S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

Embed Size (px)

Citation preview

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    1/100

    Brian ParsonsFebruary 19, 2013

    Overview of the

    2012 AASHTO BikeGuide

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    2/100

    2009 MUTCD FHWA

    Public Right-of-Way

    Accessibility Guidelines

    (PROWAG)

    2010 Highway Capacity

    Manual

    Relationship to other manuals

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    3/100

    NCHRP - National Academy of

    Sciences

    Scoping Study: 2004-2006

    Preparation of the content of the

    4th Edition: 2007-2009

    Final edits/State DOT balloting

    process: 2010-2012

    How the Guide was

    developed

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    4/100

    How the AASHTO Bike Guide is

    usedState DOTs

    Some adopt the Guide

    Some use it to create their own

    versions

    Local Jurisdictions Use AASHTOs version

    Use the States version, or

    Develop own version

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    5/100

    Guide expanded from 75

    pages to over 200 pages

    3 chapters to 7 chapters Sold 1200 copies in the first

    month

    Release of the guide June

    2012

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    6/100

    Chapters

    Chapter 1: Introduction

    Chapter 2: Bicycle Planning

    Chapter 3: Bicycle

    Operation and Safety Chapter 4: Design of On-

    Road Facilities

    Chapter 5: Design of Shared

    Use Paths

    Chapter 6: Bicycle Parking

    Facilities

    Chapter 7: Maintenance

    and Operations

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    7/100

    Chapters

    Chapter 1: Introduction

    Chapter 2: Bicycle Planning

    Chapter 3: Bicycle

    Operation and Safety Chapter 4: Design of On-

    Road Facilities

    Chapter 5: Design of Shared

    Use Paths

    Chapter 6: Bicycle Parking

    Facilities

    Chapter 7: Maintenance

    and Operations

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    8/100

    Guidance on how tochoose bikeway type

    Affirms lane diets and

    road diets Expanded bike lane

    guidance

    Major changes in 2012 Guide

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    9/100

    Expanded signalguidance

    Expanded shared use

    path guidance(including paths

    adjacent to roads)

    Major changes in 2012 Guide

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    10/100

    No differentiation of

    what type of bikeway

    was appropriate given

    roadway characteristics

    Choosing bikeway type 1999

    Guide

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    11/100

    Detailed guidance on facility

    selection

    Support for bike lanes and

    shared use paths wherevolumes and speeds are

    higher

    Warnings against using wide

    outside lane as a standard

    treatment for high volume

    roads

    Choosing bikeway type 2012

    Guide

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    12/100

    Permission tonarrow lane

    widths to create

    bike lanes

    10 and 11 wide

    travel lanes are

    acceptable

    Roadway retrofit

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    13/100

    Provides guidelines for road diets

    Road diets

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    14/100

    Nuanced guidance on widths (4 to 7feet)

    Measures to reduce crashes with

    car doors

    Bike lanes adjacent to back-in angleparking

    Bike lanes at roundabouts

    Buffered bike lanes

    Green bike lanes, etc.

    Bike lanes

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    15/100

    Old Guide weak

    New Guide strong

    Detailed guidance on all

    aspects of signal design

    Signal design

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    16/100

    Shared use paths

    Extensive intersection

    design guidance

    Major change: paths next to

    roads are not forbidden,

    provides guidance on how

    to design them

    AASHTO NACTO G id

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    17/100

    AASHTO covers design comprehensively

    AASHTO covers paths + on-road

    bikeways

    AASHTO covers many but not all

    innovations

    NACTO is a source of information for

    solutions that are currently being tested

    AASHTO vs. NACTO Guides:

    either/or?

    h h

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    18/100

    Bike lanes

    Cycle track design

    One-way protected cycle tracks

    Raised cycle tracks

    Two-way cycle tracks

    What is in the NACTO

    Guide?

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    19/100

    Bike boxes and other

    intersection designs (including

    non-standard)

    Colored pavement material

    guidance

    Bicycle boulevards

    What is in the NACTO Guide?

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    20/100

    NACTO Illustrations of bikeway

    types

    Wh t i NOT i th NACTO

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    21/100

    Planning for bicycles

    Bicyclist operating characteristics

    Geometric design values and details

    Shared use path design Bridges

    General road compatibility with bicycles

    Bike parking

    Maintenance

    What is NOT in the NACTO

    Guide?

