Sigma Approach Web About Us Global Issue Focus i-DID : An
Introduction i-DID : Project Planning i-DID : Design Concept and
Prototype i-DID : Technical Analysis i-DID : Testing and Result
i-DID : Cost Analysis i-DID : Future Improvement Conclusion Q &
A
Slide 3
Approach One We are a clique of committed youngsters whom
concern about mother earth. We are technical figures from different
background whom love to contribute. We are SIGMA TEAM !!! About
Us
Slide 4
Approach Two Facts and Numbers: 70% of Earth are covered by
water A Malaysian use 226 liters of water per day A Singaporean use
154 liters of water per day Recommended water consumption per day
is 165 liters per day (For Malaysian) Saving up to RM 18.33 per
month by practicing the above recommendation Every cycle of washing
machine operation consumes at least 37.86 liters of water 90% of
the water amount above is under-heating Global Issue Focus OUR
FOCUS Source: The Star, 22 March 2011
Slide 5
Approach Three Problem Statement Inefficient usage of washing
machine with excessive water consumption for small quantity of
subjects Problem on drying either new or used small sized item in
proper manner and low-cost consumption High cost and energy
consumption of modern dehumidifier i-DID : An Introduction ?
Slide 6
Approach Three Project Objectives The following objectives are
designed as guideline to solve the stated problems: To provide a
low-cost integration system which has similar output of washing
machine and dryer. To design an eco-concern system with low risk to
environment and consumer. To utilize new cheap and abundant natural
resources as alternative of drying and dehumidifying method. i-DID
: An Introduction
Slide 7
Approach Four Task Allocation i-DID : Project Planning PROJECT
LEADER Public Relation Schedule Planning SECRETARY Project
Documentation Presentation Mode RESEARCH & TEST ENGINEER
Chemical Test & Analysis Resources Evaluation DESIGN ENGINEER I
Prototype Fabrication Process Analysis DESIGN ENGINEER II Prototype
Design Structural Analysis BUSINESS STRATEGIST Project Cost
Analysis Business Planning
Slide 8
Approach Four i-DID : Project Planning
Slide 9
Approach Four i-DID : Project Planning SOFTWARE Microsoft
Office Word Microsoft Office PowerPoint Microsoft Office Excel
AutoCAD 2007 Google Sketch Up Adobe Photoshop CS4 Online Scientific
Calculator HARDWARE Basic Tool Kit Jig Saw Machine (AC) Drilling
Machine (AC and DC) Shearing Machine TIG Welding Machine Cutting
Equipments Joining Components PROJECT COMPONENTS USED ELECTRICAL
COMPONENT 12-V Rechargeable Battery Cooling Fan Exhaust Fan Dual
Switches LED Indicator Soldering Equipment Circuit Board
Slide 10
Approach Five Competitive Values Design Concept Health and
Safety Factor Eco-Concept Ergonomic i-DID : Design Concept and
Prototype OUR ADVANTAGES Efficient Energy Consumption
User-Friendliness Environmental-FriendlinessProcess Sustainability
Multi-Purpose FeatureLow-Cost Factor
Slide 11
Approach Five Technical Design i-DID : Design Concept and
Prototype
Slide 12
Approach Five i-DID : Design Concept and Prototype MAIN
OPERATING SPACE Cooling Fans Exhaust Fan Hanger Rack DEHUMIDIFIER
SPACE Charcoal Charcoal Holder Base CIRCUIT CENTRE 12-V
Rechargeable Battery Circuit Board Switch & LED Indicator
Slide 13
Approach Five i-DID : Design Concept and Prototype COMPONEN T
DESIGN JUSTIFICATION Structure Foundation Cover Poles Base Made up
of aluminum. Aluminum has the properties as follow: Lightweight :
Aluminum has one-third specific weight of steel High corrosion
resistance: For sustainability, protection and conservation
Impermeable: Do not allow light or taste go through Non-toxic: Do
not release odor Transparent Perspex Allow user to see-through the
process while the device is operating As part of health and safety
factor Base WheelEase for mobility and user-friendliness factors
Dual SwitchesHealth and safety factor and performance efficiency
concern M-Shape Hanger Increase contact with surface area of the
subject. High load capacity. Fans PositionGood coverage of air flow
in the operating space
Slide 14
Approach Six The mechanism process flow of the device runs as
follows: The cooling fans draw the external air into the main
operating space. The air drawn cooling up the space, dry up the
subject and vaporize the water from subject into air inside the
operating space. The exhaust fan beneath the hanger draws the wet
air/humidity in the operating space and channel them to
dehumidifying component in other compartment. i-DID : Technical
Analysis TECHNICAL ANALYSIS PROCESS THEORY TECHNICAL CALCULATION
