Savannah Cruise Ship Study

Embed Size (px)

Citation preview

  • 7/28/2019 Savannah Cruise Ship Study

    1/44

    1

    Date: October 13, 2010

    June 25, 2013

    Savannah Cruise Feasibility Study

    CRUISE SHIP STAGING AREA STUDY

    Phase I Report Presentation

  • 7/28/2019 Savannah Cruise Ship Study

    2/44

    2

    BEAs Team:

  • 7/28/2019 Savannah Cruise Ship Study

    3/44

    3

    REPORT PRESENTATIONJune 25, 2013Phase One, CRUISE SHIP STAGING AREA STUDYSavannah Cruise Feasibility Study

    I - Overview of Study:

    The scope of the project methodology analyzed three sites for apotential Cruise Terminal capable of handling in range of 2,700

    passengers and docking/berthing station. . The scope of thisstudy evaluated environmental impacts, navigationalchallenges, and compatibility with the Georgia Ports Authority(GPA) vessel operations on the Savannah River, technicalinvestigations, utility/traffic coordination, site challenges,

    docking requirements and identification of potentialchallenges with each site. The Phase I report has taken intoconsideration and evaluated the waterside / marine conditionsand general infrastructure existing at each of the three sitesand provided a tabulation of ranking ranging from MostDesirable to Least Desirable.

  • 7/28/2019 Savannah Cruise Ship Study

    4/44

    4

    REPORT PRESENTATIONJune 25, 2013Phase One, CRUISE SHIP STAGING AREA STUDYSavannah Cruise Feasibility Study

    I - Overview of Study (Continued)-

    The report has been developed on the basis of informationgathered and developed from meetings with and / or frominformation provided by: ;

    The U.S. Army Corps of Engineers,

    Savannah Pilots Association,

    United States Coast Guard,

    U.S. Fish and Wildlife Service,

    National Marine Fisheries Service,

    Georgia Department of Natural Resources,

    Colonial Oil,

    Limited contact with Georgia Ports Authority,

    Georgia Archaeological Site File

    Georgias Natural, Archaeological and Historic Resources GIS.

  • 7/28/2019 Savannah Cruise Ship Study

    5/44

    5

    Cruise Vessel Development Over Time

    V

    essel

    Si

    ze

    s

    900-1050 FEET

    Up To 30

    20-36

    26-30

    26-34

    1960 s

    1970 s

    1980 s

    +1990 s

    400-500

    600

    1200-2000

    2600-3800

    18

    20

    80

    90-150

    800 FEET

    500 FEET

    400 FEET

    Ship

    Displacement

    (In Thousands Grt.)

    Passengers Drafts Air Drafts

    140-175

    160-180

    -

    -

    960-1250 FEET

    30-343500-5000 150-250+/- 200

    +2000 s

  • 7/28/2019 Savannah Cruise Ship Study

    6/44

    6

  • 7/28/2019 Savannah Cruise Ship Study

    7/447

    Carnival VesselLineup

    Royal Caribbean Vessel

    Lineup

  • 7/28/2019 Savannah Cruise Ship Study

    8/448

    Critical Demographics and Psychographicswithin a One Day Drive of Savannah and

    Comparables (2009)

    Source: SRDS, PSI, Google Maps, MapInfo

    SAV JAX CHS MOB

    mil mil mil milDemographics (Persons or Households)

    2009 Population 56.4 46.2 44.3 42.0

    2009 Population Age over 55 14.5 11.9 11.1 9.8

    White Collar Workers 15.3 12.6 12.1 11.1

    Households with Income $75,000 or more 5.9 4.9 4.6 4.1

    Persons over 25 with Some College or More 18.8 15.5 14.6 13.0

    Psychographics (Adults)

    Interested in The Arts 15.4 12.6 11.9 10.8

    Rely on Newspaper to Keep Me Informed 15.0 12.3 11.7 10.7

    Prefer Specialty Stores because Have Best Brands 8.5 7.0 6.6 6.1

    Do Some Sport/Exercise Once a Week 21.1 17.2 16.4 15.0Typically Avoid Watching TV Commercials 18.9 15.4 14.8 13.5

    2009 Departing Passengers (in 1000's) 188.2 37.4 134.6

    Within a One Day Drive of:

