15
Trim: FSYD2020/319372 Sydney Trains Electricity Distribution Network Safety Management System Performance Report 2019 - 2020

Safety Management System Performance Report

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Trim: FSYD2020/319372

Sydney Trains Electricity Distribution Network

Safety Management System Performance Report 2019 - 2020

Sydney Trains Electricity Network ENSMS Performance Report 2019-2020

Version control

Version Date Comment

1.0 16 October 2020 First issue

Electronic File reference: /Users/nickloveday/Desktop/Work Docs/Annual Regulatory Reporting/2020 reports/Sydney Trains Electricity Network Performance Report 2019-2020.docx

Sydney Trains Electricity Network ENSMS Performance Report 2019-2020

Contents 1. Annual Performance Report 1

1.1. Introduction 1 1.2. Context 1 1.3. High-voltage distribution network scope 1 1.4. Data source 1

2. Summary of Performance Statistics — 2020 1

Table A.1 - Major Incidents 3 Table A.2 — Safety Incidents 4 Table A.3 - Network asset failures 4 Table A.4 - Vegetation contact with conductors 5 Table A.5 - Unintended contact, unauthorised access and electric shocks 5 Table A.6 & A.7 — Reliability and Quality of Supply 7 Table A.8 - Network-initiated property damage events 7 Table A.9 - Amendments and improvements to Formal Safety Assessments

(FSA) or Associated Risk Treatments 8 Table A.10 - Design, construction and commissioning 8 Table A.11 - Asset Inspections 8 Table A.12 — Inspections (vegetation) aerial or ground based 9 Table A.13 — Public electrical safety activities 9 Table A.14 — Internal audits performed on any aspect of the ENSMS 9 Table A.15 — External audits performed on any aspect of the ENSMS 10

3. Notes 11

3.1. Glossary 11 3.2. Referenced Documents 11

Appendix A — Endorsement 12

Electronic File reference: /Users/nickloveday/Desktop/Work Docs/Annual Regulatory Reporting/2020 reports/Sydney Trains Electricity Network Performance Report 2019-2020.docx

Sydney Trains Electricity Network ENSMS Performance Report 2019-2020

1. Annual Performance Report 1.1. Introduction This report presents the performance achieved by Sydney Trains' Electricity Network Safety Management System (ENSMS) for the calendar year ending 30th September, 2020. This report is produced in accordance with the Electricity Supply (Safety and Network Management) Regulation 2014 and is based on the template provided by the regulator (IPART) in Appendix A of their Electricity Networks Reporting Manual, September 2020.

1.2. Context Sydney Trains is the operator and maintainer of the electric passenger heavy-rail network throughout the greater metropolitan Sydney region as shown on Sydney Trains website at https://www.transport.nsw.qov.au/svdneytrains.

As an essential part of this enterprise, Sydney Trains operates a high-voltage electricity distribution network which provides reliable power to the railway assets including traction for the rolling stock, signalling and other infrastructure necessary for the safe operation of the railway.

In this context the "customer" is the railway network operation - Sydney Trains does not supply electricity to retail customers outside the rail corridor.

1.3. High-voltage distribution network scope The high-voltage distribution network comprises of the electricity assets between "bulk supply points" (where electricity is received from the major network providers) and the equipment supplying traction power (1500VDC) and low-voltage.

Note: This report excludes incidents and statistics for assets that do not form part of the high-voltage distribution network, such as:

• 1500VDC traction assets,

• Rolling stock and all non-rail infrastructure, signalling, voice/data communications systems and facilities.

1.4. Data source The performance statistics are extracted from Sydney Trains Enterprise Asset Management (EAM) system for the year ending 30th June 2020. Sydney Trains adopted EAM effective 1 July 2017 and consequently some legacy data is no longer available prior to that date. EAM is a single system developed to satisfy the needs of the whole railway enterprise and support long-term trend analysis; hence there are limitations on the data available for this report and in some tables the categorisations used do not entirely match those in the !PART manual.

