S25_Overlay Low Volume Roads_LTC2013

Embed Size (px)

Citation preview

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    1/38

    Dr. Michael Ayers, Global Pavement Consultants, Inc.

    Building Concrete Overlays on Two Lane Roads

    Under Traffic

    U.S. 184 1/2 PCC UnbondedChickasaw / Fayette County, Iowa

    Partnerships for Progress in Transportation

    Louisiana Transportation Conference

    February 17-20, 2013

    Session 25

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    2/38

    Acknowledgements

    Dr. James Cable, Cable Concrete Consultation.

    The National Concrete Pavement Technology Center,

    Iowa State University, Ames., Iowa. Federal Highway Administration.

    Cement and Aggregates Association of Louisiana(CAAL)

    2

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    3/38

    ProjectLocation

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    4/38

    US 18 Bid Information Bid date 10/19/2010

    Late start date April 14, 2011 Work period 120 working days

    Limitations No stringline at centerline

    Project stages 6 (revised to 5 on site)

    Number of bidders 6 Bid range - $8.48 million to $10.51 million

    Prime contractor Manatts Inc.

    Project length 18.97 miles

    Project current traffic Chickasaw Co. - 1800 adt/22% trucks

    Fayette Co. 3050 adt/13% trucks

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    5/38

    US 18 Construction Objectives

    Demonstrate the ability to construct PCC overlayswhile maintaining traffic on two lane roads.

    Identify design and construction features that shouldbe included in plans to:

    Achieve overlay goals.

    Encourage construction efficiency.

    Reduce construction costs.

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    6/38

    Overlay Conditions

    First single lane overlaypaving, under traffic in Iowa

    Traffic control by pilot carand flaggers, 24/7

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    7/38

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    8/38

    Pre-Paving Project Staging

    Stage I (Changes in Patching timing)

    a. Patch (BOP to EOP), maintain traffic with pilot cars

    b. Construct subdrains, culverts, foreslope flattening, ditchreshaping & erosion control (BOP to EOP)

    Stage IIa. Use TBR/Signals to reconstruct/bridge approaches

    b. Place shoulder strengthening, TBR/signals/ attenuators& flood lights at four bridges

    c. Reconstruct bridge approaches, transition pavements at a time with HMA wedge ends

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    9/38

    Paving Project Staging

    Stage III (Changes in Milling length)a. Maintain through traffic w/ lane closure (3.5 miles) &

    pilot car

    b. Mill existing HMA surface (18.9 miles)

    Stage IVa. Pave overlay(EOP west to W-14), shoulder & open to

    traffic

    Stage V

    a. Pave overlay (W-14 to BOP), shoulder & open to traffic

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    10/38

    Traffic Queue Length Patching & Milling(2mi. zone): 6 to 8 cars / trucks

    average Paving (3.5 mi. zone): 15 cars / trucks average

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    11/38

    Miscellaneous Culvert Work

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    12/38

    Subdrain Installation

    Two mile work zone 48,422 feet of tiling

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    13/38

    Full Depth Patches

    651 ConcretePatches

    Average 34 permile

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    14/38

    Full Depth PCC Patches

    Average 30 per daywith sawing in PM

    Equals about two lanemiles/day

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    15/38

    Full Depth PCC Patches

    Average 30 per daywith sawing in PM

    Equals about two lanemiles/day

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    16/38

    Longitudinal Joint Patching Prep.

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    17/38

    Longitudinal Joint Patch Repair

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    18/38

    Bridge Approach & Transitions

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    19/38

    End of Paving Temp. Transitions

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    20/38

    Overlay Survey & Concrete Yield*Milling limits set at 1/2 to 1 1/2 deep at centerline

    * One mile test section topo to:- Identify section spacings (25 or 50 ft.)

    - Number of survey shots/section (3, 5 or 9)

    - Determine basis for value engineering proposal

    * Test Section Results

    Yield changed from 26% average overrun to average

    of 6% after milling to new profile depth

    Survey interval established at 50 ft.

    Nine shot survey section for best yield fit

    Nineteen miles surveyed 3D model established optimum profile model for use

    by milling and paving machines

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    21/38

    Survey GPS / TotalStations

    Survey existingsurface Develop database Create profile

    Three wire level zcoordinates

    GPS

    x, y coordinates

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    22/38

    Milling of HMA Seven foot wide mill head

    Cut ( to 1 ) at centerline

    Based on profile grade

    Centerline pass by total stations(25 to 30 ft. per minute)

    Exterior pass by joint match (1/2 to 1mile per hour)

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    23/38

    Haul Road Selection

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    24/38

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    25/38

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    26/38

    Tie Bar Location & Installation

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    27/38

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    28/38

    Staging of PCC Overlay

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    29/38

    3.5 Mile Timeline for Opening to

    Traffic

    1.0 day- cut trench and lay tied steel(may include last safety edge)

    2.5 day- Overlay Paving1.5 day- Curing1.0 day- Shouldering1.0 day- Painting and Signing

    7.0 days- Open to traffic via Pilot Car.

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    30/38

    Traffic Shift

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    31/38

    Stringless Paving for PCC Overlay

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    32/38

    Stringless One Lane Paving Control

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    33/38

    PCC Overlay Paving

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    34/38

    Overlay Finishing Operations

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    35/38

    PCC Joint Development

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    36/38

    Finish Shouldering

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    37/38

    US 18 Overlay Conclusions

    Single lane overlay construction under traffic wassuccessful

    Multiple traffic work zones are necessary to optimizeconstruction forces and time

    Staging preoverlay and overlay operations separatelywas beneficial.

    Timely concrete delivery requires owner/contractorcooperation

    Future improvements in the contract documents canreduce costs and increase construction efficiency.

  • 7/29/2019 S25_Overlay Low Volume Roads_LTC2013

    38/38

    Michael E. Ayers

    Global Pavement Consultants, Inc.

    [email protected]

    www.globalpavements.comPhone 217-621-3438