ZT

310B

HS

L/R

310B

HS

320A

HS

START/

STOP

320A

HS

320

ZT

VALVE

POSITION

320

ZT

320B

HS

L/R

320B

HS

301

LI

DIW3

LEVEL

301

LT

302

PI

BF

PRES

302

PIT

302

YA

PRES

ALARM

302

PSH

304

FI

INJEC

FLOW

304

FIT

306

FI

BF

FLOW

306

FIT

300

VC

300

VC

MOV 310MOV 320

301A

TIT

RTD

TEMP

301A

VAH

301B

VAH

SHAFT

VIBR

301B

VAH

301A

VAH

301A

TIT

300

YZA

CP

INTR

300

YZA

HPU

CONTROL

SETPOINT

OVERRIDE

301A

V I

301B

V I

SHAFT

VIBR

301B

V I

301A

V I

BEARING

VIBR

BEARING

VIBR

301B

TIT

RTD

TEMP

301B

TIT

301C

TIT

RTD

TEMP

301C

TIT

301D

TIT

RTD

TEMP

301D

TIT

301E

TIT

RTD

TEMP

301E

TIT

301F

TIT

RTD

TEMP

301F

TIT

301G

TIT

RTD

TEMP

301G

TIT

301H

TIT

RTD

TEMP

301H

TIT

310

YSC

SPEED

CONTROL

310

YSC

320

YSC

SPEED

CONTROL

320

YSC

321

YTAH

HIGH TEMP

ALARM

321

YTAH

300

ZT

300

ZT

300

YSC

300

YSC

3R VALVE

SPEED

CONTROL

3R VALVE

POSITION

306

FQI

TOTAL

FLOW

304

FQI

TOTAL

FLOW

4

3

2

1

0

0

USE OF DOCUMENTS

25mm

SCALES

1"

CHECKED

DESIGNED

DRAWN

0

DATE

SHEET

FILE NAME

JOB NO.

D E F G HA B C

IF THIS BAR IS NOT

DIMENSION SHOWN,

ADJUST SCALES

ACCORDINGLY.

THIS DOCUMENT, INCLUDING THE INCORPORATED

DESIGNS, IS AN INSTRUMENT OF SERVICE FOR THIS

PROJECT AND SHALL NOT BE USED FOR ANY OTHER

PROJECT WITHOUT THE WRITTEN AUTHORIZATION

OF KENNEDY/JENKS CONSULTANTS.

NO. REVISION DATE BY

1668012.05

PURE WATER MONTEREY

GROUNDWATER REPLENISHMENT PROJECT

INJECTION WELL FACILITIES

PHASE 3

SEPTEMBER 2020

9/4/20

SLS

JMO

JRM

1 ADDENDUM NO. 1 9/25/2020 JMO

2 ADDENDUM NO. 2 10/2/2020 JMO

PROCESS AND INSTRUMENTATION DIAGRAM

DEEP INJECTION WELL #3

I-009

1668012.05-I-009.dwg

pw

:\\kjce-pw

.bentley.com

:kjce-pw

\D

ocum

ents\C

lients\M

onterey R

egional W

ater P

ollution C

ontrol A

gency\P

rojects\D

IW

-3 F

acilities_1668012.05\10-D

esign\10.06-D

raw

ings\Instrum

entation\1668012.05-I-009.dw

g

No. E15453

Exp. 6/30/21

RE

G

I

S

T

E

R

E

D

P

R

O

FESS

IO

N

A

L

E

N

G

I

N

E

ER

S

T

A

T

E

O

F

CAL

I

F

O

R

N

I

A

E

L

E

C

T R

I

C

A

L

SA

N

D

Y

SC

H

U

L

E

R

2

2

AutoCAD SHX Text
M
AutoCAD SHX Text
LT
AutoCAD SHX Text
301
AutoCAD SHX Text
M
AutoCAD SHX Text
FE
AutoCAD SHX Text
306
AutoCAD SHX Text
FIT
AutoCAD SHX Text
306
AutoCAD SHX Text
PIT
AutoCAD SHX Text
302
AutoCAD SHX Text
PSH
AutoCAD SHX Text
302
AutoCAD SHX Text
M
AutoCAD SHX Text
ZT
AutoCAD SHX Text
310
AutoCAD SHX Text
HS
AutoCAD SHX Text
310B
AutoCAD SHX Text
L/R
AutoCAD SHX Text
HS
AutoCAD SHX Text
310A
AutoCAD SHX Text
S/S
AutoCAD SHX Text
VT
AutoCAD SHX Text
301A
AutoCAD SHX Text
ZA
AutoCAD SHX Text
300
AutoCAD SHX Text
TSH
AutoCAD SHX Text
321
AutoCAD SHX Text
VT
AutoCAD SHX Text
301B
AutoCAD SHX Text
TIT
AutoCAD SHX Text
301A
AutoCAD SHX Text
TIT
AutoCAD SHX Text
301B
AutoCAD SHX Text
HS
AutoCAD SHX Text
300
AutoCAD SHX Text
ESTOP
AutoCAD SHX Text
TIT
AutoCAD SHX Text
301C
AutoCAD SHX Text
TIT
AutoCAD SHX Text
301D
AutoCAD SHX Text
TIT
AutoCAD SHX Text
301E
AutoCAD SHX Text
TIT
AutoCAD SHX Text
301F
AutoCAD SHX Text
TIT
AutoCAD SHX Text
301G
AutoCAD SHX Text
TIT
AutoCAD SHX Text
301H
AutoCAD SHX Text
M
AutoCAD SHX Text
FIT
AutoCAD SHX Text
304
AutoCAD SHX Text
FE
AutoCAD SHX Text
304
AutoCAD SHX Text
ZT
AutoCAD SHX Text
320
AutoCAD SHX Text
HS
AutoCAD SHX Text
320B
AutoCAD SHX Text
L/R
AutoCAD SHX Text
HS
AutoCAD SHX Text
320A
AutoCAD SHX Text
S/S
AutoCAD SHX Text
I
AutoCAD SHX Text
I
AutoCAD SHX Text
PI
AutoCAD SHX Text
302

M

HPU-400

P-400

FCV-400

DIW-4

DEEP INJECTION

WELL

(E)

RADIO

PCP-MGI

MOV-410

480V

PO

SIT

IO

N

LO

CA

L / R

EM

OT

E

OP

EN

/C

LO

SE

RIO

DIW 4

EXISTING VFD LOCATED IN

ELECTRICAL BUILDING

4160V

240V

MOV-410

BW

CAV

4160V

FCV-410

FCV-420

ETHERNET

PW

480V

I-005

TO PERCOLATION

BASIN

I-005 / C

SUPPLY FROM

AWPF

M

120V

MOV-420

PW

PW

MOV-320

PO

SIT

IO

N

LO

CA

L / R

EM

OT

E

OP

EN

/C

LO

SE

480V

ET

HE

RN

ET

120V

480V

410A

HS

START/

STOP

410A

HS

410

ZT

VALVE

POSITION

410

ZT

410B

HS

L/R

410B

HS

420A

HS

START/

STOP

420A

HS

420

ZT

VALVE

POSITION

420

ZT

420B

HS

L/R

420B

HS

401

LI

DIW4

LEVEL

401

LT

402

PI

BF

PRES

402

PIT

402

YA

PRES

ALARM

402

PSH

404

FI

INJEC

FLOW

404

FIT

406

FI

BF

FLOW

406

FIT

400

VC

400

VC

MOV 410MOV 420

401A

TIT

RTD

TEMP

401A

VAH

401B

VAH

SHAFT

VIBR

401B

VAH

401A

VAH

401A

TIT

400

YZA

CP

INTR

400

YZA

HPU

CONTROL

SETPOINT

OVERRIDE

401A

V I

401B

V I

SHAFT

VIBR

401B

V I

401A

V I

BEARING

VIBR

BEARING

VIBR

401B

TIT

RTD

TEMP

401B

TIT

401C

TIT

RTD

TEMP

401C

TIT

401D

TIT

RTD

TEMP

401D

TIT

401E

TIT

RTD

TEMP

401E

TIT

401F

TIT

RTD

TEMP

401F

TIT

401G

TIT

RTD

TEMP

401G

TIT

401H

TIT

RTD

TEMP

401H

TIT

410

YSC

SPEED

CONTROL

410

YSC

420

YSC

SPEED

CONTROL

420

YSC

421

YTAH

HIGH TEMP

ALARM

421

YTAH

400

ZT

400

ZT

400

YSC

400

YSC

3R VALVE

SPEED

CONTROL

3R VALVE

POSITION

431

AI

TOTAL CHLORINE

LEVEL

431

AI

CHLORINE ANALYZER STATION

AS-430

120V

432A

AI

PH

432A

AI

432B

AI

TEMP

432B

AI

433

AI

TOTAL CHLORINE

LEVEL

433

AI

434A

AI

PH

434A

AI

434B

AI

TEMP

434B

AI

I-004

TO INJECTION

WELLS

I-005

TO PERCOLATION

BASIN

SW

406

FQI

TOTAL

FLOW

404

FQI

TOTAL

FLOW

4

3

2

1

0

0

USE OF DOCUMENTS

25mm

SCALES

1"

CHECKED

DESIGNED

DRAWN

0

DATE

SHEET

FILE NAME

JOB NO.

D E F G HA B C

IF THIS BAR IS NOT

DIMENSION SHOWN,

ADJUST SCALES

ACCORDINGLY.

THIS DOCUMENT, INCLUDING THE INCORPORATED

DESIGNS, IS AN INSTRUMENT OF SERVICE FOR THIS

PROJECT AND SHALL NOT BE USED FOR ANY OTHER

PROJECT WITHOUT THE WRITTEN AUTHORIZATION

OF KENNEDY/JENKS CONSULTANTS.

NO. REVISION DATE BY

1668012.05

PURE WATER MONTEREY

GROUNDWATER REPLENISHMENT PROJECT

INJECTION WELL FACILITIES

PHASE 3

SEPTEMBER 2020

9/4/20

SLS

JMO

JRM

1 ADDENDUM NO. 1 9/25/2020 JMO

2 ADDENDUM NO. 2 10/2/2020 JMO

PROCESS AND INSTRUMENTATION DIAGRAM

DEEP INJECTION WELL #4

I-010

1668012.05-I-010.dwg

pw

:\\kjce-pw

.bentley.com

:kjce-pw

\D

ocum

ents\C

lients\M

onterey R

egional W

ater P

ollution C

ontrol A

gency\P

rojects\D

IW

-3 F

acilities_1668012.05\10-D

esign\10.06-D

raw

ings\Instrum

entation\1668012.05-I-010.dw

g

No. E15453

Exp. 6/30/21

RE

G

I

S

T

E

R

E

D

P

R

O

FESS

IO

N

A

L

E

N

G

I

N

E

ER

S

T

A

T

E

O

F

CAL

I

F

O

R

N

I

A

E

L

E

C

T R

I

C

A

L

SA

N

D

Y

SC

H

U

L

E

R

2

2

AutoCAD SHX Text
M
AutoCAD SHX Text
LT
AutoCAD SHX Text
401
AutoCAD SHX Text
M
AutoCAD SHX Text
FE
AutoCAD SHX Text
406
AutoCAD SHX Text
FIT
AutoCAD SHX Text
406
AutoCAD SHX Text
PIT
AutoCAD SHX Text
402
AutoCAD SHX Text
PSH
AutoCAD SHX Text
402
AutoCAD SHX Text
M
AutoCAD SHX Text
ZT
AutoCAD SHX Text
410
AutoCAD SHX Text
HS
AutoCAD SHX Text
410B
AutoCAD SHX Text
L/R
AutoCAD SHX Text
HS
AutoCAD SHX Text
410A
AutoCAD SHX Text
S/S
AutoCAD SHX Text
VT
AutoCAD SHX Text
401A
AutoCAD SHX Text
ZA
AutoCAD SHX Text
400
AutoCAD SHX Text
TSH
AutoCAD SHX Text
421
AutoCAD SHX Text
VT
AutoCAD SHX Text
401B
AutoCAD SHX Text
TIT
AutoCAD SHX Text
401A
AutoCAD SHX Text
TIT
AutoCAD SHX Text
401B
AutoCAD SHX Text
HS
AutoCAD SHX Text
400
AutoCAD SHX Text
ESTOP
AutoCAD SHX Text
TIT
AutoCAD SHX Text
401C
AutoCAD SHX Text
TIT
AutoCAD SHX Text
401D
AutoCAD SHX Text
TIT
AutoCAD SHX Text
401E
AutoCAD SHX Text
TIT
AutoCAD SHX Text
401F
AutoCAD SHX Text
TIT
AutoCAD SHX Text
401G
AutoCAD SHX Text
TIT
AutoCAD SHX Text
401H
AutoCAD SHX Text
M
AutoCAD SHX Text
FIT
AutoCAD SHX Text
404
AutoCAD SHX Text
FE
AutoCAD SHX Text
404
AutoCAD SHX Text
ZT
AutoCAD SHX Text
420
AutoCAD SHX Text
HS
AutoCAD SHX Text
420B
AutoCAD SHX Text
L/R
AutoCAD SHX Text
HS
AutoCAD SHX Text
420A
AutoCAD SHX Text
S/S
AutoCAD SHX Text
AIT
AutoCAD SHX Text
431
AutoCAD SHX Text
AE
AutoCAD SHX Text
432
AutoCAD SHX Text
PH/TEMP
AutoCAD SHX Text
AE
AutoCAD SHX Text
431
AutoCAD SHX Text
CL
AutoCAD SHX Text
AIT
AutoCAD SHX Text
432
AutoCAD SHX Text
AIT
AutoCAD SHX Text
433
AutoCAD SHX Text
AE
AutoCAD SHX Text
434
AutoCAD SHX Text
PH/TEMP
AutoCAD SHX Text
AE
AutoCAD SHX Text
433
AutoCAD SHX Text
CL
AutoCAD SHX Text
AIT
AutoCAD SHX Text
434
AutoCAD SHX Text
I
AutoCAD SHX Text
I
AutoCAD SHX Text
PI
AutoCAD SHX Text
402

STORMWATER POLLUTION PREVENTION PLAN

for

Pure Water Monterey Groundwater Replenishment Project Injection Well Field, Phase 3

Seaside, California

RISK LEVEL 1

Legally Responsible Person (LRP): Paul Sciuto

General Manager

Monterey One Water

5 Harris Court, Building D, Monterey, CA 93940

Prepared for: Monterey One Water

5 Harris Court, Building D, Monterey, CA 93940

Project Address: Seaside, California

SWPPP Prepared by:

Schaaf and Wheeler Consulting Civil Engineers 3 Quail Run Circle, Suite 101,

Salinas, CA 93907 Caitlin J. Gilmore, PE, QSD

SWPPP Preparation Date

October 1, 2020

Estimated Project Dates:

Start of Construction September 2020 Completion of Construction June 2021

PWM Well Field Phase 3 2 August 2020

PWM Well Field Phase 3 i August 2020

Table of Contents

Table of Contents ........................................................................................................................... i

SWPPP Certification Statement by Qualified SWPPP Developer (QSD) ............................... 1

Discharger or Legally Responsible Person ................................................................................. 2

Amendment Log ............................................................................................................................ 3

Section 1 SWPPP Requirements .............................................................................................. 4

1.1 Introduction ..................................................................................................................... 4

1.2 Permit Registration Documents ...................................................................................... 6

1.3 SWPPP Availability and Implementation ....................................................................... 7

1.4 SWPPP Amendments...................................................................................................... 7

1.5 Retention of Records....................................................................................................... 8

1.6 Required Non-Compliance Reporting ............................................................................ 8

1.7 Annual Report ................................................................................................................. 9

1.8 Changes to Permit Coverage ........................................................................................... 9

1.9 Construction Site Monitoring Program ........................................................................... 9

1.10 Notice of Termination .................................................................................................... 9

1.11 Contractor Activities Location Map ............................................................................ 10

Section 2 Project Information ................................................................................................ 11

2.1 Project and Site Description.......................................................................................... 11

2.1.1 Site Description ......................................................................................................... 11

2.1.2 Existing Conditions ................................................................................................... 11

2.1.3 Existing Drainage...................................................................................................... 11

2.1.4 Geology and Groundwater ........................................................................................ 12

2.1.5 Project Description.................................................................................................... 12

2.1.6 Developed Condition ................................................................................................ 12

2.2 Permits and Governing Documents .............................................................................. 12

2.3 Stormwater Run-On from Offsite Areas ....................................................................... 13

2.4 Findings of the Construction Site Sediment and Receiving Water Risk Determination

13

2.5 Construction Schedule .................................................................................................. 15

2.6 Potential Construction Activity and Pollutant Sources ................................................. 15

2.7 Identification of Non-Stormwater Discharges .............................................................. 16

PWM Well Field Phase 3 ii August 2020

2.8 Required Site Map Information .................................................................................... 17

Section 3 Best Management Practices ................................................................................... 18

3.1 Schedule for BMP Implementation .............................................................................. 18

3.2 Erosion and Sediment Control ...................................................................................... 19

3.2.1 Erosion Control ......................................................................................................... 20

3.2.2 Sediment Controls ..................................................................................................... 22

3.2.3 Tracking Control ....................................................................................................... 25

3.2.4 Wind Erosion Control ............................................................................................... 26

3.3 Non-Stormwater Controls and Waste and Materials Management .............................. 27

3.3.1 Non-Stormwater Controls ......................................................................................... 27

3.3.2 Materials Management and Waste Management ...................................................... 33

3.4 Post construction Stormwater Management Measures ................................................. 42

Section 4 BMP Inspection, Maintenance, and Rain Event Action Plans ........................... 43

4.1 BMP Inspection and Maintenance ................................................................................ 43

4.2 Rain Event Action Plans ............................................................................................... 43

Section 5 Training ................................................................................................................... 44

Section 6 Responsible Parties and Operators ....................................................................... 45

6.1 Responsible Parties ....................................................................................................... 45

6.2 Contractors List ............................................................................................................. 46

Section 7 Construction Site Monitoring Program ................................................................ 48

7.1 Purpose ...................................................................................................................... 48

7.2 Applicability of Permit Requirements ...................................................................... 48

7.3. Weather and Rain Event Tracking ............................................................................ 48

7.3.1 Weather Tracking.................................................................................................. 48

7.3.2 Rain Gauges .......................................................................................................... 49

7.4 Monitoring Locations................................................................................................ 49

7.5 Safety and Monitoring Exemptions .......................................................................... 49

7.6 Visual Monitoring ..................................................................................................... 49

7.6.1 Routine Observations and Inspections .................................................................. 50

7.6.1.1 Routine BMP Inspections ............................................................................. 50

7.6.1.2 Non-Stormwater Discharge Observations .................................................... 50

7.6.2 Rain-Event Triggered Observations and Inspections ........................................... 51

7.6.2.1 Visual Observations Prior to a Forecasted Qualifying Rain Event............... 51

PWM Well Field Phase 3 iii August 2020

7.6.2.2 BMP Inspections During an Extended Storm Event..................................... 51

7.6.2.3 Visual Observations Following a Qualifying Rain Event............................. 51

7.6.3 Visual Monitoring Procedures .............................................................................. 51

7.6.4 Visual Monitoring Follow-Up and Reporting....................................................... 52

7.6.5 Visual Monitoring Locations ................................................................................ 52

7.7 Water Quality Sampling and Analysis ...................................................................... 53

7.7.1 Sampling and Analysis Plan for Non-Visible Pollutants in Stormwater Runoff

Discharges ......................................................................................................................... 53

7.7.1.1 Sampling Schedule........................................................................................ 55

7.7.1.2 Sampling Locations ...................................................................................... 55

7.7.1.3 Monitoring Preparation ................................................................................. 56

7.7.1.4 Analytical Constituents ................................................................................. 57

7.7.1.5 Sample Collection ......................................................................................... 57

7.7.1.6 Sample Analysis............................................................................................ 57

7.7.1.7 Data Evaluation and Reporting ..................................................................... 59

7.7.2 Sampling and Analysis Plan for pH and Turbidity in Stormwater Runoff

Discharges ......................................................................................................................... 59

7.7.3 Sampling and Analysis Plan for pH, Turbidity, and SSC in Receiving Water ..... 59

7.7.4 Sampling and Analysis Plan for Non-Stormwater Discharges ............................. 59

7.7.5 Sampling and Analysis Plan for Other Pollutants Required by the Regional Water

Board 61

7.7.6 Training of Sampling Personnel ........................................................................... 61

7.7.7 Sample Collection and Handling .......................................................................... 61

7.7.7.1 Sample Collection ......................................................................................... 61

7.7.7.2 Sample Handling ........................................................................................... 62

7.7.7.3 Sample Documentation Procedures .............................................................. 63

7.8 Active Treatment System Monitoring ...................................................................... 63

7.9 Bioassessment Monitoring ........................................................................................ 63

7.10 Watershed Monitoring Option .................................................................................. 63

7.11 Quality Assurance and Quality Control .................................................................... 63

7.11.1 Field Logs ......................................................................................................... 64

7.11.2 Clean Sampling Techniques ............................................................................. 64

7.11.3 Chain of Custody .............................................................................................. 64

PWM Well Field Phase 3 iv August 2020

7.11.4 QA/QC Samples................................................................................................ 64

7.11.4.1 Field Duplicates .......................................................................................... 64

7.11.4.2 Equipment Blanks ........................................................................................ 65

7.11.4.3 Field Blanks.................................................................................................. 65

7.11.4.4 Travel Blanks ............................................................................................... 65

7.11.5 Data Verification ............................................................................................... 65

7.12 Records Retention ..................................................................................................... 66

CSMP Attachment 1: Weather Reports................................................................................. 67

CSMP Attachment 2: Monitoring Records ........................................................................... 69

CSMP Attachment 3: Example Forms ................................................................................... 71

CSMP Attachment 4: Field Meter Instructions .................................................................... 81

CSMP Attachment 5: Supplemental Information................................................................. 83

Section 8 References ................................................................................................................ 85

Appendix A: Calculations ...................................................................................................... 86

Appendix B: Site Maps .......................................................................................................... 88

Appendix C: Permit Registration Documents....................................................................... 90

Appendix D: SWPPP Amendments ....................................................................................... 92

Appendix E: Submitted Changes to PRDs ............................................................................ 95

Appendix F: Construction Schedule ..................................................................................... 97

Appendix G: Construction Activities, Materials Used, and Associated Pollutants ............. 99

Appendix H: CASQA Stormwater BMP Handbook Portal: Construction Fact Sheets .... 102

Appendix I: BMP Inspection Form ....................................................................................... 104

Appendix J: Project Specific Rain Event Action Plan Template .......................................... 112

Appendix K: Training Reporting Form .............................................................................. 114

Appendix L: Responsible Parties ........................................................................................ 116

Appendix M: Contractors and Subcontractors .................................................................... 120

Appendix N: Construction General Permit ........................................................................ 121

Appendix O: Retention of Records / Construction Records ............................................... 123

Appendix P: Agency Approvals and Miscellaneous Documents ....................................... 124

Appendix Q: Test Methods, Detection Limits, Reporting Units, Applicable NALs and NELs

125

Appendix R: Erosion Control Plans ................................................................................... 126

Appendix S: Contractor Activities Location Map .............................................................. 127

PWM Well Field Phase 3 v August 2020

PWM Well Field Phase 3 1 August 2020

SWPPP Certification Statement by Qualified SWPPP

Developer (QSD)

Project Name:

Pure Water Monterey Groundwater Replenishment Project,

Injection Well Field (PWM Well Field) Phase 3

Project Number/ID

“This Stormwater Pollution Prevention Plan and Attachments were prepared under my direction to

meet the requirements of the California Construction General Permit (SWRCB Orders No. 2009-009-

DWQ as amended by Order 2010-0014-DWQ and Order 2012-0006-DWQ). I certify that I am a

Qualified SWPPP Developer in good standing as of the date signed below.”

October 5, 2020

QSD Signature

Caitlin Gilmore, PE

Date

22060

QSD Name

Senior Project Manager, Schaaf & Wheeler

QSD Certificate Number

(415) 823-4964

Title and Affiliation

[email protected]

Telephone Number

Email

PWM Well Field 2 May 2017

Discharger or Legally Responsible Person

Approval and Certification of the Stormwater Pollution Prevention Plan

Project Name:

Pure Water Monterey Groundwater Replenishment

Project, Injection Well Field (PWM Well Field) Phase 3

Project Number/ID

“I certify under penalty of law that this document and all Attachments were prepared under my

direction or supervision in accordance with a system designed to assure that qualified personnel

properly gather and evaluate the information submitted. Based on my inquiry of the person or persons

who manage the system or those persons directly responsible for gathering the information, to the best

of my knowledge and belief, the information submitted is, true, accurate, and complete. I am aware

that there are significant penalties for submitting false information, including the possibility of fine

and imprisonment for knowing violations."

Legally Responsible Person [if organization]

Signature of [Authorized Representative of] Legally

Responsible Person or Approved Signatory

Date

Name of [Authorized Representative of] Legally

Responsible Person or Approved Signatory

Telephone Number

PWM Well Field 3 May 2017

Amendment Log

Project Name: Pure Water Monterey Groundwater Replenishment Project, Injection Well Field (PWM Well Field) Phase 3

Project Number/ID [if applicable]

Table 1.1: SWPPP Amendment Log

Amendment

No. Date

Brief Description of Amendment, include

section and page number

Prepared and Approved

By

Name:

QSD#

Name:

QSD#

Name:

QSD#

Name:

QSD#

Name:

QSD#

Name:

QSD#

Name:

QSD#

Name:

QSD#

Name:

QSD#

PWM Well Field Phase 3 4 August 2020

Section 1 SWPPP Requirements

1.1 INTRODUCTION

The Pure Water Monterey Groundwater Replenishment Project Injection Well Field (PWM Well Field)

Phase 3 comprises approximately 8.2 acres and is located in an area bounded between General

Jim Moore Boulevard, Eucalyptus Road, and Austin Road in Seaside, California. The property is

owned by the City of Seaside and is being developed by Monterey One Water and Monterey

Peninsula Water Management District (MPWMD). The projects location is shown on the Site

Map in Appendix B.

This Stormwater Pollution Prevention Plan (SWPPP) is designed to comply with California’s

General Permit for Stormwater Discharges Associated with Construction and Land Disturbance

Activities (General Permit) Order No. 2009-0009-DWQ as amended in 2010 and 2012 (NPDES

No. CAS000002) and modified by 2010-0014-DWQ and 2012-006-DWQ issued by the State

Water Resources Control Board (State Water Board).

The Contractor shall designate a Qualified SWPPP Practitioner (QSP) to implement the

provisions of the SWPPP and the Construction Site Monitoring Program (CSMP), and shall

comply with the narrative and numeric effluent standards listed below:

1. Narrative

• Storm water discharges and authorized non-storm water discharges regulated by this

General Permit shall not contain a hazardous substance equal to or in excess of

reportable quantities established in 40 C.F.R §§ 117.3 and 302.4, unless a separate

NPDES Permit has been issued to regulate those discharges.

• Dischargers shall minimize or prevent pollutants in storm water discharges and

authorized non-storm water discharges through the use of controls, structures, and

management practices that achieve BAT (Best ‘economically Available Technology)

for toxic and non-conventional pollutants and BCT (Best Conventional “pollution

control” Technology) for conventional pollutants.

2. Numeric

• Risk Level 2 dischargers are subject to a pH NAL of 6.5-8.5, and a turbidity NAL of

250 NTU.

The project is Risk Level 1 as calculated herein under section 2.4. However, Risk Level 2

requirements have been included (REAPs and NALs) for reference should the project Risk Level

change during construction.

The Contractor shall notify the Owner if the QSP is no longer associated with the work. The

Owner shall be notified within 24 hours and a qualified replacement named within 72 hours. The

replacement QSP shall meet the Permit certification requirements.

The QSP shall have the training described in Section 5 of this SWPPP and shall be listed on the

SMARTS system prior to the start of construction. The Legally Responsible Person (LRP) shall

ensure that SWPPPs for all traditional project sites are developed and amended or revised by the

Qualified SWPPP Developer (QSD).

PWM Well Field Phase 3 5 August 2020

The QSP is responsible for erosion control on the site and shall supplement the erosion control

plan shown on Construction Document where the facilities shown on the Construction

Documents are not preventing erosion. The QSP shall make corrective measures as soon as

erosion is observed and shall report these measures to the QSD by email within 24 hours.

This SWPPP has been prepared following the SWPPP Template provided on the California

Stormwater Quality Association Stormwater Best Management Practice Handbook Portal:

Construction (CASQA, 2012). In accordance with the General Permit, Section XIV, this

SWPPP is designed to address the following objectives:

• All pollutants and their sources, including sources of sediment associated with

construction, construction site erosion and other activities associated with construction

activity are controlled;

• Where not otherwise required to be under a Regional Water Quality Control Board

(Regional Water Board) permit, all non-stormwater discharges are identified and either

eliminated, controlled, or treated;

• Site BMPs are effective and result in the reduction or elimination of pollutants in

stormwater discharges and authorized non-stormwater discharges from construction

activity to the Best Available Technology/Best Control Technology (BAT/BCT)

standard; Calculations and design details as well as BMP controls for are complete and

correct, (see Appendices A and R); and

• Stabilization BMPs installed to reduce or eliminate pollutants after construction are

completed.

• Identify post-construction BMPs, which are those measures to be installed during

construction that are intended to reduce or eliminate pollutants after construction is

completed. See Section 3.4 for post –construction BMPs.

• Identify and provide methods to implement BMP inspection, visual monitoring, and

Construction Site Monitoring Program (CSMP) requirements to comply with the General

Permit.

Rain Event Action Plan (REAP)

In addition to the narrative and numeric effluent standards listed above, the discharger shall also

have the contractor’s QSP develop and implement a Rain Event Action Plan (REAP), which is

an additional Risk Level 2 requirement. A template of the REAP is included in Appendix J.

1. Additional Risk Level 2 Requirement: The discharger shall ensure a QSP develop a Rain

Event Action Plan (REAP) 48 hours prior to any likely precipitation event. A likely

precipitation event is any weather pattern that is forecast to have a 50% or greater

probability of producing precipitation in the project area. The discharger shall ensure a

QSP obtain a printed copy of precipitation forecast information from the National

Weather Service Forecast Office (e.g., by entering the zip code of the project’s location at

http://www.srh.noaa.gov/forecast).

2. The discharger shall ensure a QSP develop the REAPs for all phases of construction (i.e.,

Grading and Land Development, Streets and Utilities, Vertical Construction, Final

Landscaping and Site Stabilization).

PWM Well Field Phase 3 6 August 2020

3. The discharger shall ensure a QSP ensure that the REAP include, at a minimum, the

following site information:

a. Site Address

b. Calculated Risk Level (2 or 3)

c. Site Storm Water Manager Information including the name, company, and 24-

hour emergency telephone number

d. Erosion and Sediment Control Provider information including the name,

company, and 24-hour emergency telephone number

e. Storm Water Sampling Agent information including the name, company,

and 24-hour emergency telephone number

4. The discharger shall ensure a QSP include in the REAP, at a minimum, the following

project phase information:

a. Activities associated with each construction phase

b. Trades active on the construction site during each construction phase

c. Trade contractor information

d. Suggested actions for each project phase

5. The discharger shall ensure a QSP develop additional REAPs for project sites where

construction activities are indefinitely halted or postponed (Inactive Construction). At a

minimum, Inactive Construction REAPs must include:

a. Site Address

b. Calculated Risk Level (2 or 3)

c. Site Storm Water Manager Information including the name, company, and

24-hour emergency telephone number

d. Erosion and Sediment Control Provider information including the name,

company, and 24-hour emergency telephone number

e. Storm Water Sampling Agent information including the name, company,

and 24-hour emergency telephone number

f. Trades active on site during Inactive Construction

g. Trade contractor information

h. Suggested actions for inactive construction sites

6. The discharger shall ensure a QSP begin implementation and make the REAP available

onsite no later than 24 hours prior to the likely precipitation event.

7. The discharger shall ensure a QSP maintain onsite a paper copy of each REAP onsite in

compliance with the record retention requirements of the Special Provisions in this

General Permit.

1.2 PERMIT REGISTRATION DOCUMENTS

Required Permit Registration Documents (PRDs) shall be submitted to the State Water Board via

the Stormwater Multi Application and Report Tracking System (SMARTS) by the Legally

Responsible Person (LRP), or authorized personnel (i.e., Approved Signatory) under the

direction of the LRP. Failure to obtain coverage under this General Permit for storm water

discharges to waters of the United States is a violation of the Clean Water Act and the California

Water Code. The project-specific PRDs include:

1. Notice of Intent (NOI);

PWM Well Field Phase 3 7 August 2020

2. Risk Assessment (Construction Site Sediment and Receiving Water Risk Determination);

3. Site Map;

4. Annual Fee;

5. Signed Certification Statement (LRP Certification is provided electronically with

SMARTS PRD submittal); and

6. SWPPP.

Site Maps can be found in Appendix B. A copy of the submitted PRDs shall also be kept in

Appendix C along with the Waste Discharge Identification (WDID) confirmation.

1.3 SWPPP AVAILABILITY AND IMPLEMENTATION

The QSP shall make the SWPPP available at the construction site during working hours (see

Section 7.5 of CSMP for working hours) while construction is occurring and shall be made

available upon request by a State or Municipal inspector. When the original SWPPP is retained

by a crewmember in a construction vehicle and is not currently at the construction site, current

copies of the BMPs and map/drawing will be left with the field crew and the original SWPPP

shall be made available via a request by radio/telephone. (CGP Section XIV.C)

The SWPPP shall be implemented concurrently with the start of ground disturbing activities and

remain in effect until a Notice of Termination for the site is approved by the Regional Water

Quality Control Board.

1.4 SWPPP AMENDMENTS

The SWPPP should be revised when:

• If there is a General Permit violation.

• When there is a reduction or increase in total disturbed acreage (General Permit Section

II Part C).

• BMPs do not meet the objectives of reducing or eliminating pollutants in stormwater

discharges.

Additionally, the SWPPP shall be amended when:

• There is a change in construction or operations which may affect the discharge of

pollutants to surface waters, groundwater(s), or a municipal separate storm sewer system

(MS4);

• When there is a change in the project duration that changes the project’s risk level; or

• When deemed necessary by the QSD. All changes shall be made by the QSD as formal

amendments to the SWPPP.

The following items shall be included in each amendment:

• Who requested the amendment;

• The location of proposed change;

• The reason for change;

PWM Well Field Phase 3 8 August 2020

• The original BMP proposed, if any; and

• The new BMP proposed.

Amendment shall be logged at the front of the SWPPP and certification kept in Appendix D.

The SWPPP text shall be revised, replaced, and/or hand annotated as necessary to properly

convey the amendment. SWPPP amendments must be made by a QSD.

1.5 RETENTION OF RECORDS

The QSP is required to maintain a paper or electronic copy of all required records throughout

construction, and provide copies of these reports to the LRP when requested during the job and

at the end of the job. The LRP shall retain a copy of all required records for three years from the

date generated or the date submitted to the State Water Board or Regional Water Boards,

whichever is the latter. A copy of these records shall be maintained at the Site and within

Appendix O of this SWPPP until construction is complete. Records assisting in the determination

of compliance with the General Permit shall be made available within a reasonable time, to the

Regional Water Board, State Water Board or U.S. Environmental Protection Agency (EPA) upon

request. Requests by the Regional Water Board for retention of records for a period longer than

three years shall be adhered to.

1.6 REQUIRED NON-COMPLIANCE REPORTING

If a General Permit discharge violation occurs the QSP shall immediately notify the LRP. The

LRP shall include information on the violation with the Annual Report. Corrective measures

will be implemented immediately following identification of the discharge or written notice of

non-compliance from the Regional Water Board. Discharges and corrective actions must be

documented and include the following items:

• The date, time, location, nature of operation and type of unauthorized discharge.

• The cause or nature of the notice or order.

• The control measures (BMPs) deployed before the discharge event, or prior to receiving

notice or order.

• The date of deployment and type of control measures (BMPs) deployed after the

discharge event, or after receiving the notice or order, including additional measures

installed or planned to reduce or prevent re-occurrence.

Reporting requirements for Numeric Action Levels (NALs) exceedances are discussed in Section

7.7.2.7.

PWM Well Field Phase 3 9 August 2020

1.7 ANNUAL REPORT

The QSP is responsible for preparing certifying, and electronically submitting an Annual Report

no later than September 1st of each year. Reporting requirements are identified in Section XVI

of the General Permit and include (but are not limited to) providing a summary of :

1) Sampling and analysis results including laboratory reports, analytical methods and

reporting limits and chain of custody forms (if applicable to this Risk Level 1 site);

2) Corrective actions and compliance activities, including those not implemented;

3) Violations of the General Permit;

4) Date, time, place, and name(s) of the inspector(s) for all sampling, inspections, and field

measurement activities;

5) Visual observation and sample collection exception records; and

6) Training documentation of all personnel responsible for General Permit compliance

activities.

The LRP is responsible for certifying the Annual Report via SMARTS, and is required to retain

paper copies of all submitted documents for a period of 3 years after the Notice of Termination is

accepted.

1.8 CHANGES TO PERMIT COVERAGE

The Construction General Permit allow a permittee to reduce or increase the total acreage

covered under the General Permit when: a portion of the project is complete and/or conditions

for termination of coverage have been met; when ownership of a portion of the project is

purchased by a different entity; or when new acreage is added to the project.

Modified PRDs shall be filed electronically within 30 days of a reduction or increase in total

disturbed area if a change in permit covered acreage is to be sought. The SWPPP shall be

modified appropriately, shall be logged at the front of the SWPPP and cetrification of SWPPP

amendments are to be kept in Appendix D. Updated PRDs submitted electronically via SMARTS

can be found in Appendix E.

1.9 CONSTRUCTION SITE MONITORING PROGRAM

The QSP is to implement the Construction Site Monitoring Program (CSMP) in accordance with

the requirements found in Appendix N. The CSMP is included in this SWPPP in Section 7.

1.10 NOTICE OF TERMINATION

A Notice of Termination (NOT) must be submitted electronically by the LRP via SMARTS to

terminate coverage under the General Permit. The NOT must include a final Site Map and

representative photographs of the project site that demonstrate final stabilization has been

achieved. The NOT shall be submitted within 90 days of completion of construction. The

Regional Water Board will consider a construction site complete when the conditions of the

General Permit, Section II.D have been met and final stabilization in the form of the following is

achieved:

PWM Well Field Phase 3 10 August 2020

• The site will not pose any additional sediment discharge risk than it did prior to

construction activity.

• All construction related equipment, materials and any temporary BMPs no longer needed

are removed from the site.

• Post-construction storm water management measures are installed, and a long-term

maintenance plan that is designed for a minimum of five years has been developed.

The NOT must demonstrate through photos that the project meets all of the requirements of

Section II.D.1 of the General Permit by the 70% final cover method (no computational proof

required).

1.11 CONTRACTOR ACTIVITIES LOCATION MAP

Locations of storage areas for waste, vehicles, service, loading/unloading of materials, access

(entrance/exits) points to construction site, fueling, and water storage, water transfer for dust

control and compaction practices shall be shown on this map and updated regularly by the QSP.

All updates of the Contractor Activities Location Map shall be included in Appendix S.

PWM Well Field Phase 3 11 August 2020

Section 2 Project Information

2.1 PROJECT AND SITE DESCRIPTION

2.1.1 Site Description

The PWM Well Field site comprises approximately 8.2 acres and is located at an area bounded

by General Jim Moore Boulevard to the west, Eucalyptus Road to the north, and Austin

Road/Bureau of Land Management lands to the south and east, in Seaside, California. Phase 3 is

the development of the final two sites (Well Sites 1 and 4), which total 1.6 acres. The remaining

6.6 acres were developed during Phases 1 and 2 of the project. The property is owned by the

City of Seaside and is being developed by the Monterey One Water (M1W) and Monterey

Peninsula Water Management District (MPWMD). The project site is located approximately 2.3

miles east of the city of Sand City, and US Highway 1. The project site is located approximately

2.6 miles east of the Monterey Bay. The project is located at 36° 37' 09.62" N

121° 48' 40.39" W and is identified on the Site Map in Appendix B.

2.1.2 Existing Conditions

As of the initial date of this SWPPP, the project site is an area of dune sands with a history of

military activities due to the site formerly being used for defense purposes (former Fort Ord

lands). The project site was previously used by the United States Army for Munitions training

operations conducted at the former Fort Ord. Historic sources of contamination include remnants

of army Munitions and Explosives of Concern (MEC). Environmental cleanup activities were

conducted at this site under the Environmental Services Cooperative Agreement (ESCA)

between the Fort Ord Reuse Authority and the U.S. Army. Once these activities were completed,

the land was conveyed to the City of Seaside (City).

Phases 1 and 2 of the Project developed well sites 2 and 3 and a centrally located electrical

switchgear yard, and installed pipelines and conduits connecting these sites to existing utilities in

General Jim Moore Blvd. The Phase 2 project also deepened the existing percolation pond to

add capacity for use during backflushing of the wells.

2.1.3 Existing Drainage

The project site is gently sloped to the southwest. The elevation of the project site ranges from

300 to 450 feet above mean sea level (msl), with a 4% to 5% slope along the existing unpaved

road. Surface drainage at the site currently is limited and storm water percolates into the native

sandy soil (Dune Sands) of the area. Stormwater discharges, from the site, are not considered

direct discharges, as defined by the State Water Board into Monterey Bay. Existing site

topography, drainage patterns, and stormwater conveyance systems are shown on the Site Plan in

Appendix B.

Stormwater from the area percolates into the Salinas Valley Groundwater Basin, Seaside Sub-

Basin. The aquifer is not listed for any water quality impairment.

PWM Well Field Phase 3 12 August 2020

2.1.4 Geology and Groundwater

The site is underlain by the Seaside Groundwater Basin, which consists of a sequence of three

aquifers that overlie the Monterey Formation. The three aquifers include the deepest Santa

Margarita Aquifer, the middle Paso Robles Aquifer, and the shallowest (topmost) Dune Sands

Aquifer. The underlying soil is typically brown/yellow sand with silt or very fine grained sand

(SC/SP) up to a depth of 10 feet (based upon soil borings by (Pacific Crest Engineering, 2008,

2016). Groundwater was not encountered beneath the site up to approximately 51 feet below

ground surface. The general groundwater gradient is toward the coast (west by southwest).

2.1.5 Project Description

Project grading will occur on approximately 1.55 acres of the project, which comprises

approximately 15 percent of the total area. The limits of grading are shown on the Erosion

Control Plan in Appendix R. Grading will include both cut and fill activities, with the total

graded material estimated to be 1,500 cubic yards. No fill material will be imported during

grading activities. Graded materials are expected to be balanced onsite. Soil will be stockpiled at

locations decided upon by contractor in the field; tentative locations are shown on the Site Plan

in Appendix B. Phase 3 activities are covered under the Construction General Permit.

2.1.6 Developed Condition

Post construction surface drainage is expected to percolate into the sandy soil as it is intercepted

by the ground. A small portion of the runoff that falls on the paved areas will be collected in

drainage swales and percolated.

Post construction drainage patterns and conveyance systems are presented on the Erosion

Control Plan in Appendix R.

