Second Avenue Subway
Community Board 8 Second Avenue Subway
Task Force Update
February 1, 2016
Tom Peyton, P.E.
Project Director, Construction
Second Avenue Subway Project
11
96th Street Station
(Cut-and-Cover)
86th Street Station
2 Entrances
72nd Street Station
3 Entrances
63rd Street /
Lexington Ave Station
Phase 1: Target Cost-$4.451B--- Ridership 200,000 --- Target Completion Date-December 2016
• Scope:
Q train service
Tunnels from 92nd St to 63rd St
New Stations at 96th St, 86th St, and 72nd St
63rd St Station Connection
Track & Systems from 105th St to 63rd St
Service between 96th St & Brooklyn via Broadway Line
Phase 1 Overview
96th Street Station
3 Entrances
63rd Street Station
4 New Entrances
22
• The Second Avenue Subway Project is on time and on budget for a December 2016 completion.
• Overall Construction Progress is 90.75% complete as of January 1st.
• All 10 SAS Contracts have been awarded for Phase 1
• 5 Construction Contracts Completed:
− Tunnel Boring Machine Tunneling
− 86th St Excavation, Utility Relocation, and Road Decking
− 96th St Site Work and Heavy Civil
− 72nd St Cavern Mining, Tunnels and Heavy Civil
− 86th St Cavern Mining & Heavy Civil
Current Project Status
3
5 Active Contracts
96th St. Station Finishes, Systems, Ancillary 90.8%
Buildings and Entrances
86th St. Station Finishes, Systems, Ancillary 87.35%
Buildings and Entrances
72nd St. Station Finishes, Systems, Ancillary 75.16%
Buildings and Entrances
63rd St. Station Upgrade 95 %
Project track, Power, Signals & Communications 73.9%
Systems
4
63rd Street
3rd
Ave
Ancillary 1
124 E 63rd St
Top of
Hahn Garage
Entrance 4
(Outside)Entrance 1
(Inside)
Entrance 3
(Outside)
New Elevator Entrance 2
Ancillary 2
Lexin
gto
n A
ve
Existing Elevator Entrance
Existing Entrance
Existing Entrance
Plaza
Station Upgrade Contract
Percent Complete: 95 %
Contract Value incl. AWOs: $190.8 M
Award Date: January 13, 2011
Forecast Completion: Spring 2016
Rehabilitation of Existing 63rd Street
StationPlaza
55
Construction Progress
• Street/sidewalk restoration is near completion
• Entrance 1 build-out of ground floor space of 200 East
63rd Street (framing and glass) is complete. Building
façade work is in progress
• Plaza granite installation is underway. Elevator
enclosure work is complete
• Architectural finishes are near completion and station
systems testing is underway
MTA Capital Construction
66
Current Work Zones(SE corner of 63rd Street & Third Avenue)
MTA Capital Construction
Entrance 1
77
Current Work Zones(NW corner of 63rd Street & Third Avenue)
Plaza Restoration
MTA Capital Construction
88
Current Work Zones(NW corner of 63rd Street & Third Avenue)
Entrance 2 (Elevator Entrance)
99MTA Capital Construction
Current Work Zones(NE corner of 63rd Street & Third Avenue)
Entrance 3
1010
Current Progress
Preparation for ceiling panel installation at
mezzanine level
MTA Capital Construction
1111
Current Progress
New track wall tiles at lower level platform (on 63rd Street and
Lexington Avenue)
MTA Capital Construction
1212
Current Progress
63rd Street station area artwork
MTA Capital Construction
13
Three-Month Look Ahead
13
STATION
• Completion of architectural ceilings, wall tiles, lighting and
column enclosures
• Installation of elevators and escalators
• Testing of mechanical, electrical and plumbing systems in
new station area
MTA Capital Construction
14
Three-Month Look Ahead
14
ENTRANCE 1 (200 East 63rd Street)
• Installation of finishes and tiles
• Installation of ceiling panels above escalator incline
• Artwork installation
• 200 E. 63rd Street exterior building work
MTA Capital Construction
15
Three-Month Look Ahead
15
ANCILLARY 2/ ENTRANCE 2
(Northwest corner of 63rd Street and Third Avenue)
• Installation of granite and furnishings in the plaza area
• Receive materials via sidewalk access hatch on the
north side of 63rd Street, west of the existing work zone
OTHER SURFACE WORK
• Installation of interior finishes at Entrance 3 (northeast
corner of 63rd Street and Third Avenue) and Entrance 4
(southwest corner of 63rd Street and Third Avenue)
• Remaining sidewalk restoration work
MTA Capital Construction
