Upload
others
View
26
Download
0
Embed Size (px)
Citation preview
PRE-FEASIBILITY REPORT, SAKTHI FERRO ALLOYSi
SAKTHI FERRO ALLOYS INDIA PRIVATE LTD15/1,15/3,16,17/1,17/2,17/3,17/5,17/6,17/7,17/8 A, 17/9 and 152/32
Vasanadu village, Nadumuru Village Panchayath,Kuppam, Chittoor Dist.
Andra Pradesh, Pin - 517425
PRE-FEASIBILITY REPORT ON ENVIRONMENTAL ASPECTSOF PROPOSED EXPANSION OF
SAKTHI FERRO ALLOYS INDIA PRIVATE LTDfrom the production capacity of 27000 TPAof billets and 29000
TPA of TMT bars to 1,56,000 TPA billets and 1,44,000 TPA TMTBars
April 2019
Chennai Testing Laboratory Pvt. Ltd.A-Super 19, TVK Industrial Estate,
Guindy, Chennai 600032.E-Mail: [email protected]
PRE-FEASIBILITY REPORT, SAKTHI FERRO ALLOYSii
CONTENTS
1.0 EXECUTIVE SUMMARY................................................................................. 1
2.0 INTRODUCTION / BACKGROUND INFORMATION......................... 4
3.0 PROJECT DESCRIPTION ........................................................................... 7
4.0 SITE ANALYSIS........................................................................................... 18
5.0 PLANNING BRIEF ..................................................................................... 23
7.0 REHABILITATION AND RESETTLEMENT (R&R) PLAN.................... 26
8.0 PROJECT SCHEDULE & COST ESTIMATES ........................................... 27
9.0 ANALYSIS OF PROPOSAL ...................................................................... 28
Fig 1.0 Topo Map ……...……………………………………………………………8
Fig 2.0 HRS map ( 1 km radius ) ………………………………………………..9
Fig 3.0 Plant Layout …………………..…………………………...………………10
Fig 4.0 Process Flow Diagram …………………………….……………………...13
Fig 5.0 Material Balance 14
Fig 6.0 Water Balance Diagram……………………………………………….….16
Fig 7.0 Satellite Map ………………………………………………………………19
Fig 8.0 Physiography Map ….………………………….……………………...…20
Fig 9.0 Drainage and Water Bodies Map…………………….………………….21
Pre-feasibility Report 1 SAKTHI FERRO ALLOYS
1.0 EXECUTIVE SUMMARY
1.1 Proposed Project
The proposed project is an expansion of existing steel plant with installation of an
additional 1 X 15 TPH Induction furnace within the existing Billet/TMT Plant..
1.2 Project Location
The proposed project will be located at 15/1,15/3,16,17/1,17/2,17/3,17/5,17/6,17/7,17/8 A,
17/9 and 152/32 of Vasanadu Gollapalle village , Nadumuru village panchayath,Kuppam,
Chittoordistrict, Andra Pradesh and is devoid of any notified Eco-Sensitive within 10
kms radius of plant site and within Latitude and Longitude of 12°41’45.55” N
78°20’59.84” E , 12°41’44.49” N an78°21’07.25” E , 12°41’35.87” N78°21’03.58” E
and 12°41’37.65” N 78°20’57.33” E .
1.3 Project Proponent
M/s. Sakthi Ferro Alloys (india) Private Limited a company under Sakthi group of
companies having more than 3-decade long experience in scrap trading, Steel
Making and Marketing Business with its registered office at 8/26, Loganathan Nagar,
second street, Choolaimedu,Chennai 600094 Tamilnadu
1.4 Manufacturing Process
M.S. Scrap along with sponge Iron is melted in Electric Arc Furnace to produce
billets. The billets are then rolled into M.S. Rolled Products ie TMT Bars
1.5 Production Capacity
Products Production Details (TPA)Existing After Expansion
M. S. Billets (2 x 15 TPH, Induction Furnace) 28080 TPA 1,56,000 TPA
Rolled Products (Rolling Mill) TMT Bars 29000 TPA 1,44,000 TPA
Pre-feasibility Report 2 SAKTHI FERRO ALLOYS
1.6 Land usage of plant site
The total land requirement for the proposed expansion is 6.92 Ha
The land use is given as follows
Description Area in Ha
Built up area 1.56
Road 0.55
Scrap and Product storage area 2.01
Green belt 2.28
Vacant Lnd 0.52
Total 6.92
1.7 Raw Water Requirement
The total raw water requirement up on expansion will be 60 KLD and main water
requirement will be for cooling water make up and domestic purpose
1.8 Source of Water
Raw water will be sourced from Underground sources/Rain Water Harvesting.
