Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Stakeholder Consultative Process to Identify Issues, Problems and Solutions
Safe Disposal
of Surplus
Drainage
Effluent &
Storm Water
Rehabilitation
of Existing
Drainage
Infrastructure
Revival of
Natural
Waterways
Second Line
of Defense
d/s Kotri
Make Shift
Arrangements
for Flood
Displaced
Persons
Environment
Mitigation &
Arresting of
Sea Water
Intrusion
Inland
Wetland
Management
Mangroves
Plantation in
Coastal Area
Coastal
Wetland
Management
Conjunctive
Use of LBOD
water for
Forestry
Livelihood
Strengthening
Develop
Shrimp and
Mud Crab
Farms in
Coastal Zone
Introduction of
Brackish Water
Fish in LBOD
Catchment
Introduction of
Bio-Saline
Agriculture in
Marginal Lands
Institutional
Strengthening
& Capacity
Building
Crises
Management
Unit within
SIDA
Gender
Mainstreaming
Combating
Water-
logging and
Salinity
Drainage
Infrastructure
in Non LBOD
Areas
Divestment of
FGW
Tubewells
Rehabilitation
of SGW
Tubewells
Regional Plan and Investment Priorities
SINDH IRRIGATION AND DRAINAGE AUTHORITY SINDH WATER SECTOR IMPROVEMENT PROJECT-I (WSIP-I)
PREPARATION OF REGIONAL PLAN FOR THE LEFT BANK OF INDUS, DELTA AND COASTAL ZONE
Final Report - Phase - II
MAIN REPORT Proposed Regional Plan
Volume – I The Louis Berger Group Inc.
In Association with
Indus Associated Consultants (Pvt.) Ltd.
May 2012
Reduction of Flood Damages
Increase in Agriculture Productivity
Reduction in Poverty
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
i
The Team
Team Leader Carlos A. Gandarillas. PhD
Deputy Team Leader Muhammad Saleh Soomro. PhD
Team members Adnan Nazir
Anwer Ali Dasti Baloch
Asif Turangzai
Arif Javed
Bagh Ali Shahid. PhD
Dragica Veselinovic
Fahad Samo
Ghulam Rasool Keerio. PhD
John E. Priest
Kamran Ansari. PhD
Khadim Hussain Soofi
Muhammad Saleh Sammo (deceased)
Nazeer Ahmed
Sajjad Larik
Sajaad Ali Soomoro
Sidte Muhammad Akhtar
Syed Amanullah Husaini
Tabassum Khushk Baloch
Usman Ghani Dar
Zaigham Habib. PhD
Zakia Mangrio
Chronology of Phase II Report
Date of submission of
Preliminary Draft March 26, 2012
Comments received
from Panel of Experts/
SIDA
May 10, 2012
Submission of the
Final Report May 31, 2012
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
ii
Letter of Transmittal
31st May, 2012
Dear Mr. Junejo,
We are pleased to submit the Final Report for Phase II of the Study ‗Master / Regional Plan
for the Left Bank of Indus, Delta, and Coastal Area‘. The final report incorporates comments
received from various stakeholders and observations and recommendations of the Panel of
Experts meeting held in May 2012.
This report has been prepared with a stakeholder consultative approach involving a wide
array of stakeholders, and represents their aspirations and expectation that the identified
issues and problems will be studied and pre feasibilities are undertaken to resolve the issues,
particularly related to timely and safely draining out drainage effluent, storm and flood
waters. Accordingly this report presents a set of 16 pre feasibilities, and three position
papers.
We would like to place on record our appreciation for the guidance and support extended by
Engineer Ehsan Leghari (MD SIDA), Mrs. Farzana Abbasi (GM Transition) and Engineer
Mr. Habeeb Ursani (Director AWB Badin), and yourself in the preparation of this report.
We would also like to place on record the support provided by Mr. Fateh M. Mari, PhD,
Project Coordinator, PCMU, and Engineer Ylli Dedja, PhD, FAO Project Management
Consultant (PMC/A), and Mr. Mohammed Ehsan, The World Bank Consultant. We would
also like to express our gratitude to the Honorable Ministers, Mr. Murad Ali Shah, Minister
of Finance, Mr. Jam Saifullah Dharejo, Minister of Irrigation, Mr. Nadir Ali Khan Magsi,
Minister of Food, and Syed Raghib Abbas Shah (Member Water, WAPDA). Special thanks
are due to the Panel of Experts (PoE) for their instructive comments. We take this opportunity
to acknowledge the encouragement and guidance received from the Chairman PoE, Dr. Asad
Kazi.
We would also like to mention here the appreciation and concurrence of the President of
Pakistan on the perspective plan, who desired that the people of Sindh do not undergo this
level of misery, in the event of similar unprecedented rainfall.
Sincerely yours,
Assuring our best services and cooperation,
Carlos A. Gandarillas,
Team Leader
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
iii
PRESIDENT REVIEWS SITUATION IN
FLOOD-HIT AREAS
DAWN dated Monday, October 31, 2011
KARACHI: Presiding over a meeting at the Bilawal House on irrigation, dewatering and
drainage of flood-affected areas on Sunday, President Asif Ali Zardari directed the
government to prepare water storage and drainage plans at the divisional level in the
province.
He also called for devising a plan to divert rainwater to desert areas of the province during
floods and store it for irrigation.
Sindh Chief Minister Syed Qaim Ali Shah, Water and Power Minister Syed Naveed Qamar,
Petroleum Minister Dr Asim Hussain, provincial ministers Murad Ali Shah, Sharjeel
Memon and Saifullah Dharejo, Secretary General to President Salman Farooqui and
provincial secretaries attended the meeting.
In their briefings at the meeting, WAPDA and the provincial irrigation department claimed
that 80 per cent of the floodwaters had been drained out from the inundated areas and work
was going on round the clock to clear the remaining areas.
Foreign consultant Louis Berger gave a presentation on a drainage plan for dealing with
similar calamities in future and submitted a plan for enhancing capacity of the Left Bank
Outfall Drain (LBOD).
He asked the WAPDA and provincial authorities to give top priority to the work of clearing
the flood-affected areas because of the upcoming Rabi crop and fast approaching winter.
The president was briefed on the implementation of his earlier directives and steps taken for
dewatering various localities.
The president stressed the need for a permanent drainage plan in the country which, he
said, would reduce flood damage as incessant rains might recur due to climate change. He
directed that after the completion of the dewatering work, a mechanism should be devised to
provide wheat seed to affected areas to enable farmers to sow wheat crop because any
delay would not only adversely affect farmers, but would also reduce national crop output.
http://www.dawn.com/2011/10/31/president-reviews-situation-in-flood-hit-areas.html
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
iv
Acronyms
AWB Area Water Board
B/C Benefit Cost
BOD Biochemical Oxygen Demand
C Celsius
CDM Clean Development Mechanism
cfs Cubic feet per second
CO Community Organization
COD Chemical Oxygen Demand
DCO District Coordination Officer
DDMA District Disaster Management Agency
DPOD Dhoro Puran Outfall Drain
DRIP Drainage Reclamation Institute of Pakistan
EC Electrical Conductivity
ENMD East Nawabshah Main Drain
ETo Evapotranspiration
FGOD Fuleli Guni Outfall Drain
FGW Fresh Ground Water
FO Farmers Organization
GCA Gross Command Area
GFCAWB Ghotki Feeder Canal Area Water Board
GIS Geographic Information System
GoP Government of Pakistan
GoS Government of Sindh
ha Hectare
IAC Indus Associated Consultants Pvt.
IBIS Indus Basin Irrigation System of Pakistan
IBRD International Bank for Reconstruction and Development
INGO International Non Government Organization
IRR Internal Rate of Return
IUCN International Union for Conservation of Nature
Km Kilometer
KPOD Kadhan Pateji Outfall Drain
LBCAWB Left Bank Canal Area Water Board
LBG The Louis Berger Group Inc.
LBOD Left Bank Outfall Drain
MAF Million Acre Feet
M cft Million Cubic feet
MD Managing Director
MDP Metrological Department of Pakistan
M&E Monitoring & Evaluation
MF Micro Filtration
MH Dhoro Meharabpur Hussainabad Dhoro
mm Millimeter
MMD Mirpurkhas Main Drain
MPL Maximum Permissible Limit
NCAWB Nara Canal Area Water Board
NDP National Drainage Program
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
v
NF Nano Filtration
NEQs National Environmental Quality Standards
NGOs Non Governmental Organization
NPV Net Present Value
NTU Nephlometric Turbidity Units
NTW Dhoro Nangreja Talpur Wada Dhoro
O&M Operation & Maintenance
PBD Patoyun Branch Drain
PCRWR Pakistan Council of Research in Water Resources
PDMA Provincial Disaster Management Authority
PEPA Pakistan Environmental Protection Agency
PMU Project Management Unit
POL Petrol, Oil and Lubricants
PSQCA Pakistan Standards Quality Control Authority
RD Reduced Distance
REDD Reducing Emission from Deforestation and Forest Degradation
RF Rapid Filtration
RO Reverse Osmosis
Rs. Pak Rupees
SBD Sinjhoro Branch Drain
SCARPs Salinity Control and Reclamation Projects
SDPI Sustainable Development Policy Institute
SFD Sindh Forest Department
SGS SIDA Gender Strategy
SGW Saline Ground Water
CDA Coastal Development Authority
SIDA Sindh Irrigation and Drainage Authority
SMD Sanghar Main Drain
SMO Salinity Monitoring Organization
SSF Slow Sand Filtration
TDS Total Dissolved Salts/ Solids
TMA Taluka Municipal Administration
TSS Total Suspended Solids
UASB Up flow Anaerobic Sludge Blanket
UN United Nations
UNFCC United Nations Framework Convention on Climate Change
UV Ultra Violet
WAPDA Water and Power Development Authority
WASA Water and Sanitation Authority
WCA Water course Associations
WHO World Health Organization
WNMD West Nawabshah Main Drain
WSIP Water Sector Improvement Project Phase
WSSD World Summit on Sustainable Development
WUA Water Users Associations
WWF World Wildlife Fund for Nature
WWG Women Water Group
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
vi
Table of Contents
Page
MAIN REPORT
Letter of Transmittal ................................................................................................... ii Acronyms ..................................................................................................................... iv
Table of Contents ........................................................................................................ vi List of Figures .............................................................................................................. ix List of Boxes................................................................................................................. ix List of Maps ................................................................................................................. ix
1 INTRODUCTION........................................................................................................ 1 1.1 The Report .................................................................................................................... 1 1.2 The RPS Background .................................................................................................. 1 1.3 Phase- II Study Objectives and Scope ........................................................................ 2
1.4 Report Preparation Process ........................................................................................ 2 1.5 Stakeholder Consultation Process for Phase -II Study ............................................ 3 1.6 Report Organization .................................................................................................... 3
1.6.1 Description of Volumes ..................................................................................... 3
1.6.2 Outline of the Main Report ................................................................................ 3
2 RECAP OF THE PHASE- I STUDY ......................................................................... 4 2.1 Brief Overview of Phase I Study ................................................................................. 4
2.2 Summary of Issues and Problems Identified by Stakeholders ................................ 4 3 OVERVIEW OF 2011 FLOODS ................................................................................ 5 3.1 Rapid Assessment......................................................................................................... 5
3.2 Key Field Observations on the floods ........................................................................ 6 3.2.1 Depth of the Storm Water .................................................................................. 6 3.2.2 Performance of the Drainage System ................................................................ 6
3.2.3 Drainage Behavior of LBOD System at Different Flood Levels ....................... 7 3.2.4 Impact of the Irrigation System Operation on the Floods.................................. 8
3.3 The Lessons Learnt ...................................................................................................... 8 3.3.1 Under Designed Drainage Network ................................................................... 9
3.3.2 Deferred Maintenance of Irrigation and Drainage Infrastructure ...................... 9 3.3.3 Encroachment in the Waterways ....................................................................... 9 3.3.4 Delayed Closure of Irrigation Canals ................................................................ 9
3.3.5 Absence of Trigger Mechanism for Disaster Management ............................... 9 3.3.6 Absence of Make Shift Shelters ....................................................................... 10
3.4 Paradigm Shift (Change in the perception of the stakeholders) ........................... 10 3.5 Policy Makers Guidelines for the Regional Plan Focus ......................................... 10 4 HYDROLOGY AND HYDRAULIC SIMULATIONS AT A GLANCE ............. 12
4.1 Hydrology Simulations .............................................................................................. 12 4.1.1 Methodology .................................................................................................... 12 4.1.2 Rainfall Patterns ............................................................................................... 12 4.1.3 Rainfall Frequency Analysis ............................................................................ 13
4.2 Hydraulic Simulations ............................................................................................... 14 4.2.1 Methodology .................................................................................................... 15 4.2.2 Simulation Results ........................................................................................... 15 4.2.3 Simulations for Offloading Discharge of LBOD ............................................. 16
5 THE PROPOSED INTERVENTIONS/PROJECTS .............................................. 18 5.1 Interventions Proposed and Agreed by the Stakeholders ...................................... 18 5.2 Typology of the Approved Interventions ................................................................. 23
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
vii
5.3 Brief Description of Pre-feasibilities of Suggested Interventions .......................... 24 5.3.1 Pre-feasibility 1: Rehabilitation and Improvement of LBOD Drainage
Infrastructure .................................................................................................... 25 5.3.2 Pre-feasibility 2: Revival of Natural Waterways to Drain out Storm Water ... 30 5.3.3 Pre-feasibility 3: Rehabilitation of SCARP and Drainage Tubewells of LBOD
System .............................................................................................................. 34 5.3.4 Pre-feasibility 4: Ghotki SCARP (Saline Zone) .............................................. 35 5.3.5 Pre-feasibility 5: Privatization of FGW SCARP Tubewells ............................ 37 5.3.6 Pre-feasibility 6: Second Line of Defense for Left Bank of Indus D/S Kotri .. 39 5.3.7 Pre-feasibility 7: Elevated Platforms for Flood Displaced Persons ................. 40
