Upload
others
View
7
Download
0
Embed Size (px)
Citation preview
SCHEDULING AND PERFORMANCE OF ROAD CONSTRUCTION
PROJECTS IN RWANDA:
A CASE STUDY OF CAMP KANOMBE –BUSANZA ROAD
CONSTRUCTION PROJECT
JESSIKA NINSIMA
MBA/43189/2016
A Research project Submitted in Partial Fulfillment of the Requirements
for the Award of the Degree of Master of Business Administration (Project
Management Option) of Mount Kenya University
NOVEMBER 2017
ii
DECLARATION
This research is my original work and has not been presented to any other Institution. No part
of this research should be reproduced without the author’s consent or that of Mount Kenya
University.
Student’s Name: Jessika Ninsima
Signature………………………………….. Date …………………………………………..
Declaration by the supervisor
This research proposal has been submitted with our approval as the Mount Kenya University
Supervisor.
Names: Dr Tom Mulegi, PhD
Signature……………………………….. Date.………………………………………………
iii
DEDICATION
Special thanks to my Husband Mbasha Eric for the support towards the completion of the
MBA program. My children ; Ean and Eliora for the patience along this entire journey. The
family of Nirere Deo for their support and courage they gave me. I Love you all.
iv
ACKNOWLEDGEMENT
Thanks to the Almighty God for the guidance and protection throughout my studies. I
recognition to my supervisor Dr Tom Mulegi, the Academic guidance, inspiration; without
him it would have been practically hard to come to this point of the research.
I acknowledge efforts of my colleagues, classmates for the help through: group assignments,
discussions; I want to thank you from the depth of my heart.
The management of Mount Kenya University Kigali Campus for the knowledge, skills and
suggestions; without all of them this research could not have been successful.
Finally, to all who contributed in diverse ways in the success of this study, God bless you.
v
ABSTRACT
This study was sought to assess the influence of scheduling on project performance in the
public sector in Rwanda. The following specific objectives guided the study : assessing how
scheduling practices influence Road construction project in Kicukiro District; establishing
differences between d scheduling Practices and Performance of Road construction projects in
Kicukiro District and; establishing the relationship between scheduling and project success of
Road construction project in Kicukiro District. Significantly, the study findings will help the
researcher to understand the theoretical orientations to the study; as well as meeting the
requirements for the award of the master degree in project management. Kicukiro District,
MKU and other stakeholders in project management will acquire more knowledge on
scheduling practices. The descriptive research design anchored the study owing to the nature
and size of target population. The target population for the study was 133; composed of 98
Kicukiro District staff, 3 staff of Kanombe Sector, 2 staff of Busanza Cell and 30 site
Managers of Horizon Road Construction Company Ltd. Two sampling techniques were used
including: stratified sampling and simple random sampling. The Correlation coefficient
approach was used to explain the relationship between the variables under investigation.
Analysis of variance method was used to establish differences between scheduling Practices
and Performance of Road Construction Projects. The study revealed that all elements of
scheduling had appositive relationship with project performance at a significance level of
0.01. Results further indicate that time scheduling and budget scheduling had a very strongly
positive correlation with project performance (sig: 0.000 < 0.001). The recommendations
were that Kicukiro District, Donors/Partners should lay much emphasis on maintenance of
existing roads and other infrastructures.
vi
TABLE OF CONTENTS
TABLE OF CONTENTS ....................................................................................................... vi
LIST OF TABLES................................................................................................................... x
FIGURE .................................................................................................................................. xi
LIST OF ABBREVIATIONS AND ACRONYMS ............................................................. xii
DEFINITIONS OF KEY TERMS ...................................................................................... xiii
CHAPTER ONE: INTRODUCTION TO THE STUDY ..................................................... 1
1.0 Introduction ....................................................................................................................... 1
1.1 Background of the Study .................................................................................................. 1
1.2 Problem Statement ............................................................................................................ 2
1.3 Objectives of Study ............................................................................................................ 3
1.3.1 General Objective ........................................................................................................... 3
1.3.2 Specific Objectives .......................................................................................................... 3
1.4 Research Questions ........................................................................................................... 3
1.5 Significance of the Study ................................................................................................... 3
1.6 Limitations of the Study .................................................................................................... 4
1.7 Scope of the Study ............................................................................................................. 4
1.7.1 Content Scope ................................................................................................................. 4
1.7.2 Geographical Scope ........................................................................................................ 5
vii
1.7.3 Time Scope ...................................................................................................................... 5
1.8 Organization of the study ................................................................................................. 5
CHAPTER TWO: REVIEW OF RELATED LITERATURE ............................................ 6
2.0 Introduction ....................................................................................................................... 6
2.1 Theoretical Literature ....................................................................................................... 6
2.1.1 Human Resource forecasting ......................................................................................... 6
2.1.2 Time Scheduling ............................................................................................................. 8
2.1.3 Budgeting ........................................................................................................................ 9
2.1.4 Quality of Product ........................................................................................................ 11
2.1.5 Stakeholder satisfaction ............................................................................................... 12
2.2 Empirical Literature ....................................................................................................... 13
2.3 Critical Review and Research Gap identification ........................................................ 14
2.4 Theoretical Framework .................................................................................................. 15
2.4.1 Scientific Management Theory ....................................... Error! Bookmark not defined.
2.4.2 Management Theory of Frank and Lillian Gilbreth ..... Error! Bookmark not defined.
2.4.3 Management Theory of Henri Fayol .............................. Error! Bookmark not defined.
2.5 Conceptual framework ................................................................................................... 16
2.6 Summary .......................................................................................................................... 16
CHAPTER THREE: RESEARCH METHODOLOGY .................................................... 18
3.0 Introduction ..................................................................................................................... 18
3.1 Research Design ............................................................................................................... 18
viii
3.2 Target Population ............................................................................................................ 18
3.3 Sample Design .................................................................................................................. 19
3.3.1 Sample Size ................................................................................................................... 19
3.3.1 Sample Size ................................................................................................................... 19
3.4 Data Collection Methods ................................................................................................. 20
3.4.1 Data Collection Instruments ........................................................................................ 20
3.4.2 Administration of Data Collection Instruments ........................................................ 20
3.4.3 Reliability and validity ................................................................................................. 20
CHAPTER FOUR: RESEARCH FINDINGS AND DISCUSSION ................................. 23
4.0 Introduction ..................................................................................................................... 23
4.1 Demographic characteristics of respondents ................................................................ 23
4.1.1 Gender distribution ...................................................................................................... 23
4.1.2 Distribution of respondents per age ............................................................................ 24
4.1.3 The experience of respondents .................................................................................... 24
4.2 Presentation of Findings ................................................................................................. 25
4.2.1 The scheduling practices in Road construction project in Kicukiro district .......... 26
4.2.2 Establishing Differences between Different Scheduling Practices and Project
Performance ........................................................................................................................... 31
4.2.3 Establish the relationship between scheduling and performance of Road
Construction project in Kicukiro district. ........................................................................... 32
CHAPTER FIVE: SUMMARY, CONCLUSIONS AND RECOMMENDATIONS ....... 37
5.0 Introduction ..................................................................................................................... 37
ix
5.1 Summary of Findings ...................................................................................................... 37
5.1.1 The implication of scheduling practices of Road construction project in Kicukiro
................................................................................................................................................. 38
District .................................................................................................................................... 38
5.1.2 Establishing Differences between Different Scheduling Practices and Project
Performance ........................................................................................................................... 39
5.1.3 The relationship between scheduling and performance in Road construction in .. 39
5.2 Conclusions ...................................................................................................................... 40
5.3 Recommendations ........................................................................................................... 40
5.3.1 To the public sector (Kicukiro District) ..................................................................... 40
5.3.2 To contractor and shareholder.................................................................................... 40
5.3.3 To Donor and Partners ................................................................................................ 41
5.3.4 To Staff .......................................................................................................................... 41
5.4 Suggestions for further study ......................................................................................... 41
REFERENCES ...................................................................................................................... 42
APPENDICES ....................................................................................................................... 47
APPENDIX 1: AUTHORIZATION LETTER ................................................................... 49
APPENDIX 2: ACCEPTANCE LETTER .......................................................................... 50
APPENDIX 3: QUESTIONNAIRE .................................................................................... 51
APPENDIX 4: LIST OF RESPONDENTS AND THEIR CURRENT POSITION ....... 59
x
LIST OF TABLES
Table 3. 1 Indicates population by categories ......................................................................... 18
Table 3. 2 The coefficients of Cronbach’s Alpha ................................................................... 21
Table 4. 1 Gender distribution of respondents ........................................................................ 23
Table 4. 2 Age distribution of respondents ............................................................................. 24
Table 4. 3 Experience of respondents ..................................................................................... 24
Table 4. 4 Respondents opinion on Project scheduling .......................................................... 26
Table 4. 5 Respondents views on Scheduling practices used ................................................. 27
Table 4. 6 Respondents views on frequency of use of scheduling practices the in project .. 27
Table 4. 7 Project budgeting ................................................................................................... 28
Table 4. 8 Specific project timelines....................................................................................... 29
Table 4. 9 Respect timelines ................................................................................................... 30
Table 4. 10 Human Resource forecasting ............................................................................... 30
Table 4. 11 ANOVA Results .................................................................................................. 31
Table 4. 12 Results of Discrete correlation of elements of scheduling with Project
Performance ............................................................................................................................ 33
Table 4. 13 Results of correlation of aggregate scheduling with Project Performance .......... 34
xi
FIGURE
Figure 2. 1 Conceptual Framework ........................................................................................ 16
xii
LIST OF ABBREVIATIONS AND ACRONYMS
ANN Artificial Neural Networks
ANOVA Analysis of Variance
HRP Human Resources Planning
KPI Key Performance Indicators
MBA Master of Business Administration
MININFRA Ministry of Infrastructure
MKU Mount Kenya University
PCM Project Cycle Management
PMBOK Project Management Body of Knowledge
PNA Planning Needs Assessment
RMF Road Maintenance Fund
WBS Work Breakdown Structure
xiii
DEFINITIONS OF KEY TERMS
A project: A series of tasks having definite objectives; start and end points.
