Sample PMP Exam Question

Embed Size (px)

Citation preview

  • 8/7/2019 Sample PMP Exam Question

    1/1

    Sample PMP Exam Question

    You are managing a telecom project. You have got two teams reporting to you. One team is responsible for

    equipment installation and the other team is responsible to commission and test that equipment. Both teams

    are working in parallel such that as soon as the installation teams finishes equipment installation at one site

    they move on to another site for installations and the commissioning and testing team start their activities

    on the newly installed site. The reporting structure is such that each of the teams have 5 engineers headedby a team lead. Each team member interacts with each other, however only the team leads interact withyou. Both the team leads also interact with each other to synchronize their operations.

    How many communication channels do you have in your project?

    A. 33

    B. 23

    C. 42

    D. 78

    Hint: Calculate communication channels for each team and add them together.

    Solution

    The correct answer is: A

    Reference: PMBOK4 - pg:253

    Explanation: This was a hard question, wasn't it? Lets analyze the scenario to calculate the answer. Here

    we have two independent teams. Each team has 6 members, i.e., 5 engineers and one team lead. Each team

    member is interacting with each other, so communication channels for each team are (6)(6-1)/2=15. Both

    the team leads are communicating with you so there are two communication channels for this interaction.

    Further since both the team leads are interacting with each other there is an another communication channel

    between them. Hence the total communication channels in your project is 15+15+2+1=33. Choice A is theonly correct answer to this question.