Table 2.1 Construction Site Estimates

Construction site area 1.55 acres

Percent impervious before construction 1.3 %

Runoff coefficient before construction 0.11

Percent impervious after construction 1.6 %

Runoff coefficient after construction 0.12

2.2 PERMITS AND GOVERNING DOCUMENTS

In addition to the General Permit, the following documents have been taken into account while

preparing this SWPPP

• Regional Water Quality Control Board requirements (Land Application for well

development and aquifer testing

• Right of Entry Agreements

PWM Well Field Phase 3 13 August 2020

• Approvals and Permits from City of Seaside that include

o Encroachment Permit (for work in General Jim Moore Blvd)

o Grading Permits

o Soil Management Plan (included in the Work Plan, Schaaf and Wheeler, 2016)

• Well Drilling Permits from Monterey County

• Seaside Basin Monitoring and Management Plan

• Contract Documents that include Work Plan (Schaaf and Wheeler, 2016) and design

drawings (dated August 2020)

• Air Quality Regulations and Permits

• Federal Endangered Species Act

• National Historic Preservation Act/Requirements of the State Historic Preservation

Office

• State of California Endangered Species Act

2.3 STORMWATER RUN-ON FROM OFFSITE AREAS

There is no anticipated offsite run-on to this construction site because the site is undeveloped,

upland areas are vegetated with maritime chaparral, and stormwater runoff infiltrates the soil

upon interception. The soils are hydrologic soil Group A, NRCS curve number 35.

2.4 FINDINGS OF THE CONSTRUCTION SITE SEDIMENT AND RECEIVING WATER RISK DETERMINATION

A construction site risk assessment has been performed for the project and the resultant risk level

is Risk Level 1.

The risk level was determined through the use of the EPA’s individual method for Sediment Risk

and Site Specific Analysis to determine the Receiving Water Risk. The risk level is based on

project duration, location, proximity to impaired receiving waters and soil conditions. A copy of

the Risk Level determination submitted on SMARTS with the PRDs is included in Appendix C.

Table 2.2 and Table 2.3 summarize the sediment and receiving water risk factors and document

the sources of information used to derive the factors.

Table 2.2 Summary of Sediment Risk

RUSLE

Factor Value Method for establishing value

R 48.19 EPA’s Rainfall Erosivity Calculator (uses site location and project duration)

K 0.1 Site Specific K Factor (using data from Boring logs and Erickson triangular

nomograph for soil erodibility (K) factor)

LS 1.82 LS Factors for Construction Sites (Table from Renard et al, 1997)

Total Predicted Sediment Loss (tons/acre) 8.77

PWM Well Field Phase 3 14 August 2020

Table 2.2 Summary of Sediment Risk

RUSLE

Factor Value Method for establishing value

Overall Sediment Risk

Low Sediment Risk < 15 tons/ acre

Medium Sediment Risk >= 15 and < 75 tons/acre

High Sediment Risk >= 75 tons/acre

Low Medium

High

Runoff from the project site discharges to a percolation depression tributary to the Seaside

Groundwater Basin.

Table 2.3 Summary of Receiving Water Risk

Receiving Water Name

303(d) Listed for

Sediment Related

Pollutant(1)

TMDL for Sediment

Related Pollutant(1)

Beneficial Uses of

COLD, SPAWN, and

MIGRATORY(1)

Seaside Groundwater Basin Yes No Yes No Yes No

Overall Receiving Water Risk Low

High

(1) If yes is selected for any option the Receiving Water Risk is High

Risk Level 1 sites are subject to the narrative effluent limitations specified in the General Permit.

The narrative effluent limitations require stormwater discharges associated with construction

activity to minimize or prevent pollutants in stormwater and authorized non-stormwater through

the use of controls, structures, and best management practices. This SWPPP has been prepared

to address Risk Level 1 requirements (General Permit Attachment C).

PWM Well Field Phase 3 15 August 2020

2.5 CONSTRUCTION SCHEDULE

The site sediment risk was determined based on construction taking place between September 1,

2020 to June 1, 2021. Modification or extension of the schedule (start and end dates) may affect

risk determination and permit requirements. The LRP shall contact the QSD if the schedule

changes during construction to address potential impact to the SWPPP. The estimated schedule

for planned work can be found in Appendix F.

Listed below are the identified phases of construction and their proposed start dates:

September 1, 2020 – February 28, 2021 Site grading, well drilling and development

January 1, 2021 – March 31, 2021 Site grading, trenching and utility installation

February 1, 2021 – May 31 Surface Improvement Construction/Testing

June 1, 2021 – June 30, 2021 Site cleanup and closeout

2.6 POTENTIAL CONSTRUCTION ACTIVITY AND POLLUTANT SOURCES

The following is a list of example construction materials and activities that have the potential to

contribute pollutants, other than sediment, to storm water run-off:

• Vehicle fluids, including oil, grease, petroleum, and coolants

• Asphaltic emulsions associated with asphalt concrete paving operations

• Cement materials associated with Portland cement concrete (PCC) paving operations,

trench installation and utility installation

• Base and subbase material

• Joint and curing compounds

• Concrete curing compounds

• Paints

• Solvents, thinners, and acids

• Raw landscaping materials and wastes (topsoil, plant materials, herbicides, fertilizers,

mulch, pesticides)

• BMP materials (sandbags)

• Treated lumber (materials and waste)

• PCC rubble

• General litter

Construction activities that have the potential to contribute sediment to storm water discharges

include:

• Clearing and grubbing operations

• Grading operations

• Utility excavation operations

• Well drilling and development operations

• Landscaping operations

PWM Well Field Phase 3 16 August 2020

• Painting

The QSP is required to maintain an ongoing and active list of potential pollutant sources,

construction activities, and identify areas of the site where additional BMPs are necessary to

reduce or prevent pollutants in discharges. This “SWPPP Construction Site Pollutant Checklist”

must be consistent with the Material Safety Data Sheets (MSDS) for the project. It is

recommended that the SWPPP and MSDS be kept together at the site office, together with the

Stormwater Management Plan.

Appendix G includes a template for list of construction activities and associated materials that

are anticipated to be used onsite. These activities and associated materials will or could

potentially contribute pollutants, other than sediment, to stormwater runoff.

The anticipated activities and associated pollutants were used in Section 3 to select the Best

Management Practices for the project. Location of anticipated pollutants and associated BMPs

are show on the Erosion Control Plans in Appendix R.

For sampling requirements for non-visible pollutants associated with construction activity please

refer to Section 7.7.1. For a full and complete list of onsite pollutants, refer to the Material

Safety Data Sheets (MSDS), which are retained onsite at the construction trailer.

2.7 IDENTIFICATION OF NON-STORMWATER DISCHARGES

Non-stormwater discharges consist of discharges which do not originate from precipitation

events. The General Permit provides allowances for specified non-stormwater discharges that do

not cause erosion or carry other pollutants.

Non-stormwater discharges into storm drainage systems or waterways, which are not authorized

under the General Permit and listed in the SWPPP, or authorized under a separate NPDES

permit, are prohibited.

Non-stormwater discharges that are authorized from this project site include the following:

• Well development test water under WQO 2014-0194-DWQ

Activities at this site that may result in unauthorized non-stormwater discharges include:

• Vehicle and equipment cleaning, fueling and maintenance

• Drilling

• Boring

• Concrete mixing

• Crushing

• Painting

• Mortar mixing

Steps will be taken, including the implementation of appropriate BMPs, to ensure that

unauthorized discharges are eliminated, controlled, disposed, or treated on-site.

Discharges of construction materials and wastes, such as fuel or paint, resulting from dumping,

spills, or direct contact with rainwater or stormwater runoff, are also prohibited.

PWM Well Field Phase 3 17 August 2020

2.8 REQUIRED SITE MAP INFORMATION

The construction project’s Site Map(s) showing the project location, surface water boundaries,

geographic features, construction site perimeter and general topography and other requirements

identified in Attachment B of the General Permit is located in Appendix B and Appendix R.

Table 2.5 identifies Map or Sheet Nos. where required elements are illustrated.

Table 2.5 Required Map Information

Included on Map/Plan Sheet No. (1) Required Element

Vicinity Map/G-001 The project’s surrounding area (vicinity)

Erosion Control Plan/C001 Site layout

Erosion Control Plan/C002 & C003 Construction site boundaries

Erosion Control Plan/C002 & C003 Drainage areas

Erosion Control Plan/C002 & C003 Discharge locations

Erosion Control Plan/C002 & C003 Sampling locations

Erosion Control Plan/C002 & C003 Areas of soil disturbance (temporary or permanent)

Erosion Control Plan/C002 & C003 Active areas of soil disturbance (cut or fill)

Erosion Control Plan/C002 & C003 Locations of runoff BMPs

Erosion Control Plan/ C002 & C003 Locations of erosion control BMPs

Erosion Control Plan/ C002 & C003 Locations of sediment control BMPs

NA ATS location (if applicable)

NA Locations of sensitive habitats, watercourses, or other features

which are not to be disturbed

NA Locations of all post construction BMPs

Location to be decided in the field by

the Contractor Waste storage areas

Location to be decided in the field by

the Contractor Vehicle storage areas

Location to be decided in the field by

the Contractor Material storage areas

Erosion Control Plan/C003 Entrance and Exits

Location to be decided in the field by

the Contractor Fueling Locations

Notes: (1) Indicate maps or drawings that information is included on (e.g., Vicinity Map, Site Map, Drainage Plans,

Grading Plans, Progress Maps, etc.)

PWM Well Field Phase 3 18 August 2020

Section 3 Best Management Practices

3.1 SCHEDULE FOR BMP IMPLEMENTATION

The QSP is required to install BMPs as shown on the Erosion Control Plans included in

Appendix R and implement/install the BMPs listed in this section of the SWPPP. The Contractor

shall modify the Erosion Control Plan to reflect the phase of construction and the weather

conditions.

The Contractor shall install BMPs before the site is disturbed (e.g., to provide protection during

grading operations or to reduce or minimize pollution from historic areas of contamination

during construction). The erosion control plan shall be implemented year round.

A BMP Consideration Checklist has been provided in Appendix H, followed by the Fact Sheets

for the BMPs that are recommended for this project, which are included in the following

sections. BMPs will be installed in a sequence to follow the progress of demolition and

construction. As each area of the site is disturbed, BMPs will be installed to conform to the

specific site requirements. In general, the project will have limited areas exposed at any time.

Where practical, construction will occur during dry periods. The site BMP implementation

schedule is shown in Table 3.1, and described in the subsequent sections.

PWM Well Field Phase 3 19 August 2020

Table 3.1 BMP Implementation Schedule

BMP Implementation Duration

Ero

sio

n

Co

ntr

ol

EC-1, Scheduling Prior to Construction Entirety of Project

EC-2, Preservation of Existing

Vegetation Start of Construction Entirety of Project

EC-4, Hydroseeding End of Construction Post construction

EC-7, Geotextiles and Mats During the Construction During certain

field activities

EC-9, Earth Dikes and Drainage

Swales End of Construction Post construction

EC-16, Non-Vegetative Stabilization End of Construction Post construction

Sed

imen

t C

on

trol

SE-1, Silt Fence Start of Construction Entirety of Project

SE-4, Check Dams Start of Construction End of Project

SE-5, Fiber Rolls Start of Construction Entirety of Project

SE-6, Gravel Bag Berm Start of Construction Entirety of Project

SE-7, Street Sweeping and

Vacuuming Start of Construction Entirety of Project

SE-8, Sandbag Barrier Start of Construction Entirety of Project

SE-10, Storm Drain Inlet Protection Start of Construction Entirety of Project

Tra

ckin

g

Con

trol

TC-1, Stabilized Construction

Entrance/Exit Start of Construction Entirety of Project

TC-3, Entrance/Outlet Tire Wash Start of Construction Entirety of Project

Win

d

Ero

sio

n

WE-1, Wind Erosion Control Start of Construction Entirety of Project

3.2 EROSION AND SEDIMENT CONTROL

Erosion and sediment controls are required by the General Permit to provide effective reduction

or elimination of sediment related pollutants in stormwater discharges and authorized non-

stormwater discharges from the Site. Applicable BMPs are identified in this section for erosion

control, sediment control, tracking control, and wind erosion control.

PWM Well Field Phase 3 20 August 2020

3.2.1 Erosion Control

Erosion control, also referred to as soil stabilization, consists of source control measures that are

designed to prevent soil particles from detaching and becoming transported in stormwater

runoff. Erosion control BMPs protect the soil surface by covering and/or binding soil particles.

This construction project will implement the following practices to provide effective temporary

and final erosion control during construction:

1. Preserve existing vegetation where required and when feasible.

2. The area of soil disturbing operations shall be controlled such that the Contractor is able

to implement erosion control BMPs quickly and effectively.

3. Stabilize non-active areas within 14 days of cessation of construction activities or sooner

if stipulated by local requirements.

4. Control erosion in concentrated flow paths by applying geotextiles and mats, earth dikes

and drainage swales, and straw bales.

5. Prior to the completion of construction, apply permanent erosion control and stabilization

methods such as hydroseeding and other non-vegetative stabilization methods to

remaining disturbed soil areas.

Sufficient erosion control materials shall be maintained onsite to allow implementation in

conformance with this SWPPP.

The following temporary erosion control BMP selection table indicates the BMPs that shall be

implemented to control erosion on the construction site. Fact Sheets for temporary erosion

control BMPs are provided in Appendix H.

PWM Well Field 21 May 2017

Table 3.2 Temporary Erosion Control BMPs

CASQA

Fact

Sheet

BMP Name

Meets a

Minimum

Requirement(1)

BMP Used If not used, state reason

YES NO

EC-1 Scheduling ✓ X

EC-2 Preservation of Existing

Vegetation ✓ X

EC-3 Hydraulic Mulch ✓(2) X Not applicable at the site.

EC-4 Hydroseed ✓(2) X

EC-5 Soil Binders ✓(2) X Not applicable at the site.

EC-6 Straw Mulch ✓(2) X Not applicable at the site.

EC-7 Geotextiles and Mats ✓(2) X

EC-8 Wood Mulching ✓(2) X Not applicable at the site.

EC-9 Earth Dike and Drainage Swales ✓(3) X

EC-10 Velocity Dissipation Devices X

EC-11 Slope Drains X Not applicable at the site.

EC-12 Stream Bank Stabilization X Not applicable at the site.

EC-14 Compost Blankets ✓(2) X Not applicable at the site.

EC-15 Soil Preparation-Roughening X Not applicable at the site.

EC-16 Non-Vegetated Stabilization ✓(2) X

WE-1 Wind Erosion Control ✓ X

Alternate BMPs Used: If used, state reason:

(1) Applicability to a specific project shall be determined by the QSD. (2) The QSD shall ensure implementation of one of the minimum measures listed or a combination thereof to achieve and maintain the Risk Level

requirements. (3) Run-on from offsite shall be directed away from all disturbed areas, diversion of offsite flows may require design/analysis by a licensed civil engineer

and/or additional environmental permitting

PWM Well Field 22 May 2017

These temporary erosion control BMPs shall be implemented in conformance with the following

guidelines and as outlined in the BMP Factsheets provided in Appendix H. If there is a conflict

between documents, the Site Map will prevail over narrative in the body of the SWPPP or

guidance in the BMP Fact Sheets. Site specific details in the Site Map prevail over standard

details included in the Site Map. The narrative in the body of the SWPPP prevails over guidance

in the BMP Fact Sheets.

EC-1 Scheduling

A portion of the work requiring soil disturbance may occur in the winter months. If possible, the

majority of the soil disturbance (pipeline/utility trenching, site grading) will be scheduled for the

dry season.

EC-2 Preservation of Existing Vegetation

Existing vegetation at the site will be preserved and protected where practical.

EC-4 Hydroseeding

Vegetation that is disturbed as a result of the land disturbance and construction will be replaced

by hydroseeding after the construction ends.

EC-7 Geotextiles and Mats

The contractors will use geotextiles and/or mats as needed to provide stable surfaces for drilling

equipment.

EC-10 Velocity Dissipation Devices

Velocity dissipation devices will be installed at the toe of slopes.

EC-16 Non-Vegetated Stabilization

Post construction, the well sites will be stabilized using non-vegetated stabilization methods such

as asphaltic pavement.

3.2.2 Sediment Controls

Sediment controls are temporary or permanent structural measures that are intended to

complement the selected erosion control measures and reduce sediment discharges from active

construction areas. Sediment controls are designed to intercept and settle out soil particles that

have been detached and transported by the force of water.

The following sediment control BMP selection table indicates the BMPs that shall be

implemented to control sediment on the construction site. Fact Sheets for temporary sediment

control BMPs are provided in Appendix H.

PWM Well Field 23 May 2017

Table 3.3 Temporary Sediment Control BMPs, Tracking Control BMPs and Wind Erosion Control BMPs

CASQA

Fact Sheet BMP Name

Meets a Minimum

Requirement(1)

BMP

used

If not used, state reason

Y

ES

N

O

SE-1 Silt Fence ✓(2) (3) X

SE-2 Sediment Basin X Not applicable at the site. No

runoff to capture

SE-3 Sediment Trap X Not applicable at the site. No

runoff to capture

SE-4 Check Dams X

SE-5 Fiber Rolls ✓(2)(3) X

SE-6 Gravel Bag Berm ✓(3) X

SE-7 Street Sweeping ✓ X

SE-8 Sandbag Barrier X

SE-9 Straw Bale Barrier X Not applicable at the site.

SE-10 Storm Drain Inlet

Protection ✓ RL2&3 X

SE-11 ATS X Not applicable at the site.

SE-12 Manufactured Linear

Sediment Controls X Not applicable at the site.

SE-13 Compost Sock and Berm ✓(3) X Not applicable at the site.

SE-14 Biofilter Bags ✓(3) X Not applicable at the site.

TC-1 Stabilized Construction

Entrance and Exit ✓ X

TC-2 Stabilized Construction

Roadway X

TC-3 Entrance Outlet Tire Wash X

WE-1 Wind Erosion Control X

Alternate BMPs Used: If used, state reason:

(1) Applicability to a specific project shall be determined by the QSD (2) The QSD shall ensure implementation of one of the minimum measures listed or a combination thereof to

achieve and maintain the Risk Level requirements (3)Risk Level 2 &3 shall provide linear sediment control along toe of slope, face of slope, and at the grade breaks

of exposed slope

These temporary sediment control BMPs shall be implemented in conformance with the

following guidelines and in accordance with the BMP Fact Sheets provided in Appendix H. If

there is a conflict between documents, the Site Map will prevail over narrative in the body of the

SWPPP or guidance in the BMP Fact Sheets. Site specific details in the Site Map prevail over

PWM Well Field 24 May 2017

standard details included in the Site Map. The narrative in the body of the SWPPP prevails over

guidance in the BMP Fact Sheets.

SE-1 Silt Fence

Refer to the plans for silt fence installation and maintenance. In general, silt fence shall be

installed around the perimeter of any disturbed area on the Project site. Silt fence shall be

installed at the perimeter of the project and around any temporary spoil areas and material

stockpiles.

A silt fence is a temporary sediment barrier consisting of woven geotextile stretched across and

attached to supporting posts, trenched-in and, depending upon the strength of fabric used,

supported with plastic or wire mesh fence. Silt fences trap sediment by intercepting and

detaining small amounts of sediment-laden runoff from disturbed areas in order to promote

sedimentation behind the fence. Silt fences are proposed on top of slopes to reduce the potential

for wind to carry sediment from disturbed soils. Silt fences shall remain in place until the

disturbed area is permanently stabilized, after which, the silt fence shall be removed and properly

disposed of.

SE-4 Check Dams

Refer to the plans for check dam placement placement. In general straw bale check dams shall be

installed in unlined roadside ditches where velocities may result in sediment transport. around

the perimeter of any disturbed area on the Project site.

A check dam shall consist of one or more rice straw bales staked in place using wooden stakes,

slowing the flow of water in the roadside ditch and acting as a filter to catch sediment.

SE-5 Fiber Rolls

Refer to the plans for fiber roll placement. In general fiber rolls shall be installed around the

perimeter of any disturbed area on the Project site. The QSP shall install fiber rolls at the limits

of rough grading and around all inlets to be protected where possible. See SE-6 where fiber rolls

cannot be installed.

A fiber roll consists of straw, coir, or other biodegradable materials bound into a tight tubular roll

wrapped by netting, which can be photodegradable or natural. Additionally, gravel core fiber

rolls are available, which contain an embedded ballast material such as gravel or sand for

additional weight when staking the rolls is not feasible (i.e. inlet protection). For this project,

fiber rolls are proposed at the toe and on the face of slopes along the contours. Fiber rolls

intercept runoff, reduce its flow velocity, release the runoff as sheet flow, and provide removal of

sediment from the runoff (through sedimentation). By interrupting the length of a slope, fiber

rolls can also reduce sheet and rill erosion until vegetation is established.

SE-6 Gravel Bag Berm

Gravel bag berms may be used in areas where fiber rolls are difficult or impossible to stake

down, such as paved areas. The QSP may install gravel bag berms for inlet protection, or as part

of a linear sediment barrier along gutters or depressions.

A gravel bag berm is a series of gravel-filled bags placed on a level contour to intercept sheet

flows. Gravel bags pond sheet flow runoff, allowing sediment to settle out, and release runoff

slowly as sheet flow, preventing erosion.

SE-7 Street Sweeping and Vacuuming

PWM Well Field 25 May 2017

Power brooms will be used for street sweeping. Sweeping will occur daily in areas with

construction activities where needed.

SE-8 Sandbag Barrier

There are no identified locations where sandbag barriers will be necessary. The QSP shall use

sandbag barriers where gravel bags or fiber rolls are not sufficient in capturing sediment, or

where sediment traps are necessary.

Sand-filled bags have limited porosity, which is further limited as the fine sand tends to quickly

plug with sediment, limiting or completely blocking the rate of flow through the barrier.

SE-10 Storm Drain Inlet Protection

Refer to the plans for locations of storm drain inlets which require protection.

Storm drain inlet protection consisting of a fiber roll around a storm drain, drop inlet, or curb

inlet will be used. In areas where fiber rolls are unable to be installed, the QSP may use gravel

bag berms around the storm drain structure. Storm drain inlet protection measures temporarily

pond runoff before it enters the storm drain, allowing sediment to settle. Temporary geotextile

storm drain inserts attach underneath storm drain grates to capture and filter storm water.

3.2.3 Tracking Control

Tracking control consists of preventing or reducing the tracking of sediment off-site by vehicles

leaving the construction area. Street Sweeping and Vacuuming (SE-7) is also a tracking control

practice. All sites must have a stabilized construction entrance and implement controls to prevent

off-site tracking of sediment or other loose construction-related materials. These controls should

be inspected daily.

Attention to control of tracking sediment off site is essential, as dirty streets and roads near a

construction site create a nuisance to the public and can generate complaints to elected officials

and regulators. These complaints often result in immediate inspections and regulatory actions.

The QSP will implement the following practices for effective sediment tracking control during

construction:

• Stabilize all construction entrances and exits to prevent the off-site tracking of loose

construction/landscape materials.

• Implement/install the tracking control BMPs listed below.

Table 3.4 Temporary Tracking Control BMPs

CASQA

Fact Sheet BMP Name

Meets a Minimum

Requirement(1)

BMP used

If not used, state reason

YE

S

N

O

TC-1 Stabilized Construction

Entrance and Exit ✓ X

TC-2 Stabilized Construction

Roadway X

TC-3 Entrance Outlet Tire

Wash X

PWM Well Field 26 May 2017

Table 3.4 Temporary Tracking Control BMPs

CASQA

Fact Sheet BMP Name

Meets a Minimum

Requirement(1)

BMP used

If not used, state reason

YE

S

N

O

Alternate BMPs Used: If used, state reason:

(1) Applicability to a specific project shall be determined by the QSD (2) The QSD shall ensure implementation of one of the minimum measures listed or a combination thereof to

achieve and maintain the Risk Level requirements (3)Risk Level 2 &3 shall provide linear sediment control along toe of slope, face of slope, and at the grade breaks

of exposed slope

Tracking Control BMPs

The California Stormwater BMP Handbook - Construction contains fact sheets for tracking

control BMPs. The table below indicates the tracking control BMPs that are required, because

they are certain to be needed, and those that should be implemented as needed.

TC-1 Stabilized Construction Entrance and Exit

A construction entrance/exit shall be provided as shown on plans. The existing driveway from

Eucalyptus Road onto the site shall be used as the construction entrance/exit. A new paved

driveway entrance from General Jim Moore Blvd will be constructed as part of this project. That

driveway will not be used for construction traffic to reduce the tracking of mud and dirt onto

General Jim Moore Boulevard.

TC-2 Stabilized Construction Roadway

The existing construction access road is shown on the plans. The road is partially paved and

partially unpaved. The unpaved segment will be maintained as part of the work.

TC-3 Entrance Outlet Tire Wash

A tire wash shall be provided as shown on plans. This measure is intended to reduce the tracking

of mud and dirt onto General Jim Moore Boulevard.

3.2.4 Wind Erosion Control

Wind erosion control consists of applying water or other dust palliatives to prevent or minimize

dust nuisance.

Other BMPs that control wind erosion are EC-1 through EC-8, and EC-14 through EC-16. Be

advised that some of the dust palliatives/chemical dust suppression agents may have potential

water quality impacts.

PWM Well Field 27 May 2017

The QSP will implement the following practices for effective wind erosion control during

construction:

• Good housekeeping to prevent wind erosion of materials on site.

• Implement/install the wind erosion control BMP listed below and described in the Fact

Sheet in Appendix H.

Wind Erosion Control BMP

The California Stormwater BMP Handbook - Construction contains a fact sheet for wind erosion

control BMPs. As indicated in the table below, the wind erosion control BMPs are required.

Table 3.5 Temporary Wind Erosion Control BMPs

CASQA

Fact Sheet BMP Name

Meets a Minimum

Requirement(1)

BMP used

If not used, state reason

YE

S

N

O

WE-1 Wind Erosion Control X

Alternate BMPs Used: If used, state reason:

(1) Applicability to a specific project shall be determined by the QSD (2) The QSD shall ensure implementation of one of the minimum measures listed or a combination thereof to

achieve and maintain the Risk Level requirements (3)Risk Level 2 &3 shall provide linear sediment control along toe of slope, face of slope, and at the grade breaks

of exposed slope

3.3 NON-STORMWATER CONTROLS AND WASTE AND MATERIALS MANAGEMENT

3.3.1 Non-Stormwater Controls

Non-stormwater discharges into storm drainage systems or waterways, which are not authorized

under the General Permit, are prohibited. Non-stormwater discharges for which a separate

NPDES permit is required by the local Regional Water Board are prohibited unless coverage

under the separate NPDES permit has been obtained for the discharge. The selection of non-

stormwater BMPs is based on the list of construction activities with a potential for non-

stormwater discharges identified in Section 2.7 of this SWPPP.

The following non-stormwater control BMP selection table indicates the BMPs that shall be

implemented to control sediment on the construction site. Fact Sheets for temporary non-

stormwater control BMPs are provided in Appendix H.

PWM Well Field 28 May 2017

Table 3.6 Temporary Non-Stormwater BMPs

CASQA Fact

Sheet BMP Name

Meets a

Minimum

Requirement(1)

BMP used If not used, state reason

YES NO

NS-1 Water Conservation Practices ✓ X

NS-2 Dewatering Operation X Not applicable at the site.

NS-3 Paving and Grinding Operation X Not applicable at the site

NS-4 Temporary Stream Crossing X Not applicable at the site.

NS-5 Clear Water Diversion X Not applicable at the site.

NS-6 Illicit Connection/Discharge ✓ X Not applicable at the site.

NS-7 Potable Water/Irrigation X

NS-8 Vehicle and Equipment Cleaning ✓ X Not applicable at the site.

NS-9 Vehicle and Equipment Fueling ✓ X

NS-10 Vehicle and Equipment Maintenance ✓ X

NS-11 Pile Driving Operation X Not applicable at the site.

NS-12 Concrete Curing X

NS-13 Concrete Finishing X

NS-14 Material and Equipment Use Over Water X Not applicable at the site.

NS-15 Demolition Removal Adjacent to Water X Not applicable at the site.

NS-16 Temporary Batch Plants X Not applicable at the site.

Alternate BMPs Used: If used, state reason:

(1) Applicability to a specific project shall be determined by the QSD

PWM Well Field Phase 3 29 August 2020

Non-stormwater BMPs shall be implemented in conformance with the following guidelines and

in accordance with the BMP Fact Sheets provided in Appendix H. If there is a conflict between

documents, the Site Map will prevail over narrative in the body of the SWPPP or guidance in the

BMP Fact Sheets. Site specific details in the Site Map prevail over standard details included in

the Site Map. The narrative in the body of the SWPPP prevails over guidance in the BMP Fact

Sheets.

NS-1 Water Conservation Practices

Practice suitable for all construction sites where water is used, including piped water, metered

water, trucked water, and water from a reservoir.

The following practices shall be implemented:

• Keep water equipment in good working condition.

• Stabilize water truck filling area.

• Repair water leaks promptly.

• Washing of vehicles and equipment on the construction site is discouraged.

• Avoid using water to clean construction areas. If water must be used for cleaning or

surface preparation, surface shall be swept and vacuumed first to remove dirt. This will

minimize amount of water required.

• Direct construction water runoff to areas where it can soak into the ground or be collected

and reused.

• Authorized non-stormwater discharges to the storm drain system, channels, or receiving

waters are acceptable with the implementation of appropriate BMPs. • Lock water tank valves to prevent unauthorized use.

• Cleaning.

NS-7 Potable Water/Irrigation

Potable water will be brought at the site and maintained in the following manner:

• Direct water from offsite sources around or through a construction site, where feasible, in

a way that minimizes contact with the construction site.

• Shut off the water source to broken lines, sprinklers, or valves as soon as possible to

prevent excess water flow.

NS-9 Vehicle and Equipment Fueling

Vehicle equipment fueling procedures are designed to prevent fuel spills and leaks, and reduce or

eliminate contamination of stormwater. This can be accomplished by using offsite facilities,

fueling in designated areas only, enclosing or covering stored fuel, implementing spill controls,

and training employees and subcontractors in proper fueling procedures.

Implementation recommendations:

PWM Well Field Phase 3 30 August 2020

• Use offsite fueling stations as much as possible. These businesses are better equipped to

handle fuel and spills properly. Performing this work offsite can also be economical by

eliminating the need for a separate fueling area at a site.

• Discourage “topping-off” of fuel tanks.

• Absorbent spill cleanup materials and spill kits shall be available in fueling areas and on

fueling trucks. Other options to washing equipment onsite include contracting with either

an offsite or mobile commercial be disposed of properly after use.

• Drip pans or absorbent pads shall be used during vehicle and equipment fueling, unless

the fueling is performed over an impermeable surface in a dedicated fueling area.

• Use absorbent materials on small spills. Do not hose down or bury the spill. Remove the

adsorbent materials promptly and dispose of properly.

• Avoid mobile fueling of mobile construction equipment around the site; rather, transport

the equipment to designated fueling areas. With the exception of tracked equipment such

as bulldozers and large excavators, most vehicles shall be able to travel to a designated

area with little lost time.

• Train employees and subcontractors in proper fueling and cleanup procedures.

• When fueling must take place onsite, designate an area away from drainage courses to be

used. Fueling areas shall be identified in the SWPPP.

• Dedicated fueling areas shall be protected from stormwater run-on and runoff, and shall

be located at least 50 ft away from downstream drainage facilities and watercourses.

Fueling must be performed on level-grade areas.

• Protect fueling areas with berms and dikes to prevent run-on, runoff, and to contain spills.

• Nozzles used in vehicle and equipment fueling shall be equipped with an automatic

shutoff to control drips. Fueling operations shall not be left unattended.

• Use vapor recovery nozzles to help control drips as well as air pollution where required

by Air Quality Management District (AQMD).

• Federal, state, and local requirements shall be observed for any stationary above ground

storage tanks.

NS-10 Vehicle and Equipment Maintenance

Prevent or reduce the contamination of stormwater resulting from vehicle and equipment

maintenance by running a “dry and clean site”. The best option would be to perform maintenance

activities at an offsite facility. If this option is not available, then work should be performed in

designated areas only, while providing cover for materials stored outside, checking for leaks and

spills, and containing and cleaning up spills immediately. Employees and subcontractors must be

trained in proper procedures.

Implementation recommendations:

• Use offsite repair shops as much as possible. These businesses are better equipped to

handle vehicle fluids and spills properly. Performing this work offsite can also be

economical by eliminating the need for a separate maintenance area.

• If maintenance must occur onsite, use designated areas, located away from drainage

courses. Dedicated maintenance areas shall be protected from stormwater run-on and

runoff, and shall be located at least 50 ft from downstream drainage facilities.

PWM Well Field Phase 3 31 August 2020

• Drip pans or absorbent pads shall be used during vehicle and equipment maintenance

work that involves fluids, unless the maintenance work is performed over an

impermeable surface in a dedicated maintenance area.

• Place a stockpile of spill cleanup materials where it will be readily accessible. All fueling

trucks and fueling areas are required to have spill kits and/or use other spill protection

devices.

• Use adsorbent materials on small spills. Remove the absorbent materials promptly and

dispose of properly.

• Inspect onsite vehicles and equipment daily at startup for leaks, and repair immediately.

• Keep vehicles and equipment clean; do not allow excessive build-up of oil and grease.

• Segregate and recycle wastes, such as greases, used oil or oil filters, antifreeze, cleaning

solutions, automotive batteries, hydraulic and transmission fluids. Provide secondary

containment and covers for these materials if stored onsite.

• Train employees and subcontractors in proper maintenance and spill cleanup procedures.

• Drip pans or plastic sheeting shall be placed under all vehicles and equipment placed on

docks, barges, or other structures over water bodies when the vehicle or equipment is

planned to be idle for more than 1 hour.

• For long-term projects, consider using portable tents or covers over maintenance areas if

maintenance cannot be performed offsite.

• Consider use of new, alternative greases and lubricants, such as adhesive greases, for

chassis lubrication and fifth-wheel lubrication.

• Properly dispose of used oils, fluids, lubricants, and spill cleanup materials.

• Do not place used oil in a dumpster or pour into a storm drain or watercourse.

• Properly dispose of or recycle used batteries.

• Do not bury used tires.

NS-12 Concrete Curing

Concrete and its associated curing materials have basic chemical properties that can raise the pH

of water to levels outside of the permitted range. Discharges of stormwater and non-stormwater

exposed to concrete during curing may have a high pH and may contain chemicals, metals, and

fines. Proper procedures and care should be taken when managing concrete curing materials to

prevent them from coming into contact with stormwater flows, which could result in high pH

discharge.

Implementation recommendations:

Chemical Curing

• Avoid over spray of curing compounds.

• Minimize the drift by applying the curing compound close to the concrete surface. Apply

an amount of compound that covers the surface, but does not allow any runoff of the

compound.

• Use proper storage and handling techniques for concrete curing compounds. Refer to

WM-1, Material Delivery and Storage.

• Protect drain inlets prior to the application of curing compounds.

PWM Well Field Phase 3 32 August 2020

• Refer to WM-4, Spill Prevention and Control.

Water Curing for Retaining Walls, and other Structures

• Direct cure water away from inlets and watercourses to collection areas for evaporation

or other means of removal in accordance with all applicable permits. See WM-8 Concrete

Waste Management.

• Collect cure water at the top of slopes and transport to a concrete waste management area

in a non-erosive manner. See EC-9 Earth Dikes and Drainage Swales, and EC-10,

Velocity Dissipation Devices.

• Utilize wet blankets or a similar method that maintains moisture while minimizing the

use and possible discharge of water.

Education

• Educate employees, subcontractors, and suppliers on proper concrete curing techniques to

prevent contact with discharge as described herein. Arrange for the QSP or the

appropriately trained contractor’s superintendent or representative to oversee and enforce

concrete curing procedures.

NS-13 Concrete Finishing

Concrete finishing methods are used for paint removal, curing compound removal, and final

surface finish appearances. Methods include sand blasting, shot blasting, grinding, or high

pressure water blasting. Stormwater and non-stormwater exposed to concrete finishing by-

products may have a high pH and may contain chemicals, metals, and fines. Proper procedures

and implementation of appropriate BMPs can minimize the impact that concrete-finishing

methods may have on stormwater and non-stormwater discharges.

Implementation recommendations:

• Collect and properly dispose of water from high-pressure water blasting operations.

• Collect contaminated water from blasting operations at the top of slopes. Transport or

dispose of contaminated water while using BMPs such as those for erosion control. Refer

to EC-9, Earth

• Dikes and Drainage Swales, and EC-10, Velocity Dissipation Devices.

• Direct water from blasting operations away from inlets and watercourses to collection

areas for infiltration or other means of removal (dewatering). Refer to NS-2 Dewatering

Operations.

• Protect inlets during sandblasting operations. Refer to SE-10, Storm Drain Inlet

Protection.

• Refer to WM-8, Concrete Waste Management for disposal of concrete debris.

• Minimize the drift of dust and blast material as much as possible by keeping the blasting

nozzle close to the surface.

• When blast residue contains a potentially hazardous waste, refer to WM-6, Hazardous

Waste Management.

Education

PWM Well Field Phase 3 33 August 2020

Educate employees, subcontractors, and suppliers on proper concrete finishing techniques to

prevent contact with discharge as described herein. Arrange for the QSP or the appropriately

trained contractor’s superintendent or representative to oversee and enforce concrete finishing

procedures.

3.3.2 Materials Management and Waste Management

Materials management control practices consist of implementing procedural and structural BMPs

for handling, storing and using construction materials to prevent the release of those materials

into stormwater discharges. The amount and type of construction materials to be utilized at the

Site will depend upon the type of construction and the length of the construction period. The

materials may be used continuously, such as fuel for vehicles and equipment, or the materials

may be used for a discrete period, such as soil binders for temporary stabilization.

Waste management consist of implementing procedural and structural BMPs for handling,

storing and ensuring proper disposal of wastes to prevent the release of those wastes into

stormwater discharges.

Materials and waste management pollution control BMPs shall be implemented to minimize

stormwater contact with construction materials, wastes and service areas; and to prevent

materials and wastes from being discharged off-site. The primary mechanisms for stormwater

contact that shall be addressed include:

• Direct contact with precipitation

• Contact with stormwater run-on and runoff

• Wind dispersion of loose materials

• Direct discharge to the storm drain system through spills or dumping

• Extended contact with some materials and wastes, such as asphalt cold mix and treated

wood products, which can leach pollutants into stormwater.

A list of construction activities is provided in Section 2.6. The following Materials and Waste

Management BMP selection table indicates the BMPs that shall be implemented to handle

materials and control construction site wastes associated with these construction activities. Fact

Sheets for Materials and Waste Management BMPs are provided in Appendix H.

PWM Well Field 34 May 2017

Table 3.7 Temporary Materials Management BMPs

CASQA Fact

Sheet BMP Name

Meets a

Minimum

Requirement(1)

BMP used

If not used, state reason

YES NO

WM-01 Material Delivery and Storage ✓ X

WM-02 Material Use ✓ X

WM-03 Stockpile Management ✓ X

WM-04 Spill Prevention and Control ✓ X

WM-05 Solid Waste Management ✓ X

WM-06 Hazardous Waste Management ✓ X

WM-07 Contaminated Soil

Management ✓ X

WM-08 Concrete Waste Management ✓ X

WM-09 Sanitary-Septic Waste

Management ✓ X

WM-10 Liquid Waste Management ✓ X

Alternate BMPs Used: If used, state reason:

(1) Applicability to a specific project shall be determined by the QSD.

PWM Well Field Phase 3 35 August 2020

Material management BMPs shall be implemented in conformance with the following guidelines

and in accordance with the BMP Fact Sheets provided in Appendix H. If there is a conflict

between documents, the Site Map will prevail over narrative in the body of the SWPPP or

guidance in the BMP Fact Sheets. Site specific details in the Site Map prevail over standard

details included in the Site Map. The narrative in the body of the SWPPP prevails over guidance

in the BMP Fact Sheets.

WM-1 Material Delivery and Storage

The following steps shall be taken to minimize risk:

• Chemicals must be stored in water tight containers with appropriate secondary

containment or in a storage shed.

• When a material storage area is located on bare soil, the area shall be lined and bermed.

• Use containment pallets or other practical and available solutions, such as storing

materials within newly constructed buildings or garages, to meet material storage

requirements.

• Stack erodible landscape material on pallets and cover when not in use.

• Contain all fertilizers and other landscape materials when not in use.

• Temporary storage areas shall be located away from vehicular traffic.

• Material Safety Data Sheets (MSDS) shall be available on-site for all materials stored

that have the potential to effect water quality.

• Construction site areas shall be designated for material delivery and storage.

• Material delivery and storage areas shall be located away from waterways, if possible.

o Avoid transport near drainage paths or waterways.

o Surround with earth berms or other appropriate containment BMP. See EC-9,

Earth Dikes and Drainage Swales.

o Place in an area that will be paved.

• Storage of reactive, ignitable, or flammable liquids must comply with the fire codes of

the area. Contact the local Fire Marshal to review site materials, quantities, and proposed

storage area to determine specific requirements. See the Flammable and Combustible

Liquid Code, NFPA30.

• An up to date inventory of materials delivered and stored onsite shall be kept. Hazardous

materials storage onsite shall be minimized.

• Hazardous materials shall be handled as infrequently as possible.

• Keep ample spill cleanup supplies appropriate for the materials being stored. Ensure that

cleanup supplies are in a conspicuous, labeled area.

• Employees and subcontractors shall be trained on the proper material delivery and

storage practices.

• Employees trained in emergency spill cleanup procedures must be present when

dangerous materials or liquid chemicals are unloaded.

• If significant residual materials remain on the ground after construction is complete,

properly remove and dispose of materials and any contaminated soil. See WM-7,

Contaminated Soil Management. If the area is to be paved, pave as soon as materials are

removed to stabilize the soil.

Material Storage Areas and Practices

PWM Well Field Phase 3 36 August 2020

• Liquids, petroleum products, and substances listed in 40 CFR Parts 110, 117, or 302 shall

be stored in approved containers and drums and shall not be overfilled. Containers and

drums shall be placed in temporary containment facilities for storage.

• A temporary containment facility shall provide for a spill containment volume able to

contain precipitation from a 25 year storm event, plus the greater of 10% of the aggregate

volume of all containers or 100% of the capacity of the largest container within its

boundary, whichever is greater.

• A temporary containment facility shall be impervious to the materials stored therein for a

minimum contact time of 72 hours.

• A temporary containment facility shall be maintained free of accumulated rainwater and

spills. In the event of spills or leaks, accumulated rainwater and spills shall be collected

and placed into drums. These liquids shall be handled as a hazardous waste unless testing

determines them to be non-hazardous. All collected liquids or non-hazardous liquids shall

be sent to an approved disposal site.

• Sufficient separation shall be provided between stored containers to allow for spill

cleanup and emergency response access.

• Incompatible materials, such as chlorine and ammonia, shall not be stored in the same

temporary containment facility.

• Materials shall be covered prior to, and during rain events.

• Materials shall be stored in their original containers and the original product labels shall

be maintained in place in a legible condition. Damaged or otherwise illegible labels shall

be replaced immediately.

• Bagged and boxed materials shall be stored on pallets and shall not be allowed to

accumulate on the ground. To provide protection from wind and rain throughout the rainy

season, bagged and boxed materials shall be covered during non-working days and prior

to and during rain events.

• Stockpiles shall be protected in accordance with WM-3, Stockpile Management.

• Materials shall be stored indoors within existing structures or completely enclosed

storage sheds when available.

• Proper storage instructions shall be posted at all times in an open and conspicuous

location.

• An ample supply of appropriate spill cleanup material shall be kept near storage areas.

