74
S&C ELECTRIC COMPANY Specialists in Electric Power Switching and Protection Instruction Sheet 1051-541 May 19, 2003 © 2003 New Release S&C M Series ® Switch Operators With Voltage and Current Sensing Option Reciprocating and Rotating Switch Operation Operating Instructions TABLE OF CONTENTS Section Page Section Page INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 SAFETY INFORMATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 OPERATIONS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 HARDWARE & SOFTWARE Comparing Rotating and Reciprocating Operators . . .6 Switch Operator Modules . . . . . . . . . . . . . . . . . . . . . . . . 6 Faceplate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 Faceplate LEDs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8 Faceplate Switches . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 Power Management System . . . . . . . . . . . . . . . . . . . . . 12 Battery Charger/Control I/O Board. . . . . . . . . . . . . . . . 12 Battery Management. . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 Battery Care and Maintenance . . . . . . . . . . . . . . . . . . . 15 Switch Operator Software . . . . . . . . . . . . . . . . . . . . . . . 15 IntelliLINK . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16 SCADA Communications Equipment . . . . . . . . . . . . . . 16 OVERVIEW OF M SERIES OPERATIONS . . . . . . . . . . . . . 17 SWITCH OPERATOR AUTOMATIC OPERATIONS . . . . . . 21 VIEWING OVERCURRENT FAULT INFORMATION . . . . . . 27 VIEWING DATA LOGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35 GENERATING REPORTS . . . . . . . . . . . . . . . . . . . . . . . . . . . 38 SAVING A SETUP CONFIGURATION . . . . . . . . . . . . . . . . . 39 VIEWING INTELLILINK WITHOUT DATA . . . . . . . . . . . . . . 41 USING SNAPSHOTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42 UPDATING CONTROL SOFTWARE . . . . . . . . . . . . . . . . . . . 44 SWITCH ACTUATOR MONITORING & CONTROL LOGIC Angular Position . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48 SWITCH OPERATIONS The Close Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50 The Open Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50 Test Open and Close Operations . . . . . . . . . . . . . . . . . . 51 Emergency Open and Close. . . . . . . . . . . . . . . . . . . . . . 51 Jog Open and Close . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51 Operating Problems and Error Conditions . . . . . . . . . 51 FAULT DETECTION AND AUTOMATIC OPERATION Voltage Sensing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55 Voltage Loss Detection . . . . . . . . . . . . . . . . . . . . . . . . . 55 Overcurrent Fault Detection Option . . . . . . . . . . . . . . 55 Fault Logging . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55 Automatic Operations . . . . . . . . . . . . . . . . . . . . . . . . . . 56 VIEWING OVERCURRENT FAULT INFORMATION . . . . . 61 ROUTINE DATA LOGGING INFORMATION Data Logging Menu . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65 Daily Highs and Lows Data. . . . . . . . . . . . . . . . . . . . . . 65 Data Logging Interval . . . . . . . . . . . . . . . . . . . . . . . . . . 66 GENERATING REPORTS . . . . . . . . . . . . . . . . . . . . . . . . . . . 68 SAVING A SETUP CONFIGURATION. . . . . . . . . . . . . . . . . 69 VIRTUAL MEMORY FILES . . . . . . . . . . . . . . . . . . . . . . . . . 70 UPDATING CONTROL SOFTWARE . . . . . . . . . . . . . . . . . . 71 RUNNING SETUP SOFTWARE FROM DOS Start Setup from DOS . . . . . . . . . . . . . . . . . . . . . . . . . . 73 Change DOS Startup Information . . . . . . . . . . . . . . . . 73

S&C M Series Switch Operators With Voltage and Current

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Instruction Sheet 1051-541S&C ELECTRIC COMPANY Specialists in Electric Power Switching and Protection
Instruction Sheet 1051-541 May 19, 2003 ©2003
New Release
S&C M Series® Switch Operators With Voltage and Current Sensing Option Reciprocating and Rotating Switch Operation
Operating Instructions
INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .2
OPERATIONS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5
HARDWARE & SOFTWARE Comparing Rotating and Reciprocating Operators . . .6 Switch Operator Modules . . . . . . . . . . . . . . . . . . . . . . . .6 Faceplate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7 Faceplate LEDs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .8 Faceplate Switches . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11 Power Management System . . . . . . . . . . . . . . . . . . . . .12 Battery Charger/Control I/O Board. . . . . . . . . . . . . . . .12 Battery Management. . . . . . . . . . . . . . . . . . . . . . . . . . . .13 Battery Care and Maintenance . . . . . . . . . . . . . . . . . . .15 Switch Operator Software . . . . . . . . . . . . . . . . . . . . . . .15 IntelliLINK . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .16 SCADA Communications Equipment. . . . . . . . . . . . . .16
OVERVIEW OF M SERIES OPERATIONS . . . . . . . . . . . . .17
SWITCH OPERATOR AUTOMATIC OPERATIONS . . . . . .21
VIEWING OVERCURRENT FAULT INFORMATION . . . . . .27
VIEWING DATA LOGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . .35
USING SNAPSHOTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .42
SWITCH ACTUATOR MONITORING & CONTROL LOGIC Angular Position . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .48
SWITCH OPERATIONS The Close Operation. . . . . . . . . . . . . . . . . . . . . . . . . . . .50 The Open Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . .50 Test Open and Close Operations. . . . . . . . . . . . . . . . . .51 Emergency Open and Close. . . . . . . . . . . . . . . . . . . . . .51 Jog Open and Close . . . . . . . . . . . . . . . . . . . . . . . . . . . .51 Operating Problems and Error Conditions . . . . . . . . .51
FAULT DETECTION AND AUTOMATIC OPERATION Voltage Sensing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55 Voltage Loss Detection . . . . . . . . . . . . . . . . . . . . . . . . . 55 Overcurrent Fault Detection Option . . . . . . . . . . . . . . 55 Fault Logging . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55 Automatic Operations . . . . . . . . . . . . . . . . . . . . . . . . . . 56
VIEWING OVERCURRENT FAULT INFORMATION . . . . . 61
ROUTINE DATA LOGGING INFORMATION Data Logging Menu . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65 Daily Highs and Lows Data. . . . . . . . . . . . . . . . . . . . . . 65 Data Logging Interval . . . . . . . . . . . . . . . . . . . . . . . . . . 66
GENERATING REPORTS . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
VIRTUAL MEMORY FILES . . . . . . . . . . . . . . . . . . . . . . . . . 70
UPDATING CONTROL SOFTWARE . . . . . . . . . . . . . . . . . . 71
RUNNING SETUP SOFTWARE FROM DOS Start Setup from DOS. . . . . . . . . . . . . . . . . . . . . . . . . . 73 Change DOS Startup Information . . . . . . . . . . . . . . . . 73
1051-541 2
INTRODUCTION
WARNING The equipment covered by this publication must be operated and maintained by qual- ified persons who understand any hazards involved and are thoroughly trained in the operation and maintenance of electronic control devices which are used in conjunc- tion with power distribution equipment. These instructions are intended only for such qualified persons. They are not intended to be a substitute for adequate training and experience in safety procedures for this type of equipment.
Qualified Persons
Thoroughly and carefully read this instruction sheet before programming, operating, or maintaining your S&C M Series Switch Operator. Familiarize yourself with “SAFETY INFORMATION” on pages 3 and 4.
Retain this Instruction Sheet
This instruction sheet is a permanent part of your S&C M Series Switch Operator. Designate a location where you can easily retrieve and refer to this publication.
Warranty The standard warranty contained in S&C’s standard conditions of sale, as set forth in Price Sheet 150, is applicable to the S&C M Series Switch Operator.
3 1051-541
Understanding Safety-Alert Messages
There are several types of safety-alert messages which may appear throughout this instruction sheet as well as on labels attached to the M Series Switch Operator. Famil- iarize yourself with these types of messages and the importance of the various signal words, as explained below.
Following Safety Instructions
If you do not understand any portion of this instruction sheet and need assistance, con- tact your nearest S&C Sales Office or call S&C Headquarters at (773) 338-1000, Monday through Friday between 8:30 AM and 5:00 PM Central Standard Time. (In Canada, call S&C Electric Canada Ltd. at (416) 249-9171.)
Replacement Instructions and Labels
If you need additional copies of this instruction sheet, contact your nearest S&C Sales Office, S&C Headquarters, or S&C Electric Canada Ltd.
It is important that any missing, damaged, or faded labels on the equipment be replaced immediately. Replacement labels are available by contacting your nearest S&C Sales Office, S&C Headquarters, or S&C Electric Canada Ltd.
DANGER “DANGER” identifies the most serious and immediate hazards which will likely re- sult in serious personal injury or death if instructions, including recommended pre- cautions, are not followed.
WARNING “WARNING” identifies hazards or unsafe practices which can result in serious per- sonal injury or death if instructions, including recommended precautions, are not fol- lowed.
CAUTION “CAUTION” identifies hazards or unsafe practices which can result in minor personal injury or product or property damage if instructions, including recommended precau- tions, are not followed.
NOTICE “NOTICE” identifies important procedures or requirements that, if not followed, can result in product or property damage if instructions are not followed.