2. Summary of Performance Statistics 2020 Incident statistics are reported in four groups as required by the !PART Reporting Manual, as follows:

Tier 1 and Tier 2 performance measures, which are lagging indicators, align with the network operator's incident reporting requirements and the objectives of the ESSNM Regulation. They are relevant to all network operators and reflect the outcomes achieved from the actions taken to manage risks associated with the regulatory objectives.

Tier 3 and Tier 4 performance measures, which are leading indicators, are also aligned with incident reporting requirements (where applicable) and are intended to monitor the risk controls that each network operator has put in place as articulated through its SMS Formal Safety Assessments. Tier 4 measures are leading indicators that monitor operational

Page 1 of 12

Sydney Trains Electricity Network ENSMS Performance Report 2019-2020

activities associated with maintaining the control environment. Tier 3 measures are leading indicators that signal the potential for a Tier 1 or 2 incident to occur.

Major incident

(eg. asset failures with major

consequences (eg, bush fire))

Minor incident (eg, asset failures with minor consequences

(eg, fee starts))

Significant i Tier 1 reportable incident

Tier 2 Reportable consequence realised

4. Near miss

(eg asset failures without consequence)

Tier 3 Barrier failure

Safety Management System non-compliances (eg, controls not

implemented Of delivered)

Tier 4 Process failure

Tier Refer Summary of Performance Statistics —2020

1 Major incidents with consequences >$500k

Table A.1 1 major incident — poles destroyed by external bushfire near Mt Victoria- Blackheath (Gospers Mountain fire) December 2019-January 2020.

2 Minor incident - reportable consequence realised

Table A.2 None

3 Barrier failure — asset failures without consequence and control failure near misses

Tables A.3 — A.6

4 Process failure — controls not implemented or delivered

Tables A.9-A.15

Page 2 of 12

Commentary Discipline Meet

BLUE MOUNTAINS BUSHARE RECOVERY PROGRAM 12/02/2020 Number of Repaired /

Inspected Tested Damaged Assets Replaced Outstanding Cfsmaged

6 0 1

1 1

Corms Cable Sections • Rbre 12 12 12

2 1 1

75 75 0

Traffic Hut 1 1 0 1

Sleepers (Up and Down 82,000 82,000 NA SO SO 0 Main)

Turnouts 28 28 20 1 1 Poles 716 716 120

541 461

HVConductors (in) 256,300 256,300 N/A 37,000

OHW DC Conductors (m) 54,000 54,000 N/A 0 1500V

Section Hut 4 4 1 3 3 Substation 2 2 0 1 1 Distribution Locations 40 40 35 40 35 Trees 1000 1000 N/A

1 1 NewnesSubstation

The following table summarises the extent of the damage to railway assets as assessed at 12th February 2020. The rail corridor was closed and rail replacement bus services were implemented on 21 December between Lithgow and Mount Victoria, with rail services resuming on Tuesday 21 January.

Embankments /cuttings 35 35

100 Not to be replaced (higZai)

0

Tested Uthgow and Newnes Junction

10 A pole was recently identified with bums to the heed, this Is being assessed.

O Components were repaired or replaced associated with conductor

75 Minor damage

SO 110% repairs completed

100 AfechanIcal damaee does not require testing

54 Number of trees inspected unknown and uncountable

27,000 0 14

Total 395,193 394,834 837

Page 3 of 12

Signalling

Track

Track

Electrical

Elechical

Electrical

Electrical

Electrical

Electrical

Vegetation

Geotech Heritage

Cornms 25 2 2 25 25

Comma

Comms Comma

Comms

6

310 7

7

3

170 7

7

3

170 7

7

Comms 4 2 2 2 0 0 0 New number is 6 • additional required to get coverage In Zig Zag