• Also see WM-6, Hazardous Waste Management, for storing of hazardous wastes.

Material Delivery Practices

Keep an accurate, up-to-date inventory of material delivered and stored onsite.

Arrange for employees trained in emergency spill cleanup procedures to be present when

dangerous materials or liquid chemicals are unloaded.

Spill Cleanup

• Contain and clean up any spill immediately.

• Properly remove and dispose of any hazardous materials or contaminated soil if

significant residual materials remain on the ground after construction is complete. See

WM-7, Contaminated

PWM Well Field Phase 3 37 August 2020

• Soil Management.

• See WM-4, Spill Prevention and Control, for spills of chemicals and/or hazardous

materials. If spills or leaks of materials occur that are not contained and could discharge

to surface waters, non-visible sampling of site discharge may be required. Refer to the

General Permit or to your project specific Construction Site Monitoring Plan to determine

if and where sampling is required.

WM-2 Material Use

The following steps shall be taken to minimize risk:

• Minimize use of hazardous materials onsite.

• Follow manufacturer instructions regarding uses, protective equipment, ventilation,

flammability, and mixing of chemicals.

• Train personnel who use pesticides. The California Department of Pesticide Regulation

and

• County Agricultural Commissioners license pesticide dealers, certify pesticide

applicators, and conduct onsite inspections.

• Train employees and subcontractors in proper material use.

• Supply Material Safety Data Sheets (MSDS) for all materials.

• Dispose of latex paint and paint cans, used brushes, rags, absorbent materials, and drop

cloths, when thoroughly dry and are no longer hazardous, with other construction debris.

• Do not remove the original product label; it contains important safety and disposal

information. Use the entire product before disposing of the container.

• Mix paint indoors or in a containment area. Never clean paintbrushes or rinse paint

containers into a street, gutter, storm drain, or watercourse. Dispose of any paint thinners,

residue, and sludge(s) that cannot be recycled, as hazardous waste.

• For water-based paint, clean brushes to the extent practicable, and rinse to a drain leading

to a sanitary sewer where permitted, or contain for proper disposal off site. For oil-based

paints, clean brushes to the extent practicable, and filter and reuse thinners and solvents.

• Use recycled and less hazardous products when practical. Recycle residual paints,

solvents, nontreated lumber, and other materials.

• Use materials only where and when needed to complete the construction activity. Use

safer alternative materials as much as possible. Reduce or eliminate use of hazardous

materials onsite when practical.

• Document the location, time, chemicals applied, and applicator’s name and

qualifications.

• Keep an ample supply of spill cleanup material near use areas. Train employees in spill

cleanup procedures.

• Avoid exposing applied materials to rainfall and runoff unless sufficient time has been

allowed for them to dry.

• Discontinue use of erodible landscape material within 2 days prior to a forecasted rain

event and materials shall be covered and/or bermed.

• Provide containment for material use areas such as masons’ areas or paint

mixing/preparation areas to prevent materials/pollutants from entering stormwater.

PWM Well Field Phase 3 38 August 2020

WM-3 Stockpile Management

Stockpiling of material is anticipated at the construction site. Contractor shall cover all stockpiles

that are not being used at the end of the day. Stockpiles not used for 14 days shall be removed

from the site. Dust control measures will be implemented on any stockpiled materials.

WM-4 Spill Prevention and Control

Employees will be trained to identify the type of spill (Minor, Semi-Significant or

Significant/Hazardous), and respond accordingly. Spills will not be cleaned up using water. The

spills will be cleaned up using materials specified for the type of spill. The used clean up

material and the recovered materials no longer suitable for the intended purpose will be disposed

off site as per the applicable regulations. Regular meetings will be held to discuss these

procedures as continuing education for new employees. Keep material or waste storage areas

clean, well-organized, and equipped with enough cleanup supplies for the material being stored.

Implement spill and leak prevention procedures for chemicals and hazardous substances stored

on the job site. Whenever you spill or leak chemicals or hazardous substances at the job site, you

are responsible for all associated cleanup costs and related liability.

Report minor, semi-significant, and significant or hazardous spills to the WPC manager. The

WPC manager must notify the Engineer immediately. As soon as it is safe, contain and clean up

spills of petroleum materials and sanitary and septic waste substances listed under 40 CFR, Parts

110, 117, and 302.

Minor Spills

Minor spills consist of quantities of oil, gasoline, paint, or other materials that are small enough

to be controlled by a 1st responder upon discovery of the spill.

Clean up a minor spill using the following procedures:

1. Contain the spread of the spill

2. Recover the spilled material using absorption

3. Clean the contaminated area

4. Dispose of the contaminated material and absorbents promptly and properly under "Waste

Management" of these special provisions

Semi-Significant Spills

Semi-significant spills consist of spills that can be controlled by a 1st responder with help from

other personnel.

Clean up a semi-significant spill immediately using the following procedures:

1. Contain the spread of the spill.

2. On paved or impervious surfaces, encircle and recover the spilled material with absorbent

materials. Do not allow the spill to spread widely.

3. If the spill occurs on soil, contain the spill by constructing an earthen dike and dig up the

contaminated soil for disposal.

4. If the spill occurs during precipitation, cover the spill with 10-mil plastic sheeting or other

material to prevent contamination of runoff.

PWM Well Field Phase 3 39 August 2020

5. Dispose of the contaminated material promptly and properly under "Waste Management" of

these special provisions.

Significant or Hazardous Spills

Significant or hazardous spills consist of spills that cannot be controlled by job site personnel.

Immediately notify qualified personnel of a significant or hazardous spill. Take the following

steps:

1. Do not attempt to clean up the spill until qualified personnel have arrived

2. Notify the Engineer and follow up with a report

3. Obtain the immediate services of a spill contractor or hazardous material team

4. Notify local emergency response teams by dialing 911 and county officials by using the

emergency phone numbers retained at the job site

5. Notify the California Emergency Management Agency State Warning Center.

6. Notify the National Response Center at (800) 424-8802 regarding spills of Federal reportable

quantities under 40 CFR 110, 119, and 302

7. Notify other agencies as appropriate, including:

o Fire Department

o Public Works Department

o Coast Guard

o Highway Patrol

o City Police or County Sheriff's Department

o Department of Toxic Substances

o California Division of Oil and Gas

o Cal/OSHA

o Regional Water Resources Control Board

8. Prevent a spill from entering stormwater runoff before and during cleanup activities. Do

not bury or wash the spill with water.

WM-5 Solid Waste Management

The following steps shall be taken to help keep a clean site and reduce stormwater pollution:

• Select designated waste collection areas onsite.

• Inform trash-hauling contractors that the site will accept only watertight dumpsters for

onsite use.

• Inspect dumpsters for leaks and repair any dumpster that is not watertight.

• Locate containers in a covered area or in a secondary containment.

• Provide an adequate number of containers with lids or covers that can be placed over the

container to keep rain out or to prevent loss of wastes when it is windy.

• Plan for additional containers and more frequent pickup during the demolition phase of

construction.

• Collect site trash daily, especially during rainy and windy conditions.

• Remove solid waste promptly since erosion and sediment control devices tend to collect

litter.

• Make sure that toxic liquid wastes (used oils, solvents, and paints) and chemicals (acids,

pesticides, additives, curing compounds) are not disposed of in dumpsters designated for

PWM Well Field Phase 3 40 August 2020

construction debris.

• Do not hose out dumpsters on the construction site. Leave dumpster cleaning to the trash

hauling contractor.

• Arrange for regular waste collection before containers overflow.

• Clean up immediately if a container does spill.

• Make sure that construction waste is collected, removed, and disposed of only at

authorized disposal areas.

Regular meetings will be held to discuss these procedures as continuing education for new

employees.

Collection, Storage, and Disposal

• Littering on the project site is prohibited.

• To prevent clogging of the storm drainage system, litter and debris removal from

drainage grates, trash racks, and ditch lines is a priority.

• Trash receptacles shall be provided in the contractor’s yard, field trailer areas, and at

locations where workers congregate for lunch and break periods.

• Litter from work areas within the construction limits of the project site shall be collected

and placed in watertight dumpsters at least weekly, regardless of whether the litter was

generated by the contractor, the public, or others. Collected litter and debris shall not be

placed in or next to stormwater drainage systems, or watercourses.

• Dumpsters of sufficient size and number shall be provided to contain the solid waste

generated by the project.

• Full dumpsters shall be removed from the project site and the contents shall be disposed

of by the trash hauling contractor.

• Construction debris and waste shall be removed from the site biweekly or more

frequently as needed.

• Construction material visible to the public shall be stored or stacked in an orderly

manner.

• Stormwater run-on shall be prevented from contacting stored solid waste through the use

of berms, dikes, or other temporary diversion structures or through the use of measures to

elevate waste from site surfaces.

• Solid waste storage areas shall be located at least 50 ft from drainage facilities and

watercourses and shall not be located in areas prone to flooding or ponding.

• Except during fair weather, construction and highway planting waste not stored in

watertight dumpsters shall be securely covered from wind and rain by covering the waste

with tarps or plastic.

• Segregate potentially hazardous waste from non-hazardous construction site waste.

• Make sure that toxic liquid wastes (used oils, solvents, and paints) and chemicals (acids,

pesticides, additives, curing compounds) are not disposed of in dumpsters designated for

construction debris.

• For disposal of hazardous waste, see WM-6, Hazardous Waste Management. Have

hazardous waste hauled to an appropriate disposal and/or recycling facility.

• Salvage or recycle useful vegetation debris, packaging and surplus building materials

when practical. For example, trees and shrubs from land clearing can be used as a brush

PWM Well Field Phase 3 41 August 2020

barrier, or converted into wood chips, then used as mulch on graded areas. Wood pallets,

cardboard boxes, and construction scraps can also be recycled.

WM-6 Hazardous Waste Management

Hazardous Waste Management will be implemented as per the contract specifications for any

requirements pertaining to handling of contaminated material. Any waste generated will be

stored in watertight containers and stored in a location approved by the Engineer until it is

disposed of by a licensed hazardous waste transporter.

WM-7 Contaminated Soil Management

Prevent or reduce the discharge of pollutants to stormwater from contaminated soil and highly

acidic or alkaline soils by conducting pre-construction surveys, inspecting excavations regularly,

and remediating contaminated soil promptly. Look for contaminated soil as evidenced by

discoloration, odors, differences in soil properties, abandoned underground tanks or pipes, or

buried debris. Prevent leaks and spills. Contaminated soil can be expensive to treat and dispose

of properly. However, addressing the problem before construction is much less expensive than

after the structures are in place. The contractor may further identify contaminated soils by

investigating:

• Past site uses and activities

• Detected or undetected spills and leaks

• Acid or alkaline solutions from exposed soil or rock formations high in acid or alkaline

forming elements

• Contaminated soil as evidenced by discoloration, odors, differences in soil properties,

abandoned underground tanks or pipes, or buried debris.

• Suspected soils should be tested at a certified laboratory

WM-8 Concrete Waste Management

Concrete waste will be handled in accordance with contract documents. Collect and dispose of

Portland concrete, AC, or HMA waste at locations where saw-cutting, coring, grinding, grooving

or hydro-concrete demolition of Portland cement concrete, AC or HMA create a residue or

slurry. Concrete waste will be collected and disposed as appropriate portable washout bins. If

any spilled material is observed, the spilled material shall be removed and placed into the

concrete washout bin. WM-4 Spill Prevention and Control BMPs shall be implemented in case

of any spill.

WM-9 Sanitary/Septic Waste Management

Sanitary or septic wastes shall be treated or disposed of in accordance with state and local

requirements. The sanitary facilities shall be located at least 50 feet away from storm drains. The

weekly QSP inspection shall include a review of sanitary facilities and disposal shall be

monitored.

PWM Well Field Phase 3 42 August 2020

WM-10 Liquid Waste Management

Well drilling fluids will be hauled off-site for disposal at a licensed wastewater treatment facility

in accordance with the contract documents.

3.4 POST CONSTRUCTION STORMWATER MANAGEMENT MEASURES

Post construction BMPs are permanent measures installed during construction, designed to

reduce or eliminate pollutant discharges from the site after construction is completed.

This site is located in an area subject to a Phase I or Phase II Municipal Separate Storm Sewer

System (MS4) permit approved Stormwater Management Plan. Yes No

The following source control post construction BMPs to comply with General Permit Section

XIII.B and local requirements have been identified for the site:

• Local percolation basins (seepage pits) are incldued on several well sites to handle

local run-off. These will be inspected and cleaned periodically.

• The main backwash percolation basin will be periodcally maintained by removing

accumulated silt and scarifying the pond bottom.

A plan for the post construction funding and maintenance of these BMPs has been developed to

address at minimum five years following construction. The post construction BMPs that are

described above shall be funded and maintained by the LRP. If required, post construction

funding and maintenance will be submitted with the NOT.

PWM Well Field Phase 3 43 August 2020

Section 4 BMP Inspection, Maintenance, and Rain

Event Action Plans

4.1 BMP INSPECTION AND MAINTENANCE

The General Permit requires routine weekly inspections of BMPs, along with inspections before,

during, and after qualifying rain events. A BMP inspection checklist must be filled out for

inspections and maintained on-site with the SWPPP. The inspection checklist includes the

necessary information covered in Section 7.6. A blank inspection checklist can be found in

Appendix I. Completed checklists shall be kept in CSMP Attachment 2 “Monitoring Records.

BMPs shall be maintained regularly to ensure proper and effective functionality. If necessary,

corrective actions shall be implemented within 72 hours of identified deficiencies and associated

amendments to the SWPPP shall be prepared by the QSD.

Specific details for maintenance, inspection, and repair of Construction Site BMPs can be found

in the BMP Factsheets in Appendix H.

4.2 RAIN EVENT ACTION PLANS

Rain Event Action Plans (REAPs) are not required for Risk Level 1 projects.

PWM Well Field Phase 3 44 August 2020

Section 5 Training

Appendix L identifies the QSPs for the project. To promote stormwater management awareness

specific for this project, periodic training of job-site personnel shall be included as part of routine

project meetings (e.g. daily/weekly tailgate safety meetings), or task specific trainings as needed.

The QSP shall be responsible for providing this information at the meetings, and subsequently

completing the training logs shown in Appendix K, which identifies the site-specific stormwater

topics covered as well as the names of site personnel who attended the meeting. Tasks may be

delegated to trained employees by the QSP provided adequate supervision and oversight is

provided. Training shall correspond to the specific task delegated including: SWPPP

implementation; BMP inspection and maintenance; and record keeping.

Documentation of training activities (formal and informal) is retained in SWPPP Appendix K.

PWM Well Field Phase 3 45 August 2020

Section 6 Responsible Parties and Operators

6.1 RESPONSIBLE PARTIES

Approved Signatories who are responsible for SWPPP implementation and have authority to sign

permit-related documents are listed below. Written authorizations from the LRP for these

individuals are provided in Appendix L. The Approved Signatories assigned to this project are:

Name Title Phone Number

Paul Sciuto , PE General Manager Monterey

One Water

(831) 645-4634

QSPs identified for the project are identified in Appendix L. The QSP shall have primary

responsibility and significant authority for the implementation, maintenance and

inspection/monitoring of SWPPP requirements. The QSP will be available at all times

throughout the duration of the project. Duties of the QSP include but are not limited to:

• Implementing all elements of the General Permit and SWPPP, including but not limited

to:

o Ensuring all BMPs are implemented, inspected, and properly maintained;

o Performing non-stormwater and stormwater visual observations and inspections;

o Performing non-stormwater and storm sampling and analysis, as required;

o Performing routine inspections and observations;

o Implementing non-stormwater management, and materials and waste management

activities such as: monitoring discharges; general Site clean-up; vehicle and

equipment cleaning, fueling and maintenance; spill control; ensuring that no materials

other than stormwater are discharged in quantities which will have an adverse effect

on receiving waters or storm drain systems; etc.;

• The QSP may delegate these inspections and activities to an appropriately trained

employee, but shall ensure adequacy and adequate deployment.

• Ensuring elimination of unauthorized discharges.

• The QSPs shall be assigned authority by the LRP to mobilize crews in order to make

immediate repairs to the control measures.

• Coordinate with the Contractor(s) to assure all of the necessary corrections/repairs are

made immediately and that the project complies with the SWPPP, the General Permit and

approved plans at all times.

• Notifying the LRP or Authorized Signatory immediately of off-site discharges or other

non-compliance events.

PWM Well Field Phase 3 46 August 2020

6.2 CONTRACTORS LIST

Contractor

Name:

Title:

Company:

Address:

Phone Number:

Number (24/7):

Qualified SWPPP Practitioner

Name: TBD

Title:

Company:

Address:

Phone Number:

Number (24/7):

Assigned inspector: QSP, TBD

Contact phone:

Alternate inspector: QSP, TBD

Contact phone: TBD

Sampling Analysis / Laboratory

Laboratory Name: Monterey Bay Analytical Services

Street Address: 4 Justin Court, Suite D

City/ State / Zip: Monterey, CA 93940

Telephone Number: (831) 375-MBAS (6227)

Point of Contact: TBD

ELAP Certification

Number:

Sample Collection Contractor / Personnel

PWM Well Field Phase 3 47 August 2020

Name: TBD

Title:

Company:

Address:

Phone Number:

Number (24/7):

Assigned inspector: QSP, TBD

Contact phone:

Alternate inspector: QSP, TBD

Contact phone: TBD

PWM Well Field Phase 3 48 August 2020

Section 7 Construction Site Monitoring Program

7.1 Purpose

This Construction Site Monitoring Program was developed to address the following objectives:

1. To demonstrate that the site is in compliance with the Discharge Prohibitions and

Numeric Action Levels (NALs) of the Construction General Permit;

2. To determine whether non-visible pollutants are present at the construction site and are

causing or contributing to exceedances of water quality objectives;

3. To determine whether immediate corrective actions, additional Best Management

Practices (BMP) implementation, or SWPPP revisions are necessary to reduce pollutants

in stormwater discharges and authorized non-stormwater discharges;

4. To determine whether BMPs included in the SWPPP and REAP are effective in

preventing or reducing pollutants in stormwater discharges and authorized non-

stormwater discharges.

7.2 Applicability of Permit Requirements

This project has been determined to be a Risk Level 1 project. The General Permit identifies the

following types of monitoring as being applicable for a Risk Level 1 project.

Risk Level 1

• Visual inspections of Best Management Practices (BMPs);

• Visual monitoring of the site related to qualifying storm events;

• Visual monitoring of the site for non-stormwater discharges;

• Sampling and analysis of construction site runoff for non-visible pollutants when

applicable; and

• Sampling and analysis of construction site runoff as required by the Regional Water

Board when applicable.

7.3. Weather and Rain Event Tracking

Visual monitoring and inspections requirements of the General Permit are triggered by a

qualifying rain event. The General Permit defines a qualifying rain event as any event that

produces ½ inch of precipitation. A minimum of 48 hours of dry weather will be used to

distinguish between separate qualifying storm events.

7.3.1 Weather Tracking

The QSP should daily consult the National Oceanographic and Atmospheric Administration

(NOAA) for the weather forecasts. These forecasts can be obtained at http://www.srh.noaa.gov/.

Weather reports should be printed and maintained with the SWPPP in CSMP Attachment 1

“Weather Reports”.

PWM Well Field Phase 3 49 August 2020

7.3.2 Rain Gauges

The QSP shall install 1 rain gauge on the project site. Locate the gauge in an open area away

from obstructions such as trees or overhangs. Mount the gauge on a post at a height of 3 to 5 feet

with the gauge extending several inches beyond the post. Make sure that the top of the gauge is

level. Make sure the post is not in an area where rainwater can indirectly splash from sheds,

equipment, trailers, etc.

The rain gauge shall be read daily during normal site scheduled hours. The rain gauge should be

read at approximately the same time every day and the date and time of each reading recorded.

Log rain gauge readings in CSMP Attachment 1 “Weather Records”. Follow the rain gauge

instructions to obtain accurate measurements.

Once the rain gauge reading has been recorded, accumulated rain shall be emptied and the gauge

reset. For comparison with the site rain gauge, the nearest appropriate governmental rain

gauge(s) is located at MONTEREY PENINSULA AIRPORT, Station GHCND:USW00023259.

7.4 Monitoring Locations

Monitoring locations are shown on the Erosion Control Plan in Appendix R. Monitoring

locations are described in the Sections 7.6 and 7.7.

Whenever changes in the construction site might affect the appropriateness of sampling

locations, the sampling locations shall be revised accordingly. All such revisions shall be

implemented as soon as feasible and the SWPPP amended. Temporary changes that result in a

one-time additional sampling location do not require a SWPPP amendment.

7.5 Safety and Monitoring Exemptions

Safety practices for sample collection will be in accordance with the Contractor’s Health and

Safety Plan. This project is not required to collect samples or conduct visual observations

(inspections) under the following conditions:

• During dangerous weather conditions such as flooding and electrical storms.

• Outside of scheduled site business hours.

Scheduled site business hours are: 7:00 a.m. to 5:00 p.m., Monday-Friday. 24-hour operations

during well drilling and development.

If monitoring (visual monitoring or sample collection) of the site is unsafe because of the

dangerous conditions noted above then the QSP shall document the conditions for why an

exception to performing the monitoring was necessary. The exemption documentation shall be

filed in CSMP Attachment 2 “Monitoring Records”.

7.6 Visual Monitoring

Visual monitoring includes observations and inspections. Inspections of BMPs are required to

identify and record BMPs that need maintenance to operate effectively, that have failed, or that

could fail to operate as intended. Visual observations of the site are required to observe storm

water drainage areas to identify any spills, leaks, or uncontrolled pollutant sources.

Table 7.1 identifies the required frequency of visual observations and inspections. Inspections

and observations will be conducted at the locations identified in Section 7.6.5.

PWM Well Field Phase 3 50 August 2020

Table 7.1 Summary of Visual Monitoring and Inspections

Type of Inspection Frequency

Routine Inspections

BMP Inspections Weekly1

BMP Inspections – Tracking Control Daily

Non-Stormwater Discharge Observations Quarterly during daylight hours

Rain Event Triggered Inspections

Site Inspections Prior to a Qualifying Event Within 48 hours of a qualifying event 2

BMP Inspections During an Extended Storm

Event Every 24-hour period of a rain event3

Site Inspections Following a Qualifying Event Within 48 hours of a qualifying event2

1 Most BMPs must be inspected weekly; those identified above must be inspected more frequently.

2 Inspections are required during scheduled site operating hours.

3 Inspections are required during scheduled site operating hours regardless of the amount of precipitation on any

given day.

7.6.1 Routine Observations and Inspections

Routine site inspections and visual monitoring are necessary to ensure that the project is in

compliance with the requirements of the Construction General Permit.

7.6.1.1 Routine BMP Inspections

Inspections of BMPs are conducted weekly to identify and record:

• BMPs that are properly installed;

• BMPs that need maintenance to operate effectively;

• BMPs that have failed; or

• BMPs that could fail to operate as intended.

Tracking control BMPs are inspected daily.

7.6.1.2 Non-Stormwater Discharge Observations

Each drainage area will be inspected for the presence of or indications of prior unauthorized and

authorized non-stormwater discharges. Inspections for non-stormwater discharges will be

conducted quarterly. Inspections will record:

• Presence or evidence of any non-stormwater discharge (authorized or unauthorized);

• Pollutant characteristics (floating and suspended material, sheen, discoloration, turbidity,

odor, etc.); and

• Source of discharge.

PWM Well Field Phase 3 51 August 2020

7.6.2 Rain-Event Triggered Observations and Inspections

Visual observations of the site and inspections of BMPs are required prior to a qualifying rain

event; following a qualifying rain event, and every 24-hour period during a qualifying rain event.

Pre-rain inspections will be conducted after consulting NOAA and determining that a

precipitation event with a 50% or greater probability of precipitation has been predicted.

7.6.2.1 Visual Observations Prior to a Forecasted Qualifying Rain Event

Within 48-hours prior to a qualifying event a stormwater visual monitoring site inspection will

include observations of the following locations:

• Stormwater drainage areas to identify any spills, leaks, or uncontrolled pollutant sources;

• BMPs to identify if they have been properly implemented;

• Any stormwater storage and containment areas to detect leaks and ensure maintenance of

adequate freeboard.

BMP inspections and visual monitoring will be triggered by a NOAA quantitative predicted

forecast (QPF) that indicates ½-inch or more of rain will occur in the project area.

7.6.2.2 BMP Inspections During an Extended Storm Event

During an extended rain event BMP inspections will be conducted to identify and record:

• BMPs that are properly installed;

• BMPs that need maintenance to operate effectively;

• BMPs that have failed; or

• BMPs that could fail to operate as intended.

If the construction site is not accessible during the rain event, the visual inspections shall be

performed at all relevant outfalls, discharge points, downstream locations. The inspections

should record any projected maintenance activities.

7.6.2.3 Visual Observations Following a Qualifying Rain Event

Within 48 hours following a qualifying rain event (0.5 inches of rain) a stormwater visual

monitoring site inspection is required to observe:

• Stormwater drainage areas to identify any spills, leaks, or uncontrolled pollutant sources;

• BMPs to identify if they have been properly designed, implemented, and effective;

• Need for additional BMPs;

• Discharge of stored or contained rain water.

7.6.3 Visual Monitoring Procedures

Visual monitoring shall be conducted by the QSP (see Section 6: Contractors) or staff trained by

and under the supervision of the QSP. Their training qualifications are provided in Appendix K.

Stormwater observations shall be documented on the Visual Inspection Field Log Sheet (see

CSMP Attachment 3 “Example Forms”). BMP inspections shall be documented on the site

specific BMP inspection checklist. Any photographs used to document observations will be

referenced on stormwater site inspection report and maintained with the Monitoring Records in

Attachment 2.

PWM Well Field Phase 3 52 August 2020

The QSP shall within 3 days of the inspection submit copies of the completed inspection report

to QSD. The completed reports will be kept in CSMP Attachment 2 “Monitoring Records”.

7.6.4 Visual Monitoring Follow-Up and Reporting

Correction of deficiencies identified by the observations or inspections, including required

repairs or maintenance of BMPs, shall be initiated and completed as soon as possible.

If identified deficiencies require design changes, including additional BMPs, the implementation

of changes will be initiated within 72 hours of identification and be completed as soon as

possible. When design changes to BMPs are required, the SWPPP shall be amended to reflect

the changes.

Deficiencies identified in site inspection reports and correction of deficiencies will be tracked on

the Inspection Field Log Sheet or BMP Inspection Report and shall be submitted to the QSP and

shall be kept in CSMP Attachment 2 “Monitoring Records”.

The QSP shall within 3 days of the inspection submit copies of the completed Inspection Field

Log Sheet or BMP Inspection Report with the corrective actions to QSD.

Results of visual monitoring must be summarized and reported in the Annual Report.

7.6.5 Visual Monitoring Locations

The inspections and observations identified in Sections 7.6.1 and 7.6.2 will be conducted at the

locations identified in this section.

BMP locations are shown on the Site Maps in SWPPP Appendix R.

There is 1 drainage area on the project site and the contractor’s yard, staging areas, and storage

areas. Drainage areas are shown on the Erosion Control Plan in Appendix R and Table 7.2

identifies each drainage area by location.

Table 7.2 Site Drainage Areas

Location

No. Location

DA-1 At the site of Deep Injection Well-3 (from maps)

DA-2 At the site of Deep Injection Well 4

There are no stormwater storage or containment areas on the project site. Stormwater drains to

the existing percolation area adjacent to the backwash percolation basin. The backwash basin is

intended to percolate water from backwashing the injection wells, so it will fill and drain weekly.

PWM Well Field Phase 3 53 August 2020

There is 1 discharge location on the project site. Site stormwater discharge location(s) are shown

on the Erosion Control Plan in Appendix R and Table 7.3 identifies each stormwater discharge

location.

Table 7.3 Site Stormwater Discharge Locations

Location

No. Location

SWD-1 Discharge from DA-1 (See Erosion Control Plan in Appendix R)

SWD-2 Discharge from DA-2

7.7 Water Quality Sampling and Analysis

7.7.1 Sampling and Analysis Plan for Non-Visible Pollutants in Stormwater Runoff Discharges

This Sampling and Analysis Plan for Non-Visible Pollutants describes the sampling and analysis

strategy and schedule for monitoring non-visible pollutants in stormwater runoff discharges from

the project site.

Sampling for non-visible pollutants will be conducted when (1) a breach, leakage, malfunction,

or spill is observed; and (2) the leak or spill has not been cleaned up prior to the rain event; and

(3) there is the potential for discharge of non-visible pollutants to surface waters or drainage

system.

The following construction materials, wastes, or activities, as identified in Section 2.6, are

potential sources of non-visible pollutants to stormwater discharges from the project. Storage,

use, and operational locations are shown on the Site Maps in Appendix B.

Materials

• Vehicle fluids, including oil, grease, petroleum, and coolants

• Asphaltic emulsions associated with asphalt concrete paving operations

• Cement materials associated with Portland cement concrete (PCC) paving operations,

trench installation and utility installation

• Base and subbase material

• Joint and curing compounds

• Concrete curing compounds

• Paints

• Solvents, thinners, and acids

• Raw landscaping materials and wastes (topsoil, plant materials, herbicides, fertilizers,

mulch, pesticides)

• BMP materials (sandbags)

• Treated lumber (materials and waste)

• PCC rubble

PWM Well Field Phase 3 54 August 2020

General litter

Activities

• Clearing and grubing operations

• Grading operations

• Utility excavation operations

• Well drilling and development operations

• Landscaping operations

• Painting

There are NO existing site features that may be potential sources of non-visible pollutants to

stormwater discharges from the project.

No soil amendments that have the potential to change the chemical properties, engineering

properties, or erosion resistance of the soil will be used on the project site.

PWM Well Field Phase 3 55 August 2020

7.7.1.1 Sampling Schedule

Samples for the potential non-visible pollutant(s) and a sufficiently large unaffected background

sample shall be collected during the first two hours of discharge from rain events that result in a

sufficient discharge for sample collection. Samples shall be collected during the site’s scheduled

hours and shall be collected regardless of the time of year and phase of the construction.

Collection of discharge samples for non-visible pollutant monitoring will be triggered when any

of the following conditions are observed during site inspections conducted prior to or during a

rain event.

• Materials or wastes containing potential non-visible pollutants are not stored under

watertight conditions. Watertight conditions are defined as (1) storage in a watertight

container, (2) storage under a watertight roof or within a building, or (3) protected by

temporary cover and containment that prevents stormwater contact and runoff from the

storage area.

• Materials or wastes containing potential non-visible pollutants are stored under watertight

conditions, but (1) a breach, malfunction, leakage, or spill is observed, (2) the leak or

spill is not cleaned up prior to the rain event, and (3) there is the potential for discharge of

non-visible pollutants to surface waters or a storm drain system.

• A construction activity, including but not limited to those in Section 2.6, with the

potential to contribute non-visible pollutants (1) was occurring during or within 24 hours

prior to the rain event, (2) BMPs were observed to be breached, malfunctioning, or

improperly implemented, and (3) there is the potential for discharge of non-visible

pollutants to surface waters or a storm drain system.

• Soil amendments that have the potential to change the chemical properties, engineering

properties, or erosion resistance of the soil have been applied, and there is the potential

for discharge of non-visible pollutants to surface waters or a storm drain system.

• Stormwater runoff from an area contaminated by historical usage of the site has been

observed to combine with stormwater runoff from the site, and there is the potential for

discharge of non-visible pollutants to surface waters or a storm drain system.

7.7.1.2 Sampling Locations

Sampling locations are based on proximity to planned non-visible pollutant storage, occurrence

or use; accessibility for sampling, and personnel safety. Planned non-visible pollutant sampling

locations are shown on the Erosion Control Plan in Appendix R and include the locations

identified in Tables 7.4 through 7.5.

One sampling location each on the project site and the contractor’s yard have been identified for

the collection of samples of runoff from planned material and waste storage areas and areas

where non-visible pollutant producing construction activities are planned.

PWM Well Field Phase 3 56 August 2020

Table 7.4 Non-Visible Pollutant Sample Locations – Contractors’ Yard

Sample Location

Number Sample Location Description

Sample Location Latitude and

Longitude

(Decimal Degrees)

NV-1 Discharge location from Well Site 1 36° 37' 09.62" N

121° 48' 40.39" W

1 sampling location(s) has been identified for the collection of an uncontaminated sample of

runoff as a background sample for comparison with the samples being analyzed for non-visible

pollutants. This location(s) was selected such that the sample will not have come in contact with

the operations, activities, or areas identified in Section 7.7.1 or with disturbed soils areas.

Table 7.5 Non-Visible Pollutant Sample Locations – Background (Unaffected Sample)

Sample Location

Number Sample Location

Sample Location Latitude and

Longitude

(Decimal Degrees)

BGD-1

TBD ; Select sampling location

upstream of the location where site

activities are planned

TBD

TBD

7.7.1.3 Monitoring Preparation

Non-visible pollutant samples will be collected by the Contractor, QSP, or his trained sampling

personnel listed in Section 6. The QSP or his/her designee will contact Monterey Bay Analytical

Services 24 hours prior to a predicted rain event or for an unpredicted event, as soon as a rain

event begins if one of the triggering conditions is identified during an inspection to ensure that

adequate sample collection personnel and supplies for monitoring non-visible pollutants are

available and will be mobilized to collect samples on the project site in accordance with the

sampling schedule. An adequate stock of monitoring supplies and equipment for monitoring

non-visible pollutants will be available on the project site prior to a sampling event. Monitoring

supplies and equipment will be stored in a cool temperature environment that will not come into

contact with rain or direct sunlight. Sampling personnel will be available to collect samples in

accordance with the sampling schedule. Supplies maintained at the project site will include, but

are not limited to, clean powder-free nitrile gloves, sample collection equipment, coolers,

appropriate number and volume of sample bottles, identification labels, re-sealable storage bags,

paper towels, personal rain gear, ice, and Effluent Sampling Field Log Sheets and Chain of

Custody (CoC) forms, which are provided in CSMP Attachment 3 “Example Forms”

.

PWM Well Field Phase 3 57 August 2020

7.7.1.4 Analytical Constituents

Table 7.6 lists the specific sources and types of potential non-visible pollutants on the project site

and the water quality indicator constituent(s) for that pollutant.

Table 7.6 Potential Non-Visible Pollutants and Water Quality Indicator Constituents

Pollutant Source Pollutant Water Quality Indicator

Constituent

Cleaning Acids pH

7.7.1.5 Sample Collection

Samples of discharge shall be collected at the designated non-visible pollutant sampling

locations shown on the Erosion Control Plan in Appendix R or in the locations determined by

observed breaches, malfunctions, leakages, spills, operational areas, soil amendment application

areas, and historical site usage areas that triggered the sampling event.

Grab samples shall be collected and preserved in accordance with the methods identified in the

Table, “Sample Collection, Preservation and Analysis for Monitoring Non-Visible Pollutants”

provided in Section 7.7.1.6. Only the QSP, or personnel trained in water quality sampling under

the direction of the QSP shall collect samples.

Sample collection and handling requirements are described in Section 7.7.7.

7.7.1.6 Sample Analysis

Samples shall be analyzed using the analytical methods identified in the Table 7.11, by Monterey

Bay Analytical Services. Laboratory address and point of contact information is listed in Section

6. Samples will be picked up by Laboratory Courier.

PWM Well Field 58 May 2017

Table 7.7 Sample Collection, Preservation and Analysis for Monitoring Non-Visible Pollutants

Constituent Analytical Method Minimum Sample

Volume Sample Containers

Sample

Preservation

Reporting

Limit

Maximum

Holding Time

pH SM 4500H+B

EPA 9040C/ 9045D

100 ml

100 ml

250 ml P

250 ml P

None

None 6.5 – 8.5

-

14 days

Turbidity SM 2130B 100 ml 250 ml P None 250 NTU 48 Hr

VOCs

EPA 8015

EPA 8021

EPA 8260

40 ml

40 ml

40 ml

3X 40 ml

3X40 ml

3X40 ml

HCL

HCL

HCL

14 days

14 days

14days

Notes:

PWM Well Field Phase 3 59 August 2020

7.7.1.7 Data Evaluation and Reporting

The QSP shall complete an evaluation of the water quality sample analytical results.

Runoff/downgradient results shall be compared with the associated upgradient/unaffected results

and any associated run-on results. Should the runoff/downgradient sample show an increased

level of the tested analyte relative to the unaffected background sample, which cannot be

explained by run-on results, the BMPs, site conditions, and surrounding influences shall be

assessed to determine the probable cause for the increase.

As determined by the site and data evaluation, appropriate BMPs shall be repaired or modified to

mitigate discharges of non-visible pollutant concentrations. Any revisions to the BMPs shall be

recorded as an amendment to the SWPPP.

The General Permit prohibits the storm water discharges that contain hazardous substances equal

to or in excess of reportable quantities established in 40 C.F.R. §§ 117.3 and 302.4. The results

of any non-stormwater discharge results that indicate the presence of a hazardous substance in

excess of established reportable quantities shall be immediately reported to the Regional Water

Board and other agencies as required by 40 C.F.R. §§ 117.3 and 302.4.

Results of non-visible pollutant monitoring shall be reported in the Annual Report.

7.7.2 Sampling and Analysis Plan for pH and Turbidity in Stormwater Runoff Discharges

Sampling and analysis of runoff for pH and turbidity is not required for Risk Level 1 projects

unless one of the aforementioned sampling triggers occurs.

7.7.3 Sampling and Analysis Plan for pH, Turbidity, and SSC in Receiving Water

This project is not subject to Receiving Water Monitoring.

7.7.3.1 Sampling Schedule and Locations

This project is not subject to Receiving Water Monitoring.

7.7.4 Sampling and Analysis Plan for Non-Stormwater Discharges

This project is not subject to the non-stormwater sampling and analysis requirements of the

General Permit because it is a Risk Level 1 project, unless triggered by above criteria.

PWM Well Field 60 May 2017

PWM Well Field Phase 3 61 August 2020

7.7.5 Sampling and Analysis Plan for Other Pollutants Required by the Regional Water Board

The Regional Water Board has not specified monitoring for additional pollutants.

7.7.6 Training of Sampling Personnel

Sampling personnel shall be trained to collect, maintain, and ship samples in accordance with the

Surface Water Ambient Monitoring program (SWAMP) 2008 Quality Assurance Program Plan

(QAPrP). Training records of designated contractor sampling personnel are provided in

Appendix K.

The stormwater sampler(s) and alternate(s) have received the following stormwater sampling

training: TBD

Name Training

INSERT LIST OF TRAINING COURSES

INSERT LIST OF TRAINING COURSES

The stormwater sampler(s) and alternates have the following stormwater sampling experience:

Name Experience

INSERT LIST OF STORMWATER SAMPLING EXPERIENCE

INSERT LIST OF STORMWATER SAMPLING EXPERIENCE

7.7.7 Sample Collection and Handling

7.7.7.1 Sample Collection

Samples shall be collected at the designated sampling locations shown on the Site Maps and

listed in the preceding sections. Samples shall be collected, maintained and shipped in

accordance with the SWAMP 2008 Quality Assurance Program Plan (QAPrP).

Grab samples shall be collected and preserved in accordance with the methods identified in

preceding sections.

To maintain sample integrity and prevent cross-contamination, sample collection personnel shall

follow the protocols below.

• Collect samples (for laboratory analysis) only in analytical laboratory-provided sample

containers;

• Wear clean, powder-free nitrile gloves when collecting samples;

• Change gloves whenever something not known to be clean has been touched;

• Change gloves between sites;

• Decontaminate all equipment (e.g. bucket, tubing) prior to sample collection using a

trisodium phosphate water wash, distilled water rinse, and final rinse with distilled water.

(Dispose of wash and rinse water appropriately, i.e., do not discharge to storm drain or

receiving water). Do not decontaminate laboratory provided sample containers;

PWM Well Field Phase 3 62 August 2020

• Do not smoke during sampling events;

• Never sample near a running vehicle;

• Do not park vehicles in the immediate sample collection area (even non-running

vehicles);

• Do not eat or drink during sample collection; and

• Do not breathe, sneeze, or cough in the direction of an open sample container.

The most important aspect of grab sampling is to collect a sample that represents the entire

runoff stream. Typically, samples are collected by dipping the collection container in the runoff

flow paths and streams as noted below.

i. For small streams and flow paths, simply dip the bottle facing upstream until full.

ii. For larger stream that can be safely accessed, collect a sample in the middle of the flow

stream by directly dipping the mouth of the bottle. Once again making sure that the

opening of the bottle is facing upstream as to avoid any contamination by the sampler.

iii. For larger streams that cannot be safely waded, pole-samplers may be needed to safely

access the representative flow.

iv. Avoid collecting samples from ponded, sluggish or stagnant water.

v. Avoid collecting samples directly downstream from a bridge as the samples can be

affected by the bridge structure or runoff from the road surface.

Note, that depending upon the specific analytical test, some containers may contain

preservatives. These containers should never be dipped into the stream, but filled indirectly from

the collection container.

7.7.7.2 Sample Handling

Turbidity and pH measurements must be conducted immediately. Do not store turbidity or pH

samples for later measurement.

Samples for laboratory analysis must be handled as follows. Immediately following sample

collection:

• Cap sample containers;

• Complete sample container labels;

• Sealed containers in a re-sealable storage bag;

• Place sample containers into an ice-chilled cooler;

• Document sample information on the Effluent Sampling Field Log Sheet; and

• Complete the CoC.

All samples for laboratory analysis must be maintained between 0-6 degrees Celsius during

delivery to the laboratory. Samples must be kept on ice, or refrigerated, from sample collection

through delivery to the laboratory. Place samples to be shipped inside coolers with ice. Make

sure the sample bottles are well packaged to prevent breakage and secure cooler lids with

packaging tape.

Ship samples that will be laboratory analyzed to the analytical laboratory right away. Hold times

are measured from the time the sample is collected to the time the sample is analyzed. The

General Permit requires that samples be received by the analytical laboratory within 48 hours of

the physical sampling (unless required sooner by the analytical laboratory).

PWM Well Field Phase 3 63 August 2020

7.7.7.3 Sample Documentation Procedures

All original data documented on sample bottle identification labels, Effluent Sampling Field Log

Sheet, and CoCs shall be recorded using waterproof ink. These shall be considered accountable

documents. If an error is made on an accountable document, the individual shall make

corrections by lining through the error and entering the correct information. The erroneous

information shall not be obliterated. All corrections shall be initialed and dated.

Duplicate samples shall be identified consistent with the numbering system for other samples to

prevent the laboratory from identifying duplicate samples. Duplicate samples shall be identified

in the Effluent Sampling Field Log Sheet.

Sample documentation procedures include the following:

Sample Bottle Identification Labels: Sampling personnel shall attach an identification label to

each sample bottle. Sample identification shall uniquely identify each sample location.

Field Log Sheets: Sampling personnel shall complete the Effluent Sampling Field Log Sheet and

Receiving Water Sampling Field Log Sheet for each sampling event, as appropriate.

Chain of Custody: Sampling personnel shall complete the CoC for each sampling event for

which samples are collected for laboratory analysis. The sampler will sign the CoC when the

sample(s) is turned over to the testing laboratory or courier.

7.8 Active Treatment System Monitoring

An Active Treatment System (ATS) will be deployed on the site?

Yes No

This project does not require a project specific Sampling and Analysis Plan for an ATS because

deployment of an ATS is not planned.

7.9 Bioassessment Monitoring

This project is not subject to bioassessment monitoring because it is not a Risk Level 3 project.

