Upload
father
View
232
Download
1
Embed Size (px)
Citation preview
7/24/2019 SAP invoice
1/86
You can create invoicing plans directly for network activities (external, service, or general
costs) or components procured externally.
This means that it is possible to plan costs and outgoing payments on the basis of dates
entered in the invoicing plan. Costs are not simply distributed, but are calculated precisely
at the times specified in the invoicing plan.
You can create an invoicing plan by copying a reference invoicing plan.
The reference invoicing plan fixes cost and payment times relative to a start date.
lternatively, you can copy billing milestones as dates to the invoicing plan of the activity. !f
you copy the milestones rather than creating them manually, they can be postponed
along with the dates in the invoicing plan if the activities are rescheduled.
You cannot create invoicing plans in combination with unit costings (for general costs
activities or material components).
"
7/24/2019 SAP invoice
2/86
$n the basis of days, periods or fiscal years one can plan payment flows i.e. revenues
and expenditure.
!n %&' elements, manual planning of revenues and expenditure is by period. t
commitment item level (roect Cash *anagement master data) planning takes place.
The +uantity structure in the network and the billing plans in the %&' or ' document
are valuated in the automatic planning of financial data.
utomatic planning will be done by day. lanned line items will be written.
&ased on assignment to -/ accounts commitment items will be determined. 0nlike
revenue and costs calculation, payment date calculation takes account of the
customer and vendor payment terms respectively.
1ote2 The credit side payment plan of the network is determined using theasynchronous network costing only.
The dates and the payment terms are used in the ' billing plan for planning incoming
payments. 'ales order items will also be used in assigning the billing plan data and
payment terms(of the dates or sales order item).The delivery date including the
payment conditions is used if there is no billing plan for the sales order item.
"
7/24/2019 SAP invoice
3/86"
!n the case of activities processed externally and externally procured components,
invoicing plan including payment conditions are used 4 or, the delivery dates including
payment conditions are used where there is no invoicing plan
!f an invoicing plan has been maintained, payment data is only planned for
general costs activities
7/24/2019 SAP invoice
4/86
lanned revenues and incoming payments is relevant in billing plan.
ates for own payments are relevant only for payments (not revenues).
*ilestone billing dates appear as planned incoming payments and planned revenues. Two
things are important for dates and amounts i.e. payment terms and payment target
(example2 payment 3 week after invoice issue, with 56 discount)
$nce the proect is executed, invoice billing will be generated and appear in the proect as
actual revenues and customer payment obligations. %ith respect to dawn payment date,
down payment re+uests will be generated by the billing program which are recorded inthe payment data for the proect.
&illing plan can be created for a sales order, a sales order item or for a billing element in the
%&'.
lanned costs and planned outgoing payments are relevant during the !nvoicing plan.
"
7/24/2019 SAP invoice
5/86"
!nvoicing planes can be created for externally7processed activities, externally7
procured material components, service activities and cost activities.
7/24/2019 SAP invoice
6/86
epending on the transaction, you can calculate costs for one network (example2 network
maintenance) or a range of networks (example2 all networks for selected %&' elements
in structure planning or the proect planning board).
You can calculate network costs asynchronously. The advantage of this is that you can select
and cost broader ranges (example2 to 8) and carry out costing in the background.
"
7/24/2019 SAP invoice
7/86
Costing variant controls calculation of planned and actual cost. Costing variant
is assigned to order type. 1etworks are of order category 5#.
The valuation procedure is defined by valuation variant which is a component of
costing variant. &ased on valuation variant prices are determined by the system to
value componenets material, activity type, processes, subcontracting and external
activities. 9aluation variant searches for prices in se+uence from the price sources.
rice entered first is selected first
*aterials2rice is selected either from purchasing date or material master record
ctivity type : rocesses2 rice is selected either from activity based costing or
cost center accounting
;xternallly processed activity2price is selected either from the activity or from
purchasing information record
"
7/24/2019 SAP invoice
8/86
%hen customi=ing the order value update, you stipulate, for each order category and
type, whether the order or network is appended 7 that is, whether its planned costs are
added to the proect cost plan for assigned %&' elements.
There are two tables for the order type (network type). The first is defined per order type,
the second (parameters for network) per order type and plant.
third important table is the network profile, containing default values for the network and
its activities.
The costing variants for plan and actual costs are determined at network header level.
The costing sheet and overhead key are determined at activity level. They control processcost accounting or application of overhead. epending on the creation process, these
keys are inherited from the network header or the assigned %&' element.
"
7/24/2019 SAP invoice
9/86
The costing variant contains the basic control information needed to carry out
costing. The valuation variant contains all the information which controls the
valuation of2
*aterial components
!nternal activities
;xternal activities
This information also
controls how
overheads areapplied.
9aluation can be
determined plant by plant.