  • 7/28/2019 Savannah Cruise Ship Study

    9/449

    REPORT PRESENTATIONJune 25, 2013Phase One , CRUISE SHIP STAGING AREA STUDY

    Savannah Cruise Feasibility Study

    1- General Locations of Sites A, B, and C

    2- General Characteristics of Sites A, B, and C

    3- Site Analysis and Comparisons:Each of the three sites; A, B, and C were studied and the report presents thefindings for the following parameters for each of the sites,

    SITE & INFRASTRUCTURE DATA Location

    Site Acreage

    Distance to Major Highway

    Water and Sewer System

    Electrical Service Availability

    NAVIGATION & HYDROGRAPHIC INFORMATION

    WATER SIDE STRUCTURES PRELIMINARY DREDGE ANALYSIS

    UPLANDS NATURAL RESOURCES

    MARINE BIOLOGICAL HABITATS

    UNDERWATER ARCHEOLOGY

    OTHER ISSUES

  • 7/28/2019 Savannah Cruise Ship Study

    10/4410

    Cruise Terminal Sites For Analysis

    SITE A:

    SILO TRACT

    SITE B

    POWELL DYFFRYN

    TRACT

    SITE C

    SAVANNAH RIVER

    LANDING

  • 7/28/2019 Savannah Cruise Ship Study

    11/4411

    Site A: Silo / Atlantic Cement Tract

  • 7/28/2019 Savannah Cruise Ship Study

    12/4412

    Site A: Silo / Atlantic Cement Tract

  • 7/28/2019 Savannah Cruise Ship Study

    13/4413

    Site B: Powell Dufferyn Tract

  • 7/28/2019 Savannah Cruise Ship Study

    14/4414

    Site B: Powell Dufferyn Tract

  • 7/28/2019 Savannah Cruise Ship Study

    15/4415

    Site C: Savannah River Landing Tract

  • 7/28/2019 Savannah Cruise Ship Study

    16/4416

    Site C: Savannah River Landing Tract

  • 7/28/2019 Savannah Cruise Ship Study

    17/44

    17

    Phase I - Project Issues Access to Major Highways

    Level Of Service (LOS) rankings obtained from 2004 MPC traffic congestion study.

  • 7/28/2019 Savannah Cruise Ship Study

    18/44

    18

    Site & Infrastructure - Location

    SITE A:

    SILO TRACT

    SITE B

    POWELL DYFFRYN

    TRACT

    SITE C

    SAVANNAH RIVER

    LANDING

  • 7/28/2019 Savannah Cruise Ship Study

    19/44

    19

    Site & Infrastructure - Acreage

    A

    B

    C

    Site Area: +/- 21.5 Acres

    Site Area: +/- 14.5 Acres

    Site Area: +/- 55 Acres

  • 7/28/2019 Savannah Cruise Ship Study

    20/44

    20

    Site & Infrastructure Distance to MajorHighway

    Level Of Service (LOS) rankings obtained from 2004 MPC traffic congestion study.

  • 7/28/2019 Savannah Cruise Ship Study

    21/44

    21

    Site & Infrastructure Water & Sewer(costs associated with selected site for these improvements investigated in next phase of the study)

    Site A-

    Water:Existing 16 main @Hutchinson Island Rd.

    Need 12 main extended 650 ft.

    Sewer :

    Need 6-8 main extended 650 ft.

    Existing 10 main @Hutchinson Island Rd.

    Site B-Water:

    Existing 16 water main stubbed out at Wayne Shackleford Pkwy

    Need 12 main extended 2,300 ft..

    Sewer :

    Existing stubbed out 8 force main at Wayne Shackleford Pkwy

    Site C-Water:

    Existing 12 main serving site but needs 1,000 ft extension for terminal

    Sewer :

    System never completed, needs completed and accepted by City

  • 7/28/2019 Savannah Cruise Ship Study

    22/44

    22

    Site & InfrastructureElectrical Service

    Site A-3 Phase - @ 25 kV available at site 12-14 kV required for cruise terminal service

    Do not foresee major electrical changes needed to serve site

    Site B-3 phase overhead available now at this site

    System modifications/maintenance needed for service

    Site C-Does not have electrical wiring on site, but private conduits

    and manhole are existing at the site

    GA Power indicated complex process to get power to

    terminal site

    Site would have largest projected cost of the 3 alternative

    sites

    Need electrical power study to consider alternative methods

    vs. cost

  • 7/28/2019 Savannah Cruise Ship Study

    23/44

    23

    Navigation & Hydrographic Information

    Issues Applicable To All Sites- Ships greater than 800 ft turning to occur upriver at Kings Landing

    For maneuvering Pilots request additional 100 ft mooring area each end of ship

    Seasonality effects passage, such as in the spring when fog is common, limitvessel operations in the river. Other ports like Tampa and New Orleans havesimilar fog from time to time.

