SCAN UPDATE SEGMENT 18811, 19915 ROW OCS-G28684 United States Department of the Interior BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT Gulf of Mexico OCS Region 1201 Elmwood Park Boulevard New Orleans, Louisiana 70123-2394 In Reply Refer To: GE 1035A Ms. Kemberlia Ducote LLOG Exploration Offshore, L.L.C. 1001 Ochsner Boulevard Suite 200 Covington, LA 70433 Dear Mr. Ducote: January 11,2018 Reference is made to your request dated December 14, 2017, received by this office on December 15, 2017, to modify Pipeline Segment No. 18811 by retrieving an associated flowline jumper from Neidermeyer Manifold to a PLET, all in Mississippi Canyon Area Block 253. The jumper is being removed to aid in the investigation of failure incident of a well jumper associated with Pipeline SegmentNo. 19174. A separate application will be submitted to install a new jumper. The pipeline prior to flowline jumper removal is described as follows: Segment No. Size (Inches) Length (feet) Service Origin Destination 18811 06 27,599 Bulk Oil Neidermeyer Manifold A-Delta House Mississippi Canyon Mississippi Canyon Block 253 Block 254 The pipeline after well iumper removal is described as follows: Segment No. Size (Inches) Length (feet) Service Origin Destination 18811 06 27,539 Bulk Oil PLET A-Delta House Mississippi Canyon Mississippi Canyon Block 253 Block 254 The proposed flowline jumper to be removed follows: is assigned SegmentNo. 19915 is described as Segment No. Size (Inches) Length (feet) Service Origin Destination 19915 06 60 Bulk Oil Neidermeyer Manifold PLET Mississippi Canyon Mississippi Canyon Block 253 Block 253 Pursuant to 30 CER 250.1000(b), your application is hereby approved.

SCAN UPDATE ROW OCS-G28684 United States Department …3.3 ROV to setup rigging on jumper and prepare to make cuts. 3.4 ROV to use super grinder to make cuts on belly 1' past the bend

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: SCAN UPDATE ROW OCS-G28684 United States Department …3.3 ROV to setup rigging on jumper and prepare to make cuts. 3.4 ROV to use super grinder to make cuts on belly 1' past the bend

SCAN UPDATE SEGMENT 18811, 19915 ROW OCS-G28684

United States Department of the Interior BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT

Gulf of Mexico OCS Region 1201 Elmwood Park Boulevard

New Orleans, Louisiana 70123-2394

In Reply Refer To: GE 1035A

Ms. Kemberlia Ducote LLOG Exploration Offshore, L.L.C. 1001 Ochsner Boulevard Suite 200

Covington, LA 70433

Dear Mr. Ducote:

January 11,2018

Reference is made to your request dated December 14, 2017, received by this office on December 15, 2017, to modify Pipeline Segment No. 18811 by retrieving an associated flowline jumper from Neidermeyer Manifold to a PLET, all in Mississippi Canyon Area Block 253. The jumper is being removed to aid in the investigation of failure incident of a well jumper associated with Pipeline SegmentNo. 19174.

A separate application will be submitted to install a new jumper.

The pipeline prior to flowline jumper removal is described as follows:

Segment No.

Size (Inches)

Length (feet)

Service Origin Destination

18811 06 27,599 Bulk Oil Neidermeyer Manifold A-Delta House Mississippi Canyon Mississippi Canyon Block 253 Block 254

The pipeline after well iumper removal is described as follows:

Segment No.

Size (Inches)

Length (feet)

Service Origin Destination

18811 06 27,539 Bulk Oil PLET A-Delta House Mississippi Canyon Mississippi Canyon Block 253 Block 254

The proposed flowline jumper to be removed follows:

is assigned SegmentNo. 19915 is described as

Segment No.

Size (Inches)

Length (feet)

Service Origin Destination

19915 06 60 Bulk Oil Neidermeyer Manifold PLET Mississippi Canyon Mississippi Canyon Block 253 Block 253

Pursuant to 30 CER 250.1000(b), your application is hereby approved.

