Upload
others
View
26
Download
0
Embed Size (px)
Citation preview
Confidential
Secondary Control Equipment
Modernisation ED2 Engineering Justification Paper
ED2-NLR(O)-SPEN-001-NCP-EJP
Issue Date Comments
Issue 1 30th June 2021 First Issue
Issue 2 30th November 2021 Second Issue
Scheme Name Secondary Control Equipment Modernisation
PCFM Cost Type Non-Load Related - Asset Replacement
Activity Secondary Control Equipment Modernisation
Primary Investment Driver Condition driven asset modernisation programme
Reference ED2-NLR(O)-SPEN-001-NCP-EJP
Output Type Operational IT and Telecoms Strategy
Cost SPD - £5.76m SPM - £2.76m
Delivery Year 2023-2028
Reporting Table CV11 (Substation RTUs, marshalling kiosks, receivers)
Outputs included in ED1 No
Business Plan Section Maintaining a Safe & Resilient Network
Primary Annex Annex 4A.16: Operational IT and Telecoms Strategy
Spend Apportionment ED1 ED2 ED3
£m £8.52m £m
ED2-NLR(O)-SPEN-001-NCP-EJP - Secondary Control Equipment Modernisation
1
Confidential
Technical Governance Process
Project Scope Development IP1(S)
To be completed by the Service Provider or Asset Management. The completed form, together with an accompanying report, should be endorsed by the appropriate sponsor and submitted for approval. IP1 – To request project inclusion in the investment plan and to undertake project design work or request a modification to an existing project
IP1(S) – Confirms project need case and provides an initial view of the Project Scope IP2 – Technical/Engineering approval for major system projects by the System Review Group (SRG) IP2(C) – a Codicil or Supplement to a related IP2 paper. Commonly used where approval is required at more than one SRG, typically connection projects which require
connection works at differing voltage levels and when those differing voltage levels are governed by two separate System Review Groups. IP2(R) – Restricted Technical/Engineering approval for projects such as asset refurbishment or replacement projects which are essentially on a like-for-like basis and not requiring a full IP2 IP3 – Financial Authorisation document (for schemes > £100k prime)
IP4 – Application for variation of project due to change in cost or scope
PART A – PROJECT INFORMATION
Project Title: Secondary Control Equipment Modernisation
Project Reference: ED2-NLR(O)-SPEN-001-NCP-EJP
Decision Required: To give concept approval for the project scope to replace legacy secondary control equipment.
Summary of Business Need:
To continue the ED1 replacement programme for end of life secondary control equipment. Obsolescence, cyber security
risk, age of assets, lack of manufacturer support and absence of serviceable spares have driven the targeted replacement of
legacy secondary control equipment in RIIO-ED2.
Summary of Project Scope, Change in Scope or Change in Timing:
The project will continue the ED1 programme targeting the replacement of secondary control equipment based on
obsolescence, associated support issues and component failure modes.
Expenditure Forecast (in 2020/21 Prices)
Licence
Area
Reporting
Table Description
Total
(£m)
Incidence (£m)
2023/24 2024/25 2025/26 2026/27 2027/28
SPD CV11
Op IT and Telecoms -
Substation RTUs,
marshalling kiosks,
receivers
5.76 1.15 1.15 1.15 1.15 1.15
Sub-Total 5.76 1.15 1.15 1.15 1.15 1.15
SPM CV11
Op IT and Telecoms -
Substation RTUs,
marshalling kiosks,
receivers
2.76 0.55 0.55 0.55 0.55 0.55
Sub-Total 2.76 0.55 0.55 0.55 0.55 0.55
SPEN Total 8.52 1.71 1.70 1.70 1.70 1.70
PART B – PROJECT SUBMISSION
Proposed by Chris Halliday Signature
Date: 30th Nov 2021
Endorsed by Brian Thomas Signature
Date: 30th Nov 2021
PART C – PROJECT APPROVAL
Approved by John Gray Signature
Date: 30th Nov 2021
ED2-NLR(O)-SPEN-001-NCP-EJP - Secondary Control Equipment Modernisation
2
Confidential
Contents 1 Introduction .................................................................................................................................... 3
2 Background Information ................................................................................................................. 3
3 Optioneering ................................................................................................................................... 7
4 Detailed Analysis & Costs ................................................................................................................ 8
5 Deliverability & Risk ...................................................................................................................... 10
6 Conclusion ..................................................................................................................................... 15
7 Appendices .................................................................................................................................... 16
ED2-NLR(O)-SPEN-001-NCP-EJP - Secondary Control Equipment Modernisation
3
Confidential
1 Introduction In the early 2000s, SPEN started implementing a number of initiatives to improve 11kV secondary
network system performance. These initiatives included the introduction of secondary control
equipment to enable the remote disconnection of faulted network sections and restoration of
customers from alternative sources where possible.
