Prepared By: Abdul Noushad H A
PUNCH POINTS IN
RFE1 SURVEY(TD LTE)
Customer : Circle : KERALA
CONTENTS:
1. Punch Points of GBM(Ground Base Mast) site.
2. Punch Points of RP1(shared) site.
3. Punch Points of P1(own) site.
2 RJIL-SAMSUNG Project PP of RFE1 survey
MARAD site (GBM):
1. Lightening Arrester was not properly installed.
RJIL-SAMSUNG Project PP of RFE1 survey 3
2. Ground cable not connected to TGB.
RJIL-SAMSUNG Project PP of RFE1 survey 4
3. Water logged in EB supply pipe.
RJIL-SAMSUNG Project PP of RFE1 survey 5
4.Only Non-critical MCB’s are available.
RJIL-SAMSUNG Project PP of RFE1 survey 6
5. No signage board available.
RJIL-SAMSUNG Project PP of RFE1 survey 7
6.Pole got cracked on the top of tower.
RJIL-SAMSUNG Project PP of RFE1 survey 8
7. Platform got damaged.
RJIL-SAMSUNG Project PP of RFE1 survey 9
7. Cable routing is not proper
RJIL-SAMSUNG Project PP of RFE1 survey 10
LESSI Hospital(RP1):
1. Lightning Arrestor not installed in all sectors.
RJIL-SAMSUNG Project PP of RFE1 survey 11
2. Rusted cable tray.
RJIL-SAMSUNG Project PP of RFE1 survey 12
3. No DANGER and CAUTION signage board.
RJIL-SAMSUNG Project PP of RFE1 survey 13
4. Water leakage inside the shelter.
RJIL-SAMSUNG Project PP of RFE1 survey 14
ASAD ROAD (P1):
1.No TGB installed.
RJIL-SAMSUNG Project PP of RFE1 survey 15
2. L A installed only in Alpha
sector.
RJIL-SAMSUNG Project PP of RFE1 survey 16
3. No signage board.
RJIL-SAMSUNG Project PP of RFE1 survey 17