1.9 Solid Waste Generation & Method of Disposal
The quantity of solid waste that would be generated from the Proposed Plant are as
follows
S. No. Description Quantity Generated(TPA)
Mode of Disposal
1. Slag 6408 The slag will be used forland filling in low lying areain the plant it self. Groundslag will be Sold to Cementmanufacturers
Pre-feasibility Report 3 SAKTHI FERRO ALLOYS
1.10 Man Power Requirement
A total of 500-employees would be needed for the operation of the proposed plant
after expansion.
1.11 Air Pollution Control
The major source of air pollution is melting of Scrap/Sponge Iron in Electric
Induction Furnace , Which is provided with Scrubber / Stack to minimize impact on
air pollution.
1.12 Estimated Project Cost
The total project cost for the proposed expansion is 14 Crores.
1.13 Pollution Control Cost
The total pollution control cost for proposed plant is `1.08 Crores.
Pre-feasibility Report 4 SAKTHI FERRO ALLOYS
2.0 INTRODUCTION / BACKGROUND INFORMATION
2.1 PROJECT & PROPONENT
M/s. Sakthi Ferro Alloys (India) Private Limited is a part of Sakthi Group and is a
continuously performing company with more than three decades of experience in
the field of steel/metal trading, manufacturing and marketing. M/s. Sakthi Ferro
Alloys (India) Private Limited is a privately owned company.
M/s. Sakthi Ferro Alloys (India) Private Limited is already producing M.S. Rolled
Products through its group entities to a tune of 1,00,000 MT/Annum of Rolled
Products.
Sakthi Ferro Alloys India Private Limited sells its Rolled Product both domestically
and overseas.
Now, it is proposed to expand of existing plant with following production capacity
Products Production Details (TPA)Existing After Expansion
M. S. Billets (2 x 15 TPH, Induction Furnace) 28080 TPA 1,56,000 TPA
Rolled Products (Rolling Mill) TMT Bars 29000 TPA 1,44,000 TPA
2.2 NATURE OF PROPOSED PROJECT
The proposed project is a expansion of its existing facility by installing an additional
Induction furnace of 1X15 T and expansion of the Rolling facilities to produce billets
and TMT bars. M.S. Scrap along with Sponge Iron will be melted in Electric
Pre-feasibility Report 5 SAKTHI FERRO ALLOYS
Induction Furnace. The molten metal is cast into billets, and the billets are then
rolled into products.
2.3 NEED FOR THE PROJECT
Government of India has approved the National Steel Policy (NSP) 2017, as it seeks
to create a globally competitive Steel Industry in India. NSP 2017 targets 300 million
tonnes (MT) Steel making capacity, and 160 kg/capita steel production by 2030.
Huge Scope for growth is offered by India’s Comparatively low per capita steel
consumption, and expected rise in consumption due to increased infrastructural
construction and thriving transport industry. Government of India focus on
infrastructure, and restarting road projects is aiding boost in demand for steel.
Further, likely acceleration in rural economy and infrastructure is expected to lead
growth in demand for steel.
India is at present third largest producer of steel, and is all set to be the second
largest producer of steel by 2021. The growth in Indian Steel Industry is largely
driven by domestic availability of raw material such as Iron-ore, and cost effective
labour.
Further, remedial measures taken by Government of India to promote domestic steel
production, such as anti dumping duties, safeguard duties, and temporary
introduction of minimum import price, notified quality control order etc.
The Policy of Government of India also stipulates adoption of energy efficient
technologies, to improve overall productivity and reduce energy intensity.
The Government of India has also announced a policy for providing preference to
domestically manufactured Iron and Steel products in Government Procurement.