The ?&y period? indicator enables you to calculate costs for internally7processed
activities period by period.
The costing type contains further detailed information for controlling costing.
"
7/24/2019 SAP invoice
10/86
You can classify the resources in broadly 5 categories from the networks point of
view2 !nternal and external activities.
!nternally processed activities2 These activities work are carried out by
machines and or persons of own company. You can schedule the activities as
per re+uirement, distribute the work among persons.
;xternally processed activities2 these activities are executed processed by other
companies. These are carried out by purchasing department. The service
activities are also procured externally however different from externally
processed activity that you need to define service specification and the limit for
the unplanned activities which is provided by the service provider.
"
7/24/2019 SAP invoice
11/86
Business scenario
To execute a proect, materials are re+uired
which can be procured externally (purchasing) or
manufactured in own company (roduction). These
materials are managed in proect7specific stock.
s the proect controller, you are interested in2
The values in the proect, at the different stages of purchasing or production
(proect controlling)
'tocks of raw materials, semi7finished and finished products used for your proect
"
7/24/2019 SAP invoice
12/86"
(stock controlling)
*aterials provide linkage between many other ' functional modules like
*aterials *anagement (urchasing and !nventory *anagement), 'ales and
istribution, plant maintenance and roduction lanning and Control.
The materials are assigned to activities which helps in material re+uirement and
planning in a proect.
The product which is manufactured in your project is in turn made up ofa variety of material components.
The first step is to plan the procurement and consumption of the requiredcomponents in your project.
Projects are linked to Materials management, Sales and istri!ution and
Production Planning via materials.
7/24/2019 SAP invoice
13/86
!n order to plan the material re+uirements of a proect, materials can be assigned to
activities. $n the basis of stock, the materials are classified as stock or non7stock items.
The item category stock items (/) are for such materials which are stored in stock e.g. proect
stock, sales order stock or warehouse stock and reservations can be created for such
materials. &ased on the +uantity re+uired in the proect, the re+uirement planning can be
initiated. The procurement element for external procurement is a purchase re+uisition and for
re+uirement planning is planned order.
or productions of assembled material, material &$* is exploded and the
re+uirement planning is executed for all the materials mentioned in &$*.
1on7stock items (1) are for materials which are to be procured directly for the network which
is not using *D (i.e. not procured via proect stock, sales order stock or warehouse stock).
or non7stock items, urchase re+uisitions are created which are passed on directly to
urchasing.
"
7/24/2019 SAP invoice
14/86
The item category ?stock item? (/) is used for materials kept in stock. %hen you save
your data, the system creates a reservation for the re+uired material. purchase
re+uisition 7 which is passed on to urchasing 7 can also be created for components
procured externally.
The main function of material re+uirements planning is to ensure material availability
(in other words, to procure the re+uired +uantities in time 7 both in7house and for sales
and distribution). This includes monitoring stocks and, above all, creating procurement
proposals for purchasing and production.
!ndependent re+uirements 7 that is, re+uirements for finished products, assemblies or raw
materials 7 trigger re+uirements planning. !n order to cover the re+uirements, order+uantities and dates have to be determined, and the corresponding procurement elements
scheduled. The procurement element for re+uirements planning is a planned order and,
for external procurement, a purchase re+uisition. urthermore, the dependent
re+uirements for materials produced in7house (in other words, the +uantity of components
re+uired to manufacture a finished product or assembly) are determined by exploding the
bill of material. lanned orders are created at each &$* level to cover re+uirements
when a material shortage occurs.
7/24/2019 SAP invoice
15/86
7/24/2019 SAP invoice
30/86>
7/24/2019 SAP invoice
31/86>
7/24/2019 SAP invoice
32/86
!t is common in engineering proects for critical components with long and unreliable
delivery times to be purchased at an early stage in the proect much before the
proect activities in which the components will be used are specified. dvance
procurement process is used in such situations.
dvance procurement can only be used when you are using sales order or proect
stock .
>
7/24/2019 SAP invoice
33/86
Order Categories and order types
ocuments are used to enter business transactions in the D" 'ystem. $rders are
one type of business transaction. $rders are determined by their order category.
The network is an order category. $rder types are prescribed by the system for the
relevant applications.
You can define your own order types within an order category. The order type
describes how the order is controlled.
Customi=ing includes two tables, one for the order type and another for the
order typeplant combination.
The order category is used to control2
3. 1umber assignment
5. efault value settings
". 0ser7specific status management
7/24/2019 SAP invoice
34/86>
You can assign various ' orders to a proectF examples include internal orders,
production orders, and plant maintenance orders. You can then use the proect
hierarchy reports to evaluate these assigned orders with the %&' element.
;ach order is a cost obect with its own costing parameters such as planned costingvariant, actual costing variant, and overhead sheet. The planned costs of assigned
orders are used to determine the planned costs of the proect.