DEHUMIDI FYING COMPONE NT 1 PROCESS THEORY
Slide 15
Approach Six Device Mechanism The mechanism of the device:
drying and dehumidifying Using Latent Heat of Vaporization Theory,
following principles are benefited for the process within the
device. i-DID : Technical Analysis
Slide 16
Approach Six 4 important terms to be well-comprehended: RPM
(rotational per minute) The angular speed of the fan or moving air
CFM (cubic feet meter) The air volume flow rate (either input or
output) Air Changes Per Hour, N The rate of air changes (input or
output) in an hour period Operating Space Size Size of main
operating space where the process occurs The Fan Law stated that:
i-DID : Technical Analysis 2 TECHNICAL CALCULATION
Slide 17
Approach Six Provided that formula shown is the Air Changes Per
Hour, N The industrial standard has classified the normal air
changes per hour for extremely damp or wet place as N=6. By
substituting the values into the formula given, the value of Q
obtained is 0.338 CFM. Thus, Q=0.338 CFM is the minimum air flow
rate required to have N=6 or 6 air changes per hour. At this rate,
using the formula of Fan Law, the estimated speed obtained is 47.94
RPM. i-DID : Technical Analysis
Slide 18
Approach Six Concerning the air flow rate, the CFM ratio is
calculated to find the efficiency of the air flow rate. Thus, the
flow rate efficiency ratio of the fan specification to the minimum
requirement of flow rate for at N=6 is 46 times more efficient.
With the specification of flow rate = 0.338 CFM, air changes
increase from N=6 to N=179 or approximately 3 air changes per
minute. i-DID : Technical Analysis
Slide 19
Approach Six Objective: Amount of Energy Required (Per Unit
Weight) of The Original Material Thus, at 0.3 kg mass of towel,
i-DID : Technical Analysis
Slide 20
Approach Six Thus, moisture within 60 g dry area obtained:
Amount of humidity needed to be eliminated: Calculating the energy
(heat) required for vaporization process: i-DID : Technical
Analysis
Slide 21
Approach Six Assumptions: saturation temperature of water = 100
Celsius and at standard atmospheric pressure. Thus, latent heat of
vaporization of water = 2257 kJ/kg and specific heat capacity of
cotton = 1162 J/(kg.C) Thus the energy required for vaporization
process of water is 526.93 kJ. Converting the value into hourly
rate of power, the amount required to be overcame is 0.1466 kWh.
i-DID : Technical Analysis
Slide 22
Approach Six Cooling Capacity VS Latent Heat of Vaporization
The energy required for vaporization process = 0.1466 kWh The
average cooling capacity for each fan in used = 70 Watt
Calculation: Estimated Hour of Usage = 1.25 hours, Thus, Hourly
Rate of Power (Each Fan) = 0.0875 kWh Since two fans are in used,
thus Hourly Rate of Power = 0.175 kWh 0.175 kWh is higher than
0.1466 kWh, thus the vaporization process is stable. i-DID :
Technical Analysis
Slide 23
Approach Six Device Power Consumption VS Other Device Power
Consumption i-DID Power Consumption : 8.4 Watt or 0.0105 kWh per
load Evaporative Cooler : 0.4 kWh per hour Washing Machine
(Mechanical Operation) : 0.256 kWh per load Washing Machine
(Automatic, Heating Water Electrically) : 6.0 kWh per load Power
saving per load between washing machine (mechanical operation) and
i-DID is 0.2455 kWh. Considering both machines are used everyday
per year, the power saving is 89.61 kWh. i-DID : Technical
Analysis
Slide 24
Approach Six Eliminate Mold and Humid Air Odour-Absorption
Feature Cost-Saving Abundant Green Resource Low Risk Possibility
i-DID : Technical Analysis 3 DEHUMIDIFYING COMPONENT WHY USE CHARCO
AL ?
Slide 25
Approach Seven The completed prototype has been undergoing
several types of testings to measure its performance in carrying
out the assigned task. The tests that have been carried out are:
Dehumidifying Components Comparison Test Device Performance Test
Voltage Volume Test i-DID : Testing and Result
Slide 26
Approach Seven Dehumidifying Components Comparison Test i-DID :
Testing and Result Test Description Test Procedure To measure the
performance efficiency of different dehumidifying components of
different portions at constant conditions All the tests are carried
out simultaneously at the constant conditions (temperature,
pressure, volume and humidity rate) Four different same-sized and
covered box are arranged in proper manner. A small beaker of pure
water (100% humidity) is allocated in each box. The volume of water
is kept constant. Then, each box is assigned with different
portions and types of dehumidifying components. All observations
and data are recorded.