The Supervisory Control and Data Acquisition (SCADA) system is the means by which each item of
plant on network is securely monitored and controlled in real time. SCADA enables the network to
be managed including remote control of plant for planned and unplanned works and recovery of
critical alarms and indications. SCADA is not only critical for network management but also safety
management, risk mitigation and resource response. The SCADA central system used for electrical
network operations is referred to as the Network Management System (NMS). Legacy secondary
control equipment communicates with the NMS using insecure, vendor-locked proprietary SCADA
protocols over unencrypted radio links.
Constant monitoring and control of the secondary network is critical to ensure a safe, secure and
reliable supply to all customers. Managing the electrical network requires constant data
communications between the SPEN control room and substations. Remote Terminal Units (RTUs)
take the signals from all the plant in the secondary substation and converts them to signals suitable
to be transmitted to the NMS in the SPEN control room. Pole mounted substations come with an
inbuilt RTU so only require a communications device in order to be monitored and controlled
remotely. Secondary control equipment including ground mount RTUs and radio modems deployed
in the early to mid-2000s are now approaching end of life.
Since the initial installation of secondary control equipment, there have been radical changes in the
distribution network resulting from the electrification of transport, distributed generation, storage
and demand side response. It is no longer acceptable to operate the secondary network on a fit and
forget basis; an analogue layer of monitoring is required to improve efficiency of assets and allow
additional network capacity to be unlocked through enhanced visibility of the distribution network.
Fault management is no longer the sole consideration for secondary control equipment; the focus
must be expanded to embrace the requirement for real-time network management. Legacy
secondary control equipment is a major constraint and replacing it should be used as an opportunity
to improve the monitoring functionality of secondary substations to accelerate the transition from a
Distribution Network Operator (DNO) to a Distributed System Operator (DSO).
The majority of the secondary control equipment was installed in the early to mid-2000s. Despite
the age concerns the main drivers for the replacement of the secondary control equipment are
obsolescence, cyber security risk, lack of manufacturer support and absence of serviceable spares.
The replacement activity began in ED1, will ramp up significantly in ED2 and is due to be completed
in ED3.
This justification paper supports the intention for SPEN to invest £8.52m over the RIIO-ED2 period
to replace and upgrade the existing population of secondary control equipment.
2 Background Information This paper supports a proposal to continue the programme started in ED1 of modernising the legacy
population of secondary control equipment. Ensuring the integrity of the secondary control asset
base is critical to maintaining continuous monitoring and control of the network such that faults can
be managed quickly, safely and efficiently. The RTUs and radio modems classed as secondary control
ED2-NLR(O)-SPEN-001-NCP-EJP - Secondary Control Equipment Modernisation
4
Confidential
equipment have been assessed according to the methodology determined by Protection Equipment
Asset Health Assessment Methodology, ASSET-01-025. Using an appropriate method for
classification of protection and control equipment asset health enables all protection and control
assets to be assessed in the same way against the same criteria. This method enables SPEN to form
protection and control modernisation priorities and target appropriate investment. The RTUs and
radios covered by this justification are rated at Health Index 5 due to the following reasons
• Withdrawal of manufacturer support
• Limited ability to support as spares can no longer be purchased
• Limited means of equipment substitution as products are vendor locked
• Increasing failure rate and significant defects with a 336% increase in annual defects reported
between 2017 (237) and 2020 (796)
• Non-compliance with technical policy regarding cyber security
• Special call outs required to manually clear buffer problem
2.1 ED1 Track Record
Due to the health index rating, a programme of replacement started in RIIO-ED1. It was intended
that this programme would significantly ramp up RIIO-ED2 and be completed during the RIIO-ED3
price control.