You assign orders to the proect either by assigning a %&' element to the order
header or by assigning the order to a network and activity as a subnetwork. !f the
assignment is re+uired only for cost control and analysis, you need to assign order to
the relevant %&' element. !f the assignment is re+uired both for scheduling and
cost control, you need to assign the order as a subnetwork. The %&' element is
derived from the network activity. 1ote that production orders cannot be assigned as
subnetworks.
ocuments are used to enter business transactions in the D"
'ystem. $rders are one type of business transaction.
$rders are determined by their order category.
The network is an order category. $rder types are prescribed by the system for the
relevant applications.
You can define your own order types within an order category. The order type
describes how the order is controlled.
Customi=ing includes two tables, one for the order type and another for the
order typeplant combination.
The order type is used to control2
1umber assignment
efault value settings
0ser7specific status management 0ser7
specific field control
lant and order type parameters are used to control2
!f the network is activity7 or header7assigned
lanned and actual costing variants
The settlement rule strategy
7/24/2019 SAP invoice
35/86
You can use the ?appended? indicator to specify, per order category, whether an
order is appended 7 that is, whether the planned values for the order are included
in the planned value of the corresponding %&' element2
3. !f the ?appended? indicator is set, the order planned value increases the
%&' element planned value. The information system shows the total
as the proect plan. %hen cost planning is taken over as the budget,
the values from appended orders also contribute to the budget.
5. !f the ?appended? indicator is not set, the order planned value is not
added to the %&' planned value. !n budgeting, the plan total for such
orders must be added manually so that these orders can use funds
later.
>
7/24/2019 SAP invoice
36/86
You can use the ?appended? indicator to specify, per order category, whether an
order is appended 7 that is, whether the planned values for the order are included
in the planned value of the corresponding %&' element2
$nce released, all orders are apportioned 7 this means that their plan, commitment,
and actual values are funds assignments against the funds in the proect. The
order value table contains an indicator which you can use to make orders
?apportioned? earlier, at the ?created? stage.
You can set appended and apportioned indicator based on the order category,order
type, and controlling area
n exception to apportionment at release is in the case of networks for preliminary
planning.!n roect 'ystem customi=ing,you can specify network types to be used
for preliminary planning.reliminary planning networks are never apportioned.Their
related plan values do no increase the assigned value for the relevant %&'element
!n the case of networks (order category 5#), you can use the network type
parameters to determine whether the network is2
Geader7assigned or activity7assigned 7 that is, whether costs are managed in
the network activities or collected in the header
>
7/24/2019 SAP invoice
37/86>
preliminary planning network whose plan, commitment, and actual values
are not apportioned 7 meaning that they do not appear as assigned values
in the proect.
7/24/2019 SAP invoice
38/86
Header-Assigned Networks
!n a Geader7assigned networks all the costs (activity and material) are assigned at
network header level
fter assignment of network header to a %&' element, ll costs are transferred to
%&' element. ssignment of activities to %&' elements is only to summari=e thedates
%e you have to use header7assigned networks to assign networks to sales order in
case sales order are not assigned to proects as no assignments can be made to a
sales order item in the network activity.
Activity-Assigned Networks
Costs are collected on activities in case activites are used as account assigned
obects.lantnetwork type parameters deines the condition if the network header
or network activities are to be used as cost obects.
ctivity7 assigned networks are usually used when activities are assigned to various
%&' elements.Gere every activity in the network is an account assignment obect.
%hich implies we can analy=e planned costs, commitments and actual costs
for each activity.
The costs are aggregated and displayed for the %&' elements to which
the activities are assigned.
>
7/24/2019 SAP invoice
39/86>
ctivity account assignment is a special feature of networks. ll other order types are
header7assigned. ctivity account assignment is controlled via the appropriate
indicator in the table ?arameters for network type?.
Geader assigned networks should be used when networks are assigned to salesorders without %&'.Geader assigned networks can also be used when the
enitre network is assigned to a single %&' element
7/24/2019 SAP invoice
40/86
' document item assignment is controlled via the account assignment category.
The account assignment category is controlled via ' re+uirements type
determination.
!mportant factors that affect account assignment are the strategy group, the *D
type and item category group from the material master of the product as well as
the document type of the ' document.
The system defaults the item category when you create an order. You can accept
the default or overwrite it. ermitted item categories are defined in Customi=ing.
The permitted planning strategies are assigned to the material using the planning
strategy group. This is necessary so that you can find the correct re+uirements type
in independent re+uirements management and sales order management.
The default re+uirements type is the main strategy in the planning strategy group.
!f no planning strategy group is defined in the material master, the system uses the
item category group (sales and distribution screen in the material master) and, if
necessary, the *D characteristic to search for the re+uirements type for the salesorder.