33

10

0

11

30

a 11

4

54

158

8

5

56

30

6

23

130

205

45

32

40

130

205

53

53

44

184

363

53

53

Signalling

Signalling

Signalling

Signalling

Signalling

8 Power pending born 11ilv

SO 50,000M to be replaced R5 from Risk Registw

17 3,500m to be replaced

0 O Power pending from Edgecombe

14 Power Pending

DTR5

Cable Sections. Copper

Pits

Cornms Rooms

Zen worksite Repeater Systern

WS Ftadlo

0

3

140 0

Signals Track Circuit Ends

MulticoreCables

Point Ends

Locations 4 2 locations completely damaged Edgecombe remaining

Sydney Trains Electricity Network ENSMS Performance Report 2019-2020

Table A.1 - Major Incidents

Tier 1 incidents are defined as a 'Major Incident' in accordance with the Electricity networks reporting manual — Incident reporting (Reporting Manual - Incident Reporting).

ESSNM Objective

Description of each major incident reported

Safety of members of the public None

Safety of persons working on the network None

Protection of property Third-party property None

Network property A One - During December, the Gospers Mountain Thegafire' caused extensive damage to a 25km stretch of the Blue Mountains rail line, particularly to power, communications and signalling infrastructure.

No external property or lives affected.

Safety risks arising from loss of electricity supply B None

Notes:

A. For the purpose of this report, a "major incident" involves losses exceeding $500,000 in relation to damage caused to electricity works as defined in the IPART Reporting Manual.

B. As defined for major reliability incidents in IPART's Reporting Manual incident reporting requirements

Sydney Trains Electricity Network ENSMS Performance Report 2019-2020

Table A.2 — Safety Incidents

Tier 2 incidents are defined as an 'Incident' in accordance with the IPART Reporting Manual - Incident Reporting.

ESSNM Objective

Description of each major incident reported

Safety of members of the public 0 None

Safety of persons working on the network 0 None

Protection of third party property 0 None

Safety risks arising from loss of electricity supply 0 None

Table A.3 - Network asset failures

Performance Measure Population

5-year average annual

functional failuresA,F

Annual functional failures for reporting period

UnassistedA Assisted'

No fire

Fire N o

fire

Fire

Contained Escaped Contained Escaped

Towers 0 0 0 0 0 0 0 0

Poles (including street lighting columns/poles & stay poles) 12477 8 2 0 0 0 0 0

Pole-top structures N/A 25 1 2 0 2 0 0

Conductor - HV OH (including sub-transmission) A, B, C 921km 3 4 1 0 2 0 0

Conductor- HV UG (including sub-transmission) A ' C 403km 3 o 0 0 3 0 0

Conductor - LV OH" N/A 10 1 0 0 0 0 0

Conductor - LV UGA, c N/A 3 0 0 0 1 0 0

Power transformers° 286 3 0 0 0 0 0 0

Distribution transformers 284 2 0 0 0 0 0 0

Reactive plantE 89 4 0 0 0 0 0 0

Switchgear - distribution (Overhead) 0 1 0 0 0 0 0 0

Switchgear - distribution (Ground based) 1234 16 2 1 0 7 0 0

Protection relays or systems 2698 8 0 0 0 6 0 0

Substation SCADA system 260 8 0 0 0 0 0 0

Protection Batteries 1170 4 0 0 0 2 0 0

Page 4 of 12

Detail Event count

2016

Event count - Current reporting

period

Event count Event count Event count 2019 2018 2017

/A

/A

/A

/A

/A

/A

/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

Electric shock and arc flash incidents

Public 0 0 4 I

[ I

)

Public worker 0 0 0

Network Employee / contractor 3 4 4

Accredited Service Provider 0 0 0 I

Livestock or domestic pet 0 0 1 I

Contact with energised overhead equipment

Public road vehicle 2 2 1 I

Plant & equipment 3 2 3 I

Agricultural or other 1 0 0

Network vehicle 0 0 0 I

Contact with energised underground equipment

/A N/A

/A N/A

Sydney Trains Electricity Network ENSMS Performance Report 2019-2020

Notes:

A. Refer Glossary for definitions and acronyms.

B. Transmission and sub-transmission voltages are generally 33kV AC nominal and above. Transmission conductors form part of a transmission network. Sub-transmission conductors form part of a distribution network.

