Scaffold Construction

Embed Size (px)

Citation preview

  • 7/29/2019 Scaffold Construction

    1/33

    By: Georgia Tech Occupational

    Safety and Health Program

    Scaffolding: Your Key to

    Stability

  • 7/29/2019 Scaffold Construction

    2/33

    29 CFR 1926 Subpart L

    1926.450 Scope and Application

    1926.451 General Requirements

    1926.452 Additional Requirements

    1926.453 Aerial Lifts

    1926.454 Training RequirementsAppendices A thru E

  • 7/29/2019 Scaffold Construction

    3/33

    Most Frequently Cited Hazards

    Scaffolds above 10 ft.-Fall Protection

    Scaffold Access

    Scaffold Working Levels-Decked

    Aerial Lift-Harness/Lanyard

    Training in use of scaffolds

  • 7/29/2019 Scaffold Construction

    4/33

    National Statistics

    A significant percentage

    of personnel in

    construction (65) work

    from scaffolds routinely

    There are approximately

    50 fatalities related to

    scaffolds each year.

    There are approximately

    4500 employee injuries

    each year as a result of

    using scaffolds.

    For the period 1980-1985

    falls from scaffolds

    accounted for 17% of the

    fatalities for falls fromelevations.

  • 7/29/2019 Scaffold Construction

    5/33

    Georgia Statistics

    The total number of fall related fatalities in

    2000 was 25.

    The number of fatalities involving scaffolds

    were 6.

    Falls from scaffolds represented twenty five

    percent of the total fatalities in the state

  • 7/29/2019 Scaffold Construction

    6/33

    Hazards

    Injured workers revealed that 72% of the

    accidents were caused by:

    Platform failure

    Support failure

    Slipping

    Being struck by an object

  • 7/29/2019 Scaffold Construction

    7/33

    Requirements for Competent

    Person A competent person is a person on the

    project who has knowledge to identify and

    the authority to correct site hazardsOSHA 10 or 30 hour training card could

    support the fact you had training and areknowledgeable

    The 10 or 30 hour OSHA training card alonedoes not necessarily mean you are a competent

    person

  • 7/29/2019 Scaffold Construction

    8/33

    Requirements for Competent

    Person Scaffolds have to be inspected daily by a

    competent person

    Scaffolds must be erected, moved,

    dismantled or altered under the supervision

    of a competent person

    Work by qualified workers selected by thecompetent person

  • 7/29/2019 Scaffold Construction

    9/33

    Capacity 29 CFR 1926.451(a)

    Each scaffold and scaffold component must

    be capable of supporting four times the

    intended weight.

    Direct connections to the roof and

    counterweights of suspended scaffolds must

    resist four times the tipping moment or 1.5times tipping moment imposed by scaffold

    operating at stall load

  • 7/29/2019 Scaffold Construction

    10/33

    Capacity 29 CFR 1926.451(a)

    Suspension ropes including hardware must

    support six times the maximum intended

    load

    The stall load of any scaffold hoist shall not

    exceed three times its rated load.

    Scaffolds must be designed by a qualifiedperson and loaded accordingly.

  • 7/29/2019 Scaffold Construction

    11/33

    Platform Construction 29 CFR

    1926.451(b) All working levels of scaffolds are required

    to be fully decked.

    No gaps greater than one inch allowed

    Each scaffold platform shall be at least 18

    inches wide.

    Ladder jack, roof bracket and pump jack can be12 inches wide.

  • 7/29/2019 Scaffold Construction

    12/33

    Platform Construction 29 CFR

    1926.451(b) The front edge shall not be more than 14

    inches from face (if in excess rails

    required).

    The end of each platform will extend over

    the center line by six inches (unless

    hooked).

  • 7/29/2019 Scaffold Construction

    13/33

    Platform Construction

    Requirement for overhang based on length:

    10 ft or less platformnot to exceed 12 inches

    More than 10 ft not toexceed 18 inches

    For extended

    platforms overlap oversupports by 12 inches(unless secured)

    Wood platforms shall

    not be covered with

    opaque finishes. Components

    (different) shall not be

    mixed unless they fit

    (integrity maintained).

  • 7/29/2019 Scaffold Construction

    14/33

    Supported Scaffolds, 29 CFR

    1926.451(c) Scaffolds with a width to height of more

    than 4:1 need to be restrained

    Guys, ties, and braces installed in

    accordance to manufacturer

    Ties, guys, wires must be used for eccentric

    load

  • 7/29/2019 Scaffold Construction

    15/33

    Supported Scaffolds, 29 CFR

    1926.451(c) Supported poles, legs, and posts need to

    bear on base plates and mudsills or other

    firm foundation. Footing must be rigid and sound.

