SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC OVERVIEW OF THE NEW REACTORS BUSINESS LINE (Public Meeting) Purpose: The purpose of the briefing is to provide the Commission with a discussion of strategic considerations associated with the New Reactor Business Line. Scheduled: Duration: Location: Participants: NRC Staff October 20, 2016 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, Executive Director for Operations Vanna L. Ordaz, Deputy Director, Office of New Reactors Frank Akstulewicz, Director Division of New Reactor Licensing John Monninger, Director, Division of Safety Systems and Risk Assessment Laura Dudes, Deputy Regional Administrator for Construction, Region II Michael Cheak, Director, Division of Construction Inspection & Operational Programs Topics: Large Light Water and Small Modular Reactor Licensing o Goals, challenges, strategies, projections, and trends Advanced Reactor Licensing o Goals, challenges, and strategies Construction oversight o Goals, challenges, strategies, and transition to operations ITAAC o Uncompleted ITAAC Pilot Vendor inspections o Goals, challenges, and strategies International Cooperation Project Aim Implementation Presentation 60 mins.* 1

SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

SCHEDULING·NOTE

Title: STRATEGIC PROGRAMMATIC OVERVIEW OF THE NEW REACTORS BUSINESS LINE (Public Meeting)

Purpose: The purpose of the briefing is to provide the Commission with a discussion of strategic considerations associated with the New Reactor Business Line.

Scheduled:

Duration:

Location:

Participants:

NRC Staff

October 20, 2016 9:30 a.m.

2 hours

Commissioners' Conference Room, 1st fl OWFN

Victor Mccree, Executive Director for Operations Vanna L. Ordaz, Deputy Director, Office of New Reactors Frank Akstulewicz, Director Division of New Reactor Licensing John Monninger, Director, Division of Safety Systems and Risk

Assessment

Laura Dudes, Deputy Regional Administrator for Construction, Region II

Michael Cheak, Director, Division of Construction Inspection & Operational Programs

Topics:

• Large Light Water and Small Modular Reactor Licensing o Goals, challenges, strategies, projections, and trends

• Advanced Reactor Licensing o Goals, challenges, and strategies

• Construction oversight o Goals, challenges, strategies, and transition to operations

• ITAAC o Uncompleted IT AAC Pilot

• Vendor inspections o Goals, challenges, and strategies

• International Cooperation • Project Aim Implementation

Presentation

60 mins.*

1

Page 2: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Commission Q & A

Discussion ~ Wrap-Up

*For presentation only and does not include time for Commission Q & A's

30 mins.

5 mins.

2

Page 3: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

U.S.NRC United States uclear Regulatory Commission

Protecting People and the Environment

New Reactors Business Line Commission Briefing

October 20, 2016 Victor Mccree

Executive Director for Operations

Page 4: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

L_ __

U.S.NRC U ni ted States Nuclea r Regul ato ry C ommission

Protecting People and the Environment

Overview of the New Reactor Program

Vonna Ordaz Deputy Director

Office of New Reactors

2

_ _I

Page 5: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

' : .

I .

Agenda

• Large Light Water Reactor & Small Modular Reactor Licensing

· • Technical Review Effectiveness

• Construction Oversight

. -• ITAAC

• Vendor Inspection Program

• Transition to Operations

• Advanced Reactor Regulation

3

Page 6: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

.. ..

; .

Effectively Managing Substantial Workload

• Emphasizing more effective, · · . efficient, safety-focused reviews

• Ensuring safe construction

• Incorporating lessons learned and demonstrating efficiencies

• Focusing on qual,ity and accountability

4

Page 7: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Enhancing Readiness for Future Work

• Ensuring readiness to review new technologies

• Implementing innovative approaches

• Aligning resources with workload .

5

Page 8: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

l

/ U.S.NRC United States Nuclea r Regu latory Commission

Protecting People and the Environment

Large Light Water Reactor & Small Modular Reactor

Licensing

Frank Akstulewicz, Director

Division of New Reactor Licensing Office of New Reactors

6

Page 9: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Effectively Delivering on the Mission (1/3)

Completed • 32 licensing actions for Vogtle and

V .C. Summer units • Mandatory hearings

for Levy and Lee COL applications

• Safety revievv for the Turkey Point COL application -- .

