CONTRACT NO. /00 SCHEDULE "G" MATERIALS, TOOLS, AND EQUIPMENT 1.0 SAUDI ARAMCO-SUPPLIED MATERIAL, TOOLS AND EQUIPMENT 1.1 The material listed on Attachment I shall be furnished to CONTRACTOR by SAUDI ARAMCO, or, if applicable, to the Affiliated Contractor at its fabrication yard outside Saudi Arabia, during normal working hours from the locations noted on Attachment I, at no cost, and in usable condition subject only to repairs or reconditioning normal to material received at a fabrication yard or construction site. 1.2 The tools and equipment listed on Attachment I shall be furnished to CONTRACTOR by SAUDI ARAMCO during normal working hours from the locations noted on Attachment I on an "as is, where is" basis. 1.3 CONTRACTOR shall be responsible for safeguarding SAUDI ARAMCO-supplied material, tools, and equipment and ensuring that they are treated with due care, properly maintained, and used and operated in a prudent manner. 1.4 Upon completion of the WORK, or at any other time as directed by Company Representative, CONTRACTOR shall document as required by SAUDI ARAMCO, properly pack, identify and return unused or reusable SAUDI ARAMCO- supplied material, tools and equipment to any SAUDI ARAMCO designated location which is no further from the WORK Site than the original delivery point of such G-1 MP-IK-LSTK 11/92 OFF-IK-LSPB MP-IK-LSPB MP-LSTK Revised 3/06

Schedule G

Embed Size (px)

DESCRIPTION

a

Citation preview

Page 1: Schedule G

CONTRACT NO. /00

SCHEDULE "G"

MATERIALS, TOOLS, AND EQUIPMENT

1.0 SAUDI ARAMCO-SUPPLIED MATERIAL, TOOLS AND EQUIPMENT

1.1 The material listed on Attachment I shall be furnished to CONTRACTOR by SAUDI ARAMCO, or, if applicable, to the Affiliated Contractor at its fabrication yard outside Saudi Arabia, during normal working hours from the locations noted on Attachment I, at no cost, and in usable condition subject only to repairs or reconditioning normal to material received at a fabrication yard or construction site.

1.2 The tools and equipment listed on Attachment I shall be furnished to CONTRACTOR by SAUDI ARAMCO during normal working hours from the locations noted on Attachment I on an "as is, where is" basis.

1.3 CONTRACTOR shall be responsible for safeguarding SAUDI ARAMCO-supplied material, tools, and equipment and ensuring that they are treated with due care, properly maintained, and used and operated in a prudent manner.

1.4 Upon completion of the WORK, or at any other time as directed by Com-pany Representative, CONTRACTOR shall document as required by SAUDI ARAMCO, properly pack, identify and return unused or reusable SAUDI ARAMCO-supplied material, tools and equipment to any SAUDI ARAMCO designated location which is no further from the WORK Site than the original delivery point of such items. The condition of all returned SAUDI ARAMCO-supplied material, tools, and equipment shall be as good as when received by CONTRACTOR, normal wear and tear ex-cepted.

1.5 Except as noted in Paragraph 1.1 with regard to furnishing material out-side Saudi Arabia, SAUDI ARAMCO shall be responsible only for loading and unloading those SAUDI ARAMCO-supplied items located within a SAUDI ARAMCO-operated materials supply facility. CONTRACTOR, or its Affiliated Contractor shall provide ten (10) SAUDI ARAMCO work days advance written notice of its marine vessels' arrival at a commercial port or a SAUDI ARAMCO wharf facility for receipt of SAUDI ARAMCO-sup-plied items. CONTRACTOR shall be represented at the loading or un-loading for its entire duration, and shall sign a receiving form attesting to the quantity and condition of the SAUDI ARAMCO-supplied material, tools, and equipment upon receipt.

G-1MP-IK-LSTK 11/92OFF-IK-LSPBMP-IK-LSPBMP-LSTKRevised 3/06

Page 2: Schedule G

CONTRACT NO. /00

1.6 All SAUDI ARAMCO-supplied material, tools, and equipment deemed by the Company Representative to be unusable shall be documented as re-quired by SAUDI ARAMCO, and transported by CONTRACTOR to any SAUDI ARAMCO-designated disposal location, where CONTRACTOR shall make disposal in accordance with instructions received from the Company Representative.