    Military Outload Division (MOD) use of the Ocean Terminal facilities and theNaval Vessel Protection Zone (NVPZ) in place and enforced by the US Coast

    Guard (CG) during the course of MOD operations (100 yard intercept zone / 500yard escort zone).

    US Coast Guard (CG) reports that the regulations concerning LNG vessels couldcause cruise ship delay in transit due to one of these LNG vessels transiting thearea. Such operational coordination requirements common at most major ports

    Site A- Currently only approx. 656 ft river frontage, (need 1,000 ft) therefore, additional

    waterfront access to be acquired

    Shoaling reported by Pilots in vicinity of site

    Should site be selected for further consideration, the NVPZ restrictions may alsoapply while the cruise ship is docked

  • 7/28/2019 Savannah Cruise Ship Study

    24/44

    24

    Navigation & Hydrographic InformationSite B-

    Currently only approx. 602 ft river frontage, (need 1,000 ft) therefore, additional

    waterfront access to be acquired Shoaling reported by Pilots in vicinity of site

    Concern to the Pilots, due to the sites location within a turn in the river, there ispotential for a suction effect on vessels that are moored in this area caused bypassing vessels making the turn

    Site C- Some concern of steering large vessels in vicinity of site due to curve in river

    Pilots preferred site location due to less surrounding berthing facilities whicheases maneuvering

  • 7/28/2019 Savannah Cruise Ship Study

    25/44

    25

    Water Side StructuresSite A-

    Existing in-water structure consists of 4 mooring structures each spacedapproximately 125 feet apart. These structures are located approximately 50feet from the shore and are connected by supported access ways that appear to

    be in good condition.

    New waterside mooring/berthing structures will have to be constructed

    Site B-

    Existing structure consists of center berthing area with 4 mooringstructures (2 on each side)

    Riparian boundary in relation to existing structures needs furtherinvestigation

    Engineering analysis needed to assess potential of integration into new

    cruise ship berth (new vs. modification)

    Site C-

    Approx 1,984 ft of bulk head and river walk Not designed to berth large vessels but may be integrated into cruise berthinfrastructure

    Marine structures for berthing cruise ships needs engineering analysis

    (modifications)

  • 7/28/2019 Savannah Cruise Ship Study

    26/44

    26

    Preliminary Dredge Analysis

    Site A- Approx 130 ft from Fed Channel to existing mooring structures

    Approx 34,800 cubic yards of dredging may be needed to achieve 34ft draft

    Prior land use assessment needed to evaluate sourcematerial/contributions regarding dredge spoils as contamination maybe an issue

    Existing dredge pipeline adjacent to berth area will need to be

    addressed Sediment analysis required

    USCE need to approve a dredge disposal management plan

    (Permit) Conditional on salt marsh impact and adequate river frontage,site has high probability of obtaining a USCE Sect 10/404 permit

    Site B-

    Approx 120 ft from Fed Channel to existing mooring structures Approx 24,300 cubic yards of dredging may be needed to achieve

    34 ft draft Prior land use assessment needed to evaluate source

    material/contributions regarding dredge spoils as contamination maybe an issue

    Sediment analysis required

    USCE need to approve a dredge disposal management plan

  • 7/28/2019 Savannah Cruise Ship Study

    27/44

    27

    Preliminary Dredge Analysis

    Site B- (Cont) (Permit) Conditional on good sediment analysis, high likelihood of

    approval for initial and ongoing maintenance dredging

    (Permit) Conditional on salt marsh impact and adequate riverfrontage, site has moderate probability of obtaining a USCE Sect10/404 permit

    Site C- Approx 150 ft from Fed Channel to existing mooring structures

    Approx 38,500 cubic yards of dredging may be needed to achieve34 ft draft

    Prior USCE Sect 10/404 permit (2007) for Savannah RiverwalkExtension appears to have been issued and project extended

