SE Joint Firelink and FiReControl Project

SE Joint Firelink and FiReControl Project. CFO Martin Burrell FiReControl and Firelink Project Director CFO Martin Burrell FiReControl and Firelink Project

Embed Size (px)

Citation preview

Page 1: SE Joint Firelink and FiReControl Project. CFO Martin Burrell FiReControl and Firelink Project Director CFO Martin Burrell FiReControl and Firelink Project

SE Joint Firelink and FiReControl Project

Page 2: SE Joint Firelink and FiReControl Project. CFO Martin Burrell FiReControl and Firelink Project Director CFO Martin Burrell FiReControl and Firelink Project

CFO Martin Burrell

FiReControl and Firelink Project Director

CFO Martin Burrell

FiReControl and Firelink Project Director

Page 3: SE Joint Firelink and FiReControl Project. CFO Martin Burrell FiReControl and Firelink Project Director CFO Martin Burrell FiReControl and Firelink Project

Objectives

General update on the Firelink and FiReControl projects

Introduce the papers submitted separately

Advise of forthcoming regional decisions

General update on the Firelink and FiReControl projects

Introduce the papers submitted separately

Advise of forthcoming regional decisions

Page 4: SE Joint Firelink and FiReControl Project. CFO Martin Burrell FiReControl and Firelink Project Director CFO Martin Burrell FiReControl and Firelink Project

Firelink Airwave – Macquarie ( New owners ) implement change of Airwave

management team.

Firelink schedule

Confusion over call off items functionality and use for Regional control (Pump Bay Voice Terminals). May delay Statement Of Brigade Requirements. (SOBR)

Take up of early Mobile Data Terminals may affect schedule as these are due to be fitted at Phase B of Firelink

IDDS – will now be Quality Audited by Mason Communications. A marked improvement is expected. Currently no SE IDDS signed off.

Airwave – Macquarie ( New owners ) implement change of Airwave management team.

Firelink schedule

Confusion over call off items functionality and use for Regional control (Pump Bay Voice Terminals). May delay Statement Of Brigade Requirements. (SOBR)

Take up of early Mobile Data Terminals may affect schedule as these are due to be fitted at Phase B of Firelink

IDDS – will now be Quality Audited by Mason Communications. A marked improvement is expected. Currently no SE IDDS signed off.

Page 5: SE Joint Firelink and FiReControl Project. CFO Martin Burrell FiReControl and Firelink Project Director CFO Martin Burrell FiReControl and Firelink Project

Costs

Multimillion pound budget for interim solution. Taskforce meetings in FRS’s starting 1st October.

PBVT costs could double to meet FiReControl requirements. (Request To Talk function must be added)

On going concerns over cost of call off contract

Costs

Multimillion pound budget for interim solution. Taskforce meetings in FRS’s starting 1st October.

PBVT costs could double to meet FiReControl requirements. (Request To Talk function must be added)

On going concerns over cost of call off contract

Firelink

Page 6: SE Joint Firelink and FiReControl Project. CFO Martin Burrell FiReControl and Firelink Project Director CFO Martin Burrell FiReControl and Firelink Project

FiReControlFiReControl

Page 8: SE Joint Firelink and FiReControl Project. CFO Martin Burrell FiReControl and Firelink Project Director CFO Martin Burrell FiReControl and Firelink Project

Accommodation Practical completion/lease due 14th May 07

Early occupation an option, but other considerations (business rates, H&S)

Facilities management & other decisions needed from the region if the LACC is not making decisions by early December 2007.

Facilities Management (by early December);

Utilities, early occupation; etc (April/May 08)

High quality building

Security checks on all staff and Board Members – 3 month process

Practical completion/lease due 14th May 07

Early occupation an option, but other considerations (business rates, H&S)

Facilities management & other decisions needed from the region if the LACC is not making decisions by early December 2007.

Facilities Management (by early December);

Utilities, early occupation; etc (April/May 08)

High quality building

Security checks on all staff and Board Members – 3 month process

Page 9: SE Joint Firelink and FiReControl Project. CFO Martin Burrell FiReControl and Firelink Project Director CFO Martin Burrell FiReControl and Firelink Project

Business Case

There is to be a review of Assumptions – led by Finance Working Group

Bottom Line more important than principles and discussion

Current operating costs being requested through Finance Working Group

Needs to take account of costs of “out-of-scope” and “in-scope, in-FRS”, I.e. costs that will remain with FRS after cutover

Benefits management – ongoing cost reporting (again through FFWG)