NOTICE
SAFETY INFORMATION
Thoroughly and carefully read this in- struction sheet before programming and operating your M Series Switch Op- erator.
1051-541 4
5 1051-541
OPERATIONS
This chapter contains technical information about the Switch Operator hardware and software, and how to use IntelliLINK® to carry out various routine operations. The information in this chapter is specific to the S&C M Series® Switch Operator.
WARNING These instructions do NOT replace the need for utility operation standards. Any con- flict between the information in this document and utility practices should be re- viewed by appropriate utility personnel and a decision made as to the correct procedures to follow.
Serious risk of personal injury or death may result from contact with electric distri- bution equipment when electrical isolation and grounding procedures are not fol- lowed. The equipment described in this document must be operated and maintained by qualified persons who are thoroughly trained and understand any hazards that may be involved. This document is written only for such qualified persons and is not a substitute for adequate training and experience in safety procedures for accessing high voltage equipment.
This Switch Operator is connected to switchgear operating at primary voltage levels. High voltage may be present in the wiring to the Switch Operator or the Switch Op- erator itself during certain failures of the switchgear wiring or grounding system, or due to a failure of the switch itself. For this reason, access to the Switch Operator should be treated with the same safety precautions that would be applied when ac- cessing other high voltage lines and equipment. Follow all locally-approved safety procedures when working on or around this Switch Operator.
WARNING Before attempting to access an existing switch installation, check carefully for visible or audible signs of electrical or physical malfunction (do this before touching or op- erating the Switch Operator or any other part of the installation). These warning signs include such things as smoke, fire, open fuses, crackling noises, loud buzzing, etc. If a malfunction is suspected, treat all parts of the installation, including the Switch Op- erator and associated hardware, as if they were elevated to primary (high) voltage.
CAUTION Removing the handle does not provide 100% assurance that the output actuator will not operate during a control failure. As with all control equipment, the only safe way to disable operation of the device is to disconnect the main power. This is done by opening the Switch Operator’s DC circuit breaker and removing the AC fuse.
1051-541 6
Comparing Rotating and Reciprocating Operators
The rotating and reciprocating switch operators are very similar in their function. The rotating operator produces a rotational movement to operate the switch through a rotating shaft that is located at the top of the Switch Operator. The reciprocating opera- tor converts rotational movement of the crank arm at the rear of the Switch Operator to a linear up/down motion of the operating rod to operate the switch. However, the rotating and reciprocating operators use the same software, actuator monitoring, and control logic. For this reason, the operations information given here is equally valid for both types of switch operator. For the purposes of this chapter, the only significant dif- ference between the rotating and reciprocating switch operators involves the different methods that are used to mechanically decouple the switch operator from the switch, as described in Coupling/Decoupling the Switch and Testing the Travel Limits (see Installation Chapter).
Figure 1 Interior of M Series Switch Operator Electronics Modules
(Rotating Unit Shown)
This section describes various Switch Operator components. The following section, The Switch Operator Modules, explains how these components work together to moni- tor the distribution feeder and manage switch operation.
Switch Operator Modules
The Switch Operator electronics modules are described below and shown in Figure 1.
Faceplate Circuit board
This printed circuit board is attached to the back of the faceplate. The board includes the microprocessor-based control computer and all of the faceplate LEDs and toggle switches.
HARDWARE & SOFTWARE
7 1051-541
Battery Charger/Control I/O (BC/CIO) board
This printed circuit board is attached to the inside of the control enclosure. The board contains all of the circuitry to manage the battery system (charging, battery test, power management, etc.). It also contains all of the sensor conditioning and pilot relays to control the Switch Operator drive train, and supplies/conditions power for the optional radio (for more information, see Power Management System later in this chapter).
Universal Communications Mounting Plate
This is a “standard-sized” mounting plate on which all of the various communication radios, modems and related equipment can be mounted. If the M Series Switch Opera- tor is outfitted with the optional, radio faulted circuit indicators (RFCI’s), the radio receiver for this system is installed on this mounting plate.
Drive Train Assembly
This assembly consists of the worm gear drive, miter gearbox (rotating unit only), motor, and magnetic digital shaft encoder.
Motor Control Assembly
This assembly contains all of the control components, including motor contactors, bat- tery test loads, relays, and other miscellaneous electromechanical control components.
Faceplate The M Series faceplate (Figure 2) includes LEDs and switches which allow you to monitor and control the Switch Operator.
Figure 2 M Series Faceplate
1051-541 8
Overcurrent Fault LED
This LED comes ON when a fault has been detected on any phase. This LED is always present but will only turn on if the Switch Operator is outfitted with the optional, radio faulted circuit indicators. Several types of fault indicators are available, each with its own characteristics. Please refer to the applicable vendor documentation for informa- tion on the fault indicators supplied.
Remote Communication RCV/XMT LEDs
These LEDs blink when the Switch Operator sends or receives signals through remote- communications equipment installed in the Switch Operator enclosure.
RCV LED – Blinks when the Switch Operator detects an incoming character.
XMT LED – Blinks when the Switch Operator sends one or more characters.
NOTICE To extend battery carryover time, power to the faceplate (including the LEDs is turned off by the Switch Operator when the cabinet door is closed.
NOTICE You will see activity on both of these LEDs only if remote-communications equip- ment is installed, properly connected, and receiving power. The XMT LED blinks any time a transmit is attempted, whether or not communications equipment is properly installed. (This optional equipment is usually a modem board or radio installed on the Universal Communications Mounting Plate on the back of the Switch Operator face- plate.)
9 1051-541
Error Detected LED
This LED comes ON when a severe problem has been detected. If this LED is ON, no switching or jogging operations can be performed. There are three major categories of problems (see Table 1):
Table 1 Problem Categories for the ERROR DETECTED LED
To resolve the problem, first look for obvious problems with the switch and Switch Operator installation. If you cannot find anything observable, check the BATTERY
LOW LED. If it is ON, the combination of both LEDs being ON probably means that the battery is too low to operate the switch. Once this is corrected and the BATTERY
LOW LED goes OFF, the ERROR DETECTED LED should also turn OFF.
Otherwise, you will need to use a PC or the SCADA master station to identify and resolve the problem. Refer to Chapter 5: Troubleshooting for a detailed list of the “error” indications.
Processor Status LED
This LED blinks once per second when the Switch Operator has power and the Control software is running normally.
Battery Low LED
This LED is ON when the battery is low or bad. If the ERROR DETECTED LED is OFF, then the battery is low but not bad. When the battery is low, the Switch Operator can be operated and the LED is simply a warning that the battery is approaching a dis-
Problem Category
The battery is below the ”Battery Bad” operational threshold.
Charging or replacing the batteries, then run a battery test from the faceplate or via SCADA.
Control Logic Failure
Internal control logic problems or unexpected behavior of the drive train assembly occurred during a switching operation.
Setting the “Clear Errors” field to “Clear” in the Troubleshooting: Event Status window.
Sensor Failure A critical sensor required for operation is reading out of range.
Repairing the sensor electronics.
1051-541 10
charged condition. It is normal for this LED to be ON when the Switch Operator is operating on battery power and the normal battery carryover period is nearly over.
If this LED comes ON when AC is present and there is no other reason to expect the battery to be low, the battery may be defective. Run a battery test from the faceplate or via SCADA.
If the ERROR DETECTED and BATTERY LOW LEDs are ON and AC power is present, either the battery is defective or there is a problem with the Power Manage- ment System. View the Troubleshooting: Event Status window or the SCADA points to determine the problem. (See Power Management System below and in Chapter 5:
Troubleshooting for additional details.)
The LED blinks during any battery test. The Switch Operator automatically runs the battery test at scheduled intervals. In addition, you can use a SCADA command or the faceplate BATTERY TEST/LAMP TEST switch to start a battery test at any time (see Battery Test/Lamp Test switch later in this chapter for more details).
Closed and Open LEDs
These LEDs come ON when the drive train is in a position meeting the open or closed criteria. Unless human intervention or physical damage has occurred with the switch and/or mechanical control mechanism (uncoupled, manual operation) since the last switching operation, the state of these LEDs should be an accurate reflection of the state of the distribution switch. See Switch Operations later in this chapter for details. The LEDs blink when the open and closed limits of travel have not been set, or after an error condition that has invalidated the previous settings.
Not Ready LED
This LED is ON continuously when any problem preventing normal, high-speed opera- tion of the Switch Operator is present (for more about the causes of “Not Ready” condi- tions, see Switch Operations below and Chapter 5: Troubleshooting).
The LED blinks when the Switch Operator is in “Align” mode, which allows slow-speed, “jogging” operation of the output shaft/control rod (see Align/Couple switch below).
Trip LED
This yellow LED comes ON when the Switch Operator trips open the switch using auto- matic logic (for example, sectionalizing). It turns OFF when the switch is closed.
Automatic Operation Enabled LED
This LED is ON when automatic operation of the Switch Operator is enabled.
NOTICE After replacing a defective battery, be sure to run a battery test immediately to update the battery status.
CAUTION If automatic operation is enabled, the automatic-control logic may trip the switch re- gardless of the state of the REMOTE/LOCAL switch.
11 1051-541
Automatic Operation Disabled LED
This LED is ON when automatic operation of the Switch Operator is disabled.