Page 2: SCAN UPDATE ROW OCS-G28684 United States Department …3.3 ROV to setup rigging on jumper and prepare to make cuts. 3.4 ROV to use super grinder to make cuts on belly 1' past the bend

Right-of-way No. OCS-G28684 is described as follows:

Pipeline Right-of-Way (ROW) OCS-G28684 is a 200-foot wide and approximately 5.22 miles (27,539feet) long corridor associated with the 06-5/8-inch bi-directional Pipeline Segment No. (PSN) 18811. The purpose of pipeline ROW OCS-G28684 is to operate and maintain PSN 18811 and to transport bulk oil from a Pipeline End Terminal (PLET) in Block 253 to Platform A (Delta House) in Block 254, all in Mississippi Canyon Area.

Assigned MAOP (psi):10,000 MAOP Determination: Valves, Flanges, Subsea Segment

You shall submit written notification to this office within 30 days of the completion of the pipeline modification. This notification shall include the date the modification was completed, forensic investigation findings, and an indication that the modification was completed as approved.

Sincerely,

BIMAL SHRESTHA

Digitally signed by BIMAL SHRESTHA Date: 2018.01.11 12:58:24 -06'00'

For: Bryan A. Domangue Acting Regional Supervisor Regional Field Operations

Page 3: SCAN UPDATE ROW OCS-G28684 United States Department …3.3 ROV to setup rigging on jumper and prepare to make cuts. 3.4 ROV to use super grinder to make cuts on belly 1' past the bend

D exploration offshore

December 14, 2017

Regional Supervisor Field Operations Bureau of Safety and Environmental Enforcement 1201 Elmwood Park Boulevard New Orleans, Louisiana 70123-2394 GE 1035A

Attention: Angie/Gobert/Philip Smith Pipeline Unit

RE: Application to Modify the Approved Right-of-Wav Pipeline (SN 18811) Consisting of (1) 6.625" O.D. Right-of-Way Flowline Jumper (Segment No. 18811), from Mississippi Canyon 253 Subsea Manifold, Mississippi Canyon Block 253, OCS-G-24062, to the Mississippi Canyon 253 PLET, Mississippi Canyon Block 253, OCS-G-24062, Gulf of Mexico, Offshore Louisiana

Dear Ladies and Gentleman:

Under the provisions of Title 30 CFR, Section 250 Subpart J and Title 30 CFR, Section 250 Subpart Q, LLOG Exploration Offshore, L.L.C. (LLOG) hereby submits this application in quadruplicate (original and 3 copies) for the modification of the Lease Term Pipeline Segment No. 19174.

In 2014, LLOG installed one (1) 6.625" O.D. Flowline Jumper (Segment No. 18811) fiom Mississippi Canyon 253 Subsea Manifold, Mississippi Canyon Block 253, OCS-G-24062, to the Mississippi Canyon 253 PLET, Mississippi Canyon Block 253, OCS-G-24062, Gulf of Mexico, Offshore Louisiana.

The proposed modification consists of the removal of the existing Flowline Jumper following a recent subsea inspection and structural assessment.

In support of this modification, LLOG submits the following attachments:

Proposed Removal Procedures MC 253 Flowline Jumper Details MC 253 Well Site Layout Payment Confirmation

LLOG is prepared to begin the removal as soon as possible; therefore, your earliest review and consideration will be greatly appreciated.

The installation of a new Flowline Jumper will be captured in a subsequent submission as part of this modification application. LLOG will be prepared to install a new Flowline Jumper as soon as possible.

Inquiries concerning this application should be first directed to Edie Ridgel of LLOG Exploration Offshore, L.L.C. at edier(a),llog.com. 985.801.4344. Inquires can also be directed to Mr. Glenn Mediamolle, Jr. of LLOG Exploration Offshore, L.L.C. at [email protected].

LLOG L.xplot at ion Ot lshore

lOfll Orhsner HoulmranI, Suite 100

Covincjion, Louisirnui

p 985 BUI 430(1

f 9ui) BOI /.-m V/WVJ (log corn

Page 4: SCAN UPDATE ROW OCS-G28684 United States Department …3.3 ROV to setup rigging on jumper and prepare to make cuts. 3.4 ROV to use super grinder to make cuts on belly 1' past the bend

985.801.4300 or Mr. Pete Cruz of Pinnacle Engineering Company at petec^pinnacleengr.com. 713.784.1005.