2.0 CONTRACTOR-SUPPLIED MATERIALS, TOOLS AND EQUIPMENT

2.1 Except as provided in Paragraph 1, CONTRACTOR shall supply all ma-terials, tools and equipment, and all else required for the successful completion of the WORK. CONTRACTOR-supplied material shall be new and unused, and shall be procured in accordance with Attachment II of this Schedule "G".

2.2 Except for CONTRACTOR materials sourcing directed by COMPANY or SAUDI ARAMCO pursuant to Attachment IV of this Schedule "G", CONTRACTOR supplied material, its sources and related services shall be selected on the basis of financial, quality, schedule and technical capability, provided that Saudi Manufacturers, vendors and carriers shall be preferred in accordance with Paragraphs 3.0 and 4.0.

2.3 CONTRACTOR-supplied materials shall duplicate, or have interchange-able parts with, other similar materials either being used in the construc-tion of the FACILITIES or already listed in the SAUDI ARAMCO SAP R/3 Material Master catalog.

2.4 CONTRACTOR-supplied material shall comply with Saudi Arab Standards Organization (SASO) requirements. If a SASO certificate is required for CONTRACTOR-supplied materials, CONTRACTOR shall promptly forward a copy of the SASO-approved certificate to the Company Representative.

2.5 CONTRACTOR shall supply any special tools needed to install, adjust and maintain CONTRACTOR-supplied material.

2.6CONTRACTOR shall proceed in strict accordance with General Instruction 202.305, which is incorporated by reference in this Contract, to assign plant numbers and affix tags.

2.7SAUDI ARAMCO reserves the right to reject any CONTRACTOR proposed supplier, if such supplier does not meet the supplier selection requirements of Attachment III, Paragraph 4 of Schedule “Q” – Supplier Selection.

G-2MP-IK-LSTK 11/92OFF-IK-LSPBMP-IK-LSPBMP-LSTKRevised 11/09

Page 3: Schedule G

CONTRACT NO. /00

3.0 PREFERENCE FOR SAUDI VENDORS AND CARRIERS

SAUDI ARAMCO utilizes Saudi vendors and Saudi carriers for procuring and shipping a significant portion of its material requirements, and encourages its suppliers and contractors to utilize the services of these Saudi companies for a significant share of their procurement and transportation requirements for SAUDI ARAMCO projects.

Whenever CONTRACTOR procures material or makes transportation arrange-ments, SAUDI ARAMCO encourages CONTRACTOR to contact Saudi vendors, the two national ocean carriers, the National Shipping Company of Saudi Arabia (NSCSA) and the United Arab Shipping Company (UASC), and the national airline, Saudi Arabian Airlines (SAUDIA), or their representatives (full details of which may be obtained from SAUDI ARAMCO), and to give them the opportunity of quoting in respect to CONTRACTOR's requirements.

4.0 PREFERENCE FOR SAUDI MANUFACTURERS

4.1 "Saudi Manufacturers" are industrial establishments within Saudi Arabia who mine, manufacture or assemble products using reasonable amounts of local raw materials or local manpower in their production, as certified by the Ministry of Industry and Electricity.

4.2 As far as is practicable, CONTRACTOR shall standardize material types, sizes and characteristics so that products of Saudi manufacturers can be used as standard or acceptable alternative materials.