Project Performance: Definition of how a project rates against predetermined cost
estimates, quality parameters; and timelines.
Public Sector: Domain specifically working to ensure Common Good
Scheduling: logical Link between project Activities and associated resource Requirements
and Timelines.
1
CHAPTER ONE: INTRODUCTION TO THE STUDY
1.0 Introduction
This addresses the statement of the problem, background, objectives, research questions, and
significance, limitations, scope and organization of the study.
1.1 Background of the Study
Where as project performance is a management issue frequently discussed, there is lack of
agreement by which success is judged (Crawford, 2002). In Real Project Situations, there is
no agreement on either total failure or absolute success. There are no clear indices on which
project success should be focused. Nonetheless there ought to be a clear definition of what
constitutes success.
Clarke (1999) said that a project is a performance if it achieves all of the agreed objectives,
quality parameters, timelines and costs. Scholars however, perceive the performance of a
project differently. This could be explained by the inherent differences in both the Academic
and Social Backgrounds of the scholars. The Academia therefore, needs to acknowledge that
there is no single measure of Project Performance. This argument is further supported by
Badiru (2002) who opined that a project’s relative degree of performance or failure may
change over time. Documentation by Burke (1999) further indicates the variation on the
concept of Project Performance. His Works reveal that; in the 1960s and early 1970s many
project management tools and techniques focused on the implementation phase of the project
life cycle. By the1980s emphasis had shifted to the initiation Phase of the project. Project
Scheduling entails detailing activities into their proper sequence, with appropriate
relationships defined, consistent with the execution plan. It’s imperative that the schedule is
imbedded in the project management system. The schedule should be integrated with budget,
2
resources, scope, and quality requirements to produce a virtual model of the project
execution plan.
Ever since its establishment in 1998, the Road Maintenance Fund (RMF), mandated to
ensure collection and funding for the maintenance of road networks in Rwanda has recorded
significant achievements in terms of road maintenance. Under the Road Maintenance Fund
various projects have been successfully accomplished. This study therefore sought to
establish whether the success of these projects emanated from good scheduling.
Kicukiro District which is one of the three districts of Kigali town; is bordered by
Nyarugenge District to the west, Bugesera District to the east; and Gasabo District to the
north. Aiken at el, (1990) and World Bank data (2015), purport that the public sector, which
largely formal, plays a remarkable role in ensuring economic growth.
1.2 Problem Statement
Pinto and Slevin, (1988) in their write up show that it is crucial the project manager prepares
a project schedule and follows it through the entire project Group Processes. The government
of Rwanda has made several efforts to ensure Success of Projects in the Public Sector. Some
of the most remarkable reforms include: constituting a technical committee to assess the
existing public transport problems (World Bank Report, 2015).
Although Rwanda has recorded significant achievements in developing transport
infrastructure, there are still serious limitations regarding public accessibility to transport
service (MININFRA report, 2016). Severally, the construction sector in Rwanda has not been
able to meet project timelines, budget compliance and other quality requirements; all of
which are poor performance indicators (World Bank Report, 2015). It is this standpoint that
the impact of scheduling on project performance was assessed.
3
1.3 Objectives of Study
1.3.1 General Objective
The study assessed how scheduling influences the performance of Camp Kanombe –Busanza
Road Construction Project.
1.3.2 Specific Objectives
(i) To assess the scheduling practices in Road construction project in Kicukiro District;
(ii) To establish differences between different scheduling Practices and Performance of
Road construction project in Kicukiro District.
(iii) To establish the relationship between scheduling and project success of Road
construction project in Kicukiro District.
1.4 Research Questions
The study answered the following questions in accordance to the settled objectives:
(i) What are the scheduling practices of Road construction project in Kicukiro District?
(ii) Are there differences in the relationship between the scheduling Practices and
Performance of Road construction project in Kicukiro District
iii) What is the relationship between scheduling and project success of Road construction
project in Kicukiro District?
1.5 Significance of the Study
Findings may implore public institutions internalize how relevant scheduling program are;
future researchers and practitioners to seek more deeply how the success of any scheduling
can be improved through planning practices; the community will be aware of benefits of
effective scheduling; public institutions will get more opportunities For appropriately
evaluating the contribution of project scheduling to projects in the Public Sector. Mount
4
Kenya University and other researchers will acquire to which future studies will make
reference.
Camp Kanombe–Busanza Road construction project stakeholders; will use it as the basis for
planning and application of the project scheduling into their Administrative systems.
Instructors in project management will change their orientation and methods of delivery,
capacity and importance of scheduling to students who are at the level of exploiting such
knowledge through the research. It will be of significance to the nation of Rwanda in a sense
of widening its public sector knowledge base and this lead to their high probability of
survival and prosperity.
1.6 Limitations of the Study
Some of people thought the information could cause them problems. Most respondents were
subjected to rules governing their companies; they feared for their status. The researcher had
to secure official authorization to access information from the targeted people.
The researcher put efforts in providing proper and quality work aligned to the set objectives
and goals of the study.
1.7 Scope of the Study
1.7.1 Content Scope
The study focused on the impact of scheduling on performance of road construction project.
Scheduling was addressed in terms of human resource forecasting, time scheduling and
budgeting while performance of projects was measured in terms of quality of product and
stakeholder satisfaction.
5
1.7.2 Geographical Scope
The study used Road construction project in Kicukiro District located in Kigali city, this
study assessed the influence of scheduling on project success in Camp Kanombe - Busanza
tarmac Road construction. This project was chosen because Completion of 5,8Km Camp
Kanombe–Busanza road District not get the full fund of 2, 2 billion for completion of this project
(District KICUKIRO 2017/18 Plans).
1.7.3 Time Scope
The study was conducted in relation to scheduling and performance in road construction in
Rwanda considering the period of two years (2015-2017), the period was used by the
researcher in two periods, the beginning period and closing period. This project chose 2015-
2017 because it was in the same period of completion (District KICUKIRO 2017/18 Plans).
1.8 Organization of the study
The structure of the research project started by an introduction as first chapter, the second
chapter tackled the review of related literature by developing both theoretical and empirical
literatures. This study identifies research gaps and bridges them. The third chapter discusses
the methodology including: study design, study population, sampling techniques, data
collection instruments and procedures and data analysis procedures. The fourth chapter
presents, analyzes and interprets data collected. The fifth chapter summarizes the findings
based on respondents ‘opinions and makes recommendations arising from major findings.
6
CHAPTER TWO: REVIEW OF RELATED LITERATURE
2.0 Introduction
In this chapter, the researcher focused on literature review which constitutes the essential
theory that demonstrate the effect of employee planning on project success, empirical
literature, critical review analyzed works of other people related to variables under study and
research gap identification to the study.
2.1 Theoretical Literature
In this sub title, the research focused on HR forecasting, time scheduling, budgeting, and
quality of a product and stakeholder satisfaction as follow.
2.1.1 Human Resource forecasting
Three elements are considered in the assessment of forecasting labor demand and supply, the
elements include: identifying stakeholder involved, determining appropriate planning
horizon; and defining internal and external labor force.
The Project team should include all relevant stakeholders across multiple functional areas
and organizational levels. Explicitly developing a team for the HRP process helps ensure
success of the strategies within the plan and holds those who are not meeting the goals
accountable. Also, the diversity in the team will reduce groupthink, the tendency for group
members to avoid introducing novel ideas that are outside of the group’s normal mode of
thinking for fear that they will disrupt the group consensus process (Haynes & Fryer, 2000).