    No unstable objects for supports or

    platform. Legs, posts, frames must be plumb andbraced to prevent swaying.

  • 7/29/2019 Scaffold Construction

    16/33

    Scaffold Access, 29 CFR

    1926.451(e) When scaffold

    platforms are 2 feetabove or below a pointof access ladders, stairtowers or personnelhoist must be used.

    Cross braces can not be

    climbed. Ladders set up so not

    to tip scaffold.

    Stairway type ladders

    can be used in

    1926.451(e)(3) Railing has to be

    provided

    Ramps 1926.451(e)(5)

    Rails over 6 feet

    No slope greater than

    20 degrees

  • 7/29/2019 Scaffold Construction

    17/33

    Scaffold Access

    Integral prefabricated

    scaffold access

    frames: Designed and

    constructed as ladder

    rungs

    Rung length of 8inches

    Uniform space

    Direct Access shall only

    be used when scaffold is

    not more than 14

    horizontal and 24 verticalaway.

    Safe means of access shall

    be provided during

    erecting or dismantling asdetermined by competent

    person.

  • 7/29/2019 Scaffold Construction

    18/33

    Scaffold Use 1926.451(f)

    Scaffolds shall not beexcessively loaded

    Inspection by competent

    person before each shift Damaged scaffold

    immediately repaired orreplaced.

    Maintain adequatedistance from power lines(3 ft for less than 300 Vand 10 ft for greater than300)

    Must not work on

    slippery platforms,

    debris or during highwinds.

    Standing on objects to

    increase height

    prohibited.

    Ladder may be used

    on wide area scaffold.

  • 7/29/2019 Scaffold Construction

    19/33

    Scaffold Use

    Scaffolds must be inspected before use each

    shift by competent person.

    All damaged components must be repairedor replaced immediately.

  • 7/29/2019 Scaffold Construction

    20/33

    Fall Protection, 29 CFR

    1926.451(g) Required on all

    scaffolds greater than10 feet.

    Boatswains chair,floatscaffold or similarrequire fall arrest.

    Suspension scaffoldrequires rails and fallarrest system(independent life line).

    Rail system design:

    Top rail installed between

    38 and 45 inches

    mid rail between top andworking surface

    Finished components

    must with stand:

    A force 200 pounds for toprail

    150 pounds for mid rail

  • 7/29/2019 Scaffold Construction

    21/33

    Fall Protection

    Guardrails must be free ofsharp edges.

    Ends of rails must be

    constructed so it doesoverhang the terminal

    posts

    Steel or plastic bands arenot acceptable as railing

    Cross brace may be usedas a mid rail if it meets theheight requirement (cross

    between 20-30 inches)

    Falling objectrequirements are:

    Employees on scaffold(in

    addition to hard hats) mustbe protected by toe boards,debris nets or canopy

    Area below must beprotected by barricades,canopies, toe boards on

    scaffolds over 10 feet

    Toe boards- withstand 50pounds of force and be 3.5inches wide.

  • 7/29/2019 Scaffold Construction

    22/33

    Additional Scaffolds-

    Supported, 29 CFR 1926.452 Tube and coupler:

    The existing platform

    shall not be moveduntil bearers are set

    X bracing installation

    Couplers have to made

    of structural steel Scaffolding over 125

    ft. have to be designed

    by registered engineer

    Fabricated Frame:

    The existing platform

    shall remain until theframes are set/braced

    Frames and panels

    shall be braced (joined

    with stack pin

    Scaffolding over 125

    ft. have to be designed

    by registered engineer

  • 7/29/2019 Scaffold Construction

    23/33

    Additional Scaffold-Supported

    Horse scaffolds:

    Limited to two tiers (10 ft.)