7.10 Watershed Monitoring Option

This project is not participating in a watershed monitoring option.

7.11 Quality Assurance and Quality Control

An effective Quality Assurance and Quality Control (QA/QC) plan shall be implemented as part

of the CSMP to ensure that analytical data can be used with confidence. QA/QC procedures to

be initiated include the following:

• Field logs;

• Clean sampling techniques;

• CoCs;

• QA/QC Samples; and

PWM Well Field Phase 3 64 August 2020

• Data verification.

Each of these procedures is discussed in more detail in the following sections.

7.11.1 Field Logs

The purpose of field logs is to record sampling information and field observations during

monitoring that may explain any uncharacteristic analytical results. Sampling information to be

included in the field log include the date and time of water quality sample collection, sampling

personnel, sample container identification numbers, and types of samples that were collected.

Field observations should be noted in the field log for any abnormalities at the sampling location

(color, odor, BMPs, etc.). Field measurements for pH and turbidity should also be recorded in

the field log. A Visual Inspection Field Log, and an Effluent Sampling Field Log Sheet are

included in CSMP Attachment 3 “Example Forms”.

7.11.2 Clean Sampling Techniques

Clean sampling techniques involve the use of certified clean containers for sample collection and

clean powder-free nitrile gloves during sample collection and handling. As discussed in Section

7.7.7, adoption of a clean sampling approach will minimize the chance of field contamination

and questionable data results.

7.11.3 Chain of Custody

The sample CoC is an important documentation step that tracks samples from collection through

analysis to ensure the validity of the sample. Sample CoC procedures include the following:

• Proper labeling of samples;

• Use of CoC forms for all samples; and

• Prompt sample delivery to the analytical laboratory.

Analytical laboratories usually provide CoC forms to be filled out for sample containers. An

example CoC is included in CSMP Attachment 3 “Example Forms”.

7.11.4 QA/QC Samples

QA/QC samples provide an indication of the accuracy and precision of the sample collection;

sample handling; field measurements; and analytical laboratory methods. The following types of

QA/QC will be conducted for this project:

Field Duplicates at a frequency of 1 duplicate minimum per sampling event.

(Required for all sampling plans with field measurements or laboratory analysis)

7.11.4.1 Field Duplicates

Field duplicates provide verification of laboratory or field analysis and sample collection.

Duplicate samples shall be collected, handled, and analyzed using the same protocols as primary

samples. The sample location where field duplicates are collected shall be randomly selected

from the discharge locations. Duplicate samples shall be collected immediately after the primary

sample has been collected. Duplicate samples must be collected in the same manner and as close

in time as possible to the original sample. Duplicate samples shall not influence any evaluations

or conclusion.

PWM Well Field Phase 3 65 August 2020

7.11.4.2 Equipment Blanks

Equipment blanks provide verification that equipment has not introduced a pollutant into the

sample. Equipment blanks are typically collected when:

• New equipment is used;

• Equipment that has been cleaned after use at a contaminated site;

• Equipment that is not dedicated for surface water sampling is used; or

• Whenever a new lot of filters is used when sampling metals.

7.11.4.3 Field Blanks

Field blanks assess potential sample contamination levels that occur during field sampling

activities. De-ionized water field blanks are taken to the field, transferred to the appropriate

container, and treated the same as the corresponding sample type during the course of a sampling

event.

7.11.4.4 Travel Blanks

Travel blanks assess the potential for cross-contamination of volatile constituents between

sample containers during shipment from the field to the laboratory. De-ionized water blanks are

taken along for the trip and held unopened in the same cooler with the VOC samples.

7.11.5 Data Verification

After results are received from the analytical laboratory, the QSP shall verify the data to ensure

that it is complete, accurate, and the appropriate QA/QC requirements were met. Data must be

verified as soon as the data reports are received. Data verification shall include:

• Check the CoC and laboratory reports.

Make sure all requested analyses were performed and all samples are accounted for in

the reports.

• Check laboratory reports to make sure hold times were met and that the reporting levels

meet or are lower than the reporting levels agreed to in the contract.

• Check data for outlier values and follow up with the laboratory.

Occasionally typographical errors, unit reporting errors, or incomplete results are

reported and should be easily detected. These errors need to be identified, clarified, and

corrected quickly by the laboratory. The QSP should especially note data that is an

order of magnitude or more different than similar locations, or is inconsistent with

previous data from the same location.

• Check laboratory QA/QC results.

EPA establishes QA/QC checks and acceptable criteria for laboratory analyses. These

data are typically reported along with the sample results. The QSP shall evaluate the

reported QA/QC data to check for contamination (method, field, and equipment blanks),

precision (laboratory matrix spike duplicates), and accuracy (matrix spikes and

laboratory control samples). When QA/QC checks are outside acceptable ranges, the

laboratory must flag the data, and usually provides an explanation of the potential

impact to the sample results.

• Check the data set for outlier values and, accordingly, confirm results and re-analyze

samples where appropriate.

PWM Well Field Phase 3 66 August 2020

Sample re-analysis should only be undertaken when it appears that some part of the

QA/QC resulted in a value out of the accepted range. Sample results may not be

discounted unless the analytical laboratory identifies the required QA/QC criteria were

not met and confirms this in writing.

Field data including inspections and observations must be verified as soon as the field logs are

received, typically at the end of the sampling event. Field data verification shall include:

• Check field logs to make sure all required measurements were completed and

appropriately documented;

• Check reported values that appear out of the typical range or inconsistent;

Follow-up immediately to identify potential reporting or equipment problems, if

appropriate, recalibrate equipment after sampling;

• Verify equipment calibrations;

• Review observations noted on the field logs; and

• Review notations of any errors and actions taken to correct the equipment or recording

errors.

7.12 Records Retention

All records of stormwater monitoring information and copies of reports (including Annual

Reports) must be retained for a period of at least three years from date of submittal or longer if

required by the Regional Water Board.

Results of visual monitoring, field measurements, and laboratory analyses must be kept in the

SWPPP along with CoCs, and other documentation related to the monitoring.

Records are to be kept onsite while construction is ongoing. Records to be retained include:

• The date, place, and time of inspections, sampling, visual observations, and/or

measurements, including precipitation;

• The individual(s) who performed the inspections, sampling, visual observation, and/or

field measurements;

• The date and approximate time of field measurements and laboratory analyses;

• The individual(s) who performed the laboratory analyses;

• A summary of all analytical results, the method detection limits and reporting limits, and

the analytical techniques or methods used;

• Rain gauge readings from site inspections;

• QA/QC records and results;

• Calibration records;

• Visual observation and sample collection exemption records;

• The records of any corrective actions and follow-up activities that resulted from

analytical results, visual observations, or inspections; and

• NAL Exceedance Reports.

PWM Well Field Phase 3 67 August 2020

CSMP Attachment 1: Weather Reports

PWM Well Field Phase 3 68 August 2020

PWM Well Field Phase 3 69 August 2020

CSMP Attachment 2: Monitoring Records

PWM Well Field Phase 3 70 August 2020

PWM Well Field Phase 3 71 August 2020

CSMP Attachment 3: Example Forms

PWM Well Field Phase 3 72 August 2020

PWM Well Field Phase 3 73 August 2020

Rain Gauge Log Sheet

Construction Site Name:

WDID #:

Date (mm/dd/yy)

Time (24-hr) Initials Rainfall Depth

(Inches) Notes:

PWM Well Field Phase 3 74 August 2020

Risk Level 1 Visual Inspection Field Log Sheet

Date and Time of Inspection: Report Date:

Inspection Type: □ Weekly □ Before predicted rain

□ During rain event

□ Following qualifying rain event

□ Contained stormwater release

□ Quarterly non-stormwater

Site Information

Construction Site Name:

Construction stage and completed activities:

Approximate area of exposed site:

Weather and Observations

Date Rain Predicted to Occur: Predicted % chance of rain:

Estimate storm beginning:

(date and time)

Estimate storm duration:_________

(hours)

Estimate time since last storm:

________ (days or hours)

Rain gauge reading: _______

(inches)

Observations: If yes identify location Odors Yes □ No □ Floating material Yes □ No □ Suspended Material Yes □ No □ Sheen Yes □ No □ Discolorations Yes □ No □ Turbidity Yes □ No □

Site Inspections

Outfalls or BMPs Evaluated Deficiencies Noted

(add additional sheets or attached detailed BMP Inspection Checklists)

Photos Taken: Yes □ No □ Photo Reference IDs:

Corrective Actions Identified (note if SWPPP/REAP change is needed)

Inspector Information

Inspector Name: Inspector Title:

Signature: Date:

PWM Well Field Phase 3 75 August 2020

PWM Well Field Phase 3 76 August 2020

PWM Well Field Phase 3 77 August 2020

PWM Well Field Phase 3 78 August 2020

NAL Exceedance Evaluation Summary Report Page __ of __

Project Name

Project WDID

Project Location

Date of Exceedance

Type of Exceedance

NAL Daily Average pH Turbidity

Other (specify)

Measurement or Analytical Method

Field meter

(Sensitivity: )

Lab method (specify)

(Reporting Limit: )

(MDL: )

Calculated Daily Average

pH pH units

Turbidity NTU

Rain Gauge Measurement

Inches

Compliance Storm Event

inches (5-year, 24-hour event)

Visual Observations on Day of Exceedance

PWM Well Field Phase 3 79 August 2020

NAL Exceedance Evaluation Summary Report Page __ of __

Description of BMPs in Place at Time of Event

Initial Assessment of Cause

Corrective Actions Taken (deployed after exceedance)

Additional Corrective Actions Proposed

Report Completed By

(Print Name, Title)

Signature

PWM Well Field 80 May 2017

CHAIN-OF-CUSTODY DATE: Lab ID:

DESTINATION LAB: REQUESTED ANALYSIS Notes:

ATTN:

ADDRESS:

Office Phone:

Cell Phone:

SAMPLED BY:

Contact:

Project Name

Client Sample ID Sample Sample Sample Container

Date Time Matrix # Type Pres.

SENDER COMMENTS:

RELINQUISHED BY

Signature: Print: Company: Date: TIME:

LABORATORY COMMENTS: RECEIVED BY

Signature: Print: Company: Date: TIME:

PWM Well Field 81 May 2017

CSMP Attachment 4: Field Meter Instructions

PWM Well Field 82 May 2017

PWM Well Field 83 May 2017

CSMP Attachment 5: Supplemental Information

PWM Well Field 84 May 2017

PWM Well Field 85 May 2017

Section 8 References

Project Plans and Specifications No. Monterey One Water, PWM Groundwater Replenishment

Project, Injection Well Facilities, Phase 3 dated August 2020, prepared by Kennedy/Jenks

Consultants and Schaaf and Wheeler Consulting Civil Engineers

State Water Resources Control Board (2009). Order 2009-0009-DWQ, NPDES General Permit

No. CAS000002: National Pollutant Discharges Elimination System (NPDES) California

General Permit for Storm Water Discharge Associated with Construction and Land Disturbing

Activities. Available on-line at:

http://www.waterboards.ca.gov/water_issues/programs/stormwater/construction.shtml.

State Water Resources Control Board (2010). Order 2010-0014-DWQ, NPDES General Permit

No. CAS000002: National Pollutant Discharges Elimination System (NPDES) California

General Permit for Storm Water Discharge Associated with Construction and Land Disturbing

Activities. Available on-line at:

http://www.waterboards.ca.gov/water_issues/programs/stormwater/construction.shtml.

State Water Resources Control Board (2012). Order 2012-0006-DWQ, NPDES General Permit

No. CAS000002: National Pollutant Discharges Elimination System (NPDES) California

General Permit for Storm Water Discharge Associated with Construction and Land Disturbing

Activities. Available on-line at:

http://www.waterboards.ca.gov/water_issues/programs/stormwater/construction.shtml.

Schaaf and Wheeler (2016). Pure Water Monterey Injection Well Field Civil Work Plan

Pacific Crest Engineering Inc. (2004). Percolation Test Results, General Jim Moore Boulevard

and Eucalyptus Road, Seaside California

Pacific Crest Engineering, Inc. (2016). Geotechnical Investigations, Design Phase, Groundwater

Recharge Injection Well Facilities, Pure Water Monterey Project, Seaside, California

CASQA 2009, Stormwater BMP Handbook Portal: Construction, November 2009,

www.casqa.org

PWM Well Field Phase 3 86 August 2020

Appendix A: Calculations

PWM Well Field Phase 3 87 August 2020

1

2

34

5

6

7

8

9

10

11

12

131415

1617181920

A B C

Entry

48.41

0.1

1.92

Watershed Erosion Estimate (=RxKxLS) in tons/acre

Site Sediment Risk FactorLow Sediment Risk: < 15 tons/acre

Medium Sediment Risk: >=15 and <75 tons/acreHigh Sediment Risk: >= 75 tons/acre

Sediment Risk Factor Worksheet

A) R Factor

R Factor Value

B) K Factor

Analyses of data indicated that when factors other than rainfall are held constant, soil loss is directly proportional to a rainfall factor composed of total storm kinetic energy (E) times the maximum 30-min intensity (I30) (Wischmeier and Smith, 1958). The numerical value of R is the average annual sum of EI30 for storm events during a rainfall record of at least 22 years. "Isoerodent" maps were developed based on R values calculated for more than 1000 locations in the Western U.S. Refer to the link below to determine the R factor for the project site.http://cfpub.epa.gov/npdes/stormwater/LEW/lewCalculator.cfm

K Factor Value

LS Factor Value

Low

C) LS Factor (weighted average, by area, for all slopes)

The soil-erodibility factor K represents: (1) susceptibility of soil or surface material to erosion, (2) transportability of the sediment, and (3) the amount and rate of runoff given a particular rainfall input, as measured under a standard condition. Fine-textured soils that are high in clay have low K values (about 0.05 to 0.15) because the particles are resistant to detachment. Coarse-textured soils, such as sandy soils, also have low K values (about 0.05 to 0.2) because of high infiltration resulting in low runoff even though these particles are easily detached. Medium-textured soils, such as a silt loam, have moderate K values (about 0.25 to 0.45) because they are moderately susceptible to particle detachment and they produce runoff at moderate rates. Soils having a high silt content are especially susceptible to erosion and have high K values, which can exceed 0.45 and can be as large as 0.65. Silt-size particles are easily detached and tend to crust, producing high rates and large volumes of runoff. Use Site-specific data must be submitted.

The effect of topography on erosion is accounted for by the LS factor, which combines the effects of a hillslope-length factor, L, and a hillslope-gradient factor, S. Generally speaking, as hillslope length and/or hillslope gradient increase, soil loss increases. As hillslope length increases, total soil loss and soil loss per unit area increase due to the progressive accumulation of runoff in the downslope direction. As the hillslope gradient increases, the velocity and erosivity of runoff increases. Use the LS table located in separate tab of this spreadsheet to determine LS factors. Estimate the weighted LS for the site prior to construction.

9.29472

Site-specific K factor guidance

LS Table

Receiving Water (RW) Risk Factor Worksheet Entry Score

A. Watershed Characteristics yes/no

A.1. Does the disturbed area discharge (either directly or indirectly) to a 303(d)-listed

waterbody impaired by sediment (For help with impaired waterbodies please visit the link below) or has a USEPA approved TMDL implementation plan for sediment?:http://www.waterboards.ca.gov/water_issues/programs/tmdl/integrated2010.shtml

ORA.2. Does the disturbed area discharge to a waterbody with designated beneficial uses of SPAWN & COLD & MIGRATORY? (For help please review the appropriate Regional Board Basin Plan)

http://www.waterboards.ca.gov/waterboards_map.shtml

Region 1 Basin Plan

Region 2 Basin Plan

Region 3 Basin Plan

Region 4 Basin Plan

Region 5 Basin Plan

Region 6 Basin Plan

Region 7 Basin Plan

Region 8 Basin Plan

Region 9 Basin Plan

no Low

Low Medium High

Low Level 1

High Level 3

Project Sediment Risk: Low 1Project RW Risk: Low 1

Project Combined Risk: Level 1

Combined Risk Level Matrix

Sediment Risk

Rec

eivi

ng W

ater

R

isk Level 2

Level 2

SP-SM soils, 6% to 13% passing #200 sieve

Soil Erodibility Factor (K)

The K factor can be determined by using the nomograph method, which requires that a particle size analysis (ASTM D-422) be done to determine the percentages of sand, very fine sand, silt and clay. Use the figure below to determine appropriate K value.

Erickson triangular nomograph used to estimate soil erodibility (K) factor. The figure above is the USDA nomograph used to determine the K factor for a soil, based on its texture (% silt plus very fine sand, % sand, % organic matter, soil structure, and permeability). Nomograph from Erickson 1977 as referenced in Goldman et. al., 1986.

Average Watershed Slope (%)Sheet

Flow

Length

(ft) 0.2 0.5 1.0 2.0 3.0 4.0 5.0 6.0 8.0 10.0 12.0 14.0 16.0 20.0 25.0 30.0 40.0 50.0 60.0

<3 0.05 0.07 0.09 0.13 0.17 0.20 0.23 0.26 0.32 0.35 0.36 0.38 0.39 0.41 0.45 0.48 0.53 0.58 0.636 0.05 0.07 0.09 0.13 0.17 0.20 0.23 0.26 0.32 0.37 0.41 0.45 0.49 0.56 0.64 0.72 0.85 0.97 1.079 0.05 0.07 0.09 0.13 0.17 0.20 0.23 0.26 0.32 0.38 0.45 0.51 0.56 0.67 0.80 0.91 1.13 1.31 1.47

12 0.05 0.07 0.09 0.13 0.17 0.20 0.23 0.26 0.32 0.39 0.47 0.55 0.62 0.76 0.93 1.08 1.37 1.62 1.8415 0.05 0.07 0.09 0.13 0.17 0.20 0.23 0.26 0.32 0.40 0.49 0.58 0.67 0.84 1.04 1.24 1.59 1.91 2.1925 0.05 0.07 0.10 0.16 0.21 0.26 0.31 0.36 0.45 0.57 0.71 0.85 0.98 1.24 1.56 1.86 2.41 2.91 3.3650 0.05 0.08 0.13 0.21 0.30 0.38 0.46 0.54 0.70 0.91 1.15 1.40 1.64 2.10 2.67 3.22 4.24 5.16 5.9775 0.05 0.08 0.14 0.25 0.36 0.47 0.58 0.69 0.91 1.20 1.54 1.87 2.21 2.86 3.67 4.44 5.89 7.20 8.37

100 0.05 0.09 0.15 0.28 0.41 0.55 0.68 0.82 1.10 1.46 1.88 2.31 2.73 3.57 4.59 5.58 7.44 9.13 10.63150 0.05 0.09 0.17 0.33 0.50 0.68 0.86 1.05 1.43 1.92 2.51 3.09 3.68 4.85 6.30 7.70 10.35 12.75 14.89200 0.06 0.10 0.18 0.37 0.57 0.79 1.02 1.25 1.72 2.34 3.07 3.81 4.56 6.04 7.88 9.67 13.07 16.16 18.92250 0.06 0.10 0.19 0.40 0.64 0.89 1.16 1.43 1.99 2.72 3.60 4.48 5.37 7.16 9.38 11.55 15.67 19.42 22.78300 0.06 0.10 0.20 0.43 0.69 0.98 1.28 1.60 2.24 3.09 4.09 5.11 6.15 8.23 10.81 13.35 18.17 22.57 26.51400 0.06 0.11 0.22 0.48 0.80 1.14 1.51 1.90 2.70 3.75 5.01 6.30 7.60 10.24 13.53 16.77 22.95 28.60 33.67600 0.06 0.12 0.24 0.56 0.96 1.42 1.91 2.43 3.52 4.95 6.67 8.45 10.26 13.94 18.57 23.14 31.89 39.95 47.18800 0.06 0.12 0.26 0.63 1.10 1.65 2.25 2.89 4.24 6.03 8.17 10.40 12.69 17.35 23.24 29.07 40.29 50.63 59.93

1000 0.06 0.13 0.27 0.69 1.23 1.86 2.55 3.30 4.91 7.02 9.57 12.23 14.96 20.57 27.66 34.71 48.29 60.84 72.15

LS Factors for Construction Sites. Table from Renard et. al., 1997.

Method used to calculated LSLength of sheet flow along the diagonal of the 250 ft X 100 ft work area 290.00 ftHigh point elevation 460 ft northeast corner of padLow point elevation 440 ft southwest corner of padWatershed slope (%) 7%Using Sheet Flow Length = 141 ft and watershed slope = 10%, LS value = 1.92

National Pollutant Discharge EliminationSystem (NPDES)

CONTACT US

SHARE

Rainfall Erosivity Factor Calculator for SmallConstruction SitesEPA’s stormwater regulations allow NPDES permitting authorities to waive NPDES permitting requirements for stormwaterdischarges from small construction sites if:

the construction site disturbs less than five acres, andthe rainfall erosivity factor (“R” in the revised universal soil loss equation, or RUSLE) value is less than five during the period ofconstruction activity.

If your small construction project is located in an area where EPA is the permitting authority and your R factor is less than five, youqualify for a low erosivity waiver (LEW) from NPDES stormwater permitting. If your small construction project does not qualify for awaiver, then NPDES stormwater permit coverage is required. Follow the steps below to calculate your R-Factor.

LEW certifications are submitted through the NPDES eReporting Tool or “CGP-NeT”. Several states that are authorized to implementthe NPDES permitting program also accept LEWs. Check with your state NPDES permitting authority for more information.

Submit your LEW through EPA’s eReporting ToolList of states, Indian country, and territories where EPA is the permitting authorityConstruction Rainfall Erosivity Waiver Fact SheetAppendix C of the 2017 CGP – Small Construction Waivers and Instructions

The R-factor calculation can also be integrated directly into custom applications using the R-Factor web service.

For questions or comments, email EPA’s CGP staff at [email protected].

Select the estimated start and end dates of construction by clicking the boxes and using the dropdown calendar.

The period of construction activity begins at initial earth disturbance and ends with final stabilization.

Locate your small construction project using the search box below or by clicking on the map.

Location: -121.8156977057751 , 36.61848544608761 Search

1

Start Date: 11/01/2020 End Date: 10/31/2021

2

Click the "Calculate R Factor" button below to calculate an R Factor for your small construction project.

Calculate R Factor

Bureau of Land Management, Esri, HERE, Garmin, INCREMENT P, Intermap, USGS, METI/NASA, EPA, USDA Powered by Esri

3

Facility Information

Start Date: 11/01/2020 Latitude: 36.6185

End Date: 10/31/2021 Longitude: -121.8157

Calculation ResultsRainfall erosivity factor (R Factor) = 48.41

A rainfall erosivity factor of 5.0 or greater has been calculated for your site's period of construction.

You do NOT qualify for a waiver from NPDES permitting requirements and must seek Construction General Permit (CGP)coverage. If you are located in an area where EPA is the permitting authority, you must submit a Notice of Intent (NOI) through the NPDESeReporting Tool (NeT).Otherwise, you must seek coverage under your state’s CGP.

National Pollutant Discharge EliminationSystem (NPDES)

CONTACT US

SHARE

Rainfall Erosivity Factor Calculator for SmallConstruction SitesEPA’s stormwater regulations allow NPDES permitting authorities to waive NPDES permitting requirements for stormwaterdischarges from small construction sites if:

the construction site disturbs less than five acres, andthe rainfall erosivity factor (“R” in the revised universal soil loss equation, or RUSLE) value is less than five during the period ofconstruction activity.

If your small construction project is located in an area where EPA is the permitting authority and your R factor is less than five, youqualify for a low erosivity waiver (LEW) from NPDES stormwater permitting. If your small construction project does not qualify for awaiver, then NPDES stormwater permit coverage is required. Follow the steps below to calculate your R-Factor.

LEW certifications are submitted through the NPDES eReporting Tool or “CGP-NeT”. Several states that are authorized to implementthe NPDES permitting program also accept LEWs. Check with your state NPDES permitting authority for more information.

Submit your LEW through EPA’s eReporting ToolList of states, Indian country, and territories where EPA is the permitting authorityConstruction Rainfall Erosivity Waiver Fact SheetAppendix C of the 2017 CGP – Small Construction Waivers and Instructions

The R-factor calculation can also be integrated directly into custom applications using the R-Factor web service.

For questions or comments, email EPA’s CGP staff at [email protected].

Select the estimated start and end dates of construction by clicking the boxes and using the dropdown calendar.

The period of construction activity begins at initial earth disturbance and ends with final stabilization.

Locate your small construction project using the search box below or by clicking on the map.

Location: -121.8156977057751 , 36.61848544608761 Search

1

Start Date: 11/01/2020 End Date: 10/31/2021

2

Click the "Calculate R Factor" button below to calculate an R Factor for your small construction project.

Calculate R Factor

Bureau of Land Management, Esri, HERE, Garmin, INCREMENT P, Intermap, USGS, METI/NASA, EPA, USDA Powered by Esri

3

Facility Information

Start Date: 11/01/2020 Latitude: 36.6185

End Date: 10/31/2021 Longitude: -121.8157

Calculation ResultsRainfall erosivity factor (R Factor) = 48.41

A rainfall erosivity factor of 5.0 or greater has been calculated for your site's period of construction.

You do NOT qualify for a waiver from NPDES permitting requirements and must seek Construction General Permit (CGP)coverage. If you are located in an area where EPA is the permitting authority, you must submit a Notice of Intent (NOI) through the NPDESeReporting Tool (NeT).Otherwise, you must seek coverage under your state’s CGP.

PWM Well Field Phase 3 88 August 2020

Appendix B: Site Maps

PWM Well Field Phase 3 89 August 2020

NORTHING EASTING ELEVATIONCP 1901 2119586.23 5734485.92 308.69CP 1902 2119117.78 5734293.97 317.63CP 1903 2120377.36 5736373.33 424.39CP 1904 2121557.09 5736069.28 401.99

4

3

2

1

0

0

USE OF DOCUMENTS

25mm

SCALES

1"

CHECKED

DESIGNED

DRAWN

0

Kennedy/Jenks Consultants

DATE

SHEET

FILE NAME

JOB NO.

D E F G HA B C

IF THIS BAR IS NOT

DIMENSION SHOWN,

ADJUST SCALES

ACCORDINGLY.

THIS DOCUMENT, INCLUDING THE INCORPORATED

DESIGNS, IS AN INSTRUMENT OF SERVICE FOR THIS

PROJECT AND SHALL NOT BE USED FOR ANY OTHER

PROJECT WITHOUT THE WRITTEN AUTHORIZATION

OF KENNEDY/JENKS CONSULTANTS.

NO. REVISION DATE BY

1668012.05

PURE WATER MONTEREY

GROUNDWATER REPLENISHMENT PROJECT

INJECTION WELL FACILITIES

PHASE 3

SEPTEMBER 2020

M:\K

JC

I\0

3-D

IW

-3

\D

ra

win

gs\1

66

80

12

05

-G

-0

05

.d

wg 9

/2

3/2

02

0 A

Ste

rb

en

z

(831) 883-4848Salinas, CA 93907-2348

3 Quail Run Circle, Suite 101

9/1/2020

CP 1903

424.39

INK X

CP 1902

317.63

MAG NAIL

CP 1901

308.69

MAG NAIL

PERCOLATION BASIN

(EXISTING)

WELL SITE NO. 2 (EXISTING)

WELLS MW-1D, MW-1S, DIW-1 AND VZW-1B

(E) MCWD HYDRANT

WELL SITE NO. 4 (NEW)

DIW-4

SEE C-140 1

WELL SITE NO. 3 (EXISTING)

WELLS MW-2D, MW-2S AND DIW-2

ELECTRICAL EQUIPMENT SITE

(EXISTING)

WELL SITE NO. 1 (NEW)

WELL DIW-3

SEE SHEET C-110

MONITORING WELL

(EXISTING)

MONITORING WELL

(EXISTING)

N 2118800

N 2119800

N 2120800

N 2121800

E 5

73

73

00

E 5

73

63

00

E 5

73

53

00

E 5

73

43

00

JCT

JCT

AAS

1 ADDENDUM NO. 1 9/25/2020 AAS

WELLFIELD SITE PLAN, ACCESS

AND SURVEY CONTROL

G-005

166801205-G-005.DWG

STA 24+00

END PHASE 2 / BEGIN PHASE 3

M:\K

JC

I\03-D

IW

-3\D

raw

in

gs\166801205-G

-005.d

wg

, G

005 SITE C

ON

TR

OL, 9/23/2020 6:25:21 P

M

4

3

2

1

0

0

USE OF DOCUMENTS

25mm

SCALES

1"

CHECKED

DESIGNED

DRAWN

0

Kennedy/Jenks Consultants

DATE

SHEET

FILE NAME

JOB NO.

D E F G HA B C

IF THIS BAR IS NOT

DIMENSION SHOWN,

ADJUST SCALES

ACCORDINGLY.

THIS DOCUMENT, INCLUDING THE INCORPORATED

DESIGNS, IS AN INSTRUMENT OF SERVICE FOR THIS

PROJECT AND SHALL NOT BE USED FOR ANY OTHER

PROJECT WITHOUT THE WRITTEN AUTHORIZATION

OF KENNEDY/JENKS CONSULTANTS.

NO. REVISION DATE BY

1668012.05

PURE WATER MONTEREY

GROUNDWATER REPLENISHMENT PROJECT

INJECTION WELL FACILITIES

PHASE 3

SEPTEMBER 2020

M:\K

JC

I\0

3-D

IW

-3

\D

ra

win

gs\1

66

80

12

05

-C

-1

10

.d

wg

9

/1

/2

02

0 A

Ste

rb

en

z

(831) 883-4848Salinas, CA 93907-2348

3 Quail Run Circle, Suite 101

9/1/2020

OIL MOVEMENT BOUNDARY;

SOIL ONLY ALLOWED TO

MOVE FROM THE NORTH TO

THE SOUTH, IF AT ALL

WELL DIW-3

AAS

AAS

AAS

WELL SITE NO. 1

HORIZONTAL CONTROL AND WELL DATA

C-110

166801205-C-110.DWG

EXPLORATORY

BOREHOLE

M:\K

JC

I\03-D

IW

-3\D

raw

in

gs\166801205-C

-110.d

wg

, C

-110, 9/1/2020 12:03:18 P

M

4

3

2

1

0

0

USE OF DOCUMENTS

25mm

SCALES

1"

CHECKED

DESIGNED

DRAWN

0

Kennedy/Jenks Consultants

DATE

SHEET

FILE NAME

JOB NO.

D E F G HA B C

IF THIS BAR IS NOT

DIMENSION SHOWN,

ADJUST SCALES

ACCORDINGLY.

THIS DOCUMENT, INCLUDING THE INCORPORATED

DESIGNS, IS AN INSTRUMENT OF SERVICE FOR THIS

PROJECT AND SHALL NOT BE USED FOR ANY OTHER

PROJECT WITHOUT THE WRITTEN AUTHORIZATION

OF KENNEDY/JENKS CONSULTANTS.

NO. REVISION DATE BY

1668012.05

PURE WATER MONTEREY

GROUNDWATER REPLENISHMENT PROJECT

INJECTION WELL FACILITIES

PHASE 3

SEPTEMBER 2020

S:\M

B_

Jo

bs\K

JC

I\0

3-D

IW

-3

\D

ra

win

gs\1

66

80

12

05

-C

-1

40

.d

wg

9

/2

5/2

02

0 A

Ste

rb

en

z

(831) 883-4848Salinas, CA 93907-2348

3 Quail Run Circle, Suite 101

9/1/2020

OIL MOVEMENT BOUNDARY;

SOIL ONLY ALLOWED TO

MOVE FROM THE NORTH TO

THE SOUTH, IF AT ALL

AAS

AAS

AAS

1 ADDENDUM NO. 1 9/25/2020 AAS

WELL SITE NO. 4

HORIZONTAL CONTROL AND WELL DATA

C-140

166801205-C-140.DWG

S:\M

B_Jo

bs\K

JC

I\03-D

IW

-3\D

raw

in

gs\166801205-C

-140.d

wg

, C

-140, 9/25/2020 3:58:45 P

M

PWM Well Field Phase 3 90 August 2020

Appendix C: Permit Registration Documents

PWM Well Field Phase 3 91 August 2020

Permit Registration Documents included in this Appendix

Y Permit Registration Document

Y Notice of Intent

Y Risk Assessment

Y Certification

Post Construction Water Balance

Y Copy of Annual Fee Receipt

ATS Design Documents

Y Site Map, see Appendix B

PWM Well Field Phase 3 92 August 2020

Appendix D: SWPPP Amendments

PWM Well Field Phase 3 93 August 2020

PWM Well Field Phase 3 94 August 2020

SWPPP Amendment No.

Project Name:

Project Number:

PWM Well Field Phase 3 95 August 2020

Appendix E: Submitted Changes to PRDs

PWM Well Field Phase 3 96 August 2020

Log of Updated PRDs

The General Permit allows for the reduction or increase of the total acreage covered under the General Permit

when a portion of the project is complete and/or conditions for termination of coverage have been met; when

ownership of a portion of the project is purchased by a different entity; or when new acreage is added to the

project.

Modified PRDs shall be filed electronically within 30 days of a reduction or increase in total disturbed area if a

change in permit covered acreage is to be sought. The SWPPP shall be modified appropriately, with revisions

and amendments recorded in Appendix C. Updated PRDs submitted electronically via SMARTS can be found

in this Appendix.

This appendix includes all of the following updated PRDs (check all that apply):

Revised Notice of Intent (NOI);

Revised Site Map;

Revised Risk Assessment;

New landowner’s information (name, address, phone number, email address); and

New signed certification statement.

Legally Responsible Person [if organization]

Signature of [Authorized Representative of] Legally

Responsible Person or Approved Signatory

Date

Name of [Authorized Representative of] Legally

Responsible Person or Approved Signatory

Telephone Number

PWM Well Field Phase 3 97 August 2020

Appendix F: Construction Schedule

PWM Well Field Phase 3 98 August 2020

PWM Well Field Phase 3 99 August 2020

Appendix G: Construction Activities, Materials Used, and

Associated Pollutants

PWM Well Field Phase 3 100 August 2020

PWM Well Field Phase 3 101 August 2020

Table G.1 Construction Activities and Associated Pollutants

Phase Activity

Associated Materials or

Pollutants Pollutant Category(1)

Gra

din

g a

nd

Lan

d D

evel

op

men

t

Concrete/ Masonry Cement and brick dust

Colored chalks

Concrete curing compounds

Glazing compounds

Surfaces cleaners

Saw cut slurries

Tile cutting

Removal of existing structures Demolition of asphalt, concrete,

masonry, framing, roofing,

metal structures.

Metals, Oil and Grease,

Synthetic Organics

Solid waste Litter, trash and debris

Vegetation

Gross Pollutants

Str

eets

an

d

Uti

liti

es

Ph

ase Vehicle and equipment use Equipment operation

Equipment maintenance

Equipment washing

Equipment fueling

Oil and Grease

Solid waste Litter, trash and debris

Vegetation

Gross Pollutants

Lan

dsc

apin

g a

nd

Sit

e S

tab

iliz

atio

n P

has

e Liquid waste Wash waters

Irrigation line testing/flushing

Metals, Synthetic Organics

Painting Paint thinners, acetone, methyl

ethyl ketone, stripper paints,

lacquers, varnish, enamels,

turpentine, gum spirit, solvents,

dyes, stripping pigments and

sanding

Metals, Synthetic Organics

Planting / Vegetation

Management

Vegetation control

(pesticides/herbicides)

Planting

Plant maintenance

Vegetation removal

Nutrients, Metals, Synthetic

Organics

Soil preparation/amendments Use of soil

additives/amendments

Nutrients

(1) Categories per CASQA BMP Handbook (i.e., Sediment, Nutrients, Bacteria and Viruses, Oil and Grease, Metals, Synthetic

Organics, Pesticides, Gross Pollutants, and Vector Production)

PWM Well Field Phase 3 102 August 2020

Appendix H: CASQA Stormwater BMP Handbook Portal:

Construction Fact Sheets

PWM Well Field Phase 3 103 August 2020

PWM Well Field Phase 3 104 August 2020

Appendix I: BMP Inspection Form

PWM Well Field Phase 3 105 August 2020

PWM Well Field Phase 3 106 August 2020

BMP INSPECTION REPORT

Date and Time of Inspection: Date Report Written:

Inspection Type: (Circle one)

Weekly Complete Parts

I,II,III and VII

Pre-Storm Complete Parts I,II,III,IV and VII

During Rain Event Complete Parts I, II,

III, V, and VII

Post-Storm Complete Parts I,II,III,VI and VII

Part I. General Information

Site Information Construction Site Name:

Construction stage and completed activities:

Approximate area of site that is exposed:

Photos Taken: (Circle one) Yes No

Photo Reference IDs:

Weather Estimate storm beginning: (date and time)

Estimate storm duration: (hours)

Estimate time since last storm: (days or hours)

Rain gauge reading and location: (in)

Is a “Qualifying Event” predicted or did one occur (i.e., 0.5” rain with 48-hrs or greater between events)? (Y/N) If yes, summarize forecast: Exemption Documentation (explanation required if inspection could not be conducted). Visual inspections are not required outside of business hours or during dangerous weather conditions such as flooding or electrical storms.

Inspector Information

Inspector Name: Inspector Title:

Signature: Date:

Part II. BMP Observations. Describe deficiencies in Part III.

PWM Well Field Phase 3 107 August 2020

Minimum BMPs for Risk Level 1 Sites

Failures or other short comings

(yes, no, N/A)

Action Required (yes/no)

Action Implemented

(Date)

Good Housekeeping for Construction Materials

Inventory of products (excluding materials designed to be outdoors)

Stockpiled construction materials not actively in use are covered and bermed

All chemicals are stored in watertight containers with appropriate secondary containment, or in a completely enclosed storage shed

Construction materials are minimally exposed to precipitation

BMPs preventing the off-site tracking of materials are implemented and properly effective

Good Housekeeping for Waste Management

Wash/rinse water and materials are prevented from being disposed into the storm drain system

Portable toilets are contained to prevent discharges of waste

Sanitation facilities are clean and with no apparent for leaks and spills

Equipment is in place to cover waste disposal containers at the end of business day and during rain events

Discharges from waste disposal containers are prevented from discharging to the storm drain system / receiving water

Stockpiled waste material is securely protected from wind and rain if not actively in use

Procedures are in place for addressing hazardous and non-hazardous spills

Appropriate spill response personnel are assigned and trained

Equipment and materials for cleanup of spills is available onsite

Washout areas (e.g., concrete) are contained appropriately to prevent discharge or infiltration into the underlying soil

Good Housekeeping for Vehicle Storage and Maintenance

Measures are in place to prevent oil, grease, or fuel from leaking into the ground, storm drains, or surface waters

All equipment or vehicles are fueled, maintained, and stored in a designated area with appropriate BMPs

Vehicle and equipment leaks are cleaned immediately and disposed of properly

Part II. BMP Observations Continued. Describe deficiencies in Part III.

Minimum BMPs for Risk Level 1 Sites

Adequately designed,

implemented and effective

Action Required (yes/no)

Action Implemented

(Date)

PWM Well Field Phase 3 108 August 2020

(yes, no, N/A)

Good Housekeeping for Landscape Materials

Stockpiled landscape materials such as mulches and topsoil are contained and covered when not actively in use

Erodible landscape material has not been applied 2 days before a forecasted rain event or during an event

Erodible landscape materials are applied at quantities and rates in accordance with manufacturer recommendations

Bagged erodible landscape materials are stored on pallets and covered

Good Housekeeping for Air Deposition of Site Materials

Good housekeeping measures are implemented onsite to control the air deposition of site materials and from site operations

Non-Stormwater Management

Non-Stormwater discharges are properly controlled

Vehicles are washed in a manner to prevent non-stormwater discharges to surface waters or drainage systems

Streets are cleaned in a manner to prevent unauthorized non-stormwater discharges to surface waters or drainage systems.

Erosion Controls

Wind erosion controls are effectively implemented

Effective soil cover is provided for disturbed areas inactive (i.e., not scheduled to be disturbed for 14 days) as well as finished slopes, open space, utility backfill, and completed lots

The use of plastic materials is limited in cases when a more sustainable, environmentally friendly alternative exists.

Sediment Controls

Perimeter controls are established and effective at controlling erosion and sediment discharges from the site

Entrances and exits are stabilized to control erosion and sediment discharges from the site

Sediment basins are properly maintained

Run-On and Run-Off Controls

Run-on to the site is effectively managed and directed away from all disturbed areas.

Other Are the project SWPPP and BMP plan up to date, available on-site and being properly implemented?

Part III. Descriptions of BMP Deficiencies

PWM Well Field Phase 3 109 August 2020

Deficiency

Repairs Implemented: Note - Repairs must begin within 72 hours of identification and,

complete repairs as soon as possible.

Start Date Action

1.

2.

3.

4.

Part IV. Additional Pre-Storm Observations. Note the presence or absence of floating and

suspended materials, sheen, discoloration, turbidity, odors, and source(s) of pollutants(s). Yes, No, N/A

Do stormwater storage and containment areas have adequate freeboard? If no, complete Part III. Are drainage areas free of spills, leaks, or uncontrolled pollutant sources? If no, complete Part VII and describe below.

Notes: Are stormwater storage and containment areas free of leaks? If no, complete Parts III and/or VII and describe below.

Notes:

Part V. Additional During Storm Observations. If BMPs cannot be inspected during

inclement weather, list the results of visual inspections at all relevant outfalls, discharge points, and downstream locations. Note odors or visible sheen on the surface of discharges. Complete Part VII (Corrective Actions) as needed.

Outfall, Discharge Point, or Other Downstream Location

Location Description

Location Description

PWM Well Field Phase 3 110 August 2020

Location Description

Location Description

Location Description

Location Description

Location Description

Location Description

PWM Well Field Phase 3 111 August 2020

Part VI. Additional Post-Storm Observations. Visually observe (inspect) stormwater discharges at all

discharge locations within two business days (48 hours) after each qualifying rain event, and observe (inspect) the discharge of stored or contained stormwater that is derived from and discharged subsequent to a qualifying rain event producing precipitation of ½ inch or more at the time of discharge. Complete Part VII (Corrective Actions) as needed.

Discharge Location, Storage or Containment Area

Visual Observation

Part VII. Additional Corrective Actions Required. Identify additional corrective actions not

included with BMP Deficiencies (Part III) above. Note if SWPPP change is required.

Required Actions Implementation Date

PWM Well Field Phase 3 112 August 2020

Appendix J: Project Specific Rain Event Action Plan

Template

PWM Well Field Phase 3 113 August 2020

NOT APPLICABLE

PWM Well Field Phase 3 114 August 2020

Appendix K: Training Reporting Form

PWM Well Field Phase 3 115 August 2020

Trained Contractor Personnel Log Stormwater Management Training Log and Documentation

Project Name:

WDID #:

Stormwater Management Topic: (check as appropriate)

Erosion Control Sediment Control

Wind Erosion Control Tracking Control

Non-Stormwater Management Waste Management and Materials Pollution Control

Stormwater Sampling

Specific Training Objective:

Location: Date: _

Instructor: Telephone:

Course Length (hours):

Attendee Roster (Attach additional forms if necessary)

Name Company Phone

As needed, add proof of external training (e.g., course completion certificates, credentials for

QSP, QSD).

