Upload
rogeema-kenny
View
116
Download
1
Embed Size (px)
Citation preview
Electricity Markets in South Africa16 October 2015
Presented by:
Rogeema Kenny
Presentation Content
• South Africa and Eskom overview• Generation Mix• Facts & Figures• Challenges– Energy theft– National power crisis
South Africa Eskom• Southern tip of Africa• 6 land neighbours• Atlantic and Indian Ocean• Consumes 45% of Africa’s
power• GDP per capita - $ 5,784• #1 on GINI index
• Founded in 1923• Public company in 2002• Generates 45% of electricity
in Africa• Regulated by NERSA• 42,000 MW nominal
generation capacity• 5.5 million residential
customers• 138 k other customers
Standard ratings
• Frequency – 50 Hz• System voltages– Transmission• 400 kV national grid• 765 kV, 800 kV HVDC
– Distribution• 132 kV, 66 kV
– Reticulation• 33 kV, 22 kV, 11 kV, 400 V, 230 V
Production & Consumption
Seasonal load profiles
Challenges – Energy theft
Efforts to curb tampering
Customer interface unit on customer’s property
Metering units (12) in vandal-proof, locked steel kiosk outside on sidewalk
Efforts to curb tampering
Customer interface unit on customer’s property
Metering units (12) in vandal-proof, locked steel kiosk outside on sidewalk
Interventions to combat theft
• Public awareness• Tipoff lines• Tamper fines • Repeat-offence penalties• Prosecution of offenders• Stricter monitoring
SA Power Crisis - HistoryEarly 1990’s – Eskom
foresees new capacity requirements for
2005-2008
Govt opts to bring external players to the
power market
No external parties show interest in investing in new
generation capacity
2005 – Permission is granted to Eskom to add more generation
2007/2008 – SA experiences rolling
blackouts
SA Power Crisis - Consequences
• 2007 – rolling blackouts• Quick fix generation needed• New Build program• Above average tariff increases (tariffs were not
cost-reflective)• Aggressive DSM initiatives – rooftop solar
subsidies, free CFL replacements• Aggressive renewable energy targets
SA Power Crisis - progress
• Medupi unit 6 synchronised to grid• Kusile synchronisation – late 2017• 100 MW Sere wind farm complete• 1,332 MW Ingula pumped storage – fully
operational by end 2015• REIPP program – up to 3,725 MW