Hall (1993) contends that; Human Resource Planning team should include relevant
stakeholders. These scholars further argue that this be done across functional areas and
7
organizational levels. In this study, the researcher is in agreement that developing a team for
the HRP process helps ensure success of the strategies within the plan. The researcher also
shares the opinion that those not meeting the goals should be accountable for any
shortcomings. Once this argument is adapted, the tendency for group members to avoid
introducing novel ideas that are outside of the group’s normal mode of thinking will be
minimized.
It would also be recommended to carry out a human resource audit; which has been defined
severally as; the systematic examination and analysis of an organizational workforce in order
to create an understanding of the existing staffing situation in the organization or the project.
The Human Resource audit will help compare past event with the contemporary labor
specifications. It will also be instrumental in identifying trends and patterns aspects
regarding: staff turnover, training, absence; and diversity. This is in collaboration with the
perception by Bradley, (2008) that, HR audit can identify key information about operations,
including how well employees work; as well as locating areas that need improvement.
Human Resource Forecasting also involves the external labor force; which refers sourcing of
human resources outside an organization. There should be mechanisms to evaluate external
labor force; which can be achieved by considering estimates based on regional and global
economic, environmental, and demographic changes. Economic and environment factors
include interest rates, unionization, economic growth, unemployment rates, and political
climate. Dilip, (2005) links it to Demographic factors pointing towards population-based
information such as: retirement rates, birth/mortality rates, educational attainment, primary
language, and labor shifts
8
The other important concept when dealing Human Resource Forecasting is the relationship
between Organizations Strategic Plan and Human Resource Strategic Plan. This is well
presented in Haworth at el (2003) literature, where it is indicated that; an organization’s
strategic plan leads the overall HR strategic plan. The strategic plan is a macro level set of
directives that identifies how the organization will achieve its mission and move toward its
vision. At a more complex level, other Scholars in the management discipline have also
shown that; Workforce planning offers a means of systematically aligning organizational and
program priorities with the budgetary and human resources needed to accomplish them. By
beginning the planning process with identified strategic objectives, managers and their
organizations can develop workforce plans that will help them accomplish those objectives.
At the same time, these plans provide a sound basis for justifying budget and staffing
requests, since there is a clear connection between objectives, the budget, and the human
resources needed to accomplish them. Notably, Hendry at el, (1990) opined that strategic
planning for human resources should follow organizational goals, as well as types of
projects and activities that the organization aims to execute.
2.1.2 Time Scheduling
Many times we are gone from the task level to the resources level of scheduling, but there’s
no law that says you are not working on a portfolio of projects. The project dashboard is your
best friend, whether you’re working on one or many projects. The dashboard is collecting all
the real-time data collected by you and your teams, and then it’s organizing it according to
any number of metrics to show you a picture of where you stand in real-time on the project or
many projects (Wray, 1998).
9
Several techniques and tools may be used for the project manager alongside the project teams
to adhere to project timelines. Analysis of Literature indicates that the technique can instantly
assist in adjusting the project schedule to resolve delays before getting to critical levels;
especially in instances tasks are being blocked. Wray, (1998) specifically adds that alongside
graphs and charts the project team can be able to automatically drill deeper, filter and
customize results to get timely and appropriate information. This perception is shared by Bell
and Opie (2002), contending that project scheduling may summarizing the logical
relationship between different tasks. There appears to be a general assumption that
Scheduling is one of the more difficult jobs in project management. Several literatures
however, show that coordinating delivery dates on resource estimates can be streamlined
and made more efficient when the right set of tools are used by the project Team.
There appears to be remarkable evidence on the significance of Planning in Project
Scheduling, Notably, Eshna (2012) shows that planning is very important because without
planning, the project will have no guided direction. Ideally, Project planning helps one
assess the project is, where it is going and how it will get there. By doing this, the project is
being passed through an evaluation process. This evaluation process will help the
organization set up projects which are relevant in the community, as well as pre-determining
the performance of future projects.
2.1.3 Budgeting
Performance of a project is also measured basing to the extent of compliance to the Budget.
Veit-Wilson (1998) refers to Budgeting as the process of creating a plan estimated
expenditure. Workable budgets can only be attained after determining the sources on money
to be invested in the project. Creating this spending plan allows the project team to determine
10
in advance whether there is enough money to accomplish project tasks as detailed in the
Work Break Matrix. In Case of Shortage of Funds, then you can through the planning
process, prioritize areas to be spent on and focus available money on Activities that fall along
the Critical Path of the Project. Dubnoff, (1985) postulates that budgeting facilitates
organizations as well as the project management to create a spending plan; he further
contends that it ensures that enough financial resources are mobilized to facilitate project
requirements as detailed in the Project Requirement Matrix. The Researcher concurs with
these two authors in that compliance to the projected budget or spending plan helps
organizations avoid debt or aids projects keep out of debt in case they are already indebted.
In case of amiss-Match between income and Expenditure the project is likely to run into a
crisis which in adverse situations may lead to premature project Closure. Budgeting will
therefore ensure that there is a balance between expenses and project income. Veit-Wilson,
(1998) connotes that it is the responsibility of the project manager to create the first budget,
use it and get a good feel on how it can be used to track project finances. In this study, it can
be argued that budgets ought to be mapped to the project spending plan which can be
disaggregated into six months or even be stretched to a year. This will help the project team
forecast which months project finances may be tight as well as those requiring extra
Finances. Once this is well done, the budget becomes more manageable. Many Scholars
have seconded the use of computer based budgeting soft ware to arrive at efficient budgets.
For instance, Hirsch (2009) postulates that there are several elements of budgets must clearly
defined for the project team to arrive at an operational budget. Indeed, Nibud also makes
reference to budgets in relation to a minimum income level, whereas others use terms such as
basic needs as parameters an appropriate budget. Nibud further contends that such
11
parameters may be used for the construction of credit scores (loan-to-income ratios) or as a
benchmark for non-minimum incomes. It must be made clear in project management
literature though that; budget scope should include a description of the specific budget
details; and level of income being used in particular circumstances. Peter (2013) continued
to argue that projects have so many moving parts, and are frequently changing; project
scheduling software automatically updates tasks that are dependent on one another, when one
scheduled task is not completed on time. He further remarks that the soft ware when
appropriately generates automated email alerts. Project team members will easily know when
their scheduled tasks are due or overdue, and alert the project manager in situations where
one’s availability has changed. Project scheduling is simple when managed online,
thankfully, especially since the software does all the hard part for you.
There is however, no much research done relating project Activities to project budgets as
detailed out in the Activity Cost Estimates. Owing to the fact that projects are made up of
several tasks, and each task is given a start and end date, realistic budgets estimates may be
done, which in turn enable the project to be completed on time. It is also crucial that
individual project team member’s breaks be incorporated in the Budget. People have
different schedules, and their availability and vacation or leave dates need to be documented
in order to successfully plan those tasks.
2.1.4 Quality of Product
The emphasis on Product Quality is presented in the frame by Samasundaram and Adedeji
(1992); studying trade in horizontally and vertically differentiated products. In their model,
the two researchers contend that, different consumers with heterogeneous incomes and tastes
may purchase a homogeneous good and make a discrete choice of quality and variety of a
differentiated product. The framework further shows that customer preferences generate a
demand structure reflecting that the potential of consumers who buy a higher-quality product
12
rises with income. According to Samasundaram & Adedeji, (1992) their model provides a
tractable tool for studying the welfare consequences of trade and trade policy for different
income groups in an economy. Emphatically, Crawford (2002) adds that project performance
is an important project management issue; one of the most frequently discussed topics;
concluding that a general lack of agreement concerning the criteria by which success is
judged renders monitoring of Projects difficult. Without understanding the causes of project
failure, as well as a common definition of “success”, it may not be practical to differentiate
project success from project failure. wide sources of literature classify project success into
five different tiers: project delivering most of what was in the scope; project delivering what
it was set to deliver on schedule and within the agreed budget; project delivers within the
agreed budget and to the expected quality standards; project delivers as per agreed project
objectives; and project creates significant net value for the organization after the project is
completed (Greenley, 1986). With a similar tone Clarke (1999) explains a project will be
performing at acceptable levels if it achieves all of the agreed project objectives.
2.1.5 Stakeholder Satisfaction
Project leadership requires technical competence and entails the ability to manage a team
(Kloppenborg and Petrick, 1999). Teams lead to Skill pools whose relationships should be
managed to achieve project stakeholder satisfaction. Studies indicate that project outcomes
can only be achieved through creativity as well as use of techniques or hardware. This
assertion points to a proper skill-mix of technical skills and soft skills. It has however, been
documented variously that Creating the right relationships among team members and other
stakeholders is one of the biggest challenges that face contemporary project managers.