C. Overhead service and underground service as defined in the NSW Service and Installation Rules.

D. Power Transformers are transformers where the secondary/output voltage is 5kV nominal or above.

E. Reactive plants are reactors and capacitors.

F. Average based on actuals for the past 5 years.

In 2019-2020 the notable asset failures include:

• 2 incidents of live conductors failing and falling on the ground, with no adverse consequence, and

• 2 failures of pole-top equipment causing fire ignitions, resulting in minor damage to the pole.

• 2 substation circuit breaker failures.

Table A.4 - Vegetation contact with conductors Event count -

Performance measure Current reporting period

Event count 2019

, Event count Event count Event count

2018 2017 2016

Fire starts - grown in 0 0 iii. N/A N/A

Fire start - fall in and blow in 0 0 0 !.. N/A N/A

N/A N/A

N/A N/A

Interruption - grow in 1 8 7

Interruption - Fall in and blow in 1 2 4

Table A.5 - Unintended contact, unauthorised access and electric shocks

Page 5 of 12

2017 2016 2019 2018

N/A

N/A

N/A

N/A

N/A

N/A

N/A N/A

Plant & equipment 2

Person with hand tool 3

Unauthorised access

Distribution Substations 4 10 8

Towers/poles 2 4 0

Other (eg communications equipment)

0 0 0

Safe Approach Distance

Structure/materials infringing SAD / EasementA

3 2 3

Network employee / contractor 4 3 3

Public 0 0 0

Public worker 0 2 0

TOTAL 23 32 28

N/A N/A

N/A N/A

N/A N/A

Event count Current reporting

period

Event count Event count Event count Event count Detail

Sydney Trains Electricity Network ENSMS Performance Report 2019-2020

Notes:

A. Includes structures, materials, containers constructed or placed infringing the safe approach distance or

easement as described in IS5C20.

Summary

In 2019-2020 the near-miss incidents include:

• 6 incidents of unauthorised access to poles and substations involving copper theft;

• 3 incidents involving structures or materials erected or placed under aerial lines or in easements contrary to ISSC20;

• 2 incidents of public vehicles striking poles

• 2 Configuration management errors

• 2 Operator errors (wrong asset/wrong action)

• 1 Structure erected/placed under aerial lines

• 1 Contractor exposing live buried cables

• 1 Design defect - inadequate safe clearance for maintainers

• 1 LV cable struck by excavator

• 1 LV cable cut by worker

• 1 Worker receiving an electric shock from a lighting strike

• 1 Worker infringed SAD

• 1 Working without Electrical Permit

• 1 Electrical Permit with persons not signed on, and

• 1 Worker minor injury (non-electrical).

Page 6 of 12

Detail Event count -

Current reporting period

Event count 2019 Event count Event count Event count

2018 2017 2016

Third party property (assets including vehicles, buildings, crops, livestock)

0

Network property (including non-electrical assets, vehicles, buildings)

Damage (e.g. Fire, physical impact or 0 electrical)

0 0 N/A N/A

Damage (e.g. Fire, physical impact or electrical)

0 0 N/A N/A

Sydney Trains Electricity Network ENSMS Performance Report 2019-2020

Structure/materials infringing SAD / Easement

In recent years Sydney Trains has noted a number of incidents involving:

• Materials and structures located under aerial lines, on easements or against substation perimeter fences;

• Changes made to the terrain under aerial lines, compromising the safe approach distance;

• Changes of use of pre-existing structures (predating ISSC20) which would cause large numbers of people to congregate in a location at risk in the event of a conductor failure.

Some of these have triggered the relocation of the aerial line, or the constructor/owner has been directed to remove the structure or materials, at significant cost. Sydney Trains requires all new or modified structures near aerial lines to comply with the constraints defined in ISSC20.