Local LED
This LED is ON when remote (SCADA) operation of the Switch Operator is blocked and local operation is allowed. The LED is OFF when local operation is blocked and remote operation is allowed.
Faceplate Switches
Battery Test/Lamp Test switch
Toggle this switch UP to start a battery test. The test lasts approximately 30 seconds. The BATTERY LOW LED blinks during the test. (See Power Management System later in this chapter for more details.)
Hold this switch DOWN to test the LEDs on the faceplate (all LEDs should blink).
Close/Open switch
Toggle this switch UP to request a “Close” operation. Toggle this switch DOWN to request an “Open” operation.
Enable/Disable switch
Toggle this switch UP to enable automatic switch operation. Toggle this switch DOWN to disable automatic operation. If all automatic operation features are disabled (on the Setup: Automatic Operation window), toggling the ENABLE/DISABLE switch will cause the ENABLED or DISABLED LED to blink, but will have no effect once the switch is released.
If the “Inspection Required” condition is present (see Switch Operations below), tog- gling this switch UP or DOWN clears the condition.
Remote/Local switch
Toggle this switch UP to enable remote (SCADA) control of the Switch Operator and disable commands from the faceplate CLOSE/OPEN switches and automatic opera- tion ENABLE/DISABLE switch.
Toggle this switch DOWN to disable remote (SCADA) operation of the switch operator
NOTICE If the REMOTE/LOCAL switch is in the REMOTE position, toggling the CLOSE/OPEN switch has no effect.
NOTICE If the REMOTE/LOCAL switch is in the REMOTE position, or if automatic operation is disabled (on the Setup: Automatic Operation window), toggling this switch has no effect.
1051-541 12
and enable commands from the faceplate CLOSE/OPEN switches and automatic oper- ation ENABLE/DISABLE switch (the LOCAL LED is ON when this switch is set to LOCAL).
Power Management System
The Power Management System consists of the Battery Charger/Control I/O board (see below), off-board relays and sensing components, Control software, and two Johnson Controls UPS 12-140 12 VDC batteries. When AC power is available, the system con- verts the AC power to DC, then uses the DC power to run the Switch Operator, charge the battery, and operate the communications equipment. It draws on the battery only for the current needed to operate the drive train. When external AC power is not avail- able, the system draws on the stored battery power for all Switch Operator functions.
You can monitor and control the Power Management System from the Switch Operator faceplate, with IntelliLINK, or from a SCADA master station.
Battery Charger/Control I/O Board
The Battery Charger/Control I/O (BC/CIO) board is highly efficient, computer-control- lable, uninterruptible power supply specifically designed to meet the specialized power requirements of the Switch Operator.
The BC/CIO board provides steady-state current flow for Switch Operator operation, pulsed current flow for communications equipment, and occasional large current surges for operation of the drive train. It also supplies 12-volt, 24-volt, and other DC voltages from a single 24-volt source (this design provides superior battery lifetime and carryover compared to systems which “center tap” a 24 VDC system to supply their 12 VDC requirements, or which use multiple, non-interchangeable batteries).
The BC/CIO board supplies accurate, temperature-compensated charging voltages, with current limiting and other safety mechanisms to maximize battery carryover and to minimize the possibility of battery off-gassing or explosion. This system meets or exceeds ANSI surge withstand and dielectric specifications.
Battery Charger/Control I/O Board LEDs
The BC/CIO board LEDs provide information about the state of the battery and AC power. They are located on the right side of the board (towards the back of the enclo- sure).
AC On
This LED comes ON when the Switch Operator is connected to an external AC power source, the AC LINE fuse is in the fuse holder, and AC power is being delivered to the BC/CIO board.
CHG ON
This LED comes ON when the Battery Charger is connected to the battery, and the Bat- tery Charger and battery are within the 20-30.5 volt range.
BAT ON
This LED comes ON when the battery is connected to the 24-volt DC power supply bus.
NOTICE To disable local automatic operation and have full control of the switch, you must also toggle the faceplate ENABLE/DISABLE switch to DISABLE.
13 1051-541
Battery Management
The Switch Operator continuously monitors the battery voltage. In addition, it tests the battery at regular, scheduled intervals. The interval depends on the power conditions:
• During battery discharge, the test is run hourly.
• After a power outage, the test is run every two hours for 24 hours to monitor the bat- tery status while the battery is recharged.
• After 24 hours of continuous operation on AC power, the test is run once a day.
• If a switch operation is requested and the battery test has not run within the last four hours, an abbreviated battery test is run prior to starting the switch operation.
During the battery test sequence, the Switch Operator applies a large test load to the battery system for a brief duration, monitoring both battery voltage and current draw. This is used to determine how the Switch Operator will perform during both normal and abnormal operations. The Troubleshooting: Battery System window displays the following points:
Power Supply Voltage
This shows the actual voltage presently being supplied to the 24-volt power system. If AC power is present, this voltage is supplied from the Battery Charger. If AC power is absent, this is the actual battery voltage. During battery testing, this voltage varies as the Switch Operator applies test loads to the battery system.
Battery Impedance
The Switch Operator calculates this value during battery testing. This is a measure of battery health. A fully-charged battery in good condition typically has an impedance of 0.020-0.030 ohms.
Number of Hours Until Battery Low Warning
The Switch Operator calculates an estimate of the number of hours remaining until the battery will reach the “Battery Low” warning level. This estimate is based on the results of both the battery test and the ambient temperature. The estimate assumes a nominal communication load of 90 ma at 12 VDC.
Internally, the Switch Operator calculates additional battery characteristics, including:
NOTICE You can use the BATTERY TEST/LAMP TEST switch or a SCADA command to man- ually test the battery at any time.
NOTICE As the temperature decreases, the number of hours of battery backup also decreases. Due to the dramatic effect of temperature on available battery power, the calculated number of hours may not vary by 1 count per hour. For example, if the “Number of Hours Until Battery Low Warning” is “96” and the Switch Operator is moved to a much colder location, the value might be “93” an hour later.
1051-541 14
Calculated Voltage Under Load
In order to insure adequate motor speed and torque during switch operation, the Switch Operator calculates the battery voltage based on normal loading conditions during switch operation.
Locked Rotor Torque
Based on the battery voltage, calculated battery impedance, and the impedance of the other electromechanical components, the Switch Operator calculates the amount of torque that can be delivered by the drive train under locked rotor conditions.
Based on the results of the above monitoring and tests, the Switch Operator may take the following actions:
• If any of the above monitored conditions approaches levels associated with the min- imum operational criteria, the BATTERY LOW LED turns ON, and a comparable warning is issued to the SCADA operator.
• If any of the above monitored conditions reaches the minimum operational criteria, the BATTERY LOW LED remains ON, a separate “Battery Bad” indication is issued to the SCADA operator, and operation of the motor is blocked.
• When the battery voltage falls below the minimum operational threshold of 23.90 VDC, the Switch Operator shuts down until AC is restored (or the BAT ON switch is pressed on the BC/CIO board).
• If the battery voltage falls outside the range of 20-30.5 volts DC while the Switch
Operator is operating on AC power, the Switch Operator hardware disconnects the battery from the charging system and issues an alarm. A separate battery charge fail- ure indication is issued to the SCADA Operator.
BAT ON Switch
In the middle of the BC/CIO board is a small, white, push-button switch labeled BAT
ON. When operating on battery power only, the Switch Operator energizes an output that is de-energized when the battery reaches the end of its discharge cycle. This causes the Switch Operator to be disconnected and shut down. The shut down happens after a one-minute delay. If it becomes necessary to reload the Control software when AC is not present, you can press the BAT ON switch to prevent the automatic discon- nect from interfering with the reload.
Battery Care and Maintenance
Store batteries at room temperature
To maximize battery lifetime, store all gel-cell batteries at or below room temperature. Once in service, the battery will probably be exposed to higher temperatures that will impact its lifetime. However, proper storage can avoid accelerating the process.
NOTICE You must continue to press the switch more than once per minute until the reload is complete.
15 1051-541
Keep stored batteries charged
Gel-cell batteries are designed with a 6 month maximum shelf life. This means that they can survive sitting on the shelf without being recharged and without incurring substan- tial degradation for 6 months. If you need to store them longer, it is critical to recharge them periodically. If you recharge them every month, they can sit on the shelf for years without significant degradation. To recharge a battery, connect it to your Switch Opera- tor or to an independent battery charger (such as S&C’s BC-8-24).
The best approach to storing batteries is to maintain the smallest inventory possible. Make sure that you have a procedure in place for rotating the inventory, removing the oldest batteries first.
Use batteries you know are good
Do not install used batteries in battery-backed equipment unless they have been prop- erly tested. The cost of a service call to replace a bad battery is usually higher than the cost of a new battery. Although a battery might be good enough to provide temporary standby power, the switch has a brief but large power requirement that may exceed a weak battery’s ability to deliver charge rapidly.
Avoid installing the enclosure in a sunny location
If at all possible, install the Switch Operator enclosure in a shady area. Since batteries do not do as well in warm/hot environments, do everything possible to minimize the peak operating temperature.
Switch Operator Software
M Series Switch Operators are entirely software-controlled. Each Switch Operator includes Control software (which is preloaded into the Switch Operator in the factory) and IntelliLINK (which is supplied with the Switch Operator and runs on IBM®/PC- compatible computers).