1616
Proposed Rendering of 63rd Street Plaza SW corner of 63rd Street and Third Avenue
17
Rendering of 63rd Street Station Art Installation, Mezzanine Level (Area 5)Artist – Jean Shin, MTA Arts and Design commissioned work 17
18
72nd Street Station
Finishes, MEP Systems, Ancillary Buildings
and Entrances Contract
Percent Complete : 75.16%
Contract Value incl. AWOs: $286.1 M
Award Date: February 14, 2013
Forecast Completion: October 2016
1919MTA Capital Construction
Construction Progress
• Water treatment plant between 73rd and 74th Streets
has been removed
• Ancillary 2 façade work is underway
• Entrance 3 structural work is above ground
• Ancillary 1 structural work has reached the roof level
• Entrance 1 construction continues
• Continuing with mechanical and electrical equipment
installation in station and ancillaries
• Systems contractor has commenced installation of
communications and signaling equipment
2020
Current Progress
Mezzanine Level Service Carrier Steel Framing Installation
MTA Capital Construction
21MTA Capital Construction
21
Current Progress
Main station (mezzanine level) – floor tile installation
22
Current Progress
22
Ancillary#2 NW corner 72nd Street
MTA Capital Construction
2323
Current Progress
Ancillary#1 NW corner 69th Street
MTA Capital Construction
24
Current Progress
24
Entrance 3 (southeast corner of 72nd Street and Second Avenue) at street level
MTA Capital Construction
2525
Current Progress
Entrance 1 (northeast corner of 69th Street and Second Avenue)
2626MTA Capital Construction
Three-Month Look AheadMain Station Cavern:
• Service carrier, mechanical, electrical and plumbing systems
installation, including: wall tiles, floor tiles, ceiling panels,
conduits and duct work at mezzanine level
• Installation of service carrier and ceiling panels at the platform
level
• Installation of escalators and elevators from mezzanine to
platform level
• Cable pulling through finished conduits continuing
• Continued track work in station area
2727
Three-Month Look AheadEntrance 1:
• Installation of concrete lining for the underground portion of the
entrance escalator incline
•Conduit work to start after concrete lining
•Continue work for entrance structure at street level and
installation of street level escalator
Ancillary 1, Ancillary 2, Entrance 3
•Construction of Ancillary 1 and Entrance 3 structures
•Concrete pumping at Ancillary 1 and Entrance 3
•Equipment delivery and installation at Ancillary 1, Ancillary 2 and
Entrance 3
•Electrical and mechanical equipment installation at Ancillaries 1
and 2
•Façade installation at Ancillaries 1 and 2
2828
Three-Month Look Ahead
Miscellaneous
• Concrete truck staging as needed between 74th and 75th
Streets
• Use of access hatches at Ancillary 1 and Ancillary 2 to deliver
materials to the station
• Sidewalk restoration work to commence
MTA Capital Construction
2929
3030
3131
32
33
Ancillary 2 Ancillary 1
Entrance 1
(Inside)
Ancillary 2
86th Street Station
2nd Avenue
Finishes, Entrances, Ancillaries, and MEP Systems Contract
Percent Complete : 87.35%
Contract Value: $223,000,000
Award Date: June 12, 2013
Forecast Completion: October 2016
84th 85th 86th 87th
Entrance 2
(outside)
83rd
3434
• The structural frame for the elevator at East 86th Street
has been installed
• A total of ten of the thirteen escalators have been installed
in the station
86th Street Station Milestones
3535Installation of wall panels and flooring tiles
3636
Fan is for temporary
ventilation purposes.
Rail stored for future installation
Installation of escalators
Installation of escalators at entrance 2 (north side of
86th Street) and architectural ceiling
3737
Three Month Look Ahead86th Street Station Area
East 78th to East 79th Streets – (Center of Second Avenue)
The center work zone on Second Avenue between 78th and 79 Street will
be maintained to pour concrete for tracks in the underground tunnels
East 82nd to East 85th Streets
• Water main replacement work will continue on the west side of Second
Avenue between 83rd and 84th Streets
• Sidewalk restoration on the west side of Second Avenue between 82nd and
84th Streets is ongoing.
