November 1, 2017 1
Completed and ongoing tasks:
• Construction trailers setup completed.
• Excavation and sheeting/shoring ongoing.
• Starting rebar work for footing and foundation.
Construction activities next month:
• Continuing excavation.
• Temporary construction power will be installed.
• Below grade waterproofing will be installed.
• Tower crane will be erected.
• Concrete footings and foundation walls will be installed.
Process related activities:
• Building Level Planning Committee meeting will be held in early December.
• Construction workers parking during excavation and sheeting/ shoring will be on-site.
Secondary School @Wilson
Community Newsletter (October 2017)