Forinstance, Turner re-defined the concept of ‘‘project’’ to recognize its human aspects’; as
13
an endeavor in which human, financial and material resources are organized to undertake a
unique scope of work, of given specification, within constraints of cost and time, so as to
achieve beneficial change to achieve pre-determined objectives. In a similar direction Loo
(2002) provides evidence of skill-mix of technical and people practices in top-rated internal
best practices. Skill-mix has also been evident in Social issues mostly regarding
environmental pollution are of concern to a variety of government regulatory agencies, as
well as to the communities in which corporations have their operations, employees, and
customers (Clarkson, 1991).
2.2 Empirical Literature
Whittaker (1999) indicated that a combination of inadequate risk management and weak
project plans are the common reasons for project failure. While Aladwani, (2002) in his study
revealed that Project scheduling has a mediating effect on the link between project
uncertainty and of Information Technology Projects. Additionally, a study by Nguyen,
(2003) in Vietnam showed that poor scheduling and planning were the most common causes
of project failure. Scheduling is definitely affected by human, technical and management
factors.
Results of an empirical study by Bryde and Robinson (2005) showed that contractors put
more emphasis on time and cost criteria; while the clients put more emphasis on satisfying
the needs of other stakeholders. Comparatively, Bryde and Robinsons’ study affirms that
there is disagreement among researchers on project Performance measurement concepts.
This is could have been the basis upon which Agarwal and Rathod (2006) conducted a
research on new success criteria on successful software development project; examining
different views of internal stakeholders such as Programmers, Project Managers and
14
Customer Account Managers. The study found that cost, time and quality were important
criteria for assessing the success. Secondly, they found that the scope criterion is considered
to be of utmost importance for project success.
Laufer and Tucker (1987) find several troubling phenomena from planning in construction
projects; thus nearly revealing total degeneration of the role of planning. Several other
researches on the relationship between planning factors and scheduling indicated that;
planning performance and project outcomes can differ between project with different
characteristics (Bryde and Robinison, 2005; Agarwal and Rathod, 2006; Laufer and Turker,
1987
2.3 Critical Review and Research Gap identification
Kloppenborg and Petrick ,(1999) highlight significant of skill mix in stakeholder satisfaction;
nonetheless, this study based on only two types of skills-technical verses people skills in
practice however, people skills are very diverse, an analysis of which can come up with
contrasting results.
Clarkson, (1991) generalizes social issues which is a very broad concept. There is a
significant gap culminating into a need to specify the social issue that would improve with
skill mix. This study bridges this gap considering Scheduling as the issue being investigated.
This study postulates Scheduling as a social issue from the process Perspective; Project
Scheduling can only be of value if done through teams; which teams require individual
members to enter into networking as well as relating and interacting with each other at
different phases of the project.
Product Quality as presented in the frame by Samasundaram and Adedeji (1992) is mapped
on consumers with heterogeneous incomes and tastes purchasing a homogeneous good;
hence, making a discrete choice of quality and variety of products. There is therefore a need
for a study assessing how homogenous customers would behave when purchasing a
heterogeneous good. Such a study will provide researchers the opportunity to arrive at
informed judgment of consumer behavior in diverse circumstances.
15
2.4 Theoretical Framework
A theoretical framework explains the relationship between concepts and theories used in the
study.
This study was guided by Frank and Lillian Gilbreths’ Management Theory, proponed in
1924. The theory is classified among motion and time studies; it however, interest in the
psychology of efficiency of work. Management Theory advances a “one best way” to
accomplishing any task efficiently.
The theory argues that there is one way to improving the efficiency of none. Further, stating
that one the technique is established, it can be used in turn to influence the efficiency of
similar works. This theory puts emphasis on breaking work down in incremental parts,
which the Gilbreths’ called therbligs. They asserted that by reducing the number of therbligs,
the efficiency of the worker could be increased.
Frank and Lillian Gilbreths’ Management Theory best explains this study, because it
provides a clear link between scheduling and project performance. In project management
scheduling entails breaking down the work into work package and later into small tasks and
activities. Management theory becomes even more relevant to this study by comparing
therbligs as named by the Gilbreths, to work packages, tasks; and activities as referred to in
the work break down matrix.
The breakdown of work matrix breaks down work initially into work packages, then small
tasks and finally individual activities is incremented in nature similar to what the
management theory presents. The schedule makes use of the work break down matrix which
is a specialized project management tool.
16
2.5 Conceptual framework
Independent Variable Dependent Variable
Intervening Variables
Figure 2. 1 Conceptual Framework
Source: Researcher, 2017
Figure 2.1 conceptual framework depicts scheduling as the independent variable, and project
performance as the dependent variable.
It further shows that scheduling in this study, is measured in terms of: Human Resource
Forecasting, Time scheduling, and budgeting. While project performance is measured in
terms of: Quality of product and stakeholder satisfaction. Additionally, the figure indicates
that, apart from scheduling, other factors such as technology, policy and climate change may
also influence the performance of projects.
2.6 Summary
This chapter helped to read more studies already done in different areas and related to this
study. It helped to obtain information on different themes like HR forecasting, times
scheduling, budgeting, quality of product and stakeholder satisfaction according to project
- Technology
- Policy
- Climate change
Scheduling
- HR forecasting
- Time Scheduling
- Budgeting
-
Project Performance
- Quality of Product
- Stakeholder satisfaction
17
styles in order to demonstrate the significant relationship between scheduling and project
performance in Rwanda for selected case study in road construction project.
18
CHAPTER THREE: RESEARCH METHODOLOGY
3.0 Introduction
This chapter describes the study design, study population, sampling techniques, data
collection instruments and procedures and data analysis procedures.
3.1 Research Design
The descriptive research design was used to link different parts of the study in creating
logical meaning. The design was helpful in stating the problem; discussing how previous
scholars analyzed their findings and in the process benefit from their experience.
3.2 Target Population
The target population was 133 distributed in terms of : 98 Kicukiro District staff, 3 staff of
Kanombe Sector, 2 staff of Busanza Cell; and 30 site Managers of Horizon construction
company Ltd .
Table 3. 1 Indicates population by categories
Description Population
District Staff (Kicukiro) 98
Sector staff (Kanombe) 03
Cell Staff (Busanza) 02
Site Managers of Contractor (Horizon Co) 30
Total 133
Source: Kicukiro District Report, (2016)
19
3.3 Sample Design
This section discusses sample size explicitly explaining how it was determined and
distributed. It also provides a narrative of how respondents were selected.
3.3.1 Sample Size
3.3.1 Sample Size
The sample size was determined, using Solven’s formula:
n=
n is Sample size;
N is Total Population;
e is the acceptable sampling error;
95% confidence level and
e assumed to be equal 0.5
=133/(1+133*0.05*0.05)
=133/1+0.32
= 133/1.32
=101
Respondents from population sub group were determined proportionately: Kicukiro District
(74); Kanombe Sector staff (2); Busanza Cell(2); and site managers (23).
3.3.2 Sampling Technique
The respondents were selected using different sampling techniques owing to the diverse
characteristics of the population. Stratified Random Sampling technique was used to
20
segregate the population in different categories. Purposive sampling technique was used to
select cell staff and sector staff. While simple random sampling technique was used to
district staff and site managers. This gave equal chance to every individual to participate.
3.4 Data Collection Methods
This study relied on primary and secondary data collected using a questionnaire as it was
appropriate for this study since cross cutting information could be collected at the same time
in a relatively small period of time. Questionnaire consisted of two sections: Respondents’
background information; and scheduling and project performance.
3.4.1 Data Collection Instruments
To collect the information, documentary review and questionnaire were used to do the
effective research. The questionnaires used as technique of collecting primary data from PIR’
staff and will be organized into two sections using open ended questions.
3.4.2 Administration of Data Collection Instruments
Two types of instruments were employed in data collection; those are questionnaire’s
distribution and face to face interviews in case of some clarifications or lack of
concentration. The questionnaire was personally administered by the researcher through drop
and pick method. While 101 questionnaires were given out, only 90 questionnaires were
retrieved from the respondents. The retrieved rate of 89% was achieved.
3.4.3 Reliability and validity
Reliability is the ability of questionnaires to have consistency measurement each time being
used. Cronbach’s coefficient Alpha (α) was obtained by using SSPS.
For the study to be of real meaning should apply valid and reliable instruments (Creswell,
2000). Before data collection questionnaires were pre-tested the by administering the
21
questionnaire to five respondents of Kagugu road (Gasabo District). Questionnaires were
also checked for consistency and clarity of the items. Adjustments were made for
instruments to measure what was intended. To ensure reliability and consistency of
instruments, Cronbach’s alpha criterion at a value of 0.7 was used. When all items were
perfectly reliable and measure the same response, questionnaires were accepted when
coefficient Cronbach’s Alpha is greater than 0.5 (Hamdan, Badrullah & Shahid, 2011).