This Policy seeks to accomplish PM’s Vision of “Make in India” with objective of
Nation Building and encourage domestic manufacturing and is applicable on all
Government Tenders.
Pre-feasibility Report 6 SAKTHI FERRO ALLOYS
India has now emerged as a net exporter of finished steel products. India has
emerged as a top exporter of steel to Vietnam, Bangladesh, Myanmar, Sri Lanka,
Nepal and other European / American Markets. The demand for Indian Steel
Products from overseas market is set to increase, owing to slowing down of Chinese
production, overall.
2.4 EMPLOYMENT GENERATION
Employment generation is one of the important objective of any development
activity. Employment is closely linked to eradication of poverty. Unemployment,
and under employment had been the chronic feature of the Indian Economy.
Steel Industry employs people with many different skills and diverse knowledge.
Steel Industry employs unskilled, semi skilled and skilled workforce of various
nature. The workers required will be right from handling of raw material, to
processing of production, and finally handling of finished products. Apart from
main activity, workers are required for maintenance and operation of utilities.
Indirect generation of employment also entails in the form of logistics, supply chain
and related commercial activities.
Sakthi Ferro Alloy will employ about 500 direct workers after its expansion and
generate large scale indirect employment in the transportation, and related
commercial activities.
Pre-feasibility Report 7 SAKTHI FERRO ALLOYS
3.0 PROJECT DESCRIPTION
3.1 TYPE OF PROJECT
The proposed plant is an expansion of existing steel manufacturing unit. The project
upon completion envisages production of billets and TMT bars using M.S. Scraps
and Sponge Iron as raw materials.
The Proposed Plant after expansion will consist of 1 X 15 TPH Induction Furnace in
addition to existing to 1 X 15 TPH to produce 1,56,000 TPA Billets and Rolling mill
to produce 1,44000 TPA of TMT bars
3.2 PROJECT LOCATION
The proposed expansion project of Sakthi Ferro Alloy India Private Limited is to be
located at Survey Nos. 15/1,15/3,16,17/1,17/2,17/3,17/5,17/6,17/7,17/8 A, 17/9 and 152/32 of
Vasanadu Gollapalle village, Kuppam Taluk , Chittoordistrict, Andra Pradesh. .
The Latitude and Longitude of the project site is as follows.
Latitude Longitude12°41’44.47” N 78°21’08.33” E12°41’43.97” N 78°21’08.33” E12°41’43.90” N 78°21’08.13” E12°41’42.66” N 78°21’07.90” E12°41’42.61” N 78°21’07.71” E12°41’41.44” N 78°21’07.39” E12°41’41.57” N 78°21’06.88” E12°41’40.53” N 78°21’06.88” E12°41’40.38” N 78°21’07.08” E12°41’35.87” N 78°21’03.58” E12°41’37.65” N 78°20’57.33” E12°41’45.55” N 78°21’59.84” E12°41’44.60” N 78°21’06.86” E12°41’44.49” N 78°21’07.25” E12°41’44.45” N 78°21’07.57” E12°41’44.61” N 78°21’07.80” E
The project location is as shown in Fig.1.0 – Topo Map, and Fig.2.0 1 km radius HRS
Map and Fig.3.0 Plant Layout.
Pre-feasibility Report 8 SAKTHI FERRO ALLOYS
Fig 1.0 Topo Map
Pre-feasibility Report 9 SAKTHI FERRO ALLOYS
Fig 2.0 1 Km Radius HRS Map
Pre-feasibility Report 10 SAKTHI FERRO ALLOYS
Fig 3.0 Plant Layout
Pre-feasibility Report SAKTHI FERRO ALLOYS11
3.3 PRODUCTION CAPACITY
The details of production capacity of the proposed project are as follows.
Products Production Details (TPA)Existing After Expansion
M. S. Billets (2 x 15 TPH, Induction Furnace) 28080 TPA 1,56,000 TPA
Rolled Products (Rolling Mill) TMT Bars 29000 TPA 1,44,000 TPA
3.4 MANUFACTURING PROCESS
Induction Furnace
Scrap along with Sponge Iron are the main raw materials for melting in the
Induction Furnace. The scrap / Sponge Iron will be brought into the steel plant
premises by Tipper / Dumpers / Trucks. The Scrap is unloaded either in the open
scrap yard where it will be intermittently stored or directly into the scrap bay, and
Sponge Iron will be unloaded in the closed shed.