    Prior land use assessment needed to evaluate sourcematerial/contributions regarding dredge spoils as contamination maybe an issue

    USCE need to approve a dredge disposal management plan

    Site has high probability of obtaining a USCE Sect 10/404 permit

    Existing development at site likely to make terminal permitting mucheasier

  • 7/28/2019 Savannah Cruise Ship Study

    28/44

    28

    Uplands Natural ResourcesSite A-

    Site B-

    Site C-

    For all three (3) sites, a review of the USFWS Chatham County list

    indicated that three (3) plant species as potentially occurring in

    Chatham County. Potential impacts will have to be assessed during

    Phase II of the study; once a survey with tree information is available,

    should any of these sites be selected.

  • 7/28/2019 Savannah Cruise Ship Study

    29/44

    29

    Marine Biological HabitatsSite A-

    Site B-

    Site C-

    For all three (3) sites, a review of the USFWS Chatham County list

    indicated that seventeen (17) animal species as potentially occurringin Chatham County. Potential impacts will be further assessed during

    Phase II of the study should any of these sites be selected. Although

    no listed species were observed during this study, due to the presence

    of potentially suitable habitat for the federally protected species, it

    cannot be guaranteed that listed species would not or could not use

    this site currently or in the future.

  • 7/28/2019 Savannah Cruise Ship Study

    30/44

    30

    Underwater ArcheologySite A-

    One submerged resource (poorly preserved Twentieth Century wooden barge)located at this site

    USACE, Savannah District confirmed this site is not of underwater archeological

    concern

    Site B- Underwater survey identified no underwater archeological resources at this site

    USACE, Savannah District confirmed this site is not of underwater archeologicalconcern

    Site C-USACE issued permit in 2007 for this site. Work undertaken at that time included

    an archaeological survey of the in-water and land side of the property and historic

    resources (boat wreckage, portion of old wharf, bricks) were encountered at this site

    A Programmatic Agreement between the City of Savannah, USACE, Savannah

    District and Georgia SHPO, was signed in January 2007 detailing the required

    cultural resource studies for the Riverwalk project at this site

    Further work on additional components of the archaeological survey may be required

    in order to accommodate a Cruise Terminal development at this site (use

    modification may trigger revisions)

  • 7/28/2019 Savannah Cruise Ship Study

    31/44

    31

    Other Issues:Site A-

    This site offers approximately 6 to 10 acres for potential ancillary mix-usedevelopment to serve cruise passengers and the general public; subject to local

    parking requirements for the development of a cruise terminal facility.

    Refueling at this site will likely result in the bunker barge potentially

    extending into the federal channel.

    This site is directly across Ocean Terminal site. Should this site be used for a

    cruise terminal, cruise ships calling at this facility; while the Military Outload

    Division (MOD) is in operation at Ocean Terminal, are subject to berthing

    restrictions associated with the NVPZ 100 yard intercept zone restriction.

  • 7/28/2019 Savannah Cruise Ship Study

    32/44

    32

    Other Issues:Site B-

    This site offers approximately 4 acres for potential ancillary mix-usedevelopment to serve cruise passengers and the general public; subject to local

    parking requirements for the development of a cruise terminal facility.

    Refueling at this site will likely result in the bunker barge potentially

    extending into the federal channel.

    Should this site be used for a cruise terminal, cruise ships will use the Kings

    Landing turning basin. While the MOD is in operation at Ocean Terminal,

    cruise ships sailing upstream to access the Kings Landing turning basin may

    be subject to transiting through the NVPZ 100 yard intercept zone and 500

    yard escort zone restrictions.

  • 7/28/2019 Savannah Cruise Ship Study

    33/44

    33

    Other Issues:

    Site C- This site offers approximately 40 to 45 acres for potential ancillary mix-

    use development to serve cruise passengers and the general public; subjectto local parking requirements for the development of a cruise terminal

    facility.

    Direct access for all bus and truck traffic may be achieved by routing such

    traffic to a roadway running north to south along the east boundary of the

    property to access President Street as well as Truman Parkway.

    Cruise vessels refueling at this site may accommodate the bunker barge

    without extending into the federal channel. This site currently has more

    linear distance from the existing wharf to the federal channel; final facility

    design will ultimately dictate these distances.