>
7/24/2019 SAP invoice
41/86
The account assignment category determines the C$ obect to which document
+uantities and values are assigned. You use it to determine the following2
0sing the special stock indicator (''! above), that goods movements in /ogistics use
plant stock, sales order stock or proect stock.
0sing the consumption posting indicator (Cons. above), the C$ obect to which the
values of a material document are assigned.
'ettings2
H Collective stock, consumption posting to the consumer (order, activity)
The account assignment category is important for procuring components directly.
; H Iuantities and values managed in the sales order item
This account assignment category is important for make7to7order production without
%&'.
H Iuantities managed using sales order item, values managed in proects
This account assignment category is important for non7valuated proect
stock, with %&' and sales order item
I H Iuantities and values managed in proects
This account assignment category is important for proect stock
>
7/24/2019 SAP invoice
42/86>
- H lant stock, values managed using proect
This account assignment category is important for sales order items sold
from plant stock, with
value posting to the proect. !t differs from account assignment category ?? in
the field control
of the account assignment block.
7/24/2019 SAP invoice
43/86
ctivity7&ased Costing offers a facility for allocating and distributing the overhead to its cause.
ctivity7&ased Costing provides useful information on2
$verheads reduction by process improvement
rofitability increase by highlighting unprofitable products or customers
ctivity7&ased Costing is advantageous for having2
J Transparent overheadsJ arallel +uantity and value flows
J recise assignment of internal activities to consumer
Keanut butter effect? can be avoided through even distribution of overheads among all
the cost drivers.
@
7/24/2019 SAP invoice
44/86@
!n ctivity7&ased Costing, processes are the controlling obects. rices can be either
maintained manually or using activity and cost input planning in the case of cost
centers and activity types. Through activity based costing, processes are debited to
cost obects or profitability segments.
7/24/2019 SAP invoice
45/86
Templates are created in LCustomi=ingM and determined by controlling area, costing sheet,overhead key and template environment (for networks 4 ##
7/24/2019 SAP invoice
46/86@
proect
Calculated value to be added to the
proect at the start, end or continuously
The price for the process and the allocation cost element are determined by
entering one process per line in the process template. *ulti7level processes can be
mapped by referencing another process template in the working template.
The +uantity used by the cost obect is determined using the cost driver. This enables
the allocation of the relevant values to all the levels in the process hierarchy as far
as cost obects or profitability segments.
Cost drivers can originate from many different sources in the D" 'ystem or external
systems. ;xamples 2 weight (material master), number of components, activities of a
particular category, work center (network), number of sales orders for market
segment (/!') etc. The +uantities determined by the cost driver are multiplied by the
price of the process. The resulting value is charged to the cost obect (in the
example, the %&' or networkactivity), and the process is credited.
7/24/2019 SAP invoice
47/86
ctual prices for activity types and business processes are calculated in $verhead
cost controlling at the end of the period.
ctual prices H ctual costs Iuantities consumed
The possibility of revaluation at actual prices and its specification for each
activity type are controlled in Customi=ing in the parameters for the actual
version depending on the fiscal year.
The difference between the actual price and the originally allocated price is
charged to the cost obects.
Devaluation at actual prices for activities and business processes can be done
in the roect 'ystem and in the Cost $bect Controlling.
Devaluation at actual prices using an activity type is illustrated in the example given
in the slide
@
7/24/2019 SAP invoice
48/86
$verheads calculation is used to allocate overhead costs to cost obects such as activities
and %&' elements. Calculations are done based on the Costing sheet entered in
the cost obect and the overhead key entered on the %&' element,network header or network activity. $verheads can be calculated for
planned, commitment and actual values. $verhead calculations are
done using the +uantity based or percentage allocation rates.
The following postings get generated through overheads allocation2
ebits to cost obect (%&' element, 1etwork header or1etwork activity )
Credits to cost center ( overhead order or process )
@
7/24/2019 SAP invoice
49/86@
$verhead costs are updated using the secondary cost elements
in the costing sheet credit rows and these can be simulated also.
7/24/2019 SAP invoice
50/86
Costing sheet is derived by means of the costing variant from the ?arameters for
1etwork Type? table, in the case of networks. The costing sheet and the overhead key
can be changed in the network header.
The costing sheets to be used in the activities are made a default through this.
or %&' elements, the costing sheet is derived directly from the proect profile. !n
the case of ;asy Cost lanning and the unit costing for %&' elements, the cost
planning draws on a costing sheet for a costing variant which is assigned to the
proect profile through the planning profile.
$verhead keys for activities are inherited from their respective %&' elements.
@
7/24/2019 SAP invoice
51/86
$verheads are calculated using a costing sheet.
