Schedulle Conventional Bathroom

Embed Size (px)

DESCRIPTION

Schedule Conventional Bathroom

Citation preview

  • ID Task Mode Task Name Duration Start Finish Predecessors

    1 Pekerjaan Kamar Mandi Konvensional

    0 days

    2 Rough Work 9 days Thu 10/15/15 Tue 10/27/15

    3 Carpentry 2 days Thu 10/15/15 Fri 10/16/15

    4 Plumbing 2 days Mon 10/19/15Tue 10/20/15 3

    5 Electrical 1 day Wed 10/21/15Wed 10/21/154

    6 Insulation 5 days Wed 10/21/15Tue 10/27/15 4

    7

    8 Drywall & Tilework 3 days Wed 10/28/15Fri 10/30/15

    9 Hang Drywall 1 day Wed 10/28/15Wed 10/28/156

    10 Cabinetry 1 day Wed 10/28/15Wed 10/28/159SS

    11 Flooring 2 days Thu 10/29/15 Fri 10/30/15 10

    12 1st Waterproof coating 1 day Thu 10/29/15 Thu 10/29/15 9

    13 2nd Waterproof coating

    1 day Fri 10/30/15 Fri 10/30/15 12

    14 Waterproof test 1 day Fri 10/30/15 Fri 10/30/15 12

    15

    16 Miscellaneous 1 day Tue 11/3/15 Tue 11/3/15

    17 Fitures 1 day Tue 11/3/15 Tue 11/3/15 14FS+1 day

    10/15W T F S S M T W T F S S M T W T F S S M T W T

    Oct 11, '15 Oct 18, '15 Oct 25, '15 Nov 1, '15

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 1

    Project: Schedulle Conventiona

    Date: Thu 10/15/15