• Construction of the Ancillary 1 building (northwest corner of 83rd Street) has
reached full height. Above ground work will continue, including installation
of building finishes
East 86th Street to East 87th Streets
• Construction of the Ancillary 2 building on the northwest corner of 86th Street
will reach street level in the spring
• The contractor continues to receive deliveries of equipment at the Ancillary 2
location (northwest corner of 86th Street) and the 87th Street access shaft
3838
East 86th Street to East 87th Streets (continued)
• Work zones currently on the east side of Second Avenue
between East 85th and East 87th will move to the west side in
early summer
East 86th Street between 1st and 2nd Avenues
• The structural frame for the elevator at East 86th Street has
been installed
• Traffic lanes have been reduced to two eastbound lanes and
one westbound bound lane
Three Months Construction Look Ahead
3939
Three Month Look Ahead86th Street Station Area
Underground Construction
• Installation of concrete masonry walls at the platform, mezzanine, and upper
mezzanine levels
• Installation of architectural finishes: wall panels, floor tile, acoustic panels, and
service carriers on the platform and mezzanine levels continues
• Installation of HVAC ductwork, insulation, chillers, transformers, and control
panels at all levels
• Installation of electrical conduit at all levels of the station and entrances.
40
Elevator entrance at East 86th Street
41
86th Street Entrance 1 Rendering83rd Street and Second Avenue
4242
Rendering of 86th Street Station Art InstallationArtist – Chuck Close, MTA Arts and Design commissioned work
Portraits in mosaic and tile representing NYC cultural figures & family
43
96th Street Station
Finishes, MEP Systems, Ancillary Buildings
and Entrances Contract
Percent Complete: 90.8%
Contract Value: $324,600,000
Award Date: June 22, 2012
Forecast Completion: October 2016
4444
96th Street Station Progress
Contract C2B is 90.8% complete
• Utility work continues on the west side of
Second Avenue.
• Road base pouring has started on blocks
where utility work is complete
• Installation of wall tiles, ceiling panels at
platform and mezzanine level
• Facility power equipment turned over to Con
Edison. Permanent power expected in
February
• Customer service booth on mezzanine and
dispatcher booth on platform levels nearing
completion
Elevator installation between
platform and mezzanine
45
Ruppert Park completed sidewalk
West side of Second Avenue 90th – 91st Street
4646
Curb pour and preparation for sidewalk and road base
Southwest corner 92nd Street & Second Avenue
4747
Ancillary 1 sample cladding
Northeast corner 93rd Street & Second Avenue
4848
North customer service booth (token booth)
Entrance 3 mezzanine level, 96th Street & Second Avenue
4949
Mezzanine wall tile mockup
5050
Track wall mockup
5151
Crossover tracks
92nd Street & Second Avenue
5252
Entrance 3 escalators
96th Street & Second Avenue
5353
Three-Month Look Ahead
• Completion of surface utility work on west side of Second
Avenue between 91st Street and 99th Street
• Continue pouring road base and begin asphalt pouring
on west side of Second Avenue
• Completion of west side sidewalk restorations between
90th and 104th Streets
• Shift to the east side of Second Avenue. Commencement
of sidewalk restoration from 91st to 102nd Streets
• Installation of wall tiles, ceiling panels at platform and
mezzanine level.
54
96th Street Entrance 3 rendering
SW corner 96th St and Second Avenue
5555
Rendering of 96th Street Station proposed art installationArtist – Sarah Sze, MTA Arts and Design
56
Systems Installation
• Traction Power work ongoing for three
substations and four circuit breaker houses
• Traction Power Substation installation
at 72nd St. Station nearing completion
• Pulling of Traction Power Feeder
cables is ongoing
• Low Vibration Track (LVT) System
Being Installed
− Track to be installed: 22,000 ft.
− Track installed to date: 15,155 ft.
(concreted to date)
− Aluminum 3rd rail installed: 13,500 ft.
− 96th St. Station Interlocking and 72nd St.
Station South Interlocking are complete.
72nd St. North interlocking scheduled to
be completed 1/26/16.
Note: Track as reported here consists of 2
rails and includes Special Work Portions
Installation of Special Work Portion complete at
96th St.
5757
Systems Installation
Track, Power, Signals and Communications
Systems Contract
Percent Complete: 73.9%
Contract Value incl. AWOs: $282.8 M
Award Date: January 18, 2012
Forecast Completion: October 2016
• Signal equipment being installed in relay
rooms and central instrumentation room.
Wayside equipment installation 95%
complete.
• Contractor 95% complete pulling fiber
optic and copper cables at 63rd and 72nd
Street Stations. Work ongoing at 86th
and 96th Street Stations.
• Installation of all communication room
equipment and wiring ongoing at 72nd,
86th and 96th Street Stations.
• Installation of inter-station
communication cables completed
between 86th Street and 105th Street.
96th St. Traction Power Substation Equipment
Installation ongoing.