5.3.8 Pre-feasibility 8: Rehabilitation of Coastal Wetlands ...................................... 42 5.3.9 Pre-feasibility 9: Protective Plantation of Mangroves in the Coastal Areas of
the Left Bank.................................................................................................... 44 5.3.10 Pre-feasibility 10: Use of Drainage Water for Forestation in the LBOD and
Kotri Areas ....................................................................................................... 47 5.3.11 Pre-feasibility 11: Bio-saline Agriculture in Badin and Thatta Districts ......... 49 5.3.12 Pre-feasibility 12: Rehabilitation of Deh Akro II and Chotiari Wetland
Complex ........................................................................................................... 51 5.3.13 Pre-feasibility 13: Shrimp and Mud Crab Farming in Coastal Areas of Left
Bank .............................................................................................................. 54 5.3.14 Pre-feasibility 14: Brackish Water Fish Farming in LBOD Area.................... 56
5.3.15 Pre feasibility 15: Establishment of Disaster Management Unit in SIDA...... 58 5.3.16 Pre feasibility 16: Gender Mainstreaming in Irrigation and Drainage ............ 60
5.4 Position Papers ........................................................................................................... 62 5.4.1 Position Paper 1: Drainage Effluent Intrusion in the Ghotki Area from
Southern Punjab ............................................................................................... 62
5.4.2 Position Paper 2: Sugar Industry Effluent Treatment at Source ...................... 65
5.4.3 Position Paper 3: Water Quality for Human Consumption ............................. 67
6 PROPOSED REGIONAL PLAN STRATEGY AND RECOMMENDED
INVESTMENT PLAN ............................................................................................... 69 6.1 Proposed Regional Plan preparation Process ......................................................... 69 6.2 Proposed Regional Plan Strategy ............................................................................. 69
6.2.1 Pillars of the Strategy ....................................................................................... 71
1. Safe and timely disposal of surplus drainage effluent, storm water, and
riverine flood .................................................................................................... 71
2. Combating waterlogging and salinity in non-LBOD areas.............................. 71 3. Environmental mitigation ................................................................................ 71 4. Institutional Strengthening and Capacity Building of SIDA ........................... 72
5. Livelihood support to rural communities ......................................................... 72
6.3 Screening, and Ranking of Proposed Interventions ............................................... 72
6.4 Proposed Prioritizing and Sequencing of Interventions......................................... 73 6.4.1 First Priority Core Interventions ...................................................................... 73
6.4.2 Second Priority Interventions .......................................................................... 74 6.4.3 Third Priority Interventions ............................................................................. 75 6.4.4 Interventions Not Recommended for Implementation .................................... 75
6.5 Implementation Chronogram ................................................................................... 76 6.6 Implementation Strategy for the Rehabilitation and Improvement of LBOD .... 77
6.6.1 Short Term Structural Measures ...................................................................... 78 6.6.2 Long Term Structural Measures ...................................................................... 78
6.6.3 LBOD rehabilitation construction chronogram ............................................... 79
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
viii
6.7 Implementation strategy for the revival of natural waterways to drain out storm
water .......................................................................................................................... 79 6.7.1 Suggested implementation plan for drainage in lower Sindh .......................... 80 6.7.2 Top priority works before forth coming monsoon rains .................................. 80 6.7.3 Priority-2 works ............................................................................................... 80
6.7.4 Priority-3 works ............................................................................................... 80 6.7.5 Activation of natural waterways chronogram .................................................. 80 6.7.6 Activation of Natural Waterways Investment Costs ........................................ 81
6.8 Policy Issues ................................................................................................................ 81 6.8.1 Deferred Maintenance ...................................................................................... 81
6.8.2 Effective compliance of environmental protection laws ................................. 81 6.8.3 Cost Recovery Policy ....................................................................................... 82
6.9 Summary Recommendations .................................................................................... 82 6.10 Indicative Financial Outlay of Master Plan ............................................................ 84
6.11 Investment Chronogram ........................................................................................... 84 Attachment 1: Stakeholder Consultative Process
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
ix
List of Tables
Table 1: Issues Problems and Proposed Solutions ................................................................... 18 Table 2: Pre-feasibility Interventions / Position Papers ........................................................... 23 Table 3: Main Outputs of the Pre Feasibility No. 1 ................................................................. 26
Table 4: Indicative Cost Estimates for the Rehabilitation and Remodeling of LBOD
Infrastructure. (Rs. Million) ...................................................................................... 28 Table 5: Main outputs of the Pre Feasibility No2 .................................................................... 31 Table 6: Indicative Cost Estimates for the Revival of Dhoras including bypasses (Rs. Million)
................................................................................................................................... 32
Table 7: Ranking Based on Standardized Z scores .................................................................. 73 Table 8: Indicative Financial Outlay of Master Plan ............................................................... 84
List of Figures
Figure 1: Flooded Area 2011 in LBOD Area ............................................................................ 5 Figure 2: Utilization Factor for SCARP Division.................................................................... 37
Figure 3: Three alternative costs .............................................................................................. 39 Figure 4: Cost of Elevated Platform ........................................................................................ 41
Figure 5: Soil textures in Thatta and Badin Districts ............................................................... 49 Figure 6: Crises Management Cycle ........................................................................................ 58
Figure 7: Evaporation for Fresh and Saline Water Ponds........................................................ 63 Figure 8: Quantity of Sugar Mills Effluent Flows ................................................................... 65 Figure 9: Arsenic Contamination in Badin District ................................................................. 67
Figure 10: Strategy for Regional Plan for the Left Bank of Indus Delta and Coastal Zone .... 70
List of Boxes
Box 1: Profile of Spinal Drain ................................................................................................. 25
Box 2: Profile of Chotiari Reservoir ........................................................................................ 51
List of Maps
Map 1: Study Area General Map ............................................................................................... x
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
x
Map 1: Study Area General Map
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
1
1 INTRODUCTION
1.1 The Report
This is the draft report for the Phase II of the study ‗preparation of the regional plan for the
left bank of Indus, delta, and the coastal areas‘, hereon referred as Regional Plan Study
(RPS), submitted for the approval of the Sindh Irrigation and Drainage Authority (SIDA),
Government of Sindh. The final report will be submitted to SIDA after incorporating
comments and suggestions received from SIDA and their designated review process. This
report mainly presents the pre feasibilities of the structural and nonstructural interventions
selected by the stakeholders through a consultative process that included identifying the
problems/issues, deliberating the solutions, and selection of agreed interventions based on
technical feasible options, socially acceptability, financial/economic viability, and desirable
impacts. In the following phases of the study, detailed feasibilities and tender documents for
the ranked, identified, and approved interventions will be prepared.
1.2 The RPS Background
The RPS is one of the subcomponent of the Sindh Water Sector Improvement Project Phase-
I(WSIP-I). The WSIP-I has four components, namely, i) community development and
capacity building; ii) improvement of irrigation and drainage system; iii) management plan
for irrigation and drainage infrastructure; iv) project monitoring, evaluation, and supervision
of environmental management plan; and v).project coordination, monitoring, technical
assistance and training. One of the subcomponent of component iii) is ‗preparation of
regional plan to deal with floods and drainage issues on left bank of Indus river and
designing measures for improvement of the Indus delta and the coastal zone.‘
The six year duration project, with a funding support from the World Bank was launched in
December 2007, terminating in April 2013. The main objectives of the WSIP-I includes: i)
strengthening and fast tracking the institutional reforms that are already underway in Sindh;
ii) improving the irrigation system in a systematic way covering key hydraulic infrastructure,
main and branch canals, and distributaries and minors; and iii); enhancing long term
sustainability of the irrigation system through participatory irrigation management and
developing institutions for improving operation and maintenance (O&M) of the system and
cost recovery.
The main objective and scope of the RPS is to prepare for the Government of Sindh (GoS) a
regional plan for addressing the flood issues and proving proper drainage to the area on the
left bank of Indus River through appropriate structural and nonstructural measures, including
remedial measures for any outstanding deficiencies in the Left Bank Outfall Drainage
(LBOD) system; measures for retention and/or safe disposal of drainage, storm and flood
water, and improvement of wetlands in the delta area and in the coastal zone recognizing
their environmental importance and considerable economic potential for the local
communities. The RPS is designed to be completed in four phases. The scope of each of the
four phases of the study includes:
Phase I Study: Preparation of inventory and assessment of existing conditions and
identification of issues and problems, preparation of a report that can form the basis of
consultations with all stakeholders to reach an agreement on definition of issues and
problems. The report of this phase was submitted in December 2010, and approved in June
2011. This Phase-I study is also required to cover issues related to the supply of water and
management of drainage & waste water effluent, expected to be generated by the
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
2
development of the Thar Coal mines and power complex in the future as planned by the
government.
Phase II Study Identification of solutions covering structural and non-structural options, and
institutional and management measures and their technical environmental and social
feasibility, approximate cost, workability and ranking based on pre-feasibility level studies
and analysis.
Phase III Study Preparation of detailed feasibility including technical, economic,
environmental and social viability and implementation/institutional arrangement for the
solutions identified under Phase II as high priority.
Phase IV Study Preparation of detailed designs and bidding documents for the most
preferred solution for implementation according to the international standards and
implementation manuals and institutional arrangements for non-structural solutions.
All the above study phases are to be undertaken with an extensive participatory consultations
with a wide array of stakeholders and communities in the study area, including delta and
coastal areas, activists, NGOs, various public sector agencies, and decision makers.in
identifying issues and solution options, prioritizing interventions, and participation in
planning, designing, and implementation stages. The overall regional plan process is depicted
in the following diagram.
1.3 Phase- II Study Objectives and Scope
The main objective of the Phase II study is to i) identify structural and non-structural
solutions/options and interventions; ii) prepare pre feasibilities of the interventions selected
through stakeholder consultative process, detailing rationale, output, impact, along with
technical and economic viability, sustainability, and socially acceptability. Based on the
selection criteria developed the pre feasibilities will be ranked and prioritized by the
stakeholders for the preparation of detailed feasibilities and tender documents in the
following study phases.
1.4 Report Preparation Process
Following the submission of Phase 1 study report, as a proactive strategy, the Consultants
embarked on the preparation of pre feasibilities for solutions for intervention aspired by the
stakeholders. This was based on review of available studies, field studies, surveys,
procurement of satellite imagery, and ongoing process of consultation with the stakeholders.
The near finished pre feasibilities, that were technically feasible and economically viable
were presented to the stakeholders, along with the selection criteria, at the district and Area
Water Board (AWB) levels. Based on feedback from the stakeholder workshops, 19 pre-
feasibilities were presented at the national stakeholder workshop, held on 14 January 2012 in
Karachi. The participants agreed with the Consultants selection and advised to submit the
pre-feasibilities for approval and final selection of interventions for detailed feasibilities.
During the course of preparation of pre-feasibilities, the unprecedented rains and havoc
thereof, provided an opportunity to monitor the performance of the drainage system to cope
with the strain and weaknesses in the system, and its damage to the human lives, agriculture,
livestock, private properties, irrigation, drainage, and physical infrastructures, miseries of the
flood displaced persons including their constrained access to social services, and livelihoods.