2.2 Needs Case
Despite the age concerns the main drivers for the replacement of the secondary control equipment
are obsolescence, associated support issues, non-compliance with cyber security technical policy and
significant defects. The legacy secondary control equipment uses bespoke SCADA protocols over
unencrypted radio links to communicate with the central NMS. Proprietary SCADA protocols not
only limit competition by restricting supply to a single vendor but also fail to deliver the level of
modern cyber security required to protect the network. The secondary RTUs also have capacity
restrictions, cannot be used for analogue monitoring and are limited in their ability to communicate
with modern Intelligent Electronic Devices (IEDs) and associated substation devices which are now
installed on modern substation plant. These legacy RTUs and radios cannot be updated to meet new
cyber security or functional requirements.
The original secondary control equipment manufacturer has ceased trading and key components are
no longer manufactured. The original vendor can no longer support these assets and spares cannot
be purchased therefore critical parts cannot be replaced if faulty. This represents a critical risk to
the SCADA system as if an asset fails it can lead to loss of monitoring and control to part of the
secondary network.
The majority of these essential assets were installed in the early to mid-2000s. Secondary control
equipment has a shorter life expectancy of than that of control equipment in Grid and Primary
substations in part due to the much harsher environment secondary control equipment has to
operate in.
The secondary control system is also starting to show significant defects, the graph below shows the
total defects logged per year from 2017, 2018, 2019 and 2020. There has been a 336% increase in
annual defects reported between 2017 (237) and 2020 (796).
ED2-NLR(O)-SPEN-001-NCP-EJP - Secondary Control Equipment Modernisation
5
Confidential
Figure 1: Annual defects reported in secondary control equipment
Below is 3 months of data from 7th October 2020 to 6th January 2021. In this period, 131 devices
are showing switchgear communications failures meaning the radio modem has lost communications
with the RTU. The worst offender on the list has lost communications with the RTU 10,559 times in
the 3-month period. The switchgear communications failures are believed to be a result of a bug in
modem software that fails to acknowledge an event message from the RTU meaning the events in
RTU buffer are never cleared, resulting in the number of events continuing to increase for every
new event and the SCADA message growing bigger and communication becoming sporadic and
unstable. Special call out are required to clear the RTU buffer due to the bug in the radio modem
failing to acknowledge a SCADA event.
Figure 2: SWGR Comms Fails - 3 months of data (7th October 2020 to 6th January 2021)
0
100
200
300
400
500
600
700
800
900
2017 2018 2019 2020
An
nu
al D
efec
ts R
epo
rted
Year
Secondary Control Equipment Annual Defects Reported
ED2-NLR(O)-SPEN-001-NCP-EJP - Secondary Control Equipment Modernisation
6
Confidential
The lack of vendor support for an aging population of obsolete secondary control equipment is a
current business risk. As described in ED1, this position is unsustainable as an ongoing model and
the remaining population of legacy secondary control equipment must be replaced over the medium
term. The replacement programme started in ED1, will significantly ramp up in ED2 and be
completed in ED3. Replacing the secondary control equipment over three price control periods is
the preferred strategy to allow the telecoms network to be developed and deployed in an efficient
manner in line with requirements. The remaining population can also be temporarily supported using
healthy spares recovered as part of the replacement programme. The liberated spares help prolong
the asset life of the remaining legacy equipment although not indefinitely as the spares are already in
an aged condition.
Standalone ED2 replacement activities are shown in the table below.