The Control Software
The Control software manages the minute-by-minute functioning of the Switch Opera- tor. This software continually monitors:
• single-phase voltage on the feeder
• incoming SCADA commands
• the condition of the battery
• ambient air temperature inside the Switch Operator enclosure
• external air temperature
• the software setpoint values
• fault and voltage loss information already stored in the Switch Operator
• various other setpoints and data values as needed
Based on this information, the Control software decides how to respond to overcurrent faults, a change in voltage, a command from the faceplate or SCADA master station, and other conditions.
The Control software, the setpoint values, and historical data are all stored in non-vola- tile Switch Operator memory. This memory survives power interruptions, including
1051-541 16
complete failure of the battery system. The memory chip has a minimum 10-year shelf life (without power).
IntelliLINK IntelliLINK (Setup software) allows you to communicate with the Control software while you are at the Switch Operator site. Using IntelliLINK, you can:
• Enter installation-dependent operating parameters (setpoints), such as a network address, automatic operation features, etc.
• Monitor real-time data, such as the present line voltage.
• Examine the performance and operating history of an installed Switch Operator.
• Transfer all configuration, operating, and historical data from the Switch Operator to a “report” file on your PC.
• Download new Control software into the Switch Operator.
• Troubleshoot assorted types of Switch Operator installation problems.
SCADA Communications Equipment
M Series Switch Operators include two remote communication access ports. When combined with suitable communications equipment and protocols, this permits you to remotely monitor, control, and reconfigure the Switch Operator installation.
S&C can provide the M Series Switch Operator with a variety of communications soft- ware protocols and hardware options, including:
• DNP 3.0
• UtiliNet® Radios
• MDS Radios
• Modems
Most types of communications equipment can be mounted inside the Switch Operator enclosure (on the Universal Communications Mounting Plate on the back of the face- plate). This eliminates pole clutter and provides a higher level of reliability for the over- all installation.
For more details, see the appropriate communications information, or contact S&C.
17 1051-541
This section explains how the switch control components work together to detect and respond to “faults” and voltage outages.
Signal Processing For current measurements, full scale is 4,096 amps RMS.
The switch control reports current, voltage, and phase-related data in units of amperes, volts, and kVARs. The rated accuracy of these measurements is based on the combined
accuracy of all the control components (exclusive of the sensor and sensor cable, but inclusive of all sensor conditioning components). The switch control uses the switch calibration data and the phase angle offset values to correct all AC waveform data sam- pled from the switch sensors.
RMS AC Wave- form Analysis
The switch control uses digital signal processing techniques to calculate true RMS values of current and voltage.
Because there is some response latency associated with this circuitry, voltage and cur- rent changes that occur within a few tenths of a second are sensed as a single, steady value.
For real-time, steady state monitoring and data logging, the switch control collects data at 0.2 second intervals. It then averages 8 samples and reports the “1.6 second-aver- aged” value. This results in a net response time of 1.6 seconds.
The switch control uses these “1.6 second averaged” values for the real-time display, reporting via SCADA communication, and data logging. Daily high and low values are kept for the current day and the preceding 7 days.
Phase Angle Measurements
The switch control uses digital signal processing techniques to measure the phase angles between the voltage and current waveforms on each phase.
The switch control samples the phase angle reading every 0.2 seconds, then averages 8 samples and reports the “1.6 second-averaged” value. Phase angle measurements are on a 0-360 degree range.
As part of the switch control setup, you can enter “Phase Angle Offset” values to com- pensate for both sensor-dependent and installation-dependent phase angle characteris- tics.
Overcurrent Fault & Voltage Loss Detection
To determine if an overcurrent fault exists, the switch control compares the sensed current to setpoint values for current level and fault duration. The “Current Level” set- point value can be specified in 10 amp RMS increments for phase faults and 1 amp RMS increments for ground faults.
The “Fault Duration Time Threshold” can be specified in 6.25 millisecond (approxi- mately 1/3 cycle) increments for phase faults and 50 millisecond increments for ground faults.
Phase Over- current Detection
Digital signal processing is used to extract the fundamental component of current for fault detection purposes. The switch control provides fault detection with a resolution of 1/3 cycle and peak values of approximately 4000 amps RMS. Overcurrent measure- ments are accurate to 0.5% of full scale excluding sensors. (For information about scal- ing beyond 4000 amps, contact S&C.)
To detect phase overcurrent faults:
• The switch control monitors the current on all 3 phases and compares it to the “Phase Fault Detection Current Level” setpoint.
OVERVIEW OF M SERIES OPERATIONS
1051-541 18
• When at least one peak overcurrent sample is above the setpoint every 18.75 millisec- onds (a window of time slightly longer than one cycle), the switch control registers an overcurrent condition (a potential, or pending, “fault”) on that phase.
• Once the overcurrent condition is registered, the switch control starts the “Phase Fault Duration Time Threshold” timer.
• If the overcurrent condition is present continuously for the duration of the timer, the switch control labels it a “phase overcurrent fault” and responds accordingly.
If, during any 18.75 millisecond window, overcurrent is not detected, the switch control considers the “fault” (or the overcurrent condition) to be no longer present and takes appropriate action.
• When a recognized “phase overcurrent fault” ends (after the timer has expired), the software records the maximum RMS current measured during the fault and the fault duration. Any fault lasting longer than 6.82 minutes is recorded as 6.82 minutes (409.6 seconds).
Ground Over- current Detection
The switch control hardware measures ground current as a vector sum of the three phase current fundamental components.
The Control software samples the true RMS detection hardware on 50 millisecond intervals. On each interval, the current is compared to the “Ground Fault Detection Current Level” setpoint. If the current exceeds the setpoint, and this condition persists continuously for a period of time specified by the “Ground Fault Duration Time Thresh- old” setpoint, an overcurrent fault condition is indicated and appropriate action taken.
Voltage Loss Detection
The switch control checks the voltage on all three phases at 50 millisecond intervals. Any voltage drop below the “Loss of Voltage Threshold” setpoint is considered a volt- age outage.
Inrush Restraint The Inrush Restraint feature prevents phase or ground overcurrent conditions which can occur during outage restoration (hot or cold load pickup) from falsely indicating a “fault.” It also applies when the switch is closed from the faceplate or via SCADA while power is present. The “Current Inrush Restraint Multiplier” feature enables the switch operator to differentiate between moderate overcurrents (caused by cold load pickup) and large overcurrents (caused by a fault condition) during the Inrush Restraint period.
Inrush Restraint is applied as follows:
• During a voltage outage, the switch control continuously monitors the switch status, the RMS voltage sensors, and the phase overcurrent detectors for any indication that the outage has ended.
• When voltage rises above the “Loss of Voltage Threshold” setpoint on any phase, or overcurrent is detected on any phase, the switch control checks the switch position.
• If the switch is closed, the switch control starts the “Phase Current Inrush Restraint” timer and the “Ground Current Inrush Restraint” timer.
19 1051-541
• If both “Current Inrush Restraint Multiplier” values are set to “Time Block,” the switch control ignores all overcurrent conditions until the “Inrush Restraint” timers expire.
If one or both “Current Inrush Restraint Multiplier” values are set to something other than “Time Block,” the switch control considers any overcurrent condition that exceeds the specified multiplier value to be a “fault” (see Phase Overcurrent Detection
on page 19 and Ground Overcurrent Detection on page 20 for details).
• After the inrush restraint timers expire, the switch control responds to overcurrent conditions in the normal manner (see Phase Overcurrent Detection on page 19 and Ground Overcurrent Detection on page 20 for details).
Switch Control Response To Overcurrent and Voltage Loss Events
The switch control’s response to an overcurrent condition or voltage loss depends on the settings in effect when the event occurs. For example, the values you select for the “Fault Detection Current Level” and “Fault Duration Time Threshold” setpoints deter- mine whether the switch control recognizes an overcurrent event as a “fault.” The “Automatic Operation” features that you enable, and the position of the faceplate auto- matic operation ENABLE/DISABLE switch, determine what the switch control will do when a recognized “fault” occurs.
Overcurrent Data Logging
The switch control keeps a record of each recognized event, the assumed cause of the event, and any action taken. The switch control logs all events, regardless of the posi- tion of the automatic operation ENABLE/DISABLE switch and REMOTE/LOCAL
switch.
The switch control maintains three separate, chronological logs of event data. Informa- tion is stored in these logs in a circular fashion; the newest entry always overwrites the oldest. (The switch control logs each event with millisecond timestamping, and 6.25 millisecond resolution.)
The first log is a “sequence of events” buffer. Each record in this log represents one fault event (for example, an overcurrent condition followed by voltage loss) and/or a fault-related action taken by the switch control (for example, the line switch opened because of a phase imbalance condition). The information in this log is displayed on the IntelliLINK OVERCURRENT FAULT: Fault Events window and the LCD.
The second log contains the magnitude and duration information for each “fault.” The recorded magnitude is the maximum RMS current amplitude encountered during the “fault.” The duration is recorded in units of milliseconds, with 6.25 millisecond resolu- tion and a maximum recordable fault duration of 409 seconds (6 minutes, 49 seconds). The information in this log is displayed on the IntelliLINK OVERCURRENT FAULT:
Fault Magnitudes window and the LCD.