From the bins in the Melting Bay EOT cranes will load the scrap/ sponge iron in to a
bucket which will be charged in to the Induction Furnace by EOT Crane.
The Induction Furnaces are Melting Units. The heat and stirring in a coreless
Induction Furnace is caused by magnetic forces which result from the interaction of
the electrical current flowing in the induction coil and in the molten bath itself melts
the metal and can increase the bath temp. to required temperature of 1600°C to
1650°C. Slag formed is taken out in the process.
There will be 2 x 15 T Electric Induction Furnaces, and the tapping temperature is
maintained to approx. 1620°C.
One heat in one Induction Furnace is estimated to take about 120 minutes on an
Pre-feasibility Report SAKTHI FERRO ALLOYS12
average. There will be two Induction Furnaces of 15 T capacity .The Melting Bay has
to therefore handle 24 heats every 24 hours.
Slag handling
The slag generated during melting will be to the extent of 4 %. De-slagging will be
done by tilting the IF forward during the process while the power is reduced to a
minimum for 1-2 min. During the process of de slagging by forward tilting will be
done 5 - 6 times every heat. The slag will fall into in a slag box parked below the
Induction Furnace. The slag pot capacity will be 10 T to take care of the slag of each
heat. The slag pot will be lifted by the EOT crane and either be emptied in a dumper
or at the end of the bay. From there the slag will be taken to the slag dumping area.
Billet Casting
Liquid steel from ladle furnace is now placed in the Turret of the Continuous
Casting Machine. The Turret shall be moved and positioned over the tundish into
which the liquid steel will flow. From the tundish the liquid steel will flow into the
mould which shapes and forms the billet. The required starting ladle temperature
for the manufacture of billet for TMT rebars, wire rod, rounds, structural / grade at
the CCM is about 1650° C. The withdrawal machine also varies the speed of the billet
to keep the level of the mould constant as the steel flow into it varies as the metering
nozzle erodes with time. After the withdrawal machine is the oxy-fuel cutting
machine which cuts the billets into 6 m / 12 m length.
Rolling Mill
The heated billets are fed to different rolling mills to produce required size of
finished products.The rolled product after last stand is transferred to Turnover
Cooling Bed and cut to specified length and after Quality inspection and requisite
Color Coding, bundling etc. is shifted to dispatch section.
Pre-feasibility Report SAKTHI FERRO ALLOYS13
Purchase of rawmaterial
Segregation of Scrap
Moving scrap and sponge iron in to InductionFurnace
Melting of Scrap
Testing bath sample
Is satisfying the IS (BIS) standards
Local - Indigenious
Final bath sample
Increase the temperature of molten steelfor required level
DEMAND IN MARKET
Imported
Add carbon or reducecarbon for therequirement
Tapping liquid metal in Laddle
Purging in Laddle with N2/Argon gassample
Laddle placing over CCM casting stand
Liquid metal filling in tundish
Laddle sample taking
Temperature CheckingLaddle sample taking
Liquid metal drawn to mould tube
Casting as billets
Rolliing mill
Passing Through TMT Box
Cutting as per required Size
Despatch
Fig 4.0 Process flow Diagram
Pre-feasibility Report 14 SAKTHI FERRO ALLOYS
Fig 5.0 Material balance (Existing & Expansion)
Induction Furnace(Existing – 15 T x 1 Nos.
Enhancement - 15 T x 1 No.)
51030 TPA (Sponge Iron)
119070 TPA (Scrap)
Continuous Casting Machine
Rolling / Bar / Wire Rod/ Structural Mills (Existing 1 Nos. &Additional 3 Nos.)
1,44,000 TPATMT Bars
1,56,000 TPA Billets
Slag6408 TPA
Oxidation loss1745 TPA
ReturnableScrap
4806 TPA
Burning Loss6000 TPA
Crop Ends6000 TPA
Mill Scale1140 TPA
Pre-feasibility Report 15 SAKTHI FERRO ALLOYS
3.5 RAW MATERIAL REQUIREMENT
The major raw material required is virgin scrap and sponge iron for Induction
Furnace. The Annual requirement of raw materials on the basis of achievable
production will be as follows
Description Quantity (TPA)Existing Upon Expansion
M.S. Scrap 21623 119070
Sponge Iron 9267 51030
Sponge Iron is stored in closed shed and M.S. Scrap on metalled surface.