Equipment Type SPD SPM Total
Ground Mount RTU 1038 425 1463
Pole Mounted Recloser 371 323 694
Pole Mounted Switch 296 398 694
Total 1705 1146 2851 Table 1: Standalone ED2 replacement activities on SPM and SPD
ED2-NLR(O)-SPEN-001-NCP-EJP - Secondary Control Equipment Modernisation
7
Confidential
3 Optioneering
# Options Decision Comment
0 Upgrade secondary control
equipment with bespoke solution
engineered to support legacy
protocols and data models
Proposed
(credible
solution)
Baseline Case (minimal intervention)
1 Upgrade secondary control
equipment with solution based
on secure, industry standard
protocols - Extended timescales
(recovered equipment used as
spares)
Adopted
(credible
solution)
Costed as Option 1 - Move to industry standard
protocols and subsequent development to telecoms
network, sets a good foundation for smart grid
initiatives to be built upon. Extended implementation
timescales defer capital and allow time for strategy and
programme implementation to mature and optimise.
2 Upgrade secondary control
equipment with solution based
on secure, industry standard
protocols - Condensed
timescales
Proposed
(credible
solution)
Costed as Option 2 - Move to industry standard
protocols and subsequent development to telecoms
network, sets a good foundation for smart grid
initiatives to be built upon.
3 Do nothing (stop programme
after ED1).
Rejected
(non-
credible
solution)
This would increase the risk of secondary control
equipment failures leading to loss of visibility and control
for secondary substations thus compromising the
control room’s ability to manage the network 24/7. This
is an unacceptable risk level. Table 2: Optioneering table
ED2-NLR(O)-SPEN-001-NCP-EJP - Secondary Control Equipment Modernisation
8
Confidential
4 Detailed Analysis & Costs
4.1 Selected Option Summary
Option 1 proposes replacing the unsupported secondary control equipment no longer available for
purchase and unsuitable for modern cyber security requirements. During the RIIO-ED1 price
control, funding was approved to commence a programme of this nature. Replacement secondary
control equipment will be cyber secure and support the most common industry protocols and
international standards; ensuring the assets can be supported for the longest period possible and
remove the risks associated with single supplier dependence. Vendor specific proprietary protocols
are no longer fit for purpose. Replacement RTUs are suitable for modern IEDs but also capable of
supporting hardwired I/O as this is the defacto arrangement for most existing substation plant
installations. The move to modern secondary control equipment will also reduce whole life cost of
assets by reducing operational expenditure and environmental impact associated with having to visit
each site to collect log files or upgrade configuration/firmware as this will be able to be carried out
remotely.
The replacement of end of life secondary control equipment started in ED1. The primary drivers for
replacement activities to commence in ED1 were obsolescence, cyber security risk and lack of
equipment support and parts. The equipment vendor has ceased trading and the key control
components are no longer manufactured. All useable spares will continue to be recovered to
support existing asset base. It is essential that this equipment is replaced before failure, as it is
integral to ensuring current levels of network performance are maintained.
The move to modern SCADA protocols required telecoms infrastructure development due to
higher bandwidth and cyber security requirements. Over the ED1 period, SPEN have trialled an
Internet Protocol (IP) based communications network suitable for modern standard SCADA
protocols. This transition from legacy slow speed serial links to higher speed IP infrastructure has
required significant development of the operational telecoms infrastructure.
Although it is possible to carry out bespoke development works to enable legacy protocols on
modern secondary control equipment and this would have reduced the work required on the
telecoms infrastructure, this would have added significant equipment development costs, severely
limited vendors capable of providing a solution and would have failed to deliver the required level of
cyber security. Continuation of legacy bespoke protocols not only restricts the range of control
equipment suppliers but also the NMS solutions on which the legacy protocols need to be
supported.
Failure to move to industry standard equipment would result in high secondary control equipment
costs in comparison to industry averages as the equipment would have been bespoke. SPEN would
also be unable to share the benefits of innovation, making it more difficult to develop smart grid
initiatives. SPEN remain firmly committed to replace legacy secondary control equipment with
equipment that utilises modern standard protocols and support industry standards. There is no
reason to halt the programme of replacement or change the programme to one based on the
installation of equipment engineered to support insecure, legacy protocols. The approach of buying
secondary control equipment which communicates using the latest generation of industry standard
protocols over an IP network is more sustainable over the long term than perpetuating legacy
protocols and also allows SPEN access to a larger supplier cohort resulting in cost reduction
through competitive tendering.
