1
www.GlobalPlasmaSolutions.com © 2019 Global Plasma Solutions, Inc. ® GPS, GPS-iBAR, Global Plasma Solutions and are trademarks of Global Plasma Solutions, Inc. VALENCIA COLLEGE The Challenge The Valencia College Lake Nona Campus was constructed in 2012 and in- cluded the campus’s first building. The project included state-of-the-art academic spaces, teaching labs, student services, bookstore, library, cafe, a Dean’s suite, and administrative offices. The 88,821 sq. ft. campus was a $21.7 million project. The Solution Global Plasma Solutions installed the GPS-iBAR ® in all the air handling units on campus. The GPS-iBAR is perfect for such a large facility because it kills mold, bacteria, and airborne pathogens while maintaining clean cooling coils. Odor Control SAVED $ 180,000 AND REDUCED CFM BY 9,300 The Results The Valencia College, Lake Nona Campus was awarded 3 Green Globe certifications by Green Building Initiative. The GPS-iBAR reduced the outside air needed for ventilation by 9,300 CFM and saved $180,000 in chiller cost. The iBar was also compatible with their current air handling unit, which avoided costly renovation expenses. Testing revealed that there was no Fungi or Bacteria detected on the cooling coil fins. ODORS NEUTRALIZED ENERGY SAVED

S VALENCIA COLLEGE NEUTRALIZED - Global Plasma Solutions...VALENCIA COLLEGE The Challenge The Valencia College Lake Nona Campus was constructed in 2012 and in - cluded the campus’s

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: S VALENCIA COLLEGE NEUTRALIZED - Global Plasma Solutions...VALENCIA COLLEGE The Challenge The Valencia College Lake Nona Campus was constructed in 2012 and in - cluded the campus’s

www.GlobalPlasmaSolutions.com

© 2019 Global Plasma Solutions, Inc.® GPS, GPS-iBAR, Global Plasma Solutions and are trademarks of Global Plasma Solutions, Inc.

VALENCIA COLLEGE

The ChallengeThe Valencia College Lake Nona Campus was constructed in 2012 and in-cluded the campus’s first building. The project included state-of-the-art academic spaces, teaching labs, student services, bookstore, library, cafe, a Dean’s suite, and administrative offices. The 88,821 sq. ft. campus was a $21.7 million project.

The SolutionGlobal Plasma Solutions installed the GPS-iBAR® in all the air handling units on campus. The GPS-iBAR is perfect for such a large facility because it kills mold, bacteria, and airborne pathogens while maintaining clean cooling coils.

Odor Control

SAVED$180,000AND REDUCED CFM BY

9,300

The ResultsThe Valencia College, Lake Nona Campus was awarded 3 Green Globe certifications by Green Building Initiative. The GPS-iBAR reduced the outside air needed for ventilation by 9,300 CFM and saved $180,000 in chiller cost. The iBar was also compatible with their current air handling unit, which avoided costly renovation expenses. Testing revealed that there was no Fungi or Bacteria detected on the cooling coil fins.

ODORSNEUTRALIZED