SAP ECC 6.0
PROCESS DOCUMENT OF PROCESS
ORDER CHANGE AND RELEASE
CHANGE PROCESS ORDER – T-CODE – COR2
Change and Release Process Order – Initial
Screen – COR2
Enter the process order no to change and release and press
enter following screen will be displayed
Check the scheduling type , order quantity
and start date
Check stock type it should be Quality
inspection and the required batch no
is assigned
After checking stock type and batch
click on Materials
After clicking on materials icon following
screen will be displayed
Enter the batch no for all the
components if required
By pressing the F4 batches will be displayed select
the required batch for all the components.
Batch is selected for the first component similarly
select batches for the remaining components
Batch selection for all the components then click
on the header icon to go to the main screen
Following screen will be displayed, click on the
scheduling the order icon to schedule the order
Scheduling carried out will be displayed at the
bottom of the screen
Check the material availability by clicking the
icon material availability check
Status will be displayed at the bottom of the screen if
materials are not available system will display the
material not available list
Click on the icon capacity availability
check
Select continue on the information message
System will display the capacity availability
message select continue
Click on the icon to release the order
After Releasing the order save the order
Order is saved and the order no will be
displayed at the bottom of the screen