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    22/100

    Bike boxes Bicycle signal

    heads

    Does not use the

    term cycle track Warns against

    putting bike lane

    between parking

    lane and curb

    Issues NOT addressed by AASHTO

    Guide

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    23/100

    Example: Two-Way Cycle track 15th Street

    Washington, DC

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    24/100

    One way cycle track 9th AvenueNew York City

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    25/100

    Questions?

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    26/100

    Brian Parsons

    Louisiana Pedestrian/Bicycle

    Coordinator

    (225) 379-1954

    [email protected]

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    27/100

    Local Public Agency Programs

    Partnering to Improve the Quality of

    Life for Louisianans

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    28/100

    Agenda

    Actions for Partnering to Improve the

    Quality of Life for Louisianans

    The Manual Training

    The Agreement

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    29/100

    How it started

    Nationally, FHWA reviews found significant

    issues with LPA administered projects across

    the country

    Process review on the LA Urban System

    Program by FHWA, April 2010, identified

    several LPA risk areas

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    30/100

    What is an LPA?

    A Local Public Agency (LPA) includes: Parish Government

    City Government

    Municipal Government

    Airport Authorities

    ***all of the above are also referred to asEntity in legal agreements

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    31/100

    Where to go for

    help?

    The Local Public Agency

    (LPA) Manual and Appendixhttp://www.dotd.la.gov/administration/lpa/

    http://www.dotd.la.gov/administration/lpa/http://www.dotd.la.gov/administration/lpa/
  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    32/100

    LPA Manual Highlights

    Put together in 2011 by DOTD & FHWA as a

    tool to assist LPAs to fulfill the requirements of

    implementing a transportation project

    One stop shopping for all information on

    programs and projects that LPAs can apply for

    Will be updated for MAP-21

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    33/100

    Sections of the LPA Manual

    DOTDs Project Delivery Process and Flowchart

    FHWA Programs & Fact Sheet links

    How projects in each of the programs are

    selected and programmed

    Specific Program Information

    Frequently Asked Questions

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    34/100

    Sections of the

    LPA Manual Appendix

    Acronyms/Abbreviations & Definitions

    FinancialAudit & accountability, billings/payments

    PlanningStatewide, regionally significant

    EngineeringAgreements, number system, process forlarge projects, design, survey & right-of-way, utility

    relocation, preservation projects, traffic management plan(TMP), pavement & geotechnical

    S i f h

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    35/100

    Sections of the

    LPA Manual Appendix

    (cont.)

    ConstructionConstruction engineering & inspection

    (CEI), close-out procedures

    MiscellaneousWeb information, permits, Americanswith Disabilities Act (ADA)

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    36/100

    Training

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    37/100

    Core Training Partnership

    Core Team

    DOTD

    FHWA

    LTAP

    Nick Verret, Marie Walsh, Mary Stringfellow, Ann Wills

    LTAP FHWA DOTD

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    38/100

    Identified At Risk Areas

    Core Training Federal Funding

    Not understanding the Entity-State Agreement

    Responsible Charge not implemented Local Public Agency Manual

    Reporting

    Technical Training Modules

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    39/100

    Development of Training

    Preparation Researched other states

    Attended the MS training Jan 24, 2012

    Qualification Core Training Presentation &Materials Creation

    Marketing

    Qualification Core Training Pilot August 21,2012

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    40/100

    Target Audience

    The Qualifications Core Training is

    required for any Local Public Agency

    (LPA) project sponsor and for everyconsultant working on LPA projects

    receiving federal or state funding through

    DOTD

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    41/100

    Qualification Core Training

    Classes

    9 sessions taught around the state Fall 2012

    6 hour sessions (9 AM 3 PM)

    Cost - Free

    5 PDHs offered for engineers

    Over 300 people trained

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    42/100

    NEXT SESSION

    April 11, 2013DOTD HQ Auditorium

    Sign-up on DOTDs website

    Qualification Core Training

    Classes

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    43/100

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    44/100

    https://www.ltrc.lsu.edu/ltap/fr/lpa_core_training.html

    https://www.ltrc.lsu.edu/ltap/fr/lpa_core_training.htmlhttps://www.ltrc.lsu.edu/ltap/fr/lpa_core_training.html
  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    45/100

    Additional Training

    Modules Purpose To provide detailed technical

    assistance

    Topics Planning, Preconstruction,

    Construction Contract Administration

    Core Team: DOTD, FHWA, LTAP, LTRC

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    46/100

    Future LPA Training Modules

    Planning - Stage 0 Feasibility & application

    completion, complete streets policy

    Preconstruction - Project management,

    environmental (NEPA), consultant

    expectations/selection, engineering, complete

    streets policy, acquiring right-of-way/real

    estate, Title VI civil rights compliance (ADA,etc.), utility conflicts and relocations

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    47/100

    Future Modules (cont.)

