Upload
madeleine-kelley
View
225
Download
0
Tags:
Embed Size (px)
Citation preview
Schematic Design of an Accelerated Bridge Construction ProjectMichael P. Culmo, P.E.
Vice President of Transportation and Structures
CME Associates, Inc., East Hartford, CT
Reference Manual
• Use the Connections Details Manual– Type study concept– Select details from various
states
Case Scenario
• 4 lane bridge over an expressway
• Existing bridge has deteriorated beyond repair
• Heavy traffic on both roadways
• There is a short but undesirable detour
Public Involvement
• Public hearing heldPublic hearing held
• Businesses do not want a long Businesses do not want a long construction process with stage construction process with stage constructionconstruction
• Businesses are not keen about a detourBusinesses are not keen about a detour
• They will accept a short term closure with They will accept a short term closure with the detourthe detour– As opposed to a long term staged projectAs opposed to a long term staged project
Design Approach Options
• Build a temporary bridge to speed up construction of the new bridge– $$$$– Not that fast
• Use multi-stage construction– Very long construction– Will require long term lane closures
• Establish the detour and accelerate the bridge construction to less than 30 days
Existing Bridge
Deck Joints
Low Clearance
Existing bridge issues
Proposed Bridge Type
• After a formal type study, the owner opted with the following structure criteria– Use NEXT Beams to accelerate construction
• Design as simple span for Dead Load and continuous spans for Live Load
– Increase clearance by raising approach grades (3’)– Use integral abutments (no deck joints)– Composite concrete deck– Membrane waterproofing and Bituminous wearing
surface– Use Precast Rail System
• (Vermont/NH system)
Substructures
• Push abutments back to top of slopePush abutments back to top of slope– Minimize wingwall requirementsMinimize wingwall requirements– Use integral abutments with flying wingsUse integral abutments with flying wings– Eliminate spray attack on abutmentsEliminate spray attack on abutments
• Place abutments in a different footprint than the Place abutments in a different footprint than the existingexisting– facilitates constructionfacilitates construction
• Use open frame pier bent on spread footingsUse open frame pier bent on spread footings
Proposed Bridge
Move abutment away from
roadway
No Deck joints Increase vertical clearance
Bridge Section
Beam Design
• Preliminary Beam Sizing– Use PCI NEXT
Beam Standards
Beam Design
• LLDF
Beam Design
• AASHTO LL Distribution Factor – Type K
Moment
Shear
Beam Design
• AASHTO LLDF
Type H
Moment
Shear
Beam Design
Structure Type H K
LLDF
Moment
0.96 0.752
LLDF
Shear
1.17 0.938
How to select details
FHWA manual “Connection details for prefabricated bridge elements and systems”
1. Review Chapter 1• Investigate connection types, materials,
tolerances
2. Search applicable sections of other chapters for details
Section 1.4 Typical Connection Types
• After reviewing chapter 1, the owner chose the following connection types– Grouted reinforcing splice couplers
• Quick, proven system• Can develop full bar strength• Simplifies the design process (similar to CIP)
– Grouted Voids• Easy for simple connections
– Concrete Closure pours between precast elements• Use for a limited number of connections (slower)
Grouted Reinforcing Splice Connectors
• Emulates a reinforcing steel lap splice
• Multiple companies – non-proprietary
• Used in precast parking garages and stadiums and bridges
Grouted Reinforcing Splice Connectors
• Emulates a reinforcing steel lap splice
• Multiple companies – non-proprietary
• Used in precast parking garages and stadiums and bridges
• Time Lapse Video on YoutubeTM – Search “Georgia Pier
Construction”• Installation Video on YoutubeTM
Search “Georgia Pier Construction”Installation video
Footing to Sub-grade Connection
Footing Details
Footing to Column Connection
Footing to Column Connection
Column to Cap Connection
Column to Cap Connection
Completed Pier
Footing to subgrade
connection
Column to footing
connection
Column to cap
connection
Abutment Details
• Integral Abutment to precast piles– Section 3.2.3.1 Precast Integral Abutment to
Piles
• Detail developed by Maine DOT– Used on three different bridges
Abutment to Pile Connection
Abutment to Pile Connection
Abutment To Wingwall Connection
Abutment To Wingwall Connection
Approach Slab Connection
Completed Abutment
Pile to cap connection
Approach slab connection
Flying Wingwall
connection
Abutment cap connection
Deck Design with Next Beam
• Design as a conventional cast in place deck– Use max stem spacing for design (5.0 feet)– Design overhang from outside stem (2.53 feet)
Parapet Connection
Parapet Connection
Superstructure to Integral Abutment Connection
Use a similar detail at the pier
Completed Bridge
Precast Integral Abutment
Composite Deck Membrane
waterproofing with bit.
Wearing surface
Precast Pier
Precast Parapet
Final Bridge
Estimated Construction Schedule
Costs
• Typical New Bridge (Cost=$200/sf) = $1,920,000
• Premium for ABC (assume 20%) = $384,000
• Temporary Bridge (Cost=$60/sf) = ($576,000)
Net Savings = $192,000
Note: These prices will vary by region
• Ways to reduce bid prices with ABC• Standardization• Programmatic (not one of a kind)• Reduced project site costs (trailers, etc.)• Reduced Maintenance of Traffic Costs• Inflation
• Other Non- Bid Savings with ABC• Fewer Police Details• Reduced Resident Engineering time
• User Costs• Plus: $$ Can be significant• Minus: $$ Not in the budget
Other Cost Savings
Quality
• Florida has had very good success with precast piers in very harsh environments
• Precast concrete beams require no maintenance
• Integral abutments eliminate deck joints
Old Adage
By elimination of temporary bridges or costly By elimination of temporary bridges or costly stage construction schemes, stage construction schemes,
you you CANCAN have all three have all three
Rapid Rapid ConstructionConstruction
High QualityHigh Quality
Low CostLow Cost
You can only You can only have any twohave any two
Conclusions• It is possible to build a complete bridge in 30
days (or less)• The FHWA manual provides a starting point for
a complete bridge prefabrication project• You do not need to sacrifice quality to get rapid
construction• You can save money on an accelerated bridge
project by:– Reducing construction time– Eliminate temporary bridges or staging