Sincerely,

LLOG Exploration Offshore, L.L.C.

Kemberlia Ducote Secretary

Attachments & Enclosures

Page 5: SCAN UPDATE ROW OCS-G28684 United States Department …3.3 ROV to setup rigging on jumper and prepare to make cuts. 3.4 ROV to use super grinder to make cuts on belly 1' past the bend

A PINNACLE L % E N G I N E E R I N G LL0G

e x p l o r a t i o n

Document Title: Neidermeyer South Flowline Jumper Recovery Procedure

Project Name: Delta House Jumper Recovery

Pinnacle Doc. No. PRD007-203128 Pinnacle Job No. 203128

Signature Legend:

ID: MED PAC

Name: Mike Demmer Pete Cruz

Title: Project Engineer Project Manager

Job #s: Delta House Jumper Recovery

203128 - Inspector charge to 203198 - AFE SI7476002-1

Pinnacle Engineering, Inc. LLOG Exploration Company

Approval Status Description

A Issued for Review MED PAC 12/13/17 For hifonnation Only.

Rev Description Origin Check Approval Date Name Date

Delta House MC 253 South Flowline Jumper Recovery Rev A Page 1 of6

Page 6: SCAN UPDATE ROW OCS-G28684 United States Department …3.3 ROV to setup rigging on jumper and prepare to make cuts. 3.4 ROV to use super grinder to make cuts on belly 1' past the bend

Document Title: Flowline Jumper Recovery Procedure Revision No.: A Revision Date: 12/13/17

Contact Name Company Phone Offshore

Glenn Mediamolle glennm(S)llog.com

LLOG 985.801.4765 W Construction Manager

Glenn Mediamolle glennm(S)llog.com

985.640.7515 M Construction Manager Offshore Construction Manager

Julian Williams Julian.Williams(5)llog.com

LLOG 985.801.4767 W 985.377.3837 M

Mike Demmer Pinnacle 713.784.1005 W Project Manager mdememer(S)pinnacleengr. com 210.394.0485 M

Offshore Inspectors Pinnacle 713.784.1005 W

MC 254 "A", Delta Delta House LLOG 337.761.8706 House Control

Room MC 254 "A", Delta Aron Steinocher & John LLOG 985.801.4704 W House Operations Leimkuhler 985.789.3302 M Engineer & Aron.steinocher(S),llog.com 985.801.4748 W Facilities Engineer [email protected] 985.789.2417 M MC 254 "A", Delta Hilton Weaver LLOG 337.761.8701 House Foreman Hilton.weaver(S)llogproduction.com

MC 254 "A", Delta House OIMs

Hilton Weaver & Joe Keller LLOG 337.761.8701 MC 254 "A", Delta House OIMs Joe.kellerraUloaproduction.com

Hilton.weaverroUlogproduction.com MC 254 'A", Delta Chuck Breaux & Gene Lord LLOG 337.761.8702 House Operation Chuck.breaux(a)llo gproduction. com Supervisor Gene. lord(2)llo aproduction .com LLOG Fourchon fourchonbase(S)llog.com LLOG 985.396.4110 Wl Base TumKey Dock

fourchonsup(aUlo a .com 985.396.0404 W2

164 Dudley Bemard Rd. Fourchon, La 70357 Dispatcher whodatbase(S)lloa.com LLOG 985.396.4048

Flight Logistics logistics(S)llog.com LLOG

Page 2 of 6

Page 7: SCAN UPDATE ROW OCS-G28684 United States Department …3.3 ROV to setup rigging on jumper and prepare to make cuts. 3.4 ROV to use super grinder to make cuts on belly 1' past the bend

Document Title: Flowline Jumper Recovery Procedure Revision No.: A Revision Date: 12/13/17

Section

1

2

3

4

Table of Contents

Introduction

General Information

Jumper Removal

Drawings

Page

4

4

4

7

Page 3 of 6

Page 8: SCAN UPDATE ROW OCS-G28684 United States Department …3.3 ROV to setup rigging on jumper and prepare to make cuts. 3.4 ROV to use super grinder to make cuts on belly 1' past the bend

Document Title: Flowline Jumper Recovery Procedure Revision No.: A Revision Date: 12/13/17

1.0 Introduction

LLOG has done recent metrology on the Neidermeyer field and have determined that the south flowline jumper needs to be recovered and reworked due to changes in the initial metrology measurements.