NOTICE If the “Inrush Restraint” times are set to “0”, no inrush restraint occurs.
1051-541 20
NOTICE Due to the delayed rise and fall times of the hardware, the logged time for detection of ground overcurrent faults may be delayed relative to the logged time for phase overcurrent faults caused by the same event. In addition, the accuracy of recorded duration times for ground overcurrent events is affected by the 50 millisecond sam- pling interval and hardware rise and fall times. Peak magnitude data of ground over- current is also affected by the amount of time that the event is present. Accurate magnitude recording requires the condition to be present for approximately 400 mil- liseconds. (See the 1051-530 Software Setup for additional details.)
21 1051-541
The M Series switch operator can carry out several automatic operations: sectionaliz- ing, phase imbalance protection, phase imbalance protection with automatic reclose, and one- or two-shot-lockout of a faulted circuit. These are explained below.
Line Sectionalizing
The switch control can sectionalize a distribution circuit based on detected fault cur- rent and voltage fluctuations associated with source-side recloser operation.
When Sectionalizing is enabled, the switch control uses the following logic to deter- mine when to trip open the switch:
• The switch control continuously monitors all sensed voltage phases and compares the voltage to the “Loss of Voltage Threshold” setpoint value.
• If the voltage drops below the setpoint on all sensed phases, the switch control starts the “Sectionalizer Reset and Extended Voltage Loss Time” timer. In addition, the con- trol sets an internal counter of recloser operations to “1.”
If a phase or ground overcurrent fault was present within 0.6 seconds prior to the detected loss of voltage, the control assumes the voltage loss was caused by a source- side breaker or recloser opening in response to a load-side overcurrent fault.
If an overcurrent fault was not detected prior to the loss of voltage, the control assumes the voltage loss was caused by a source-side breaker or recloser opening in response to a source-side overcurrent fault.
• The switch control continues to monitor the voltage levels. The control adds one count to the counter for each time the source-side device opens.
• If the “Successful Reclose Reset Time” is greater than zero, then the “reset on success- ful reclose” logic is also active. If voltage returns on all sensed phases (above the loss of voltage threshold) and current is below the fault detection threshold, and this condi- tion persists without interruption for longer than the “Successful Reclose Reset Time,” the sectionalizing counts and memory timer are reset, and sectionalizing is canceled.
• If the “Sectionalizer Reset and Extended Voltage Loss Time” timer expires before the counter reaches the appropriate “Recloser Counts to Trip” value, the switch control resets the counter to zero. Later voltage losses are considered part of a different reclose sequence. However, if 3-phase voltage is not present when the timer expires, an “extended voltage loss” condition exists and the switch control opens the switch.
If the counter reaches the setpoint value before the timer expires, and the problem was a load-side fault, the control trips open the switch.
NOTICE For any of the automatic operation features to work correctly, you must enter an ap- propriate value for the “Loss of Voltage Threshold” setpoint (see the SETUP: Site- Re-
lated window explanation in 1051-530 Software Setup for more details).
SWITCH OPERATOR AUTOMATIC OPERATIONS
1051-541 22
If the counter reaches the setpoint value before the timer expires, and the problem was a source-side fault, the control notes the events but does not trip open the switch.
To Enable Sectionalizing:
1 In the “Features Enabled” field on the SETUP: Automatic Operation window, select a combination that includes “Sectionalizing.”
2 If desired, at the SETUP: Automatic Operation window, set the “Successful Reclose Reset Time” to coordinate with the reclosers.
3 Use either the faceplate automatic operation ENABLE/DISABLE switch or a SCADA command to enable automatic operation of the switch control.
Phase Loss Protection
If the Phase Loss Protection feature is enabled, the switch control trips open the switch in response to a persistent phase imbalance condition – in order to prevent damage to customer equipment.
When Phase Loss Protection is enabled, the switch control uses the following logic to determine when to trip open the switch:
• When the switch control detects a loss of voltage on one or two phases, it starts the “Phase Loss Protection Time Threshold” timer.
• If the voltage loss persists, and true RMS current remains below the “Phase Loss Pro- tection Current Threshold” setpoint until the timer expires, the switch control trips open the switch.
• If voltage returns before the timer expires, the switch control terminates the timing operation.
• If voltage returns on one phase before the timer expires, but is then lost on another phase, the switch control restarts the timer.
NOTICE When the “Fault Current Required Before First/All Voltage Loss(es)” is set to “All”, the operator will not trip open unless all voltage losses were preceded by fault cur- rent. However, it may still operate based on the “Recloser Counts to Trip, Voltage Loss Only” setpoint. (See 1051-530.)
23 1051-541
To Enable Phase Loss Protection:
1 In the “Features Enabled” field on the SETUP: Automatic Operation window, select a combination that includes “Phase Loss Protection.”
2 At the SETUP: Automatic Operation window, enter values for the “Phase Loss Protec- tion Time Threshold” and the “Phase Loss Protection Current Threshold.” You can also enter a “Phase Loss Protection Voltage Threshold”; otherwise, the switch control uses the “Loss of Voltage Threshold” on the SETUP: Site-Related window. (See the SETUP:
Automatic Operation window explanation in the Setup chapter for details.)
3 Use either the faceplate automatic operation ENABLE/DISABLE switch or a SCADA command to enable automatic operation of the switch control.
Phase Loss Protection with Automatic Reclose
When the Automatic Reclose feature is enabled, and the switch is tripped open because of a phase imbalance, the switch control recloses the switch once voltage is again present on all three phases. (If Phase Loss Protection is enabled, but Automatic Reclose is not, an operator must use the faceplate switch or a SCADA command to manually close the tripped switch.)
When Automatic Reclose is enabled, the switch control uses the following logic to determine when to reclose the switch:
• The switch control monitors the line for the return of all voltage phases.
• As soon as the switch control senses that voltage is present on all three phases, it starts the “Automatic Reclose” timer.
• If voltage remains continuously present for the duration of the timer, the switch control recloses the tripped switch.
CAUTION Be sure to select a conservative value for the “Phase Loss Protection Current Thresh- old” – one that is clearly below the load break rating for the line switch.
CAUTION Automatic reclose is not available in conjunction with automatic transfer.
1051-541 24
To Enable Automatic Reclose:
1 In the “Features Enabled” field on the SETUP: Automatic Operation window, select a combination that includes “Phase Loss Protection with Automatic Reclose.”
2 At the SETUP: Automatic Operation window, enter values for the “Phase Loss Protec- tion Time Threshold,” the “Phase Loss Protection Current Threshold,” and the “Phase Loss Protection Automatic Reclose Time Threshold.” You can also enter a “Phase Loss Protection Voltage Threshold”; otherwise, the switch control uses the “Loss of Voltage Threshold” on the SETUP: Site-Related window. (See the SETUP: Automatic Opera-
tion window explanation in the Setup chapter for details.)
3 Use either the faceplate automatic operation ENABLE/DISABLE switch or a SCADA command to enable automatic operation of the switch control.
Shots-to-Lockout The shots-to-lockout feature allows the field technician or SCADA operator to test a potentially faulted line by reducing the counts to trip to either one or two for a speci- fied time period. If the circuit is then de-energized by a source-side protective device (recloser, breaker, etc.), and the switch control sees the transition from voltage present to loss of voltage, the switch control opens the switch immediately. This allows the faulted line segment to be isolated and prevents the source-side device from reclosing into a fault multiple times.
When the line switch is closed, you can also enable shots-to-lockout. This feature is useful for extending the shots-to-lockout functionality to a load-side manual switch.
NOTICE Automatic Reclose only occurs if the switch operator tripped the switch open due to phase imbalance; switches opened for other reasons must be reclosed manually.
NOTICE If the source-side device opens and recloses very quickly, sensors on the load side of the switch may not have enough time to sense both the voltage increase (when the switch closes) and the voltage loss (when the source-side device opens) before the source-side device recloses. Under these conditions, the switch operator cannot car- ry out shots-to-lockout, except during a transfer event. For best results, always orient the switch so that the sensors are on the source side.
CAUTION It is very important that the end of the shots-to-lockout timer and the source breaker operation are coordinated. Operation of the breaker at the same time the switch opens could result in failure of the switch.
25 1051-541
The feature is enabled indefinitely (“latched”), until disabled by toggling the faceplate REMOTE/LOCAL switch to REMOTE.
When shots-to-lockout is enabled:
• When the line switch is open: If you close the switch into a fault and the source-side protective device (recloser, circuit breaker, etc.) detects the fault, the source-side device opens and voltage is lost on all phases.
When the line switch is closed: If a load-side manual switch on the circuit closes into a fault and the source-side protective device (recloser, circuit breaker, etc.) detects the fault, the source-side device opens and voltage is lost on all phases.
• The switch control recognizes that the source-side device opened. If the “Number of Shots Required for Lockout” is set to “One,” the switch control trips open the switch right away. If it is set to “Two,” the switch control waits until the source-side device recloses and opens a second time. Then the switch control trips open its switch. If the “Overcurrent Required before Shots-To-Lockout Operation” setpoint is also enabled, the switch control only opens the switch if the 3-phase voltage loss was preceded by an overcurrent.