PWM Well Field Phase 3 116 August 2020

Appendix L: Responsible Parties

PWM Well Field Phase 3 117 August 2020

OPTIONAL

Authorization of Approved Signatories

Project Name:

WDID #:

Name of

Personnel

Project Role Company Signature Date

____________________________ ______________________________

LRP’s Signature Date

____________________________ ______________________________

LRP Name and Title Telephone Number

PWM Well Field Phase 3 118 August 2020

Identification of QSP

Project Name:

WDID #:

The following are QSPs associated with this project

Name of Personnel(1) Company Date

(1) If additional QSPs are required on the job site add additional lines and include information here

PWM Well Field Phase 3 119 August 2020

Authorization of Data Submitters

Project Name:

WDID #:

Name of

Personnel

Project Role Company Signature Date

___________________________ ______________________________

Approved Signatory’s Signature Date

____________________________ ______________________________

Approved Signatory Telephone Number

Name and Title

PWM Well Field Phase 3 120 August 2020

Appendix M: Contractors and Subcontractors

PWM Well Field Phase 3 121 August 2020

Appendix N: Construction General Permit

PWM Well Field Phase 3 122 August 2020

INSTRUCTIONS

• Include a copy of the General Permit, or reference permanent location of General Permit

that is kept on the construction site.

PWM Well Field Phase 3 123 August 2020

Appendix O: Retention of Records / Construction

Records

PWM Well Field Phase 3 124 August 2020

Appendix P: Agency Approvals and Miscellaneous

Documents

PWM Well Field Phase 3 125 August 2020

Appendix Q: Test Methods, Detection Limits,

Reporting Units, Applicable NALs and

NELs

PWM Well Field Phase 3 126 August 2020

Appendix R: Erosion Control Plans

NTS

ENTRANCE/OUTLET TIRE WASH

C003

1

NONE

NONE

NONE

NONE

NONE

4

3

2

1

0

0

USE OF DOCUMENTS

25mm

SCALES

1"

CHECKED

DESIGNED

DRAWN

0

Kennedy/Jenks Consultants

DATE

SHEET

FILE NAME

JOB NO.

D E F G HA B C

IF THIS BAR IS NOT

DIMENSION SHOWN,

ADJUST SCALES

ACCORDINGLY.

THIS DOCUMENT, INCLUDING THE INCORPORATED

DESIGNS, IS AN INSTRUMENT OF SERVICE FOR THIS

PROJECT AND SHALL NOT BE USED FOR ANY OTHER

PROJECT WITHOUT THE WRITTEN AUTHORIZATION

OF KENNEDY/JENKS CONSULTANTS.

NO. REVISION DATE BY

1668012.05

PURE WATER MONTEREY

GROUNDWATER REPLENISHMENT PROJECT

INJECTION WELL FACILITIES

PHASE 3

SEPTEMBER 2020

S:\M

B_

Jo

bs\K

JC

I\0

3-D

IW

-3

\D

ra

win

gs\1

66

80

12

05

-C

-0

01

.d

wg 9

/2

5/2

02

0 A

Ste

rb

en

z

(831) 883-4848Salinas, CA 93907-2348

3 Quail Run Circle, Suite 101

9/1/2020

CJM

CJM

AAS

1 ADDENDUM NO. 1 09/25/2020 AAS

EROSION CONTROL PLAN/SITE PLAN

C-001

166801205-C-001.DWG

S:\M

B_Jo

bs\K

JC

I\03-D

IW

-3\D

raw

in

gs\166801205-C

-001.d

wg

, C

001, 9/25/2020 3:54:22 P

M

NOTE:

1. WASTE STORAGE AREAS, VEHICLE STORAGE AREAS

AND MATERIAL STORAGE AREAS TO BE DETERMINED

BY CONTRACTOR

2. SEE SHEET C-001 FOR LEGEND

4

3

2

1

0

0

USE OF DOCUMENTS

25mm

SCALES

1"

CHECKED

DESIGNED

DRAWN

0

Kennedy/Jenks Consultants

DATE

SHEET

FILE NAME

JOB NO.

D E F G HA B C

IF THIS BAR IS NOT

DIMENSION SHOWN,

ADJUST SCALES

ACCORDINGLY.

THIS DOCUMENT, INCLUDING THE INCORPORATED

DESIGNS, IS AN INSTRUMENT OF SERVICE FOR THIS

PROJECT AND SHALL NOT BE USED FOR ANY OTHER

PROJECT WITHOUT THE WRITTEN AUTHORIZATION

OF KENNEDY/JENKS CONSULTANTS.

NO. REVISION DATE BY

1668012.05

PURE WATER MONTEREY

GROUNDWATER REPLENISHMENT PROJECT

INJECTION WELL FACILITIES

PHASE 3

SEPTEMBER 2020

M:\K

JC

I\0

3-D

IW

-3

\D

ra

win

gs\1

66

80

12

05

-C

-0

01

.d

wg

9

/1

/2

02

0 A

Ste

rb

en

z

(831) 883-4848Salinas, CA 93907-2348

3 Quail Run Circle, Suite 101

9/1/2020

CJM

CJM

AAS

SWPPP DETAILS 1

C-002

168801205-C-001.DWG

M:\K

JC

I\03-D

IW

-3\D

raw

in

gs\166801205-C

-001.d

wg

, C

002, 9/1/2020 12:22:59 P

M

4

3

2

1

0

0

USE OF DOCUMENTS

25mm

SCALES

1"

CHECKED

DESIGNED

DRAWN

0

Kennedy/Jenks Consultants

DATE

SHEET

FILE NAME

JOB NO.

D E F G HA B C

IF THIS BAR IS NOT

DIMENSION SHOWN,

ADJUST SCALES

ACCORDINGLY.

THIS DOCUMENT, INCLUDING THE INCORPORATED

DESIGNS, IS AN INSTRUMENT OF SERVICE FOR THIS

PROJECT AND SHALL NOT BE USED FOR ANY OTHER

PROJECT WITHOUT THE WRITTEN AUTHORIZATION

OF KENNEDY/JENKS CONSULTANTS.

NO. REVISION DATE BY

1668012.05

PURE WATER MONTEREY

GROUNDWATER REPLENISHMENT PROJECT

INJECTION WELL FACILITIES

PHASE 3

SEPTEMBER 2020

M:\K

JC

I\0

3-D

IW

-3

\D

ra

win

gs\1

66

80

12

05

-C

-0

01

.d

wg

9

/3

0/2

02

0 A

Ste

rb

en

z

(831) 883-4848Salinas, CA 93907-2348

3 Quail Run Circle, Suite 101

9/1/2020

CJM

CJM

AAS

1 ADDENDUM NO. 1 09/25/2020 AAS

2 ADDENDUM NO. 2 10/1/2020 AAS

SWPPP DETAILS 2

C-003

166801205-C-001.DWG

M:\K

JC

I\03-D

IW

-3\D

raw

in

gs\166801205-C

-001.d

wg

, C

003, 9/30/2020 10:32:07 A

M

PWM Well Field Phase 3 127 August 2020

Appendix S: Contractor Activities Location Map

D50 = 12 " RIP RAPENERGY DISSAPATORSEE

--1

16" DIP,FL X FL (TYP)

1' AIR GAP

3'-2" DIP SPOOL

#5 REBAR @ 12" EA WAY

12"

CALTRANS 48RX GRATEWITH RING AND ANCHOR BOLTS

16" DIP5' COVER

TIDEFLEX SERIES 35FLANGED CHECK VALVE

6"

#5 REBAR @ 12"EA WAY

24" HDPE, S=0.18%

SEE DETAIL--2

1

PRECAST H-20MANHOLE

RIM ELEV 298.0'INVERT 285.1 FT

GROUT SLOPE2" MIN

3

2

24" CLASS 2 BASE95% COMPACTION

4' X 4' CONC. PADTOP ELEV 297.5

4'

5'

ECCENTRIC CONE

FLARED END SECTION

SPLASH GUARDSEE

--3

4

SUPPORTBLOCK

1.5'

12" ROCKABOVE PIPE

TCE

TCE

TCE

TCE

G E

N E

R A

L

J

I M

M

O O

R E

B

L V

D .

295

290

285

EQUIVALENT,

TYP

ASTM A-36,

30°

TOE OF SLOPEPLAN

O.C. (EACH LAYER)

J" BOLTS, OR

NUTS & WASHERS 2 GALVANIZED

REINF. STEELSYMMETRICAL

CL

SECTION

2 FT. MIN.ABOUT

2 FT MIN

ALL AROUND

THICKENEDEXTENT OF

PLACED AT

ON EACH 1/2 X 6 IN.

CL

12 INCHES #5 BARS

TYP.

2 M

IN F

T.

2 MIN FT.

2 M

IN F

T.

2 MIN FT.

8 MIN IN.

30 DEGREEINTERVALS THROUGH PIPE.

AREA

6 FT

6 FT

#4 AT 12 INCH O.C. MINIMUM OR EQUIVALENT WELDEDWIRE FABRIC. 2 INCH CLEAR ALL SIDES.

42" Ø SCH 40 STL PIPE

2" X 2" X 3 8" PLATE STL12" Ø HOLE FOR 3 8" Ø BOLT

(TYP OF 4)

90°

PLAN VIEW

ELEVATION VIEW

TYP ALLWELDS

38"

18"

NOTE: ANCHOR SPLASH GUARD TO CATCH BASIN GRATE WITH 3 8"Ø SS TYPE 316 BOLTS, (TYP OF 4). PROVIDE 3" X 3" X 3 8" BACKING PLATES UNDER GRATE

FABRICATED PIPE AND BACKING PLATES SHALL BE HOT DIPPED GALVANIZED.

4

3

2

1

0

0USE OF DOCUMENTS

25mm

SCALES1"

CHECKED

DESIGNED

DRAWN

0

Kennedy/Jenks Consultants

DATE

SHEET

FILE NAME

JOB NO.

D E F G HA B C

IF THIS BAR IS NOTDIMENSION SHOWN,

ADJUST SCALESACCORDINGLY.

THIS DOCUMENT, INCLUDING THE INCORPORATEDDESIGNS, IS AN INSTRUMENT OF SERVICE FOR THISPROJECT AND SHALL NOT BE USED FOR ANY OTHERPROJECT WITHOUT THE WRITTEN AUTHORIZATION

OF KENNEDY/JENKS CONSULTANTS.

NO. REVISION DATE BYC:\U

sers

\jtab

ije\D

eskt

op\W

OR

K\K

JCI\R

EC

OR

D D

RA

WIN

GS

\166

8012

02-C

-174

.dw

gJT

AB

IJE

7/2

3/20

20 3

:34

PM

INJECTION WELL FACILITIESPHASE 2

1668012*02

DECEMBER 2017

MONTEREY REGIONAL WATER POLLUTION CONTROL AGENCYMONTEREY, CA

PURE WATER MONTEREYGROUNDWATER REPLENISHMENT PROJECT

200 Fourth Street, Suite 210, Santa Rosa, CA 95401-8534

(831) 883-4848Salinas, CA 93907-2348

3 Quail Run Circle, Suite 101CONSULTING CIVIL ENGINEERS

Schaaf Wheeler

RECORD DRAWING 6/30/2020 AASPERCOLATION BASIN

SECTIONS AND DETAILS 2 C-174AAS

JCT

JCT

4

3

2

1

0

0USE OF DOCUMENTS

25mm

SCALES1"

CHECKED

DESIGNED

DRAWN

0

Kennedy/Jenks Consultants

DATE

SHEET

FILE NAME

JOB NO.

D E F G HA B C

IF THIS BAR IS NOTDIMENSION SHOWN,

ADJUST SCALESACCORDINGLY.

THIS DOCUMENT, INCLUDING THE INCORPORATEDDESIGNS, IS AN INSTRUMENT OF SERVICE FOR THISPROJECT AND SHALL NOT BE USED FOR ANY OTHERPROJECT WITHOUT THE WRITTEN AUTHORIZATION

OF KENNEDY/JENKS CONSULTANTS.

NO. REVISION DATE BYC:\U

sers

\jtab

ije\D

eskt

op\W

OR

K\K

JCI\R

EC

OR

D D

RA

WIN

GS

\166

8012

02-C

-174

.dw

gJT

AB

IJE

7/2

3/20

20 3

:34

PM

INJECTION WELL FACILITIESPHASE 2

1668012*02

DECEMBER 2017

MONTEREY REGIONAL WATER POLLUTION CONTROL AGENCYMONTEREY, CA

PURE WATER MONTEREYGROUNDWATER REPLENISHMENT PROJECT

200 Fourth Street, Suite 210, Santa Rosa, CA 95401-8534

(831) 883-4848Salinas, CA 93907-2348

3 Quail Run Circle, Suite 101CONSULTING CIVIL ENGINEERS

Schaaf Wheeler

RECORD DRAWING 6/30/2020 AAS

-B

-A

SCALE: 1/4" = 1'

SECTION-A

SCALE: 1/4" = 1'

SECTION-B

SCALE: 1" = 10'

PERCOLOATION POND INLET

166801202-C-174.DWG

-1

NTS

PIPE OUTFALL DETAIL-2

20'

20'

RIP RAP

GUARD POSTS6-FT O.C.

SEE 3/C-012

KEY NOTES:1. NEMA 4X JUNCTION BOX FOR

LEVEL TRANSDUCER2. AVANTI INTERNATIONSL 4" PIPE

CLAMP3. 4" PERFORATED PVC PIPE4. TRUMBULL ADJUSTABLE PIPE

SUPPORT

FLARED END SECTION

24" HDPE

NTS

INLET SPLASH GUARD-3

1

1

RECORD DRAWINGSTHESE RECORD DRAWINGS HAVE BEEN PREPAREDBASED ON INFORMATION BY THE CONTRACTOR ANDOTHERS. KENNEDY/JENKS CONSULTANTS HAS NOTVERIFIED THE ACCURACY OR COMPLETENESS OFTHE INFORMATION PROVIDED TO THEM AND DOESNOT WARRANT THE ACCURACY OF COMPLETENESSOF THESE RECORD DRAWINGS. USERS OF THESERECORD DRAWINGS ASSUME ALL RISK OF LOSSRESULTING FROM THEIR USE.

FOR REFERENCE ONLY - NOT PART OF THE CONTRACT DOCUMENTS

AutoCAD SHX Text
"

"General Decision Number: CA20200018 10/02/2020

Superseded General Decision Number: CA20190018

State: California

Construction Types: Building, Heavy (Heavy and Dredging) and

Highway

Counties: Alameda, Calaveras, Contra Costa, Fresno, Kings,

Madera, Mariposa, Merced, Monterey, San Benito, San Francisco,

San Joaquin, San Mateo, Santa Clara, Santa Cruz, Stanislaus and

Tuolumne Counties in California.

BUILDING CONSTRUCTION PROJECTS; DREDGING PROJECTS (does not

include hopper dredge work); HEAVY CONSTRUCTION PROJECTS (does

not include water well drilling); HIGHWAY CONSTRUCTION PROJECTS

Note: Under Executive Order (EO) 13658, an hourly minimum wage

of $10.80 for calendar year 2020 applies to all contracts

subject to the Davis-Bacon Act for which the contract is

awarded (and any solicitation was issued) on or after January

1, 2015. If this contract is covered by the EO, the contractor

must pay all workers in any classification listed on this wage

determination at least $10.80 per hour (or the applicable wage

rate listed on this wage determination, if it is higher) for

all hours spent performing on the contract in calendar year

2020. If this contract is covered by the EO and a

classification considered necessary for performance of work on

the contract does not appear on this wage determination, the

contractor must pay workers in that classification at least the

wage rate determined through the conformance process set forth

in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is

higher than the conformed wage rate). The EO minimum wage rate

will be adjusted annually. Please note that this EO applies to

the above-mentioned types of contracts entered into by the

federal government that are subject to the Davis-Bacon Act

itself, but it does not apply to contracts subject only to the

Davis-Bacon Related Acts, including those set forth at 29 CFR

5.1(a)(2)-(60). Additional information on contractor

requirements and worker protections under the EO is available

at www.dol.gov/whd/govcontracts.

Modification Number Publication Date

0 01/03/2020

1 01/10/2020

2 01/24/2020

3 01/31/2020

4 02/07/2020

5 03/06/2020

6 03/13/2020

7 04/17/2020

8 06/05/2020

9 06/19/2020

10 06/26/2020

11 07/03/2020

12 07/10/2020

13 07/17/2020

14 07/24/2020

15 08/07/2020

16 08/14/2020

17 08/21/2020

18 09/04/2020

19 09/11/2020

20 09/18/2020

21 10/02/2020

ASBE0016-004 01/01/2019

AREA 1: CALAVERAS, FRESNO, KINGS, MADERA, MARIPOSA, MERCED,

MONTEREY, SAN BENITO, SAN JOAQUIN, SANTA CRUZ, STANISLAUS &

TOULMNE COUNTIES

AREA 2: ALAMEDA, CONTRA COSTA, SAN FRANSICO, SAN MATEO & SANTA

CLARA COUNTIES

Rates Fringes

Asbestos Removal

worker/hazardous material

handler (Includes

preparation, wetting,

stripping, removal,

scrapping, vacuuming, bagging

and disposing of all

insulation materials from

mechanical systems, whether

they contain asbestos or not)

Area 1......................$ 28.20 9.27

Area 2......................$ 36.53 9.27

----------------------------------------------------------------

ASBE0016-008 01/01/2020

AREA 1: ALAMEDA, CONTRA COSTA, MONTEREY, SAN BENITO, SAN

FRANSICO, SAN MATEO, SANTA CLARA, & SANTA CRUZ

AREA 2: CALAVERAS, COLUSA, FRESNO, KINGS, MADERA, MARIPOSA,

MERCED, SAN JOAQUIN, STANISLAU, & TUOLUMNE

Rates Fringes

Asbestos Workers/Insulator

(Includes the application of

all insulating materials,

Protective Coverings,

Coatings, and Finishes to all

types of mechanical systems)

Area 1......................$ 71.16 23.39

Area 2......................$ 54.26 23.39

----------------------------------------------------------------

BOIL0549-001 10/01/2016

AREA 1: ALAMEDA, CONTRA COSTA, SAN FRANCISCO, SAN MATEO & SANTA

CLARA COUNTIES

AREA 2: REMAINING COUNTIES

Rates Fringes

BOILERMAKER

Area 1......................$ 43.28 37.91

Area 2......................$ 39.68 35.71

----------------------------------------------------------------

BRCA0003-001 08/01/2019

Rates Fringes

MARBLE FINISHER..................$ 35.41 16.45

----------------------------------------------------------------

BRCA0003-003 08/01/2019

Rates Fringes

MARBLE MASON.....................$ 49.42 27.86

----------------------------------------------------------------

BRCA0003-005 05/01/2019

Rates Fringes

BRICKLAYER

( 1) Fresno, Kings,

Madera, Mariposa, Merced....$ 41.88 22.19

( 7) San Francisco, San

Mateo.......................$ 42.34 25.83

( 8) Alameda, Contra

Costa, San Benito, Santa

Clara.......................$ 44.16 21.71

( 9) Calaveras, San

Joaquin, Stanislaus,

Toulumne....................$ 39.66 20.76

(16) Monterey, Santa Cruz...$ 39.51 23.49

----------------------------------------------------------------

BRCA0003-008 07/01/2019

Rates Fringes

TERRAZZO FINISHER................$ 37.58 17.33

TERRAZZO WORKER/SETTER...........$ 48.53 26.84

----------------------------------------------------------------

BRCA0003-011 04/01/2019

AREA 1: Alameda, Contra Costa, Monterey, San Benito, San

Francisco, San Mateo, Santa Clara, Santa Cruz

AREA 2: Calaveras, San Joaquin, Stanislaus, Tuolumne

AREA 3: Fresno, Kings, Madera, Mariposa, Merced

Rates Fringes

TILE FINISHER

Area 1......................$ 29.94 16.38

Area 2......................$ 25.60 14.30

Area 3......................$ 26.58 15.65

Tile Layer

Area 1......................$ 49.90 19.16

Area 2......................$ 42.67 16.81

Area 3......................$ 40.27 18.58

----------------------------------------------------------------

CARP0022-001 07/01/2020

San Francisco County

Rates Fringes

Carpenters

Bridge Builder/Highway

Carpenter...................$ 52.65 30.82

Hardwood Floorlayer,

Shingler, Power Saw

Operator, Steel Scaffold &

Steel Shoring Erector, Saw

Filer.......................$ 52.80 30.82

Journeyman Carpenter........$ 52.65 30.82

Millwright..................$ 52.75 32.41

----------------------------------------------------------------

CARP0034-001 07/01/2020

Rates Fringes

Diver

Assistant Tender, ROV

Tender/Technician...........$ 51.90 34.02

Diver standby...............$ 58.09 34.02

Diver Tender................$ 57.09 34.02

Diver wet...................$ 101.42 34.02

Manifold Operator (mixed

gas)........................$ 62.09 34.02

Manifold Operator (Standby).$ 57.09 34.02

DEPTH PAY (Surface Diving):

050 to 100 ft $2.00 per foot

101 to 150 ft $3.00 per foot

151 to 220 ft $4.00 per foot

221 ft.-deeper $5.00 per foot

SATURATION DIVING:

The standby rate shall apply until saturation starts. The

saturation diving rate applies when divers are under

pressure continuously until work task and decompression are

complete. The diver rate shall be paid for all saturation

hours.

DIVING IN ENCLOSURES:

Where it is necessary for Divers to enter pipes or tunnels,

or other enclosures where there is no vertical ascent, the

following premium shall be paid: Distance traveled from

entrance 26 feet to 300 feet: $1.00 per foot. When it is

necessary for a diver to enter any pipe, tunnel or other

enclosure less than 48"" in height, the premium will be

$1.00 per foot.

WORK IN COMBINATION OF CLASSIFICATIONS:

Employees working in any combination of classifications

within the diving crew (except dive supervisor) in a shift

are paid in the classification with the highest rate for

that shift.

----------------------------------------------------------------

CARP0034-003 07/01/2020

Rates Fringes

Piledriver.......................$ 52.90 34.02

----------------------------------------------------------------

CARP0035-007 07/01/2019

AREA 1: Alameda, Contra Costa, San Francisco, San Mateo, Santa

Clara counties

AREA 2: Monterey, San Benito, Santa Cruz Counties

AREA 3: Calaveras, Fresno, Kings, Madera, Mariposa, Merced, San

Joaquin, Stanislaus, Tuolumne Counties

Rates Fringes

Modular Furniture Installer

Area 1

Installer I................$ 27.46 22.14

Installer II...............$ 22.18 20.42

Lead Installer.............$ 30.91 22.64

Master Installer...........$ 35.13 22.64

Area 2

Installer I................$ 24.81 22.14

Installer II...............$ 20.01 20.42

Lead Installer.............$ 27.78 22.64

Master Installer...........$ 31.41 22.64

Area 3

Installer I................$ 23.86 22.14

Installer II...............$ 19.24 20.42

Lead Installer.............$ 26.66 22.64

Master Installer...........$ 30.08 22.64

----------------------------------------------------------------

CARP0035-008 08/01/2019

AREA 1: Alameda, Contra Costa, San Francisco, San Mateo, Santa

Clara counties

AREA 2: Monterey, San Benito, Santa Cruz Counties

AREA 3: San Joaquin

AREA 4: Calaveras, Fresno, Kings, Madera, Mariposa, Merced,

Stanislaus, Tuolumne Counties

Rates Fringes

Drywall Installers/Lathers:

Area 1......................$ 50.50 30.64

Area 2......................$ 44.62 30.64

Area 3......................$ 41.02 29.15

Area 4......................$ 43.77 30.64

Drywall Stocker/Scrapper

Area 1......................$ 25.25 17.86

Area 2......................$ 22.31 17.86

Area 3......................$ 20.51 16.88

Area 4......................$ 21.89 17.86

----------------------------------------------------------------

CARP0152-001 07/01/2020

Contra Costa County

Rates Fringes

Carpenters

Bridge Builder/Highway

Carpenter...................$ 52.65 30.82

Hardwood Floorlayer,

Shingler, Power Saw

Operator, Steel Scaffold &

Steel Shoring Erector, Saw

Filer.......................$ 52.80 30.82

Journeyman Carpenter........$ 52.65 30.82

Millwright..................$ 52.75 32.41

----------------------------------------------------------------

CARP0152-002 07/01/2020

San Joaquin County

Rates Fringes

Carpenters

Bridge Builder/Highway

Carpenter...................$ 52.65 30.82

Hardwood Floorlayer,

Shingler, Power Saw

Operator, Steel Scaffold &

Steel Shoring Erector, Saw

Filer.......................$ 46.92 30.82

Journeyman Carpenter........$ 46.77 30.82

Millwright..................$ 49.27 32.41

----------------------------------------------------------------

CARP0152-004 07/01/2020

Calaveras, Mariposa, Merced, Stanislaus and Tuolumne Counties

Rates Fringes

Carpenters

Bridge Builder/Highway

Carpenter...................$ 52.65 30.82

Hardwood Floorlayer,

Shingler, Power Saw

Operator, Steel Scaffold &

Steel Shoring Erector, Saw

Filer.......................$ 45.57 30.82

Journeyman Carpenter........$ 45.42 30.82

Millwright..................$ 47.92 32.41

----------------------------------------------------------------

CARP0217-001 07/01/2020

San Mateo County

Rates Fringes

Carpenters

Bridge Builder/Highway

Carpenter...................$ 52.65 30.82

Hardwood Floorlayer,

Shingler, Power Saw

Operator, Steel Scaffold &

Steel Shoring Erector, Saw

Filer.......................$ 52.80 30.82

Journeyman Carpenter........$ 52.65 30.82

Millwright..................$ 52.75 32.41

----------------------------------------------------------------

CARP0405-001 07/01/2020

Santa Clara County

Rates Fringes

Carpenters

Bridge Builder/Highway

Carpenter...................$ 52.65 30.82

Hardwood Floorlayer,

Shingler, Power Saw

Operator, Steel Scaffold &

Steel Shoring Erector, Saw

Filer.......................$ 52.80 30.82

Journeyman Carpenter........$ 52.65 30.82

Millwright..................$ 52.75 32.41

----------------------------------------------------------------

CARP0405-002 07/01/2020

San Benito County

Rates Fringes

Carpenters

Bridge Builder/Highway

Carpenter...................$ 52.65 30.82

Hardwood Floorlayer,

Shingler, Power Saw

Operator, Steel Scaffold &

Steel Shoring Erector, Saw

Filer.......................$ 46.83 30.82

Journeyman Carpenter........$ 46.77 30.82

Millwright..................$ 49.27 32.41

----------------------------------------------------------------

CARP0505-001 07/01/2020

Santa Cruz County

Rates Fringes

Carpenters

Bridge Builder/Highway

Carpenter...................$ 52.65 30.82

Hardwood Floorlayer,

Shingler, Power Saw

Operator, Steel Scaffold &

Steel Shoring Erector, Saw

Filer.......................$ 46.92 30.82

Journeyman Carpenter........$ 46.77 30.82

Millwright..................$ 49.27 32.41

----------------------------------------------------------------

CARP0605-001 07/01/2020

Monterey County

Rates Fringes

Carpenters

Bridge Builder/Highway

Carpenter...................$ 52.65 30.82

Hardwood Floorlayer,

Shingler, Power Saw

Operator, Steel Scaffold &

Steel Shoring Erector, Saw

Filer.......................$ 46.92 30.82

Journeyman Carpenter........$ 46.77 30.82

Millwright..................$ 49.27 32.41

----------------------------------------------------------------

CARP0701-001 07/01/2020

Fresno and Madera Counties

Rates Fringes

Carpenters

Bridge Builder/Highway

Carpenter...................$ 52.65 30.82

Hardwood Floorlayer,

Shingler, Power Saw

Operator, Steel Scaffold &

Steel Shoring Erector, Saw

Filer.......................$ 45.57 30.82

Journeyman Carpenter........$ 45.42 30.82

Millwright..................$ 47.92 32.41

----------------------------------------------------------------

CARP0713-001 07/01/2020

Alameda County

Rates Fringes

Carpenters

Bridge Builder/Highway

Carpenter...................$ 52.65 30.82

Hardwood Floorlayer,

Shingler, Power Saw

Operator, Steel Scaffold &

Steel Shoring Erector, Saw

Filer.......................$ 52.80 30.82

Journeyman Carpenter........$ 52.65 30.82

Millwright..................$ 52.75 32.41

----------------------------------------------------------------

CARP1109-001 07/01/2020

Kings County

Rates Fringes

Carpenters

Bridge Builder/Highway

Carpenter...................$ 52.65 30.82

Hardwood Floorlayer,

Shingler, Power Saw

Operator, Steel Scaffold &

Steel Shoring Erector, Saw

Filer.......................$ 45.57 30.82

Journeyman Carpenter........$ 45.42 30.82

Millwright..................$ 47.92 32.41

----------------------------------------------------------------

ELEC0006-004 12/01/2018

SAN FRANCISCO COUNTY

Rates Fringes

Sound & Communications

Installer...................$ 40.52 3%+19.05

Technician..................$ 46.60 3%+19.05

SCOPE OF WORK: Including any data system whose only function

is to transmit or receive information; excluding all other

data systems or multiple systems which include control

function or power supply; inclusion or exclusion of

terminations and testings of conductors determined by

their function; excluding fire alarm work when installed

in raceways (including wire and cable pulling) and when

performed on new or major remodel building projects or

jobs for which the conductors for the fire alarm system are

installed in conduit; excluding installation of raceway

systems, line voltage work, industrial work, life-safety

systems (all buildings having floors located more than 75'

above the lowest floor level having building access);

excluding energy management systems.

FOOTNOTE: Fire alarm work when installed in raceways

(including wire and cable pulling), on projects which

involve new or major remodel building construction, for

which the conductors for the fire alarm system are

installed in the conduit, shall be performed by the inside

electrician.

----------------------------------------------------------------

ELEC0006-007 06/01/2020

SAN FRANCISCO COUNTY

Rates Fringes

ELECTRICIAN......................$ 78.00 3%+35.96

----------------------------------------------------------------

ELEC0100-002 09/01/2020

FRESNO, KINGS, AND MADERA COUNTIES

Rates Fringes

ELECTRICIAN......................$ 40.00 24.85

----------------------------------------------------------------

ELEC0100-005 12/01/2019

FRESNO, KINGS, MADERA

Rates Fringes

Communications System

Installer...................$ 35.25 20.86

Technician..................$ 40.54 21.02

SCOPE OF WORK

Includes the installation testing, service and maintenance,

of the following systems which utilize the transmission

and/or transference of voice, sound, vision and digital for

commercial, education, security and entertainment purposes

for the following: TV monitoring and surveillance,

background-foreground music, intercom and telephone

interconnect, inventory control systems, microwave

transmission, multi-media, multiplex, nurse call system,

radio page, school intercom and sound, burglar alarms, and

low voltage master clock systems.

A. SOUND AND VOICE TRANSMISSION/TRANSFERENCE SYSTEMS

Background foreground music, Intercom and telephone

interconnect systems, Telephone systems Nurse call systems,

Radio page systems, School intercom and sound systems,

Burglar alarm systems, Low voltage, master clock systems,

Multi-media/multiplex systems, Sound and musical

entertainment systems, RF systems, Antennas and Wave Guide,

B. FIRE ALARM SYSTEMS Installation, wire pulling and testing

C. TELEVISION AND VIDEO SYSTEMS Television monitoring and

surveillance systems Video security systems, Video

entertainment systems, Video educational systems, Microwave

transmission systems, CATV and CCTV

D. SECURITY SYSTEMS Perimeter security systems Vibration

sensor systems Card access systems Access control systems,

Sonar/infrared monitoring equipment

E. COMMUNICATIONS SYSTEMS THAT TRANSMIT OR RECEIVE

INFORMATION AND/OR CONTROL SYSTEMS THAT ARE INTRINSIC TO

THE ABOVE LISTED SYSTEMS SCADA (Supervisory Control and

Data Acquisition) PCM (Pulse Code Modulation) Inventory

Control Systems, Digital Data Systems Broadband and

Baseband and Carriers Point of Sale Systems, VSAT Data

Systems Data Communication Systems RF and Remote Control

Systems, Fiber Optic Data Systems

WORK EXCLUDED Raceway systems are not covered (excluding

Ladder-Rack for the purpose of the above listed systems).

Chases and/or nipples (not to exceed 10 feet) may be

installed on open wiring systems. Energy management

systems. SCADA (Supervisory Control and Data Acquisition)

when not intrinsic to the above listed systems (in the

scope). Fire alarm systems when installed in raceways

(including wire and cable pulling) shall be performed at

the electrician wage rate, when either of the following two

(2) conditions apply:

1. The project involves new or major remodel building trades

construction.

2. The conductors for the fire alarm system are installed in

conduit.

----------------------------------------------------------------

ELEC0234-001 12/23/2019

MONTEREY, SAN BENITO AND SANTA CRUZ COUNTIES

Rates Fringes

ELECTRICIAN

Zone A......................$ 51.47 26.64

Zone B......................$ 56.62 26.80

Zone A: All of Santa Cruz, Monterey, and San Benito Counties

within 25 air miles of Highway 1 and Dolan Road in Moss

Landing, and an area extending 5 miles east and west of

Highway 101 South to the San Luis Obispo County Line

Zone B: Any area outside of Zone A

----------------------------------------------------------------

* ELEC0234-003 12/01/2019

MONTEREY, SAN BENITO, AND SANTA CRUZ COUNTIES

Rates Fringes

Sound & Communications

Installer...................$ 42.93 21.09

Technician..................$ 49.37 21.28

SCOPE OF WORK: Including any data system whose only function

is to transmit or receive information; excluding all other

data systems or multiple systems which include control

function or power supply; inclusion or exclusion of

terminations and testings of conductors determined by

their function; excluding fire alarm work when installed

in raceways (including wire and cable pulling) and when

performed on new or major remodel building projects or

jobs for which the conductors for the fire alarm system are

installed in conduit; excluding installation of raceway

systems, line voltage work, industrial work, life-safety

systems (all buildings having floors located more than 75'

above the lowest floor level having building access);

excluding energy management systems.

FOOTNOTE: Fire alarm work when installed in raceways

(including wire and cable pulling), on projects which

involve new or major remodel building construction, for

which the conductors for the fire alarm system are

installed in the conduit, shall be performed by the inside

electrician.

----------------------------------------------------------------

ELEC0302-001 02/25/2019

CONTRA COSTA COUNTY

Rates Fringes

CABLE SPLICER....................$ 60.48 26.06

ELECTRICIAN......................$ 53.76 25.86

----------------------------------------------------------------

ELEC0302-003 12/01/2019

CONTRA COSTA COUNTY

Rates Fringes

Sound & Communications

Installer...................$ 40.31 21.01

Technician..................$ 46.36 21.19

SCOPE OF WORK: Including any data system whose only function

is to transmit or receive information; excluding all other

data systems or multiple systems which include control

function or power supply; inclusion or exclusion of

terminations and testings of conductors determined by

their function; excluding fire alarm work when installed

in raceways (including wire and cable pulling) and when

performed on new or major remodel building projects or

jobs for which the conductors for the fire alarm system are

installed in conduit; excluding installation of raceway

systems, line voltage work, industrial work, life-safety

systems (all buildings having floors located more than 75'

above the lowest floor level having building access);

excluding energy management systems.

FOOTNOTE: Fire alarm work when installed in raceways

(including wire and cable pulling), on projects which

involve new or major remodel building construction, for

which the conductors for the fire alarm system are

installed in the conduit, shall be performed by the inside

electrician.

----------------------------------------------------------------

ELEC0332-001 06/01/2020

SANTA CLARA COUNTY

Rates Fringes

CABLE SPLICER....................$ 82.25 40.66

ELECTRICIAN......................$ 71.52 40.34

FOOTNOTES: Work under compressed air or where gas masks are

required, orwork on ladders, scaffolds, stacks, ""Bosun's

chairs,"" or other structures and where the workers are not

protected by permanent guard rails at a distance of 40 to

60 ft. from the ground or supporting structures: to be paid

one and one-half times the straight-time rate of pay.

Work on structures of 60 ft. or over (as described above):

to be paid twice the straight-time rate of pay.

----------------------------------------------------------------

ELEC0332-003 12/01/2019

SANTA CLARA COUNTY

Rates Fringes

Sound & Communications

Installer...................$ 42.93 21.08

Technician..................$ 49.37 21.28

SCOPE OF WORK: Including any data system whose only function

is to transmit or receive information; excluding all other

data systems or multiple systems which include control

function or power supply; inclusion or exclusion of

terminations and testings of conductors determined by

their function; excluding fire alarm work when installed

in raceways (including wire and cable pulling) and when

performed on new or major remodel building projects or

jobs for which the conductors for the fire alarm system are

installed in conduit; excluding installation of raceway

systems, line voltage work, industrial work, life-safety

systems (all buildings having floors located more than 75'

above the lowest floor level having building access);

excluding energy management systems.

FOOTNOTE: Fire alarm work when installed in raceways

(including wire and cable pulling), on projects which

involve new or major remodel building construction, for

which the conductors for the fire alarm system are

installed in the conduit, shall be performed by the inside

electrician.

----------------------------------------------------------------

ELEC0595-001 06/01/2020

ALAMEDA COUNTY

Rates Fringes

CABLE SPLICER....................$ 69.00 3%+38.52

ELECTRICIAN......................$ 60.00 3%+38.52

----------------------------------------------------------------

ELEC0595-002 06/01/2020

CALAVERAS AND SAN JOAQUIN COUNTIES

Rates Fringes

CABLE SPLICER....................$ 48.00 7.75%+25.33

ELECTRICIAN

(1) Tunnel work.............$ 42.00 7.75%+25.33

(2) All other work.........$ 40.00 7.75%+25.33

----------------------------------------------------------------

ELEC0595-006 12/01/2019

ALAMEDA COUNTY

Rates Fringes

Sound & Communications

Installer...................$ 42.93 3%+20.22

Technician..................$ 53.66 3%+20.22

SCOPE OF WORK: Including any data system whose only function

is to transmit or receive information; excluding all other

data systems or multiple systems which include control

function or power supply; inclusion or exclusion of

terminations and testings of conductors determined by

their function; excluding fire alarm work when installed

in raceways (including wire and cable pulling) and when

performed on new or major remodel building projects or

jobs for which the conductors for the fire alarm system are

installed in conduit; excluding installation of raceway

systems, line voltage work, industrial work, life-safety

systems (all buildings having floors located more than 75'

above the lowest floor level having building access);

excluding energy management systems.

FOOTNOTE: Fire alarm work when installed in raceways

(including wire and cable pulling), on projects which

involve new or major remodel building construction, for

which the conductors for the fire alarm system are

installed in the conduit, shall be performed by the inside

electrician.

----------------------------------------------------------------

ELEC0595-008 12/01/2019

CALAVERAS AND SAN JOAQUIN COUNTIES

Rates Fringes

Communications System

Installer...................$ 35.25 3%+20.22

Technician..................$ 44.06 3%+20.22

SCOPE OF WORK: Including any data system whose only function

is to transmit or receive information; excluding all other

data systems or multiple systems which include control

function or power supply; inclusion or exclusion of

terminations and testings of conductors determined by

their function; excluding fire alarm work when installed

in raceways (including wire and cable pulling) and when

performed on new or major remodel building projects or

jobs for which the conductors for the fire alarm system are

installed in conduit; excluding installation of raceway

systems, line voltage work, industrial work, life-safety

systems (all buildings having floors located more than 75'

above the lowest floor level having building access);

excluding energy management systems.

FOOTNOTE: Fire alarm work when installed in raceways

(including wire and cable pulling), on projects which

involve new or major remodel building construction, for

which the conductors for the fire alarm system are

installed in the conduit, shall be performed by the inside

electrician.

----------------------------------------------------------------

ELEC0617-001 06/01/2020

SAN MATEO COUNTY

Rates Fringes

ELECTRICIAN......................$ 66.00 39.77

----------------------------------------------------------------

ELEC0617-003 12/01/2019

SAN MATEO COUNTY

Rates Fringes

Sound & Communications

Installer...................$ 42.93 21.09

Technician..................$ 49.37 21.28

SCOPE OF WORK: Including any data system whose only function

is to transmit or receive information; excluding all other

data systems or multiple systems which include control

function or power supply; inclusion or exclusion of

terminations and testings of conductors determined by

their function; excluding fire alarm work when installed

in raceways (including wire and cable pulling) and when

performed on new or major remodel building projects or

jobs for which the conductors for the fire alarm system are

installed in conduit; excluding installation of raceway

systems, line voltage work, industrial work, life-safety

systems (all buildings having floors located more than 75'

above the lowest floor level having building access);

excluding energy management systems.

FOOTNOTE: Fire alarm work when installed in raceways

(including wire and cable pulling), on projects which

involve new or major remodel building construction, for

which the conductors for the fire alarm system are

installed in the conduit, shall be performed by the inside

electrician.

----------------------------------------------------------------

ELEC0684-001 06/01/2020

MARIPOSA, MERCED, STANISLAUS AND TUOLUMNE COUNTIES

Rates Fringes

ELECTRICIAN......................$ 41.00 3%+24.58

CABLE SPLICER = 110% of Journeyman Electrician

----------------------------------------------------------------

ELEC0684-004 12/01/2019

MARIPOSA, MERCED, STANISLAUS AND TUOLUMNE COUNTIES

Rates Fringes

Communications System

Installer...................$ 35.25 20.86

Technician..................$ 40.54 21.02

SCOPE OF WORK: Including any data system whose only function

is to transmit or receive information; excluding all other

data systems or multiple systems which include control

function or power supply; inclusion or exclusion of

terminations and testings of conductors determined by

their function; excluding fire alarm work when installed

in raceways (including wire and cable pulling) and when

performed on new or major remodel building projects or

jobs for which the conductors for the fire alarm system are

installed in conduit; excluding installation of raceway

systems, line voltage work, industrial work, life-safety

systems (all buildings having floors located more than 75'

above the lowest floor level having building access);

excluding energy management systems.

FOOTNOTE: Fire alarm work when installed in raceways

(including wire and cable pulling), on projects which

involve new or major remodel building construction, for

which the conductors for the fire alarm system are

installed in the conduit, shall be performed by the inside

electrician.

----------------------------------------------------------------

ELEC1245-001 06/01/2020

Rates Fringes

LINE CONSTRUCTION

(1) Lineman; Cable splicer..$ 59.14 20.78

(2) Equipment specialist

(operates crawler

tractors, commercial motor

vehicles, backhoes,

trenchers, cranes (50 tons

and below), overhead &

underground distribution

line equipment)...........$ 47.24 19.59

(3) Groundman...............$ 36.12 19.19

(4) Powderman...............$ 51.87 18.79

HOLIDAYS: New Year's Day, M.L. King Day, Memorial Day,

Independence Day, Labor Day, Veterans Day, Thanksgiving Day

and day after Thanksgiving, Christmas Day

----------------------------------------------------------------

ELEV0008-001 01/01/2020

Rates Fringes

ELEVATOR MECHANIC................$ 69.78 34.765+a+b

FOOTNOTE:

a. PAID VACATION: Employer contributes 8% of regular hourly

rate as vacation pay credit for employees with more than 5

years of service, and 6% for 6 months to 5 years of service.

b. PAID HOLIDAYS: New Years Day, Memorial Day, Independence

Day, Labor Day, Veterans Day, Thanksgiving Day, Friday

after Thanksgiving, and Christmas Day.

----------------------------------------------------------------

ENGI0003-001 06/24/2019

""AREA 1"" WAGE RATES ARE LISTED BELOW

""AREA 2"" RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1

RATES.

