Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
© Allen & Overy 2015 1
SAPVIA’s 19th Networking Event: Early connection as
a selection criteria under REIPPP
Jason van der Poel
Partner
Allen & Overy (South Africa) LLP
9 December 2015
© Allen & Overy 2015 2
525Partners
2,651Lawyers
4,910People
47Offices
33Countries
Allen & Overy – A global snapshot
© Allen & Overy 2015 3
* Associated office
AMERICAS
New York
São Paulo
Toronto
Washington, D.C.
AFRICA
Casablanca
Johannesburg
ASIA PACIFIC
Bangkok
Beijing
Hanoi
Ho Chi Minh City
Hong Kong
Jakarta*
Perth
Shanghai
Singapore
Sydney
Tokyo
Yangon
EUROPE
Amsterdam
Antwerp
Athens**
Barcelona
Belfast
Bratislava
Brussels
Bucharest*
Budapest
Düsseldorf
Frankfurt
Hamburg
Istanbul
London
Luxembourg
Madrid
Mannheim
Milan
Moscow
Munich
Paris
Prague
Rome
Warsaw
MIDDLE EAST
Abu Dhabi
Doha
Dubai
Riyadh*
** Representative office
Global presence
© Allen & Overy 2015
Selected relevant awards
RENEWABLE ENERGY LAW FIRM OF THE YEAR – UK 2014Finance Monthly 2015
AFRICAN RENEWABLES DEAL OF THE YEAR
LAKE TURKANAPFI Thomson Reuters 2014
AFRICAN RENEWABLES DEAL OF THE YEAR
LAKE TURKANAIJ Global 2014
EUROPEAN SOLAR DEAL OF THE YEAR
MEGALIMIJ Global 2014
INTERNATIONAL LAW FIRM OF THE YEAR
IFLR 2014
4
© Allen & Overy 2015
Our South African team
Lionel Shawe
Partner
Mike Duncan
Partner
Jason van der Poel
Partner
Lisa Botha
Partner
Khurshid Fazel
Partner
Sibusiso Zungu
Director
Lindani Mthembu
Director
Allen Leuta
Director
Anthony Colegrave
Director
Kathleen Wong
Counsel
Supported by 5 senior associates, 11 associates, 2 trainees
All working across:Projects and project financing, Banking and financial services, Asset management, Financial services regulation,
Derivatives, Restructuring, Securitisation, Trade finance, Tax, Corporate/M&A
5
© Allen & Overy 2015
What are we seeing from behind our desks?
6
Successful closure of REIPPPP Round 3 Projects, although in some
instances, there was a large cost variance between the Cost Estimate
Letters and the Budget Quote.
The delay in commencement of work, the slowing down and the suspension
of work on our REIPPPP Round 4 preferred bidder projects.
Expedited Bid Phase bid submission date postponed to 11 November 2015
but large number of bids were submitted. Some Cost Estimate Letters had
not been issued before the previous 2 November deadline but all appeared
to have Cost Estimate Letters by 11 November.
Potential new IPP investors are jittery and adopting a wait and see attitude.
.
© Allen & Overy 2015
Why are we seeing this?
7
Application on 26 September 2015 by Eskom Transmission (Grid Code
Advisory Committee) to NERSA RSA Grid Code secretariat for an exemption
from the Network code 2(2) for the issue of budget quotes to customers until
the end of the MYPD3 period (31 March 2018) on account of Eskom’s
“serious liquidity issues”.
NERSA statement that it cannot issue guarantees to Eskom outside the
regulatory process and that Eskom must follow the prescribed process by
submitting either an adjustment in terms of the Regulatory Clearing Account
or an early tariff Application. Eskom board expressed willingness to engage
on this basis and made a MYPD3 RCA submission in November 2015, which
NERSA is now considering.
IPP Office establishment of a strategic grid connection committee to examine
the way forward; ongoing engagement – very helpfully reported on at this
year’s Windaba.
Market eagerly awaiting clarity.
© Allen & Overy 2015
Connection as a Qualification Criterion under the
RFP
8
Bidder must submit a Project Schedule, which must include the anticipated
time for completion of the Transmission/Distribution Works (Part B clause
2.6.1.7 (Project Schedule)).
Bidder must liaise with relevant Grid Provider (Part A), and provide cost
estimate letter for indicative cost and indicative timeline for grid connection
(Part B clause 2.6.1.8.2 (Time and Cost of Grid Connection)).