4.3 For each material requirement whose value exceeds Ten Thousand U.S. Dollars ($10,000), and for which SAUDI ARAMCO's Approved Local Manufacturers List in SAP R/3 lists a Saudi manufacturer, CONTRACTOR shall either directly purchase the materials from a technically acceptable Saudi manufacturer or develop competitive quotations from at least three (3) Saudi manufacturers. If less than three (3) manufacturers are listed then all shall receive quotation requests. If CONTRACTOR determines to purchase such material from a Saudi manufacturer, CONTRACTOR may place the order without further SAUDI ARAMCO involvement or compensation. Otherwise, CONTRACTOR shall advise SAUDI ARAMCO of:

4.3.1 the lowest technically acceptable Saudi manufacturer quotation, including the price F.O.B. the Manufacturer’s plant or warehouse plus the costs of moving the material to the WORK Site; and

G-3MP-IK-LSTK 11/92OFF-IK-LSPBMP-IK-LSPBMP-LSTKRevised 5/10

Page 4: Schedule G

CONTRACT NO. /00

4.3.2 the lowest technically acceptable non-Saudi manufacturer quo-tation, including the price F.O.B. the port of export plus the cost of export packing and preparation, insurance, Saudi Arab Customs Duties with the material Harmonized Codes, ocean freight, levies and port fees, and the other costs of moving the material to the WORK Site.

CONTRACTOR shall separately state the costs comprising each quota-tion in Saudi Riyals, converted, if necessary, at SAUDI ARAMCO's pre-vailing currency exchange rates.

4.4 Promptly after receipt of the two quotations described in Paragraphs 4.3.1 and 4.3.2, SAUDI ARAMCO shall have the right to direct CONTRACTOR to purchase the material from the Saudi manufacturer, and CONTRACTOR shall comply with SAUDI ARAMCO's direction. SAUDI ARAMCO's exercise of its right shall have no effect on any of CONTRAC-TOR's other obligations under this Contract, and the material so pur-chased shall be considered CONTRACTOR-supplied material.

4.5 If SAUDI ARAMCO exercises its right under Paragraph 4.4, upon receipt of the material at the WORK Site SAUDI ARAMCO shall pay CONTRAC-TOR an amount determined by subtracting the price described in Para-graph 4.3.2 from the price described in Paragraph 4.3.1. Except for this amount, SAUDI ARAMCO shall pay no other compensation of any kind arising out of or as a result of SAUDI ARAMCO's direction.

4.6 If CONTRACTOR's records do not establish CONTRACTOR's compliance with this Paragraph 4, CONTRACTOR shall pay SAUDI ARAMCO ten percent (10%) of the purchase price for material so procured.

5.0 ADDITIONAL MATERIALS

Should CONTRACTOR require additional material, SAUDI ARAMCO may, at its sole discretion, make available certain materials for the FACILITIES. Such materials shall be transferred by a letter, initiated by CONTRACTOR, and signed by both CONTRACTOR and SAUDI ARAMCO, and shall be considered SAUDI ARAMCO-supplied. The price for such materials shall be established solely by SAUDI ARAMCO at the time of the transfer. SAUDI ARAMCO shall accept the agreed transfer price as full and complete compensation for such transfers. Such material shall be made available to CONTRACTOR at a location specified by SAUDI ARAMCO. CONTRACTOR shall be responsible for collecting the material from its location and transporting it to the WORK Site. The agreed transfer price for such material shall be deducted from CONTRACTOR’s invoices by mean of an internal account. CONTRACTOR shall take such actions as may be necessary to establish this internal account prior to any transfers.

G-4MP-IK-LSTK 11/92OFF-IK-LSPBMP-IK-LSPBMP-LSTKRevised 3/06

Page 5: Schedule G

CONTRACT NO. /00

SAUDI ARAMCO shall not be obligated to accept for return any unused transferred material.

6.0 SAUDI ARAB CUSTOMS DUTY FOR CONTRACTOR-SUPPLIED TOOLSAND EQUIPMENT

CONTRACTOR shall not include in the Contract Price Saudi Arab Customs duties for any CONTRACTOR-supplied tools and equipment to be used in connection with the WORK and then re-exported. If CONTRACTOR re-exports such tools and equipment and is unable to obtain a refund of Saudi Arab Customs duties deposited with Saudi Arab Customs, SAUDI ARAMCO shall promptly reimburse CONTRACTOR for Saudi Arab Customs duties paid by CONTRACTOR on such tools and equipment. CONTRACTOR shall submit its invoice to SAUDI ARAMCO for such reimbursement accompanied with proof that CONTRACTOR has deposited the duties, re-exported the tools and equipment, and failed after reasonable effort to obtain a refund of deposited duties.