3.6 WATER / ENERGY REQUIREMENT
3.6.1 RAW WATER REQUIREMENT
The raw water requirement for the operation of the plant upon expansion will be as
follows, and will be sourced from ground water within plant site.
Description Qty (KLD)
Induction coil/Rolling mill cooling make-up 40
DM. Plant Regeration 5
Domestic Consumption 15
Total 60
The Fresh Water drawn from ground will be only 60 Cu.m/day for make up in process and
domestic consumption
The detailed Water Balance Diagram is as shown in Fig 6.0.
Pre-feasibility Report 16 SAKTHI FERRO ALLOYS
Fig 6.0 Water Balance Diagram
All values are in KLD
Raw Water60
Induction Furnace1 & 2 Cooling
Rolling MillCooling
D.M. Water
Evaporation Loss – 20
Evaporation Loss – 7
30
10
5 5
3
10
18 Neutralization Tank
Green Belt
18
DomesticConsumption15
12 Septic Tank withDispersion
Trench
12
Pre-feasibility Report 17 SAKTHI FERRO ALLOYS
3.6.2 ENERGY CONSUMPTION
The entire power requirements in existing and after expansion are 2.06 MW and
13.82 MW respectively. After expansion 13.82 MW will be sourced from APSPDCL.
Back up power :
DG Set 1 x 380 KVA
3.7 SOURCES OF POLLUTION AND ITS CONTROL
3.7.1 WATER ENVIRONMENT
The only major source of waste water is cooling water blow down and DM plant
regeneration waste which is subjected to treatment in neutralization tank and used
for green belt development.
3.7.2 SOLID WASTE MANAGEMENT
The solid waste generated will be only of 6408 TPA of slag from melting, in Electric
Induction Furnace, which is disposed to downstream building material producers.
The 200 kg waste and residues containing oil generated will be handed over to
authorized recyclers.
3.7.3 AIR ENVIRONMENT
The only major sources of air emission is melting of scrap / Sponge Iron in Electric
Induction Furnace , where in hood with an ID fan is provided, and the resultant
emission are cleared in a water spray packed wet scrubber , with stack 36 m height is
provided.
Pre-feasibility Report 18 SAKTHI FERRO ALLOYS
4.0 SITE ANALYSIS
4.1 CONNECTIVITY
The proposed plant will be located at Vasanadu post, Kuppam tehsil, Chittoor dist.
Andra Pradhesh state. The project site is located at distance of 7 km from Kuppam
Railway station. Plant site is well connected from Krishnagiri Road NH-48
(Chennai – Banglore Road), about 18 km south.
4.2 LAND FORM, LAND USE & LAND OWNERSHIP
The total land area of the existing plant is 6.92 Ha and the additional installation of
one 1 X 15 T EIF and enhancement of its rolling facility doesn’t envisage any
additional procurement of land. Out of 6.92 hectors 1.56 hectors will be built up area,
2.01 hectors will be Scrap and Product storage area, 0.55 hectors will be road,2.28
hectors will be green belt and remaining 0.52 hectors will be vacant land.
4.3 TOPOGRAPHY
Topography is Plain. The Topography of the proposed project site is as shown in
Fig.7.0 Satellite Imagery Map & Fig.8.0 Physiography Map.
4.4 DRAINAGE PATTERN & WATER BODIES
Drainage and Water Bodies around the vicinity of plant site and also within 10 km
radius of the plant site is as shown in Fig.9.0 Drainage and Water bodies Map.
Pre-feasibility Report 19 SAKTHI FERRO ALLOYS
Fig 7.0 Satellite Imagery Map
Pre-feasibility Report 20 SAKTHI FERRO ALLOYS
Fig 8.0 Physiography Map
Pre-feasibility Report 21 SAKTHI FERRO ALLOYS
Fig 9.0 Drainage & Water Bodies Map
Pre-feasibility Report 22 SAKTHI FERRO ALLOYS
4.5 SOIL CLASSIFICATION
The soils in general are characterized by sand/clay content, poor nitrate and
phosphorus contents. The fertility status of the lands, mostly under rain fed
agricultural use, is generally medium except in some pockets where the soils are
fertile.
