Upload
alice-goodwin
View
219
Download
0
Embed Size (px)
DESCRIPTION
Priority rules Select the order in which job will be processed First come first served (FCFS) – jobs are processed in the order which they arrive at a machine or work center Shortest processing time (SPD) – according to processing time, shortest job first Earliest due date (EDD) – according to due date, earliest due date first. Critical ratio (CR) – smallest ratio of time remaining until due date to processing time remaining.
Citation preview
SchedulingSeminar exercises
2010.10.14Process and Production
Management
Scheduling• Estabilishing the timing of the use of equipment,
facilities and human activities in an organization.– High volume systems (characterized by standardized
equipment and activities that provide identical or highly similar operations on products – autos, personnal computers, radios, TVs)
– Intermediate – volume systems (ouput fall between the standardized type of output of the high volume systems and made-to-order output of job shops. Work centers periodically shift from one product to another, but lot size relatively high.
– Low-volume systems (products are made to order, and orders differ in terms of processing requirements, materials needed, processing time.)
Priority rules• Select the order in which job will be processed• First come first served (FCFS) – jobs are
processed in the order which they arrive at a machine or work center
• Shortest processing time (SPD) – according to processing time, shortest job first
• Earliest due date (EDD) – according to due date, earliest due date first.
• Critical ratio (CR) – smallest ratio of time remaining until due date to processing time remaining.
Assumptions
• The set of jobs is known• Setup time is independent of processing
sequence• Setup time is deterministic• Process time are deterministic• There will be no interruptions in
processing such as machine breakdowns, accidents, or workes illness.
Example 1Job/
productProcessing time (days)
Due date
(days)A 2 7B 8 16C 4 4D 10 17E 5 15F 12 18
• Determine the sequence of jobs/products
• Determine average flow time
• Determine average tardiness
• Determine average number of jobs at the workcenter
• Job flow time – the length of time a job is at a particular workstation or work center. (it includes not only procesing time, but waiting time, transportation time)– Average flow time = total flow time /number of jobs
• Job lateness – length of time the job completion date is exceed the date the job was due to promised to the customer– Average tardiness=total lateness/number of products
• Makespan – is the total time needed to complete a group of jobs (time between start the first and completion of the last one)– Average number of jobs=total flow time/makespan (it
reflects the average work-in-process inventory if the jobs represent equal amount of inventory)
FCFSJob/
productProcessin time (days)
Due date (days)
(2)
Flow time(3)
Days tardy (0 if negative)(3)-(2)
A 2 7 2 2-7=-50B 8 16 2+8=10 10-16=-60C 4 4 10+4=14 14-4=10D 10 17 14+10=24 25-17=7E 5 15 24+5=29 29-15=14F 12 18 29+12=41 41-18=23
41 120 54
• Aft=120/6=20 days• At=54/6=9 days• M=41 Aj=120/41=2,93 pieces
ABCDEF
SPTJob/
productProcessin time (days)
Due date (days)
(2)
Flow time(3)
Days tardy (0 if negative)(3)-(2)
A 2 7 2 2-7=-50C 4 4 2+4=6 6-4=2E 5 15 5+6=11 11-15=-40B 8 16 11+8=19 19-16=3D 10 17 19+10=29 29-17=12F 12 18 29+12=41 41-18=23
41 108 40
• Aft=108/6=18 days• At=40/6=6,67 days• Aj=108/41=2,63 pieces
ACEBDF
EDDJob/
productProcessin time (days)
Due date (days)
(2)
Flow time(3)
Days tardy (0 if negative)(3)-(2)
C 4 4 4 4-4=0A 2 7 4+2=6 6-7=-10E 5 15 5+6=11 11-15=-40B 8 16 11+8=19 19-16=3D 10 17 19+10=29 29-17=12F 12 18 29+12=41 41-18=23
41 110 38
• Aft=110/6=18,33 days• At=38/6=6,33 days• Aj=110/41=2,68 pieces
CAEBDF
CRJob/
productProcessin time (days)
Due date
(days)(2)
CR0
A 2 7 (7-0)/2=3,5
B 8 16 (16-0)/8=2
C 4 4 (4-0)/4=1
D 10 17 (17-0)10=1,7
E 5 15 (15-0)/5=3
F 12 18 (18-0)/12=1,5
41
Remaining time untill due to dat (on the 0th day)
1.
CR4
(7-4)/2=1,5
(16-4)/8=1,5
-------
(17-4)/10=1,3
(15-4)/5=2,2
(18-4)/12=1,172.
???
Job/ product CR16
A (7-16)/2=-4,5
B (16-16)/8=0
C -------
D (17-16)/10=0,1
E (15-16)/5=-0,2
F -----
CR18
--------
(16-18)/8=-0,25
-------
(17-18)/10=-0,1
(15-18)/5=-0,6
---------
1.
2.
3.
4.
CR23
--------
(16-23)/8=-0,875
-------
(17-23)/10=-0,6
-------
---------
4.
5.
CRCFAEBDJob/
productProcessin
time (days)
Due date (days)
(2)C 4 4F 12 18A 2 7E 5 15B 8 16D 10 17
41
Flow time(3)
44+12=1616+2=1818+5=2323+8=3131+10=41133
• Aft=133/6=22,16 days• At=58/6=9,66 days• Aj=133/41=3,24 pieces
Days tardy (0 if negative)(3)-(2)4-4=016-18=-2018-7=1123-15=831-16=1541-17=2458
Sequencing Jobs through two Work Center
• Job time is known and constant• Job time is independent of job sequence• All job must follow the same two-step job
sequence• Job priorities cannot be used• All units must be completed at the first
work center before moving on to the second work center
Example 2Job/
product#1 #2
A 5 5B 4 3C 8 9D 2 7E 6 8F 12 15
• Select the job with the shortest time. – If the shortest time at
first wc, schedule that job first.
– If the time at the 2nd wc, schedule the work last.
• Eliminate the job and its time from further consideration
• Repeat steps
D BAE C F
Chart
D E C F A B#1
D E C F A B#2
2 8
1512F86E72D98C34B55A
#2#1Job/ product
1512F86E72D98C34B55A
#2#1Job/ product
16 28 33 37
2 9 17 26
Idle time
28 43 48 51
Flow time: 51 hours
Thank you for your attention!