Bidder must clarify which parts of the grid connection works will be
implemented by the Bidder, any element defined as self-build or own build –
it seems that Eskom build is no longer applicable.
Bidder must be capable of complying with Codes by Scheduled COD.
Earliest connection comparative to others is not a specific
technical requirement for qualification, nor is it one of the
evaluation criteria.
© Allen & Overy 2015
Benefits of early connection: CSIR study
9
As the diesel, mid
merit coal and LNG fuel saving value of
wind and PV declines
as the South African system becomes less
constrained, bringing
such projects online
early maximises NPV for the system
According to CSIR study each month
earlier grid connection adds an NPV of 0.5 r-ct/kWh
during the entire PPA
Projects with early connection capability could be favoured by:
• adjusting proposed tariffs upwards for evaluation purposes by 0.5r-
ct/kWh for every month of committed COD after base month; and
• increasing penalties for late COD.
Source: CSIR Report: Value of earlier grid connection of renewable projects: a power system and macroeconomic cost-benefit analysis, 17 August 2015
© Allen & Overy 2015
Geographical blindness in the REIPPP bid process
10
Out of 8400 MW of IPP solar farms, 6400 MW is
allocated to the Northern Cape, whilst only 2000 MW is
dispersed elsewhere in the country
2000
6400
Levelised cost of renewable energy (RE) supplied at the
point of connection to the grid is weighted at 70% for bid
evaluation. Solar PV bidders generally opt for areas with
the highest irradiation and thus the best energy yields -
typically in the Solar Corridor.
Source: Analysis: SA renewable energy bid process flawed, Pierre Potgieter and Chris Yelland, EE Publishers; GIZ Study Report: Analysis of options for the future allocation of PV farms in South Africa
© Allen & Overy 2015
Geographical blindness in the REIPPP bid process
11
Solar irradiation in South AfricaSource: GIZ Study Report: Analysis of options for the future allocation of PV farms in South Africa
© Allen & Overy 2015
Geographical blindness in the REIPPP bid process
12
Cost
Socio-economic
Development
IGNORED: the costs of additional
grid infrastructure and upgrades,
and transmission losses to the point
of consumption.
RESULT: grid congestion, time
delays and importantly, additional
real delivered costs when the
transmission grid upgrades and
transmission losses are included
Source: Analysis: SA renewable energy bid process flawed, Pierre Potgieter and Chris Yelland, EE Publishers
© Allen & Overy 2015
Renewable Energy Development Zones
13
GIZ study: 3 options, one of which the allocation of facilities is predominantly
within defined Renewable Energy Development Zones (REDZ)
REDZ:
• considers transmission losses, municipalities with high social need and
development potential, priority areas for renewable energy manufacturing
and import activities, and existing transmission infrastructure
• integrates environmental, economic and social factors to identify
geographical areas where in the medium to long-term wind and solar PV
development will have the lowest impact on the environment while
yielding the highest possible social and economic benefit
Source: GIZ Study Report: Analysis of options for the future allocation of PV farms in South Africa
© Allen & Overy 2015
Renewable Energy Development Zones
14
Scenario A: Current allocation strategy predominantly in the Solar Corridor (maximum energy yield)
Scenario B: Allocation predominantly close to load centres (minimum grid reinforcements)
Scenario C: REDZ
Total levelized cost of electricity of PV generationSource: GIZ Study Report: Analysis of options for the future allocation of PV farms in South Africa
Total levelised costs for all three scenarios – very similar.
© Allen & Overy 2015
Rethinking bid selection
15
• Unfairly favours projects with low levelised cost at
the point of connection
• Alternative strategies:
• Choose projects that can connect quicker to
maximise diesel, coal and gas cost offset
• better distribution allowing for much needed
generation capacity to be connected faster
• Minimisation of transmission grid upgrades and
transmission losses
Proposed PV allocation in REDZSource: GIZ Study Report: Analysis of options for the future allocation of PV farms in South Africa
© Allen & Overy 2015
Key Allen & Overy contacts
Jason van der Poel
Partner
+27 (0)10 597 9850
+27 76 123 5323
© Allen & Overy 2015 17
These are presentation slides only. The information within these slides does not constitute definitive advice and should not be used as the basis for giving definitive advice without checking the primary sources.
Allen & Overy means Allen & Overy LLP and/or its affiliated undertakings. The term partner is used to refer to a member of Allen & Overy LLP or an employee or consultant with equivalent standing and qualifications or an individual with equivalent status in one of Allen & Overy LLP’s affiliated undertakings.
JH: 61261