"An elevated view of the entire Vogtle 3 and 4 construction site." Photo courtesy of Georgia Power Company

7

Page 10: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Effectively Delivering on the Mission (2/3)

Issued • ESP to PSEG • COLs for South

Texas Project Units 3 & 4

• Milestone schedule letter to GEH for ABWR DC rene~al application

"South Texas Project Units 3 & 4" Photo courtesy of nuclearstreet.com

8

Page 11: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Effectively Delivering on the Mission (3/3)

• Completed the North Anna COL application safety revievv 3 months ahead of schedule

• Employing a staggered Phase 2 revievv of APR-1400 DC application to maintain 42-month revievv schedule

"North Anna Power Station Unit 3" Photo courtesy of Dominion

9

Page 12: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Employing Lessons Learned to SMR Licensing Work

• Addressed Regulatory Gap • issues

• Issued readiness assessment for NuScale DC application

• Completed acceptance revievv of Tennessee Valley Authority's tendered ESP application

"NuScale Reactor Diagram" Photo courtesy of NuScale Power, LLC

10

Page 13: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Emphasizing Agility Using Resources in FY 2017

• Challenge: Balancing resources in certain skill set areas

• Strategy: Effectively using rotations, details, and resource sharing with NRR

45 ii) 40 LU I-LL 35 -II) I-z 30 LU ...J

:; 25 :::> 20 CJ LU LU 15 ~ j:: 10 ...J ...J :::> 5 LL

0

LLWR and SMR Direct Licensing Review Resources for FY 2017 by Quarter

41

-- 38

34

-----------------------33 ___________________ _ .._ 31

32 31

Ql Q2 Q3 Q4

FY 2017 QUARTER

-FTE .

---- Baseline FTE (minus hearings)

11

Page 14: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Preparing for Licensing Work in FY 2017 and Beyond

• Reviewing increased number of licensing actions for the AP1000 design center

• Completing review of current applications

• Preparing for new COL., ESP, and DC applications

• Supporting international activities

12

Page 15: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

~u.S.NRC U ni ted rates uclea r Regul atory Co mmission

Protecting People and the Environment

Increasing Effectiveness and Efficiency of Technical

Reviews John Monninger, Director

Division of Safety Systems and Risk Assessment

Office of New Reactors

13

- J

Page 16: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Enhancing Execution of our Safety Mission

• Continuing to assess and apply lessons learned

• Standardizing practices and focusing efforts

• Benefiting from risk-informed approaches

14

Page 17: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Enhancing Licensing Review · Tools

• Issued job aids for audits, confirmatory analysis, and requests for additional information - Clarified the purpose of the tools

- Identified best practices and vvhat to avoid

15

Page 18: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Implementing Risk-Informed Approaches

• Capitalizing on the Standard Review Plan framework for SM Rs

• Developing the NuScale safety focused revi·ew approach - Integrated consideration of safety­

significance, defense-in-depth, risk insights, and safety margin

_:_ I

Page 19: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

, U.S.NRC Un ited States Nuclear Regulatory Commission

Protecting People and the Environment

Construction Oversight

Laura Dudes Deputy Regional Administrator,

Construction Region II

17

Page 20: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Effectively Meeting Challenges of the Dynamic Construction Environment (1/3)

Placement of the Auxiliary Building Module,

Vogtle Unit 4

Placement of the In-containment refueling water

storage module, VC Summer Unit 2

18

Page 21: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Effectively Meeting Challenges of the Dynamic Construction Environment (2/3)

Mechanical Module Receipt Inspection at Vogtle AP1000 Site

Chemical and volume control system pumps

19

Page 22: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Effectively Meeting Challenges of the Dynamic Construction Environment (3/3)

Q ... .Jl a. e 8

11

1

8

2

lanned lnspec ions and IC Completion with 5 affing Skill Se

Civil Engrnee-ring

Mechanical Engineering

Electrical Engineering

~r e-0p, start-up and operational testing

......- Inspection Completed

......-1crJ.s sub · ed

1009 2010 20U 2012 2.013 2014 2015 1016 2017 1018 2019 2010

= _g ... ::I .a 'i:: ... . ra c ... CJ Ill

20

Page 23: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Transition: Construction to Operations