The overhead surcharge can either be a percentage if it is value driven or an absolute value
of measure if it is +uantity driven. The overhead is calculated against a base which is defined
by the cost elements. Cost elements or cost element areas are collected in base lines.
actors such as Controlling area, company code, plant, overhead group, network type, time
period and plan versus actual determine the overhead rate applied. $verhead key assigned
to the cost obect decides the determination of overhead group in customi=ing. Thus a single
costing sheet with flexible rates can be made use of different organi=ational units or
individual activities.
@
7/24/2019 SAP invoice
52/86@
networksactivities.
s part of the network costing, the system automatically determines planned
costs when you plan dates and resources for the following obects2
a. or internally processed activities2 activity inputs
b. or externally processed activities : service activities2 rimary costs
c. or genreal costs activities2 primary costs
d. *aterial componenets2 primeary costs.
You can use planning templates to create +uantity structures for ;asy Cost
lanning.
You can enter +uantities and prices in the template, or regulate activation using
formulas or conditions.
You can use characteristics assigned to the planning template as variables for the
formulasconditions. The characteristics are valued by the user when theplanning templates are copied into ;asy Cost lanning.
7/24/2019 SAP invoice
53/86
0nit costing is done to calculate cost plan per %&' element. Gere we use
planned +uantities instead of cost.
!t is not period dependent
t cost element level, plan values are displayed
!nput information related to sources of supply, +uantities and prices mark the useof unit costing to generate cost plan per %&' element
@
7/24/2019 SAP invoice
54/86
Structure Oriented Panning!
'implest type of planning is structure based planning. lan values are displayed
in hierarchy
The total cost planned is aggregate
!t is neither by cost element nor is period specific
9arious views are used to display the different values in structure7oriented
planning
lanned total 9iew7this shows total aggregate at superior %&' element (/evel
3 %&' element)
The distributable or distributed view7This view is used to check distribution of
budget among child %&' element
Cumulative or remainder view7This view is used to check distribution of budget
across years
$rdernetwork view7This displays the planned cost od appended ordersnetworksassigned to %&' element
Cost Element Planning/Activity Input Planning:
%hen more detailed information is re+uired, cost element planning is done. !t
is independent of proect scheduling
*anual reschedule of cost planning becomes mandatory if a proect or
individual
@
7/24/2019 SAP invoice
55/86@
package schedule is changed
This planning is adopted if precise information is available as it becomes sure not
to reschedulepostpone the proect
7/24/2019 SAP invoice
56/86
The plan profile is used to control overall costrevenue planning. !t contains costing variants
for the unit costing or ;asy Cost lanning.
!t also contains indicators for updating revenue plan values via customer +uotations or sales
orders.
You assign the plan profile to the proect by way of the proect profile. You can change it in the
proect definition.
Costs and revenues can be planned in different C$ plan versions.
You either specify the plan version during planning or, if you are using ;asy Cost lanning,
you assign it to the controlling area.
lanning layouts are used to plan costs, revenues, payments, and statistical key figures.
You can use the Deport ainter to create the layouts and can assign them to planner profiles.
0sers can choose planner profiles and assign them to the user master record.
lanning profile2 0se transaction $'&
The lanning profile contains the settings related to planning. !t control overall
costrevenue planning. lanning profile is assigned to proect using proect profile. Costing
variant are
@
7/24/2019 SAP invoice
57/86@
relevant if we are using unit costing and easy cost planning
C$ plan version is re+uired to be specified if we are using easy cost planning.
lanner profile and planning layouts are specific to use of detailing planning
using Kcost elementactivity inputN
7/24/2019 SAP invoice
58/86
lanning profile is contains the settings for overall planning, detailed planning
and unit costing
etails for each field can be checked using
3 !mportant field details are as2
Total 9alue2 efines overall planning without any reference to fiscal year
nnual lanning2 efines overall planning with reference to fiscal year
&ottom up lanning2 $verall planning values are extrapolated after saving
;xchange rate type2 etermines which exchange rate is to be used for currency
conversion of overall values
A
7/24/2019 SAP invoice
59/86
Transaction $OOT to edit costing and valuation variant
Costing variant is mostly used for unit costing ,easy cost planning and also used for
costing networks. The field costing type determines for which %&' element
(costing obect) costing is done
9aluation variant determines the prices and rates. !n the above mentioned slide,system will first check for Klanned price 3N if it fails, system will check for Kstandard
priceN and again if it fails it will check for Kmoving average priceN from material
master. !f system now fails, it will trigger an error message during cost determination
A
7/24/2019 SAP invoice
60/86
"nternay-processed activities!
!f no distribution key or work center is maintained in the activity, the costs are distributed
evenly over the earliest dates in the activity. 9aluation is at the rate in the valuation variant.
epending on the strategy being used, the system can determine the most current date.
valuation is determined by the rate maintained in the valuation variant. &ased on the
strategy adopted, system determines the latest date. !f no work centerdistribution key is
maintained, the system distributes the cost evenly over the earliest dates.