There is to be a review of Assumptions – led by Finance Working Group

Bottom Line more important than principles and discussion

Current operating costs being requested through Finance Working Group

Needs to take account of costs of “out-of-scope” and “in-scope, in-FRS”, I.e. costs that will remain with FRS after cutover

Benefits management – ongoing cost reporting (again through FFWG)

Page 10: SE Joint Firelink and FiReControl Project. CFO Martin Burrell FiReControl and Firelink Project Director CFO Martin Burrell FiReControl and Firelink Project

Implementation Funding New burdens process gradually being understood – not a bid or a claims

process, but CLG submits estimates

Some finance has been confirmed in Circulars

Some held back “depending on Checkpoint 1 and Resource Plan”

May shortly have to do rapid response on 3-year budget needs

Grant structure all altered – future funding may be RSG (resisted by FFWG as not flowing), or ring-fenced, or passed to Region to disburse to FRSs

New burdens process gradually being understood – not a bid or a claims process, but CLG submits estimates

Some finance has been confirmed in Circulars

Some held back “depending on Checkpoint 1 and Resource Plan”

May shortly have to do rapid response on 3-year budget needs

Grant structure all altered – future funding may be RSG (resisted by FFWG as not flowing), or ring-fenced, or passed to Region to disburse to FRSs

Page 11: SE Joint Firelink and FiReControl Project. CFO Martin Burrell FiReControl and Firelink Project Director CFO Martin Burrell FiReControl and Firelink Project

Transition Planning Transition plans being developed;

Transition Governance letter from Peter Betts requesting CFOs to sign off prioritisation of FiReControl and readiness of internal FRS project structures

Checkpoints and Gates to be signed off by CFO/PO. Some information still awaited from EADS and CLG

Some S31 funding now, more depending on progress

Major risks: data/IT systems; Convergence (information from EADS/CLG delayed)

EADS:

Not where they would wish to be, but confident in achieving Oct 09 cutover

Transition plans being developed;

Transition Governance letter from Peter Betts requesting CFOs to sign off prioritisation of FiReControl and readiness of internal FRS project structures

Checkpoints and Gates to be signed off by CFO/PO. Some information still awaited from EADS and CLG

Some S31 funding now, more depending on progress

Major risks: data/IT systems; Convergence (information from EADS/CLG delayed)

EADS:

Not where they would wish to be, but confident in achieving Oct 09 cutover

Page 12: SE Joint Firelink and FiReControl Project. CFO Martin Burrell FiReControl and Firelink Project Director CFO Martin Burrell FiReControl and Firelink Project

General LACC

Shadow company incorporated 14th Aug 2007. Registered Number 632450

First board meeting to be set up – 1st week November?

Insurance

SLAs

HR policies being drafted for decision by LACC early 2008

Shift patterns

Staffing numbers

Staff selection measures

Terms and conditions

LACC

Shadow company incorporated 14th Aug 2007. Registered Number 632450

First board meeting to be set up – 1st week November?

Insurance

SLAs

HR policies being drafted for decision by LACC early 2008

Shift patterns

Staffing numbers

Staff selection measures

Terms and conditions

Page 13: SE Joint Firelink and FiReControl Project. CFO Martin Burrell FiReControl and Firelink Project Director CFO Martin Burrell FiReControl and Firelink Project

Decisions required by Regional Management Board

1. South East Fire and Rescue Company LTD

Formulation of LACC

Agree Members’ Agreement, Memorandum and Articles of Assoc.

2. Cost Apportionment

1. South East Fire and Rescue Company LTD

Formulation of LACC

Agree Members’ Agreement, Memorandum and Articles of Assoc.

2. Cost Apportionment

Page 14: SE Joint Firelink and FiReControl Project. CFO Martin Burrell FiReControl and Firelink Project Director CFO Martin Burrell FiReControl and Firelink Project

Decisions required by Regional Management Board

HR

1. TUPE - FRSs or LACC to make redundancies?

2. RCCD recruitment – Panel interview RMB representation 19.11.07

Financial and Legal Support

1. Recruit Regional Treasurer + buy in specialist advice as and when required via Diane Henshaw

HR

1. TUPE - FRSs or LACC to make redundancies?

2. RCCD recruitment – Panel interview RMB representation 19.11.07

Financial and Legal Support

1. Recruit Regional Treasurer + buy in specialist advice as and when required via Diane Henshaw

Page 15: SE Joint Firelink and FiReControl Project. CFO Martin Burrell FiReControl and Firelink Project Director CFO Martin Burrell FiReControl and Firelink Project