SCHEDULE POWER SHUTDOWN & POWER ENERGIZE
MESSRS : PT. TSUCHIYAPROJECT NAME : TSUCHIYA NEW FACTORY PROJECTWORK : POWER SHUTDOWN AT TSUCHIYA PROJECT
NO WORK DESCRIPTION OKTOBER - NOVEMBER - DESEMBER 2013
28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 41 PREPARATION
2 WIRING CABLE 20kV FROM EXISTING TO NEW ELECTRICAL ROOM
3 INCOMING TRAFO, PANEL MVMDB & LVMDB
4 SETTING TRAFO, PANEL MVMDB & LVMDB
5 WIRING CABLE 20kV FROM TRAFO TO INCOMING PANEL MVMDB
6 INSTAL SUPPORT & INSTAL CABLE RACK UILITY AREA
7 WIRING CABLE FROM PANEL LVMDB TO PANEL DISTRIBUTION
8 CEK FROM ANDALAN (STANDAR LAYAK OPERATIONAL ATAU SLO) Get Certificate
9 POWER SHUT DOWN MVMDB EXISTING
10 POWER SHUT DOWN SUBTATION CIKARANG LISTRINDO
11 TERMINATION CABLE 20Kv (RAYCHEM) - NEW & EXISTING ELECTRICAL ROOM
12 FINISHING AND CLEANING AREA ELECTRICAL ROOM NEW & EXISTING
13 POWER ENERGIZE
14
15
16
17
18
19
20
21
PREPARED BY :
INDONESIA ENGINEERING
( TEUKU BACHTIAR )
SCHEDULE POWER SHUTDOWN & POWER ENERGIZE
OKTOBER - NOVEMBER - DESEMBER 2013 REMARKS5 6 7 8 9 10 11 12 13 14 15
Standby Power
APPROVED BY :
( JULIANA WAGYU )