This required reallocating Consultants focus and resources to closely evaluate the systems‘
capacity and alternatives options and interventions to ensure safe disposal of storm water in
the event of future similar extremes.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
3
During the preparation of the report sufficient Consultants resources were reallocated to
provide support and assistance to SIDA and the Core 5 Engineers, and providing information
and analysis to the irrigation department and senior politicians, including the President and at
the provincial Cabinet level. This also included preparation of a plan of emergency works to
restore the capacity of the drainage system, and measures to ensure safe disposal through
natural waterways in the event of similar rains.
1.5 Stakeholder Consultation Process for Phase -II Study
During this Phase of the study, 12 workshops were organized at the district level, 3 at the
Area Water Board (AWB) level, and one regional/national level, The Consultants supported
by fifteen local partner NGOs and a consortium of six organizations/NGOs, strived hard to
bring relevant stakeholders into the workshops, attended by about a little over one thousand
participants, of which 121 were women. In addition to this six TV programs were held for
wider dissemination and feedback.
In these workshops, the stakeholders were facilitated to express their aspirations and
apprehensions vis-à-vis the possible solutions and interventions proposed by the Consultants.
Based on the stakeholder consensus and agreement 16 interventions were selected for
preparing the pre-feasibilities. The conceptual outline of the selected pre-feasibilities was
presented in a regional/national workshop, held on 14 January 2012 in Karachi, for the final
selection and approval of the stakeholders. Attachment 1 presents a summary exposition of
the consultative process, during both the phases of the study.
1.6 Report Organization
1.6.1 Description of Volumes
The report has been organized in four volumes.
i. Volume I is the Main report (this volume).
ii. Volume II embodies the detailed pre feasibilities.
iii. Volume III presents the hydrology and hydraulic simulation studies.
iv. Volume IV presents the consultation process, and workshop proceedings.
v. Volume V is the Atlas.
vi. Volume VI presents the Preliminary Drawings
1.6.2 Outline of the Main Report
The section I introduces the report in terms of background to the RPS, its purpose, report
preparation process, and coverage of the report. The section II provides a brief recap of the
Study Phase 1 report. Section III summaries the findings of the hydrology and hydraulic
simulation models, while section IV presents a rapid assessment of the 2011 floods, lessons
learnt including a change in the mindset of the stakeholders, and guidelines and directives of
the decision makers. Section V presents project/intervention briefs on basis for the ranking
and selection of pre feasibilities, comments from the participants of the provincial
stakeholder workshop. Section VI presents recommendations for screening and the selection
of interventions.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
4
2 RECAP OF THE PHASE- I STUDY
2.1 Brief Overview of Phase I Study
The Phase study commenced in April 2010, and a draft was submitted in December 2010.
The phase I study report, after a series of reviews and incorporation of comments was
finalized and approved in the June 2011. This Phase of the study was dedicated to the
identification of issues and problems associated with the impacts of spreading water logging
and salinity; institutional breakdown for management of water delivery, drainage, floods and
disasters; environmental problems and resultant spread of poverty and deteriorating
livelihoods among the growing population.
The main activities during the preparation of the study Phase 1 were i) review of available
relevant reports and interaction with staff of relevant agencies, ii) field visits to assess the
performance of existing infrastructure, wetlands, and coastal areas and improvements and
revival needs; iii) preparation of technical, descriptive and analytical reports on area
description, inventory of existing irrigation and drainage infrastructure and issues related to
its operation and maintenance, impact of seawater intrusion, institutional issues, disaster
management etc.; iv) scoping sessions and intensive consultation with the stakeholders at the
village, district, regional, and provincial levels.
About 5,000 persons were consulted/participated in the workshops. The objective was to
solicit the perceptions about issues related to safe disposal of drainage, flood and storm water,
and impact of these infrastructures on poverty and livelihoods.
The Phase 1 report was organized in eight thematic areas detailing of the work and findings
that addressed the requirements of the scope of work mentioned in the contract. The thematic
areas included: i) overview and development of planning for drainage and flooding; ii) water
resources and water usage for drainage and flooding; iii) impacts of drainage and flood on
environment and wetlands; iv) flooding, disaster management and mitigation; v) structures
for irrigation drainage and flood protection; vi) overview of current agriculture, livelihood,
and economic aspect of drainage & floods; vii) social issues of drainage operation and
flooding; and viii) review of capacities of provincial agencies involved in execution of the
irrigation and drainage projects and its management.
2.2 Summary of Issues and Problems Identified by Stakeholders
During the course of the Phase 1 study, extensive consultations were held with the
stakeholders, including knowledgeable people and opinion makers, NGOs and activists to
solicit their perception and opinions vis-à-vis the issues and problems related to the
performance of the irrigation and drainage subsectors, and their adverse impact on
agriculture, general welfare and livelihoods, and environment, need for extending the
drainage infrastructure in the areas outside the LBOD system, need and options for the safe
and timely disposal of storm water, and apprehensions regarding increasing the capacity of
existing drainage system in the lower reaches of LBOD system. In addition to this they
expressed their concern on the sea encroachment damaging the productivity of farm land,
fisheries potential, and quality of life. The findings were presented in a series of workshop in
the study area and in the national workshop, and were the basis for formulating various
options to ensure safe disposal of drainage and storm water effluent.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
5
Series1, Badin,
3,726, 32%
Series1,
Sanghar, 3,322,
29%
Series1, Mirpur
Khas, 2,145,
18%
Series1,
Umer Kot,
1,016, 9%
Series1,
Nawabshah, 782,
7%
Series1, Tando
Allah Yar, 301,
3%Series1, T.M
Khan, 289, 2%
Flooded Area 2011
3 OVERVIEW OF 2011 FLOODS
3.1 Rapid Assessment
The monsoon of 2011 was manifested by remarkably high rainfall event in Sindh, particularly
in the left bank of Indus. The cumulative rainfall varied between 423 mm to as high as 1,143
mm. The Tharparkar district recorded the highest rainfall, followed by 866 mm in the
Mirpurkhas, 628 mm in Shaheed Benazirabad, 615 mm in Badin district, 544 mm at Chhor in
Umerkot district, and 423 at Padidan in the Naushehro Feroze district. In Tharparkar district,
where the infiltration rate is quite high, the runoff was minimal, compared with the other
areas in the left bank. The average intensity during the 8 August to 18 September was about
800 mm. The area inundated in seven severely affected districts of Sindh is shown in Figure-
1
As the gradient of the coastal
areas is near zero, the disposal
of the runoff was inhibitive
causing inundation and
stagnation of the storm water. In
addition to this infrastructure
such as rail and road networks,
canal and drains, and
encroachments in the natural
water ways also inhibited the
free flow. The delay in the
evacuation of the storm water
runoff was further compounded
by the breaches in the irrigation
and drainage network. The
situation further exasperated with the
gushing influx of storm water into the drainage system beyond its design discharge capacity
of 4,600 cusecs.
Two to six feet of stagnated water marooned the settlements and restricted access to social
infrastructure submerged the standing crops including fodder, and a significant number of
livestock, particularly milch animals were lost. It also damaged the productive, physical, and
communication infrastructure. It is estimated that about 500 people succumbed to the floods.
According to the Provincial Disaster Management Authority (PDMA) estimates about 38.5
thousand villages were affected, mostly in Badin district followed by Shaheed Benazirabad,
Sanghar, and Umerkot districts, causing misery to about 9.3 million flood affectees. PDMA
also estimates that about 1.6 million houses were fully or partially damaged. A large number
of flood displaced persons had to take refuge on the sparse higher grounds. Of these about
769 thousand people were provided refuge in the relief camps.
PDMA estimates that due to the storm water floods, about one third of the paddy area, half of
the area under chilies, and 80 percent of the cotton area, and about 90 percent of the tomato
and onion acreage were wiped out. In terms of production, it is estimated that about two
million bales of cotton, 250 thousand mt of paddy, 330 thousand mt of onion, 77 thousand mt
of chilies, and some 70 thousand mt of tomato were lost to the catastrophe. In addition to this
about 117 thousand animals were lost, excluding a significant number of poultry in the
houses and the poultry farms.
Figure 1: Flooded Area 2011 in LBOD Area
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
6
3.2 Key Field Observations on the floods
3.2.1 Depth of the Storm Water
During the field visits, observations were made to sound the depth of flooding in the affected
areas. It was observed on 15 August that, in the vicinity of breached canals, water was about
four feet deep across the countryside inundating villages, submerging crops, and was flowing
over the roads eroding its shoulders. The sheet flow of water was wide across, trapped by the
communication infrastructure, such as roads and railroad, and embankments. The culverts
were inadequate in number and mostly found choked and hindered enormous sheet flows.
3.2.2 Performance of the Drainage System
While assessing the performance of the LBOD System it should be taken into account that
between its upper reaches and Badin, the natural gradient reduces from 0.000118 to
0.000055, which substantially reduces the velocity of the storm water flows. If peak storm
flows are not instantly evacuated out of the system, ponding effect is experienced in the lower
reaches of the drainage system, and hence, lower reaches of the system need much higher
evacuation rate than the upper reaches. Similarly the tail reaches of the two main branches of
the LBOD namely KPOD and DPOD are four to seven feet below the sea level, retarding the
conveyance velocity of the drain during high tide, particularly during the flood season.
In addition to this the operation of the irrigation system in the Mirpurkhas area, as observed
during 2006 and 2011 floods has its bearing on the capacity and performance of the drainage
system. During the months of July and August, the Nara-Jamrao system operate at the
maximum level hence during floods a number of breaches occur in the irrigation system,
causing secondary breaches in the drainage system, particularly in the sub-drains.
The abovementioned scenario is based on standard hydrological return period estimations
using Log Pears III method and calculations of runoff using Soil Survey Curve Numbers
(SSCN). Maximum capacity of LBOD is adopted from its actual functioning during the
floods of 2011.
Despite siltation, the drainage system coped flows that were about two to three times higher
than the design capacity. It suggests a generally good physical performance of the Spinal
drain above the berm level. Considering the quantity of water that flowed through this section
over a period of one month, physical breaches of the banks and berms were limited.
The Consultants made extensive visits to the flood affected areas, where ever accessible. It
was noted with relief that the LBOD spinal drain performed fairly well despite breaches,
overtopping in some areas, rain cuts on the banks and sloughing of the banks. The band aid
repair of the spinal drain breaches by the concerned agencies was timely and effective.
Specifically it was observed that:
i. the spinal drain was flowing at the maximum available depth covering primary
and secondary berms after its junction with MMD at RD 297. The main sub-
catchment tributary drains also performed satisfactorily;
ii. the Nawabshah East and West drains received normal flows of storm water from
their respective drainage areas;
iii. the Sanghar sub-component also functioned below it maximum capacity; the canal
escapes however, were discharging water to the spinal drain;
iv. the Mirpurkhas Main Drain (MMD) and its lower network was under the highest
pressure, and was the first to suffer a breach on 12 August at RD 365, which
received high quantities of runoff from the larger catchment of Mirpurkhas, and
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
7
most of its branch drains flowing at the top level or overtopping. It was also
receiving high quantities of canal water from the Jamrao Canal, and MMD was
flowing bank full at the crossing of Tando Jan Muhammad-Jhudo road
overtopping the banks at several points upstream and downstream. The left bank
of MMD downstream from the road bridge was submerged and it confluence with
the Dhoro Puran water that was flowing adjacent to it;
v. the storm water accumulated in the Dhoro Puran upstream of Jhudo town
overtopped into MMD. At one place the Dhoro Puran was passing through the
culvert with insufficient capacity. This section has been narrowed due to
encroachments that resulted in the overtopping of the banks.
Although the behavior of the branch drains could not be observed in detail, nonetheless,
widespread over-flowing of the sub-drains indicated an overall capacity deficit of the branch
system. About 40 breaches in the drains, as reported by the rapid assessment conducted by
the Pakistan Red Crescent Society (PRCS), suggest the need for a follow up on field
assessment. However, it was concluded that:
i. due to insufficient capacity of the sub-drains the Badin sub-component started
surcharging first. On the 12th of August a breach in the Shadi-Bahader system
was observed. The water was back flowing from the sub-drain with high velocity
quickly submerged a large area;
ii. the surface ditch and culvert systems were observed to be inadequate to the
requirement of conveying ponded water toward drains. Culverts to pass water
under railways and roads were too few and of insufficient capacities;
iii. deep cuts made by the local populace to pass water from canal breaches even
though a small culvert already was passing water, submerged the road connections,
particularly in the Digri town in the Mirpurkhas district.