7.0 CAPITAL SPARE PARTS, START-UP SPARE PARTS, OPERATING SPARE PARTS AND OPERATING MATERIALS

7.1 CAPITAL SPARE PARTS: “Capital Spare Parts” are those major replacement parts or complete units essential to continuous operation when long delivery or manufacturing economy is a significant factor. Capital Spare Parts are subject to Start-up and Operating Spare Parts support the same as Parent Equipment. CONTRACTOR shall procure the Capital Spare Parts listed in Attachment III of this Schedule “G” concurrently with the procurement of Parent Equipment.

Prior to issuing purchase orders CONTRACTOR shall identify and recommend to SAUDI ARAMCO additional requirements for Capital Spare Parts not identified in Attachment III. The recommendations shall also include long lead time, machined, molded or cast parts which can best be supplied when included in the manufacturing schedule of the Parent Equipment, and their quoted material prices and any other information required for their justification. If SAUDI ARAMCO determines that additional Capital Spare Parts are necessary a Change Order will be issued.

7.2 START-UP SPARE PARTS: “Start-Up Spare Parts” are parts or components required during construction, pre-commissioning, and commissioning. CONTRACTOR shall provide the Start-Up Spare Parts associated with all CONTRACTOR-furnished equipment and specifically identified SAUDI ARAMCO-furnished equipment.

G-5MP-IK-LSTK 11/92OFF-IK-LSPBMP-IK-LSPBMP-LSTKRevised 3/06

Page 6: Schedule G

CONTRACT NO. /00

7.3 OPERATING SPARE PARTS: “Operating Spare Parts” are spare parts or components that are required for continuous operation of the plant, equipment, or system after commissioning of the FACILITY. SAUDI ARAMCO shall purchase and ship all Operating Spare Parts for all CONTRACTOR-furnished equipment, SAUDI ARAMCO-furnished equipment, or Capital Spare Parts.

7.4 OPERATING MATERIALS: “Operating Materials” are consumable materials that are required for the continuous operation of the facility and are consumed in the normal course of operations and, therefore, require periodic replenishment. CONTRACTOR shall supply all required quantities of chemicals, filtration materials, lubricants, desiccants, industrial gases, emulsifiers, batteries, transformer oils, and any other catalysts, operating fluids, consumable, and materials required for the initial charge, pre-commissioning and start-up, and commissioning of the FACILITIES. All unused materials provided in accordance with this Paragraph shall be properly packed and documented by CONTRACTOR and shall become the property of SAUDI ARAMCO. CONTRACTOR shall also provide a forecast of the initial charge and start-up quantities of all items referenced in this Paragraph to SAUDI ARAMCO no later than twelve (12) months prior to Mechanical Completion of the FACILITIES, or each separable portion thereof, achieving partial Mechanical Completion. The forecast shall include quantities expected during Start-up and normal maximum and minimum operating conditions as well as during summer and winter operating conditions, and any other limiting conditions. CONTRACTOR shall identify the cataloged Material Master numbers (9CAT’s) for the same or equivalent bulk chemicals and lubricants that are in the SAP R/3 Material Master catalog and include these in the applicable Project Record Books.

8.0 DATA ACQUISITION FOR OPERATING SPARE PARTS AND OPERATINGMATERIALS

CONTRACTOR shall provide to SAUDI ARAMCO all Vendor and Sub-Vendor data on Operating Spare Parts and Operating Materials in strict accordance with the instructions contained in SAEP-3101. For the purposes of establishing Contract payments pursuant to Schedule “C”, procurement of any equipment or material item shall not be considered complete unless the CONTRACTOR has submitted, and SAUDI ARAMCO has approved, the Operating Spare Parts Data and Operating Materials Data required per SAEP-3101.

9.0 LIFE CYCLE COSTING (LCC)

9.1 CONTRACTOR shall obtain competitive quotations from at least three manufacturers for the equipment identified in Paragraph 3 of the

G-6MP-IK-LSTK 11/92OFF-IK-LSPBMP-IK-LSPBMP-LSTKRevised 11/09

Page 7: Schedule G

CONTRACT NO. /00

Attachment IV in this Schedule, and ensure that each quotation includes the specific LCC data elements required therein.