Setting the “Number of Shots to Lockout” to “Two” prevents the switch control from trying to open the switch at the same time as the source-side device is performing its instantaneous reclose. If the “Overcurrent Required before Shots-To-Lockout Opera- tion” setpoint is also enabled, the relationship between the detection of overcurrent and voltage losses follows the “Fault Current Required before First/All Voltage Loss(es)” setpoint.
• The switch remains open until you close it with a SCADA command or manually from the switch control faceplate.
Local Shots-to- Lockout
To carry out the shots-to-lockout command from the switch control faceplate:
1. On Page 1 of the SETUP: Automatic Operation window, make sure that:
• The “Features Enabled” setpoint is set to an option that includes “Sectionalizing.”
• The “Number of Shots Required for Lockout” setpoint is set to the appropriate
number for this switch control.
• The “Shots-To-Lockout Time Threshold” setpoint contains a value higher than
zero.
to the appropriate value for this switch control.
2. Set the faceplate REMOTE/LOCAL switch to LOCAL.
1051-541 26
3. Hold the faceplate automatic operation ENABLE/DISABLE switch in the ENABLE
position. (This will cause the ENABLED LED to blink while you are holding the switch.)
4. While you hold the ENABLE/DISABLE switch in the ENABLE position, toggle the CLOSE/OPEN faceplate switch (for the circuit you want to test) to the CLOSE posi- tion. This will cause the CLOSED LED for the selected switch to blink. If the line switch is open, this action closes it.
5. Release the ENABLE/DISABLE switch.
• If the line switch was previously open, the “lockout” mode remains in effect
(and the CLOSED LED continues to blink) for the duration of the “Shots-To-
Lockout Time Threshold.” If the appropriate number of voltage losses is
detected during this time, the switch control trips open the switch.
• f the line switch was already closed, the “lockout” mode remains in effect
(and the CLOSED LED continues to blink) indefinitely. To disable it, toggle
the REMOTE/LOCAL switch to REMOTE.
Remote Shots-to- Lockout
You can also carry out shots-to-lockout from a SCADA master station. (See the appro- priate communications document for more details.) However, latched shots-to-lockout is not available remotely.
NOTICE To use remote shots-to-lockout, the M Series faceplate REMOTE/LOCAL switch must be set to REMOTE and the automatic operation ENABLE/DISABLE switch set to ENABLE.
27 1051-541
When a line switch has been tripped (opened automatically) by the switch control, the information on the OVERCURRENT FAULT windows can help you determine the source and cause of the problem.
View the Fault Events Log
Click the Overcurrent Fault button on any window to open the OVERCURRENT
FAULT MENU window, then click the Fault Events button.
Figure 3 OVERCURRENT FAULT: Fault Events Window
The OVERCURRENT FAULT: Fault Events window (Figure 3) shows a chronological listing of fault-related events for the switch(es). The record for each event includes the time, the switch number (if applicable), the type of event, the switch control’s interpre- tation of the event, and the action taken.
This log includes four pages of data. Once the log is full, each new event over-writes the oldest event in the log. To find the most recent event, look for the message with a times- tamp that is older than the time for the message above it.
This window includes two columns:
Date/Time……MSec
This is the time (to the nearest 6.25 milliseconds) when the event was logged. (The switch control logs the event after the fault event and all described actions are com- pleted.)
VIEWING OVERCURRENT FAULT INFORMATION
Event
This is the event message, which describes the event, the assumption the switch con- trol made about the event, and the action(s) taken. These messages are explained below.
Phase A OC; Fault current sensed & cleared; Noted
The switch control detected an overcurrent fault on Phase A. That overcurrent fault has ended. The switch control is waiting to see if voltage will be lost on all three phases. (If all voltage is lost, the switch control will begin timing for a possible recloser operation.)
The M Series displays similar messages for Phase B, Phase C and Ground overcurrent conditions.
Phase B OC; Fault current sensed & cleared; Noted
See <Emphasis-Italic>Phase A OC; Fault current sensed & cleared; Noted above.
Phase C OC; Fault current sensed & cleared; Noted
See <Emphasis-Italic>Phase A OC; Fault current sensed & cleared; Noted above.
Ground OC; Fault current sensed & cleared; Noted
See <Emphasis-Italic>Phase A OC; Fault current sensed & cleared; Noted above.
OC then voltage o.k.; Load-side protective open; Noted
The switch control detected an overcurrent fault. This condition was not followed within 0.6 seconds by a loss of voltage on the same phase. The control assumed that a load-side fault occurred, but the condition was cleared on the load side (by a fuse, recloser, etc.).
No timer, or other action, is started for this type of event.
OC then VL; Source-side protective open; Counting
The switch control detected an overcurrent fault, which was followed within 0.6 sec- onds by a loss of voltage on all phases. The switch control assumed that a load-side fault occurred and the condition was cleared on the source side by a three-phase device (such as a breaker, interrupter, or recloser). The control added one count to the recloser operations counter.
Reclose memory time limit; Sequence ended; Count reset
The “Sectionalizer Reset” timer expired. The M Series will consider future events to be part of a different event sequence.
VL; Source-side fault; Sectionalizing disarmed
The switch control detected a three-phase voltage loss but no overcurrent fault condi- tion. The control assumed that a source-side fault occurred and the condition was
29 1051-541
cleared on the source side by a three-phase device (such as a breaker, interrupter, or recloser). The control started the “Sectionalizer Reset” timer and set the value in the recloser operations counter to “1.” Because the fault was on the source side, the con- trol will not trip open the switch due to recloser counts with fault current detected, but will open the switch if the “Recloser Counts to Trip, Voltage Loss Only” count is reached.
VL; Load-side fault; Sectionalizing armed
The switch control previously detected a phase or ground overcurrent fault, followed within 0.6 seconds by three-phase voltage loss. The control then assumed that the present voltage loss was associated with the previous load-side fault, and that the con- dition was again cleared on the source side by a three-phase device (such as breaker, interrupter, or recloser). The control incremented the recloser operations counter.
Full count reached; Source-side fault; Noted
The full count was reached on the recloser operations counter. Because the first volt- age loss in the sequence was not preceded by an overcurrent fault, the control took no sectionalizing action on the count of “Recloser Counts to Trip, Fault Current Detected.”
Full count reached; Load-side fault; Noted
The full count was reached on the recloser operations counter. Because the first volt- age loss in the sequence was preceded by an overcurrent fault (as well as all subse- quent voltage losses, if the “Fault Current Required Before First/All Voltage Loss(es)” is set to “All”), the control will take the appropriate sectionalizing action.
Full count reached with sectional. disabled;; Noted
The full count was reached on the recloser operations counter. Because sectionalizing was disabled, the switch control did not trip open the switch.
To identify the exact events that led to this action, review the earlier log messages.
Full count reached;; Open operation executed
The full count was reached on the recloser operations counter, so the switch control tripped open the switch.
To identify the exact events that led to this action, review the earlier log messages.
No OC before VL; Source-side open; Counting
The switch control detected a three-phase voltage outage which was not preceded by an overcurrent fault. The control assumed that a source-side fault occurred and the condition was cleared by a source-side device. The control added one count to the recloser operations counter.
OC then VL; Source-side fuse blown for load-side fault
The switch control detected a phase or ground overcurrent fault. This was followed within 0.6 seconds by a loss of voltage on the same phase, without all other phases losing voltage. The control assumed a load-side fault occurred and the condition was cleared on the source side by a fuse or single-phase recloser.
1051-541 30
No OC then VL; Source-side (SS) fuse blown - SS fault
The switch control detected a loss of voltage on one or two phases, which was not pre- ceded by an overcurrent fault. The control assumed that a source-side fault occurred and the condition was cleared on the source side by a fuse or a single-phase recloser.
CLOSE operation executed, shots-to-lockout requested
In response to an automatic transfer command, or a SCADA or faceplate “Shots-To- Lockout” command, the control closed the switch and started the “Shots-To-Lockout” timer.
Lockout close complete with event after - OPEN executed
An operator requested a “shots-to-lockout” operation. The switch control detected the appropriate number of three-phase voltage losses (within the specified shots-to-lock- out time interval) so it tripped open the switch. If “Overcurrent Required before Shots- To-Lockout Operation” is enabled, the switch control also detected overcurrent. (If the “Number of Shots Required for Lockout” is set to 2, the relationship between the detec- tion of overcurrent and voltage losses follows the “Fault Current Required before First/All Voltage Loss(es)” setpoint.)
Persistent phase imbalance;; OPEN executed
The switch control detected a loss of voltage on one or two (but not all three) phases. The imbalance continued for the full count of the “Phase Loss Protection Time Thresh- old” timer. Because this loss occurred while Phase Loss Protection and automatic oper- ation were both enabled, the switch control tripped open the switch.
Phase imbalance w. reclose enabled;; Waiting
The switch control detected a phase imbalance while Automatic Reclose was enabled. The control tripped open the line switch and is now waiting for three-phase voltage to return.
Switch closed; Operator action; Reclose canceled
While the switch control was waiting for three-phase voltage to return (with Automatic Reclose enabled), an operator manually closed the line switch (from the faceplate or via SCADA command). This operator action canceled the pending “Automatic Reclose” operation.