Slide 27
Approach Seven The data obtained are tabulated in table as
follows: The efficiency percentage (%) = i-DID : Testing and
Result
Slide 28
Approach Seven From the table, a dehumidifying components
performance graph is constructed. i-DID : Testing and Result
Slide 29
Approach Seven Test Analysis Based on the test conducted: Rate
of humidity absorption process in dehumidifying components are
tested. 100% charcoal portion has the highest efficiency as a
dehumidifying component with approximately 14.30%. The 100%
charcoal portion is presented in form of granular and powder form
in order to increase contact area with air. The efficiency of the
100% charcoal portion can be further increase by using driving
force device such as fan or blower. i-DID : Testing and Result
Slide 30
Approach Seven Device Performance Test i-DID : Testing and
Result Test Description Test Procedure To measure the overall
performance efficiency of the device in completing the assigned
task The machine is setup with the charcoal supply. The machine is
switched on for operation and left for 5 minutes for reaching
stabilization. A small towel is prepared and original weight is
recorded. The towel is wet up and the initial wet weight is
recorded. The small towel is put and arranged into the main
operating space. The top cover of the device is closed down to
start the process. The weight of the towel is recorded in every 10-
minutes interval. The experiment is carried out for one hour. All
observations and data are recorded.
Slide 31
Approach Seven From the table, a device performance graph is
constructed. i-DID : Testing and Result
Slide 32
Approach Seven Test Analysis The experiment is carried out in
an-hour period to find the change in humidity (water absorbed) by
the towel. After 60-minutes, the change of mass observed is 0.16
kg. As the mass of towel (0.1 kg) is kept constant, the mass of
water in the towel has reduced from 0.2 kg to 0.04 kg. At 0.04 kg
mass of water, the humidity is at 16 % compared to 0.2 kg mass of
water (humidity is at 80%) In an hour the drying efficiency is
estimated 80%. i-DID : Testing and Result
Slide 33
Approach Seven Voltage Volume Test i-DID : Testing and Result
Test Description Test Procedure To measure the DC power supply
lifetime for every load or usage. The test is carried out at the
constant conditions (temperature, pressure, volume and humidity
rate) All switches are ensured to be switch on. Both ends of the DC
power supply are connected with the multi-meter to find the current
readings. The average current readings are taken by using a
multi-meter. The data is calculated and analyzed to find the
estimated life time period of a power supply.
Slide 34
Approach Seven Test Analysis Test result found that the process
used an estimated amount of 0.7 ampere for each cycle run an hour.
Provided that the rechargeable DC power supply runs 7.2 ampere,
thus it is recommended the power supply to be recharged after
10-hours of usage. i-DID : Testing and Result
Slide 35
Approach Eight PRODUCTION COST The production cost include
materials cost and handling cost. The cost are calculated in both
individual mean and mass production mean i-DID : Cost Analysis
TECHNICAL ANALYSIS COST ANALYSIS PRODUCTION COST COSTS COMPARISON
BUSINESS STRATEGY
Slide 36
Approach Eight The cost analysis as shown is considering mass
production cost reduction factor, profit as well as the delivery
cost. i-DID : Cost Analysis RM 125 ONL Y !!!
Approach Eight Considering we have spent about a load per day
for the unnecessary small items to be washed in laundry or washing
machine, we have actually wasted not only energy, water resource
but also our money estimated about $19O per year !! i-DID : Cost
Analysis
Slide 40
Approach Eight BUSINESS STRATEGY i-DID : Cost Analysis OUR
CLIENTS
Slide 41
Approach Nine Multi towels to dry at the same time with same
duration of drying time Increase the efficiency Reduce the duration
of drying time (from currently 70 mins to 35 mins) For gym purpose,
we can reduce our product in size and the duration of drying time
is estimated 10 mins Include timerFor auto off purpose (oven
concept) i-DID : Future Improvement
Slide 42
Approach Nine i-DID : Conclusion Minimum Power Consumptio n
Minimum Cost BEST Output and BEST Product!!! i-DID achieve :- Long
Sustainability Eco- Friendly Low Energy Consumption User-Friendly
Lowest Cost