Table 3. 2 The coefficients of Cronbach’s Alpha
Construct Number of Items Cronbach Alpha
Scheduling practices of Road construction project 5 0.906
Differences between different scheduling Practices and
Performance 6 0.903
Relationship between scheduling and performance of Road
construction project 7 0.914
Source: Research data
Reliability Statistics of the questionnaire had a number of items 22(questions) and coefficient
of Cronbach’s was 0.653 >0.5. The questionnaire was therefore reliable.
3.5 Data analysis Procedure
The research questions was coded by using SPSS version 21 to produce results which were
presented, analyzed and interpreted in chap four. Statistical treatment was drafted in tables
and descriptive statistics methods was also used where frequencies, percentages and mean
was drawn in responses to the study of the research question. Person’s correlation coefficient
established the relationship between scheduling and project success; while analysis of
variance (ANOVA) established differences between scheduling Practices and Performance.
22
3.6 Ethical Considerations
The respondents were asked to tick their response to each statement by checking one of the
categories of agreement or disagreement using five scale exceptions on section (a) question
three and four. The researcher avoided any forms of bias and kept respondents’ views
confidential to avoid any diverse effect that may result from the information given.
23
CHAPTER FOUR: RESEARCH FINDINGS AND DISCUSSION
4.0 Introduction
This chapter is divided into sections: demographic characteristics of sampled respondents;
assessment of scheduling practices, differences between scheduling Practices and
Performance of Road construction project; and establishing the relationship between
scheduling practices and project performance of Road construction project in Kicukiro
district.
4.1 Demographic characteristics of respondents
General information studied in the research project includes gender, age, current position,
Experience of respondents.
4.1.1 Gender distribution
Table 4.1 Indicates respondents’ distribution by gender.
Table 4. 1 Gender distribution of respondents
Source: Researcher data, 2017
In Table 4.1, revealed that respondents by gender range 63.30% were male and 36.70% were
female. These Results collaborate with findings in a study by Lindgren and Packendorff
(2006), there is need for other studies on gender specifically addressing the in terms of
Respondents Gender Frequency Percent
Employees
Male 57 63.30
Female 33 36.70
Total 90 100.00
24
situation of individuals’ in the workplace. Such studies who help society understand how
differences in gender roles affect building of project teams.
4.1.2 Distribution of respondents per age
Table 4. 2 Age distribution of respondents
Respondents Age(years) Frequency Percent
Employees age range
20-25 9 10.00
26-30 30 33.30
31-35 31 34.40
36-40 14 15.60
Above 40 6 06.70
Total 90 100.00
Source: Researcher data, 2017
In Table 4.2, revealed that respondents in the age range of 26-30years (33.30%), 31-35years
(34.40%) are more than other age range and employees with this age range were strong
physically and mentally, knowledgeable with skills in their professional fields. The age
range of 20-30 is still in schools and age range of 31-35 and 36-40years they finished schools
and they have responsibilities that compels them to seek for any available job opportunities.
And the lowest percentage lies in the range of 40 and above reason being that they may not
physically strong to perform strong work in the construction industry.
4.1.3 The experience of respondents
Table 4. 3 Experience of respondents
Respondents Number of Frequency Percent
25
(working years)
Employees experience
1-3 54 60.00
4-6 22 24.40
7-10 14 15.60
Total 90 100.00
Source: Researcher data, 2017
In the Table 4.3 showed that employees were professional with skills and knowledge in that
the information given was trusted on scheduling practices. The employees were involved in
Road construction project activities. And employees with experience their responses were
trusted with completeness and accuracy about the scheduling practices and project
performance.
The study found that experience of individuals in a team associated with better team
performance. This revelation provides insight into how the interactions of members may
contribute to the development of more capabilities in the project. Incases horizontal
interactions between managers of different project, shared experiences will increase project
success through learning.
4.2 Presentation of Findings
During questionnaire examination process, data were obtained on project scheduling
practices that were done by employees in the project performance. Data were also obtained
based on scheduling practices. The study was used to understand further current project
performance.
26
4.2.1 The scheduling practices in Road construction project in Kicukiro district
This objective was achieved by: getting respondents views on whether scheduling is done,
respondent views on scheduling practices used, respondents views on frequency of use of the
scheduling practices.
Table 4. 4 Respondents opinion on Project scheduling
Respondents’ opinion Frequency Percentage frequency
Activities scheduled 42 46.70
Activities not scheduled 2 2.20
Not sure of scheduled activities 46 51.10
Total 90 100.0
Source: Researcher data, 2017
The Table 4.4 respondents confirmed that project activities were not sure whether well
scheduled (51.10%) and other part of respondents (46.70%) agreed that project activities.
There are a couple of important reasons why planning and scheduling are important for your
business. For one, a solid plan and schedule helps keep costs down and allows you to operate
according to a budget. The findings point to the importance of scheduling in the management
of projects. In line with this finding, several other studies have argued that scheduling
facilitates the project team to organize and complete projects in a timely, quality and
financially responsible manner. There is therefore agreement in different project management
literatures that Effective project scheduling plays a crucial role in ensuring project success.
27
Table 4. 5 Respondents views on Scheduling practices used
Source: Researcher data, 2017
In Table 4.5 respondents used scheduling practices as follows; Time scheduling (44.40%),
budgeting (35.60%) and HR forecasting (20.0%) in the Road construction in Kicukiro
district. This showed that respondents were used to some scheduling practices than the other
as shown respectively. This is supported by the argument the act of choosing among
articulated projects is sufficient to obtain an optimal allocation of capital. However, for this
to be achieved, attention should be directed to the relationship between performance and
capital budgeting procedures.
Table 4. 6 Respondents views on frequency of use of scheduling practices the in project
Scheduling practices Frequency Percentage
frequency
HR forecasting 18 20.00
Time scheduling 40 44.40
Budgeting 32 35.60
Total 90 100.0
28
Scheduling practices Frequency Percentage
frequency
HR forecasting 11 12.20
Time scheduling 30 33.30
Budgeting 49 54.40
Total 90 100.0
Source: Researcher data, 2017
Results in Table 4.6 indicate that the most used Scheduling practice was Budgeting
(54.40%), and least was HR forecasting (12.20%); despite the revelation in the results,
generally, this area lacks theoretical foundation. This is shown in Pinto and Prescott (1988)
study where it was concluded that the ‘Personnel factor’ was the only factor in their research
that was marginal for project success.
Respondents were asked whether budgeting is facilitated in projects; and whether the
projected budgets are well facilitated. The Data reveals the respondents opinions:
Table 4. 7 Project budgeting
Respondents’ opinion Frequency Percentage
frequency
Budgets well facilitated 49 54.40
29
Budgets not well facilitated 14 15.60
Not Sure of Budgets facilitation 27 30.00
Total 90 100.00
Source: Researcher data, 2017
The Table 4.7 respondents showed that budgets were well facilitated (54.40%) to support
project performance. The results support the argument that budgets are a critical planning
tool without which a project may not even take off. Several people interviewed agreed that:
Budgeting is an important aspect of the project planning process. They also asserted that
projects will only be completion at the right time properly budgeted; or else it ends up
costing two or three times the budget. However, it’s important to consider that budgets are
arrived at by aligning planned activities to outputs.
Respondents were asked whether time schedules are important in projects; and whether
Timelines are observed in projects.
The Data reveals the respondents opinions:
Table 4. 8 Specific project timelines
Respondents’ opinion Frequency Percentage
frequency
project timelines specified 42 46.70
project timelines not specified 4 4.40
Not Sure of project timelines 44 48.90
Total 90 100.00
Source: Researcher data, 2017
30
Table 4.8 indicated that project timelines was specified (46.70%) and respondents were not
sure of project timelines (48.90%). Accurate time estimation is a skill essential for good
project management. Results imply that Time estimates require setting deadlines for projects
tasks which largely depends on competence as a project manager. Where the project manager
is not familiar with the task to be carried out, it is likely the amount of time needed to
implement projects will be underestimated.
Table 4. 9 Respect timelines
Respondents’ opinion Frequency Percentage
frequency
Respect timelines 44 48.90
No respect of timelines 10 11.10
Not Sure of respect timelines 36 40.00
Total 90 100.00
Source: Researcher data, 2017
The Table 4.9 revealed that respondents confirmed that respect timelines in the project. Not
Sure of respect timelines (40.00). Results of this study imply that Respect for timelines
entails creating a simple project management timeline for the project. From this perspective,
Project management timeline helps to set clear directions and priorities.
Respondents were asked whether human resource forecasting is important in projects; The
Data reveals the respondents opinions:
Table 4. 10 Human Resource forecasting
31
Views Frequency Percentage frequency
HR forecasting used 10 11.1
HR forecasting Not used 2 2.2
Not sure of HR forecasting 78 86.7
Total 90 100.0
Source: Researcher data, 2017
The Table 4.10 showed that respondents were not aware of the HR forecasting scheduling
(86.70%, Not sure of HR forecasting scheduling) as scheduling practices. It was established
through interviews that both mandatory and binary methods are used in HR Forecasting; in
projects are matched with workers sometimes based on quantities characteristic.