Costs activity!
Case 32!nvoice plan maintained2the values in periods are as per the values mentioned
in invoicing plan
Case 52!nvoicing plan not maintained and distribution key maintained2The activity value
is
A
7/24/2019 SAP invoice
61/86A
distributed to the periods based on the distribution key maintained in the activity
Case "2!nvoicing plan not maintained and distribution key not maintained2The
costs are distributed evenly over the earliest dates in the activity
!f an invoicing plan has been maintained, the values in the periods are set
as specified in the invoicing plan.
$therwise, the activity value is distributed to the periods using the distribution key in
the activity. !f no distribution key is maintained in the activity, the costs are distributed
evenly over the earliest dates in the activity.
Service activities or e#ternay-processed activities!
Case 32!nvoice plan maintained2the values in periods are as per the
values mentioned in invoicing plan
Case 52!nvoicing plan not maintained2The activity value is set in the period of the
latest activity start date.lso the system determines the price from the purchasing info
record or the activity value.
!nvoicing plan has priority for the values
!f an invoicing plan has been maintained, the values in the periods are set
as specified in the invoicing plan.
$therwise, the activity value is set in the period of the latest activity start
date.
The invoicing plan has priority for the values. !f no invoicing plan has been
maintained, the system determines the price from the purchasing info record or
the activity value.
$ateria components!
Case 32!nvoice plan maintained2the periods and ,in some cases,values are
taken from invoicing plan
Case 52!nvoicing plan not maintained2The system determines the price from the
purchasing info record or the price is taken from material master as per
valuation variant.Gere material re+uirement date determines the period
!f an invoicing plan has been maintained, the periods and, in some cases, the
values are taken from the invoicing plan. !f no invoicing plan has been maintained,
the values are taken from the purchasing info record or the price is taken from the
7/24/2019 SAP invoice
62/86A
material master per the valuation variant. !n this case, the period is that from
the material re+uirements date.
7/24/2019 SAP invoice
63/86
The customer accepts the +uotation. sales order is created in the system, where
appropriate using the +uotation as a template. The activities listed in the +uotation
are entered in the sales order as sales order items.
The items are assigned to the proect. They are used for revenue planning and for
posting revenues to the proect by means of milestone billing.
Two companies are responsible for executing the proect 7 !;' - and !;' 0O.
!;' 0O creates a sales order for !;' - and assigns the document item to the
billing element T73##PP.3.5.
/ater on, !;' 0O bills its services to !;' - on a resource7related basis.
billing re+uest is created in the system via resource7related billing. This is billed and
results in revenues for !;' 0O.
A
7/24/2019 SAP invoice
64/86
!n ' where proect is a controlling obect2
'ales order created and after structuring of proect sales order will account assigned to%&'. Then revenue planned in sales order.
$nce %ork completed in proect, actual cost captured in %&' and inal product will
be delivered to Client.
&illing will be completed and actual revenue generated. ctual Devenue will
be transferred to %&'.
%hile Desult analysis performed for proect the ctual Devenue and Cost will settled
to the profitability segment.
Sae document structureJ 'ales ocument type represents the type of business transaction and functions and
the flow of document with in sale order. rocessing.
J !tem Categories are assigned to sales document category. %hile creation of 'ales order
it will default the item category but user can change it as per re+uirement.
J 'chedule line category is assigned to !tem Category. %hile creation of document
system will default the scheduled line category but it can changed according to
re+uirement.
A
7/24/2019 SAP invoice
65/86A
"tem Category
J Item Category is determine by Sales Document type and thematerials Items category group in a sales order.
J Item Category controls function for Sales Order like Item Type,Pricing, illing Plan, resource related or deli!ery related.
J It controls if pricing is rele!ance for billing, rele!ance for Deli!erySchedule "ine Item, and contains Incompletion "og and Partner te#t.
7/24/2019 SAP invoice
66/86
(3)Depresents a process of make7to7order production without a work breakdown structure.
!n this case, the sales order item is the contolling instrument. ccount assignment category
; specifies that the sales order item forms a separate C$ obect.
Costs and revenues of the sales order item are usually settled to the profitability segment.
(5)0sing assembly processing, you can generate a network when you create the sales order.
%hen you save your data, the system creates a %&' and assigns the sales order item to a
%&' element in this %&'. !n this case, the sales order depicts the sales view, the proect is
the controlling instrument, and logistical processing is represented by the network.
ccount assignment categories or I (Cons. H in each case) specify that revenues
are assigned to the billing %&' element of the proect.(")s an alternative to assembly processing, you can assign a sales order item to a %&'
element in a proect. Controlling takes place in the proect. You can assign orders or
documents to the proect. 9alue assignment to the proect is controlled via account
assignment categories -, and I. These differ from each other in the way that they
manage +uantities.