3.2.3 Drainage Behavior of LBOD System at Different Flood Levels
The LBOD drainage network provides drainage to the major areas of Shaheed Benizirabad,
Sanghar, Mirpurkhas and Badin districts. This was built to drain the saline effluent of
drainage tube wells and the storm water of 125 mm rain through outfall into sea. It was
designed with an average drainage coefficient of about 2 cusecs per square mile. The
maximum flows during the current floods show that the drainage network can achieve a
coefficient of 3.5 cusecs per square mile, evacuating the same within four to five days, in an
average rainfall year. Timely evacuation during this period is possible only if average rainfall
in the catchment remains below 115 mm. The base flow from irrigation and vertical drainage
is close to 3,000 cusecs, almost double of the design capacity.
Four canal escapes, two from Jamrao canal and one from Mithrao canal discharge into the
LBOD, while one escape from Akram Wah discharge into DPOD. The discharge capacity of
these escapes is about 1,000 cusecs. The main purpose of these escapes is to provide safety to
the irrigation channels. During July and August, these escapes are frequently operated. The
fishing in LBOD is another reason for operating these escapes
The post flood discharge measurements made by the Consultants show that despite the flows
were above the designed capacity, more than 12,000 cfs was flowing in the LBOD tail
reaches, without overtopping and breaching. Similarly, the discharges measured in the
various main drains significantly surpassed the respective capacities. In the Shaheed
Benazirabad district the drains accommodated about 4,446 cusecs against a designed
discharge capacity of 1,651 cusecs, while Sanghar main drain carried a discharge of 3,314
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
8
cusecs against a designed capacity of 2,188 cusecs. Similarly the main drains in the
Mirpurkhas and Badin districts carried about 2,067 cusecs and some 2,378 cusecs
respectively, against a corresponding design discharges of 1,592, and 2,908 cusecs.
3.2.4 Impact of the Irrigation System Operation on the Floods
The management of the irrigation system also has its consequences on the performance of the
drainage system. Despite the minimal demand for canal supplies during this period, there was
considerable delay in suspending canal withdrawals exerting pressure on the drainage system.
As the watercourses were blocked by most farmers, the actual water level exceeded the
design capacity of the canals, that caused canal breaches in the distributaries and the larger
Jamrao West Branch canal. Moreover, this exerted pressure on the canal escapes. During the
critical five days August 12 through August 16, the canals continued to flow even though
repairs were undertaken largely by local landowners. It was observed and noted that:
i. During the rainy season, wherever the canal system continued to operate, the
farmers blocked the watercourses, that exerted pressure in the system;
ii. The canal escapes continued to discharge large flows into LBOD because, as
noted above, the canal head works were not closed although many distributaries
had been closed in upstream areas of the Nara and Rohri Canal Commands.
Consequently, the main and branch canals of the Nara and Rohri systems were
surcharged and had to continue operations even though breaches had occurred
flooding the countryside; The breaches in the irrigation system started occurring
since 12th
August, while it was still raining. According to SIDA field data, eleven
breaches in Nara canal distributaries and minors occurred on 11th and 12th of
August. The obvious cause of these breaches was the closing of watercourses by
the farmers, while the main canal system was still operational. Two breaches
occurred in the Left Bank Canal Area. The water from nine minor canals of the
Shadi sub-division (Akram Wah System) was disposed of to the sub, branch and
the main drains of the LBOD system.
iii. On 11th of August, Akram Wah (Lined Channel) was closed, while, flows in
Fuleli and Pinyari were reduced. The Pinyari and Fuleli canals were subsequently
closed on 12th August. However, Jamrao and Rohri irrigation systems were not
closed during the floods. Later on, as a response to the breaches and reduced water
demand, some of the branch and distributary canals were closed but a number of
breaches had to be repaired, while the main canals continued to operate.
Nonetheless, the closure of the canals with breaches did reduce the flow outside
the system. It was also observed with concern that in Badin District. Some of the
drainage tubewells continued to pump the saline water into the LBOD spinal drain
even though the adjoining areas were flooded by breaches.
3.3 The Lessons Learnt
The natural calamities and disaster despite the destruction and miseries also offers
opportunities to plan coping mechanisms for a resilient future. It brings out weaknesses in the
system and to adopt corrective measures. Disasters also trigger new dynamics and challenges
the status quo of conventional inefficient management and governance of the resources and
offers lessons for more responsive and responsible management. The 2011 storm water
disaster is not an exception, and offered an opportunity to adopt proactive interventions for
future, such as disaster preparedness, and remodelling and rehabilitation of infrastructure for
climate proofing against the extreme weather event threats. Some of the lessons learnt are as
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
9
follows.
3.3.1 Under Designed Drainage Network
The existing drainage infrastructure was designed for 5 year return period and for a rainfall of
125 mm to be evacuated in 5 days. The last two decades have witnessed more frequent high
rainfall events, and the flood disasters. The intensity of 2011 rains was unprecedented; about
5 to 6 times higher than the design capacity of the drainage system. The data on year wise
rainfall and daily max/min rainfall suggests that the need to remodel and rehabilitate the
existing drainage infrastructure on a 20 year return period basis so as to enable the system to
timely and safely dispose the high intensity storm water flows.
3.3.2 Deferred Maintenance of Irrigation and Drainage Infrastructure
The stakeholders complained that the drains are clogged with weeds and siltation, and the
banks have numerous rain cuts, and deliberate relief cuts by farmers during previous rains,
which were not fixed. This increases the vulnerability and risk of breaches, which were
witnessed during 2011 floods.
3.3.3 Encroachment in the Waterways
The major cause of timely disposal of the storm water flood was the obstructions in the
natural waterways aka dhoras. These dhoras used to be operational before the construction of
the LBOD system. The blockades include unauthorized construction of adobe and brick
walled structures, and cultivation. It was also observed that the inadequate size of the
drainage outlets, culverts, also caused ponding of flood water in the depressions and could
not be evacuated due to barricades all around. It warrants provision of adequate drainage
outlets, culverts, bridges, waterways to facilitate the prompt disposal of flood water.
In addition to this the intersecting roads, bridges, and the spinal drain further constrict the
gushing storm water flows. This recognizes the need to provide siphons or super passages to
facilitate the storm water flows through the dhoras. The GoS has recently enacted legislation
in this regard, and it needs to be enforced and complied with.
3.3.4 Delayed Closure of Irrigation Canals
It was noted with grave concern that despite the prior prediction of the extreme rain event,
the irrigation infrastructure remained open delivering regular irrigation water supplies in the
main canal systems. This resulted in about 55 reported breaches in the main canals and the
minors/distributaries while heavy downpour continued generating significant high storm
water flows. Both combined caused miseries for the communities at large. There is exigent
dire need for coordination between the Meteorology department and other functionaries
responsible for disaster management to be proactive and to timely disseminate the
information widely.
3.3.5 Absence of Trigger Mechanism for Disaster Management
Absence of a coordinated flood preparedness plan by the line agencies is one of the major
concern, particularly access to space for make-shift shelter or arrangement, boats for rescue
operations, pumping sets for evacuating flood water, access to food supplies, potable water,
and medical facilities, fodder for animals and similar other supporting items essentially
needed for flood affected population.
Due to the absence of a trigger mechanism to provide rescue, relief and rehabilitation
strategy, timely support could not be provided to the flood affectees. An appropriate advance
action would have diluted the miseries created by the floods of this event. Thus the line
agencies including the PDMA, Irrigation Department, Food Department, Health Department,
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
10
Local Government Department, Education Department, Agriculture Department, Pakistan
Army, District Governments, Local and International NGOs need to develop preparedness
strategies to face such natural calamities.
3.3.6 Absence of Make Shift Shelters
Based on the reports of Intergovernmental Panel on Climate Change (IPCC), Pakistan is
among the top ten countries most vulnerable to climate change. Therefore, as an immediate
preventive measure, the raised platforms may be built at suitable places for the affected
population to get temporary shelter in case of rain or river flood disaster for the people,
livestock and their belongings.
3.4 Paradigm Shift (Change in the perception of the stakeholders)
Since its construction, a sizeable population of the Badin district maintained that the LBOD
drainage network has brought significant miseries to them. They believed that priority was
given to improving the productivity of Shaheed Benazirabad, Sanghar and Mirpurkhas
districts at their cost. They felt that the disposal of drainage effluent generated from the
vertical and surface drainage network, into the sea, passing through their districts has creating
significant negative externalities for them. Consequently, this had an adverse impact on the
productivity of farmland, fish potential, limiting livelihood opportunities. They also opined
that due to the seawater intrusion and back flows in the drains rendering their once fertile
lands saline and water logged, thereby severely irreversibly impairing the coastal
environment. This resulted in decrease in the natural resource bases, dwindled livelihood
thereby significantly increasing the poverty.
During the 2011 floods, the consultants made a number of field visits to identify the issues
and problems faced by the communities in the flooded areas, and to observe the performance
of the drainage system.
The devastating floods brought a change in the perception of the stakeholders about the
effectiveness of the drainage infrastructure, and its utility, and need for its rehabilitation and
remodeling where required. This has softened the opposing stance and negative perceptions
amongst the stakeholders in the Badin and Thatta districts. Most people in the field now
tacitly acknowledge that the LBOD system played a role in evacuating 2011 flood waters, as
the LBOD system accommodated three times more flows than its design capacity,
notwithstanding few incidents of overtopping and/or breaches.
Most persons now accredit that the drainage network did depress the flooding disaster. They
concede that without which the losses to the lives and property would have been manifold.
Most of the communities have realized that drainage infrastructure needs to be revamped to
provide timely evacuation of the storm water. While talking to the communities, it was noted
that the negative perceptions of the stakeholders has been watered down, and has dented the
complete rejection of the drainage system, while appreciating is positive aspects.
3.5 Policy Makers Guidelines for the Regional Plan Focus
After a briefing to the President of Pakistan by the Chief Minister, Minister for Irrigation,
Minister for Food, Secretary IPD, MD SIDA and other senior officials, officers of Military 5
Corp, and the Consultants held on 30 October, 2011, the President commented that ‗we
cannot afford revisit of such a catastrophe‘ and directed that a field visit should be forthwith
undertaken to review the situation and preparation of an action plan and its implementation
before the advent of 2012 monsoon, so as to ensure a safe and timely disposal of storm water
drainage from the left bank of Indus.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
11
After a joint review mission by the ministers, Secretary IPD, MD SIDA, officers of the
Engineering 5 Corp, and the Consultants, visited the area. The assessment and
recommendations were presented to the President in subsequent meetings for approval. The
President desired that the recommendation should be fast tracked and emergency works to be
in place by the end of June 2012. He also emphasized that emergency works to relieve from
the ponded storm water in the low lying areas, and repair and rehabilitation of critical
infrastructure including dhoras so as storm water is timely and safely drained in the event if
2012 rains of last year intensity.
In a follow up meetings with the Minister of Irrigation, Secretary Irrigation, and MD SIDA
desired that the strategy of the regional plan being prepared by the Consultants should now
focus on: i) the repair, rehabilitation of LBOD and Kotri Barrage drainage network within the
left bank; and ii) diversion and offloading flows in LBOD to Thar Desert through revived
dhoras.
In compliance of the directives of the President of Pakistan a perspective plan for the
drainage system improvement was formulated by the Consultants in consultation with SIDA,
and WAPDA officials, and got approval from the policy makers.
The objective of the perspective, as guided by the President is to restore and enhance the
discharge capacity of existing drainage system, and restoration of old and existing dhoras,
both to cater for 20 years return period flood.
The salient elements of the strategy are:
i. rehabilitation and strengthening of the existing vulnerable and damaged drainage
infrastructure on emergency basis and its completion by the end of financial year
2011/12;
ii. clearance of obstructions and encroachment of dhoras, and reactivation of the
dhoras to off load storm water pressure on the LBOD;
iii. remodeling and enhancing of the discharge capacity of existing drainage network,
and retarding sea water intrusion; and
iv. construction of surface drains to safely pass the storm water in areas outside the
LBOD areas.
The detail of the action plan and time frame for different activities is mentioned in the
following sections 5.3.1 and 5.3.2.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
12
4 HYDROLOGY AND HYDRAULIC SIMULATIONS AT A GLANCE
The hydrology analyses aims at updating the key hydrological parameters and understanding
rainfall patterns causing floods. An integrated hydraulic assessment of the LBOD system has
been carried out for the first time. The results of hydrology and hydraulic simulations were
adopted as determining the design parameters for the drainage system rehabilitation and
integration of dohras as a disposal vehicle and diverting storm water to the depressions in the
Thar Desert.