    Construction Contract Administration

    Construction Engineering and Inspection (CEI)

    Including Site Manager, final audit (Form 2059, As

    Built Plans), construction signing, CEI consultantselection

    Material Testing

    Civil rights compliance (Disadvantage BusinessEnterprise (DBE), subcontracting, etc.)

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    48/100

    Tentative Dates

    Planning Late Spring/Early Summer 2013

    Preconstruction Late Summer/Early Fall

    2013

    Construction Contract Administration Late

    Spring/Early Summer 2013

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    49/100

    Entity-State Agreement

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    50/100

    Entity-State Agreement

    A written/signed agreement between the State andthe Sponsoring Entity (an LPA) identifying theresponsibilities of each entity LEGALLY BINDING

    Every project must have an agreement signed by

    both parties before a project can move forward An agreement must be executed prior to a

    reimbursable stage of a project

    The agreement identifies the funding provisions fora project

    A B i I f i

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    51/100

    Agreement Basic Information

    Project Number

    Project Title

    Parish & District where

    project will be constructed

    Sponsoring entitys legal

    name and Federal

    Identification Number

    A detailed project

    description & scope of work

    Amount or percentage of

    federal funding eligible to

    be used for the project &

    matching funds required

    Responsible Charge

    Design, Right of Way, Utilities

    Project Contract Letting

    Construction plus

    Construction Engineering &

    Inspection

    Cost Reimbursements

    Project Record Keeping

    Civil Rights

    Maintenance Responsibilities

    Public Liability

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    52/100

    New & Improved Agreement

    DOTD has revised the Entity/State agreement

    template to make it clearer and simpler to

    understand

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    53/100

    Funding

    An Entity can decide to pay for the work

    done in each phase of the project all on

    their own, or ask for federal/state funds

    to reimburse the cost of this work, but

    this decision must be documented in this

    agreement

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    54/100

    FundingPhase Local Match

    Percentage

    Federal

    Percentage

    Conceptual Plans and

    Environmental Decision

    20% 80%

    Preconstruction Engineering 20% 80%

    Right-of-Way Acquisition and

    Relocation

    100% N/A

    Utility Relocation 100% N/A

    Construction Engineering &

    Inspection 20% 80%

    Construction 20% 80%

    F di C it t

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    55/100

    Funding Commitment -

    MPO Area

    Amounts are limited by the TIP

    Any changes must be coordinated by the

    Entity with the MPO

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    56/100

    Funding Commitment LetterPhase Local Match

    Percentage

    Federal

    Percentage

    Total

    Conceptual Plans and

    Environmental Decision

    N/A N/A N/A

    Preconstruction

    Engineering

    20% -$3,750.00 80% -$15,000.00 100% - $ 18,750

    Right-of-WayAcquisition and

    Relocation

    N/A N/A N/A

    Utility Relocation N/A N/A N/A

    Construction

    Engineering &Inspection

    20% - $3000 80% - $12,000 100% - $15,000

    Construction 20% - $25,000 80% -$100,000 100% - $125,000

    Total $31,750.00 $127,000 $158,750.00

    Funding Commitment

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    57/100

    Funding Commitment

    Letter Non-MPO

    The Project Manager will revise the

    commitment letter accordingly

    Amounts may be limited by the Program

    Any changes must be coordinated by the

    Entity with the Program Manager

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    58/100

    Cost Disbursements

    The cost reimbursement process that DOTD will use

    is Disbursement this disburses to the Entity

    monthly the correct federal ratio of the approved

    project costs (i.e. pre-construction engineering

    services, right-of-way acquisitions, utility

    adjustments and/or the costs of construction)

    Upon receipt of each disbursement requested, Entity

    is required to tender payment for the invoiced costto the vendor

    Disbursement vs

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    59/100

    Disbursement vs.

    Reimbursement

    OLD - Reimbursement

    LPA pays contractor

    LPA submits cancelled

    check

    LPA reimbursed for

    agreed percentage by

    DOTD

    NEW - Disbursement

    LPA submits copy of

    invoice to DOTD

    DOTD sends LPA

    appropriate percentage

    LPA pays contractor

    LPA provides proof of

    payment to contractor

    within 60 days to DOTD

    MS

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    60/100

    What are FHWA funds

    FHWA funds are called Federal-aid funds They are cost reimbursable funds can

    be provided to an LPA by the FHWA

    through DOTD

    All FHWA funding program are

    reimbursement programs NOT Grant

    programs.

