View
27
Download
1
Tags:
Embed Size (px)
Citation preview
SAFETY PRECAUTIONS DURING MARCH’09
SHUT DOWN
PRESENTED BY,
Mr. Jahanzeb Khan
Date: 07.03.11
KRIBHCO SHYAM FERTILISER LTD.
AMMONIA PLANT COMMISSIONED ON 22/11/1995
REASSESSED CAPACITY 1520 MTPD (w.e.f. 01/04/2000)
TECHNOLOGY HALDOR TOPSOE
UREA PLANT
COMMISSIONED ON 23/11/1995
REASSESSED CAPACITY 2 X 1310 MTPD
(w.e.f. 01/04/2000)
TECHNOLOGYSNAM PROGETTI
ATR- March 2009
Duration- 19.5 Days Dates
-Start of shut down : 13/03/2009
-Urea one unit production : 31/03/2009
-Ammonia production : 01/04/2009
-Urea 2nd unit start up : 01/04/2009
Ammonia Plant
-Primary reformer tube & catalyst replacement.
-Secondary reformer job
-RG Boiler job
-HTS Catalyst job
-Synthesis gas turbine overhauling
-Ammonia converter jobs
-Synthesis loop boiler Replacement
MAJOR JOBS
Energy saving Schemes
Ammonia Product Heater installation PR NG Fuel pre heating PAC discharge line modification CAPH duct modification Ammonia Plant DCS replacement
Urea Plant
Urea reactors and stripper inspection Exchangers cleaning Blow down and vent stack pipe replacement HP passivation air compressor installation Prilling Tower epoxy coating Bentley Nevada vibration monitoring system
hook up
Offsites
CT return header shifting Job GTG-I Generator overhauling
Why Annual Turnarounds ????
ATR, a planned activity- annually or biannually Annual turnarounds for:
-Jobs – Breakdowns, repairs, overhauls, improvements, modifications etc-Statutory compliances-Cleaning of equipment
-Catalyst loading, washings, internal repairs -Inspections and testing of equipment & machines -
Adding new equipments -Up gradations & replacements
Shutdown job lists
ATR job list include -Uncompleted jobs from the previous ATR
-Jobs identified during the entire year-Special inspections – statutory, testing, improvements-Jobs out of analysis reports – NDT, tech suppliers, OEMs-Jobs that can be only done during utilities stoppage-Jobs on vessels for catalyst change, cleaning, repairs etc
Jobs Planning
Job lists reviewed on monthly basis between departments
Unique job number for each job which gets frozen All jobs are identified & tagged in field before ATR Each job planned – manpower, material & timelines Bar chart for major planned jobs Spacing of jobs as per vendor availability Risk assessment for each job by process &
maintenance No job done without a permit
Material / Spares planning
Done well in advance – ATR material separately identified
Early orders for each critical items & OEM supplies All temporary lines, fittings, structures - pre fabricated Prior testing & overhauling of equipments like Cranes, forklifts, lifting tools etc Access equipment, hydraulic platforms etc Portable tools like grinders, drills, welding machines etc Advance availability of materials & tools from
contractors
Services planning
Advance intimation of the ATR dates to all Pre visits of service providers for job understanding Tests for skilled workers conducted – welders,
riggers etc Clear guidelines for safety in job execution Safety training given in advance to all external work
force
Annual Turn Around – Job Cycle
Start
Preparation of ATR job list
Meetings between Production & Maintenance functions to finalize the Shut Down Manual.
Check the Risk Assessments
Identify the Safety Guide lines / PPE requirements
Inputs:
Maintenance repairs
Inspections
Process requirements
NDT recommendations
Cleaning
Carry out risk assessment
Continued ……
YES
No
JOB CYCLE…. Continued
Include all Guide line in Shut Down Manual against Each Job.