4.1 Hydrology Simulations
Objectives
The hydrology analysis aims at:
i. A review of the rainfall patterns causing moderate and heavy floods in LBOD
catchments; and
ii. Updating hydraulic parameters used at the design stage of the drainage network
4.1.1 Methodology
The hydrological analysis includes daily monsoon rainfall patterns, estimation of rainfall
frequency in terms of return periods, rain- runoff and drainage coefficients for different
LBOD sub-catchments.
The rainfall frequency has been estimated employing Log Pearson (LP) Type-III for the daily
maximum rainfall. The daily maximum rainfall is the consistent set of data available from all
meteorological stations. However, it is not the same as 24 hour maximum storm, hence a
distinction should be made. Based on literature review, factors used to convert different
frequency storms are presented. The LP III distribution is a recommended method to model
the flood flows and precipitation for return period estimation (Guidelines for Determining
Flood Flow Frequency - Federal Agencies USA).
The runoff has been estimated using already adopted Curve Number (CN) Method to convert
storm-rainfall into runoff. These curves are developed by Soil Conservation Service (SCS)
USA and have been adopted globally. Selection of CN values considers soil classification and
land use characteristics. However, factors intercepting rainfall before it falls to the land
surface, evaporation and infiltration are considered outside the CN values. Only three rainfall
stations exist in large LBOD service area. By using their point rain over large irregular sub-
catchments, another important assumption on uniformity of the rainfall is made.
The time series data on rainfall include 70 years data for Badin, and 44 years data for
Shaheed Benazirabad (Nawabshah), and Mirpurkhas districts (adopted from Chorr station).
4.1.2 Rainfall Patterns
A review of daily monsoon rains during flood years of 1994, 2003, 2006, 2011 identifies
following patterns:
i. heavy and prolonged downpour, with a recurrence pattern during late August and
early September caused major floods in the years 1994, 2006, and 2011. Historical
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
13
data shows that the rains may spread over few days to a couple of weeks. Given
the discharge capacity of the drainage system, the runoff generated for two
successive days would inundate a large area. The limiting cushioning capacity of
the local depressions, dhands, dhoras, and aquifer is quickly consumed. Hence,
prolonged storms can exponentially increase the drainage volume;
ii. for the year 2011, the weighted average monsoon rains in Sindh is 272 percent
higher than normal. All the four districts sub-catchments had more than 400 mm
rain during one month (11th of August to 13th of September) and about 300 mm
during one week. A combination of more than one hydrological system,
concurrent wind direction from the Bay of Bengal, and cyclones in the Arabian
seas generated severe monsoon intensity in 2011.
iii. the intensive and prolonged rains in the upper catchment area exerted considerable
pressure on the capacity of the LBOD network throughout its length. This caused
overtopping, breaches, and inundation of the low lying areas. The runoff from the
adjacent areas outside the LBOD command also entered into the LBOD system.
iv. continued irrigation flows during the 2011 floods also caused canal breaches in
many reaches resulting in the inundation of agriculture lands and unauthorized
interventions by the farmers.
v. medium and low floods of 2006 and 2010 indicate a combination of four factors
that help in managment of the flood flows and damages to the Badin area:
heavy rains are not wide spread or not occur across the LBOD sub-catchments
at the same time. As a consequence, flood peaks are not simultaneously
generated in all sub-catchments, and the drainage effluent from the main and
branch drains is accommodated by the spinal drain, KPOD and DPOD;
breaches and relief cuts in the middle section remain in the manageable range,
practically offloading LBOD Spinal and reducing flood volumes reaching to
the tail section of Spinal and KPOD;
irrigation system is closed on time and flows from irrigation canals through
breaches or direct diversion not enhance the rain-runoff quantities, efficient
disaster management measures help in minimizing the local damages.
4.1.3 Rainfall Frequency Analysis
The recurrence frequencies were estimated for 5 to 500 years return periods. The return
periods of 10 and 20 years are selected for estimation of capacity related variables. For the
return periods of 10 and 20 years, precipitation values for Shaheed Benazirabad are 107 mm
and 126 mm, for Chorr 127 mm and 145mm, and for Badin 152 mm and 165mm,
respectively.
The return periods for two days storm have been estimated for Badin district over a 15 years
period. Expected 2 days storm, rainfall for 10, 15, and 20 year return periods are 273 mm,
297 mm and 312 mm respectively, which is about 80 percent higher compared to a one day
storms. The small dataset used here seems biased towards the wet years. However, two days
storms are important and needs to be estimated for three stations using larger datasets.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
14
A large arid basin, with local storage potential and high sub-surface water movement, can
have a only a part of runoff converted into floods, especially at low rainfalls. The reduction
factors used to convert runoff into flood-flows are empirical and need calibration for local
conditions. For the LBOD catchments, the empirical coefficients adopted by WAPDA and
the National Drainage Manual were used (NESPAK 2008, National Drainage Manual), which
estimates that about 33 percent of the runoff is converted into the drainage flows. A five day
evacuation period is considered appropriate for the standing crops. This suggests that if about
33 percent of the gross runoff is evacuated within five days, crop damages would be the
minimum.
The gross drainage flows from LBOD catchment for return periods of 10 and 20 years have
been estimated, respectively as 7,000 cfs and 9,200 cfs. These values indicate accumulated
drainage quantities at RD 159 of the spinal drain. From Badin, about 50 percent storm water
flows directly into the KPOD, hence not accounted at RD 159. For 7,000 cfs, contributing
sub catchments will be Shaheed Benazirabad 1,851 cfs, Sanghar 1,431 cfs, Mirpurkhas 1,636
cfs, of Badin 2,125 cfs. For a 9,200 cfs runoff flow at RD 159-LBOD, Shaheed Benazirabad
would account for 2,558 cfs, followed by 2,104 cfs from Mirpurkahs, 1,973 cfs from
Sanghar, and 2,550 cfs from Badin district.
For a 9,000 cusecs drainage discharge, drainage coefficients (in cusecs per square mile) from
the catchments will be Shaheed Benazirabad 2.62, Sanghar 2.98, Mirpurkhas 3.58 and Badin
5.82 respectively. These are more than double of the design values for Badin and three to
four times higher for three upper catchments. The capacities of the tertiary and the secondary
drainage networks have been estimated considering drainage coefficients of each catchment,
representing flow rate (cubic feet or cusecs) from a catchment of one square mile. The
drainage coefficients are important in determining capacities of the secondary drainage
channels. At the tertiary level, gross capacities of the field drains are normally kept lower
than the estimated discharge coefficients, to avoid excessive flows into the secondary system.
High volume of sheet-flows during floods can convey more water into the secondary system,
exceeding gross capacity of the controlled drainage inlets. The final selections for the
capacity are influenced by economic benefits vis-à-vis cost of the project on a long term
bases.
4.2 Hydraulic Simulations
Objectives
Hydraulic analysis has been carried out to address the following:
i) Evaluation of hydraulic behavior of LBOD network and its post-design trends to
provide guidelines for physical and operational changes;
ii) Assessing hydraulic response of the key physical components and proposed
interventions under full operational range; and
iii) Calibration and validation of a model, which could be used at a later stage to recap
performance of the drainage network.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
15
4.2.1 Methodology
An easily replicable and robust methodology has been adopted by developing a mathematical
hydraulic simulation model to represent the design and post design physical conditions of the
LBOD system. Analytical scenarios were developed and simulated for the existing
operational range. These scenarios can be easily modified to compare different options or
historical developments. The one-dimensional model HAC-RAS was applied to model three
sets of physical parametersof LBOD original design, pre-flood situation and proposed
modifications to cater drainage flows at ten and 20 years return periods. The model has been
calibrated and validated using standard procedures. The design and actual cross-sections were
defined in detail, including berms a inspection paths. Standard design templates were
developed for each reach, maintaining geometrical details such as the lower section of
LBOD, main prism having 1V:3H side slope, and the upper section between the banks and
the inspection paths. For scenario analysis four discharge ranges have been identified; the
base flow, design discharge and flows at 10 years and 20 year return periods. For each
discharge range, drainage contribution from each of catchment area has been estimated and
further divided into discharges of the main and branch drains.
Calibration results for the LBOD, the confluence reaches, and the KPOD are encouraging.
Simulated water surface profiles and depth-discharge curves closely conform to the design
values, reflecting the accuracy of cross-sections, bed slope and roughness coefficient. The
model can be further used to test the physical or operational interventions.
4.2.2 Simulation Results
4.2.2.1 Design characteristics of LBOD
Four flow distribution patterns (1,300 cfs, 4,400 cfs, 7,000 cfs and 9,000 cfs) has been
simulated for the LBOD spinal drain, KPOD, DPOD and the outfall drains. Simulation results
indicate design flexibilities and limitations of the system, performance of the drainage
network under different hydrological conditions and highlight the scope for improvements.
For example, at the base flow of1,300 cfs, about 26 percent capacity of the spinal drain is
utilized, while hydraulic depth varies from 35 percent to 60 percent of the design depth in
different reaches. At the low flow levels, the velocity does not remain consistent in different
reaches, while, local storage occurs in the tail reach. The hydraulic parameters for all the
reaches of LBOD at four flow levels has been estimated, including discharge, cross sectional
area, water surface elevations, velocity, depth, top-width and free board.
The simulation results also indicate the capacity margins available in different sections of the
LBOD. The weak sections of the Spinal Drain (because of bank elevation and capacity
constraints) have been identified. The simulation results indicate that most of the spinal drain
(with design parameters) could function without overtopping at 7,000 cfs flow levels.
Examples of model output show its potential and scope for further applications.
4.2.2.2 Backwater flow from LBOD to main/branch drains
Under the normal conditions, drainage water levels in the spinal drain are two to three feet
lower than the out-falling main and branch drains. The spinal drain was designed at the
lowest available ridge, while elevation of the out-falling drains is governed by their service
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
16
areas. During flood operations, all the structures become submerged. Increased water levels
in the LBOD and relatively lower levels in a branch drain can make the working head
negative causing a backwater flow from the Spinal to a secondary drain. During floods, this
situation may continue for many days. The high bank-full volume of water in the LBOD
Spinal and a negative working head can push large volume of water back into the secondary
system causing overtopping and breaches.
4.2.2.3 Simulation of Actual Profile of LBOD
A detailed model was built to represent the actual physical parameters. The physical data was
based on a cross-sectional survey undertaken by NESPAK in 2008 for preparing a
rehabilitation study for LBOD, DPOD and KPOD. A comparison with limited survey in 2011
show that the physical data of 2008, adequately represents the pre-flood conditions of the
network.
The cross-sections are entered as x-y coordinates at all critical locations; head and tail of each
reach, upstream and downstream of outfalls. Actual sections show scouring, deepening and
narrowing of the bed in some reaches, sediment deposition mostly along the left side and
increase in the top width. Berms of the LBOD have been eroded or shifted along most of its
length. The inspection path has been raised in the tail reaches after the floods of 2003 and
2006.
The simulations confirm the performance of the LBOD during floods of 2011 was
satisfactory. Higher discharges could pass through the actual sections. However, increase in
the capacity is not uniform, following variations in the size and shape of the new sections.
Because of the geometrical changes, water surface profile, depth, top width and other
hydraulic parameters show different patterns for the four flow ranges (1300 cfs, 4400 cfs,
7000 cfs and 9000 cfs). Changes in the hydraulic parameters have been compared with the
design, and the changes in the top-width and depth at minimum and maximum flows has been
discussed in the report.
A scenario is presented to develop an optimal cross-sectional profile of the spinal drain to
accommodate 9,000 cfs flows in the tail reach. Starting from the actual section, new cross-
sectional templates were developed for all the reaches. These simulations show that the
LBOD can be restored to a new capacity level by adopting and regularizing already increased
top-width and raised berms. All the hydraulic parameters for the new sections were calculated
and compared with the existing geometry and presented as tables. The model can compute
detail of physical changes with reference to any previous sections and can directly estimate
cut and fill quantities for the changes confirmed by the user.
4.2.3 Simulations for Offloading Discharge of LBOD
To offload LBOD during floods, three diversion weirs are simulated comparing impacts on
the discharges and the water levels. The weirs are placed in the reaches receiving runoff
generated in the Sanghar, Mirpurkhas and Badin sub-catchments. To maximize water level
control, weirs are kept 80 ft wide and shallow in depth. To represent high flood situation,
downstream water levels were not fixed allowing submergence. The offloading of 3,000 cfs
is targeted at the maximum flows. The diversions start at the design flows of 4,400 cfs by
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
17
diverting 450 cfs, because of increased water levels in the Spinal. About 2,000 cfs will be
diverted at 7,000 cfs. The diversion weir at RD 203 would be the most effective. However,
the diverted volume of storm water will be influenced by the relative drainage contribution
from different sub-catchments and downstream water levels. The locations of a weir will also
influence its role in water-level control. The weir parameters defined in the model can be
easily changed to compare more options.