    S

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    61/100

    The Flow of Federal Funding

    Federal Transportation Funds

    Administered by FHWA Authorization of Funds

    To State DOTs

    DOTD is responsible for ensuring that ALL Federal and State

    laws and regulations are followed DOTD is always the direct recipient of FHWA funds facilitate

    funding to sub-recipients

    To Sub-recipients using federal funds (Local Public Agencies (LPA))

    Answer to DOTD for ensuring that ALL Federal and State laws andregulations are followed

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    62/100

    Federal-aid Funds

    Federal Law requires states to be fiscallyresponsible for all sub-recipients (LPAs) properexpenditure of federal funds

    The LPA sponsored projects must be compliantwith all applicable federal and staterequirements

    Non-compliance can result in partial or

    complete withdrawal of federal participationand funding in the project

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    63/100

    Moving Ahead for Progress in

    the 21st Century - MAP 21

    New 2 Year National Transportation Law

    Provides States With More Flexibility

    Consolidation of Programs 6 Core Program Structure

    Combined many small programs into the core programs

    Requires Performance Measures and GreaterAccountability

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    64/100

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    65/100

    Programs Affecting LPAs

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    66/100

    FHWA MAP 21

    Websitehttp://www.fhwa.dot.gov/map21/

    http://www.fhwa.dot.gov/map21/http://www.fhwa.dot.gov/map21/
  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    67/100

    MAP 21 Fact Sheets

    Fact Sheets on:

    Highway Safety Improvement Program (HSIP)

    Metropolitan Planning

    Railway-Highway Crossings

    Surface Transportation Program (STP)

    Transportation Alternatives Program (TAP) Tribal Transportation Program

    Stages of a

    http://www.fhwa.dot.gov/map21/hsip.cfmhttp://www.fhwa.dot.gov/map21/mp.cfmhttp://www.fhwa.dot.gov/map21/rhc.cfmhttp://www.fhwa.dot.gov/map21/stp.cfmhttp://www.fhwa.dot.gov/map21/tap.cfmhttp://www.fhwa.dot.gov/map21/ttp.cfmhttp://www.fhwa.dot.gov/map21/ttp.cfmhttp://www.fhwa.dot.gov/map21/tap.cfmhttp://www.fhwa.dot.gov/map21/stp.cfmhttp://www.fhwa.dot.gov/map21/rhc.cfmhttp://www.fhwa.dot.gov/map21/rhc.cfmhttp://www.fhwa.dot.gov/map21/rhc.cfmhttp://www.fhwa.dot.gov/map21/mp.cfmhttp://www.fhwa.dot.gov/map21/hsip.cfm
  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    68/100

    Stages of a

    Transportation Project

    Stage 0 Feasibility/Planning

    Stage 1 Environmental

    Stage 2 Funding

    Stage 3 Preconstruction (Design, R/W, Utilities)

    Stage 4 Letting (Bidding)

    Stage 5 Construction

    Stage 6 Maintenance

    AW

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    69/100

    What Can Federal Funds Be Used

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    70/100

    What Can Federal Funds Be UsedFor Within the LPA Programs?

    Transportation Planning

    Preliminary Engineering (pre-construction) Design,Right of Way Acquisition, Utility Relocation

    Construction

    Construction Engineering and Inspection

    ***Matching Funds from the LPA are usually required

    for all of the above & LPA owns the contracts forthese types of projects**

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    71/100

    State Funding

    DOTD Transportation Trust Funds

    (TTF) can only be spent on State

    owned roads. The only exception is

    the Off-System Bridge Replacement

    Program which was amended by law

    Funding Decisions Need to be

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    72/100

    g

    Made for All Project Stages If 100% Local Funds are used for Preliminary Engineering (Pre

    Construction):

    Entity performs work in-house

    Entity selects their own consultant to help with work (if

    needed)

    If Federal Funds are used for Preliminary Engineering (with Local

    and/or State match)

    DOTD advertises and selects a consultant for the LPA

    DOTD HQ advertises (lets) all federally funded Construction

    projects for the LPA

    Why Does DOTD have to Select

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    73/100

    yConsultants for Design and

    Advertise Construction Projectsif an LPA is signing both these

    contracts????

