Upload
elam
View
27
Download
0
Tags:
Embed Size (px)
DESCRIPTION
SARMa – Sustainable Aggregates Resource Management WP5. Günter Tiess, Montan University of Leoben 15-17 June, Region of Emilia Romagna, Bologna. Background/Overview Purpose of WP 5 Important issues of WP5 Overview of WP 5 Details of WP 5. Content of Presentation. - PowerPoint PPT Presentation
Citation preview
SARMa – Sustainable Aggregates Resource Management
WP5
Günter Tiess, Montan University of Leoben
15-17 June, Region of Emilia Romagna, Bologna
Content of Presentation
• Background/Overview
• Purpose of WP 5
• Important issues of WP5
• Overview of WP 5
• Details of WP 5
Background
• Discrepancy in aggregates managament practices and policies among old and new EU member states and canditate countries is large.– Thus, it is very important to create a strategic harmonization of
legislation and policies through SARM and SSM across SEE.
Purpose of WP5
• WP addresses transnational aspects and possibilities for harmonizing policies/legislation related to
– 1) SARM– 2) secure supply, – 3) establishment of a Regional Centre for SARM and SSM.
• First 2 activities lead to recommendations for creation of a Aggregate Intelligence System (AIS) for SEE.
– multi-purpose, multi-scale interoperable
• Outputs will be summarized in a manual – incorporating outputs of WP4, – using in dissemination activities (workshops, brochures).
• Workshops on transnational supply: Will emphasize how to ensure SSM,
– considering environmental impacts – considering increased recycling, – enhancing economic development across SEE.
• Regional Centre has potential to become a durable result of the project.
Important issues of WP5
1. Creation of a SARMa-method and SSM-Policies
2. Implementation of transnational view of theoretical and practical outputs in SEE.
3. Know-how transfer through AIS integration and Regional Centre establishment of SARM and SSM,
– in order to achieve efficient implementation of SARM harmonized approaches,
• thus increasing sustainable quality of life,
• resource efficiency and long term cooperation in SEE countries.
Overview of WP 5
WP 5 / Objectives
5.1 Legislation and policies harmonizationCross-border case studies, integrating SARM into land
use planning, AIS-design
5.2 Sustainable supply among SEESynthesis on supply aspects of case studies, land use planning, management, AIS-clarifiaction
SARM and SSM Manual for national and transantional level 5.3SARM and SSM manual, recommend SEE countries to develop their aggregates resource management.
Feasibility study and action plan for Regional Centre on SARM in SEE 5.4Long term implementation of SARMa, i.e.Outputs of WP3,4,5. As well as AIS.
S
A
R
M
WP 5 / Methodology
• WP5 will be based on outcomes of W1-W4.
• WP5.1: Harmonization– Case studies in defined areas (AT-SI-HU-HR + GR,
RO + IT)• WP 5.2: Securing supply
– Synthesis of collected information from WP 5.1• WP 5.3: Manual (national/transnational)
– Partners of WP4 and WP 5, providing information• WP 4: Regional centre
– Feasibility study
Details of WP 5
WP 5.1: Harmonization of legislation and
policies
• Partners will – oversee case studies in their areas, – create reports
• trans-border, cross-country, synthesis
– design of AIS (contribution )– development of recommendation for decision makers
TASK Nr. PARTNERS
(Leader: IGME)
LOCATION Start - End
TASK 1
TASK 2
TASK 3
MUL, MINGORP, GeoZS, MBFH, ER
AT-SI-HU-
HR and GR, RO, IT
August 2010 – October 2011
WP 5.1: Harmonization - TASK 1
Responsability Methodology Outputs DeadlineIGME and all partners from WP 5.1
*Case studies in selected countries, i.e. AT-SI-HU-
HR and GR, RO, IT
*defining criteria how to conduct studies i.e. to be able to cover transnational aspects;
*using standardized format to facilitate analysation/synthezation in WP5.2
* depending on country specific issues/SEE: close cooperation with stakeholders of dedicated regions (e.g.: Austria: Chamber of Commerce, land use planning authority in St. Pölten)
Reports
(trans-border, cross-country, synthesis)
Linked to AT-SI-HU-
HR and GR, RO, IT
Pages?: 50-70?
October 2011
Subdeadline:
Cross-border case studies
WP 5.1 Harmonization – TASK 2
Responsability Methodology Outputs DeadlineIGME and All Partners from WP 5.1
*using basically information from WP4, i.e. existing legislation, land use planning approaches in SEE, related to AT-SI-HU-HR and GR, RO, IT
*using information from TASK 1/WP5.1
*depending on country specific issues/SEE: close cooperation with stakeholders of dedicated regions (e.g.: Austria: Chamber of Commerce, land use planning authority in St. Pölten)
*recommendations, e.g. related to existing and/or implementing transnational/best practices
Guidelines for integrating SARM (especially: methods) into legislation, land use planning
in AT-SI-HU- HR and GR, RO, IT
including recommendations for stakeholders on harmonization of procedures
Guidelines in small reports?