2.0 General Information

2.1 Locations

MC 253 South PLET (flowline) SN 18811

2.2 6" Jumper

6.625"OD x 0.750" WT, API 5L Gr. X65 Insulation: GSPU, 2" thick Jumper length/weight in air:

MC 253 South: 60714 Kips

2.3 Initial Conditions -Jumper will be flushed with brine to 2 times the jumper volume prior to arriving in the field

-The plet and manifold valves will be closed after the flushing operation.

3.0 Jumper Removal

3.1 Mobilize ROV vessel to MC 253 Neidermeyer field.

3.2 Locate jumper and perform video survey. Call Delta House and confirm the Neidermeyer field is powered down and wells are shut in.

3.3 ROV to setup rigging on jumper and prepare to make cuts.

3.4 ROV to use super grinder to make cuts on belly 1' past the bend tangents.

3.5 Install plugs and recover belly section of jumper first.

3.6 ROV to rig up to PLET-side of jumper and unlatch the KLV8 as per FMC operating procedure. Install plugs and recover section to deck and put in containment or cutting box.

Page 4 of 6

Page 9: SCAN UPDATE ROW OCS-G28684 United States Department …3.3 ROV to setup rigging on jumper and prepare to make cuts. 3.4 ROV to use super grinder to make cuts on belly 1' past the bend

Document Title: Flowline Jumper Recovery Procedure Revision No.: A Revision Date: 12/13/17

3.7 ROV to rig up to MANF-side of jumper and unlatch the KLV8 as per FMC operating procedure. Install plugs and recover section to deck and put in containment or cutting box.

3.8 Inspect pipe with NORM Meter.

3.9 Verify pipe ends are still capped to prevent oxidation.

3.10 Install FMC short term protection caps on plet and manifold hubs.

3.11 Demobilize

Page 5 of 6

Page 10: SCAN UPDATE ROW OCS-G28684 United States Department …3.3 ROV to setup rigging on jumper and prepare to make cuts. 3.4 ROV to use super grinder to make cuts on belly 1' past the bend

Document Title: Flowline Jumper Recovery Procedure Revision No.: A Revision Date: 12/13/17

4.0 Drawings

Drawing No. Rev. Title

203100-9007A 6 MC 253 Wellsite Layout Neidermeyer

203100-9019B 1 Neidermeyer PLET Jumper Details South PLET Jumper Spool

OPR10039959 E Operating Procedure for KLV8

Page 6 of 6

Page 11: SCAN UPDATE ROW OCS-G28684 United States Department …3.3 ROV to setup rigging on jumper and prepare to make cuts. 3.4 ROV to use super grinder to make cuts on belly 1' past the bend

eo-o" (FABRICATE AT 70-0". FIELD TRIM TO FIT)

40-0"

MATERIAL SUMMARY ITEM QTY. WT. (kips) DESCRIPTION

1 120 L.F. 7.91 PIPE, 6^80 x 0.750 WT, API 5L GR X65, PSL2, SEAMLESS, 12-14 MILS

FBE, WITH 2.0" GSPU

2 ONE 3.00 6 ' KLV8 CLAMP CONNECTOR ASSEMBLY, 10K, COMPLETE WITH 60" PUP

OF 6.625" x 0.750 WT GR. X70 PIPE, FMC TECHNOLOGIES

3 ONE 3.00 8 ' KLV8 CLAMP CONNECTOR ASSEMBLY. 10K. COMPLETE WITH 60" PUP

OF 8.625" x 1.000 WT GR. X70 PIPE. FMC TECHNOLOGIES

4 2 0.04 eo. ROV PANEL, KLV8, FMC, FOR 6.625" 00 PIPE (TO FIT UNDER GSPU INSULATED

PIPE, REF. FMC TECHNOLOGIES DWG. DU100079316) (ROV PANEL TO BE

INSTALLED AND PLUMBED BY FMC PERSONNEL AT FABRICATION YARO)^

ONE - REDUCER, 8" x 6", CONCENTRIC, ENOS PREPPED TO 8.625" x 1.000 WT )