Table A.6 & Al — Reliability and Quality of Supply Sydney Trains does not collect data in respect of quality of supply for the high-voltage distribution network as the system is inherently dedicated to supplying the railway (i.e. signalling and rolling stock) and the railway has its own standards for those which differ from consumer electricity standards.

Network reliability is measured in the form of "delay-minutes" to rolling stock for the 1500VDC supply to rolling stock; these events pose a business risk, not a safety risk. Short disruptions in the 1500VDC supplies to signalling and rolling stock are frequent events (daily) and the network includes redundancy to accommodate these with no operational impact.

Table A.8 - Network-initiated property damage events

Note: Table A.8 excludes Sydney Trains network assets damaged by external bushfire; that data is provided at Table A.1.

Page 7 of 12

Sydney Trains Electricity Network ENSMS Performance Report 2019-2020

Table A.9 - Amendments and improvements to Formal Safety Assessments (FSA) or Associated Risk Treatments

FSA Amendment / Improvements

Safety risks arising from Loss of Supply

Revised to include external references concerning the estimated likelihood of loss of supply, and systemic causes & controls

Safety risks to Workers and Public Revised to include systemic causes & controls

Safety risks arising from Bushfire Rewritten, external audit conducted in October 2020.

Table A.10 - Design, construction and commissioning

Performance Measure

Event count - Current

reporting period Event count 2019

Event count Event count Event count 2018 2017 2016

Project closeout reports completed

Project closeout reports audited

78 47 3 N/A N/A

0 1 2 N/A N/A

The design and implementation of Sydney Trains electrical projects may be undertaken internally or outsourced; that design is based on factors such as resourcing, scheduling constraints and the backlog of work assigned to external contractors; it is not "contestable" in the sense used by IPART.

Only "Type Approved" equipment may be used for the design, construction and maintenance of Sydney Trains assets and standard designs are used for most installations; this simplifies the safety assurance task considerably. Deviations are treated as new designs, including a safety hazard assessment in each case.

The Electricity Distribution Unit inspects all electrical installations prior to energisation.

Table A.11 - Asset Inspections

Asset tasks - by bushfire risk priority Region

10 (worst) z° 3-4'

North - Central Coast

Open 0 0 62

Outstanding 0 0 0

Blue Mountains

Open 0 0 102

Outstanding 0 0 21

South & Illawarra

Open 0 0 9

Outstanding 0 0 0

Metropolitan

Open 0 0 0

Outstanding 0 0 0

Defects - Total 0 0 ' 194

Page 8 of 12

Sydney Trains Electricity Network ENSMS Performance Report 2019-2020

Notes:

a Category 1 Defects: Refers to defects that are to be completed between 1-7 days. b Category 2 Defects: Refers to defects that are to be completed between 8-31 days.

Category 3+4 Defects: Refers to defects that are to be completed after 31 days or more.

As at 30 September there are no open or outstanding asset maintenance tasks in priority 1 or 2 locations, ie they are 100% complete. All tasks are planned for completion by 15 December.

Table A.12 — Inspections (vegetation) aerial or ground based

Performance measure Population Target (Feeders) (poles)

Achieved Outstanding Comments

Inspections—North Region 31 Feeders 2179 2179 0

Inspections — Blue Mountains _ 22 Feeders 2052 2052 0

Inspections — South & Illawarra 13 Feeders 753 753 0

Inspections - Metropolitan 0 Feeders 0 0 0

Inspections - Total 129 Feeders 4984 4984 0

Sydney Trains has completed its inspection program as at 30th September, with zero inspections outstanding.

Table A.13 — Public electrical safety activities Network operator public

safety programs! campaigns Details

Public Safety SP D 79038 V1.0 Sydney Trains Electricity Distribution Network Public Safety Awareness Plan prepared.