    Should this site be used for a cruise terminal, cruise ships will use the

    Kings Landing turning basin. While the MOD is in operation at Ocean

    Terminal, cruise ships sailing upstream to access the Kings Landing turning

    basin may be subject to transiting through the NVPZ 100 yard intercept and

    500 yard escort zone restrictions.

  • 7/28/2019 Savannah Cruise Ship Study

    34/44

    34

    SITE RANKING SCORE CARD

  • 7/28/2019 Savannah Cruise Ship Study

    35/44

    35

    Conclusions and Recommendations

    Study identifies that each of three sites have issues and concernsthat need to be addressed should it be chosen as

    the preferred site by the City of Savannah to move forward to the

    next pre-development/permitting stage.

    None of the three sites identified a highly significant negative

    factor that the team considered as a fatal flaw which would

    would eliminate it from further consideration.

    Analysis was limited to the critical factors identified and studied for

    the alternative sites.

    Site rankings were presented in a score card format for presentation

    purposes. Using the method for comparing the three sites, the ranking

    of the sites are:

    First Place: THE SAVANNAH RIVER LANDING (SRL) TRACT

    Second Place Tie: Powell Dufferyn Tract and Silo / Atlantic Cement

    Tract

  • 7/28/2019 Savannah Cruise Ship Study

    36/44

    36

    Questions & Discussion

    Thank you.

  • 7/28/2019 Savannah Cruise Ship Study

    37/44

    37

    Overview of Next Phase Two:Cruise terminal Site & Landside FacilitiesPlanning

    I- Land Side Due Diligence

    II- Site Analysis (including qualitative testing)

    III- Conceptual Cruise Terminal/Site Plan DesignIV- Traffic Analysis

    Final Report Project deliverables

  • 7/28/2019 Savannah Cruise Ship Study

    38/44

    38

    I - Land Side Due DiligenceAssemble available information

    Historical Engineering data

    Available City and GIS data Zoning and development constraints

  • 7/28/2019 Savannah Cruise Ship Study

    39/44

    39

    II - Site Analysis

    Existing infrastructure

    Soils

    Environmental Natural Resources

    Wetlands

    Site Contamination

    Cultural Resources Zoning & development permitting analysis

  • 7/28/2019 Savannah Cruise Ship Study

    40/44

    40

    II - Site Analysis (Cont)Site Qualitative Analysis & Testing

    USACE Wetland Delineation / Reverification plan Georgia Department of Natural Resources Marshlands

    Delineation / Reverification plan Coordination meeting with USACE pertaining to the Sediment

    Testing Scope of Work definition and Sampling Analysis Plan

    Dredge Spoils Testing per USACE Sediment Testing Scope ofWork; includes preparation of a sampling and analysis plan,

    dredge sediment and water sampling, and evaluation of dredgespoil disposal options.

  • 7/28/2019 Savannah Cruise Ship Study

    41/44

    41

    III - Conceptual Cruise Terminal/Site Plan Design

    Define programmatic elements for terminal

    Develop Terminal Design Concept for each site Ingress & egress

    Parking

    Utility infrastructure Location of buildings, docks, and ancillary facilities

    Ingress and egress for passenger cars, busses/public transit andservice vehicles

    Cruise vessel docking footprint and proximity to Savannah River

    channel Open space and buffers

    Adjacent existing and proposed development

    Preliminary probable estimate of construction cost and schedule

  • 7/28/2019 Savannah Cruise Ship Study

    42/44

    42

    IV - Traffic Analysis

    Project trips generated by terminal

    Identify routes to primary highways

    Access to public transit Impacts to existing roadways

    Preliminary Traffic Impact Report based oninformation gathered and available from local and state

    jurisdictions.

    Provide Traffic Impact Analysis that includes counts atup to 4 intersections, exclusive of signal warrants ortiming analysis

  • 7/28/2019 Savannah Cruise Ship Study

    43/44

    43

    Project Deliverables

    Phase 1 & 2 Provide support documentation

    needed for USACE Permit applications. The project proponent (not mentioned in RFP); will

    need to also apply for and receive a Coastal MarshlandsProtection Act Permit from the State of Georgia

    Department of Natural Resources Coastal ResourceDivision

  • 7/28/2019 Savannah Cruise Ship Study

    44/44

    Questions & Discussion

    Thank you.