A
7/24/2019 SAP invoice
67/86
*ethods for plan revenue in a proect are2
a. *anual revenue planning2 this can be based on structure or revenue element
where the later is a cost element and period based.
b. ' billing plan2 this is cost element and period based planning.
c. ' document2 this is part of integration with ' module where sales order itemor +uotation items are used as revenue planning. This kind of planning is cost
element and period based.
A
7/24/2019 SAP invoice
68/86
Devenues can be planned in proects using the following methods2
*anual planning in billing elements in the proect structure.
This type of planning can follow the same procedure as cost planning, or can be by
revenue element.
'ales orders (all ' documents assigned).
'ales order items are assigned to %&' elements. !n Customi=ing, you can stipulate, for a
combination of sales document category (+uotation, order, and so on), sales
document type, controlling area, and system status, whether the billing data (for
example, in a billing plan) from a sales order should update the revenue plan for an
assigned %&' element. The dates and planned revenues concerned originate eitherfrom the billing plan for the sales order items or (if there is no billing plan) from the
net value and apportionment data for the item. The revenue element originates from
-/ account determination in '.
&illing plan in proect billing elements.
The revenue element is defined in Customi=ing.
A
7/24/2019 SAP invoice
69/86
There are different ways of creating billing plans2
*anually
&y copying a reference billing plan
!n ' and ', reference billing plans can be
called upon automatically
&y copying billing milestones from work
breakdown structures or networks
&y copying billing milestones automatically from
the network in assembly processing
A
7/24/2019 SAP invoice
70/86
!n the ' document, you can define a detailed billing plan with a number of billing dates
instead of ust a single billing date. billing plan is a schedule containing individual billing
data for a particular sales document.
*ilestone billing is widely used in proects (for example, construction proects).
!f you use milestone billing, the total value to be billed is apportioned to the individual dates
in the billing plan per defined rules.
&illing plan dates can be blocked for billing
You can set billing blocks manually or remove them by activating billing milestones.
s of Delease
7/24/2019 SAP invoice
71/86B
7/24/2019 SAP invoice
72/86
The term ?Version" is used in the proect system in different contexts. ifferent
types of versions include simulation versions, proect versions and C$ planning
versions are available in ' roect 'ystem which are discussed below.
roect versions, are snapshots of a proect at a specific point in time, and are
used for documenting the progress of a proect over time. &oth +uantities and
values are stored in versions and it can be created either manually, or
automatically when a status changes. !n the case of status change, the proect
profile contains a reference to a version profile which specifies the name of
the proect version to be created when a particular user or system status is
set.
'imulation versions2 !n the roect 'ystem, these are versions that you can
change. You might, for example, create simulation versions in the following
situations2
!n the +uotation phase2 generally speaking, at this stage there is not yet
an operative proect.
To draw up alternative planning scenarios for existing operative proects
or parts of these.
C$ plan versions are used to plan revenues and costs. You can copy values
from one version to another. You can change planned values manually in every
version and cost values are retained.
B
7/24/2019 SAP invoice
73/86
'imulation versions are used to draw up alternative ?what ifQ? planning
scenarios. They are created manually, can be changed, and, if necessary,
deleted again which is unlike released operative %&'s with activities.
'imulation versions are useful during the +uotation phase of a proect
and possible to plan several simulation versions.
You can create simulation versions even at the time of execution of proect,
where you can copy from operative to simulation versions, compare, analy=e
and work with other versions and transfer them back to the operative
proect.
%hen an operative proect is copied to a simulation version or vice versa, a
log file is created which contains the obects that were transferred and any
error messages that were issued in the process.
'imulation versions can be created either for an entire %&', or for
sub7 hierarchies of a %&'.
'imulation versions are edited in the proect planning board or in proectplanning board from ' D"
7/24/2019 SAP invoice
74/86
'imulation customi=ation consists of two steps2
3. 9ersion keys2 one should work with permissible version keys since these cannot
be deleted once simulations has been created.
5. 'imulation profile2 This determines which all obects will be copied while creating
simulations (in addition to the structure information) from simulation tooperative (and vice versa). !f there are no simulation profile, all the texts will be
copied. The simulation profile will be defaulted in the proect due to assignment
in proect profile.
Rust like proect version, simulation versions can be compared with each other in
information system, whereas the cost element report does not support the
simulation versions. 0nlike operative proects, simulation versions cannot be
changed in structure info system.
