Update for the
1998 Trinity Bond Program
March 2015
Overview
2
Trinity River Corridor Project addresses regional
concerns but flood risk reduction is the cornerstone.
Five inter-related components of which flood control
is primary
• Flood Control
• Ecosystem Restoration
• Transportation
• Recreation
• Economic Development
Implementation leads to the unification and
sustainability of Dallas
Trinity River Corridor Geographic Areas
3
Status of the individual project components of the BVP
4
Trinity Fields/Elm Fork Greenbelt
Original Component Current Component Status
Elm Fork Levee (with Corps)
Elm Fork Drainage Improvements (without Corps)
Held in case needed for levee repairs; Recommendations to Council Spring 2015
Not Included MoneyGram (Elm Fork) Soccer Complex
Complete
Not Included
Elm Fork Greenbelt Master Plan
Completes Spring 2015
Not Included California Crossing Canoe Launch
Complete
5
Trinity Forest Original Component Current Component Status
Santa Fe Trestle Trail Santa Fe Trestle Trail Complete
Moore Park Moore Park Complete
Boat Ramp at Sylvan & Loop 12
Boat Ramp at Sylvan & Loop 12
Complete
Nature Center Audubon Center Complete
Horse Park Texas Horse Park Complete
MLK Gateway MLK Gateway/Cedar Crest Bridge
Substantially Complete
Rochester Gateway William Blair Jr. Gateway Complete
6
Trinity Forest Original Component Current Component Status
I-20 Gateway Great Trinity Forest Gateway and Horse Trails
Complete
Loop 12 Gateway Loop 12 Gateway at Lower Chain of Wetlands
Open to Public; More improvements to be completed Spring 2015
Trinity Trails (Phase I & 2) Buckeye Trail; Trinity Forest Trails (Phase I & 2)
Complete; Phase 3/AT&T Substantially Complete; Phase 4 Joppa Connection Completes late Spring 2015
Not Included Trinity Golf Course Under Construction
Not Included South Central/Joppa Gateway Park
Under Construction
7
Trinity Planning Original Component Current Component Status
Master Implementation Plan Master Implementation Plan Complete
Not Included
Trinity Comprehensive Land Use Plan
Complete
Not Included
Balanced Vision Plan Complete
Not Included
Schematic Design of BVP, including design guidelines for Trinity Parkway
Complete
8
Flood Control Original Component Current Component Status
Chain of Wetlands 1. Lower Chain 2. Upper Chain
1. Complete 2. Under Construction
Lamar Levee Lamar Levee 35% design complete; No federal funding
Cadillac Heights Levee Cadillac Heights Levee No Federal Funding
Not Included Buyout of Cadillac Heights residential properties
Phase 1 - 95% Complete; Phase 2 - 50% Complete
First 33 Acre Lake in a Chain of Lakes (Eastside, Off Channel)
Phase I Lakes – 23 Acres (near Commerce) and 20 Acres West Dallas Lake (near Westmoreland)
Construction begins Spring 2015 pending EIS complete
9
14.5 ac. 8.5 ac.
Potential connecting
channels
Flood Control Original Component Current Component Status
Not Included Pavaho Pump Station Complete
Not Included Baker Pump Station Substantially Complete
Not Included Able Pump Station Under Construction
Not Included 100-Year Levee Fixes Complete
Not Included Hampton, Charlie, Trinity Portland Pump Stations & Delta (rehab)
35% Design Complete; Future Funding Required
10
Transportation Original Component Current Component Status
Woodall Rodgers Bridge Margaret Hunt Hill Bridge Complete
Beckley/Commerce Intersection
Beckley/Commerce Intersection
Construction begins Spring 2015
Split Trinity Parkway as a Toll Toad
1. Combined Trinity Parkway as Toll Road
2. SM Wright/ Trinity Phase I
1. Pending EIS and Funding 2. Awarded for
Construction (SM Wright)
Not Included Sylvan Bridge replacement Substantial Completion
Not Included
I30/I35 Bridges – Margaret McDermott Bridge
Under Construction
11
Transportation Original Component Current Component Status
Not Included South Lamar Award Construction Spring 2015
Not Included Riverfront Phase I/ Continental
Under Construction
Not Included Riverfront Phase II Under Design
Not Included Cadiz Under Construction
Not Included Canada Drive from Westmoreland to Hampton
Under Design
Not Included Morris Street Under Construction
12
Other Added Elements Original Component
Current Component Status
Not Included Standing Wave Open – awaiting study of adjustments
Not Included Pavaho Wetlands Construction completes Spring 2015
Not Included Commerce Overlook Complete
Not Included Trinity Skyline Trail Phase I Completed; Phase 2 Under Design; Phase 3 funding recently approved through TAPS grants (Sylvan to Irving)
Not Included Continental Bridge and West Dallas Gateway
Complete
13
Other Added Elements Original Component
Current Component Status
Not Included Bellview Connector Feasibility Study Complete
Not Included Big Spring Historic Designation and Conservation Planning Underway
Not Included Undergrounding of Oncor’s 345 KVA line
Complete
Not Included Trinity Strand Trail Phase I Complete; Phase II Funded
14
Funding (amount/expenditures)
• Total City Expenditures and Encumbrances
• % of all Trinity Related Bond Program Funds Expended or Encumbered
• Private Funding Donated to Date
$ 464.6 Million
84%
$60 Million
15
Activities/Involvement
• Number of Visitors to Continental Bridge/West Dallas Gateway (mid-June through end of 2014)
• Amount of tires removed from Trinity River
• # of Corporate/Private and Non-Profit Partners
• # of Volunteers for Cleanups (2014)
• Pumping Capacity Added
• Trails Added
72,250
Over 198 Tons
37
6,000
990K Gallons Per Minute
39.7 miles 16