Respondents were however noted delays in the start of project increased time needed to
deliver the subsequent projects; the managers concurred with this opinion saying, such
incidences happened in projects that were running through phases.
4.2.2 Establishing Differences between Different Scheduling Practices and Project
Performance
Table 4. 11 ANOVA Results
Source: Researcher data, 2017
Model R R Square F Adjusted R Square Sig
1 .852a .726 76.096 .717 .000
a. Predictors: (Constant), Budgeting scheduling, HR forecasting , Time scheduling(IV)
b. Project performance (DV)
32
It showed that r 2= 0.726, which meant that 72.60% of total variation in y could be explained
by linear relationship between x and y and the remaining total variation of 14.80% was
unexplained. This correlation was generally described as positively strong. The one-way
analysis of variance (ANOVA) was used to determine whether there are any statistically
significant differences between the means of three or more independent (unrelated) groups.
r2 is the percentage of variation in the response that is explained by the model. The higher
the r2 value, the better the model fits your data. r2 is always between 0% and 100%. The
significance value is 0.000 (p = .000), which is below 0.05. Indicating that there are
significant differences in on how elements of the Independent Variable (Scheduling)
influence Project Performance.
4.2.3 Establish the relationship between scheduling and performance of Road
Construction project in Kicukiro district.
Multiple regressions were used to predict project performance based on the value of:
budgeting, time scheduling and human resource forecasting. The variable which was to be
predicted was called the dependent variable (project performance). The variables used to
predict the value of the dependent variable were called the independent (scheduling).
Multiple linear regressions attempted to model the relationship between several constructs of
the independent variable constructs of the independent variable constructs of the independent
variable and project performance (dependent variable) by fitting a linear equation to observed
data.
Y = B0 + B1 x1 + B2 x2 +……… Bk xk+ Ε
Independent variable: xk, and Coefficient: Bk, Unknown factor: ε, and Dependent variable:Y
Assume that: Y: Project performance.
33
x1: HR forecasting, x2: Time scheduling, X3: Budgeting.
The R-squared value, denoted by r2, is the square of the proportion of variation in the
dependent variable that can be attributed to the independent variable. The Linear coefficient
correlation. The findings suggest that a better understanding of the contribution of each
individual element in the project schedule to project performance can be obtained if
researcher correlates project performance with discrete correlation elements of project
scheduling.
Table 4. 12 Results of Discrete correlation of elements of scheduling with Project
Performance
Model Unstandardized Coefficients Standardized
Coefficients
Sig.
B Std. Error Beta
1
(Constant) .114 .245 .643
HR forecasting .281 .092 .187 .003
Time scheduling 1.427 .140 1.147 .000
Budgeting scheduling .620 .131 .511 .000
**Correlation is significant at 0.01 levels (2-tailed)
The study revealed that all elements of scheduling had appositive relationship with project
performance at a significance level of 0.01. Results further indicate that time scheduling and
budget scheduling had a very strongly positive correlation with project performance (sig:
0.000 < 0.001). Human resource forecasting had a comparably weaker correlation with
performance (sig. 0.003 < 0.001).
34
Data in Table 4.12 shows there are significance differences on how the different elements of
scheduling influence project performance, while Human resources forecasting, time
scheduling and budget scheduling influence the performance of projects; they do so at
different levels. The results further indicate that the implementation of each project
schedule component influences project performance measures differently.
The use of budgeting scheduling has an effect on the project of Road construction.
Specifically, this study reveals that the adoption of written budgets is related to size and
structure, and for projects using written budgets, the extent of use is related to project
structure, strategy and perceived environmental uncertainty. Finally, this study provides
evidence of a relationship between budgeting practice and performance. It further shows that
project’s performance is positively associated with the use of written budgets.
It can therefore be argued that more refined tests of the “fit” between project contingency
factors and extent of operating budget; can further, provide evidence of a positive association
between the extent of “budget fit” and performance.
In spite of decades of research, several projects continue to fail. The evidence of research
shows that project managers concentrate on achieving timescales and budgets for projects to
be successful in the future, the criteria for success and associated factors that influence
success need to be defined clearly, agreed by all parties at the start of the project, and
reviewed as the project progresses. Project managers should be concentrating on success
criteria relating to users and sponsors and, consequently, the factors to deliver those success
criteria.
Table 4. 13 Results of correlation of aggregate scheduling with Project Performance
Scheduling performance
35
scheduling Pearson correlation 1 .923**
Sig. (2-tailed) .000
N 76 76
Performance Pearson Correlation .923** 1
Sig. (2-tailed) .000
N 76 76
**Correlation is significant at 0.01 level (2-tailed)
Source: primary data
In addition, the results highlight the varying influence of the aggregated schedule as a whole,
on project performance measures. Results in Table 4.19, the research focuses on the
correlation between scheduling and project performance. The results show that aggregate
scheduling has a very strong relationship with project performance (sig.0.000<0.01).
These results are in agreement with findings of a study by; Monte Carlo simulation, in his
analysis of modeling and analyzing real-world systems and situations. His study also
Emphasizes the influence of project scheduling, In the field of project management, Monte
Carlo simulation can quantify the effects of risk and uncertainty in project schedules and
budgets, giving the project manager a statistical indicator of project performance such as
target project completion date and budget. This congruence in the two studies confirms the
existing relationship between scheduling and performance of projects; which was the general
objective for carrying out this study.
Further, the results of this study are consistent with two prominent models in project
management; Bromilow’s time cost model and the piecewise model. Consistent with findings
of this study, the two models appear to confirm that time scheduling has a significant
relationship with project performance. While these two models elude to the fact that project
36
duration is important in assessing the success or viability of specifically a construction
project. A time‐cost relationship for most projects in Nigeria has been developed based on
Bromilow's time‐cost model. Cost data on 87 completed building projects executed within
the period 1991–2000 were obtained. The data were subjected to regression analyses using
double log and later the piecewise model with breakpoint. For the Nigerian situation, the
Bromilow's time‐cost model was found to be T = 63C0.262 with poor predictive abilities
(R = 0.453, R2 = 0.205). An improved model using piecewise model with good predictive
abilities (R = 0.875, R2 = 0.765) was found to be T = 118.563−0.401C (C ⩽ 408) or 603.427
+ 0.610C (C>408). The model is shown to be useful in predicting project durations.
Further confirmation was on the Relevance of Human Resoucrce forecasting in project
performance. Other studies seem to have concentrated on Human resource forecasting, from
the perspective of constructing competent teams; and wherefrom the power of teams in
propelling performance of projects. The agreement is Human resource forecasting is an
important factor in the performance of projects. Results from 32 project groups in a large
Research and Development organization showed that group cohesiveness, physical distance,
job satisfaction, and innovative orientation were associated with performance of projects.
Hierarchical regression analyses revealed that group cohesiveness accounted for unique
variance in four performance criteria, both contemporaneously and one year later. An
innovative orientation added unique variance to the quality of projects as rated initially by
group members and as rated by management one year later. Type of Research and
Development moderated the relationship between innovative orientation and members'
ratings of project quality, in that a significant relationship was found for research projects,
but not for projects engaged in product development or technical service.
37
CHAPTER FIVE: SUMMARY, CONCLUSIONS AND
RECOMMENDATIONS
5.0 Introduction
In this chapter, the study summarizes the findings based on respondents’ opinions and
applicability of scheduling and project performance in Kicukiro District. The summary of the
study are presented in line with the objectives of the research. The study also presents the
conclusions of findings also recommendations of the researcher and suggestions of the
possible areas for the future researchers have been outlined.
5.1 Summary of Findings
The study entitled “scheduling and performance of road construction project in Rwanda.
A Case Study of Camp kanombe –busanza Road Construction Project.
The specific objectives were the following: to assess the scheduling practices, to establish
differences between different scheduling practices and project performance, to establish the
relationship between scheduling and performance of Road construction project in Kicukiro
District. A sampling technical used were stratified sampling in order to have all various parts
of the population equally covered in data collection; simple random sampling was also used
to select individuals from each sub group of the population. Correlation coefficient
approaches were used to explain and interpret the relationship between scheduling and
project performance and analysis of variance (ANOVA) were used to establish differences
between different scheduling practice and project performance of public organizations.
38
Questionnaires was used as instruments of data collection and data was analyzed using
Statistical Package for Social Science (SPSS) version 21, Spreadsheets, tables, percentages
were used where applicable to come up with conclusion and recommendations.
The descriptive approach was undertaken to find out the characteristics of variables of
interest in a situation and analytical based on qualitative and quantitative data both from
primary and a secondary sources were also considered. The target population of this study
was 133 where 101 were enough for sample size using stratified sampling technique.