AND 6.625" x 0.750 WT, ASTW A860, WPHY65 ^ ^ - ^ - ^ — - ~

13.99 kips

ELEVATION

6" SOUTH PLET JUMPER SPOOL DETAILS SCALE: V8"=r-0"

33

NEIDERMEYER SATELLITE PLET JUMPER SPOOL (REF. DWG. 9019C)

NORTH PLET JUMPER SPOOL (REF. DWG. 9019A)

SOUTH PLET JUMPER SPOOL (REF. DETAIL)

WELL JUMPER SPOOL (REF. DWG. 9015A)

WELL JUMPER SPOOL (REF. DWG. 9015B)

MC 253 WELL SS001 CONNECTORS CLOCKED TO POSITION 2 ON BOTH ENDS

SECTION SCALE: N.T.S.

Haang a

mm Z m o u ^ NOTES

I. HYDROTEST: THE 6̂ 8(9 JUMPER SPOOL SHALL BE HYDROTESTED TO A MINIMUM OF 12,500 (-0. +200) PSI ANO HELD FOR A PERIOD OF 4 HOURS. THE PRESSURE SHALL HOLD OR RISE OVER THE LAST TWO HOURS.

THIS DRAWING IS THE PROPERTY OF AND EMBODIES CONFIDENTIAL INFORMATION OF PINNACLE ENGINEERING. INC. k LLOG EXPLORATION OFFSHORE INC. THIS DRAWING AND THE INFORMATION THEREON SHALL NOT BE REPRODUCED OR DISCLOSED TO ANY OTHER PARTY OR USED FOR ANY OTHER PURPOSE OTHER THAN FOR THE BENEFIT OF ANO AS AUTHORIZED BY PINNACLE ENGINEERING, INC. OR LLOG EXPLORATION OFFSHORE INC.

1 Vl-K ADDED REDUCER m *c 0 6-10-14 APPROVED FOR CONSTRUCTION ROD PAC NO. DMt KSCRPTICH Br

JUL 112im APPROVED FOR •eONSTRU CTION

MC 208 WELL SSOOl

MC 253 NEIDERMEYER WELL SITE KEY PLAN SCALE: r=50'-0"

If r. w% $ PETER A. CRUZ <i

" • 90900 „

PINNACLE C I N E E R I N C

TX REGISTERED ENGR FIRM F-567

Drawn By J. GUEVARA Dote 10-24-13 Checked By R. DETHLOFF Date 6-10-H Designed By Date Approved By P. CRUZ Dote 6-10-14

LLOG e x p l o r a t i o n

DELTA HOUSE SUBSEA DEVELOPMENT MISSISSIPPI CANYON 254

NEIDERMEYER PLET JUMPER DETAILS SOUTH PLET JUMPER SPOOL

JOB NO. 203100 SCALE: NOTED 9019B

Page 12: SCAN UPDATE ROW OCS-G28684 United States Department …3.3 ROV to setup rigging on jumper and prepare to make cuts. 3.4 ROV to use super grinder to make cuts on belly 1' past the bend

PLET

DRILL CENTER "NEIDERMEYER" FLYING LEAD LENGTHS LOCATION SFL HFL EFL OFL

HDM TO MC 203 SSOOl 345' - - -HDM TO MC 253 SSOOl 310' - - -

HDM TO MANIFOLD 260' - - -UTH TO HDM "M" SHAPE (2 REQ'D) - - -

MC 208 SSOOl TO MANIFOLD - 120' - -MC 253 SSOOl TO MANIFOLD - 120' 95' -

MC 208 SSOOl TO JUMPER FLOWMETER - - 100' -MC 253 SSOOl TO JUMPER FLOWMETER - - 90' -

UTH TO 3" UMB. COBRA HEAD - - - 45' (2 REQ'D) UTH TO SRM - - 50' (2 REQ'D) 50' (2 REQ'D)