B
7/24/2019 SAP invoice
75/86
%hen you transfer data from operative proects to simulation versions (or
vice versa), the following obects are copied2
%ork breakdown structure
1etwork with activities, activity elements, relationships, and
subnetworks *ilestones
*aterials for the activity
ocuments, ' texts and long texts (depending on the simulation profile
used)
Capacity re+uirements
!nvoicing plan for the network, and billing plan for the %&' element
(as of Delease )
The following obects are not copied2
$ther orders (e.g. no production orders)
roduction resourcestools
B
7/24/2019 SAP invoice
76/86
roect versions enable you to record a snapshot of a proect at a specific
moment in time 7 this can be used for future comparison with the
operative proect.
You can create a proect version automatically (i.e. triggered by a system or user
status).
You can also create a proect version manually2
%hile changing the %&'
%hile changing the network
!n the 'tructureates information system for one or more proects
ata transfer when 9ersion profile settings are used while using these transactions2
3. 'tatus dependent proect versions.
5. TC network maintenance C155 or %&' element maintenance CR#5
ata transfer which is !ndependent of version profile and dependent on
database profile2
". TC C1A3 and C1A5
7/24/2019 SAP invoice
77/86B
The version profile is maintained in the ' customi=ation and assigned to
roect profile or network profile.
7/24/2019 SAP invoice
78/86
You use a version profile to define two different kinds of information. irst, you
specify which version is created automatically when a specific system status or
user status is set. 'econd, you specify which data is to be written to the
versions that are created automatically.
You need to define a version profile, if you wish to have versions created
automatically, or if you wish to generate versions directly when editing the %&'
or networks.
You do not need to define a version profile, if you wish to generate versions
manually from the 'tructureates information system.
The version profile is entered in the proect profile and network profile.
B
7/24/2019 SAP invoice
79/86
roect planning board is a tool in ' ' which helps and enable you to
process edit the entire proect structure which are %&' element, activities,
relationships, milestones, material components, ' texts, documents and
assigned obects to them.
!t is similar to -antt chart based on interactive ' environment.
This comprises of hierarchy structure of your proect and the corresponding
date situation.
You can custom made the display in proect planning board to suite your
re+uirement.
roect planning board can also be useful for planning dates and resources
i.e. work, external processing, for planning costs using activities.
B
7/24/2019 SAP invoice
80/86
roect planning board profile contains default values for the appearance
of planning board.
The settings in this proect planning board profile is valid for both, simulation
versions and operative proects.
The graphical display can be changed and adapt as per user needs inthe planning board and customi=ation using proect planning board
assistant.
B
7/24/2019 SAP invoice
81/86
roect planning board is a graphical interface based on -antt chart which can
be used for creating and maintaining data like proect definition, %&' element,
activities, relationships, milestones, documents and ' texts.
0seful for 'cheduling and monitoring.
You can view date view, and other overviews of proect at the bottom of -anttchart like capacity overview.
You can view logs, hierarchal graphic of %&' element and 1etworks and
network activities.
This is the only transaction where we can change simulation versions for
releases earlier than ' D"
7/24/2019 SAP invoice
82/86
ssembly processing will be helpful while one is planning and producing or
servicing same product for several times with similar constellations. %hich means
the basic structure will be same while data like duration, dates, +uantities etc. will be
changing. !n assembling processing, a network and %&' element : roect (if
re+uired) is automatically created based on the customi=ation, while a sales
document is created and saved. The proect number is derived from 'alesdocument and this process generates assignment between sales document :
proect. This incurs that the same information will be shared by sales and proect
team. !f the data is changed in roect will update 'ales document (and vice versa)
which helps in delays and disagreement between sales and proect department.
rocess flow2
!f a sales order is created for a material which has strategy group for assembly
processing has been assigned, the assembly processing will start.
The *D processing is omitted in the assembly processing and creates a operativeorder (network in case of ') directly from sales order.
ssembly processing is carried out statically in ' which means only one network
for one sales document item.
&ased on the customer re+uirements date, backward scheduling is carried out and
availability check is done for re+uired material components. %hich enables to
inform customer about feasibility of re+uired date or else system will propose new
date.
E
7/24/2019 SAP invoice
83/86E
lso, the calculated cost will be transferred from network the sales order.
%hile saving the sales document, %&' element structure : proect definition will
be created which is identified by sales order number.
'ince the sales document and the proect is directly connected, any changes
one obect will update reflect in other automatically.
7/24/2019 SAP invoice
84/86
The re+uirement class which is assigned with the sales order while creating it will
start assembly processing, one assembly order automatically created by system
and start assembly processing in the back ground. &y this method *D is ignored
and an operational order created directly from 'ales $rder.
&elow is the list of ssembly order which can be created27
1etwork, roduction $rder, planned order, lant maintenance or 'ervice order and
rocess $rder.
ssembly rocessing contains all the date of 'ales order and assembly order. 'o
if there is any change done later to any document it will reflects in both document.
E
7/24/2019 SAP invoice
85/86E
7/24/2019 SAP invoice
86/86