Date Item AM PM Total Total to Date Remarks 13.04.2 016 Beam Delivere d 0 0 0 176 No Beam Delivered 13.04.2 016 Beam Cast 0 0 0 372 No Beam Cast 13.04.2 016 Full Stressin g 0 1 1 364 1 Beam Full Stressed 13.04.2 016 Grouting 0 0 0 356 No Beam Grouted only preparation. 13.04.2 016 Initial Stressin g 2 0 2 355 2 Beams Initial Stressed 13.04.2 016 Ducting complete 0 1 1 405 1 Beam Duct Completed Date PS2-51/52 (20.010M) AM/PM Total to date Remarks 13.04.2016 Beams Cast 0 5 G1,G2,G3,G4,G5 Full Stressing 0 4 G1,G2,G3,G4 Grouting 0 3 G1,G2,G3 Day Shift Night Shift OT 9:00PM OT

Sample

  • Upload
    rolly

  • View
    212

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Sample

Date Item AM PM TotalTotal to

DateRemarks

13.04.2016Beam

Delivered0 0 0 176  No Beam Delivered

13.04.2016 Beam Cast 0 0 0 372 No Beam Cast

13.04.2016Full

Stressing0 1 1 364 1 Beam Full Stressed

13.04.2016 Grouting 0 0 0 356 No Beam Grouted only preparation.

13.04.2016Initial

Stressing2 0 2 355 2 Beams Initial Stressed

13.04.2016Ducting

complete 0 1 1 405 1 Beam Duct Completed

DatePS2-51/52 (20.010M)

AM/PM Total to date Remarks

13.04.2016

Beams Cast 0 5 G1,G2,G3,G4,G5

Full Stressing 0 4 G1,G2,G3,G4

Grouting 0 3 G1,G2,G3

Manpower FreyssinetDay Shift Night Shift

OT 9:00PM OT 10:00PM7:00AM 6:00PM 5:00PM 4:00AM

13.04.2016

PIC 1 - - -

Engineer 1 - - -

Supervisor 5 - - -

Safety officer 1 - - -

Warehouseman 1 - - -

Page 2: Sample

Duct Operator 1 - -

Mechanic 1 - - -

Foreman 2 - - -

Leadman 3 - - -

Labor in Warehouse 1 - - -

Labor in Duct Fabrication 2 - - -

Labor in Grouting and Preparation 9 - - -

Labor in Stressing 4 - - -

Labor in Threading and

Cutting4 - - -

Labor in Ducting Installation 7 - - -

Total Manpower 43 - - -