SEE AREA DEFINITIONS BELOW

Rates Fringes

OPERATOR: Power Equipment

(AREA 1:)

GROUP 1.....................$ 49.02 30.74

GROUP 2.....................$ 47.49 30.74

GROUP 3.....................$ 46.01 30.74

GROUP 4.....................$ 44.63 30.74

GROUP 5.....................$ 43.36 30.74

GROUP 6.....................$ 42.04 30.74

GROUP 7.....................$ 40.90 30.74

GROUP 8.....................$ 39.76 30.74

GROUP 8-A...................$ 37.55 30.74

OPERATOR: Power Equipment

(Cranes and Attachments -

AREA 1:)

GROUP 1

Cranes.....................$ 50.65 30.74

Oiler......................$ 36.63 30.39

Truck crane oiler..........$ 43.55 30.74

GROUP 2

Cranes.....................$ 48.14 30.74

Oiler......................$ 36.36 30.39

Truck crane oiler..........$ 43.33 30.74

GROUP 3

Cranes.....................$ 46.40 30.74

Hydraulic..................$ 38.32 30.39

Oiler......................$ 36.14 30.39

Truck Crane Oiler..........$ 43.06 30.74

GROUP 4

Cranes.....................$ 43.36 30.74

OPERATOR: Power Equipment

(Piledriving - AREA 1:)

GROUP 1

Lifting devices............$ 45.89 30.39

Oiler......................$ 36.63 30.39

Truck crane oiler..........$ 39.20 30.39

GROUP 2

Lifting devices............$ 44.07 30.39

Oiler......................$ 36.36 30.39

Truck Crane Oiler..........$ 38.98 30.39

GROUP 3

Lifting devices............$ 42.39 30.39

Oiler......................$ 36.14 30.39

Truck Crane Oiler..........$ 38.71 30.39

GROUP 4

Lifting devices............$ 40.62 30.39

GROUP 5

Lifting devices............$ 39.32 30.39

GROUP 6

Lifting devices............$ 37.98 30.39

OPERATOR: Power Equipment

(Steel Erection - AREA 1:)

GROUP 1

Cranes.....................$ 46.30 30.39

Oiler......................$ 36.63 30.39

Truck Crane Oiler..........$ 39.20 30.39

GROUP 2

Cranes.....................$ 43.79 30.39

Oiler......................$ 36.36 30.39

Truck Crane Oiler..........$ 38.98 30.39

GROUP 3

Cranes.....................$ 42.05 30.39

Hydraulic..................$ 38.32 30.39

Oiler......................$ 36.14 30.39

Truck Crane Oiler..........$ 38.71 30.39

GROUP 4

Cranes.....................$ 39.01 30.39

GROUP 5

Cranes.....................$ 35.13 30.39

OPERATOR: Power Equipment

(Tunnel and Underground Work

- AREA 1:)

SHAFTS, STOPES, RAISES:

GROUP 1....................$ 40.77 30.39

GROUP 1-A..................$ 43.24 30.39

GROUP 2....................$ 39.51 30.39

GROUP 3....................$ 38.18 30.39

GROUP 4....................$ 37.04 30.39

GROUP 5....................$ 35.90 30.39

UNDERGROUND:

GROUP 1....................$ 40.67 30.39

GROUP 1-A..................$ 43.14 30.39

GROUP 2....................$ 39.41 30.39

GROUP 3....................$ 38.08 30.39

GROUP 4....................$ 36.94 30.39

GROUP 5....................$ 35.80 30.39

FOOTNOTE: Work suspended by ropes or cables, or work on a

Yo-Yo Cat: $.60 per hour additional.

POWER EQUIPMENT OPERATOR CLASSIFICATIONS

GROUP 1: Operator of helicopter (when used in erection work);

Hydraulic excavator, 7 cu. yds. and over; Power shovels,

over 7 cu. yds.

GROUP 2: Highline cableway; Hydraulic excavator, 3-1/2 cu.

yds. up to 7 cu. yds.; Licensed construction work boat

operator, on site; Power blade operator (finish); Power

shovels, over 1 cu. yd. up to and including 7 cu. yds.

m.r.c.

GROUP 3: Asphalt milling machine; Cable backhoe; Combination

backhoe and loader over 3/4 cu. yds.; Continuous flight tie

back machine assistant to engineer or mechanic; Crane

mounted continuous flight tie back machine, tonnage to

apply; Crane mounted drill attachment, tonnage to apply;

Dozer, slope brd; Gradall; Hydraulic excavator, up to 3 1/2

cu. yds.; Loader 4 cu. yds. and over; Long reach excavator;

Multiple engine scraper (when used as push pull); Power

shovels, up to and including 1 cu. yd.; Pre-stress wire

wrapping machine; Side boom cat, 572 or larger; Track

loader 4 cu. yds. and over; Wheel excavator (up to and

including 750 cu. yds. per hour)

GROUP 4: Asphalt plant engineer/box person; Chicago boom;

Combination backhoe and loader up to and including 3/4 cu.

yd.; Concrete batch plant (wet or dry); Dozer and/or push

cat; Pull- type elevating loader; Gradesetter, grade

checker (GPS, mechanical or otherwise); Grooving and

grinding machine; Heading shield operator; Heavy-duty

drilling equipment, Hughes, LDH, Watson 3000 or similar;

Heavy-duty repairperson and/or welder; Lime spreader;

Loader under 4 cu. yds.; Lubrication and service engineer

(mobile and grease rack); Mechanical finishers or spreader

machine (asphalt, Barber-Greene and similar); Miller

Formless M-9000 slope paver or similar; Portable crushing

and screening plants; Power blade support; Roller operator,

asphalt; Rubber-tired scraper, self-loading (paddle-wheels,

etc.); Rubber- tired earthmoving equipment (scrapers); Slip

form paver (concrete); Small tractor with drag; Soil

stabilizer (P & H or equal); Spider plow and spider puller;

Tubex pile rig; Unlicensed constuction work boat operator,

on site; Timber skidder; Track loader up to 4 yds.;

Tractor-drawn scraper; Tractor, compressor drill

combination; Welder; Woods-Mixer (and other similar Pugmill

equipment)

GROUP 5: Cast-in-place pipe laying machine; Combination

slusher and motor operator; Concrete conveyor or concrete

pump, truck or equipment mounted; Concrete conveyor,

building site; Concrete pump or pumpcrete gun; Drilling

equipment, Watson 2000, Texoma 700 or similar; Drilling and

boring machinery, horizontal (not to apply to waterliners,

wagon drills or jackhammers); Concrete mixer/all; Person

and/or material hoist; Mechanical finishers (concrete)

(Clary, Johnson, Bidwell Bridge Deck or similar types);

Mechanical burm, curb and/or curb and gutter machine,

concrete or asphalt); Mine or shaft hoist; Portable

crusher; Power jumbo operator (setting slip-forms, etc., in

tunnels); Screed (automatic or manual); Self-propelled

compactor with dozer; Tractor with boom D6 or smaller;

Trenching machine, maximum digging capacity over 5 ft.

depth; Vermeer T-600B rock cutter or similar

GROUP 6: Armor-Coater (or similar); Ballast jack tamper;

Boom- type backfilling machine; Assistant plant engineer;

Bridge and/or gantry crane; Chemical grouting machine,

truck-mounted; Chip spreading machine operator; Concrete

saw (self-propelled unit on streets, highways, airports and

canals); Deck engineer; Drilling equipment Texoma 600,

Hughes 200 Series or similar up to and including 30 ft.

m.r.c.; Drill doctor; Helicopter radio operator;

Hydro-hammer or similar; Line master; Skidsteer loader,

Bobcat larger than 743 series or similar (with

attachments); Locomotive; Lull hi-lift or similar; Oiler,

truck mounted equipment; Pavement breaker, truck-mounted,

with compressor combination; Paving fabric installation

and/or laying machine; Pipe bending machine (pipelines

only); Pipe wrapping machine (tractor propelled and

supported); Screed (except asphaltic concrete paving);

Self- propelled pipeline wrapping machine; Tractor;

Self-loading chipper; Concrete barrier moving machine

GROUP 7: Ballast regulator; Boom truck or dual-purpose

A-frame truck, non-rotating - under 15 tons; Cary lift or

similar; Combination slurry mixer and/or cleaner; Drilling

equipment, 20 ft. and under m.r.c.; Firetender (hot plant);

Grouting machine operator; Highline cableway signalperson;

Stationary belt loader (Kolman or similar); Lift slab

machine (Vagtborg and similar types); Maginnes internal

full slab vibrator; Material hoist (1 drum); Mechanical

trench shield; Pavement breaker with or without compressor

combination); Pipe cleaning machine (tractor propelled and

supported); Post driver; Roller (except asphalt); Chip

Seal; Self-propelled automatically applied concrete curing

mahcine (on streets, highways, airports and canals);

Self-propelled compactor (without dozer); Signalperson;

Slip-form pumps (lifting device for concrete forms); Tie

spacer; Tower mobile; Trenching machine, maximum digging

capacity up to and including 5 ft. depth; Truck- type loader

GROUP 8: Bit sharpener; Boiler tender; Box operator;

Brakeperson; Combination mixer and compressor

(shotcrete/gunite); Compressor operator; Deckhand; Fire

tender; Forklift (under 20 ft.); Generator;

Gunite/shotcrete equipment operator; Hydraulic monitor; Ken

seal machine (or similar); Mixermobile; Oiler; Pump

operator; Refrigeration plant; Reservoir-debris tug (self-

propelled floating); Ross Carrier (construction site);

Rotomist operator; Self-propelled tape machine; Shuttlecar;

Self-propelled power sweeper operator (includes vacuum

sweeper); Slusher operator; Surface heater; Switchperson;

Tar pot firetender; Tugger hoist, single drum; Vacuum

cooling plant; Welding machine (powered other than by

electricity)

GROUP 8-A: Elevator operator; Skidsteer loader-Bobcat 743

series or smaller, and similar (without attachments); Mini

excavator under 25 H.P. (backhoe-trencher); Tub grinder

wood chipper

----------------------------------------------------------

ALL CRANES AND ATTACHMENTS

GROUP 1: Clamshell and dragline over 7 cu. yds.; Crane, over

100 tons; Derrick, over 100 tons; Derrick barge

pedestal-mounted, over 100 tons; Self-propelled boom-type

lifting device, over 100 tons

GROUP 2: Clamshell and dragline over 1 cu. yd. up to and

including 7 cu. yds.; Crane, over 45 tons up to and

including 100 tons; Derrick barge, 100 tons and under;

Self-propelled boom-type lifting device, over 45 tons;

Tower crane

GROUP 3: Clamshell and dragline up to and including 1 cu.

yd.; Cranes 45 tons and under; Self-propelled boom-type

lifting device 45 tons and under;

GROUP 4: Boom Truck or dual purpose A-frame truck,

non-rotating over 15 tons; Truck-mounted rotating

telescopic boom type lifting device, Manitex or similar

(boom truck) over 15 tons; Truck-mounted rotating

telescopic boom type lifting device, Manitex or similar

(boom truck) - under 15 tons;

-----------------------------------------------------------

PILEDRIVERS

GROUP 1: Derrick barge pedestal mounted over 100 tons;

Clamshell over 7 cu. yds.; Self-propelled boom-type lifting

device over 100 tons; Truck crane or crawler, land or barge

mounted over 100 tons

GROUP 2: Derrick barge pedestal mounted 45 tons to and

including 100 tons; Clamshell up to and including 7 cu.

yds.; Self-propelled boom-type lifting device over 45 tons;

Truck crane or crawler, land or barge mounted, over 45 tons

up to and including 100 tons; Fundex F-12 hydraulic pile rig

GROUP 3: Derrick barge pedestal mounted under 45 tons; Self-

propelled boom-type lifting device 45 tons and under;

Skid/scow piledriver, any tonnage; Truck crane or crawler,

land or barge mounted 45 tons and under

GROUP 4: Assistant operator in lieu of assistant to engineer;

Forklift, 10 tons and over; Heavy-duty repairperson/welder

GROUP 5: Deck engineer

GROUP 6: Deckhand; Fire tender

-------------------------------------------------------------

STEEL ERECTORS

GROUP 1: Crane over 100 tons; Derrick over 100 tons; Self-

propelled boom-type lifting device over 100 tons

GROUP 2: Crane over 45 tons to 100 tons; Derrick under 100

tons; Self-propelled boom-type lifting device over 45 tons

to 100 tons; Tower crane

GROUP 3: Crane, 45 tons and under; Self-propelled boom-type

lifting device, 45 tons and under

GROUP 4: Chicago boom; Forklift, 10 tons and over; Heavy-duty

repair person/welder

GROUP 5: Boom cat

--------------------------------------------------------------

--

TUNNEL AND UNDERGROUND WORK

GROUP 1-A: Tunnel bore machine operator, 20' diameter or more

GROUP 1: Heading shield operator; Heavy-duty repairperson;

Mucking machine (rubber tired, rail or track type); Raised

bore operator (tunnels); Tunnel mole bore operator

GROUP 2: Combination slusher and motor operator; Concrete

pump or pumpcrete gun; Power jumbo operator

GROUP 3: Drill doctor; Mine or shaft hoist

GROUP 4: Combination slurry mixer cleaner; Grouting Machine

operator; Motorman

GROUP 5: Bit Sharpener; Brakeman; Combination mixer and

compressor (gunite); Compressor operator; Oiler; Pump

operator; Slusher operator

-----------------------------------------------------------

AREA DESCRIPTIONS:

POWER EQUIPMENT OPERATORS, CRANES AND ATTACHMENTS,TUNNEL AND

UNDERGROUND [These areas do not apply to Piledrivers and

Steel Erectors]

AREA 1: ALAMEDA, CALAVERAS, CONTRA COSTA, FRESNO, KINGS,

MADERA, MARIPOSA, MERCED, MONTEREY, SAN BENITO, SAN

FRANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ,

STANISLAUS, TUOLUMNE

AREA 2 -NOTED BELOW

THE REMAINING COUNTIES ARE SPLIT BETWEEN AREA 1 AND AREA 2 AS

NOTED BELOW:

CALAVERAS COUNTY:

Area 1: Remainder

Area 2: Eastern Part

FRESNO COUNTY:

Area 1: Remainder

Area 2: Eastern Part

MADERA COUNTY:

Area 1: Remainder

Area 2: Eastern Part

MARIPOSA COUNTY:

Area 1: Remainder

Area 2: Eastern Part

MONTEREY COUNTY:

Area 1: Remainder

Area 2: Southwestern part

TUOLUMNE COUNTY:

Area 1: Remainder

Area 2: Eastern Part

----------------------------------------------------------------

ENGI0003-008 07/01/2019

Rates Fringes

Dredging: (DREDGING:

CLAMSHELL & DIPPER DREDGING;

HYDRAULIC SUCTION DREDGING:)

AREA 1:

(1) Leverman...............$ 47.88 33.10

(2) Dredge Dozer; Heavy

duty repairman.............$ 42.92 33.10

(3) Booster Pump

Operator; Deck

Engineer; Deck mate;

Dredge Tender; Winch

Operator...................$ 41.80 33.10

(4) Bargeman; Deckhand;

Fireman; Leveehand; Oiler..$ 38.50 33.10

AREA 2:

(1) Leverman...............$ 49.88 33.10

(2) Dredge Dozer; Heavy

duty repairman.............$ 44.92 33.10

(3) Booster Pump

Operator; Deck

Engineer; Deck mate;

Dredge Tender; Winch

Operator...................$ 43.80 33.10

(4) Bargeman; Deckhand;

Fireman; Leveehand; Oiler..$ 40.50 33.10

AREA DESCRIPTIONS

AREA 1: ALAMEDA,BUTTE, CONTRA COSTA, KINGS, MARIN, MERCED,

NAPA, SACRAMENTO, SAN BENITO, SAN FRANCISCO, SAN JOAQUIN,

SAN MATEO, SANTA CLARA, SANTA CRUZ, SOLANO, STANISLAUS,

SUTTER, YOLO, AND YUBA COUNTIES

AREA 2: MODOC COUNTY

THE REMAINGING COUNTIES ARE SPLIT BETWEEN AREA 1 AND AREA 2

AS NOTED BELOW:

ALPINE COUNTY:

Area 1: Northernmost part

Area 2: Remainder

CALAVERAS COUNTY:

Area 1: Remainder

Area 2: Eastern part

COLUSA COUNTY:

Area 1: Eastern part

Area 2: Remainder

ELDORADO COUNTY:

Area 1: North Central part

Area 2: Remainder

FRESNO COUNTY:

Area 1: Remainder

Area 2: Eastern part

GLENN COUNTY:

Area 1: Eastern part

Area 2: Remainder

LASSEN COUNTY:

Area 1: Western part along the Southern portion of border

with Shasta County

Area 2: Remainder

MADERA COUNTY:

Area 1: Except Eastern part

Area 2: Eastern part

MARIPOSA COUNTY

Area 1: Except Eastern part

Area 2: Eastern part

MONTERREY COUNTY

Area 1: Except Southwestern part

Area 2: Southwestern part

NEVADA COUNTY:

Area 1: All but the Northern portion along the border of

Sierra County

Area 2: Remainder

PLACER COUNTY:

Area 1: Al but the Central portion

Area 2: Remainder

PLUMAS COUNTY:

Area 1: Western portion

Area 2: Remainder

SHASTA COUNTY:

Area 1: All but the Northeastern corner

Area 2: Remainder

SIERRA COUNTY:

Area 1: Western part

Area 2: Remainder

SISKIYOU COUNTY:

Area 1: Central part

Area 2: Remainder

SONOMA COUNTY:

Area 1: All but the Northwestern corner

Area 2: Remainder

TEHAMA COUNTY:

Area 1: All but the Western border with Mendocino & Trinity

Counties

Area 2: Remainder

TRINITY COUNTY:

Area 1: East Central part and the Northeastern border with

Shasta County

Area 2: Remainder

TUOLUMNE COUNTY:

Area 1: Except Eastern part

Area 2: Eastern part

----------------------------------------------------------------

ENGI0003-019 06/29/2020

SEE AREA DESCRIPTIONS BELOW

Rates Fringes

OPERATOR: Power Equipment

(LANDSCAPE WORK ONLY)

GROUP 1

AREA 1.....................$ 39.95 30.28

AREA 2.....................$ 41.95 30.28

GROUP 2

AREA 1.....................$ 36.35 30.28

AREA 2.....................$ 38.35 30.28

GROUP 3

AREA 1.....................$ 31.74 30.28

AREA 2.....................$ 33.74 30.28

GROUP DESCRIPTIONS:

GROUP 1: Landscape Finish Grade Operator: All finish grade

work regardless of equipment used, and all equipment with a

rating more than 65 HP.

GROUP 2: Landscape Operator up to 65 HP: All equipment with

a manufacturer's rating of 65 HP or less except equipment

covered by Group 1 or Group 3. The following equipment

shall be included except when used for finish work as long

as manufacturer's rating is 65 HP or less: A-Frame and

Winch Truck, Backhoe, Forklift, Hydragraphic Seeder

Machine, Roller, Rubber-Tired and Track Earthmoving

Equipment, Skiploader, Straw Blowers, and Trencher 31 HP up

to 65 HP.

GROUP 3: Landscae Utility Operator: Small Rubber-Tired

Tractor, Trencher Under 31 HP.

AREA DESCRIPTIONS:

AREA 1: ALAMEDA, BUTTE, CONTRA COSTA, KINGS, MARIN, MERCED,

NAPA, SACRAMENTO, SAN BENITO, SAN FRANCISCO, SAN JOAQUIN,

SAN MATEO, SANTA CLARA, SANTA CRUZ, SOLANO, STANISLAUS,

SUTTER, YOLO, AND YUBA COUNTIES

AREA 2 - MODOC COUNTY

THE REMAINING COUNTIES ARE SPLIT BETWEEN AREA 1 AND AREA 2 AS

NOTED BELOW:

ALPINE COUNTY:

Area 1: Northernmost part

Area 2: Remainder

CALAVERAS COUNTY:

Area 1: Except Eastern part

Area 2: Eastern part

COLUSA COUNTY:

Area 1: Eastern part

Area 2: Remainder

DEL NORTE COUNTY:

Area 1: Extreme Southwestern corner

Area 2: Remainder

ELDORADO COUNTY:

Area 1: North Central part

Area 2: Remainder

FRESNO COUNTY

Area 1: Except Eastern part

Area 2: Eastern part

GLENN COUNTY:

Area 1: Eastern part

Area 2: Remainder

HUMBOLDT COUNTY:

Area 1: Except Eastern and Southwestern parts

Area 2: Remainder

LAKE COUNTY:

Area 1: Southern part

Area 2: Remainder

LASSEN COUNTY:

Area 1: Western part along the Southern portion of border

with Shasta County

Area 2: Remainder

MADERA COUNTY

Area 1: Remainder

Area 2: Eastern part

MARIPOSA COUNTY

Area 1: Remainder

Area 2: Eastern part

MENDOCINO COUNTY:

Area 1: Central and Southeastern parts

Area 2: Remainder

MONTEREY COUNTY

Area 1: Remainder

Area 2: Southwestern part

NEVADA COUNTY:

Area 1: All but the Northern portion along the border of

Sierra County

Area 2: Remainder

PLACER COUNTY:

Area 1: All but the Central portion

Area 2: Remainder

PLUMAS COUNTY:

Area 1: Western portion

Area 2: Remainder

SHASTA COUNTY:

Area 1: All but the Northeastern corner

Area 2: Remainder

SIERRA COUNTY:

Area 1: Western part

Area 2: Remainder

SISKIYOU COUNTY:

Area 1: Central part

Area 2: Remainder

SONOMA COUNTY:

Area 1: All but the Northwestern corner

Area 2: Reaminder

TEHAMA COUNTY:

Area 1: All but the Western border with mendocino & Trinity

Counties

Area 2: Remainder

TRINITY COUNTY:

Area 1: East Central part and the Northeaster border with

Shasta County

Area 2: Remainder

TULARE COUNTY;

Area 1: Remainder

Area 2: Eastern part

TUOLUMNE COUNTY:

Area 1: Remainder

Area 2: Eastern Part

----------------------------------------------------------------

IRON0377-001 07/01/2020

ALAMEDA, CONTRA COSTA, SAN MATEO, SANTA CLARA & SAN FRANCISCO

COUNTIES

Rates Fringes

Ironworkers:

Fence Erector...............$ 34.58 24.81

Ornamental, Reinforcing

and Structural..............$ 42.50 33.45

PREMIUM PAY:

$6.00 additional per hour at the following locations:

China Lake Naval Test Station, Chocolate Mountains Naval

Reserve-Niland,

Edwards AFB, Fort Irwin Military Station, Fort Irwin Training

Center-Goldstone, San Clemente Island, San Nicholas Island,

Susanville Federal Prison, 29 Palms - Marine Corps, U.S. Marine

Base - Barstow, U.S. Naval Air Facility - Sealey, Vandenberg AFB

$4.00 additional per hour at the following locations:

Army Defense Language Institute - Monterey, Fallon Air Base,

Naval Post Graduate School - Monterey, Yermo Marine Corps

Logistics Center

$2.00 additional per hour at the following locations:

Port Hueneme, Port Mugu, U.S. Coast Guard Station - Two Rock

----------------------------------------------------------------

IRON0433-005 07/01/2020

REMAINING COUNTIES

Rates Fringes

IRONWORKER

Fence Erector...............$ 34.58 24.81

Ornamental, Reinforcing

and Structural..............$ 41.00 33.45

PREMIUM PAY:

$6.00 additional per hour at the following locations:

China Lake Naval Test Station, Chocolate Mountains Naval

Reserve-Niland,

Edwards AFB, Fort Irwin Military Station, Fort Irwin Training

Center-Goldstone, San Clemente Island, San Nicholas Island,

Susanville Federal Prison, 29 Palms - Marine Corps, U.S. Marine

Base - Barstow, U.S. Naval Air Facility - Sealey, Vandenberg AFB

$4.00 additional per hour at the following locations:

Army Defense Language Institute - Monterey, Fallon Air Base,

Naval Post Graduate School - Monterey, Yermo Marine Corps

Logistics Center

$2.00 additional per hour at the following locations:

Port Hueneme, Port Mugu, U.S. Coast Guard Station - Two Rock

----------------------------------------------------------------

LABO0067-002 06/29/2020

AREA ""A"" - ALAMEDA, CONTRA COSTA, SAN FRANCISCO, SAN MATEO AND

SANTA CLARA COUNTIES

AREA ""B"" - CALAVERAS, FRESNO, KINGS, MADERA, MARIPOSA,

MERCED, MONTEREY, SAN BENITO, SAN JOAQUIN, STANISLAUS, AND

TUOLUMNE COUNTIES

Rates Fringes

Asbestos Removal Laborer

All Counties................$ 25.05 12.00

LABORER (Lead Removal)

Area A......................$ 33.07 25.30

Area B......................$ 32.07 25.30

ASBESTOS REMOVAL-SCOPE OF WORK: Site mobilization; initial

site clean-up; site preparation; removal of

asbestos-containing materials from walls and ceilings; or

from pipes, boilers and mechanical systems only if they are

being scrapped; encapsulation, enclosure and disposal of

asbestos-containing materials by hand or with equipment or

machinery; scaffolding; fabrication of temporary wooden

barriers; and assembly of decontamination stations.

----------------------------------------------------------------

LABO0073-002 06/25/2018

CALAVERAS AND SAN JOAQUIN COUNTIES

Rates Fringes

LABORER (TRAFFIC CONTROL/LANE

CLOSURE)

Escort Driver, Flag Person..$ 29.54 23.65

Traffic Control Person I....$ 29.84 23.65

Traffic Control Person II...$ 27.34 23.65

TRAFFIC CONTROL PERSON I: Layout of traffic control, crash

cushions, construction area and roadside signage.

TRAFFIC CONTROL PERSON II: Installation and removal of

temporary/permanent signs, markers, delineators and crash

cushions.

----------------------------------------------------------------

LABO0073-003 07/01/2020

SAN JOAQUIN COUNTY

Rates Fringes

LABORER

Mason Tender-Brick..........$ 32.84 23.71

----------------------------------------------------------------

LABO0073-005 06/25/2018

Rates Fringes

Tunnel and Shaft Laborers:

GROUP 1.....................$ 37.82 24.11

GROUP 2.....................$ 37.59 24.11

GROUP 3.....................$ 37.34 24.11

GROUP 4.....................$ 36.89 24.11

GROUP 5.....................$ 36.35 24.11

Shotcrete Specialist........$ 38.34 24.11

TUNNEL AND SHAFT CLASSIFICATIONS

GROUP 1: Diamond driller; Groundmen; Gunite and shotcrete

nozzlemen

GROUP 2: Rodmen; Shaft work & raise (below actual or

excavated ground level)

GROUP 3: Bit grinder; Blaster, driller, powdermen, heading;

Cherry pickermen - where car is lifted; Concrete finisher

in tunnel; Concrete screedman; Grout pumpman and potman;

Gunite & shotcrete gunman & potman; Headermen; High

pressure nozzleman; Miner - tunnel, including top and

bottom man on shaft and raise work; Nipper; Nozzleman on

slick line; Sandblaster - potman, Robotic Shotcrete Placer,

Segment Erector, Tunnel Muck Hauler, Steel Form raiser and

setter; Timberman, retimberman (wood or steel or substitute

materials therefore); Tugger (for tunnel laborer work);

Cable tender; Chuck tender; Powderman - primer house

GROUP 4: Vibrator operator, pavement breaker; Bull gang -

muckers, trackmen; Concrete crew - includes rodding and

spreading, Dumpmen (any method)

GROUP 5: Grout crew; Reboundman; Swamper/ Brakeman

----------------------------------------------------------------

LABO0073-007 06/25/2018

CALAVERAS AND SAN JOAQUIN COUNTIES

Rates Fringes

LABORER (CONSTRUCTION CRAFT

LABORERS)

Construction Specialist

Group.......................$ 30.49 23.20

GROUP 1.....................$ 29.79 23.20

GROUP 1-a...................$ 30.01 23.20

GROUP 1-c...................$ 29.84 23.20

GROUP 1-e...................$ 30.34 23.20

GROUP 1-f...................$ 30.37 23.20

GROUP 2.....................$ 29.64 23.20

GROUP 3.....................$ 29.54 23.20

GROUP 4.....................$ 23.23 23.20

See groups 1-b and 1-d under laborer classifications.

LABORER (GARDENERS,

HORTICULTURAL & LANDSCAPE

LABORERS)

(1) New Construction........$ 29.54 23.20

(2) Establishment Warranty

Period......................$ 23.23 23.20

LABORER (GUNITE)

GROUP 1.....................$ 29.75 22.31

GROUP 2.....................$ 29.25 22.31

GROUP 3.....................$ 28.66 22.31

GROUP 4.....................$ 28.54 22.31

LABORER (WRECKING)

GROUP 1.....................$ 29.79 23.20

GROUP 2.....................$ 29.64 23.20

FOOTNOTES:

Laborers working off or with or from bos'n chairs, swinging

scaffolds, belts shall receive $0.25 per hour above the

applicable wage rate. This shall not apply to workers

entitled to receive the wage rate set forth in Group 1-a

below.

---------------------------------------------------------

LABORER CLASSIFICATIONS

CONSTRUCTION SPECIALIST GROUP: Asphalt ironer and raker;

Chainsaw; Laser beam in connection with laborers' work;

Cast-in- place manhole form setter; Pressure pipelayer;

Davis trencher - 300 or similar type (and all small

trenchers); Blaster; Diamond driller; Multiple unit drill;

Hydraulic drill

GROUP 1: Asphalt spreader boxes (all types); Barko, Wacker

and similar type tampers; Buggymobile; Caulker, bander,

pipewrapper, conduit layer, plastic pipelayer; Certified

hazardous waste worker including Leade Abatement;

Compactors of all types; Concrete and magnesite mixer, 1/2

yd. and under; Concrete pan work; Concrete sander; Concrete

saw; Cribber and/or shoring; Cut granite curb setter;

Dri-pak-it machine; Faller, logloader and bucker; Form

raiser, slip forms; Green cutter; Headerboard, Hubsetter,

aligner, by any method; High pressure blow pipe (1-1/2"" or

over, 100 lbs. pressure/over); Hydro seeder and similar

type; Jackhammer operator; Jacking of pipe over 12 inches;

Jackson and similar type compactor; Kettle tender, pot and

worker applying asphalt, lay-kold, creosote, lime, caustic

and similar type materials (applying means applying,

dipping or handling of such materials); Lagging, sheeting,

whaling, bracing, trenchjacking, lagging hammer; Magnesite,

epoxyresin, fiberglass, mastic worker (wet or dry); No

joint pipe and stripping of same, including repair of

voids; Pavement breaker and spader, including tool grinder;

Perma curb; Pipelayer (including grade checking in

connection with pipelaying); Precast-manhole setter;

Pressure pipe tester; Post hole digger, air, gas and

electric; Power broom sweeper; Power tampers of all types

(except as shown in Group 2); Ram set gun and stud gun;

Riprap stonepaver and rock-slinger, including placing of

sacked concrete and/or sand (wet or dry) and gabions and

similar type; Rotary scarifier or multiple head concrete

chipping scarifier; Roto and Ditch Witch; Rototiller;

Sandblaster, pot, gun, nozzle operators; Signalling and

rigging; Tank cleaner; Tree climber; Turbo blaster;

Vibrascreed, bull float in connection with laborers' work;

Vibrator; Hazardous waste worker (lead removal); Asbestos

and mold removal worker

GROUP 1-a: Joy drill model TWM-2A; Gardner-Denver model DH143

and similar type drills; Track driller; Jack leg driller;

Wagon driller; Mechanical drillers, all types regardless of

type or method of power; Mechanical pipe layers, all types

regardless of type or method of power; Blaster and powder;

All work of loading, placing and blasting of all powder and

explosives of whatever type regardless of method used for

such loading and placing; High scalers (including drilling

of same); Tree topper; Bit grinder

GROUP 1-b: Sewer cleaners shall receive $4.00 per day above

Group 1 wage rates. ""Sewer cleaner"" means any worker who

handles or comes in contact with raw sewage in small

diameter sewers. Those who work inside recently active,

large diameter sewers, and all recently active sewer

manholes shal receive $5.00 per day above Group 1 wage

rates.

GROUP 1-c: Burning and welding in connection with laborers'

work; Synthetic thermoplastics and similar type welding

GROUP 1-d: Maintenance and repair track and road beds. All

employees performing work covered herein shall receive $

.25 per hour above their regular rate for all work

performed on underground structures not specifically

covered herein. This paragraph shall not be construed to

apply to work below ground level in open cut. It shall

apply to cut and cover work of subway construction after

the temporary cover has been placed.

GROUP 1-e: Work on and/or in bell hole footings and shafts

thereof, and work on and in deep footings. (A deep footing

is a hole 15 feet or more in depth.) In the event the

depth of the footing is unknown at the commencement of

excavation, and the final depth exceeds 15 feet, the deep

footing wage rate would apply to all employees for each and

every day worked on or in the excavation of the footing

from the date of inception.

GROUP 1-f: Wire winding machine in connection with guniting

or shot crete

GROUP 2: Asphalt shoveler; Cement dumper and handling dry

cement or gypsum; Choke-setter and rigger (clearing work);

Concrete bucket dumper and chute; Concrete chipping and

grinding; Concrete laborer (wet or dry); Driller tender,

chuck tender, nipper; Guinea chaser (stake), grout crew;

High pressure nozzle, adductor; Hydraulic monitor (over 100

lbs. pressure); Loading and unloading, carrying and hauling

of all rods and materials for use in reinforcing concrete

construction; Pittsburgh chipper and similar type brush

shredders; Sloper; Single foot, hand-held, pneumatic

tamper; All pneumatic, air, gas and electric tools not

listed in Groups 1 through 1-f; Jacking of pipe - under 12

inches

GROUP 3: Construction laborers, including bridge and general

laborer; Dump, load spotter; Flag person; Fire watcher;

Fence erector; Guardrail erector; Gardener, horticultural

and landscape laborer; Jetting; Limber, brush loader and

piler; Pavement marker (button setter); Maintenance, repair

track and road beds; Streetcar and railroad construction

track laborer; Temporary air and water lines, Victaulic or

similar; Tool room attendant (jobsite only)

GROUP 4: Final clean-up work of debris, grounds and building

including but not limited to: street cleaner; cleaning and

washing windows; brick cleaner (jobsite only); material

cleaner (jobsite only). The classification ""material

cleaner"" is to be utilized under the following conditions:

A: at demolition site for the salvage of the material.

B: at the conclusion of a job where the material is to be

salvaged and stocked to be reused on another job.

C: for the cleaning of salvage material at the jobsite or

temporary jobsite yard.

The material cleaner classification should not be used in

the performance of ""form stripping, cleaning and oiling

and moving to the next point of erection"".

--------------------------------------------------------

GUNITE LABORER CLASSIFICATIONS

GROUP 1: Structural Nozzleman

GROUP 2: Nozzleman, Gunman, Potman, Groundman

GROUP 3: Reboundman

GROUP 4: Gunite laborer

----------------------------------------------------------

WRECKING WORK LABORER CLASSIFICATIONS

GROUP 1: Skilled wrecker (removing and salvaging of sash,

windows and materials)

GROUP 2: Semi-skilled wrecker (salvaging of other building

materials)

----------------------------------------------------------------

LABO0073-009 07/01/2018

CALAVERAS AND SAN JOAQUIN COUNTIES

Rates Fringes

LABORER (Plaster Tender).........$ 32.02 23.00

Work on a swing stage scaffold: $1.00 per hour additional.

----------------------------------------------------------------

LABO0261-003 06/25/2018

SAN FRANCISCO AND SAN MATEO COUNTIES

Rates Fringes

LABORER (TRAFFIC CONTROL/LANE

CLOSURE)

Escort Driver, Flag Person..$ 20.54 23.65

Traffic Control Person I....$ 30.84 23.65

Traffic Control Person II...$ 28.34 23.65

TRAFFIC CONTROL PERSON I: Layout of traffic control, crash

cushions, construction area and roadside signage.

TRAFFIC CONTROL PERSON II: Installation and removal of

temporary/permanent signs, markers, delineators and crash

cushions.

----------------------------------------------------------------

LABO0261-005 06/25/2018

SAN FRANCISCO AND SAN MATEO COUNTIES

Rates Fringes

Tunnel and Shaft Laborers:

GROUP 1.....................$ 37.82 24.11

GROUP 2.....................$ 37.59 24.11

GROUP 3.....................$ 37.34 24.11

GROUP 4.....................$ 36.89 24.11

GROUP 5.....................$ 36.35 24.11

Shotcrete Specialist........$ 38.34 24.11

TUNNEL AND SHAFT CLASSIFICATIONS

GROUP 1: Diamond driller; Groundmen; Gunite and shotcrete

nozzlemen

GROUP 2: Rodmen; Shaft work & raise (below actual or

excavated ground level)

GROUP 3: Bit grinder; Blaster, driller, powdermen, heading;

Cherry pickermen - where car is lifted; Concrete finisher

in tunnel; Concrete screedman; Grout pumpman and potman;

Gunite & shotcrete gunman & potman; Headermen; High

pressure nozzleman; Miner - tunnel, including top and

bottom man on shaft and raise work; Nipper; Nozzleman on

slick line; Sandblaster - potman, Robotic Shotcrete Placer,

Segment Erector, Tunnel Muck Hauler, Steel Form raiser and

setter; Timberman, retimberman (wood or steel or substitute

materials therefore); Tugger (for tunnel laborer work);

Cable tender; Chuck tender; Powderman - primer house

GROUP 4: Vibrator operator, pavement breaker; Bull gang -

muckers, trackmen; Concrete crew - includes rodding and

spreading, Dumpmen (any method)

GROUP 5: Grout crew; Reboundman; Swamper/ Brakeman

----------------------------------------------------------------

LABO0261-009 06/25/2018

SAN FRANCISCO, AND SAN MATEO COUNTIES

Rates Fringes

LABORER (CONSTRUCTION CRAFT

LABORERS - AREA A:)

Construction Specialist

Group.......................$ 31.49 23.20

GROUP 1.....................$ 30.79 23.20

GROUP 1-a...................$ 31.01 23.20

GROUP 1-c...................$ 30.84 23.20

GROUP 1-e...................$ 31.34 23.20

GROUP 1-f...................$ 31.37 23.20

GROUP 2.....................$ 30.64 23.20

GROUP 3.....................$ 30.54 23.20

GROUP 4.....................$ 24.23 23.20

See groups 1-b and 1-d under laborer classifications.

LABORER (GARDENERS,

HORTICULTURAL & LANDSCAPE

LABORERS - AREA A:)

(1) New Construction........$ 30.54 23.20

(2) Establishment Warranty

Period......................$ 24.23 23.20

LABORER (WRECKING - AREA A:)

GROUP 1.....................$ 30.79 23.20

GROUP 2.....................$ 30.64 23.20

Laborers: (GUNITE - AREA A:)

GROUP 1.....................$ 30.75 22.31

GROUP 2.....................$ 30.25 22.31

GROUP 3.....................$ 29.66 22.31

GROUP 4.....................$ 29.54 22.31

FOOTNOTES:

Laborers working off or with or from bos'n chairs, swinging

scaffolds, belts shall receive $0.25 per hour above the

applicable wage rate. This shall not apply to workers

entitled to receive the wage rate set forth in Group 1-a

below.

---------------------------------------------------------

LABORER CLASSIFICATIONS

CONSTRUCTION SPECIALIST GROUP: Asphalt ironer and raker;

Chainsaw; Laser beam in connection with laborers' work;

Cast-in- place manhole form setter; Pressure pipelayer;

Davis trencher - 300 or similar type (and all small

trenchers); Blaster; Diamond driller; Multiple unit drill;

Hydraulic drill

GROUP 1: Asphalt spreader boxes (all types); Barko, Wacker

and similar type tampers; Buggymobile; Caulker, bander,

pipewrapper, conduit layer, plastic pipelayer; Certified

hazardous waste worker including Leade Abatement;

Compactors of all types; Concrete and magnesite mixer, 1/2

yd. and under; Concrete pan work; Concrete sander; Concrete

saw; Cribber and/or shoring; Cut granite curb setter;

Dri-pak-it machine; Faller, logloader and bucker; Form

raiser, slip forms; Green cutter; Headerboard, Hubsetter,

aligner, by any method; High pressure blow pipe (1-1/2"" or

over, 100 lbs. pressure/over); Hydro seeder and similar

type; Jackhammer operator; Jacking of pipe over 12 inches;

Jackson and similar type compactor; Kettle tender, pot and

worker applying asphalt, lay-kold, creosote, lime, caustic

and similar type materials (applying means applying,

dipping or handling of such materials); Lagging, sheeting,

whaling, bracing, trenchjacking, lagging hammer; Magnesite,

epoxyresin, fiberglass, mastic worker (wet or dry); No

joint pipe and stripping of same, including repair of

voids; Pavement breaker and spader, including tool grinder;

Perma curb; Pipelayer (including grade checking in

connection with pipelaying); Precast-manhole setter;

Pressure pipe tester; Post hole digger, air, gas and

electric; Power broom sweeper; Power tampers of all types

(except as shown in Group 2); Ram set gun and stud gun;

Riprap stonepaver and rock-slinger, including placing of

sacked concrete and/or sand (wet or dry) and gabions and

similar type; Rotary scarifier or multiple head concrete

chipping scarifier; Roto and Ditch Witch; Rototiller;

Sandblaster, pot, gun, nozzle operators; Signalling and

rigging; Tank cleaner; Tree climber; Turbo blaster;

Vibrascreed, bull float in connection with laborers' work;

Vibrator; Hazardous waste worker (lead removal); Asbestos

and mold removal worker

GROUP 1-a: Joy drill model TWM-2A; Gardner-Denver model DH143

and similar type drills; Track driller; Jack leg driller;

Wagon driller; Mechanical drillers, all types regardless of

type or method of power; Mechanical pipe layers, all types

regardless of type or method of power; Blaster and powder;

All work of loading, placing and blasting of all powder and

explosives of whatever type regardless of method used for

such loading and placing; High scalers (including drilling

of same); Tree topper; Bit grinder

GROUP 1-b: Sewer cleaners shall receive $4.00 per day above

Group 1 wage rates. ""Sewer cleaner"" means any worker who

handles or comes in contact with raw sewage in small

diameter sewers. Those who work inside recently active,

large diameter sewers, and all recently active sewer

manholes shal receive $5.00 per day above Group 1 wage

rates.

GROUP 1-c: Burning and welding in connection with laborers'

work; Synthetic thermoplastics and similar type welding

GROUP 1-d: Maintenance and repair track and road beds. All

employees performing work covered herein shall receive $

.25 per hour above their regular rate for all work

performed on underground structures not specifically

covered herein. This paragraph shall not be construed to

apply to work below ground level in open cut. It shall

apply to cut and cover work of subway construction after

the temporary cover has been placed.

GROUP 1-e: Work on and/or in bell hole footings and shafts

thereof, and work on and in deep footings. (A deep footing

is a hole 15 feet or more in depth.) In the event the

depth of the footing is unknown at the commencement of

excavation, and the final depth exceeds 15 feet, the deep

footing wage rate would apply to all employees for each and

every day worked on or in the excavation of the footing

from the date of inception.