Discussion: which form of guidelines? Must be very practically, to be applied.
October 2011
Subdeadline:
Proposals on harmonization of legislation and policies and methods for incorporating SARM into land use planning and management
WP 5.1 – Harmonization – TASK 3
Responsability Methodology Outputs DeadlineAll partners from WP 5.1
*Defining AIS, related to SARMa:AIS=System, comprising data, information, maps, legislation, practices, protocols, procedures,
How shall it work?
QUESTION:AIS-at which WP will this issue basically defined/discussed?
*collecting information from WP 5.1 task 1, 2 (including WP4)
*analysing, synthesizing
*recommendations
Structure and protocol for multi-scale interoperable Aggregate Intelligence System
How do we handle it?
Regarding transnational aspects: „AIS – issue“ is very important: I need more information: we have to discuss it.
October 2011:Subdeadline:
Design of structure and protocols for Aggregate Intelligence System
WP 5.2
PARTNERS
(leader: MUL)
LOCATION Start - End
TASK 1
TASK 2
TASK 3
METE
PELLA
MINGORP
MBFH
GeoZS
FGG MGK10
Same Location as Action 5.1 plus AL and BA will also look at their trans-border aggregate supply issues
August 2010 – October 2011
Securing Sustainable Supply Across SEE
Role of partners:•review case studies•synthesizing, preparation of proposals on harmonisation/addressing SSM in land use planning •analysing of AIS issues.
WP 5.2: Securing supply in SEE – TASK 1
Responsability Methodology Outputs Deadline
MUL and all partners of WP 5.2
*review and synthesis on supply aspects of case studies (5.1) plus BA and AL
*indication of „pro and contra issues“ in dedicated areas
*Indication of best practices
*recommendations
Recommendations on securing SSM in SEE, i.e. AT-SI-HU-HR and GR, RO, IT
Recommendations in small reports?
October 2011:Subdeadline:
Review and synthesis on supply aspects of case studies (5.1)
Action 5.2: Securing supply in
SEE – TASK 2
Responsability Methodology Outputs Deadline
MUL and all partners of WP 5.2
*strong reliance on 5.2/ TASK 1 outputs
* close cooperation with stakeholders of dedicated regions in SEE (i.e.conducted case studies related to AT-SI-HU-HR and GR, RO, IT)
*Proposals have to be refeered to „AIS-discussion“
*Recommendations on securing SSM in land use planning and management in SEE-regions, i.e. AT-SI-HU-HR and GR, RO, IT
Recommendations in small reports?
October 2011:
Subdeadline:
proposals on harmonization of supply policies / legislation and methods for addressing SSM in land use planning and management,
WP 5.2: Securing supply in SEE – TASK 3
Clarifying contributions of AIS to SSM planning
Responsability Methodology Outputs Deadline
MUL and all partners of WP 5.2
*strong reliance on WP4 and 5.2/ TASK 2
*Analysing, finding out the „gaps“- with regard to SSM
planning in SEE
Is there a possibility to find/define a criteria how to manage the issue „clarify “.
How to messure?
* close cooperation with stakeholders of dedicated
regions in SEE
*Recommendation:
Which design/structure of AIS will be needed (or would be the
best one) to feed in existing SSM planning, i.e. to
„contribute, harmonize and improve secure supplying“ in
SEE
I believe: much discussion is needed to checkt this issue
October 2011:
Subdeadline:
WP 5.3
TASK Nr. PARTNERS LOCATION Start - End
TASK 1 All Partners from WP4 and
WP5
N/A December 2010 – October 2011
Preparation of manual for national and transnational level
WP 5.3
Responsability Methodology Outputs Deadline
All partners from WP4 and
WP5
*arranging collected
information on SARM and SSM
700 copies in english and 1500 in local languages
October 2011:
Subdeadline:
Manual on SARM and SSM
WP 5.4
TASK Nr. PARTNERS
(leader: GeoZS)
LOCATION Start - End
TASK 1 MUL
IGME
TUC MBFH
IGR
FGG
N/A February 2010 – October 2011
Follow-up activities: SARM regional centre
WP 5.4
Responsability Methodology Outputs Deadline
GeoZS and partners from ACTION 5.4
*conduct feasibility study and develop
action plan for Regional Centre on SARM in SEE
*based also on outputs of WP3,
WP4 and WP5 as well as AIS.
Regional Centre to carry forward the
work and conclusions of
SARMa.
Joint Action plan for Regional
Centre on SARM.
October 2011
Follow-up activities: SARM regional centre