Hand Over the S/D Manual to all Concerned Dept. /Section/ Persons
Stoppage, Isolation and Purging of Equipments as Per SOP
Issue the SWP for Maintenance crew
Return all SWP after completing
the Job to S/I
Updation on SAP
Trial Run by Production
Carry out the job with full Adherence of SWP
Guidelines
Process Planning – Shutdown Manual
A Comprehensive Process Handbook which includes: Schedule of shutdown & start up Detailed job lists (Area wise) & Bar chart for major jobs Risk assessment of each activity Procedures for Shutdown of each section Special activities - hydro testing, catalyst replacement,
cleaning Purging of sections & checklist of major maintenance jobs with sketches Critical inspections & vessel entry Start up of utilities & each sections
Safe Work Procedures
A safe work procedure can be defined as the written instruction of a task/activity outlining the preferred method whilst emphasizing ways to minimise any risk(s) of harm. A safe work procedure outlines the hazards, risks and associated controls measures to be applied to ensure the task/activity is conducted in a way to reduce the risk of injury.
DEVELOPMENT
Safe work procedures should be developed for all tasks/activities, processes, and the operation of equipment and machinery, where a risk assessment identifies the requirements as a suitable control measure to reduce the risk of injury.
PROCESS STEPS
To aid in the development of a safe work procedure the following steps should be followed:
Step 1. Observe the task or process;Step 2. Record the sequence of basic job stepsStep 3. Assess potential hazards of each stepsStep 4. Review associated legislative
requirements
Step 5. Assess the risk of Hazards;
Step 6. Suggest ways of eliminating and controlling the hazards;
Step 7. Test the procedure by consultation and verify relevant issues are documented
Step 8. Obtain approval of the procedure from a supervisor or manager.
In determining potential hazards in a task or process the following factors could be considered
Is there exposure to noise, fumes or dust? How can equipment fail in any way? Is the work physically strainers? Is the work made harder by external factors ( climate,
noise etc.)? Is there enough space to move about? Can the person be caught in, on or between anything
Can the person be struck by or contacted by anything while doing this step of the job
Do loads need to be lifted/or handled? Can the person slip or trip or fall What level of supervision is required? Is the work made harder by the way it is organised ? Is there any requirement specified in relevant legislation?
PRIORITIES
It is recognized that, in some areas, the preparation of safe work procedures may take some time.
The priorities for the preparation of safe work procedure should be:
All new task where there is a high to medium risk should have safe work procedures prepared before they are put into general use;
For existing processes, safe work procedures for high risk tasks should be prepared first, followed by medium and low risk tasks;
Safety Systems in ATR
Safety of Man, Machine & Equipment – Top Priority No job without Risk assessment & Scheme / procedure No job without Safety Permit All class 1 permits - Inspected by Safety officer Additional process people posted as safety officers Safety observers – Internal & External Cross functional inspection teams for entry & box up of
each Vessel Check lists and sign-offs for each inspection Registers for blinds / vessel entry with sign-offs
Safety in ATR
Training Communication of safety norms to all personnel Safety talk every morning & before start of each job
Contractors Medical tests before jobs Training & tests on job execution Checking & certification of all new equipment brought to site 100% adherence to use of PPEs Proper arrangements for rescue - availability of crane, ambulance & constant watch on working personnel inside the
vessel
Checking of Safety Systems & Logics
Each component of safety logic is checked Trip switches, transmitters, vibration probes & other
key elements are removed, calibrated & installed back
After installation all Trip interlocks cross checked through manual simulation
Stroke checking of ALL control valves Calibration of all critical PSVs Hydro test of all critical exchangers
Start up
Systematic leak check - initially with IG at lower pressure then at operating pressure
For each activity like purging, filling, start up etc A documented procedure cum check list Optimum utilization of trained manpower for different
activities Comparison of efficiencies – machines, reactors, exchangers, catalysts performance etc
Shutdown Report & Records
Shutdown report includes: Planned vs. actual timings for major activities Details of key jobs done Section wise observations of inspections & repairs Surprises Analysis & improvements achieved Observations regarding safety & environment lapses Identification of area of improvements Learning & best practices observed
AFTER ATR
AMMONIA PLANT CAPACITY : 1725 TPD
UREA PLANT CAPACITY : 2825 MTPD
ON STREAM DAYS : 350
ANNUAL UREA PRODUCTION : 988750 MT
THANK YOU