The hydraulic performance of the existing DPOD weir and bifurcation of LBOD at RD 159
has been analyzed for three weir crest levels, such as 12.8 ft, 10,3 ft and 8.3 ft. The discharge
at RD 159 varies from 1,300 cfs to 9,000 cfs. Results include:
i) water distribution pattern between KPOD and DPOD,
ii) impact of weir height on the water levels in the LBOD, and
iii) scope of further lowering of the weir, if any
Unsteady state simulations are used for the analysis. Results include discharge and levels at
which DPOD starts functioning, water division between KPOD and DPOD, and influence of
submergence in DPOD. A gated structure replacing the existing weir will be more effective at
low flows.
Evolution of water surface profiles in LBOD, KPOD and DPOD, from low to high flows at
six hours interval has been plotted to show the combined influence of relative slopes and
capacities available in the three channels. At high flows, submergence of the structure
increases because of flat water profiles in DPOD. While, KPOD is much less submerged as
its actual slope is relatively steep.
The hydraulic simulations show the potential of using a well calibrated hydraulic model for
the selection of design parameters, understanding and managing optimal operations during
floods and analyzing comparative performance over a historical period is highly promising.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
18
5 THE PROPOSED INTERVENTIONS/PROJECTS
5.1 Interventions Proposed and Agreed by the Stakeholders
The participatory consultative approach was used throughout all consultations. The
stakeholders were given detailed presentations on issues and problems identified during the
first phase of the project. Based on the findings, the Consultants have considered and
identified several interventions as solutions of the issues and problems. These are presented
in the following table.
Table 1: Issues Problems and Proposed Solutions
Issue & problems Proposed intervention / solutions
1. Rehabilitation and Improvement of LBOD Drainage Infrastructure
The outfall drainage system has caused
significant degradation of natural
resources such as farm land, wetlands, and
has negative impact on quality of life and
livelihoods in the tail reaches of LBOD.
The reasons include overflow of storm
water from the drainage network, tidal
effect in KPOD and Badin area drains, sea
water intrusion in the dhands, and ponding
during foods the upper portions of Badin
Stakeholders located in some of the
settlements along the KPOD felt
threatened by overtopping of KPOD and
desired fortification.
Rehabilitation of Nawabshah, Sanghar,
Mirpurkhas components, and Badin area
Drainage systems.
Rehabilitation/remodeling of spinal drains
Rehabilitation of KPOD
Remodeling of DPOD for 4,000 cfs
Provision of structure with vertical sliding
gates on KPOD at suitable location to check
Tidal effects in KPOD and Badin area drains
Protection embankments be provided for
settlements located along the KPOD.
2. Revival of Natural Waterways To Drain Out Storm water
The absence of uninterrupted natural
waterways result in the ponding and
delayed evacuation of storm water floods
causing considerable damage to the
standing crops, private properties, physical
and productive, and communications
infrastructure. Moreover, the storm water
is lost to the sea, whereas it could be
harvested and stored.
Revival and reactivation of dhoras, and
removal of encroachments to provide free
passage to the storm water towards depressions
in the Thar Desert;
Provision of bypasses to protect the urban
settlements;
Provision of structures to off load pressure
on LBOD system during high flood season; and
Facilitate timely evacuation of storm water
flows from areas presently not served by the
LBOD and or other drainage systems
3. Rehabilitation of LBOD and SCARP Tubewells
The performance of SCARP tubewells is
abysmal as more than 50 percent
tubewells are dysfunctional or non-
operational. At most places the pumps,
Refurbishment of SGW SCARP tubewells,
and its operation and maintenance.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
19
Issue & problems Proposed intervention / solutions
motors, electrical fitting, PMTs, and even
the LTL and HTL has been vandalized.
This is causing reversal of saline water
table.
4. Ghotki SCARP (Saline Zone)
The water logging and salinity
situation is worsening in the Ghotki area,
and needs a project to mitigate the
situation.
A salinity control project was prepared
by the Consultants hired by WAPDA. The
stakeholders desire that drainage projects
is implemented to control the rising water
table to arrest the decreasing farm
productivity.
A review needs to be undertaken to assess
the current situation and update the existing
feasibility report and make recommendations
accordingly, if the project is feasible. Also
suggest any modification, if required.
The stakeholders are generally not
satisfied with the performance of the fresh
ground water tubewells, and desired that
their performance is improved.
In pursuance of the policy of the GoS, that
no further fresh groundwater will be funded, and
the existing ones are divested. Also in areas
where the FGW SCARP tubewells will be
divested, credit line will be arranged to help
farmers to invest in the development of private
tubewells. A review of existing feasibility
prepared by the consultants engaged for the
purpose needs to be undertaken to update its
findings and making recommendations
accordingly
6. Second Line of Defense for the Left Bank of Indus d/s Kotri
Communities along the flood
protection bunds feel vulnerable to flood
havoc.
Second Line of Defense for Indus River
Bunds downstream of Kotri Barrage on Left
Bank be constructed in two Stages,
Communities, particularly along the flood
protection bunds and beyond, are apprehensive
of unexpected breaches during floods, thy feel
that they will be trapped between the two bunds
and will suffer major and longer flooding;
Stakeholders also have reservations on the
construction of additional bunds that would
involve land acquisition and resettlement issues;
They proposed to strengthen the original
band to avoid possible breaches in the area
7. Elevated Platforms for Flood Displaced Persons
Absence of any higher ground for
taking refuge by marooned communities
Elevated platforms or widened sections along
the roads, and canal bunds would also help in
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
20
Issue & problems Proposed intervention / solutions
refuging from inundation.
8. Rehabilitation of Coastal Wetlands
Failure of the Cholri Weir and
breaches in the bunds have caused
brackish water dhands turned into marine.
The entire ecosystem has changed
affecting the fauna and flora of the dhand
complex
The livelihood opportunities have
dwindled
The LBOD/KPOD outfall
infrastructure was not designed properly
and has caused miseries to the
communities in lower reaches
Stakeholder‘s are apprehensive of any
reconstruction or extension of LBOD
and/or KPOD
The dhands shall be provided with a bund
about 500 m from the Tidal Link to allow
breathing space for the tidal water
This 500 m distance will be occupied by
mangrove plantation and other local tree species
to minimize the erosion due to rains and tidal
effects
The bund shall extend from the northern end
of the dhands moving southwards and westward
cordoning the entire dhand complex with an
embankment
From the KPOD side at RD(-12) a diversion
canal shall be provided with a gated structure to
allow the storm water from KPOD to enter in
dhands to a manageable capacity.
From southern side, a sluice gate with a
channel shall be provided to evacuate the
dhands when the water in dhands reach to a
risky level
Divert storm water from LBOD, reducing
the discharge in the main drain, thus making it
safer for the people and land in Badin and
Thatta Districts.
Storm water of up to 2,000 cusecs will be
offloaded from KPOD to the dhands through
this arrangement. Thus the dhands will have
water of good quality suitable for local fish
species and for the reed grass for the livestock
of the local communities. Likewise the
environment of dhands will attract the migratory
birds and water fowl nesting and breeding.
9. Protective Plantation of Mangroves in the Coastal Areas of Left Bank
Sea water intrusion is damaging crop
lands, and fresh water bodies
Coastal erosion
Deforestation of mangroves
Decline of fish resource
Limited livelihood opportunities
Fragile coastal environment
Raising of mangrove and salt resistant plant
nurseries
Plantation of mangroves to protect wetlands
and tidal link
Plant mangroves in blank mudflats in coastal
areas (in backwater and frontage of sea)
Raising of salt tolerant tree species in supra
tidal zone
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
21
Issue & problems Proposed intervention / solutions
10 Use of Drainage Water for Forestation in the LBOD and Kotri Areas
Continuous deforestation is causing
degradation of forest and agro ecosystems,
thereby declining productivity of forest
and farmlands
Shortage of tree resource and
associated services
Lack of participatory approach and
coordination
Decline in per ha vegetation cover
Limited livelihood opportunities
Provision of drainage water for forestation in
forest and farm lands close to the LBOD
system;
Supplement fresh water with drainage water
to reduce water shortage.
11. Biosaline Agriculture in Badin and Thatta Districts
Water scarcity below Kotri barrage has
adversely affected the agro-ecosystems.
The persistent drought conditions since
last decade has degraded lands
leaving the lands without crop for
prolong periods induce desertification and
reduce productivity
Reduced production resulted in decline
in livelihood opportunities.
Bio-saline agriculture can be practiced on
marginal saline lands using brackish water for
growing salt tolerant food and fodder crops,
bushes and trees
Surface drains mostly carry pancho water
from rice fields that has the TDS up to 2.0 dS/m
and can be used for growing salt tolerant species
of crops, grasses and halophytes.
This intervention can best utilize our water
resources on one hand and can reduce load on
drainage outfall on the other.
By growing crops, grasses and trees that help
reduce the soil salinity will be grown to
rehabilitate the salt affected soils on one hand
and provide livelihood for the farmers on the
other
12. Rehabilitation of Deh Akro II and Chotiari Wetland Complex
The ecosystem in the wetland is under
severe threat causing damage to the
wildlife and economy. The seepage from
the Chotiari lake is causing water logging
and salinity
Revival of wetland complex with assured
supplies allocated from the Nara canal system,
and
Construction of interceptor drains to check
seepage from the Chotiari lake
13. Shrimp and Mud Crab Farming in the Coastal Areas of Left Bank
Depleting fish resources in the coastal
area has reduced livelihood opportunities,
has also increased poverty.
Promotion of shrimp and mud crab production
14. Brackish Water Fish farming in LBOD Area
Livelihood for fishermen community
of the area has declined, due to
Construction of earthen fish ponds on private
lands located in the command area of LBOD.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
22
Issue & problems Proposed intervention / solutions
degradation of fisheries resources due to
deterioration of the dhands water quality Establish brackish water fish hatcheries
Involve fish farmers in identification of
areas for fish ponds
Conduct on the job trainings to fish farmers
for capacity building
15. Establishment of Disaster Management Cell in SIDA
Absence of community awareness
regarding preparing and coping with water
hazards.
Also there is no advance warning
mechanism
Establishment of a SIDA Disaster/Crisis
Management Cell for preparing, training and
coordinating plans for emergency response
services in case of emergency situations and
disasters within SIDA‘s ordinance.
Provision of training to the SIDA staff
16. Gender Mainstreaming In Irrigation and Drainage
The enabling environment for women
to play active role in water management is
missing, and the SIDA, AWB, and FOs
need to be made aware of gender
sensitivities
Support to be provided to the Social section
in SIDA to organize training courses to sensitize
the stakeholders
17. Drainage Effluent Intrusion in the Ghotki Area from Southern Punjab
Drainage effluent intrusion from
Southern Punjab into the Ghotki Area is
causing degradation of land
Analysis of the situation and identification of
mitigation options, and actions to be taken at the
intergovernmental level
18. Sugar Industry Effluent Treatment at Source
Water sources, both surface water and
groundwater, are increasingly polluted due
to unchecked disposal of untreated
pollutants emanating from the increasing
disposal of urban sewerage and solid
waste, leaching of agrochemicals,
untreated hazardous industrial waste,
particularly from sugar mills.
Despite cost effective available
techniques, there is a lack of compliance
and ineffectiveness of EPA to control
pollution and contamination of water ways
and of the drainage system.
Depending upon the resources available any
of the physical, chemical or biological treatment
technologies may be used to treat the
wastewaters at source before disposing it off
into streams.
Four stages of wastewater treatment are
commonly employed all over the world for
treating industrial wastewaters. These are:
1)Preliminary treatment 2) Primary treatment 3)
secondary treatment and 4) Tertiary treatment
Up flow Anaerobic Sludge Blanket (UASB)
system for treatment of highly concentrated
wastewater from agriculture industries is
increasingly popular and wastewater from sugar
mills and distilleries can be treated for
significant reduction in pollution levels.
Methane gas produced in USAB system can be
used as an energy source.
Lagoons have several advantages when used
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
23
Issue & problems Proposed intervention / solutions
correctly. They can be used for secondary
treatment or as a supplement to other processes.
While treatment ponds require substantial land
area and are predominantly used by smaller
communities.
19. Access to Potable Water in the Left Bank
Safe and clean drinking water is not
available particularly in the saline
underground water areas and in the delta
and coastal areas.