NOTICE If, before the timer expires, voltage is restored on any phase and then lost on all three phases, the M Series will trip open the switch. If “Overcurrent Required before Shots- To-Lockout Operation” is enabled, the switch control also detected overcurrent.
NOTICE When full voltage returns, the control will start the “Automatic Reclose” timer. When voltage is continuously present for the full count of the timer, the control will reclose the switch.
31 1051-541
Voltage OK after imbalance; Voltage restored; Waiting
After the switch control tripped open the switch because of a phase imbalance, three- phase voltage returned. Because Automatic Reclose was enabled, the control started the “Automatic Reclose” timer. The control is waiting for the timer to expire.
Imbalance corrected w. reclose enabled; CLOSE executed
After the switch control tripped open the switch because of a phase imbalance, three- phase voltage was restored and remained present for the full count of the “Automatic Reclose” timer. Because Automatic Reclose was enabled, the control reclosed the switch.
No OC before VL; Voltage Loss Only count reached
The switch control detected a three-phase voltage outage which was not preceded by an overcurrent fault. Sectionalizing on voltage loss only is enabled, and the “Recloser Counts to Trip, Voltage Loss Only” has been reached.
Open operation executed on Voltage Loss Only
Sectionalizing on voltage loss only is enabled, and the “Recloser Counts to Trip, Voltage Loss Only” has been reached. The switch control sent the command to open the switch.
Sectionalizing disabled on Voltage Loss Only;; None
The necessary criteria for sectionalizing on voltage loss only have been reached, but the feature is disabled. Neither a count of voltage losses nor an extended voltage loss will cause an operation.
Reclose memory time limit; Extended Volt Loss; OPEN
The reclose memory time limit expired without the restoration of voltage on any phase. This constitutes an extended voltage loss condition. The switch control opened the switch.
Shots-to-lockout latched on
An operator enabled the “shots-to-lockout” operation on a closed switch. The switch control will open the switch if the detected three-phase voltage count equals the “Num- ber of Shots Required for Lockout.”
Successful reclose; Sequence ended; Count reset
The “Successful Reclose Reset Time” timer has expired. The switch control will con- sider future events to be part of a different event sequence.
NOTICE When the “Automatic Reclose Time...” setpoint value is reached, the switch operator will close the switch.
1051-541 32
View the Fault Magnitude and Duration Log
Click the Overcurrent Fault button on any window to open the OVERCURRENT
FAULT MENU window, then click the Fault Magnitudes button.
Figure 4 OVERCURRENT FAULT: Fault Magnitudes Window
The OVERCURRENT FAULT: Fault Magnitudes window (Figure 4) shows a chrono- logical listing of peak magnitude and duration data for overcurrent fault events. The record for each event includes the date, time, phase, magnitude, and fault duration.
The log can hold information for 16 events. Once the log is full, each new event over- writes the oldest event in the log. To find the most recent event, look for the message with a timestamp that is older than the time for the message above it.
The window includes the following fields:
Date/Time……MSec
This is the time (to the nearest 6.25 milliseconds) when the event began. (The switch control logs each event when it ends.)
Phase
This is the phase, and switch if applicable, on which the overcurrent fault occurred (for example, A2, C1, or G2).
Mag. (Amps)
This is the peak (maximum) overcurrent fault magnitude during the event. This is dis- played as an RMS, asymmetric number.
33 1051-541
Duration (Sec)
This is the duration of the overcurrent fault event. The value is displayed in units of sec- onds, with resolution to the nearest 0.00625 seconds (6.25 milliseconds). The maximum recorded fault duration is 409.6 seconds (6.82 minutes). Any fault that lasts longer than that is recorded as 409.6 seconds.
View the AC Power Outages Log
Click the Overcurrent Fault button on any window to open the OVERCURRENT
FAULT MENU window, then click the Power Outages button.
Figure 5 OVERCURRENT FAULT: AC Power Outages Window
The OVERCURRENT FAULT: AC Power Outages window (Figure 5) shows a chrono- logical listing of voltage outage events. The record for each event includes the date, time, and phase status for each event.
An event is recorded each time:
• Voltage drops below the “Loss of Voltage Threshold” setpoint on any phase (see the SETUP: Site-Related window in the Setup chapter for details).
• Voltage rises above the “Loss of Voltage Threshold” setpoint.
The log can hold information for 16 events. Once the log is full, each new event over- writes the oldest event in the log. To find the most recent event, look for the message with a timestamp that is older than the time for the message above it.
1051-541 34
Date/Time……MSec
This is the time (to the nearest 6.25 milliseconds) when the event began. (This time is logged as soon as the event occurs.)
Event
This is the phase, and switch if applicable, on which the voltage loss event occurred (for example, A2, C1, G2, or Control Power).
NOTICE The switch operator records a “Control Power” voltage loss event whenever the Pow- er Supply/Control I/O module detects loss of AC power and switches to battery back- up power.
35 1051-541
View Routine Data Logging Information
The data logging windows show high and low values and trend data for voltage and cur- rent amplitude, phase, and related parameters. When a customer complains of a service outage or low voltage, the information on the DATA LOGGING windows can help you determine what happened and why it happened.
View the “Daily Highs and Lows” Data
Click the Data Logging button on any window to open the DATA LOGGING MENU win- dow, then click the button for the time period that contains the day you want to view. Then, if necessary, click the PgUp and PgDn buttons to move to the correct day.
Figure 6 DATA LOGGING: Daily Highs and Lows
Each DATA LOGGING: Daily Highs and Lows window (see Figure 6 example) shows the highest and lowest voltage and current (along with associated power factor, kVAR, and kW values) for each switch for a 24-hour period (12 midnight to 12 midnight). You can view the high/low data for today and for each of the preceding 7 days.
The switch control records the voltage on all three phases when any one phase is higher/lower than the previous high/low recorded on any phase.
The switch control also records the current on all three phases, based on the average 3-phase current. In addition, when a new daily high or low occurs, it records the power factor (per phase), kVARs (per phase and total), and total kW at that time.
Each displayed value is the “1.6 second averaged” value for that parameter. To obtain a “1.6 second averaged” value, the switch control samples the data every 0.2 seconds. Then it adds together 8 consecutive samples and divides the total by 8.
VIEWING DATA LOGS
View the DATA LOGGING: Data for Most Recent Week Menu
At the DATA LOGGING: Data for Most Recent Week Menu window (Figure 7), you can select the set of “daily profile” data that you want to view (data for Sunday, data for Monday, etc.). This data consists of “15 minute averaged” values for voltage, current, and kVAR for each of the most recent 7 days.
To display the DATA LOGGING: Data for Most Recent Week Menu window, click the Most Recent Week button (for the desired switch, if applicable) at the DATA LOGGING
MENU window.
Figure 7 DATA LOGGING: Data for Most Recent Week Menu Window
View the Profile Data for One Day
Each DATA LOGGING: Profile Data window (see example, Figure 8) shows the data for one day (12 midnight to 12 midnight) during the preceding week.
To display a DATA LOGGING: Profile Data window, click the button for the day you want to view at the DATA LOGGING: Data for Most Recent Week window (for the desired switch, if applicable).
NOTICE If you select to view information for today, you will see values from two separate days. For example, if it is now 3:01 PM on a Tuesday and you select “Profile Data for Tuesday”, all the data entries through 3:00 PM are today’s values. All the entries for times after 3:00 PM are from Tuesday of last week.
37 1051-541
The recorded numbers are “15 minute averaged” values.
The switch control samples the data every 0.2 seconds. It adds together 8 consecutive samples and divides the total by 8, to yield a “1.6 second averaged” value. Then it adds together all the “1.6 second averaged” values in the time span (for example, 2:31 a.m. - 3:00 a.m. for a 30 minute time span), and divides that total by the number of values.
1051-541 38
You can use the Report feature to save the Control software settings and stored data to your computer in a CSV (comma-separated value) file. You can keep the report as a per- manent record and use the report data in spreadsheets or other types of programs.
1. Connect your portable computer to the switch control and start the IntelliLINK software.
For details, see To Start the IntelliLINK Software in the Setup chapter. If your com- puter is already connected to the switch control, you can skip this step.
2. At any IntelliLINK window, click the Report Menu button.
3. At the REPORT MENU window, click the Full Report button to generate a report.
The Full report includes all the information contained in the switch control.
4. In the Save Report dialog box, specify a name and location for this report, then click Save.
If you do not specify a location, the file is saved to the same directory as the program files for this switch control (for example, the default location for SNCD-S0X report files is C:\ELine\SNCD-S0X\). The extension “.CSV” is added automatically.
When the report is complete, the message “Task completed” appears on the status line of the Writing Report dialog box.
5. Click OK.
The software closes the dialog box and displays the REPORT MENU window.
GENERATING REPORTS
39 1051-541
If two or more switch controls use a similar setup configuration and the same software
version, you can save the configuration from one switch control and load it into the other(s). Then you only need to manually adjust the setpoints that are different for each switch control.
Save a Setup Configuration
1. Determine which switch control contains the configuration you want to save.
2. Connect your computer to the selected switch control and start the IntelliLINK software.
For details, see To Start the IntelliLINK Software in the Setup chapter. If your com- puter is already connected to the switch control, you can skip this step.