9.2 CONTRACTOR shall technically evaluate the quotations received, by ascending commercial value, until three or more are considered acceptable or until all quotations received have been evaluated, and provide SAUDI ARAMCO a copy of each technically acceptable quotation. The quotation shall identity the specific LCC data elements required in Paragraph 3 of the Attachment IV in this Schedule, the price F.O.B. port of export, and costs for export packing and preparation, insurance, ocean freight, levies and port fees, and all other costs to deliver the goods to the WORK Site. CONTRACTOR shall identify CONTRACTOR’s proposed source of supply, and separately detail any additional costs that would be incurred should SAUDI ARAMCO direct CONTRACTOR to purchase the equipment from another source. All cost or price information shall be converted to US Dollars at SAUDI ARAMCO’s prevailing currency exchange rates.

9.3 Within ten (10) working days after receipt of acceptable quotation copies and the price and cost information described in Paragraph 2, SAUDI ARAMCO shall have the right to direct CONTRACTOR to purchase the equipment from any manufacturer technically qualified by CONTRACTOR other than the CONTRACTOR’s proposed source of supply. CONTRACTOR shall comply with SAUDI ARAMCO’s direction. If SAUDI ARAMCO exercises its right, it shall compensate CONTRACTOR for any difference between the total delivered equipment cost (as determined pursuant to paragraph 2 above) of CONTRACTOR’s proposed source of supply and that of the SAUDI ARAMCO directed manufacturer. SAUDI ARAMCO’s exercise of its right shall have no effect on any of CONTRACTOR’s other obligations under this Contract, and the equipment so purchased shall be considered CONTRACTOR-supplied equipment.

9.4 If the equipment purchased fails to meet the efficiency warranty set forth in the applicable SAMSS as stated in SAEP-341, CONTRACTOR shall pay SAUDI ARAMCO in accordance with the penalty provisions included in the Guarantee And Warranty section of that applicable SAMSS.

9.5 If CONTRACTOR’s records do not establish CONTRACTOR’s compliance with these Life Cycle Costing Requirements, CONTRACTOR shall pay SAUDI ARAMCO ten percent (10%) of the purchase price for equipment so procured.

G-7MP-IK-LSTK 11/92OFF-IK-LSPBMP-IK-LSPBMP-LSTKRevised 3/06

Page 8: Schedule G

CONTRACT NO. /00

10.0 TRANSLATION

Because of the technical nature of Attachment I, it has not been translated into Arabic. CONTRACTOR and SAUDI ARAMCO agree to be bound by the English text.

END OF SCHEDULE "G"

G-8MP-IK-LSTK 11/92OFF-IK-LSPBMP-IK-LSPBMP-LSTKRevised 3/06

Page 9: Schedule G

CONTRACT NO.

SCHEDULE "G"

ATTACHMENT I

SAUDI ARAMCO-SUPPLIED MATERIALS, TOOLS AND EQUIPMENT

1.0 SAUDI ARAMCO-SUPPLIED MATERIAL

Description Unit Quantity Delivery Point

None

2.0 SAUDI ARAMCO-SUPPLIED TOOLS AND EQUIPMENT

Description Unit Quantity Delivery Point

None

END OF ATTACHMENT I

G-I-1 of 1MP-IK-LSTK 11/92OFF-IK-LSPBMP-IK-LSPBMP-LSTKRevised 4/01

Page 10: Schedule G

CONTRACT NO.

SCHEDULE "G"

ATTACHMENT II

MATERIALS PROCUREMENT BY CONTRACTOR

1.0 CONTRACTOR's PROCUREMENT PLAN

CONTRACTOR shall submit for SAUDI ARAMCO's review a Procurement Plan within thirty (30) days after the effective date of this Contract. At minimum, the Procurement Plan shall cover the following:

1.1 A description of the procurement process and the way procurement in-formation will flow from quotation development through delivery to WORK Site.

1.2 A description of engineering/procurement/purchasing interfaces, correc-tive actions, and procedures for SAUDI ARAMCO review of documents when required.