ED2-NLR(O)-SPEN-001-NCP-EJP - Secondary Control Equipment Modernisation
9
Confidential
SPEN proposes the continued deployment of modern secondary control equipment using open
standard protocols with secure, encrypted IP communications technology. This new solution will
provide the necessary infrastructure between control room and the secondary distribution network
for the data-requirements of the smart grid and will provide functionality for supporting remote
management and maintenance to increase operational efficiency.
An improvement is expected in CI/CML by moving to standard control equipment as this opens up a
range of modern telecommunications solutions to improve telecontrol availability and reliability that
bespoke control equipment could not support.
Standalone ED2 replacement activities are shown in the table below.
Equipment Type SPD SPM Total
Ground Mount RTU 1038 425 1463
Pole Mounted Recloser 371 323 694
Pole Mounted Switch 296 398 694
Total 1705 1146 2851
Table 3: Standalone ED2 replacement activities on SPM and SPD
4.2 Alternative Options Summary
Baseline
Bespoke engineered equipment based on current experience is more expensive to purchase than
industry standard equipment. Perpetuation of legacy protocols has many long-term risks due to
associated limited range of suppliers and even more limited range of products on which the
legacy protocols can still be supported. As a result, support is expected to be an issue in the future
and the supportable asset life of these products could be less than industry standard products.
Upgrading the secondary control equipment with a bespoke solution engineered to support legacy
protocols and data models would also fail to address to issues around cyber security and stop
modern IEDs being integrated.
Option 2
Moving to equipment which utilises modern standard protocols and supports industry standards for
substation automation opens up many benefits and opportunities. Condensing this transition and
replacing the remaining asset base in ED2 would accelerate the benefits and opportunities however
doing this would miss the opportunity to extend the existing asset life by recovering spares during
the replacement programme.
Option 3
Doing nothing in ED2 and stopping the programme after ED1 would increase the risk of secondary
control equipment failures leading to loss of visibility and control for secondary substations thus
compromising the control room’s ability to manage the network 24/7. This is an unacceptable risk
level.
ED2-NLR(O)-SPEN-001-NCP-EJP - Secondary Control Equipment Modernisation
10
Confidential
4.3 Options Technical Summary table
# Option Technical Summary
0 Baseline Replace 2851 secondary control assets in SPM and SPD with bespoke
solution. Total cost £10.25m.
1 Option 1 Replace 2851 secondary control assets in SPM and SPD with industry
standard solution (extended timescales). Total cost (excluding pension
contribution) £8.56m.
2 Option 2 Replace 5702 secondary control assets in SPM and SPD with industry
standard solution (condensed timescales). Total cost £16.76m.
Table 4: Options Technical Summary table
4.4 Options Cost summary tables
# Option Cost Breakdown £m NARMs
Risk Change £/Risk
0 Baseline Replace 1463 Sec GM units £8,63 n/a n/a
Replace 694 Sec PMAR units £0.53
Replace 694 Sec PMSW units £1.08
Total £10.25
1 Option 1 Replace 1463 Sec GM units £7.32 n/a n/a
Replace 694 Sec PMAR units £0.26
Replace 694 Sec PMSW units £0.8
Pension Contribution £0.18
Total £8.56
2 Option 2 Replace 2926 Sec GM units £14.63 n/a n/a
Replace 1388 Sec PMAR units £0.52
Replace 1388 Sec PMSW units £1.6
Total £16.76 Table 5: Options Cost Summary table
Please note that this analysis was carried out before a pensions adjustment was made, and so the total costs
differ slightly from the final scheme.
ED2-NLR(O)-SPEN-001-NCP-EJP - Secondary Control Equipment Modernisation
11
Confidential
5 Deliverability & Risk
5.1 Preferred Options & Output Summary
The preferred option is to upgrade the remaining secondary control equipment with a solution
based on secure, industry standard protocols over an extended timescale of 2 price control periods
RIIO-ED2 and RIIO-ED3.