GROUP 1-f: Wire winding machine in connection with guniting

or shot crete

GROUP 2: Asphalt shoveler; Cement dumper and handling dry

cement or gypsum; Choke-setter and rigger (clearing work);

Concrete bucket dumper and chute; Concrete chipping and

grinding; Concrete laborer (wet or dry); Driller tender,

chuck tender, nipper; Guinea chaser (stake), grout crew;

High pressure nozzle, adductor; Hydraulic monitor (over 100

lbs. pressure); Loading and unloading, carrying and hauling

of all rods and materials for use in reinforcing concrete

construction; Pittsburgh chipper and similar type brush

shredders; Sloper; Single foot, hand-held, pneumatic

tamper; All pneumatic, air, gas and electric tools not

listed in Groups 1 through 1-f; Jacking of pipe - under 12

inches

GROUP 3: Construction laborers, including bridge and general

laborer; Dump, load spotter; Flag person; Fire watcher;

Fence erector; Guardrail erector; Gardener, horticultural

and landscape laborer; Jetting; Limber, brush loader and

piler; Pavement marker (button setter); Maintenance, repair

track and road beds; Streetcar and railroad construction

track laborer; Temporary air and water lines, Victaulic or

similar; Tool room attendant (jobsite only)

GROUP 4: Final clean-up work of debris, grounds and building

including but not limited to: street cleaner; cleaning and

washing windows; brick cleaner (jobsite only); material

cleaner (jobsite only). The classification ""material

cleaner"" is to be utilized under the following conditions:

A: at demolition site for the salvage of the material.

B: at the conclusion of a job where the material is to be

salvaged and stocked to be reused on another job.

C: for the cleaning of salvage material at the jobsite or

temporary jobsite yard.

The material cleaner classification should not be used in

the performance of ""form stripping, cleaning and oiling

and moving to the next point of erection"".

--------------------------------------------------------

GUNITE LABORER CLASSIFICATIONS

GROUP 1: Structural Nozzleman

GROUP 2: Nozzleman, Gunman, Potman, Groundman

GROUP 3: Reboundman

GROUP 4: Gunite laborer

----------------------------------------------------------

WRECKING WORK LABORER CLASSIFICATIONS

GROUP 1: Skilled wrecker (removing and salvaging of sash,

windows and materials)

GROUP 2: Semi-skilled wrecker (salvaging of other building

materials)

----------------------------------------------------------------

LABO0261-011 05/01/2018

SAN FRANCISCO AND SAN MATEO COUNTIES:

Rates Fringes

MASON TENDER, BRICK..............$ 35.37 20.70

FOOTNOTES: Underground work such as sewers, manholes, catch

basins, sewer pipes, telephone conduits, tunnels and cut

trenches: $5.00 per day additional. Work in live sewage:

$2.50 per day additional.

----------------------------------------------------------------

LABO0261-014 07/01/2017

SAN FRANCISCO AND SAN MATEO COUNTIES:

Rates Fringes

PLASTER TENDER...................$ 34.70 23.11

Work on a swing stage scaffold: $1.00 per hour additional.

----------------------------------------------------------------

LABO0270-003 06/25/2018

AREA A: SANTA CLARA

AREA B: MONTEREY, SAN BENITO AND SANTA CRUZ COUNTIES

Rates Fringes

LABORER (TRAFFIC CONTROL/LANE

CLOSURE)

Escort Driver, Flag Person

Area A.....................$ 30.54 23.65

Area B.....................$ 29.54 23.65

Traffic Control Person I

Area A.....................$ 30.84 23.65

Area B.....................$ 29.84 23.65

Traffic Control Person II

Area A.....................$ 28.34 23.65

Area B.....................$ 27.34 23.65

TRAFFIC CONTROL PERSON I: Layout of traffic control, crash

cushions, construction area and roadside signage.

TRAFFIC CONTROL PERSON II: Installation and removal of

temporary/permanent signs, markers, delineators and crash

cushions.

----------------------------------------------------------------

LABO0270-004 06/25/2018

MONTEREY, SAN BENITO, SANTA CLARA, AND SANTA CRUZ COUNTIES

Rates Fringes

Tunnel and Shaft Laborers:

GROUP 1.....................$ 37.82 24.11

GROUP 2.....................$ 37.59 24.11

GROUP 3.....................$ 37.34 24.11

GROUP 4.....................$ 36.89 24.11

GROUP 5.....................$ 36.35 24.11

Shotcrete Specialist........$ 38.34 24.11

TUNNEL AND SHAFT CLASSIFICATIONS

GROUP 1: Diamond driller; Groundmen; Gunite and shotcrete

nozzlemen

GROUP 2: Rodmen; Shaft work & raise (below actual or

excavated ground level)

GROUP 3: Bit grinder; Blaster, driller, powdermen, heading;

Cherry pickermen - where car is lifted; Concrete finisher

in tunnel; Concrete screedman; Grout pumpman and potman;

Gunite & shotcrete gunman & potman; Headermen; High

pressure nozzleman; Miner - tunnel, including top and

bottom man on shaft and raise work; Nipper; Nozzleman on

slick line; Sandblaster - potman, Robotic Shotcrete Placer,

Segment Erector, Tunnel Muck Hauler, Steel Form raiser and

setter; Timberman, retimberman (wood or steel or substitute

materials therefore); Tugger (for tunnel laborer work);

Cable tender; Chuck tender; Powderman - primer house

GROUP 4: Vibrator operator, pavement breaker; Bull gang -

muckers, trackmen; Concrete crew - includes rodding and

spreading, Dumpmen (any method)

GROUP 5: Grout crew; Reboundman; Swamper/ Brakeman

----------------------------------------------------------------

LABO0270-005 07/01/2020

MONTEREY AND SAN BENITO COUNTIES

Rates Fringes

LABORER

Mason Tender-Brick..........$ 32.84 23.71

----------------------------------------------------------------

LABO0270-007 06/25/2018

MONTEREY, SAN BENITO, AND SANTA CRUZ, COUNTIES

Rates Fringes

LABORER (CONSTRUCTION CRAFT

LABORERS - AREA B)

Construction Specialist

Group.......................$ 30.40 23.20

GROUP 1.....................$ 29.79 23.20

GROUP 1-a...................$ 30.01 23.20

GROUP 1-c...................$ 29.84 23.20

GROUP 1-e...................$ 30.34 23.20

GROUP 1-f...................$ 30.37 23.20

GROUP 2.....................$ 29.64 23.20

GROUP 3.....................$ 29.54 23.20

GROUP 4.....................$ 23.23 23.20

See groups 1-b and 1-d under laborer classifications.

LABORER (GARDENERS,

HORTICULTURAL & LANDSCAPE

LABORERS - AREA B)

(1) New Construction........$ 29.54 23.20

(2) Establishment Warranty

Period......................$ 23.23 23.20

LABORER (GUNITE - AREA B)

GROUP 1.....................$ 29.75 22.31

GROUP 2.....................$ 29.25 22.31

GROUP 3.....................$ 28.66 22.31

GROUP 4.....................$ 28.54 22.31

LABORER (WRECKING - AREA B)

GROUP 1.....................$ 29.79 23.20

GROUP 2.....................$ 29.64 23.20

FOOTNOTES:

Laborers working off or with or from bos'n chairs, swinging

scaffolds, belts shall receive $0.25 per hour above the

applicable wage rate. This shall not apply to workers

entitled to receive the wage rate set forth in Group 1-a

below.

---------------------------------------------------------

LABORER CLASSIFICATIONS

CONSTRUCTION SPECIALIST GROUP: Asphalt ironer and raker;

Chainsaw; Laser beam in connection with laborers' work;

Cast-in- place manhole form setter; Pressure pipelayer;

Davis trencher - 300 or similar type (and all small

trenchers); Blaster; Diamond driller; Multiple unit drill;

Hydraulic drill

GROUP 1: Asphalt spreader boxes (all types); Barko, Wacker

and similar type tampers; Buggymobile; Caulker, bander,

pipewrapper, conduit layer, plastic pipelayer; Certified

hazardous waste worker including Leade Abatement;

Compactors of all types; Concrete and magnesite mixer, 1/2

yd. and under; Concrete pan work; Concrete sander; Concrete

saw; Cribber and/or shoring; Cut granite curb setter;

Dri-pak-it machine; Faller, logloader and bucker; Form

raiser, slip forms; Green cutter; Headerboard, Hubsetter,

aligner, by any method; High pressure blow pipe (1-1/2"" or

over, 100 lbs. pressure/over); Hydro seeder and similar

type; Jackhammer operator; Jacking of pipe over 12 inches;

Jackson and similar type compactor; Kettle tender, pot and

worker applying asphalt, lay-kold, creosote, lime, caustic

and similar type materials (applying means applying,

dipping or handling of such materials); Lagging, sheeting,

whaling, bracing, trenchjacking, lagging hammer; Magnesite,

epoxyresin, fiberglass, mastic worker (wet or dry); No

joint pipe and stripping of same, including repair of

voids; Pavement breaker and spader, including tool grinder;

Perma curb; Pipelayer (including grade checking in

connection with pipelaying); Precast-manhole setter;

Pressure pipe tester; Post hole digger, air, gas and

electric; Power broom sweeper; Power tampers of all types

(except as shown in Group 2); Ram set gun and stud gun;

Riprap stonepaver and rock-slinger, including placing of

sacked concrete and/or sand (wet or dry) and gabions and

similar type; Rotary scarifier or multiple head concrete

chipping scarifier; Roto and Ditch Witch; Rototiller;

Sandblaster, pot, gun, nozzle operators; Signalling and

rigging; Tank cleaner; Tree climber; Turbo blaster;

Vibrascreed, bull float in connection with laborers' work;

Vibrator; Hazardous waste worker (lead removal); Asbestos

and mold removal worker

GROUP 1-a: Joy drill model TWM-2A; Gardner-Denver model DH143

and similar type drills; Track driller; Jack leg driller;

Wagon driller; Mechanical drillers, all types regardless of

type or method of power; Mechanical pipe layers, all types

regardless of type or method of power; Blaster and powder;

All work of loading, placing and blasting of all powder and

explosives of whatever type regardless of method used for

such loading and placing; High scalers (including drilling

of same); Tree topper; Bit grinder

GROUP 1-b: Sewer cleaners shall receive $4.00 per day above

Group 1 wage rates. ""Sewer cleaner"" means any worker who

handles or comes in contact with raw sewage in small

diameter sewers. Those who work inside recently active,

large diameter sewers, and all recently active sewer

manholes shal receive $5.00 per day above Group 1 wage

rates.

GROUP 1-c: Burning and welding in connection with laborers'

work; Synthetic thermoplastics and similar type welding

GROUP 1-d: Maintenance and repair track and road beds. All

employees performing work covered herein shall receive $

.25 per hour above their regular rate for all work

performed on underground structures not specifically

covered herein. This paragraph shall not be construed to

apply to work below ground level in open cut. It shall

apply to cut and cover work of subway construction after

the temporary cover has been placed.

GROUP 1-e: Work on and/or in bell hole footings and shafts

thereof, and work on and in deep footings. (A deep footing

is a hole 15 feet or more in depth.) In the event the

depth of the footing is unknown at the commencement of

excavation, and the final depth exceeds 15 feet, the deep

footing wage rate would apply to all employees for each and

every day worked on or in the excavation of the footing

from the date of inception.

GROUP 1-f: Wire winding machine in connection with guniting

or shot crete

GROUP 2: Asphalt shoveler; Cement dumper and handling dry

cement or gypsum; Choke-setter and rigger (clearing work);

Concrete bucket dumper and chute; Concrete chipping and

grinding; Concrete laborer (wet or dry); Driller tender,

chuck tender, nipper; Guinea chaser (stake), grout crew;

High pressure nozzle, adductor; Hydraulic monitor (over 100

lbs. pressure); Loading and unloading, carrying and hauling

of all rods and materials for use in reinforcing concrete

construction; Pittsburgh chipper and similar type brush

shredders; Sloper; Single foot, hand-held, pneumatic

tamper; All pneumatic, air, gas and electric tools not

listed in Groups 1 through 1-f; Jacking of pipe - under 12

inches

GROUP 3: Construction laborers, including bridge and general

laborer; Dump, load spotter; Flag person; Fire watcher;

Fence erector; Guardrail erector; Gardener, horticultural

and landscape laborer; Jetting; Limber, brush loader and

piler; Pavement marker (button setter); Maintenance, repair

track and road beds; Streetcar and railroad construction

track laborer; Temporary air and water lines, Victaulic or

similar; Tool room attendant (jobsite only)

GROUP 4: Final clean-up work of debris, grounds and building

including but not limited to: street cleaner; cleaning and

washing windows; brick cleaner (jobsite only); material

cleaner (jobsite only). The classification ""material

cleaner"" is to be utilized under the following conditions:

A: at demolition site for the salvage of the material.

B: at the conclusion of a job where the material is to be

salvaged and stocked to be reused on another job.

C: for the cleaning of salvage material at the jobsite or

temporary jobsite yard.

The material cleaner classification should not be used in

the performance of ""form stripping, cleaning and oiling

and moving to the next point of erection"".

--------------------------------------------------------

GUNITE LABORER CLASSIFICATIONS

GROUP 1: Structural Nozzleman

GROUP 2: Nozzleman, Gunman, Potman, Groundman

GROUP 3: Reboundman

GROUP 4: Gunite laborer

----------------------------------------------------------

WRECKING WORK LABORER CLASSIFICATIONS

GROUP 1: Skilled wrecker (removing and salvaging of sash,

windows and materials)

GROUP 2: Semi-skilled wrecker (salvaging of other building

materials)

----------------------------------------------------------------

LABO0270-010 06/25/2018

SANTA CLARA COUNTY

Rates Fringes

LABORER (CONSTRUCTION CRAFT

LABORERS - AREA A:)

Construction Specialist

Group.......................$ 31.49 23.20

GROUP 1.....................$ 30.79 23.20

GROUP 1-a...................$ 31.01 23.20

GROUP 1-c...................$ 30.84 23.20

GROUP 1-e...................$ 31.34 23.20

GROUP 1-f...................$ 30.37 23.20

GROUP 2.....................$ 30.64 23.20

GROUP 3.....................$ 30.54 23.20

GROUP 4.....................$ 24.23 23.20

See groups 1-b and 1-d under laborer classifications.

LABORER (GARDENERS,

HORTICULTURAL & LANDSCAPE

LABORERS - AREA A:)

(1) New Construction........$ 30.54 23.20

(2) Establishment Warranty

Period......................$ 24.23 23.20

LABORER (GUNITE - AREA A:)

GROUP 1.....................$ 30.75 22.31

GROUP 2.....................$ 30.25 22.31

GROUP 3.....................$ 29.66 22.31

GROUP 4.....................$ 29.54 22.31

LABORER (WRECKING - AREA A:)

GROUP 1.....................$ 30.79 23.20

GROUP 2.....................$ 30.64 23.20

FOOTNOTES:

Laborers working off or with or from bos'n chairs, swinging

scaffolds, belts shall receive $0.25 per hour above the

applicable wage rate. This shall not apply to workers

entitled to receive the wage rate set forth in Group 1-a

below.

---------------------------------------------------------

LABORER CLASSIFICATIONS

CONSTRUCTION SPECIALIST GROUP: Asphalt ironer and raker;

Chainsaw; Laser beam in connection with laborers' work;

Cast-in- place manhole form setter; Pressure pipelayer;

Davis trencher - 300 or similar type (and all small

trenchers); Blaster; Diamond driller; Multiple unit drill;

Hydraulic drill

GROUP 1: Asphalt spreader boxes (all types); Barko, Wacker

and similar type tampers; Buggymobile; Caulker, bander,

pipewrapper, conduit layer, plastic pipelayer; Certified

hazardous waste worker including Leade Abatement;

Compactors of all types; Concrete and magnesite mixer, 1/2

yd. and under; Concrete pan work; Concrete sander; Concrete

saw; Cribber and/or shoring; Cut granite curb setter;

Dri-pak-it machine; Faller, logloader and bucker; Form

raiser, slip forms; Green cutter; Headerboard, Hubsetter,

aligner, by any method; High pressure blow pipe (1-1/2"" or

over, 100 lbs. pressure/over); Hydro seeder and similar

type; Jackhammer operator; Jacking of pipe over 12 inches;

Jackson and similar type compactor; Kettle tender, pot and

worker applying asphalt, lay-kold, creosote, lime, caustic

and similar type materials (applying means applying,

dipping or handling of such materials); Lagging, sheeting,

whaling, bracing, trenchjacking, lagging hammer; Magnesite,

epoxyresin, fiberglass, mastic worker (wet or dry); No

joint pipe and stripping of same, including repair of

voids; Pavement breaker and spader, including tool grinder;

Perma curb; Pipelayer (including grade checking in

connection with pipelaying); Precast-manhole setter;

Pressure pipe tester; Post hole digger, air, gas and

electric; Power broom sweeper; Power tampers of all types

(except as shown in Group 2); Ram set gun and stud gun;

Riprap stonepaver and rock-slinger, including placing of

sacked concrete and/or sand (wet or dry) and gabions and

similar type; Rotary scarifier or multiple head concrete

chipping scarifier; Roto and Ditch Witch; Rototiller;

Sandblaster, pot, gun, nozzle operators; Signalling and

rigging; Tank cleaner; Tree climber; Turbo blaster;

Vibrascreed, bull float in connection with laborers' work;

Vibrator; Hazardous waste worker (lead removal); Asbestos

and mold removal worker

GROUP 1-a: Joy drill model TWM-2A; Gardner-Denver model DH143

and similar type drills; Track driller; Jack leg driller;

Wagon driller; Mechanical drillers, all types regardless of

type or method of power; Mechanical pipe layers, all types

regardless of type or method of power; Blaster and powder;

All work of loading, placing and blasting of all powder and

explosives of whatever type regardless of method used for

such loading and placing; High scalers (including drilling

of same); Tree topper; Bit grinder

GROUP 1-b: Sewer cleaners shall receive $4.00 per day above

Group 1 wage rates. ""Sewer cleaner"" means any worker who

handles or comes in contact with raw sewage in small

diameter sewers. Those who work inside recently active,

large diameter sewers, and all recently active sewer

manholes shal receive $5.00 per day above Group 1 wage

rates.

GROUP 1-c: Burning and welding in connection with laborers'

work; Synthetic thermoplastics and similar type welding

GROUP 1-d: Maintenance and repair track and road beds. All

employees performing work covered herein shall receive $

.25 per hour above their regular rate for all work

performed on underground structures not specifically

covered herein. This paragraph shall not be construed to

apply to work below ground level in open cut. It shall

apply to cut and cover work of subway construction after

the temporary cover has been placed.

GROUP 1-e: Work on and/or in bell hole footings and shafts

thereof, and work on and in deep footings. (A deep footing

is a hole 15 feet or more in depth.) In the event the

depth of the footing is unknown at the commencement of

excavation, and the final depth exceeds 15 feet, the deep

footing wage rate would apply to all employees for each and

every day worked on or in the excavation of the footing

from the date of inception.

GROUP 1-f: Wire winding machine in connection with guniting

or shot crete

GROUP 2: Asphalt shoveler; Cement dumper and handling dry

cement or gypsum; Choke-setter and rigger (clearing work);

Concrete bucket dumper and chute; Concrete chipping and

grinding; Concrete laborer (wet or dry); Driller tender,

chuck tender, nipper; Guinea chaser (stake), grout crew;

High pressure nozzle, adductor; Hydraulic monitor (over 100

lbs. pressure); Loading and unloading, carrying and hauling

of all rods and materials for use in reinforcing concrete

construction; Pittsburgh chipper and similar type brush

shredders; Sloper; Single foot, hand-held, pneumatic

tamper; All pneumatic, air, gas and electric tools not

listed in Groups 1 through 1-f; Jacking of pipe - under 12

inches

GROUP 3: Construction laborers, including bridge and general

laborer; Dump, load spotter; Flag person; Fire watcher;

Fence erector; Guardrail erector; Gardener, horticultural

and landscape laborer; Jetting; Limber, brush loader and

piler; Pavement marker (button setter); Maintenance, repair

track and road beds; Streetcar and railroad construction

track laborer; Temporary air and water lines, Victaulic or

similar; Tool room attendant (jobsite only)

GROUP 4: Final clean-up work of debris, grounds and building

including but not limited to: street cleaner; cleaning and

washing windows; brick cleaner (jobsite only); material

cleaner (jobsite only). The classification ""material

cleaner"" is to be utilized under the following conditions:

A: at demolition site for the salvage of the material.

B: at the conclusion of a job where the material is to be

salvaged and stocked to be reused on another job.

C: for the cleaning of salvage material at the jobsite or

temporary jobsite yard.

The material cleaner classification should not be used in

the performance of ""form stripping, cleaning and oiling

and moving to the next point of erection"".

--------------------------------------------------------

GUNITE LABORER CLASSIFICATIONS

GROUP 1: Structural Nozzleman

GROUP 2: Nozzleman, Gunman, Potman, Groundman

GROUP 3: Reboundman

GROUP 4: Gunite laborer

----------------------------------------------------------

WRECKING WORK LABORER CLASSIFICATIONS

GROUP 1: Skilled wrecker (removing and salvaging of sash,

windows and materials)

GROUP 2: Semi-skilled wrecker (salvaging of other building

materials)

----------------------------------------------------------------

LABO0270-011 07/01/2017

MONTEREY, SAN BENITO, SANTA CRUZ, SANTA CLARA COUNTIES

Rates Fringes

LABORER (Plaster Tender).........$ 34.70 21.22

Work on a swing stage scaffold: $1.00 per hour additional.

----------------------------------------------------------------

LABO0294-001 07/01/2020

FRESNO, KINGS AND MADERA COUNTIES

Rates Fringes

LABORER (Brick)

Mason Tender-Brick..........$ 32.84 23.71

----------------------------------------------------------------

LABO0294-002 06/25/2018

FRESNO, KINGS, AND MADERA COUNTIES

Rates Fringes

LABORER (TRAFFIC CONTROL/LANE

CLOSURE)

Escort Driver, Flag Person..$ 29.54 23.65

Traffic Control Person I....$ 29.84 23.65

Traffic Control Person II...$ 27.34 23.65

TRAFFIC CONTROL PERSON I: Layout of traffic control, crash

cushions, construction area and roadside signage.

TRAFFIC CONTROL PERSON II: Installation and removal of

temporary/permanent signs, markers, delineators and crash

cushions.

----------------------------------------------------------------

LABO0294-005 06/25/2018

FRESNO, KINGS, AND MADERA COUNTIES

Rates Fringes

Tunnel and Shaft Laborers:

GROUP 1.....................$ 37.82 24.11

GROUP 2.....................$ 37.59 24.11

GROUP 3.....................$ 37.34 24.11

GROUP 4.....................$ 36.89 24.11

GROUP 5.....................$ 36.35 24.11

Shotcrete Specialist........$ 38.34 24.11

TUNNEL AND SHAFT CLASSIFICATIONS

GROUP 1: Diamond driller; Groundmen; Gunite and shotcrete

nozzlemen

GROUP 2: Rodmen; Shaft work & raise (below actual or

excavated ground level)

GROUP 3: Bit grinder; Blaster, driller, powdermen, heading;

Cherry pickermen - where car is lifted; Concrete finisher

in tunnel; Concrete screedman; Grout pumpman and potman;

Gunite & shotcrete gunman & potman; Headermen; High

pressure nozzleman; Miner - tunnel, including top and

bottom man on shaft and raise work; Nipper; Nozzleman on

slick line; Sandblaster - potman, Robotic Shotcrete Placer,

Segment Erector, Tunnel Muck Hauler, Steel Form raiser and

setter; Timberman, retimberman (wood or steel or substitute

materials therefore); Tugger (for tunnel laborer work);

Cable tender; Chuck tender; Powderman - primer house

GROUP 4: Vibrator operator, pavement breaker; Bull gang -

muckers, trackmen; Concrete crew - includes rodding and

spreading, Dumpmen (any method)

GROUP 5: Grout crew; Reboundman; Swamper/ Brakeman

----------------------------------------------------------------

LABO0294-008 06/25/2018

FRESNO, KINGS, AND MADERA COUNTIES

Rates Fringes

LABORER (CONSTRUCTION CRAFT

LABORERS - AREA B:)

Construction Specialist

Group.......................$ 30.49 23.20

GROUP 1.....................$ 29.79 23.20

GROUP 1-a...................$ 30.01 23.20

GROUP 1-c...................$ 29.84 23.20

GROUP 1-e...................$ 30.34 23.20

GROUP 1-f...................$ 30.37 23.20

GROUP 2.....................$ 29.64 23.20

GROUP 3.....................$ 29.54 23.20

GROUP 4.....................$ 23.23 23.20

See groups 1-b and 1-d under laborer classifications.

LABORER (GARDENERS,

HORTICULTURAL & LANDSCAPE

LABORERS - AREA B:)

(1) New Construction........$ 29.54 23.20

(2) Establishment Warranty

Period......................$ 23.23 23.20

LABORER (GUNITE - AREA B:)

GROUP 1.....................$ 29.75 22.31

GROUP 2.....................$ 29.25 22.31

GROUP 3.....................$ 28.66 22.31

GROUP 4.....................$ 28.54 22.31

LABORER (WRECKING - AREA B:)

GROUP 1.....................$ 29.79 23.20

GROUP 2.....................$ 29.64 23.20

FOOTNOTES:

Laborers working off or with or from bos'n chairs, swinging

scaffolds, belts shall receive $0.25 per hour above the

applicable wage rate. This shall not apply to workers

entitled to receive the wage rate set forth in Group 1-a

below.

---------------------------------------------------------

LABORER CLASSIFICATIONS

CONSTRUCTION SPECIALIST GROUP: Asphalt ironer and raker;

Chainsaw; Laser beam in connection with laborers' work;

Cast-in- place manhole form setter; Pressure pipelayer;

Davis trencher - 300 or similar type (and all small

trenchers); Blaster; Diamond driller; Multiple unit drill;

Hydraulic drill

GROUP 1: Asphalt spreader boxes (all types); Barko, Wacker

and similar type tampers; Buggymobile; Caulker, bander,

pipewrapper, conduit layer, plastic pipelayer; Certified

hazardous waste worker including Leade Abatement;

Compactors of all types; Concrete and magnesite mixer, 1/2

yd. and under; Concrete pan work; Concrete sander; Concrete

saw; Cribber and/or shoring; Cut granite curb setter;

Dri-pak-it machine; Faller, logloader and bucker; Form

raiser, slip forms; Green cutter; Headerboard, Hubsetter,

aligner, by any method; High pressure blow pipe (1-1/2"" or

over, 100 lbs. pressure/over); Hydro seeder and similar

type; Jackhammer operator; Jacking of pipe over 12 inches;

Jackson and similar type compactor; Kettle tender, pot and

worker applying asphalt, lay-kold, creosote, lime, caustic

and similar type materials (applying means applying,

dipping or handling of such materials); Lagging, sheeting,

whaling, bracing, trenchjacking, lagging hammer; Magnesite,

epoxyresin, fiberglass, mastic worker (wet or dry); No

joint pipe and stripping of same, including repair of

voids; Pavement breaker and spader, including tool grinder;

Perma curb; Pipelayer (including grade checking in

connection with pipelaying); Precast-manhole setter;

Pressure pipe tester; Post hole digger, air, gas and

electric; Power broom sweeper; Power tampers of all types

(except as shown in Group 2); Ram set gun and stud gun;

Riprap stonepaver and rock-slinger, including placing of

sacked concrete and/or sand (wet or dry) and gabions and

similar type; Rotary scarifier or multiple head concrete

chipping scarifier; Roto and Ditch Witch; Rototiller;

Sandblaster, pot, gun, nozzle operators; Signalling and

rigging; Tank cleaner; Tree climber; Turbo blaster;

Vibrascreed, bull float in connection with laborers' work;

Vibrator; Hazardous waste worker (lead removal); Asbestos

and mold removal worker

GROUP 1-a: Joy drill model TWM-2A; Gardner-Denver model DH143

and similar type drills; Track driller; Jack leg driller;

Wagon driller; Mechanical drillers, all types regardless of

type or method of power; Mechanical pipe layers, all types

regardless of type or method of power; Blaster and powder;

All work of loading, placing and blasting of all powder and

explosives of whatever type regardless of method used for

such loading and placing; High scalers (including drilling

of same); Tree topper; Bit grinder

GROUP 1-b: Sewer cleaners shall receive $4.00 per day above

Group 1 wage rates. ""Sewer cleaner"" means any worker who

handles or comes in contact with raw sewage in small

diameter sewers. Those who work inside recently active,

large diameter sewers, and all recently active sewer

manholes shal receive $5.00 per day above Group 1 wage

rates.

GROUP 1-c: Burning and welding in connection with laborers'

work; Synthetic thermoplastics and similar type welding

GROUP 1-d: Maintenance and repair track and road beds. All

employees performing work covered herein shall receive $

.25 per hour above their regular rate for all work

performed on underground structures not specifically

covered herein. This paragraph shall not be construed to

apply to work below ground level in open cut. It shall

apply to cut and cover work of subway construction after

the temporary cover has been placed.

GROUP 1-e: Work on and/or in bell hole footings and shafts

thereof, and work on and in deep footings. (A deep footing

is a hole 15 feet or more in depth.) In the event the

depth of the footing is unknown at the commencement of

excavation, and the final depth exceeds 15 feet, the deep

footing wage rate would apply to all employees for each and

every day worked on or in the excavation of the footing

from the date of inception.

GROUP 1-f: Wire winding machine in connection with guniting

or shot crete

GROUP 2: Asphalt shoveler; Cement dumper and handling dry

cement or gypsum; Choke-setter and rigger (clearing work);

Concrete bucket dumper and chute; Concrete chipping and

grinding; Concrete laborer (wet or dry); Driller tender,

chuck tender, nipper; Guinea chaser (stake), grout crew;

High pressure nozzle, adductor; Hydraulic monitor (over 100

lbs. pressure); Loading and unloading, carrying and hauling

of all rods and materials for use in reinforcing concrete

construction; Pittsburgh chipper and similar type brush

shredders; Sloper; Single foot, hand-held, pneumatic

tamper; All pneumatic, air, gas and electric tools not

listed in Groups 1 through 1-f; Jacking of pipe - under 12

inches

GROUP 3: Construction laborers, including bridge and general

laborer; Dump, load spotter; Flag person; Fire watcher;

Fence erector; Guardrail erector; Gardener, horticultural

and landscape laborer; Jetting; Limber, brush loader and

piler; Pavement marker (button setter); Maintenance, repair

track and road beds; Streetcar and railroad construction

track laborer; Temporary air and water lines, Victaulic or

similar; Tool room attendant (jobsite only)

GROUP 4: Final clean-up work of debris, grounds and building

including but not limited to: street cleaner; cleaning and

washing windows; brick cleaner (jobsite only); material

cleaner (jobsite only). The classification ""material

cleaner"" is to be utilized under the following conditions:

A: at demolition site for the salvage of the material.

B: at the conclusion of a job where the material is to be

salvaged and stocked to be reused on another job.

C: for the cleaning of salvage material at the jobsite or

temporary jobsite yard.

The material cleaner classification should not be used in

the performance of ""form stripping, cleaning and oiling

and moving to the next point of erection"".

--------------------------------------------------------

GUNITE LABORER CLASSIFICATIONS

GROUP 1: Structural Nozzleman

GROUP 2: Nozzleman, Gunman, Potman, Groundman

GROUP 3: Reboundman

GROUP 4: Gunite laborer

----------------------------------------------------------

WRECKING WORK LABORER CLASSIFICATIONS

GROUP 1: Skilled wrecker (removing and salvaging of sash,

windows and materials)

GROUP 2: Semi-skilled wrecker (salvaging of other building

materials)

----------------------------------------------------------------

LABO0294-010 07/01/2018

CALAVERAS, FRESNO, KINGS, MADERA, MARIPOSA, MERCED, SAN

JOAQUIN, STANISLAUS & TUOLUMNE

Rates Fringes

Plasterer tender.................$ 32.02 23.00

Work on a swing stage scaffold: $1.00 per hour additional.

----------------------------------------------------------------

LABO0294-011 07/01/2017

FRESNO, KINGS, AND MADERA COUNTIES

Rates Fringes

LABORER (Plaster Tender).........$ 31.02 22.52

Work on a swing stage scaffold: $1.00 per hour additional.

----------------------------------------------------------------

LABO0304-002 06/25/2018

ALAMEDA COUNTY

Rates Fringes

LABORER (TRAFFIC CONTROL/LANE

CLOSURE)

Escort Driver, Flag Person..$ 30.54 23.65

Traffic Control Person I....$ 30.84 23.65

Traffic Control Person II...$ 28.34 23.65

TRAFFIC CONTROL PERSON I: Layout of traffic control, crash

cushions, construction area and roadside signage.

TRAFFIC CONTROL PERSON II: Installation and removal of

temporary/permanent signs, markers, delineators and crash

cushions.

----------------------------------------------------------------

LABO0304-003 06/26/2017

ALAMEDA COUNTY

Rates Fringes

Tunnel and Shaft Laborers:

GROUP 1.....................$ 36.60 24.83

GROUP 2.....................$ 36.37 24.83

GROUP 3.....................$ 36.12 24.83

GROUP 4.....................$ 35.67 24.83

GROUP 5.....................$ 35.13 24.83

Shotcrete Specialist........$ 37.12 24.83

TUNNEL AND SHAFT CLASSIFICATIONS

GROUP 1: Diamond driller; Groundmen; Gunite and shotcrete

nozzlemen

GROUP 2: Rodmen; Shaft work & raise (below actual or

excavated ground level)

GROUP 3: Bit grinder; Blaster, driller, powdermen, heading;

Cherry pickermen - where car is lifted; Concrete finisher

in tunnel; Concrete screedman; Grout pumpman and potman;

Gunite & shotcrete gunman & potman; Headermen; High

pressure nozzleman; Miner - tunnel, including top and

bottom man on shaft and raise work; Nipper; Nozzleman on

slick line; Sandblaster - potman, Robotic Shotcrete Placer,

Segment Erector, Tunnel Muck Hauler, Steel Form raiser and

setter; Timberman, retimberman (wood or steel or substitute

materials therefore); Tugger (for tunnel laborer work);

Cable tender; Chuck tender; Powderman - primer house

GROUP 4: Vibrator operator, pavement breaker; Bull gang -

muckers, trackmen; Concrete crew - includes rodding and

spreading, Dumpmen (any method)

GROUP 5: Grout crew; Reboundman; Swamper/ Brakeman

----------------------------------------------------------------

LABO0304-004 06/25/2018

ALAMEDA COUNTY

Rates Fringes

LABORER (CONSTRUCTION CRAFT

LABORERS - AREA A:)

Construction Specialist

Group.......................$ 31.49 23.20

GROUP 1.....................$ 30.79 23.20

GROUP 1-a...................$ 31.01 23.20

GROUP 1-c...................$ 30.84 23.20

GROUP 1-e...................$ 31.34 23.20

GROUP 1-f...................$ 30.37 23.20

GROUP 2.....................$ 30.64 23.20

GROUP 3.....................$ 30.54 23.20

GROUP 4.....................$ 24.23 23.20

See groups 1-b and 1-d under laborer classifications.

LABORER (GARDENERS,

HORTICULTURAL & LANDSCAPE

LABORERS - AREA A:)

(1) New Construction........$ 30.54 23.20

(2) Establishment Warranty

Period......................$ 24.23 23.20

LABORER (GUNITE - AREA A:)

GROUP 1.....................$ 30.75 22.31

GROUP 2.....................$ 30.25 22.31

GROUP 3.....................$ 29.66 22.31

GROUP 4.....................$ 29.54 22.31

LABORER (WRECKING - AREA A:)

GROUP 1.....................$ 30.79 23.20

GROUP 2.....................$ 30.64 23.20

FOOTNOTES:

Laborers working off or with or from bos'n chairs, swinging

scaffolds, belts shall receive $0.25 per hour above the

applicable wage rate. This shall not apply to workers

entitled to receive the wage rate set forth in Group 1-a

below.

---------------------------------------------------------

LABORER CLASSIFICATIONS

CONSTRUCTION SPECIALIST GROUP: Asphalt ironer and raker;

Chainsaw; Laser beam in connection with laborers' work;

Cast-in- place manhole form setter; Pressure pipelayer;

Davis trencher - 300 or similar type (and all small

trenchers); Blaster; Diamond driller; Multiple unit drill;

Hydraulic drill

GROUP 1: Asphalt spreader boxes (all types); Barko, Wacker

and similar type tampers; Buggymobile; Caulker, bander,

pipewrapper, conduit layer, plastic pipelayer; Certified

hazardous waste worker including Leade Abatement;

Compactors of all types; Concrete and magnesite mixer, 1/2

yd. and under; Concrete pan work; Concrete sander; Concrete

saw; Cribber and/or shoring; Cut granite curb setter;

Dri-pak-it machine; Faller, logloader and bucker; Form

raiser, slip forms; Green cutter; Headerboard, Hubsetter,

aligner, by any method; High pressure blow pipe (1-1/2"" or

over, 100 lbs. pressure/over); Hydro seeder and similar

type; Jackhammer operator; Jacking of pipe over 12 inches;

Jackson and similar type compactor; Kettle tender, pot and

worker applying asphalt, lay-kold, creosote, lime, caustic

and similar type materials (applying means applying,

dipping or handling of such materials); Lagging, sheeting,

whaling, bracing, trenchjacking, lagging hammer; Magnesite,

epoxyresin, fiberglass, mastic worker (wet or dry); No

joint pipe and stripping of same, including repair of

voids; Pavement breaker and spader, including tool grinder;

Perma curb; Pipelayer (including grade checking in

connection with pipelaying); Precast-manhole setter;

Pressure pipe tester; Post hole digger, air, gas and

electric; Power broom sweeper; Power tampers of all types

(except as shown in Group 2); Ram set gun and stud gun;

Riprap stonepaver and rock-slinger, including placing of

sacked concrete and/or sand (wet or dry) and gabions and

similar type; Rotary scarifier or multiple head concrete

chipping scarifier; Roto and Ditch Witch; Rototiller;

Sandblaster, pot, gun, nozzle operators; Signalling and

rigging; Tank cleaner; Tree climber; Turbo blaster;

Vibrascreed, bull float in connection with laborers' work;

Vibrator; Hazardous waste worker (lead removal); Asbestos

and mold removal worker

GROUP 1-a: Joy drill model TWM-2A; Gardner-Denver model DH143

and similar type drills; Track driller; Jack leg driller;

Wagon driller; Mechanical drillers, all types regardless of

type or method of power; Mechanical pipe layers, all types

regardless of type or method of power; Blaster and powder;

All work of loading, placing and blasting of all powder and

explosives of whatever type regardless of method used for

such loading and placing; High scalers (including drilling

of same); Tree topper; Bit grinder

GROUP 1-b: Sewer cleaners shall receive $4.00 per day above

Group 1 wage rates. ""Sewer cleaner"" means any worker who

handles or comes in contact with raw sewage in small

diameter sewers. Those who work inside recently active,

large diameter sewers, and all recently active sewer

manholes shal receive $5.00 per day above Group 1 wage

rates.

GROUP 1-c: Burning and welding in connection with laborers'

work; Synthetic thermoplastics and similar type welding

GROUP 1-d: Maintenance and repair track and road beds. All

employees performing work covered herein shall receive $

.25 per hour above their regular rate for all work

performed on underground structures not specifically

covered herein. This paragraph shall not be construed to

apply to work below ground level in open cut. It shall

apply to cut and cover work of subway construction after

the temporary cover has been placed.

GROUP 1-e: Work on and/or in bell hole footings and shafts

thereof, and work on and in deep footings. (A deep footing

is a hole 15 feet or more in depth.) In the event the

depth of the footing is unknown at the commencement of

excavation, and the final depth exceeds 15 feet, the deep

footing wage rate would apply to all employees for each and

every day worked on or in the excavation of the footing

from the date of inception.

GROUP 1-f: Wire winding machine in connection with guniting

or shot crete

GROUP 2: Asphalt shoveler; Cement dumper and handling dry

cement or gypsum; Choke-setter and rigger (clearing work);

Concrete bucket dumper and chute; Concrete chipping and

grinding; Concrete laborer (wet or dry); Driller tender,

chuck tender, nipper; Guinea chaser (stake), grout crew;

High pressure nozzle, adductor; Hydraulic monitor (over 100

lbs. pressure); Loading and unloading, carrying and hauling

of all rods and materials for use in reinforcing concrete

construction; Pittsburgh chipper and similar type brush

shredders; Sloper; Single foot, hand-held, pneumatic

tamper; All pneumatic, air, gas and electric tools not

listed in Groups 1 through 1-f; Jacking of pipe - under 12

inches

GROUP 3: Construction laborers, including bridge and general

laborer; Dump, load spotter; Flag person; Fire watcher;

Fence erector; Guardrail erector; Gardener, horticultural

and landscape laborer; Jetting; Limber, brush loader and

piler; Pavement marker (button setter); Maintenance, repair

track and road beds; Streetcar and railroad construction

track laborer; Temporary air and water lines, Victaulic or

similar; Tool room attendant (jobsite only)

GROUP 4: Final clean-up work of debris, grounds and building

including but not limited to: street cleaner; cleaning and

washing windows; brick cleaner (jobsite only); material

cleaner (jobsite only). The classification ""material

cleaner"" is to be utilized under the following conditions:

A: at demolition site for the salvage of the material.

B: at the conclusion of a job where the material is to be

salvaged and stocked to be reused on another job.

C: for the cleaning of salvage material at the jobsite or

temporary jobsite yard.

The material cleaner classification should not be used in

the performance of ""form stripping, cleaning and oiling

and moving to the next point of erection"".

--------------------------------------------------------

GUNITE LABORER CLASSIFICATIONS

GROUP 1: Structural Nozzleman

GROUP 2: Nozzleman, Gunman, Potman, Groundman

GROUP 3: Reboundman

GROUP 4: Gunite laborer

----------------------------------------------------------

WRECKING WORK LABORER CLASSIFICATIONS

GROUP 1: Skilled wrecker (removing and salvaging of sash,

windows and materials)

GROUP 2: Semi-skilled wrecker (salvaging of other building

materials)

----------------------------------------------------------------

LABO0304-005 05/01/2018

ALAMEDA COUNTY

Rates Fringes

Brick Tender.....................$ 35.37 20.70

FOOTNOTES: Work on jobs where heat-protective clothing is

required: $2.00 per hour additional. Work at grinders: $.25

per hour additional. Manhole work: $2.00 per day additional.

----------------------------------------------------------------

LABO0304-008 07/01/2017

ALAMEDA AND CONTRA COSTA COUNTIES:

Rates Fringes

Plasterer tender.................$ 34.70 23.11

Work on a swing stage scaffold: $1.00 per hour additional.

----------------------------------------------------------------

LABO0324-002 06/25/2018

CONTRA COSTA COUNTY

Rates Fringes

LABORER (TRAFFIC CONTROL/LANE

CLOSURE)

Escort Driver, Flag Person..$ 30.54 23.65

Traffic Control Person I....$ 30.84 23.65

Traffic Control Person II...$ 28.34 23.65

TRAFFIC CONTROL PERSON I: Layout of traffic control, crash

cushions, construction area and roadside signage.

TRAFFIC CONTROL PERSON II: Installation and removal of

temporary/permanent signs, markers, delineators and crash

cushions.