    DOTDs procedures for both of these activities havebeen previously approved by FHWA as meeting

    all Federal requirements DOTD facilitates the

    projects for LPAs to use Federal funds (with theEntity/State Agreement)

    The Brooks Act USC 40 Ch 11

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    74/100

    The Brooks Act USC 40 Ch 11

    The federal Brooks Act requires agencies topromote open competition by advertising, ranking,

    selecting, and negotiating contracts based on

    demonstrated competence and qualifications for

    the type of engineering and design services being

    procured, and at a fair and reasonable price.

    LA State Law procurement requirements forprofessional services do NOT meet the Brooks Act

    LPA vs. FHWA funding

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    75/100

    g

    LPA signs & owns all contractsStage of a Project LPA Paying 100% Federal $$ will

    Reimburse costs

    Conceptual Plans and

    Environmental Decision

    LPA can do work orpick consultant

    DOTD process used forconsultant selection

    Preconstruction

    Engineering

    LPA can do work orpick consultant

    DOTD process used forconsultant selection

    Right-of-Way Acquisition

    and Relocation

    LPA purchases must follow fed.

    procedures

    LPA purchases mustfollow Federal procedures

    Utility Relocation LPA handles LPA handles must followDOTD procedures

    Construction Engineering& Inspection

    LPA can do work orpick consultant

    DOTD process used forconsultant selection

    Construction N/A DOTD process used forproject - award to low bid

    contractor

    Responsible Charge

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    76/100

    On Your Projects (See Handout)

    If an LPA accepts Federal-aid funds - FederalRegulation 23 CFR 635.105 LPA must provide a full

    time employee of the LPA to be in responsible

    charge of a stages of a project.

    Not required to be engineer

    Required even if a consultant is retained by LPA to act as the

    Entitys engineer

    Not a full time job, but must be full time on the Entitys staff

    Does not have to be the same person in design as in

    construction

    Responsible Charges Key Role

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    77/100

    Responsible Charge s Key Role

    Acts as the primary point of contact for the Entitywith the DOTD Project Manager / District Project

    Coordinator

    - Attends all key project related meetingsIF THE PERSON IN RESPONSIBLE CHARGE IS NOT IN

    ATTENDANCE, THE MEETING WILL BE CANCELLED

    - Is involved in and/or knowledgeable of key

    project decisions

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    78/100

    Responsible Charge

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    79/100

    This is YOUR project.It is YOUR

    responsibility to keep

    it moving!

    ibl h

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    80/100

    Responsible Charge

    Federal Regulation 23 CFR 635.105 LPA mustprovide a full time employee of the LPA to be in

    responsible charge of a project.

    Not required to be an engineer Required even if a consultant is retained by the LPA to act as

    the LPAs engineer

    Not a full time job, but must be full time on the LPAs staff

    Does not have to be the same person in design as inconstruction

    ibl Ch

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    81/100

    Responsible Charge

    Not a new rule

    New enforcement by DOTD and FHWA

    New article in the Entity-State Agreement

    Must submit quarterly or monthly reporting forms

    (frequency will depend on the projects program)

    More information can be found at:

    http://www.dotd.la.gov/administration/lpa/forms.aspx

    ibl h

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    82/100

    Responsible Charge Form

    R i F

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    83/100

    Reporting Form

    R i F

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    84/100

    Reporting Form

    K R l

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    85/100

    Key Role Acts as the primary point of contact for the LPA with

    the DOTD Project Manager and the District Project

    Coordinator

    Is involved with and/or knowledgeable of key decisions

    Attends all key project related meetings

    Any decision making meeting Project Manager will identify required

    meetings (i.e. Kickoff, Plan-in-Hand Inspection)

    IF THE PERSON IN RESPONSIBLE CHARGE IS NOT INATTENDANCE, THE MEETING WILL BE CANCELLED.

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    86/100

    Key Duties for

    LPA Responsible Charge andLDOTD

    See Handout

    W ki ith DOTD

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    87/100

    Working with DOTD

    C t l

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    88/100

    Conceptual

    LPA

    Develops the Stage 0

    Report/Program Application

    Processes the Entity-State

    Agreement Completes and submits the

    updated reporting form to the

    DOTD Project Manager with a

    copy to the District Administrator

    & the MPO (if applicable)

    DOTD

    Reviews & approves the Stage 0

    Report/Program Application

    Determines the type of required

    environmental document Prepares the Entity-State

    Agreement

    E i i

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    89/100

    Engineering

    LPA

    Submits the scope of services &

    man-hours

    Executes the contract

    Provides the schedule & budget

    Reviews, approves & transmits

    invoices to the DOTD

    Monitors the contract time &

    grants any extensions /suspensions

    DOTD

    Reviews the scope & man-hours

    Prepares & advertises the contract

    Selects the consultant with input

    from the LPA (depending on the

    program)