Look-Up & Live Sydney Trains is aware of the Look-up & Live website and is reviewing arrangements to contribute to this initiative

Table A.14 — Internal audits performed on any aspect of the ENSMS

Audit scope Identified nonconformances Actions

1 internal audit in 2019-2020 on AEO Authroisation and Accreditation Requirements

Lack of full awareness of all statutory requirements

Briefings held and requirements published on RAILSAFE

Page 9 of 12

Audit scope Identified nonconformances

Actions

Creation of a suite of FSAs to demonstrate that risks associated with all primary objectives are reduced to ALARP, where at the time of the 2018 audit a Formal Safety Assessment (FSA) had only been developed for bushfire risks.

Development of the Electrical Risk Register (ERR) to provide explicit and complete demonstration of the primary objectives of ESSNM.

Improved documentation of links between interfacing systems, processes and procedures to the ENSMS.

FSAs published internally (refer table A.9):

• Safety risks arising from Loss of Supply

• Safety risks to Workers and Public

• Safety risks arising from Bushfire

Electrical Risk Register converted to corporate Bow-Tie format

Single integrated dataset supports all FSA's.

Electrical Risk Register continues to evolve as causes, controls and evidence of implementation are identified.

September 2019:

ENSMS contents, processes and supporting procedures were appropriate and adequate to fulfil the requirements of the ESSNM, and the obligations sub-imposed by AS 5577

Sydney Trains Electricity Network ENSMS Performance Report 2019-2020

Table A.15 — External audits performed on any aspect of the ENSMS

(Remainder of page left blank)

Page 10 of 12

Sydney Trains Electricity Network ENSMS Performance Report 2019-2020

3. Notes 3.1. Glossary The following abbreviations, acronyms and definitions are used in this report.

AS Australian Standard

assisted failure a functional failure of a piece of equipment where the equipment was subject to an external force or energy source against which the standards for design and maintenance do not attempt to control (see also unassisted)

EAM Enterprise Asset Management (system), a whole-of-business data system adopted by Sydney Trains

ENSMS Electricity Network Safety Management System ESSNM Electricity Supply (Safety and Network Management) Regulation 2014

FSA Formal Safety Assessment

HV high voltage, nominal voltage lkV AC and above IPART Independent Pricing and Regulatory Tribunal of NSW, a state government

authority

LV low voltage, nominal voltage below lkV AC, nominal N/A Not Available / Not Applicable

OH overhead overhead as defined in the NSW Service and Installation Rules service

power transformers where the secondary/output voltage is 5kV nominal or above transformers

reactive plants Includes reactors and capacitors

SAD Safe Approach Distance

TfNSW Transport for New South Wales, a state government authority UG underground unassisted a functional failure of a piece of equipment where the cause of the failure is failure neither an assisted failure nor a maintenance-induced failure. underground as defined in the NSW Service and Installation Rules service

WHS Workplace Health & Safety

3.2. Referenced Documents

Electricity Supply (Safety and Network Management) Regulation 2014

Electrical Networks Reporting Manual, IPART, August 2018

AS5577-2013 Electricity network safety management systems

ISSC20 Guideline for the Management of Activities within Electricity Easements and Close to Electricity Infrastructure

Page 11 of 12

Sydney Trains Electricity Network ENSMS Performance Report 2019-2020

Appendix A - Endorsement

Annual ENSMS Performance Report for 2019-2020

Submitted by Sydney Trains ABN 38 284 779 682

To: The Chief Executive Officer Independent Pricing and Regulatory Tribunal PO Box K35 Haymarket Post Shop NSW 1240

Sydney Trains reports as follows:

1. This report documents the performance of Sydney Trains Electricity Network Safety Management System during the year 2019-2020 with all obligations to which Sydney Trains is subject to under the Electricity Supply (Safety and Network Management) Regulation 2014.

2. This report has been prepared by Sydney Trains with all due care and skill in full knowledge of conditions to which it is subject and in compliance with IPART's Electricity Network Reporting Manual.

3. This report provides information on all obligations with which Sydney Trains did not fully comply during the financial year 2019-2020.

4. This compliance report is approved by the Chief Executive:

Name. Suzanne Holden

Designation: Chief Executive

Page 12 of 12