----------------------------------------------------------------

LABO0324-006 06/25/2018

CONTRA COSTA COUNTY

Rates Fringes

Tunnel and Shaft Laborers:

GROUP 1.....................$ 37.82 24.11

GROUP 2.....................$ 37.59 24.11

GROUP 3.....................$ 37.34 24.11

GROUP 4.....................$ 36.89 24.11

GROUP 5.....................$ 36.35 24.11

Shotcrete Specialist........$ 38.34 24.11

TUNNEL AND SHAFT CLASSIFICATIONS

GROUP 1: Diamond driller; Groundmen; Gunite and shotcrete

nozzlemen

GROUP 2: Rodmen; Shaft work & raise (below actual or

excavated ground level)

GROUP 3: Bit grinder; Blaster, driller, powdermen, heading;

Cherry pickermen - where car is lifted; Concrete finisher

in tunnel; Concrete screedman; Grout pumpman and potman;

Gunite & shotcrete gunman & potman; Headermen; High

pressure nozzleman; Miner - tunnel, including top and

bottom man on shaft and raise work; Nipper; Nozzleman on

slick line; Sandblaster - potman, Robotic Shotcrete Placer,

Segment Erector, Tunnel Muck Hauler, Steel Form raiser and

setter; Timberman, retimberman (wood or steel or substitute

materials therefore); Tugger (for tunnel laborer work);

Cable tender; Chuck tender; Powderman - primer house

GROUP 4: Vibrator operator, pavement breaker; Bull gang -

muckers, trackmen; Concrete crew - includes rodding and

spreading, Dumpmen (any method)

GROUP 5: Grout crew; Reboundman; Swamper/ Brakeman

----------------------------------------------------------------

LABO0324-012 06/25/2018

CONTRA COSTA COUNTY

Rates Fringes

LABORER (CONSTRUCTION CRAFT

LABORERS - AREA A:)

Construction Specialist

Group.......................$ 31.49 23.20

GROUP 1.....................$ 30.79 23.20

GROUP 1-a...................$ 31.01 23.20

GROUP 1-c...................$ 30.84 23.20

GROUP 1-e...................$ 31.34 23.20

GROUP 1-f...................$ 30.37 23.20

GROUP 1-g...................$ 30.99 23.20

GROUP 2.....................$ 30.64 23.20

GROUP 3.....................$ 30.54 23.20

GROUP 4.....................$ 24.23 23.20

See groups 1-b and 1-d under laborer classifications.

LABORER (GARDENERS,

HORTICULURAL & LANDSCAPE

LABORERS - AREA A:)

(1) New Construction........$ 30.54 23.20

(2) Establishment Warranty

Period......................$ 24.23 23.20

LABORER (GUNITE - AREA A:)

GROUP 1.....................$ 30.75 22.31

GROUP 2.....................$ 30.25 22.31

GROUP 3.....................$ 29.66 22.31

GROUP 4.....................$ 29.54 22.31

LABORER (WRECKING - AREA A:)

GROUP 1.....................$ 30.79 23.20

GROUP 2.....................$ 30.64 23.20

FOOTNOTES:

Laborers working off or with or from bos'n chairs, swinging

scaffolds, belts shall receive $0.25 per hour above the

applicable wage rate. This shall not apply to workers

entitled to receive the wage rate set forth in Group 1-a

below.

---------------------------------------------------------

LABORER CLASSIFICATIONS

CONSTRUCTION SPECIALIST GROUP: Asphalt ironer and raker;

Chainsaw; Laser beam in connection with laborers' work;

Cast-in- place manhole form setter; Pressure pipelayer;

Davis trencher - 300 or similar type (and all small

trenchers); Blaster; Diamond driller; Multiple unit drill;

Hydraulic drill

GROUP 1: Asphalt spreader boxes (all types); Barko, Wacker

and similar type tampers; Buggymobile; Caulker, bander,

pipewrapper, conduit layer, plastic pipelayer; Certified

hazardous waste worker including Leade Abatement;

Compactors of all types; Concrete and magnesite mixer, 1/2

yd. and under; Concrete pan work; Concrete sander; Concrete

saw; Cribber and/or shoring; Cut granite curb setter;

Dri-pak-it machine; Faller, logloader and bucker; Form

raiser, slip forms; Green cutter; Headerboard, Hubsetter,

aligner, by any method; High pressure blow pipe (1-1/2"" or

over, 100 lbs. pressure/over); Hydro seeder and similar

type; Jackhammer operator; Jacking of pipe over 12 inches;

Jackson and similar type compactor; Kettle tender, pot and

worker applying asphalt, lay-kold, creosote, lime, caustic

and similar type materials (applying means applying,

dipping or handling of such materials); Lagging, sheeting,

whaling, bracing, trenchjacking, lagging hammer; Magnesite,

epoxyresin, fiberglass, mastic worker (wet or dry); No

joint pipe and stripping of same, including repair of

voids; Pavement breaker and spader, including tool grinder;

Perma curb; Pipelayer (including grade checking in

connection with pipelaying); Precast-manhole setter;

Pressure pipe tester; Post hole digger, air, gas and

electric; Power broom sweeper; Power tampers of all types

(except as shown in Group 2); Ram set gun and stud gun;

Riprap stonepaver and rock-slinger, including placing of

sacked concrete and/or sand (wet or dry) and gabions and

similar type; Rotary scarifier or multiple head concrete

chipping scarifier; Roto and Ditch Witch; Rototiller;

Sandblaster, pot, gun, nozzle operators; Signalling and

rigging; Tank cleaner; Tree climber; Turbo blaster;

Vibrascreed, bull float in connection with laborers' work;

Vibrator; Hazardous waste worker (lead removal); Asbestos

and mold removal worker

GROUP 1-a: Joy drill model TWM-2A; Gardner-Denver model DH143

and similar type drills; Track driller; Jack leg driller;

Wagon driller; Mechanical drillers, all types regardless of

type or method of power; Mechanical pipe layers, all types

regardless of type or method of power; Blaster and powder;

All work of loading, placing and blasting of all powder and

explosives of whatever type regardless of method used for

such loading and placing; High scalers (including drilling

of same); Tree topper; Bit grinder

GROUP 1-b: Sewer cleaners shall receive $4.00 per day above

Group 1 wage rates. ""Sewer cleaner"" means any worker who

handles or comes in contact with raw sewage in small

diameter sewers. Those who work inside recently active,

large diameter sewers, and all recently active sewer

manholes shal receive $5.00 per day above Group 1 wage

rates.

GROUP 1-c: Burning and welding in connection with laborers'

work; Synthetic thermoplastics and similar type welding

GROUP 1-d: Maintenance and repair track and road beds. All

employees performing work covered herein shall receive $

.25 per hour above their regular rate for all work

performed on underground structures not specifically

covered herein. This paragraph shall not be construed to

apply to work below ground level in open cut. It shall

apply to cut and cover work of subway construction after

the temporary cover has been placed.

GROUP 1-e: Work on and/or in bell hole footings and shafts

thereof, and work on and in deep footings. (A deep footing

is a hole 15 feet or more in depth.) In the event the

depth of the footing is unknown at the commencement of

excavation, and the final depth exceeds 15 feet, the deep

footing wage rate would apply to all employees for each and

every day worked on or in the excavation of the footing

from the date of inception.

GROUP 1-f: Wire winding machine in connection with guniting

or shot crete

GROUP 1-g, CONTRA COSTA COUNTY: Pipelayer (including grade

checking in connection with pipelaying); Caulker; Bander;

Pipewrapper; Conduit layer; Plastic pipe layer; Pressure

pipe tester; No joint pipe and stripping of same, including

repair of voids; Precast manhole setters, cast in place

manhole form setters

GROUP 2: Asphalt shoveler; Cement dumper and handling dry

cement or gypsum; Choke-setter and rigger (clearing work);

Concrete bucket dumper and chute; Concrete chipping and

grinding; Concrete laborer (wet or dry); Driller tender,

chuck tender, nipper; Guinea chaser (stake), grout crew;

High pressure nozzle, adductor; Hydraulic monitor (over 100

lbs. pressure); Loading and unloading, carrying and hauling

of all rods and materials for use in reinforcing concrete

construction; Pittsburgh chipper and similar type brush

shredders; Sloper; Single foot, hand-held, pneumatic

tamper; All pneumatic, air, gas and electric tools not

listed in Groups 1 through 1-f; Jacking of pipe - under 12

inches

GROUP 3: Construction laborers, including bridge and general

laborer; Dump, load spotter; Flag person; Fire watcher;

Fence erector; Guardrail erector; Gardener, horticultural

and landscape laborer; Jetting; Limber, brush loader and

piler; Pavement marker (button setter); Maintenance, repair

track and road beds; Streetcar and railroad construction

track laborer; Temporary air and water lines, Victaulic or

similar; Tool room attendant (jobsite only)

GROUP 4: Final clean-up work of debris, grounds and building

including but not limited to: street cleaner; cleaning and

washing windows; brick cleaner (jobsite only); material

cleaner (jobsite only). The classification ""material

cleaner"" is to be utilized under the following conditions:

A: at demolition site for the salvage of the material.

B: at the conclusion of a job where the material is to be

salvaged and stocked to be reused on another job.

C: for the cleaning of salvage material at the jobsite or

temporary jobsite yard.

The material cleaner classification should not be used in

the performance of ""form stripping, cleaning and oiling

and moving to the next point of erection"".

--------------------------------------------------------

GUNITE LABORER CLASSIFICATIONS

GROUP 1: Structural Nozzleman

GROUP 2: Nozzleman, Gunman, Potman, Groundman

GROUP 3: Reboundman

GROUP 4: Gunite laborer

----------------------------------------------------------

WRECKING WORK LABORER CLASSIFICATIONS

GROUP 1: Skilled wrecker (removing and salvaging of sash,

windows and materials)

GROUP 2: Semi-skilled wrecker (salvaging of other building

materials)

GROUP 1-g, CONTRA COSTA COUNTY: Pipelayer (including grade

checking in connection with pipelaying); Caulker; Bander;

Pipewrapper; Conduit layer; Plastic pipe layer; Pressure

pipe tester; No joint pipe and stripping of same, including

repair of voids; Precast manhole setters, cast in place

manhole form setters

----------------------------------------------------------------

LABO0324-014 05/01/2018

CONTRA COSTA COUNTY:

Rates Fringes

Brick Tender.....................$ 35.37 20.70

FOOTNOTES: Work on jobs where heat-protective clothing is

required: $2.00 per hour additional. Work at grinders: $.25

per hour additional. Manhole work: $2.00 per day additional.

----------------------------------------------------------------

LABO0324-018 07/01/2018

ALAMEDA AND CONTRA COSTA COUNTIES:

Rates Fringes

Plasterer tender.................$ 37.14 22.32

Work on a swing stage scaffold: $1.00 per hour additional.

----------------------------------------------------------------

LABO1130-002 06/25/2018

MARIPOSA, MERCED, STANISLAUS, AND TUOLUMNE COUNTIES

Rates Fringes

LABORER (TRAFFIC CONTROL/LANE

CLOSURE)

Escort Driver, Flag Person..$ 29.54 23.65

Traffic Control Person I....$ 29.84 23.65

Traffic Control Person II...$ 27.34 23.65

TRAFFIC CONTROL PERSON I: Layout of traffic control, crash

cushions, construction area and roadside signage.

TRAFFIC CONTROL PERSON II: Installation and removal of

temporary/permanent signs, markers, delineators and crash

cushions.

----------------------------------------------------------------

LABO1130-003 06/26/2017

MARIPOSA, MERCED, STANISLAUS, AND TUOLUMNE COUNTIES

Rates Fringes

Tunnel and Shaft Laborers:

GROUP 1.....................$ 36.60 24.83

GROUP 2.....................$ 36.37 24.83

GROUP 3.....................$ 36.12 24.83

GROUP 4.....................$ 35.67 24.83

GROUP 5.....................$ 35.13 24.83

Shotcrete Specialist........$ 37.12 24.83

TUNNEL AND SHAFT CLASSIFICATIONS

GROUP 1: Diamond driller; Groundmen; Gunite and shotcrete

nozzlemen

GROUP 2: Rodmen; Shaft work & raise (below actual or

excavated ground level)

GROUP 3: Bit grinder; Blaster, driller, powdermen, heading;

Cherry pickermen - where car is lifted; Concrete finisher

in tunnel; Concrete screedman; Grout pumpman and potman;

Gunite & shotcrete gunman & potman; Headermen; High

pressure nozzleman; Miner - tunnel, including top and

bottom man on shaft and raise work; Nipper; Nozzleman on

slick line; Sandblaster - potman, Robotic Shotcrete Placer,

Segment Erector, Tunnel Muck Hauler, Steel Form raiser and

setter; Timberman, retimberman (wood or steel or substitute

materials therefore); Tugger (for tunnel laborer work);

Cable tender; Chuck tender; Powderman - primer house

GROUP 4: Vibrator operator, pavement breaker; Bull gang -

muckers, trackmen; Concrete crew - includes rodding and

spreading, Dumpmen (any method)

GROUP 5: Grout crew; Reboundman; Swamper/ Brakeman

----------------------------------------------------------------

LABO1130-005 07/01/2018

MARIPOSA, MERCED, STANISLAUS AND TUOLUMNE COUNTIES

Rates Fringes

LABORER

Mason Tender-Brick..........$ 31.20 22.20

----------------------------------------------------------------

LABO1130-007 06/25/2018

MARIPOSA, MERCED, STANISLAUS, AND TUOLUMNE , COUNTIES

Rates Fringes

LABORER (CONSTRUCTION CRAFT

LABORERS - AREA B:)

Construction Specialist

Group.......................$ 30.49 23.20

GROUP 1.....................$ 29.79 23.20

GROUP 1-a...................$ 30.01 23.20

GROUP 1-c...................$ 29.84 23.20

GROUP 1-e...................$ 30.34 23.20

GROUP 1-f...................$ 29.37 23.20

GROUP 2.....................$ 29.64 23.20

GROUP 3.....................$ 29.54 23.20

GROUP 4.....................$ 23.23 23.20

See groups 1-b and 1-d under laborer classifications.

LABORER (GARDENERS,

HORTICULTURAL & LANDSCAPE

LABORERS - AREA B:)

(1) New Construction........$ 29.54 23.20

(2) Establishment Warranty

Period......................$ 23.23 23.20

LABORER (GUNITE - AREA B:)

GROUP 1.....................$ 29.75 22.31

GROUP 2.....................$ 29.25 22.31

GROUP 3.....................$ 28.66 22.31

GROUP 4.....................$ 28.54 22.31

LABORER (WRECKING - AREA B:)

GROUP 1.....................$ 29.79 23.20

GROUP 2.....................$ 29.64 23.20

FOOTNOTES:

Laborers working off or with or from bos'n chairs, swinging

scaffolds, belts shall receive $0.25 per hour above the

applicable wage rate. This shall not apply to workers

entitled to receive the wage rate set forth in Group 1-a

below.

---------------------------------------------------------

LABORER CLASSIFICATIONS

CONSTRUCTION SPECIALIST GROUP: Asphalt ironer and raker;

Chainsaw; Laser beam in connection with laborers' work;

Cast-in- place manhole form setter; Pressure pipelayer;

Davis trencher - 300 or similar type (and all small

trenchers); Blaster; Diamond driller; Multiple unit drill;

Hydraulic drill

GROUP 1: Asphalt spreader boxes (all types); Barko, Wacker

and similar type tampers; Buggymobile; Caulker, bander,

pipewrapper, conduit layer, plastic pipelayer; Certified

hazardous waste worker including Leade Abatement;

Compactors of all types; Concrete and magnesite mixer, 1/2

yd. and under; Concrete pan work; Concrete sander; Concrete

saw; Cribber and/or shoring; Cut granite curb setter;

Dri-pak-it machine; Faller, logloader and bucker; Form

raiser, slip forms; Green cutter; Headerboard, Hubsetter,

aligner, by any method; High pressure blow pipe (1-1/2"" or

over, 100 lbs. pressure/over); Hydro seeder and similar

type; Jackhammer operator; Jacking of pipe over 12 inches;

Jackson and similar type compactor; Kettle tender, pot and

worker applying asphalt, lay-kold, creosote, lime, caustic

and similar type materials (applying means applying,

dipping or handling of such materials); Lagging, sheeting,

whaling, bracing, trenchjacking, lagging hammer; Magnesite,

epoxyresin, fiberglass, mastic worker (wet or dry); No

joint pipe and stripping of same, including repair of

voids; Pavement breaker and spader, including tool grinder;

Perma curb; Pipelayer (including grade checking in

connection with pipelaying); Precast-manhole setter;

Pressure pipe tester; Post hole digger, air, gas and

electric; Power broom sweeper; Power tampers of all types

(except as shown in Group 2); Ram set gun and stud gun;

Riprap stonepaver and rock-slinger, including placing of

sacked concrete and/or sand (wet or dry) and gabions and

similar type; Rotary scarifier or multiple head concrete

chipping scarifier; Roto and Ditch Witch; Rototiller;

Sandblaster, pot, gun, nozzle operators; Signalling and

rigging; Tank cleaner; Tree climber; Turbo blaster;

Vibrascreed, bull float in connection with laborers' work;

Vibrator; Hazardous waste worker (lead removal); Asbestos

and mold removal worker

GROUP 1-a: Joy drill model TWM-2A; Gardner-Denver model DH143

and similar type drills; Track driller; Jack leg driller;

Wagon driller; Mechanical drillers, all types regardless of

type or method of power; Mechanical pipe layers, all types

regardless of type or method of power; Blaster and powder;

All work of loading, placing and blasting of all powder and

explosives of whatever type regardless of method used for

such loading and placing; High scalers (including drilling

of same); Tree topper; Bit grinder

GROUP 1-b: Sewer cleaners shall receive $4.00 per day above

Group 1 wage rates. ""Sewer cleaner"" means any worker who

handles or comes in contact with raw sewage in small

diameter sewers. Those who work inside recently active,

large diameter sewers, and all recently active sewer

manholes shal receive $5.00 per day above Group 1 wage

rates.

GROUP 1-c: Burning and welding in connection with laborers'

work; Synthetic thermoplastics and similar type welding

GROUP 1-d: Maintenance and repair track and road beds. All

employees performing work covered herein shall receive $

.25 per hour above their regular rate for all work

performed on underground structures not specifically

covered herein. This paragraph shall not be construed to

apply to work below ground level in open cut. It shall

apply to cut and cover work of subway construction after

the temporary cover has been placed.

GROUP 1-e: Work on and/or in bell hole footings and shafts

thereof, and work on and in deep footings. (A deep footing

is a hole 15 feet or more in depth.) In the event the

depth of the footing is unknown at the commencement of

excavation, and the final depth exceeds 15 feet, the deep

footing wage rate would apply to all employees for each and

every day worked on or in the excavation of the footing

from the date of inception.

GROUP 1-f: Wire winding machine in connection with guniting

or shot crete

GROUP 2: Asphalt shoveler; Cement dumper and handling dry

cement or gypsum; Choke-setter and rigger (clearing work);

Concrete bucket dumper and chute; Concrete chipping and

grinding; Concrete laborer (wet or dry); Driller tender,

chuck tender, nipper; Guinea chaser (stake), grout crew;

High pressure nozzle, adductor; Hydraulic monitor (over 100

lbs. pressure); Loading and unloading, carrying and hauling

of all rods and materials for use in reinforcing concrete

construction; Pittsburgh chipper and similar type brush

shredders; Sloper; Single foot, hand-held, pneumatic

tamper; All pneumatic, air, gas and electric tools not

listed in Groups 1 through 1-f; Jacking of pipe - under 12

inches

GROUP 3: Construction laborers, including bridge and general

laborer; Dump, load spotter; Flag person; Fire watcher;

Fence erector; Guardrail erector; Gardener, horticultural

and landscape laborer; Jetting; Limber, brush loader and

piler; Pavement marker (button setter); Maintenance, repair

track and road beds; Streetcar and railroad construction

track laborer; Temporary air and water lines, Victaulic or

similar; Tool room attendant (jobsite only)

GROUP 4: Final clean-up work of debris, grounds and building

including but not limited to: street cleaner; cleaning and

washing windows; brick cleaner (jobsite only); material

cleaner (jobsite only). The classification ""material

cleaner"" is to be utilized under the following conditions:

A: at demolition site for the salvage of the material.

B: at the conclusion of a job where the material is to be

salvaged and stocked to be reused on another job.

C: for the cleaning of salvage material at the jobsite or

temporary jobsite yard.

The material cleaner classification should not be used in

the performance of ""form stripping, cleaning and oiling

and moving to the next point of erection"".

--------------------------------------------------------

GUNITE LABORER CLASSIFICATIONS

GROUP 1: Structural Nozzleman

GROUP 2: Nozzleman, Gunman, Potman, Groundman

GROUP 3: Reboundman

GROUP 4: Gunite laborer

----------------------------------------------------------

WRECKING WORK LABORER CLASSIFICATIONS

GROUP 1: Skilled wrecker (removing and salvaging of sash,

windows and materials)

GROUP 2: Semi-skilled wrecker (salvaging of other building

materials)

----------------------------------------------------------------

LABO1130-008 07/01/2018

CALAVERAS, FRESNO, KINGS, MADERA, MARIPOSA, MERCED, SAN

JOAQUIN, STANISLAUS & TUOLUMNE

Rates Fringes

Plasterer tender.................$ 32.02 23.00

Work on a swing stage scaffold: $1.00 per hour additional.

----------------------------------------------------------------

LABO1130-009 07/01/2018

MARIPOSA, MERCED, STANISLAUS, AND TUOLUMNE COUNTIES

Rates Fringes

LABORER (Plaster Tender).........$ 32.02 23.00

Work on a swing stage scaffold: $1.00 per hour additional.

----------------------------------------------------------------

PAIN0016-001 01/01/2019

ALAMEDA, CONTRA COSTA, MONTEREY, SAN BENITO, SAN MATEO, SANTA

CLARA, AND SANTA CRUZ COUNTIES

Rates Fringes

Painters:........................$ 42.67 24.03

PREMIUMS:

EXOTIC MATERIALS - $0.75 additional per hour.

SPRAY WORK: - $0.50 additional per hour.

INDUSTRIAL PAINTING - $0.25 additional per hour

[Work on industrial buildings used for the manufacture and

processing of goods for sale or service; steel construction

(bridges), stacks, towers, tanks, and similar structures]

HIGH WORK:

over 50 feet - $2.00 per hour additional

100 to 180 feet - $4.00 per hour additional

Over 180 feet - $6.00 per houir additional

----------------------------------------------------------------

PAIN0016-003 06/01/2020

AREA 1: ALAMEDA, CONTRA COSTA, SAN FRANCISCO, SAN MATEO & SANTA

CLARA COUNTIES

AREA 2: CALAVERAS, MARIPOA, MERCED, MONTEREY, SAN BENITO, SAN

JOAQUIN, SANTA CRUZ, STANISLAUS & TUOLUMNE COUNTIES

Rates Fringes

Drywall Finisher/Taper

AREA 1......................$ 51.51 27.39

AREA 2......................$ 47.38 25.99

----------------------------------------------------------------

PAIN0016-012 01/01/2019

ALAMEDA, CONTRA COSTA, MARIPOSA, MERCED, MONTEREY, SAN BENITO,

SAN FRANCISCO, SAN MATEO, SANTA CLARA AND SANTA CRUZ COUNTIES

Rates Fringes

SOFT FLOOR LAYER.................$ 48.60 27.43

----------------------------------------------------------------

PAIN0016-015 01/01/2019

CALAVERAS, MARIPOSA, MERCED, SAN JOAQUIN, STANISLAUS & TUOLUMNE

COUNTIES

Rates Fringes

PAINTER

Brush.......................$ 33.68 20.24

FOOTNOTES:

SPRAY/SANDBLAST: $0.50 additional per hour.

EXOTIC MATERIALS: $1.00 additional per hour.

HIGH TIME: Over 50 ft above ground or water level $2.00

additional per hour. 100 to 180 ft above ground or water

level $4.00 additional per hour. Over 180 ft above ground

or water level $6.00 additional per hour.

----------------------------------------------------------------

PAIN0016-022 01/01/2019

SAN FRANCISCO COUNTY

Rates Fringes

PAINTER..........................$ 46.29 24.03

----------------------------------------------------------------

PAIN0169-001 06/01/2020

FRESNO, KINGS, MADERA, MARIPOSA AND MERCED COUNTIES:

Rates Fringes

GLAZIER..........................$ 40.00 26.76

----------------------------------------------------------------

PAIN0169-005 07/01/2020

ALAMEDA CONTRA COSTA, MONTEREY, SAN BENITO, SAN FRANCISCO, SAN

MATEO, SANTA CLARA & SANTA CRUZ COUNTIES

Rates Fringes

GLAZIER..........................$ 52.17 30.55

----------------------------------------------------------------

PAIN0294-004 06/01/2020

FRESNO, KINGS AND MADERA COUNTIES

Rates Fringes

PAINTER

Brush, Roller...............$ 30.18 20.21

Drywall Finisher/Taper......$ 40.10 25.00

FOOTNOTE:

Spray Painters & Paperhangers recive $1.00 additional per

hour. Painters doing Drywall Patching receive $1.25

additional per hour. Lead Abaters & Sandblasters receive

$1.50 additional per hour. High Time - over 30 feet (does

not include work from a lift) $0.75 per hour additional.

----------------------------------------------------------------

PAIN0294-005 06/01/2020

FRESNO, KINGS & MADERA

Rates Fringes

SOFT FLOOR LAYER.................$ 33.30 21.42

----------------------------------------------------------------

PAIN0767-001 07/01/2020

CALAVERAS, SAN JOAQUIN, STANISLAUS AND TUOLUMNE COUNTIES:

Rates Fringes

GLAZIER..........................$ 40.61 30.76

PAID HOLIDAYS: New Year's Day, Martin Luther King, Jr. Day,

President's Day, Memorial Day, Independence Day, Labor Day,

Veteran's Day, Thanksgiving Day, and Christmas Day.

Employee rquired to wear a body harness shall receive $1.50

per hour above the basic hourly rate at any elevation.

----------------------------------------------------------------

PAIN1176-001 07/01/2020

HIGHWAY IMPR0VEMENT

Rates Fringes

Parking Lot Striping/Highway

Marking:

GROUP 1.....................$ 38.48 16.88

GROUP 2.....................$ 32.71 16.88

GROUP 3.....................$ 33.09 16.88

CLASSIFICATIONS

GROUP 1: Striper: Layout and application of painted traffic

stripes and marking; hot thermo plastic; tape, traffic

stripes and markings

GROUP 2: Gamecourt & Playground Installer

GROUP 3: Protective Coating, Pavement Sealing

----------------------------------------------------------------

PAIN1237-003 01/01/2020

CALAVERAS; SAN JOAQUIN COUNTIES; STANISLAUS AND TUOLUMNE

COUNTIES:

Rates Fringes

SOFT FLOOR LAYER.................$ 39.61 22.59

----------------------------------------------------------------

PLAS0066-002 07/01/2019

ALAMEDA, CONTRA COSTA, SAN MATEO AND SAN FRANCISCO COUNTIES:

Rates Fringes

PLASTERER........................$ 42.41 30.73

----------------------------------------------------------------

PLAS0300-001 07/01/2018

Rates Fringes

PLASTERER

AREA 188: Fresno...........$ 32.70 31.68

AREA 224: San Benito,

Santa Clara, Santa Cruz.....$ 32.88 31.68

AREA 295: Calaveras & San

Joaquin Couonties...........$ 32.70 31.68

AREA 337: Monterey County..$ 32.88 31.68

AREA 429: Mariposa,

Merced, Stanislaus,

Tuolumne Counties...........$ 32.70 31.68

----------------------------------------------------------------

PLAS0300-005 07/01/2017

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 33.49 23.67

----------------------------------------------------------------

PLUM0038-001 07/01/2020

SAN FRANCISCO COUNTY

Rates Fringes

PLUMBER (Plumber,

Steamfitter, Refrigeration

Fitter)..........................$ 75.30 46.27

----------------------------------------------------------------

PLUM0038-005 07/01/2019

SAN FRANCISCO COUNTY

Rates Fringes

Landscape/Irrigation Fitter

(Underground/Utility Fitter).....$ 63.04 31.48

----------------------------------------------------------------

PLUM0062-001 07/01/2020

MONTEREY AND SANTA CRUZ COUNTIES

Rates Fringes

PLUMBER & STEAMFITTER............$ 45.00 35.99

----------------------------------------------------------------

PLUM0159-001 07/01/2019

CONTRA COSTA COUNTY

Rates Fringes

Plumber and steamfitter

(1) Refrigeration...........$ 56.93 41.04

(2) All other work..........$ 57.82 41.04

----------------------------------------------------------------

PLUM0246-001 07/01/2020

FRESNO, KINGS & MADERA COUNTIES

Rates Fringes

PLUMBER & STEAMFITTER............$ 42.65 34.64

----------------------------------------------------------------

PLUM0246-004 01/01/2017

FRESNO, MERCED & SAN JOAQUIN COUNIES

Rates Fringes

PLUMBER (PIPE TRADESMAN).........$ 13.00 10.74

PIPE TRADESMAN SCOPE OF WORK:

Installation of corrugated metal piping for drainage, as well

as installation of corrugated metal piping for culverts in

connection with storm sewers and drains; Grouting, dry

packing and diapering of joints, holes or chases including

paving over joints, in piping; Temporary piping for dirt

work for building site preparation; Operating jack hammers,

pavement breakers, chipping guns, concrete saws and spades

to cut holes, chases and channels for piping systems;

Digging, grading, backfilling and ground preparation for

all types of pipe to all points of the jobsite; Ground

preparation including ground leveling, layout and planting

of shrubbery, trees and ground cover, including watering,

mowing, edging, pruning and fertilizing, the breaking of

concrete, digging, backfilling and tamping for the

preparation and completion of all work in connection with

lawn sprinkler and landscaping; Loading, unloading and

distributing materials at jobsite; Putting away materials

in storage bins in jobsite secure storage area; Demolition

of piping and fixtures for remodeling and additions;

Setting up and tearing down work benches, ladders and job

shacks; Clean-up and sweeping of jobsite; Pipe wrapping and

waterproofing where tar or similar material is applied for

protection of buried piping; Flagman

----------------------------------------------------------------

PLUM0342-001 07/01/2018

ALAMEDA & CONTRA COSTA COUNTIES

Rates Fringes

PIPEFITTER

CONTRA COSTA COUNTY.........$ 58.68 42.40

PLUMBER, PIPEFITTER,

STEAMFITTER

ALAMEDA COUNTY..............$ 58.68 42.40

----------------------------------------------------------------

PLUM0355-004 07/01/2020

ALAMEDA, CALAVERAS, CONTRA COSTA, FRESNO, KINGS, MADERA,

MARIPOSA, MERCED, MONTEREY, SAN BENITO, SAN JOAQUIN, SAN MATEO,

SANTA CLARA, SANTA CRUZ, STANISLAUS, AND TUOLUMNE COUNTIES:

Rates Fringes

Underground Utility Worker

/Landscape Fitter...........$ 29.90 16.30

----------------------------------------------------------------

PLUM0393-001 07/01/2020

SAN BENITO AND SANTA CLARA COUNTIES

Rates Fringes

PLUMBER/PIPEFITTER...............$ 66.66 44.83

----------------------------------------------------------------

PLUM0442-001 07/01/2020

CALAVERAS, MARIPOSA, MERCED, SAN JOAQUIN, STANISLAUS & TUOLUMNE

COUNTIES

Rates Fringes

PLUMBER & STEAMFITTER............$ 45.50 31.89

----------------------------------------------------------------

PLUM0467-001 07/01/2020

SAN MATEO COUNTY

Rates Fringes

Plumber/Pipefitter/Steamfitter...$ 70.00 37.86

----------------------------------------------------------------

ROOF0027-002 01/01/2020

FRESNO, KINGS, AND MADERA COUNTIES

Rates Fringes

ROOFER...........................$ 31.11 14.41

FOOTNOTE: Work with pitch, pitch base of pitch impregnated

products or any material containing coal tar pitch, on any

building old or new, where both asphalt and pitchers are

used in the application of a built-up roof or tear off:

$2.00 per hour additional.

----------------------------------------------------------------

ROOF0040-002 08/01/2020

SAN FRANCISCO & SAN MATEO COUNTIES:

Rates Fringes

ROOFER...........................$ 44.38 19.69

----------------------------------------------------------------

ROOF0081-001 08/01/2019

ALAMEDA AND CONTRA COSTA COUNTIES:

Rates Fringes

Roofer...........................$ 40.10 18.88

----------------------------------------------------------------

ROOF0081-004 08/01/2020

CALAVERAS, MARIPOSA, MERCED, SAN JOAQUIN, STANISLAUS AND

TUOLUMNE COUNTIES:

Rates Fringes

ROOFER...........................$ 39.73 19.11

----------------------------------------------------------------

ROOF0095-002 08/01/2020

MONTEREY, SAN BENITO, SANTA CLARA, AND SANTA CRUZ COUNTIES:

Rates Fringes

ROOFER

Journeyman..................$ 46.54 20.69

Kettle person (2 kettles);

Bitumastic, Enameler, Coal

Tar, Pitch and Mastic

worker......................$ 48.54 20.69

----------------------------------------------------------------

SFCA0483-001 07/29/2019

ALAMEDA, CONTRA COSTA, SAN FRANCISCO, SAN MATEO AND SANTA CLARA

COUNTIES:

Rates Fringes

SPRINKLER FITTER (FIRE)..........$ 65.52 32.67

----------------------------------------------------------------

SFCA0669-011 04/01/2020

CALAVERAS, FRESNO, KINGS, MADERA, MARIPOSA, MERCED, MONTEREY,

SAN BENITO, SAN JOAQUIN, SANTA CRUZ, STANISLAUS AND TUOLUMNE

COUNTIES:

Rates Fringes

SPRINKLER FITTER.................$ 38.95 25.63

----------------------------------------------------------------

* SHEE0104-001 07/01/2020

AREA 1: ALAMEDA, CONTRA COSTA, SAN FRANCISCO, SAN MATEO, SANTA

CLARA

AREA 2: MONTEREY & SAN BENITO

AREA 3: SANTA CRUZ

Rates Fringes

SHEET METAL WORKER

AREA 1:

Mechanical Contracts

under $200,000.............$ 55.92 45.29

All Other Work.............$ 64.06 46.83

AREA 2......................$ 52.90 36.44

AREA 3......................$ 55.16 34.18

----------------------------------------------------------------

SHEE0104-003 07/01/2019

CALAVERAS AND SAN JOAQUIN COUNTIES:

Rates Fringes

SHEET METAL WORKER...............$ 41.20 36.84

----------------------------------------------------------------

SHEE0104-005 07/01/2020

MARIPOSA, MERCED, STANISLAUS AND TUOLUMNE COUNTIES:

Rates Fringes

SHEET METAL WORKER (Excluding

metal deck and siding)...........$ 40.38 43.47

----------------------------------------------------------------

* SHEE0104-007 07/01/2020

FRESNO, KINGS, AND MADERA COUNTIES:

Rates Fringes

SHEET METAL WORKER...............$ 42.53 39.64

----------------------------------------------------------------

* SHEE0104-015 07/01/2020

ALAMEDA, CONTRA COSTA, MONTEREY, SAN BENITO, SAN FRANCISCO, SAN

MATEO, SANTA CLARA AND SANTA CRUZ COUNTIES:

Rates Fringes

SHEET METAL WORKER (Metal

Decking and Siding only).........$ 44.45 35.55

----------------------------------------------------------------

* SHEE0104-018 07/01/2020

CALAVERAS, FRESNO, KINGS, MADERA, MARIPOSA, MERCED, SAN

JOAQUIN, STANISLAUS AND TUOLUMNE COUNTIES:

Rates Fringes

Sheet metal worker (Metal

decking and siding only).........$ 44.45 35.55

----------------------------------------------------------------

TEAM0094-001 07/01/2018

Rates Fringes

Truck drivers:

GROUP 1.....................$ 31.68 27.86

GROUP 2.....................$ 31.98 27.86

GROUP 3.....................$ 32.28 27.86

GROUP 4.....................$ 32.63 27.86

GROUP 5.....................$ 32.98 27.86

FOOTNOTES:

Articulated dump truck; Bulk cement spreader (with or without

auger); Dumpcrete truck; Skid truck (debris box); Dry

pre-batch concrete mix trucks; Dumpster or similar type;

Slurry truck: Use dump truck yardage rate.

Heater planer; Asphalt burner; Scarifier burner; Industrial

lift truck (mechanical tailgate); Utility and clean-up

truck: Use appropriate rate for the power unit or the

equipment utilized.

TRUCK DRIVER CLASSIFICATIONS

GROUP 1: Dump trucks, under 6 yds.; Single unit flat rack (2-

axle unit); Nipper truck (when flat rack truck is used

appropriate flat rack shall apply); Concrete pump truck

(when flat rack truck is used appropriate flat rack shall

apply); Concrete pump machine; Fork lift and lift jitneys;

Fuel and/or grease truck driver or fuel person; Snow buggy;

Steam cleaning; Bus or personhaul driver; Escort or pilot

car driver; Pickup truck; Teamster oiler/greaser and/or

serviceperson; Hook tender (including loading and

unloading); Team driver; Tool room attendant (refineries)

GROUP 2: Dump trucks, 6 yds. and under 8 yds.; Transit

mixers, through 10 yds.; Water trucks, under 7,000 gals.;

Jetting trucks, under 7,000 gals.; Single-unit flat rack

(3-axle unit); Highbed heavy duty transport; Scissor truck;

Rubber-tired muck car (not self-loaded); Rubber-tired truck

jumbo; Winch truck and ""A"" frame drivers; Combination winch

truck with hoist; Road oil truck or bootperson;

Buggymobile; Ross, Hyster and similar straddle carriers;

Small rubber-tired tractor

GROUP 3: Dump trucks, 8 yds. and including 24 yds.; Transit

mixers, over 10 yds.; Water trucks, 7,000 gals. and over;

Jetting trucks, 7,000 gals. and over; Vacuum trucks under

7500 gals. Trucks towing tilt bed or flat bed pull

trailers; Lowbed heavy duty transport; Heavy duty transport

tiller person; Self- propelled street sweeper with

self-contained refuse bin; Boom truck - hydro-lift or

Swedish type extension or retracting crane; P.B. or similar

type self-loading truck; Tire repairperson; Combination

bootperson and road oiler; Dry distribution truck (A

bootperson when employed on such equipment, shall receive

the rate specified for the classification of road oil

trucks or bootperson); Ammonia nitrate distributor, driver

and mixer; Snow Go and/or plow

GROUP 4: Dump trucks, over 25 yds. and under 65 yds.; Water

pulls - DW 10's, 20's, 21's and other similar equipment

when pulling Aqua/pak or water tank trailers; Helicopter

pilots (when transporting men and materials); Lowbedk Heavy

Duty Transport up to including 7 axles; DW10's, 20's, 21's

and other similar Cat type, Terra Cobra, LeTourneau Pulls,

Tournorocker, Euclid and similar type equipment when

pulling fuel and/or grease tank trailers or other

miscellaneous trailers; Vacuum Trucks 7500 gals and over

and truck repairman

GROUP 5: Dump trucks, 65 yds. and over; Holland hauler; Low

bed Heavy Duty Transport over 7 axles

----------------------------------------------------------------

WELDERS - Receive rate prescribed for craft performing

operation to which welding is incidental.

================================================================

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave

for Federal Contractors applies to all contracts subject to the

Davis-Bacon Act for which the contract is awarded (and any

solicitation was issued) on or after January 1, 2017. If this

contract is covered by the EO, the contractor must provide

employees with 1 hour of paid sick leave for every 30 hours

they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their

own illness, injury or other health-related needs, including

preventive care; to assist a family member (or person who is

like family to the employee) who is ill, injured, or has other

health-related needs, including preventive care; or for reasons

resulting from, or to assist a family member (or person who is

like family to the employee) who is a victim of, domestic

violence, sexual assault, or stalking. Additional information

on contractor requirements and worker protections under the EO

is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within

the scope of the classifications listed may be added after

award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (ii)).

----------------------------------------------------------------

The body of each wage determination lists the classification

and wage rates that have been found to be prevailing for the

cited type(s) of construction in the area covered by the wage

determination. The classifications are listed in alphabetical

order of ""identifiers"" that indicate whether the particular

rate is a union rate (current union negotiated rate for local),

a survey rate (weighted average rate) or a union average rate

(weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed

in dotted lines beginning with characters other than ""SU"" or

""UAVG"" denotes that the union classification and rate were

prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of

the union which prevailed in the survey for this

classification, which in this example would be Plumbers. 0198

indicates the local union number or district council number

where applicable, i.e., Plumbers Local 0198. The next number,

005 in the example, is an internal number used in processing

the wage determination. 07/01/2014 is the effective date of the

most current negotiated rate, which in this example is July 1,

2014.

Union prevailing wage rates are updated to reflect all rate

changes in the collective bargaining agreement (CBA) governing

this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that

no one rate prevailed for this classification in the survey and

the published rate is derived by computing a weighted average

rate based on all the rates reported in the survey for that

classification. As this weighted average rate includes all

rates reported in the survey, it may include both union and

non-union rates. Example: SULA2012-007 5/13/2014. SU indicates

the rates are survey rates based on a weighted average

calculation of rates and are not majority rates. LA indicates

the State of Louisiana. 2012 is the year of survey on which

these classifications and rates are based. The next number, 007

in the example, is an internal number used in producing the

wage determination. 5/13/2014 indicates the survey completion

date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a

new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate

that no single majority rate prevailed for those

classifications; however, 100% of the data reported for the

classifications was union data. EXAMPLE: UAVG-OH-0010

08/29/2014. UAVG indicates that the rate is a weighted union

average rate. OH indicates the state. The next number, 0010 in

the example, is an internal number used in producing the wage

determination. 08/29/2014 indicates the survey completion date

for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of

each year, to reflect a weighted average of the current

negotiated/CBA rate of the union locals from which the rate is

based.

----------------------------------------------------------------

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can

be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on

a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests

for summaries of surveys, should be with the Wage and Hour

Regional Office for the area in which the survey was conducted

because those Regional Offices have responsibility for the

Davis-Bacon survey program. If the response from this initial

contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal

process described here, initial contact should be with the

Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations

Wage and Hour Division

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an

interested party (those affected by the action) can request

review and reconsideration from the Wage and Hour Administrator

(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the

interested party's position and by any information (wage

payment data, project description, area practice material,

etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an

interested party may appeal directly to the Administrative

Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

================================================================

END OF GENERAL DECISION"

Injection Wells Phase 3Mandatory Pre-Bid Meeting

9/17/2020 9:00

Name Company Zoom Site Tour 9/17/2020 Site Tour 9/30/2020Gabriela Raya Monterey Peninsula Engineering [email protected] Yes YesAaron Ellis Anderson Pacific Engineering [email protected] YesGary Barber Anderson Pacific Engineering [email protected] Yes YesPete Anderson Anderson Pacific Engineering [email protected] YesGlen Lamoreaux Mountain Cascade Inc. [email protected] Yes YesAlbert Vasquez Nor-Cal Pump & Well Drilling [email protected] Yes YesMark Jorgenson Pacific Infrastructure [email protected] Yes YesRoss Wickes Anvil Builders [email protected] Yes YesWes Lockard Pacific Coast West Well Drilling [email protected] Yes YesChelsea Borneman Pacific Coast West Well Drilling chelsea@pcwelldrilling. YesTom Seidel Specialty Construction, Inc [email protected] Yes YesRyan Coffin Capital Flow [email protected] YesBrian Zimmerer Zim Industries [email protected] Yes YesScott Turner PCL Construction [email protected] Yes