Untreated municipal sewage disposed
off into freshwater bodies is used for
domestic purposes by thousands of people
living in areas with brackish underground
water.
Less than 8% of total wastewater
released daily is, only partially treated
before it is released into the surface water
bodies.
For small towns or villages the ultra
filtration cell is a cost effective proposition.
Each cell can provide about 500 gallons per hr
safe drinking water to the surrounding
community of say 2,000 people. The feed water
to the plant, however, should not contain TDS
more than 700 mg/l.
In study area, where the ground water is
brackish & only source of drinking, there is a
greater need to treat ground water to remove
salinity (TDS) & other contaminants so that it is
safe for dinking. The Reverse Osmosis (RO)
technology is an appropriate for this purpose.
This technology was expensive before but now
is available at affordable cost.
5.2 Typology of the Approved Interventions
During the Phase II of the Study, pre-feasibilities were prepared for eight structural, six
nonstructural, and two institutional interventions that were selected and agreed in the national
workshop. In addition to this three position papers were developed to address and recommend
actions required to the identified relevant issues. The following section outlines the salient
features of the proposed interventions to be reviewed and selection, prioritized by the
stakeholders. In the next phase of the study detailed feasibilities will be pursued for the
selected ones. The list of the prefeasibility and the position papers prepared during this phase
of the study are as under:
Table 2: Pre-feasibility Interventions / Position Papers
A Structural Interventions
1. Rehabilitation and Improvement of LBOD Drainage Infrastructure
2. Revival of Natural Waterways to Drain out Strom Water.
3. Rehabilitation of LBOD and SCARP Tubewells
4. Ghotki SCARP (Saline Zone)
5. Privatization of FGW SCARP Tubewells
6. Second Line of Defense for Left Bank of Indus D/S Kotri
7. Elevated Platforms for Flood Displaced Persons
8. Rehabilitation of Coastal Wetlands
B Quasi Structural Interventions
9. Protective Plantation of Mangroves in the Coastal Areas of Left Bank
10. Use of Drainage Water for Forestation in the LBOD and Kotri Areas
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
24
11. Bio-saline Agriculture in Badin and Thatta Districts
12. Rehabilitation of Deh Akro II and Chotiari Wetland Complex
13. Shrimp and Mud Crab Farming in Coastal areas of Left Bank
14. Brackish Water Fish Farming in LBOD Area
C Institutional Interventions
15. Establishment of Disaster Management Unit in SIDA
16. Gender Mainstreaming in Irrigation and Drainage
D Position Papers
17. Drainage Effluent Intrusion in the Ghotki Area from Southern Punjab
18. Sugar Industry Effluent Treatment at Source
19. Access to Potable Water in the Left Bank
5.3 Brief Description of Pre-feasibilities of Suggested Interventions
Following is a brief digests of the 16 prefeasibility and 3 position papers that were agreed in
the last national workshops. For details please refer to the detailed pre-feasibilities presented
in Volume II, of the Final Report.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
25
Box 1: Profile of Spinal Drain
Length (RD) 657
Discharge (cfs) 1240 – 4600
Bed width (ft) 85 -162
Depth (ft) 8.75 -13.33
Side Slope (-) 1:03
Berm width (ft) 20
Longitudinal Slope (ft/ft) 0.000118 - 0.00005
5.3.1 Pre-feasibility 1: Rehabilitation and Improvement of LBOD Drainage
Infrastructure
Introduction/Rationale
The LBOD network, serving Shaheed Benazirabad, Sanghar, and Mirpurkhas districts, and
the Badin area drainage system was built during 1985 and 2003 to dispose off the drainage
effluent aka the base flow generating from the tile drains and saline ground water (SGW)
tubewells, and the storm water flows (SWF) generated by runoff in the catchment area.
The above mentioned drainage system provides relief to the cultural command area of about
1.73 million acres irrigated by Rohri, Nara and Akram Wah canal systems encompassing
Shaheed Benazirabad, Sanghar, Mirpur Khas and Badin districts.
During the last three decades, particularly in 1994, 2003, 2006, and 2011, the left bank of
Indus experienced repeated extreme rainfall events that caused colossal damage to human
lives, agriculture, particularly standing crops, livestock, stored grains, private and public
properties, productive and physical infrastructures. A large segment of population was
marooned and or displaced constraining their access to social services, and livelihoods, till
the return of normality. It is anticipated that due to climatic changes coming decades will
witness occurrence of such extreme weather conditions more frequently. The situation is
further exasperated by damage to tidal link and collapse of Cholri Weir, causing sea
encroachment during high tides, degrading large tracts of productive land and depressing its
productivity potential, and salinizing the fresh water bodies diminishing their fish production
potential. This has led to loss of livelihood of considerable populace.
The drainage system is in dilapidated
state, and the existing capacity of the
LBOD and Badin area drains is
insufficient to drain out the storm water
within a period of three to five days. In
the past years when the rainfall
exceeded the designed capacity, causes
inundation of the low lying areas, and
the stagnation for longer periods. This is
may be due to the deferred maintenance,
and unauthorized breaches by the
farmers along the drains and irrigation
canals to dewater their stagnant water from their fields. The weak banks with lack of
adequate free board (FB) are prone to breaches and flooding of the area. The situation is
further exasperated due to the submergence of drains at point of outfall, blocking the flows in
the network and resulting in overtopping and breaches and relief cuts. The irrigation water of
canal escapes and breaches of channels adds to the pressure.
In August and September of 2011, most parts of left bank of Indus received ever maximum
rainfall of 500 to 1,200 mm, inundated most areas with an average depth of three to four feet.
The average rainfall of was about 300 mm within 24 to 48 hours and was two to three times
exceeding the existing capacity of drainage system. The heavy rainfall in the Shaheed
Benazirabad, Sanghar, and Mirpurkhas districts generated a runoff of about 15,000 cfs, while
LBOD system was designed for a discharge of 4,600 cfs.
During the 2011 floods, despite less capacity of the drains, obstructions in the system,
encroachments in the water ways causing overtopping and breaches at a number of places,
the system performed better than anticipated. The high level of water in the spinal drain
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
26
caused submergence of the MMD and the LBOD branch drains resulting in the inundation of
adjoining villages and towns, severely damaging the life and property. Many farmers gave
relief cuts to the banks of the spinal and branch drains to evacuate the storm water. The
damage to the drainage infrastructure was enormous and quite a few watercourse aqueducts
collapsed and bridges were damaged.
To ensure the safe disposal of the storm water and to avoid the sea intrusion it is suggested
that the proposed interventions are carried out in two phases. Consultants recommend that the
emergency works be completed by June 2012, including desilting of the drain beds,
restoration of the freeboard, repair of damaged inlets, and stone pitching at vulnerable points.
It is expected that the proposed intervention would decrease the inundation period and depth
of submergence in a manner that would reduce the vulnerability to damage to the water
hazards damaging the life and property of the communities along the drainage system, and
does not disrupt their normal life and livelihoods. The provision of freeboard would also
serve as an insurance to carry discharge like the one witnessed during 2011 rainy season. In
addition to this, the intervention aims in reducing the negative impact of seawater intrusion.
Project Zone of Influence
The proposed project will rehabilitate surface drainage systems located in the districts of
Shaheed Benazirabad, Sanghar, Mirpurkhas, and Badin.
Objective:
The main objectives are to:
i. ensure safe, timely, and unconstrained disposal of drainage and storm water;
ii. to rehabilitate and improve the existing LBOD infrastructure;
iii. to divert storm water to dhoras and Thar area under extreme rainfall events
Outputs
Following structural and nonstructural interventions will be in place by the end of the project
implementation period. The structural interventions have been verified by using hydraulic
model of HEC-RAS for optimization of the solutions by predicting water levels and
discharge distribution in the network of spinal drain. The intervention of off-loading of 3,000
cfs from the spinal drain was simulated to optimize the location of weirs. The detailed
feasibility of above interventions has been initiated, and would be completed during the
Phase III of the study. The outputs are:
Table 3: Main Outputs of the Pre Feasibility No. 1
No Main Outputs
Start
Date End Date
1. Restoration of Spinal Drain (RD 815 to 159) including Structure repair 4/2012 12/2013
2. Restoration of DPOD (RD127 to RD 5) 4/2012 12/2013
3. Restoration of KPOD (RD 159 to RD 0) 4/2012 12/2013
4. Restoration of LBOD branches, KPOD, and other drains 4/2012 12/2013
5. Restoration of Mirpurkhas component surface drains 4/2012 12/2013
6. Restoration of Sanghar component Surface drains 4/2012 12/2013
7. Restoration of Nawabshah component 4/2012 12/2013
8. Restoration of Fulleli Guni drainage system 4/2012 12/2013
9. Restoration of Karo Gungro drainage system 4/2012 12/2013
10. Remodeling of LBOD drainage system for a return period of 20 years 7/2014 6/2020
11. Remodeling of KPOD to discharge of 6,000 cfs; 7/2014 6/2020
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
27
No Main Outputs
Start
Date End Date
12. Remodeling of Mirpur Khas Main Drain for Separation from Dhoro Puran. 7/2014 6/2020
13. Converting Non-Inspection Path (NIP) of Spinal/Main & all Branch drains to
par with IP 7/2014 6/2020
14. Construction of All Weather Road from RD 159 of Spinal Drain to RD 815 of
Spinal Drain. (131 miles) 7/2014 6/2020
15. Providing Pumping arrangements at outfall points of Badin Drainage System 7/2014 6/2020
16. Construction of New Bridges +WC Aqueducts on LBOD System 7/2014 6/2020
17. Construction of new inlets to support of farm drainage 7/2014 6/2020
18. Construction of Tidal Control Regulator at RD minus 12 of KPOD 7/2014 6/2020
19. Construction of Head Regulator of KPOD RD 159 7/2014 6/2020
20. Ancillary works undertaken 7/2012 12/2013
21. Supervision Consultants appointed 4/2012 12/2013
22. Site offices and residential quarters constructed 7/2012 12/2013
23. Boats and vehicles procured 7/2012 12/2013
24. Survey and scientific equipment procured 7/2012 12/2013
25. Radio communication system procured and installed 7/2012 12/2013
26. Early warning system established and operative 7/2012 12/2013
The outputs mentioned above include the emergency works, such as i) commencement of
desilting of the drainage network, raising of the embankments to maintain minimum two feet
freeboard; and iii) restoration of damaged structures. These works has already been
commissioned and are to be completed by end of the financial year 2011/12.
Requisite interventions/Standard Operating Procedures
It is proposed that the following actions are strictly complied with: i) the main canals systems
are closed at least one week before start of rainfall warning; and ii) each year the heavy earth
moving machinery is mobilized at all the vulnerable points by the middle of July.
Outcome and Impact
The main impact of the interventions will be significant reduction in damages to the standing
crops, livestock, private and public properties, and livelihood of the communities, particularly
of farm and landless household. This would also ensure uninterrupted access to social
services. In addition to this the arresting of the seawater intrusion will restore the productivity
of the degraded land and water bodies supported livelihood of displaced farmers and the
fisher folks.