• Organizational plan for the AP1000 transition

• Staff readiness for AP1000 operation - AP1000 reactor operations training - Resource agility during initial

operations - Watts Bar lessons learned

21

Page 24: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

:7 U.S.NRC U nited States Nuclear Regu latory Co mmission

Protecting People and the Environment

ITAAC, Vendor Inspection Program, &

Transition to Operations

Michael Cheok, Director Division of Construction Inspection

and Operational Programs Office of New Reactors

22

Page 25: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Successfully verifying IT AAC Closure Notifications (ICNs)

• 131 ICNs received, with 111 verified

• ICN submittals will • increase

• Closure notification submittals have been high quality

23

Page 26: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Ready for the IT AAC surge

• Issued Reg Guide 1.215 to facilitate quality ICN submittals

• NRC training on ICN verification

• Use of staff

experts to

4000

3000

... assist in i 2000

E := z

verification of 1000

ITAAC SURGE ·

0 _..-::;;.. __ _

complex IT AAC 2016 2017 2018 2019 2020

• Vogtle Cumulative Totals • VC Summer Cumulative Totals

24

Page 27: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Implementing Efficient Solutions

• Carried out a successful Uncompleted ITAAC Notification (UIN) pilot project

• Enhanced infrastructure to process UIN reviews

• Achieved greater efficiencies . with periodic, multiple-ICN Federal Register Notices

25

Page 28: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Vendor Inspection: Focusing on New Reactor Builds

• Majority of vendor inspections completed in FY2016 focused on ne\N reactor components

• Inspections targeted vendors supplying safety-significant components

26

Page 29: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Vendor Inspections are Enhancing Safety

• Maintaining technical focus on AP1000

~-

engineering and design verification

. • Closing out safety issues

• Continuing follow­up on AP1000 module fabrication

27

Page 30: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Sustained Focus on Vendor Oversight

• Continue our focus on commercial­grade dedication issues

• Continue vendor outreach

• Leveraging international partnerships

~~-i---~

28

Page 31: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Actively Preparing for Transition to Operations

• Making progress on 21 Readiness Issues

• Developing implementation plan

• Applying enhancements to the Reactor Oversight Process for new reactors

29

Page 32: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

:;; U.S.NRC United States uclear Regulatory Commission

Protecting People and the Environment

Advanced Reactor Regulation

Vonna Ordaz Deputy Director

Office of New Reactors

30

Page 33: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Increasing Emphasis on Advanced Reactors

• Industry engagement with NRC has increased

• Congressional interest remains high

• Staff aggressively working toward readiness for efficient and predictable reviews

31

Page 34: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Managing the Challenges to Advanced Reactor Readiness

• Maturity of designs - focusing on • common issues

• Clarity of schedule - effective communication

• Flexibility of regulatory review process - soliciting stakeholder feedback

32

Page 35: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Actions Focus on Readiness for Efficient Reviews

NRC Vision and Strategy: d Efficient Safely Achieving Effective an

L. ht Water Reactor Non- 19 Mission Readiness

• NRC Vision and Strategy - Three Pronged

Approach • Technical Readiness • Regulatory Readiness • Communications

Optimization

33

Page 36: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Efficient Reviews are Essential to Success

• Developing strategies and Implementation Action Plans

• Technical work on design criteria progressing

• Taking first steps to develop a licensing strategy

34

Page 37: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Communication and Coordination are Vital

• Excellent coordination with DOE

• Active communication with vendors and industry organizations

• International collaboration

35

Page 38: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Summary

· • Positively impacting safe construction

• Implementing innovative approaches to complete current licensing reviews

1 . ·• Enhancing readiness for new technologies

I

36

Page 39: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

r .. ' ;

Acronyms (1/2) • ABWR - Advanced Boiling Water

Reactor

• COL - combined license

• DOE - Department of Energy

• DC - design certification

• ESP - early site permit

I • • GEH - General Electric Hitachi

• ICN- ITAAC closure notification I : .

37

Page 40: SCHEDULING·NOTE Title: STRATEGIC PROGRAMMATIC … · 9:30 a.m. 2 hours Commissioners' Conference Room, 1st fl OWFN Victor Mccree, ... application safety revievv 3 months ahead of

Acronyms (2/2) '

• ITAAC - inspections, tests, analyses, and acceptance criteria ·

• LLWR - Large Light Water Reactor

• RAI - request for additional information

• NRR - Office of Nuclear Reactor Regul~tion

• PSEG - PSEG Power, LLC and

I · PSEG Nuclear, LLC

I • SMR - s·mall modular reactor I.