5.2 Cost Benefit Analysis Results
Option 1 - Upgrade secondary control equipment with a solution based on secure, industry standard
protocols over an extended timescale of 10 years. An improvement is expected in CI/CML by
moving to standard control equipment as this opens up a range of modern telecommunications
solutions to improve telecontrol availability and reliability that bespoke control equipment could not
support.
CBA - Option 1 Extended Timescales
Term (years from first year of RIIO-
ED2) NPV (£m)
10 £1.53
20 £2.34
30 £2.82
45 £3.20
Whole Life NPV £3.27
First year of investment out flow 2024
Option 2 - Upgrade secondary control equipment with a solution based on secure, industry standard
protocols over a condensed timescale of 5 years. An improvement is expected in CI/CML by moving
to standard control equipment as this opens up a range of modern telecommunications solutions to
improve telecontrol availability and reliability that bespoke control equipment could not support.
CBA - Option 2 Condensed Timescales
Term (years from first year of RIIO-
ED2) NPV (£m)
10 (£0.20)
20 £0.75
30 £1.33
45 £1.81
Whole Life NPV £2.04
First year of investment out flow 2024
ED2-NLR(O)-SPEN-001-NCP-EJP - Secondary Control Equipment Modernisation
12
Confidential
5.3 Cost & Volumes Profile
Standalone ED2 replacement activities are shown in the table below.
Equipment Type SPD SPM Total
Ground Mount RTU 1038 425 1463
Pole Mounted Recloser 371 323 694
Pole Mounted Switch 296 398 694
Total 1705 1146 2851 Table 6: Standalone ED2 replacement activities
The total units delivered each year as part of standalone ED2 replacement activities are shown in the
table below.
2023/24 2024/25 2025/26 2026/27 2027/28
SPD 341 341 341 341 341
SPM 230 229 229 229 229
SPEN 571 570 570 570 570
Table 7: Delivery profile – volumes
Regional variations and site specific costs are not relevant for the high volume programme as
solutions will be standard and consistent across the network.
Total Cost £m
SPD
Expenditure Item 2023/24 2024/25 2025/26 2026/27 2027/28 Total
Total £1.15 £1.15 £1.15 £1.15 £1.15 £5.76
SPM
Expenditure Item 2023/24 2024/25 2025/26 2026/27 2027/28 Total
Total £0.55 £0.55 £0.55 £0.55 £0.55 £2.76 Table 8: Delivery profile – total costs
5.4 Risks
The scope of this paper proposes the continuation of the ED1 programme; this requires support
arrangements to modernise legacy equipment. There is therefore a dependency on existing suppliers
who were selected for their ability to provide the necessary service and have been doing so
successfully during ED1. There is no perceived increase in risk during ED2.
There is also a dependency on the internal staff to manage the proposed workload which again they
have been doing to a similar extent during ED1. The team consists of highly experienced individuals
with skills that are not widely available. Whilst this always represents a risk, the scheduling of the
programme of works has been levelled as far as possible to avoid overload and ensure deliverability.
ED2-NLR(O)-SPEN-001-NCP-EJP - Secondary Control Equipment Modernisation
13
Confidential
There is no specific contingency or explicit reference to costs due to the low levels of risk
envisaged.
5.5 Outputs Included in RIIO ED1 Plans
This is a continuation of ED1 replacement programme.
5.6 Future Pathways – Net Zero
5.6.1 Primary Economic Driver
Condition driven asset modernisation programme to reduce the risk of network damage and/or
longer network outages because of failed or compromised secondary control equipment.
5.6.2 Payback Periods
The CBA indicates that a positive NPV results in all assessment periods (10, 15, 30 & 45 years).
5.6.3 Pathways and End Points
The proposed option is consistent with the SPENs DSO Strategy and Distribution Future Energy
Scenarios.
5.6.4 Asset Stranding Risks & Future Asset Utilisation
Electricity demand and LCT uptake are forecast to increase under all scenarios. The stranding risk is
therefore considered to be very low. It has been assessed that the preferred option is consistent
with the future generation and demand scenarios and that the risk of stranding is very low.