Descriptive statistics methods which include frequencies counts and percentages were used
where applicable. The data processing tools such as Excel and SPSS were used and editing,
coding and tabulation were done for analysis of data collected.
5.1.1 The implication of scheduling practices of Road construction project in Kicukiro
District
Several respondents upon interviews were of the opinion that: project Budgeting is one of the
most important parts of the project planning process. Properly budgeted projects will often
come in at or under budget upon completion. By putting in adequate time during the planning
process, you can help assure that your project will be a success. Poor planning often ends in
budget crisis - where the project winds up costing two or three times the budget. Below you
will find tips on how to budget your project - so that you don't run out of funds halfway
through. The project manager should ensure the consistency between the activities planned
and their related budget. The budget should be comparable to the planned activities and
outputs, as well as the project’s duration and the number of partners.
39
5.1.2 Establishing Differences between Different Scheduling Practices and Project
Performance
The one-way analysis of variance (ANOVA) was used to determine whether there are any
statistically significant differences between the means of three or more independent
(unrelated) groups. R2 is the percentage of variation in the response that is explained by the
model. The higher the R2 value, the better the model fits your data. R2 is always between 0%
and 100%. The significance value is 0.000 (p = .000), which is below 0.05. Indicating that
there are significant differences in on how elements of the Independent Variable
(Scheduling) influence Project Performance.
5.1.3 The relationship between scheduling and performance in Road construction in
Kicukiro District
The findings suggest that a better understanding of the contribution of each individual
element in the project schedule to project performance can be obtained if researcher
correlates project performance with discrete correlation elements of project scheduling. The
study revealed that all elements of scheduling had appositive relationship with project
performance at a significance level of 0.01. Results further indicate that time scheduling and
budget scheduling had a very strongly positive correlation with project performance (sig:
0.000 < 0.001). Human resource forecasting had a comparably weaker correlation with
performance (sig. 0.003 < 0.001).
The use of budgeting scheduling has an effect on the project of Road construction.
Specifically, this study reveals that the adoption of written budgets is related to size and
structure, and for projects using written budgets, the extent of use is related to project
structure, strategy and perceived environmental uncertainty. Finally, this study provides
40
evidence of a relationship between budgeting practice and performance. It further shows that
project’s performance is positively associated with the use of written budgets.
5.2 Conclusions
This study indicates the contribution of scheduling in achieving objectives set and signed by
Kicukiro District officials. The findings of the study reveal that the management of public
sector particularly Kicukiro District entrusted with public resources and loaded with the
responsibility of managing these resources effectively and efficiently. It is expected that the
Kicukiro District officials entrusted with the management of public resources at public sector
level was given account of how these resources are being managed under their care in order
to ensure proper utilization/accountability of these resources and expenditures.
5.3 Recommendations
The recommendations related to public sector (Kicukiro District), the donors/partners and
staff as they play important roles for the achievement of government goals/ public purposes.
5.3.1 To the public sector (Kicukiro District)
The public sector (Kicukiro District) should set laws and regulations that facilitate easily the
capacity building of staff as they are the human capital read to be developed in a wished
manner for performance. They should always increase the budget for training as one source
of production expected.
5.3.2 To contractor and shareholder
Kicukiro District should use efficiently the resource allocated to train their staff about
scheduling and planning in general so that its mandate is executed in excellence manner as it
is now and be promoted to further stage so that our country Rwanda continue in countries
41
with excellent service delivery among the whole Africa in general and East Africa countries
in particular.
5.3.3 To Donor and Partners
The donors/partners should recommend more funds based on the efficiency use of the
allocated means for training of employees for the capacity building. They should advertise
Rwanda all over the world for efficient use of the given fund among other planning activities
more especially scheduling.
5.3.4 To Staff
The staff should be serious and take their opportunities of trainings given and others planning
activities to improve their capacity in general and the country in particular.
5.4 Suggestions for further study
Due to time constraints, this research was conducted using only one public institution, it is
therefore suggested that further research can be conducted in more and different public and
private institutions in order to give broader view on the research topic.
Again the current study was based in public sector perception so for further studies should
focus in private sector perception for more harmonization into all sectors.
Budgeting and HR forecasting are among areas for further development and all are closely
associated with planning orientation in any of the sector. Further research should be
conducted to see the relationship between those said independent variables to project
performance or failure.
42
REFERENCES
Agarwal, N. & Rathod, U. 2006. Defining ‘success’ for software projects: an exploratory
revelation. International Journal of Project Manage-ment 24, 358–370.
Al-Kharashi, A. & Skitmore, M. (2009). “Causes of delays in Saudi Arabian public sector
construction projects,” Construction Management and Economics, vol. 27, no. 1, pp.
3–23.
Aiken, L. S., West, S. G., Sechrest, L., & Reno, R. R. (1990). Grad - uate training in
statistics, methodology, and measurement in psychology: A survey of PhD programs
in North America. American Psychologist, 45, 721–734.
Badiru, S. S. a. A. B. May 1992. Project management for successful implementation of
continuous quality improvement. International Journal of Project Management 10 (2):
89 - 101.
Bell, J. and Opie, C. (2002) leaning from research: Getting more from your Data.
Buckingham: Open University Press. Part discuss the way Tim Chan planned and
43
carried out a survey of student evaluation of teaching effectiveness as part of his
doctoral research (Chan 2000).
Burke, R. (1999) Project management: planning and control techniques. New York: Wiley.
Bryde, J., D. & Robinson, L. (2005). Client versus contractor perspectives on project success
criteria. International Journal of Project Management, Vol. 23, pp.622-629.
Clarke, A. (1999). A practical use of key success factors to improve the effectiveness of
project management, International Journal of Project Management, 17(3), 139-145.
Clarkson, M. B. E. (1991). Defining, evaluating, and managing corporate social performance:
The stakeholder management model. In L. E. Preston (Ed.), Research in corporate
social Performance and policy, vol. 12: 331-358. Greenwich, CT: JAI Press.
Conti, T. (2002). A road map through the fog of quality and organizational
assessments. Total Quality Management, 13(8), 1057.
Cooke-Davies, T. J., & Arzymanow, A. (2003). The maturity of project management in
different industries: An investigation into variations between project management
models. International Journal of Project Management, 21(6), 471.
Crawford, L. (2002). Project Performance Assessment. Masters in Project Management
Course, 10th-15th June, Paris, France. UTS/ESC-Lille.
Creswell, J. W. & Miller, D. L. (2000). Determining validity in qualitative inquiry. Theory in
to Practice, 39(3), 124-131.
Dubnoff, S., 1985, How much income is enough? Measuring public judgements. Public
Opinion Quarterly, vol. 49, n°3, p. 225-299.
44
Dilip (2005), “Workers’ Remittances: An Important and Stable Source of External
Development Finance,” Chapter 1 in Remittances: Development Impact and Future
Prospects, eds. Samuel Maimbo and Dilip Ratha, Washington, DC: United States.
Fayol H., 1918, L’administration positive dans l’industrie, La Technique Moderne, février
1918, 73-75.
Frederick. W. Taylor. (1947). Scientific Management Theories, New York. Harper & Row.
Gao, Z., Walters, C., Jeselskis, J. & Wipf, J. (2006). Approaches to improving the quality of
construction drawings from owner’s perspective, journal of construction engineering and
management, Vol. 132, No.11, pp. 1192-1192.
Freeman, M. & Beale, P. 1992, Measuring. project success, Project Management Journal,
Vol. 23, No. 1, pp. 8–17.
González, J., Solís, R. & Alcudia, C. (2010). “Diagnóstico sobre la Planeación y Control
de Proyectos en las PYMES de Construcción,” Revista de la Construcción, vol. 9, no.
1, pp. 17–25.
Greenley,G. (1986). Does Strategic Planning improve company performance? Long Range
Planning, Academic Management Journal 19(2), April, 101-109.
Hall, Bradley W. The New Human Capital. AMACOM Div Management Assn, 2008.
Haynes, P. and Fryer, G. (2000) Human resources, service quality and performance: a case
study. International Journal of Contemporary Hospitality Management, 12(4), 240-48.
Hendry, C., & Pettigrew, A. (1990). Human resource management: An agenda for the 1990s.
International Journal of Human Resource Management. 1, 17-43.
45
Hirsch, D., 2009, Reference budgets in Europe, Keynote Lecture on “Reference budgets for
social inclusion”, the Final Conference of the EU Progress Project “Standard
budgets”, Vienna, 20-22 October 2009.
Keller, R. T. (1989). A test of the path-goal theory of leadership with need for clarity as a
moderator in research and development organizations. Journal of Applied
Psychology, 74(2), 208-212.
KICUKIRO District Plans- 2017/18
Kloppenborg T, Petrick J. (1999) Leadership in project life cycle and team character
development. Proj Manage J 30(2):8–13.
Kumar N. J. (2004). Factors for the success of a construction project in India: an empirical
study, PhD thesis.