    Prepares the contract

    Processes & pays invoices

    (If federal funds are being used for engineering)

    E i i

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    90/100

    Engineering

    LPA and/or Design Consultant

    Prepares the environmental

    document

    Obtains all required permits

    (environmental & railroad)

    Coordinates the utility

    clearances/certification

    documentation

    DOTD

    Processes & obtains federal

    approval of the

    environmental document

    Ensures permits & utility

    clearances are obtained

    E i i

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    91/100

    Engineering

    LPA and/or Design Consultant Completes the predesign form

    Attends the predesign meeting**

    Prepares & reviews preliminary &

    final plan submittals (including cost

    estimates)

    Sends the plans to & works with the

    utility companies

    LPA distributes plans internally

    Attends the Plan-in-Hand field

    Inspection**

    **Responsible Charge must attend

    DOTD Schedules & chairs predesign

    meeting*

    Reviews preliminary & final plans

    (including cost estimates)

    Distributes plans internally toDOTD & FHWA for review

    Schedules & chairs the Plan-in-

    Hand Field Inspection*

    *Consultant performs this inLRSP & SRTS as perAgreement

    Engineering

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    92/100

    Engineering

    LPA and/or Design Consultant

    Reviews plans to ensure all

    comments have been

    addressed

    Completes Non-Standard payitem request (if applicable)

    Completes design

    exception/design waiver

    request (if applicable)

    DOTD

    Distributes the notes from

    field inspection & reviews

    Processes Non-Standard pay

    item request (if applicable)

    Processes design

    exception/design waiver

    request (if applicable)

    Engineering

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    93/100

    Engineering

    LPA

    Transmits the stamped,

    signed & dated final plans,

    the cost estimate, &

    calculations to the DOTD

    DOTD

    Prepares the submittal for

    letting

    Advertises & receives the

    bids

    Reviews the bids with the

    LPA & the MPO (if

    applicable)

    Engineering

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    94/100

    Engineering

    LPA

    Reviews the bids for

    anomalies

    Formally responds to the

    DOTD request for

    concurrence

    Awards, signs & returns the

    contract timely

    DOTD

    Awards the bid

    Prepares the contract for

    execution by the LPA & the

    contractor

    Engineering (R/W)

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    95/100

    Engineering (R/W)(if required)

    LPA and/or Design Consultant

    Prepares the preliminary

    right-of-way maps

    Attends the Joint Plan

    Review Meeting (ResponsibleCharge must attend)

    Prepares the final right-of-

    way maps

    Acquires the right-of-way

    DOTD

    Schedules & chairs the Joint

    Plan Review Meeting

    Audits the right-of-way

    acquisition files to ensure

    all parcels were acquired

    following all state & federal

    guidelines

    Working with DOTD

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    96/100

    Working with DOTD

    Construction

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    97/100

    Construction

    LPA and/or CEI Consultant

    Records the contract in the Clerk

    of Courts office

    Schedules the Preconstruction

    meeting Attends all meetings when a

    decision is needed (ResponsibleCharge must attend)

    Ensures the project is constructed

    in accordance with plans & specs

    DOTD District Project

    Coordinator

    Attends the Preconstruction

    meeting

    Attends all meetings when a

    decision is needed Verifies that the project is

    constructed in accordance with

    the plans and specifications

    Construction

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    98/100

    Construction

    LPA and/or CEI Consultant Reviews & recommends approval of

    change orders (Responsible Charge

    must be involved)

    Ensures work zone safety

    Ensures the contractors monthlyestimate documentation is provided

    to the DOTD

    Pays the contractors monthly partial

    estimates (Responsible Charge)

    Prepares/submits the CostDisbursement Certification to DOTD

    (Responsible Charge)

    DOTD Disburses monies to the LPA

    Reviews & approves change orders

    Verifies that the work zone safety

    requirements are being implemented

    on the project

    Construction

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    99/100

    Construction

    LPA and/or CEI Consultant

    Attends the final inspection(Responsible Charge must attend)

    Records the Final

    Acceptance in Clerk ofCourts office

    Ensures the Final Estimate

    & required documentation

    is transmitted to DOTDtimely

    DOTD District ProjectCoordinator

    Attends the final inspection

    Audits the final estimate

  • 7/29/2019 S29_Overview of LPA Programs and Qualification Core Training Program_LTC2013

    100/100

    Questions?