1.3 A description of all periodic reports to be produced and their scheduled issue dates, which reports shall include a Monthly Materials Procurement Status Report.

1.4 A procedure for accomplishing the standardization of material pursuant to Schedule "G" and detailed procedures for control of all material substi-tutions.

1.5 A procedure for safeguarding and controlling all CONTRACTOR-supplied and SAUDI ARAMCO-supplied materials at the WORK Site, including the continuous maintenance and control of records of identification, receipt and issuance and all other materials control and materials management procedures required to ensure the uninterrupted flow of equipment and materials.

2.0 CONTRACTOR'S PROCUREMENT DOCUMENTS

2.1 CONTRACTOR shall analyze all bids and, if requested by SAUDI ARAMCO, provide the technical and scheduling details of any proposed placement.

G-II-1 of 6MP-IK-LSTK 11/92OFF-IK-LSPBMP-IK-LSPBMP-LSTKRevised 4/01

Page 11: Schedule G

2.2 All CONTRACTOR’s requisitions and purchase orders shall also be numbered using SAUDI ARAMCO's purchase order numbering system. SAUDI ARAMCO's number shall be used on all documentation and shall be listed in CONTRACTOR reports as directed by SAUDI ARAMCO.

2.3 CONTRACTOR's purchase orders and quotation requests shall include the following requirements:

2.3.1 Applicable SAMSS's, SAES's, project specifications, and standard drawings. Where a sub-supplier will be involved, the CONTRACTOR shall require the supplier to distribute these attachments to the sub-supplier as part of the order to sub-supplier.

2.3.2 Inspection and testing requirements per the applicable Saudi Aramco Form SA-175.

2.3.3 Listing of supplier Non-Material Requirements (NMR's), referencing SA-7900 Series forms.

2.3.4 Listing of supplier QA records to be prepared, submitted, or made available for CONTRACTOR's and COMPANY's review and approval. (e.g. refractory installation, welding, repair, heat treatment procedures, welder qualifications, Hydrotesting, coating and Nondestructive Testing [NDT] procedures).

2.3.5 Provision for COMPANY's and CONTRACTOR's right of access to the supplier’s facility and WORK documents for inspection and audit per paragraph 1.5 of Schedule Q.

2.3.6 CONTRACTOR supplemental technical specifications

2.3.7 Capital Spare Parts per Schedule "G", Attachment III or as otherwise required by SAUDI ARAMCO.

2.3.8 Spare parts data requirements per Schedule "G".

2.3.9 Operating and maintenance manuals requirements.

2.3.10 Special tools to install, adjust and maintain equipment during start-up. Special tools needed for subsequent maintenance shall be provided and turned over to SAUDI ARAMCO at Project Completion.

G-II-2 of 6MP-IK-LSTK 11/92OFF-IK-LSPBMP-IK-LSPBMP-LSTKRevised 3/06

Page 12: Schedule G

2.3.11 Vendor representatives as agreed necessary for start up of equipment.

2.3.12 All information submitted shall be in the English language and units of measure as indicated in the job specification.

2.4 CONTRACTOR shall ensure that all applicable provisions of Schedule “Q” are included in all requisitions and purchase orders to suppliers and their subsuppliers.

2.5 CONTRACTOR requisitions shall be submitted to the Company Representative for review prior to placement of each Purchase Order.

3.0 MATERIALS PROCUREMENT STATUS REPORT

3.1 CONTRACTOR shall issue a Materials Status report monthly, or as otherwise requested, reporting on the status of each requisition and order. The report shall identify and track the procurement of all materials, including schedule, forecast and actual procurement milestone dates, and specifically identify all long lead items, vessels, heavy lift/oversized equipment items, specialized installation equipment, and special fabrication items. Standard CONTRACTOR reports may be used if such reports are acceptable to SAUDI ARAMCO. For all purchases the report shall include information on at least the following:

3.1.1 Quotation/requisition number and date issued for bid3.1.2 Identify if Saudi Manufacturer Equalization may be required3.1.3 Contractor Order number and date placed3.1.4 Corresponding SAUDI ARAMCO Order number3.1.5 Vendor and country of manufacture3.1.6 Change Order/revision number and date3.1.7 Brief description3.1.8 Item and tag number3.1.9 Required delivery date of design drawings/data for approval3.1.10 Delivery date for equipment/materials3.1.11 Receipt Date3.1.12 Receiving Inspection Results3.1.13 Non-Material Requirements received or missing3.1.14 Preservation Requirements received and implemented.