Lindgren, M. & Packendorff, J. (2006)”What’s new in new forms of organizing? -On the
construction of gender in project-based work.” Journal of Management Studies. Vol
43, No 4: pp. 841-866.
Loo, R. (2002) Working towards best practices in project management: a Canadian study. Int
J Pro Manage;20(2):93–8.
Marzouk, M., El-Dokhmasey, A. & El-Said, M. (2008). “Assessing construction
engineering-related delays: Egyptian perspective,” Journal of Professional Issues in
Engineering Education and Practice, vol. 134, no. 3, pp. 315–326.
MININFRA, 2016. Guideline for Construction Technologies Usable in Rwanda. Ministry of
Infrastructure, Rwanda.
Peter W. G. Morris Wiley-Blackwell (2013). The recent book ‘Reconstructing Project
Management.
46
Pinto, J. and D.P. Slevin, (1988) Critical Success Factors across the Project Life Cycle,
Project Management Journal, Vol. 19, No. 3, pp. 67-75.
PMBOK (2000). A Guide to Project Management Body of Knowledge: Project Management
Institute, Newtown Square, PA.
Rwanda maintenance fund, (2016).
Samasundaram, S. & Adedeji, B. B (1992). Project Management for Successuful
Implementation of Continuous Quality Improvement. International Journal of Project
Management, Vol10, No 2. pp 89-101.
Singh, R. (2009). “Cost and time overruns in infrastructure projects: extent, causes and
remedies,” Working Paper181, Department of Economics, University of Delhi,
Nueva Deli, India.
Veit-Wilson, J., 1998, Setting adequacy standards. How governments define minimum
incomes? Bristol: The policy Press.
Wray, A, T, K. & Bloomer, A. (1998). Projects in linguistics: a practical guide to researching
language. London: Arnold.
World Bank, 2015. Construction Policy.http://water.worldbank.org/shw-resource-
guide/institutes/infrastructure-policy-frameworks
47
APPENDICES
48
49
APPENDIX 1: AUTHORIZATION LETTER
50
APPENDIX 2: ACCEPTANCE LETTER
51
APPENDIX 3: QUESTIONNAIRE Dear respondent,
I am Jessika Ninsima, a student who is completing Master of Business Administration
(Project Management Option) at Mount Kenya University (MKU), I am currently doing my
research and your respective company was selected to help its completion.
I have pleasure and honored to present to you a questionnaire of my study titled “scheduling
and project performance in public sector in Rwanda: A case study of Road construction
project in Kicukiro District”.
You are kindly requested to spare some time and express your views on the questions by the
feeling the questionnaire.
Note that the information provided will exclusively be for academic purpose and henceforth
will be kept in confidential manner.
With kind regards
JESSIKA NINSIMA
MBA/43189/2016
Section A: Demographic Information
1. Gender: (tick one)
Male Female
□ □
52
2. Age: (tick one)
20 - 25 26 - 30 31 – 35 36 – 40 Above 40
□ □ □ □ □
3. What is your current position? _______________
4. For how many years have you occupied that position? (tick one)
1 – 3 4 - 6 7 - 10 Above 10
□ □ □ □
Section B:
Questions assessing scheduling practices in road construction project in Kicukiro
District.
1) Do you have specific scheduling practices in these projects?
a) Yes □ b) No □ c) Not sure □
2) If yes, which of these practices are used?
a) HR forecasting □ b) Time scheduling □ c) Budgeting □
3) Which of these practices is most used in this project?
a) HR forecasting □ b) Time scheduling □ c) Budgeting □
4) Which is the least used practice?
a) HR forecasting □ b) Time scheduling □ c) Budgeting □
53
4. a) Why?Explain……………………………………………………………………………...
…………………………………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………..
5) Are project activities well defined and scheduled?
a) Yes □ b) No □ c) Not sure □
If yes, Explain……………………………………………………………………………..........
..…………………………………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………..
If No, Explain…………………………………………………………………………………..
………………………………………………………………………………………………….
………………………………………………………………………………………………….
…………………………………………………………………………………………………..
Questions assessing the performance of road construction project in Kicukiro District.
1) Do you routinely budget for the project activities?
a) Yes □ b) No □ c) Not sure □
If yes, Explain……………………………………………………………………………...
..…………………………………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………..
54
If No, Explain……………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………..
2) Are project budgets well facilitated?
a) Yes □ b) No □ c) Not sure □
If yes, Explain………………………………………………………………………………..
…………………………………………………………………………………………………
…………………………………………………………………………………………………
……………………………………………………………………………………………..
If No, Explain………………………………………………………………………………..
…………………………………………………………………………………………………
…………………………………………………………………………………………………
………………………………………………………………………………………………….
3) Do you have specified project timelines?
a) Yes □ b) No □ c) Not sure □
b) If yes, why is it necessary to have
timeline……………………………………………………….….…....………………
…………………………………………………………………………………………
55
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
If no why?……………………… ………………………………………………………….
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
4) Do you respect the timelines?
a) Yes □ b) No □ c) Not sure □
If no why? …………………………… ……………………………………………………….
…………………………………………………………………………………………………
…………………………………………………………………………………………………
………………………………………………………………………………………
5) Does this project meet the quality requirements?
a) Yes □ b) No □ c) Not sure □
If yes, Explain……………………………………………………………………………… ….
..…………………………………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………..
56
If No, Explain……………………………………………………………………………… ….
…………………………………………………………………………………………………
…………………………………………………………………………………………………
………………………………………………………………………………………………….
6) Are there lessons that related projects can learn from this projects?
a) Yes □ b) No □ c) Not sure □
If yes, Explain…………………………………………………………………………………..
..…………………………………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………..
If No, Explain………………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………
………………………………………………………………………………………………….
Questions establishing the relationship between scheduling and performance in road
construction project in Kicukiro District.
1) Do these practices have an effect on the performance of the project?
a) Yes □ b) No □ c) Not sure □
57
If yes, Explain………………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………
If No, Explain……………………………………………………………………….…………
…………………………………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………
2) Are the timelines influenced by the scheduling practices?
a) Yes □ b) No □ c) Not sure □
If yes, Explain…………………………………………………………………………………
..…………………………………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………..
3) Do the scheduling practices influence the quality of the project?
a) Yes □ b) No □ c) Not sure □
If yes, Explain…………………………………………………………………………………..
..…………………………………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………..
58
If No, Explain……………………………………………………………………….…………
…………………………………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………
Thank you for participating in this study.
59
APPENDIX 4: LIST OF RESPONDENTS AND THEIR CURRENT POSITION
Current Position of Respondents Frequency Percent
Planner 2 2.20
Finance Specialist 1 1.10
Statistician 1 1.10
Land Presentative 1 1.10
Human Resource officer 5 5.60
Cell Leader’s secretary 1 1.10
Logistics Officer 1 1.10
Head of infrastructure 1 1.10
Procurement officer 6 6.70
Revenue Accountant 1 1.10
Monitoring & Evaluation Specialist 2 2.20
Director of Administration & Finance 2 2.20
Technical Manger 3 3.30
Engineer 1 1.10
Customer care 1 1.10
Procurement Specialist 2 2.20
Head of Planning 1 1.10
Infrastructure Management Team Leader 2 2.20
Local Revenue Inspector 1 1.10
60
Junior Supervisor 1 1.10
Land Nnotery 1 1.10
Messenger Officer 1 1.10
Finance Officer 1 1.10
Auditor 3 3.30
Site Manager officer 1 1.10
ICT Officer 2 2.20
Administrative Assistant 2 2.20
One Stop Center Officer 2 2.20
Site Technician 3 3.30
Driver 2 2.20
Quality Standard Officer 1 1.10
Accountant 2 2.20
Trainer of trainees 1 1.10
Social Affairs of sector 1 1.10
Land Presentative 1 1.10
Legal Specialist 1 1.10
Division Manager 1 1.10
Social affairs 1 1.10
District Secretary 1 1.10
Security Officer 1 1.10
61
Technician 1 1.10
Senior Accountant 1 1.10
Customer Care Officer 1 1.10
One Stop Center Staff 1 1.10
HR for teachers 1 1.10
Administrator 1 1.10
Senior Supervisor 1 1.10
DASSO Head 1 1.10
Budget Officer 1 1.10
Advice Coordinator 1 1.10
Legal Advisor 1 1.10
Mobilization Officer 1 1.10
Health Inspector 1 1.10
Receptionist 1 1.10
Social Affairs 1 1.10
Good governance 1 1.10
Site Accountant 1 1.10
Secretary 1 1.10
Security Officer 1 1.10
Senior Controller 1 1.10
Compensation of Teachers 1 1.10
62
Source: Researcher data
Vice Chair Persons 1 1.10
GIS officer 1 1.10
Site Team Leader 1 1.10
Executive Assistant 1 1.10
Total 90 100.00