4.6 CLIMATIC DATA
The climate of the project site is dry and the Max. dry & wet bulb temperature is 36.0
/ 32.0 °C respectively and Min. dry & wet bulb temperature 16.0 / 12.0°C
respectively. The predominant wind direction in the region W followed by SE.
Average annual rain fall of this region is about 600 mm. The average maximum
wind speed in this region is about 12 km/hr. The annual Maximum Humidity is
100% and minimum humidity is 30%.
Pre-feasibility Report 23 SAKTHI FERRO ALLOYS
5.0 PLANNING BRIEF
The area is dependent on the agriculture for their overall development and
livelihood. The area within 10 kms radius of plant site is having one steel industry
and other small, medium and large scale industries like cotton mills, Textiles,
Aluminum insulation, Granite industries and Food industries.
The total land requirement for the proposed project is 6.92 Ha
The Land usage and Break-up are as follows.
Description Area in Ha
Built up area 1.56
Road 0.55
Scrap and Product storage area 2.01
Green belt 2.28
Vacant Lnd 0.52
Total 6.92
The green belt development is already done about 25% of the total land area andremaining is in process.
Pre-feasibility Report 24 SAKTHI FERRO ALLOYS
Pre-feasibility Report 25 SAKTHI FERRO ALLOYS
6.0 PROPOSED INFRASTRUCTURE
6.1 INDUSTRIAL AREA
The proposed expansion requires construction of a platform to house Electric
Induction Furnace within the existing shed, where as all other facilities are existing.
6.2 GREEN BELT
About 2.28 hectors of total Land will be developed as Greenbelt, and 25% of the
green belt all ready done and remaining area will be developed as per MoEF
guidelines. More-over species selected are in consultation with the local forest
officer, and will be predominantly consist of local species.
Pre-feasibility Report 26 SAKTHI FERRO ALLOYS
7.0 REHABILITATION AND RESETTLEMENT (R&R) PLAN
The proposed plant is only the expansion of existing plant in the total land area of
6.92 Ha. There are no rehabilitation and resettlement or land oustees, as the land
area at present is already in use.
Pre-feasibility Report 27 SAKTHI FERRO ALLOYS
8.0 PROJECT SCHEDULE & COST ESTIMATES
8.1 TIME SCHEDULE
The construction of proposed expansion plant will take around 6 months from date
of obtaining Environmental Clearance. So, the proposed expansion will be
commissioned during the December 2019.
8.2 PROJECT COST
The total project cost for expansion will be Rs.14 Crores, which is inclusive of Rs.
1.10 Crores for pollution control activities.
Pre-feasibility Report 28 SAKTHI FERRO ALLOYS
9.0 ANALYSIS OF PROPOSAL
9.1 FINANCIAL & SOCIAL BENEFITS
Social benefits results in evaluation of project from society point of view. Proposed
steel plant will involve not only construction of the plant, but also construction of
intermediaries, which are basically facilities to the workers but will also offer
economic benefit to the local population.
Pollution from plant may cause degradation of the environment, which is the cost or
price locals have to pay for economic benefits accruing because of the proposed
project.
The significance of economic development cannot be underplayed especially in a
underdeveloped area, and Government also recommends investment in projects to
contribute in well being of the Society.
The proposed project of M/s Sakthi Ferro Alloys India Private Limited would result
in increased revenues to Government of Andra Pradhesh, and Government of India,
in terms of cumulative tax, both indirect taxes, and direct taxes.
The proposed project of M/s. Sakthi Ferro Alloys India Private Limited will also
result in augmentation of the social infrastructure, more-over investments in various
environment conservation measures will result in better living condition.
M/s Sakthi Ferro Alloys India Private Limited will invest about 0.2% of the project
cost in thrust areas for CSR activities such as income generation program, health and
hygiene, empowerment through self help groups, and water supply to near by
villages.