3.2 Identification of Source of Material

CONTRACTOR shall provide information to COMPANY/SAUDI ARAMCO on the source of all material provided by CONTRACTOR.

G-II-3 of 6MP-IK-LSTK 11/92OFF-IK-LSPBMP-IK-LSPBMP-LSTKRevised 3/06

Page 13: Schedule G

3.2.1 The source of material shall be identified as one of the following:

3.2.1.1 “Saudi Manufacturer” which means a Saudi registered company that manufactures or assembles material or equipment within Saudi Arabia. This category applies regardless of whether a Purchase Order has been placed directly with the Saudi Manufacturer or with a third party agent or vendor.

3.2.1.2 “OOK Manufacturer” which means a company that manufactures or assembles material or equipment outside of Saudi Arabia.

3.2.1.3 “Saudi Vendor” which means a Saudi registered company that acts on behalf of an OOK Manufacturer and is party to the Purchase Order executed by the CONTRACTOR.

3.2.2 List of Purchase Orders

3.2.2.1 CONTRACTOR shall prepare and provide to COMPANY/SAUDI ARAMCO a list of all Purchase Orders for material or equipment that indicates the actual or, for unplaced Purchase Orders, the likely source of the material (“Purchase Order Source of Material List”). The Source of Material List shall identify the portion of the Material Price associated with each Purchase Order. The sum of the amounts for all Purchase Orders shall be equal to 100% of the Material Price.

3.2.2.2 To the extent that a list of Purchase Orders has been included in Schedule “C” and/or a list of Purchase Orders is required for and has been prepared for determining progress payment for the Material Price, the Purchase Order Source of Material List shall be consistent with such other lists in respect to the items listed and portions of the Materials Prices associated with each item. Subject to the concurrence of the Company Representative, a single list may be used to determine progress payments for the Material Price and to serve as the Source of Material List.

3.2.2.3 In addition to the source of material and associated portion of the Material Price, the Purchase Order Source of Material List shall include:

G-II-4 of 6MP-IK-LSTK 11/92OFF-IK-LSPBMP-IK-LSPBMP-LSTKRevised 3/06

Page 14: Schedule G

3.2.2.3.1 The actual or forecast dates for PR issue, PO placement, shipment, and arrival at the site.

3.2.2.3.2 For placed Purchase Orders, the name of the Saudi Manufacturer or OOK Manufacturer and, if applicable, the name of the Saudi Vendor.

3.2.2.4 The Purchase Order Source of Material List shall be provided to COMPANY/SAUDI ARAMCO by CONTRACTOR at the end of every month every month from the month in which the first Purchase Order is placed until the month in which all materials, have been received at the WORK. All invoices for portions of the Material Price shall include an attachment that breaks down the portion of the Material Price being invoiced into separate amounts for each source of material. Progress Payments for portions of the Material Price will not be made until an up-to-date and compliant Purchase Order Source of Material List and the breakdown of the amount being invoiced has been received by COMPANY/SAUDI ARAMCO.

3.2.3 Detailed Electronic Contractor Procurement Report

CONTRACTOR shall compete and provide to COMPANY/SAUDI ARAMCO at the end of every month, from the month in which the first Purchase Order is placed until the month in which the last Purchase Order has been placed, a detailed, line item-level report for placed Purchase Orders by utilizing the program and in the format provided by COMPANY/SAUDI ARAMCO. The value of line items shall be calculated as portions of the Material Price associated with each Purchase Order.