5.6.5 Losses / Sensitivity to Carbon Prices
Not appropriate to this investment.
5.6.6 Whole Systems Benefits
The completion of this replacement programme will maintain the integrity of the distribution
network and its enduring ability to facilitate wider whole system benefits.
5.7 Environmental Considerations
5.7.1 Operational and embodied carbon emissions
The targeted replacement of secondary control equipment based on obsolescence, associated
support issues and component failure modes has the potential to result in embodied carbon from
the delivery of interventions required. There is unlikely to be any impact on SPEN’s Business Carbon
Footprint (BCF).
5.7.2 Supply chain sustainability
For us to take full account of the sustainability impacts associated of the Secondary Control
Equipment Modernisation programme, we need access to reliable data from our suppliers. The need
for carbon and other sustainability credentials to be provided now forms part of our wider
sustainable procurement policy.
5.7.3 Resource use and waste
Replacement of secondary control equipment will result in the consumption of resources and the
generation of waste materials.
ED2-NLR(O)-SPEN-001-NCP-EJP - Secondary Control Equipment Modernisation
14
Confidential
Where waste is produced it will be managed in accordance with the waste hierarchy which ranks
waste management options according to what is best for the environment. The waste hierarchy gives
top priority to preventing waste in the first instance, then preparing for re-use, recycling, recovery,
and last of all disposal (e.g. landfill).
5.7.4 Biodiversity/ natural capital
The replacement of secondary control equipment will only affect developed sites containing existing
assets. Therefore, the impact on, and the opportunity to improve biodiversity and natural capital is
expected to be minimal.
5.7.5 Preventing pollution
SPEN will always follow all relevant waste regulations and will make sure that special (hazardous)
waste produced or handled by our business is treated in such a way as to minimise any effects on
the environment.
5.7.6 Visual amenity
SPEN continually seeks to reduce the landscape and visual effects of our networks and assets. The
proposed interventions at existing sites are unlikely to generate any additional impact in relation to
visual amenity.
5.7.7 Climate change resilience
In addition to our efforts to minimise our direct carbon emissions in line with our net-zero
ambitions, we are also conscious of the need to secure the resilience of our assets and networks in
the face of a changing climate.
ED2-NLR(O)-SPEN-001-NCP-EJP - Secondary Control Equipment Modernisation
15
Confidential
6 Conclusion The options proposed have been reviewed and assessed in terms of scope, costs and risk. The
approach proposed in this paper provides the most cost-effective option to remove the risk of
secondary control equipment failures leading to loss of visibility and control for secondary
substations thus compromising the control room’s ability to manage the network 24/7. This paper is
fundamentally about justifying the continued strategic replacement of secondary control equipment
to maintain the high levels of system performance that our customers deserve.
This paper recommends continuing the replacement of end of life secondary control equipment
started in ED1 over the ED2 and ED3 price control periods. The primary drivers for replacement
are obsolescence, cyber security risk and lack of equipment support and parts. All useable spares will
continue to be recovered to support existing asset base. It is essential that this equipment is
replaced before failure, as it is integral to ensuring current levels of network performance are
maintained.
The total units delivered each year as part of standalone ED2 replacement activities are shown in the
table below.
2023/24 2024/25 2025/26 2026/27 2027/28
SPD 341 341 341 341 341
SPM 230 229 229 229 229
SPEN 571 570 570 570 570
Table 9: Delivery profile – volumes
The expenditure profile is shown in the table below.
Total Cost £m
SPD
Expenditure Item 2023/24 2024/25 2025/26 2026/27 2027/28 Total
Total £1.15 £1.15 £1.15 £1.15 £1.15 £5.76
SPM
Expenditure Item 2023/24 2024/25 2025/26 2026/27 2027/28 Total
Total £0.55 £0.55 £0.55 £0.55 £0.55 £2.76 Table 10: Delivery profile – costs
ED2-NLR(O)-SPEN-001-NCP-EJP - Secondary Control Equipment Modernisation
16
Confidential
7 Appendices N/A