3. At any IntelliLINK window, click the Setup Menu button.
4. At the SETUP MENU window, click the Save Data button.
5. In the Save Setpoints dialog box, specify a name and location for this configuration (CFG) file, then click Save.
If you do not specify a location, the file is saved to the same directory as the program files for this for this switch control (for example, the default location for SNCD-S0X report files is C:\ELine\SNCD-S0X\). The extension “.CFG” is added automatically.
NOTICE This process does not save the “Physical Location” (on the SETUP: Mis- cellaneous window), “Communications RTU Address” (on the SETUP: Communications window), or the sensor configuration data (on the SET- UP: Sensor Configuration window, if applicable).
SAVING A SETUP CONFIGURATION
Load a Saved Configuration into a Switch Control
1. Connect your computer to the switch control where you want to load the saved configuration, then start the IntelliLINK software.
For details, see To Start the IntelliLINK Software in the 1051-530 Software Setup. If your computer is already connected to the switch control, you can skip this step.
2. From the File menu, choose Load Setpoints.
3. In the dialog box, select the CFG file for the configuration you want to load, then click Open.
4. Make any setpoint changes that are required for this switch control.
For details, see the Setup chapter.
NOTICE Be sure to enter the correct value for the “Physical Location” (on the SET- UP: Miscellaneous window) and the “Communications RTU Address” (on the SETUP: Communications window), and the sensor configuration data (on the SETUP: Sensor Configuration window, if applicable).
41 1051-541
To view the IntelliLINK windows and Help file without connecting to a switch control or a snapshot:
1. Start the IntelliLINK software on your computer.
2. During startup, click Cancel to close the Connect dialog box.
If the IntelliLINK software is already running, choose Disconnect from the Connection menu, then choose Close Screenset from the File menu, to clear the present screenset from memory.
3. From the File menu, choose Open Screenset.
4. In the Open Screenset dialog box, find and select the WMN file whose name matches the version name on the Setup software disk for this switch control.
VIEWING INTELLILINK WITHOUT DATA
1051-541 42
You can save operational and data logging information in “snapshots” (VM, virtual memory files). These snapshots let you view data, generate a report, and save or change setpoint configurations even when you are not connected to a switch control. To access the stored information, you “connect” to the snapshot instead of the physical control. Each switch control Setup disk includes a sample snapshot.
1. Save Settings and Data to a Snapshot
a Connect your computer to the switch control from which you want save information, then start the IntelliLINK software.
For details, see To Start the IntelliLINK Software in the Setup chapter. If your com- puter is already connected to the switch control, you can skip this step.
b From the Tools menu, choose Snapshot > Save.
c In the dialog box, specify a file name and location for this snapshot, then click Save.
If you do not specify a location, the file is saved to the same directory as the program files for this for this switch control (for example, the default location for SNCD-S0X report files is C:\ELine\SNCD-S0X\). The extension “.VM” is added automatically.
2. View (connect to) a Snapshot
a Start the IntelliLINK software on your computer. During startup, click Cancel to close the Connect dialog box.
If the IntelliLINK software is already running, choose Disconnect from the Connection menu, then choose Close Screenset from the File menu, to clear the present screenset from memory.
b From the Connection menu, choose Connect to VM File.
The Open Controller Data File dialog box opens.
c Select the snapshot that you want to view, then click Open.
d If you plan to change the configuration settings in the snapshot, click Yes at the Connect to File dialog box. If you want to avoid accidentally changing a setting, click No.
The IntelliLINK software opens and displays the contents of the selected snapshot.
3. Save Changes You Make in the Snapshot
All changes you make to configuration settings in the snapshot are automatically saved to disk immediately. You do not need to “save” the changes in a separate operation.
USING SNAPSHOTS
43 1051-541
4. Generate a Report From a Snapshot
Follow the same procedure as when you are connected to a switch control. For details, see Generating Reports on page 4-42.
5. Create a Configuration (CFG) File From a Snapshot
This procedure allows you to prepare a setpoint configuration for a switch control which is in the field while you do not have access to a comparable device.
a Connect to the snapshot.
For details, see “2.” on page 42.
b Change the configuration settings in the snapshot as needed.
For details, see the Setup chapter.
c At any IntelliLINK window, click the Setup Menu button.
d At the SETUP MENU window, click the Save Data button.
e In the Save Setpoints dialog box, choose a file name and location for this configuration, then click Save.
If you do not specify a location, the file is saved to the same directory as the program files for this for this switch control (for example, the default location for SNCD-S0X report files is C:\ELine\SNCD-S0X\). The extension “.CFG” is added automatically.
NOTICE This process does not save the “Physical Location” (on the SETUP: Miscellaneous
window), the “Communications RTU Address” (on the SETUP: Communications
window), or the sensor configuration data (on the SETUP: Sensor Configuration
window, if applicable).
1051-541 44
Occasionally, you may need to update the software that is stored in the switch control (the Control software). The Update program, installed with the IntelliLINK software, lets you easily replace the old Control software with the newer version.
1. Install the contents of the new Setup disk on your computer.
For details, see To Start the IntelliLINK Software in the 1051-530 Software Setup.
2. Connect your computer to the Local Access port on the switch control.
3. Start the Update program.
a In Windows, choose Start menu > Programs > EnergyLine > Update.
The Update window appears (Figure 9).
NOTICE The setpoint values and historical data stored in the switch control could be lost during the update process. To be safe, always generate all needed reports, using the old IntelliLINK and Control software, before you up- date the Control software.
CAUTION We strongly recommend that the switch control have AC control power (or sensor power) as well as battery power during the update process.
If you have to update the Control software while the control has battery power only, you MUST follow the instructions described in “Updating the Control Software with Battery Power Only” on page 46. Otherwise, the update process will not run properly.
UPDATING CONTROL SOFTWARE
b Select the desired options, then click Start Update.
The update process may take 5 to 20 minutes. You can follow the progress in the lower right corner of the window. Once the update is complete, the window automatically closes.
NOTICE If your switch control is not connected to COM1 on your computer, click on the Com- munication Setup tab, select the correct comm port, click Connect, and then return to the Update Control Software tab and click Start Update.
CAUTION If you cancel the update process once it has started, you deactivate the software in the control. If you must cancel the process, start the update process again.
NOTICE If the software on the disk is not the same type as the software in the switch control, an error message appears. Noet which software version is in the switch operator, then press <Enter> to abort the update process. When you have the correct new soft- ware version, repeat the steps above.
1051-541 46
Updating the Control Software with Battery Power Only
We recommend that the switch control have both battery and AC control power (or battery and sensor power, if applicable) when updating the Control software. If you must update the Control software at a location where no AC control power is available, then you must follow these instructions to override the automatic shut-down.
Protection System Logic
All functions of the switch control are directed by the CPU, including charging and monitoring the battery system. If the CPU program stops or hangs, the control will not function and the battery or circuits might be damaged. To indicate that the CPU pro- gram is functioning properly, it sets a bit on the PS/IO board every few seconds. If that bit goes unset for 60 seconds, the PS/IO board disconnects the battery, shutting down the control and preventing damage to the control circuits and battery.
During the update process, the CPU is unable to function and does not set the bit on the PS/IO board. The protection logic disconnects the battery 60 seconds or less after the update process begins. When AC control power (or sensor power) is present, the con- trol continues to operate without battery power and completes the software update. However, if AC control power (or sensor power) is not present, the control shuts down, terminating the software update. There is no damage to the control, and the update process can be started again.
Manually Overriding the Battery Disconnect Command
You can update the Control software using only battery power by manually sending a “battery on” command to the PS/IO board. To do so, press the BAT ON switch every 30 seconds. This white momentary-contact switch is located on the PS/IO board (see Figure 10).
Updating the Control software usually takes less than five minutes – pushing the BAT
ON switch is generally easier than moving the control to a location with AC control power (or sensor power).
47 1051-541
BAT ON Switch
1051-541 48
The Switch Operator monitors the absolute angular position of the drive train assembly at all times for both the rotating and reciprocating switch operators, and also provides very precise torque and position-sensitive operation of the overhead switch. The posi- tion of the drive train assembly in relation to the desired position of the switch is shown below. Figure 11 depicts the angles graphically, and Table 2 lists the relation- ship between positions of the drive train assembly and the various operational limits imposed by the control logic.
The drive train position is monitored continuously by the control system and has a res- olution of 0.2°. The position of the switch in relation to the position of the drive train is also monitored by the control system during operation (see Switch Operations below for details).
Angular Position
SWITCH ACTUATOR MONITORING & CONTROL LOGIC
49 1051-541
(Operational Limits)
Description Value
1 Desired position of output actuator in open position. Position corresponds to open position set using faceplate “Set Limits” procedure.
(based on setup of switch travel limits)
2
Desired position of output actuator in closed position. Position corresponds to closed position set using faceplate “Set Limits” procedure, plus increment based on optional additional torque requested via IntelliLINK (see #10 below).
(based on setup of switch travel limits, plus additional requested torque)
3 Nominal amount of travel expected from movement from open to closed positions.
(based on setup of switch travel limits)
4 100% closed. This angle is use