Schedule Conventional Bathroom
Citation preview
ID Task Mode Task Name Duration Start Finish Predecessors
1 Pekerjaan Kamar Mandi Konvensional
0 days
2 Rough Work 9 days Thu 10/15/15 Tue 10/27/15
3 Carpentry 2 days Thu 10/15/15 Fri 10/16/15
4 Plumbing 2 days Mon 10/19/15Tue 10/20/15 3
5 Electrical 1 day Wed 10/21/15Wed 10/21/154
6 Insulation 5 days Wed 10/21/15Tue 10/27/15 4
7
8 Drywall & Tilework 3 days Wed 10/28/15Fri 10/30/15
9 Hang Drywall 1 day Wed 10/28/15Wed 10/28/156
10 Cabinetry 1 day Wed 10/28/15Wed 10/28/159SS
11 Flooring 2 days Thu 10/29/15 Fri 10/30/15 10
12 1st Waterproof coating 1 day Thu 10/29/15 Thu 10/29/15 9
13 2nd Waterproof coating
1 day Fri 10/30/15 Fri 10/30/15 12
14 Waterproof test 1 day Fri 10/30/15 Fri 10/30/15 12
15
16 Miscellaneous 1 day Tue 11/3/15 Tue 11/3/15
17 Fitures 1 day Tue 11/3/15 Tue 11/3/15 14FS+1 day
10/15W T F S S M T W T F S S M T W T F S S M T W T
Oct 11, '15 Oct 18, '15 Oct 25, '15 Nov 1, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: Schedulle Conventiona
Date: Thu 10/15/15