    Horses arranged directly

    over each other

    Legs nailed down and tiers

    braced

    Crawling boards:

    Extend from peak to eavesand secured to roof by ridge

    hooks or equivalent

    Pump jack scaffolds:

    Bracket must have twopositive grips

    Poles secured at the top andbottom

    Work bench is not aplatform

    Continuous length polesjoined at seam parallel to

    bracket

    Mending plates must beinstalled at 2X4 splices forstrength

  • 7/29/2019 Scaffold Construction

    24/33

    Additional Scaffolds-Supported

    Ladder jack scaffolds:

    Not to exceed 20 feet

    Ladder meet requirement of

    part X

    No bridging of platform

    Ladders must be provided

    with device to prevent

    slipping

    Constructed to bear on side

    rails and rungs or rungs (if

    rungs at length of 10

    inches)

    Window jack scaffold:

    Attached to window

    opening and not used to

    place planks betweenscaffolds

    Step, trestle, and ladder

    scaffolds:

    Platform not placed higher

    than second highest rung

    and ladder secured

    Ladders designed to part X

  • 7/29/2019 Scaffold Construction

    25/33

    Additional Requirements-

    Suspended Swing Stages:

    Platform limited to 36

    Platform must be securely

    fastened to hangars

    Platforms shall be of the

    ladder, plank, or beam type

    Two point scaffolds shall

    not be bridged together

    unless bridged and hoist isappropriately sized

    Multi level scaffolds:

    Equipped with

    independent support

    lines (equal to number

    of suspension points)

    and not attached to the

    same point as

    suspension ropes

    Supports for platform

    attached to stirrup only

  • 7/29/2019 Scaffold Construction

    26/33

    Additional Requirements-

    Mobile Requirements for mobile

    scaffolds:

    Adequately plumbed,

    braced, level and squared

    Must have means to lock

    wheels/casters

    Force to move scaffold no

    higher than 5 feet above

    support surface

    Power system must be

    designed for scaffold

    Stabilized to prevent tip

    Platform must not extendbase support without

    outriggers Caster stems-pinned

    Riding not allowed unless:

    surface floor level and freeof debris and 2:1 BXH ratio

    Outriggers on both sides

    No one allowed onextended platform

  • 7/29/2019 Scaffold Construction

    27/33

    Additional Requirement-Stilts

    Only to be used on large area scaffold

    Surfaces must be flat and free of pits

    No obstructions

    Stilts have to be maintained

    Guardrails must be raised by an amount

    equal to stilts

  • 7/29/2019 Scaffold Construction

    28/33

    Requirements for Aerial Lifts

    29 CFR 1926.453 Meet the design criteria of

    ANSI

    Aerial ladders must be

    secured in lower travelingposition by a lockingdevice before it is moved.

    Ext./Art. Platforms:

    Boom must be adequatelystowed before move

    Insulated portion must notbe altered

    A body belt or harness and

    lanyard must be used

    Employees must stand on

    floor of basket Never exceed load capacity

    Lift truck shall not be

    moved with men in basket

    unless adequately designed

    (upper controls-personnelcarriers)

    Brakes set for outrigger use

    (wheels chock)

  • 7/29/2019 Scaffold Construction

    29/33

    Aerial Lifts

    Extensible and articulating platforms:

    Lift controls must be tested each day

    Authorized employees only

    No belting off to adjacent structure

    All pneumatic and hydraulic components

    comply with ANSI A92.2-1969 and noncritical parts must have burst factor 2:1.

  • 7/29/2019 Scaffold Construction

    30/33

    Training-General

    29 CFR 1926.454 Employees must receive training from

    qualified person that includes:

    Nature of electrical, fall, and falling itemsUse of scaffold/handling

    Maximum intended load and load carryingcapabilities of scaffold

    Methods for dealing with electrical hazardsand fall protection system

    Requirements of sub L

  • 7/29/2019 Scaffold Construction

    31/33

    Training-Setup or Dismantling

    Employees must be trained in:

    Nature of scaffold hazards

    Procedures for setup, dismantling or movingthe system

    Design criteria, maximum intended load

    carrying capacities and use of scaffoldRequirements of subpart L

  • 7/29/2019 Scaffold Construction

    32/33

    Training-Need for Retraining

    When the employer has reason to believe an

    employee lacks the skill or understanding needed

    for safe work involving scaffolds, retraining shallbe performed until proficiency is regained.

    Retraining is required:

    When additional or new hazards exist.

    Changes in the type of scaffold and fall protection exist. Where there are inadequacies in an employees work.

  • 7/29/2019 Scaffold Construction

    33/33

    Resources

    www.osha.gov

    29 CFR 1926.451

    NAHB-OSHA Job Site Safety Handbook

    Construction Industry Digest

    Scaffolding Industry Association

    www.scaffold.org

    American National Standards Institute A92 (SIA): Scaffolds and other elevating devices