MC 208 SSOOl TO JUMPER ASD - - 70' -MANIFOLD TO MC 253 SSOOl JUMPER ASD - - 75' -

SRM TO MC 208 SSOOl - - 300' (2 REQ'D) -SRM TO MC 253 SSOOl - - 300' (2 REQ'D) -

SRM TO 3" UMB. COBRA HEAD - - 70' (2 REQ'D) -3" UMB. COBRA HEAD TO MANIFOLD - 260' - -

J HDM TO MC 252 SSOOl 210' - - - < MC 252 SSOOl TO MANIFOLD - 190' - - \

[ MC 252 SSOOl TO JUMPER FLOWMETER - - 100' - ) V MC 252 SSOOl TO JUMPER ASD - - 75' - )

X SRM TO MC 252 SSOOl - - 170' (2 REQ'D) - <

MC 208 WELL SSOOl (ACTUAL LOCATION IS MC 253) WELL HEADING AT 251" (FUGRO AS-BUILT) X= 1,204,390.72' Y= 10,434,793.82'

SEP 2 4 2015

APPROVED FOR CONSTRUCTION

MC 253 NEIDERMEYER

O

NOTES

1. ALL BEARING AND COORDINATES SHOWN ARE UTW NORTH ZONE 15. THIS DRAWING IS THE PROPERTY OF AND EMBODIES CONFIDENTIAL INFORMATION OF PINNACLE ENGINEERING, INC. & LLOG EXPLORATION OFFSHORE INC. THIS DRAWING AND THE INFORMATION THEREON SHALL NOT BE REPRODUCED OR DISCLOSED TO ANY OTHER PARTY OR USED FOR ANY OTHER PURPOSE OTHER THAN FOR THE BENEFIT OF AND AS AUTHORIZED BY PINNACLE ENGINEERING, INC. OR LLOG EXPLORATION OFFSHORE INC.

6 ADDED MC 252 WELL SSOOl 5 4-14-15 MOVED 70' EFL'S ROD PAC 4 1-29-15 ADDED HR ROD PAC 3 8-27-14 GENERAL REVISIONS ROD PAC 2 7-18-14 REVISED TO SHOW AS-BUILT LOCATIONS ROD PAC 1 3-24-14 GENERAL REVISIONS ROD PAC 0 11-22-13 APPROVED FOR CONSTRUCTION ROD PAC

NO. DATE DESCRIPTION

fi * % p PETER A. CRUZ fl

$3 „ 90900"'

— — —

4 PINNACLE E N G I N E E R I N G

TX REGISTERED ENGR FIRM F-567

Drawn By BAO NGUYEN

Date 1-29-15

Checked By R.OETHIOFF

Date 11-22-13

Designed By

Dale

Approved By P.CRUZ

Dale 11-22-13

LUDG e x p l o r a t i o n

DELTA HOUSE SUBSEA DEVELOPMENT MISSISSIPPI CANYON 254

MISSISSIPPI CANYON 253 WELL SITE LAYOUT - NEIDERMEYER

JOB NO. 203100 SCALE: NOTED 9007A

Page 13: SCAN UPDATE ROW OCS-G28684 United States Department …3.3 ROV to setup rigging on jumper and prepare to make cuts. 3.4 ROV to use super grinder to make cuts on belly 1' past the bend

Pay.gov - Receipt Page 1 of 1

Pay.gov Receipt

Your payment is submitted Pay.gov Tracking ID: 266IKTKQ Agency Tracking ID: 75382854896 Form Name: Pipeline ROW Modification Application Application Name: BSEE Pipeline ROW Modification Application - BY

Payment Information Payment Type: Bank account (ACH) Payment Amount: $4,169.00 Transaction Date: 12/14/2017 05:11:41 PM EST Payment Date: 12/15/2017 Region : Gulf of Mexico Contact: Carol Eaton 985-801-4300 Company Name/No: LLOG Exploration Offshore, L.L.C, 02058 Pipeline Segment No.: 18811

Account Information Account Holder Name: LLOG Exploration Offshore, L.L.C. Routing Number: 065403626 Account Number: ™ ™ ™ 8 3 2 3

Email Confirmation Receipt Confirmation Receipts have been emailed to: [email protected] [email protected]

https://www.pay.gov/public/collection/confirm/print/266IKTKQ 12114/2017