4.0 PROCUREMENT CORRESPONDENCE

All correspondence, specifications, drawings, data on spare parts and special tools, or other papers pertaining to procurement shall bear the following refer-ences:

4.1 Name of FACILITIES and location4.2 Symbol or code of FACILITIES4.3 Equipment plant tag numbers, if any4.4 SAUDI ARAMCO Contract number4.5 Quotation request or purchase order number4.6 Corresponding SAUDI ARAMCO Order number

G-II-5 of 6MP-IK-LSTK 11/92OFF-IK-LSPBMP-IK-LSPBMP-LSTKRevised 3/06

Page 15: Schedule G

5.0 SHIPPING AND HANDLING

5.1 CONTRACTOR shall be responsible for shipping, export customs duties, storage and care and protection of materials to be imported into Saudi Arabia. CONTRACTOR shall be responsible for clearing the material through Saudi Arabia Customs, offloading, inspection on receipt, delivery to the WORK Site, and care and protection of material in Saudi Arabia until Mechanical Completion.

5.2 CONTRACTOR shall arrange for all In-Kingdom heavy lifts including all coordination activities with Saudi Arab traffic authorities and Saudi Electric Company (SEC). CONTRACTOR shall provide equipment necessary to offload at the port, transport to WORK Site, offload and position the equipment at WORK Site.

END OF ATTACHMENT II

G-II-6 of 6MP-IK-LSTK 11/92OFF-IK-LSPBMP-IK-LSPBMP-LSTKRevised 3/06

Page 16: Schedule G

CONTRACT NO.

SCHEDULE "G"

ATTACHMENT III

CAPITAL SPARE PARTS

None

END OF ATTACHMENT III

G-III-1 of 1MP-IK-LSTK 11/92OFF-IK-LSPBMP-IK-LSPBMP-LSTKRevised 4/01

Page 17: Schedule G

CONTRACT NO.

SCHEDULE "G"

ATTACHMENT IV

SAUDI ARAMCO DIRECTED SOURCING OF MATERIALS

1. CONTRACTOR material sourcing directed by SAUDI ARAMCO Standards:

1.1 CONTRACTOR shall solicit quotations and purchase materials and equipment from only the sources identified for those materials listed in the SAUDI ARAMCO’s Regulated Vendor List (RVL) and the following SAUDI ARAMCO Engineering Standards, unless otherwise approved by SAUDI ARAMCO per Paragraph 1.2 below.

1.1.1 SAES-J-002 Technically Acceptable Instruments

1.1.2 SAES-Y-100 Regulated Vendors List for Custody Measurement Equipment

1.1.3 SAES-Z-002 Technically Accepted Process Automation Systems

1.2 To capture technical or material pricing advantages, CONTRACTOR is encouraged to propose vendors other than those identified under Paragraph 1.1 of this Attachment, in which case CONTRACTOR shall qualify any proposed vendors per Schedule “Q”, Attachment III, Paragraph 4. If such a vendor is considered qualified by SAUDI ARAMCO, then SAUDI ARAMCO and CONTRACTOR shall equally share any material pricing benefit as follows:

CONTRACTOR shall submit a change order request crediting SAUDI ARAMCO for one-half (fifty percent) of the difference between the proposed vendors price and the lowest price obtained from a competitive development with all vendors on the applicable regulated list under Paragraph 1.1 of this Attachment. Copies of all applicable vendor proposals shall be included in CONTRACTOR’s submittal. SAUDI ARAMCO’s decision to adopt or reject the proposal shall be final and binding on both parties.

G-IV-1 of 2MP-IK-LSTK 11/92OFF-IK-LSPBMP-IK-LSPBMP-LSTKRevised 11/09

Page 18: Schedule G

CONTRACT NO.

2. CONTRACTOR material sourcing directed by the specific requirements of this SAUDI ARAMCO Contract:

CONTRACTOR shall solicit quotations and purchase requirements only from the sources identified for the materials listed below:

(Free form input by the Contract proponent)

3. Life Cycle Costing (LCC)

3.1 CONTRACTOR shall provide quotations that include the specific data elements as required by SAEP-341 Paragraph 2 for the following equipment:

Equipment Description TAG Number

None

END OF ATTACHMENT IV

G-IV-2 of 2MP-IK-LSTK 11/92OFF-IK-LSPBMP-IK-LSPBMP-LSTKRevised 6/02