Estimated Cost of Interventions
The total cost of the project is estimated as Rs.17.6 billion including Rs.1.6 billion allocated
for the emergency repair and restoration works to be completed by June 2012. The detail of
financial year (FY) wise expenditure on various interventions/subprojects is presented in the
Table 4. After the completion of these interventions, a recurring annual expenditure estimated
at Rs.500 million would be required for the O&M and monitoring of the system.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
28
Table 4: Indicative Cost Estimates for the Rehabilitation and Remodeling of LBOD
Infrastructure. (Rs. Million)
No Main Outputs 2011/12 2012/13 2013/14 2014/20 Total
1 Restoration of Spinal Drain (RD 815 to 159) including
Structure repair 700 740 560 2,000
2 Restoration of DPOD (RD127 to RD 5) 100 200 274 574
3 Restoration of KPOD (RD 159 to RD 0) 60 40 31 131
4 Restoration of LBOD branches, KPOD, and other drains 40 280 245 565
5 Restoration of Mirpurkhas component surface drains 110 120 170 400
6 Restoration of Sanghar component Surface drains 95 140 65 300
7 Restoration of Nawabshah component 300 200 - 500
8 Restoration of Fulleli Guni drainage system 70 145 135 350
9 Restoration of Karo Gungro drainage system 30 154 40 224
10 Remodeling of LBOD drainage system for a return period
of 20 years 4,000 4,000
11 Remodeling of KPOD to discharge of 6,000 cfs; 300 300
12 Remodeling of Mirpur Khas Main Drain for Separation
from Dhoro Puran. 1,450 1,450
13 Converting Non-Inspection Path (NIP) of Spinal/Main &
all Branch drains to par with IP 1,500 1,500
14 Construction of All Weather Road from RD 159 of Spinal
Drain to RD 815 of Spinal Drain. (131 miles) 300 300
15 Providing Pumping arrangements at outfall points of
Badin Drainage System 1,000 1,000
16 Construction of New Bridges +WC Aqueducts on LBOD
System 1,350 1,350
17 Construction of new inlets to support of farm drainage 200 200
18 Construction of Tidal Control Regulator at RD minus 12
of KPOD 650 650
19 Construction of Head Regulator of KPOD RD 159 350 350
Subtotal 16,144
Physical and price contingency @ 2% 323
Total 16,467
Miscellaneous Support Costs
20 Ancillary works 490 140 630
21 Supervision Consultants 25 45 32 181 282
22 Construction of site offices and residential quarters 30 20 50
23 Procurement of boats and vehicles 8 20 72 100
24 Procurement of survey and scientific equipment 15 5 20
25 Procurement of radio communication system 5 5
26 Unallocated 5 5
Subtotal 1,092
Physical contingency @ 2% 22
Total 1,113
Grand Total Cost 17,580
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
29
Project Viability
Based on estimated of damages reported by Provincial Disaster Management Authority
(PDMA), for 2011 flood, it is anticipated that the project would be economically viable. The
IRR estimated jointly for this intervention and revival of natural waterways indicates that the
estimated internal rate of financial return of return (IFRR), based on financial prices, is about
18.1 percent. Nonetheless, detailed analysis and estimation of internal economic rate of return
(IRR) will be undertaken during the Phase III of the study, based on sample surveys in the
affected areas.
Proposed Implementation arrangements
The short term works of emergency nature and medium term measures are to be contracted
out by following the normal tendering process; while the long term interventions will follow
the international bidding route.
Safeguards
Notwithstanding with the technical requirements, detailed environment assessment and
mitigation plan, and resettlement requirements and the resettlement action plan will be
prepared in the phase III of the study, along with its costs.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
30
5.3.2 Pre-feasibility 2: Revival of Natural Waterways to Drain out Storm Water
Introduction/Rationale
In Sindh there are many short and long reaches of the abandoned river courses on both
sides of Indus. These abandoned river courses used to serve as waterways aka dhoras,
for river and storm floods. Historically these dhoras braided with several small tributaries
served as a network of natural drainage.
Over the time these dhoras have been obstructed by infrastructure such as roads, canals,
drains and unauthorized settlements. Similarly, in many reaches these dhoras have also
been interspersed by cultivation. These obstructions delay the evacuation of flood
waters, causing ponding and inundation of standing crops, loss of livestock, and at times
human lives, in addition to damage to infrastructure. The extreme rainfall event in the year
2011 was a wakeup call, which caused unparalleled loss to the human lives, marooning of
settlements, standing crops, livestock, damage to the physical and productive infrastructure,
means of communications, displacement of flood affected population and their livelihoods.
According to the recent report of PDMA the estimated value of damages from the 2011 flood
is about Rs.454 billion.
This calamity challenged the ability to cope with such a catastrophe, and warranted correction
and mitigation measures to avert similar miseries, in the event of reoccurrence of rains of
alike magnitude in future. This experience also provided an opportunity to evaluate the
performance of the drainage network, need for its strengthening, and to explore ways to
offload pressure on the drainage system. This also flagged the need for exploring ways to
evacuate areas presently not served and connected to the drainage network. This state of
affair also underscored the need to revive the network, removing obstructions, and diverting
the flood waters to the natural depressions in the Thar Desert.
To address this issue, the Consultants evaluated the possibility of employing the dormant
dhoras to ensure safe disposal of flood waters. During the course of the prefeasibility study, a
number of such potential dhoras were identified, located in the area on the left bank of Indus.
They include, Rainee Dhoro, Hussainabad-Mehrabpur Dhoro, Kandiaro-Moro Dhoro,
Miranpur-Bachal Rahu Dhoro, Sohni Dhoro, Bhaikhan Dhoro, Puran Dhoro, Digri / Sarfraz
Dhoro, Pangrio Dhoro, Hakro Dhoro, Naro Dhoro, and Pithoro Dhoro.
The field visits validated that the storm water from the catchment area ponds in these dhoras,
spills over and inundates the crops and settlements, due to blockages, and absence of outlet
for evacuating the ponded storm water.
To mitigate the situation, revival of these natural water ways is critical. The reactivation of
these dhoras would not only dispose off the storm water, will also serve as interceptor drains
to check the rising water table. Moreover, the storm water in the dhoras can be utilized by the
farmers at the tails of deficit irrigation channels after lifting through pumps.
Project Objectives
The main objectives of this intervention are to:
i. facilitate evacuation of storm water flows; and
ii. offload the pressure on the existing drainage network;
iii. protect the settlements with bypasses where critical; and
iv. harvest flood waters and its storage in the natural depressions located in the Thar
Desert
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
31
Project location
The project area will cover the command areas of Ghotki, Sukkur, and Kotri Barrages,
particularly the areas that are presently not connected to any drainage network. This project
area will also include parts of the Thar Desert where most potential depressions are located.
Project output
The main outputs that would be accomplished include:
Table 5: Main outputs of the Pre Feasibility No2
No Main Outputs Start Date End Date
Revival of Dhoras
1 Activation of dhoras, Puran up to Shakoor dhand, Sohni dhoro &
Bhai Khan dhoro and bypasses of Mirpurkhas, Jhuddo, Tando
Ghulam Ali
4/2012 6/2020
2 Activation & Restoration of pocket drains along Hiral escape/
Pithoro Dhoro, Hakro Dhoro & Naro (Nabisar) Dhoro i/c Naukot
bypass
4/2012 6/2020
3 Activation of Sarfaraz (Digri) Dhoro, including Digri bypasses 4/2012 6/2020
4 Excavation and revival of Pangrio, Kh‘ Gumbo & Roshanabad
dhoras 7/2014 6/2020
5 Excavation and revival of Ghotki dhoras 7/2014 6/2020
6 Excavation and revival of Khairpur South dhoras 7/2014 6/2020
Leftover Areas
7 Construction of surface drains in T.Adam, T.Allahyar, T.M Khan
and T.G. Ali area 7/2014 6/2020
8 Construction of surface drains in Digri area 7/2014 6/2020
9 Construction of surface drains in Umerkot, Farash and Khipro area 7/2014 6/2020
10 Construction of surface drains in Ghotki area 7/2014 6/2020
11 Construction of surface drains in Khairpur South area 7/2014 6/2020
LBOD Escapes 12 Construction of 3X Escapes on LBOD i/c Weirs and Link Channels 7/2014 6/2020
The outputs mentioned above include the emergency works, such as: channelization of the
dhoras, provision of bypasses where needed, clearance of encroachments and land
acquisition, and increasing the capacity of structures. These works have already been
commissioned and are to be completed by end of the financial year 2011/12.
Outcome and Impact
It is expected that the revival and reactivation of dhoras and providing safe and uninterrupted
passage to the storm water generated in the catchment areas presently not connected with the
existing drainage structures will evacuate water with minimal disruption to human lives,
damage to the standing crops, loss of livestock, damage to the public and private properties
and infrastructure. It would avert the colossal loss to the economy and livelihoods. Timely
evacuation of storm water will also provide continual access to social services, such as
education, health, and drinking water supply.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
32
Project Cost
The estimated indicative cost for activation of the proposed intervention is estimated at Rs.
42.7 billion. The detail of financial year (FY) wise expenditure on various major activities,
including emergency works that are to be completed by June 2012, is presented in the Table
6.
Table 6: Indicative Cost Estimates for the Revival of Dhoras including bypasses (Rs. Million)
S.No Main Outputs 2011/12 2012/13 2013/14 2014/20 Total
Revival of Dhoras
1 Activation of dhoras, Puran upto Shakoor dhand, Sohni dhoro &
Bhai Khan dhoro and bypasses of Mirpurkhas, Jhuddo, Tando
Ghulam Ali
65 615 1,320 16,409 18,409
2 Activation & Restoration of pocket drains along Hiral escape/
Pithoro Dhoro, Hakro Dhoro & Naro (Nabisar) Dhoro i/c Naukot
bypass
30 180 200 4,303 4,713
3 Activation of Sarfaraz (Digri) Dhoro, including Digri bypasses 7 27 271 286 591
4 Excavation and revival of Pangrio, Kh‘ Gumbo & Roshanabad
dhoras - - - 703 703
5 Excavation and revival of Ghotki dhoras - - - 2,160 2,160
6 Excavation and revival of Khairpur South dhoras - - - 3,057 3,057
Leftover Areas
7 Construction of surface drains in T.Adam, T.Allahyar, T.M Khan
and T.G. Ali area - - - 4,668 4,668
8 Construction of surface drains in Digri area - - - 1,149 1,149
9 Construction of surface drains in Umerkot, Farash and Khipro
area - - - 5,080 5,080
10 Construction of surface drains in Ghotki area - - - 2,111 2,111
11 Construction of surface drains in Khairpur South area - - - 434 434
LBOD Escapes
12 Construction of 3X Escapes on LBOD i/c Weirs and Link
Channels - - - 490 490
Grand Total 102 822 1,791 40,850 43,565
Project Viability
The project and its subprojects are still in the design stage. However it is anticipated that the
proposed intervention will have significant payoff in terms of losses averted and saved. This
will also require intensive field surveys to account for benefits from individual subprojects.
These will be accomplished during the preparation of detailed feasibility. Based on estimated
of damages reported by Provincial Disaster Management Authority (PDMA), for 2011 flood,
it is anticipated that the project would be economically viable. The IFRR estimated jointly for
this intervention and rehabilitation of LBOD is about 18.1 percent. Nonetheless, detailed
analysis and estimation of economic IERR will be undertaken during the Phase III of the
study, based on sample surveys in the affected areas.
Implementation Arrangements
It is proposed that the project is implemented by SIDA in the AWB areas, and by the IPD in
the areas outside the AWBs, coordinated by the WSIP PCMU.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
33
Given the exigency of intervention, it is proposed that following emergency interventions are
accomplished before the onslaught of 2012 monsoon season, completing the works by 30
June, 2012. The emergency works include:
i. activation of dhoras on left side of the LBOD spinal drain i.e. Hakro Dhoro, Naro
Dhoro and Pithoro Dhoro / Hiral Escape;
ii. activation of the full length of Dhoro Puran from Mirpurkhas to RD 110 of DPOD
including Mirpurkhas bypass.
iii. routing of MMD, Dhoro Puran through its natural path, siphoning it through
spinal drain, and discontinuing its disposal into the LBOD system;
iv. reconstruction of Dhoro Puran sections integrated with the LBOD spinal drain;
v. construction of dhora bypasses proposed at Jhudo, Digri and Naukot towns.
Safeguards
The project is expected to have significant ramifications requiring a careful assessment of
social and environment impacts. This intervention would also require land acquisition, and
involuntary settlements, and preparation of action plan to mitigate any adverse environmental
consequence, and a resettlement action plan for the displaced persons.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
34
5.3.3 Pre-feasibility 3: Rehabilitation of SCARP and Drainage Tubewells of LBOD
System
Rationale
In Sindh, the SCARP tubewells were installed in the left bank area to combat the twin
menace of waterlogging and salinity. These tubewells significantly lowered the water table
and reclaimed the affected land. However, the operational cost and maintenance of the
SCARP tubewells manifold surpassed the abiana/drainage cess collection, a heavy burden on
the exchequer. Moreover, the unauthorized power leakages further exasperated the financial
burden. With the passage of time, due to deferred maintenance, most of the tubewells, as
reported by the beneficiaries, are either dysfunctional or nonoperational.
The ground situation, as reported by the stakeholders is alarming. They reported, and as
verified by the Consultants during the field visits more than 60 percent SGW tubewells are
dysfunctional, due to want of repairs and replacement, vandalizing of pumps, motors,
electrical fittings, transformers, hookups, high or low tension lines, and deferred
maintenance. As per PID records about 740 tubewells out of 1,798 number of tubewells are
out of commission. The stakeholders in the workshops and the beneficiary farmers stated that
this number is an understatement. They also voiced their concern about reversal of
groundwater table, and loss of productivity, and desired that the concerned agencies to
revamp these tubewells and need for timely repairs and control of theft.
Project Zone of Influence
The proposed project will only rehabilitate the LBOD tubewells located in the districts of
Shaheed Benazirabad, Sanghar, Mirpurkhas, and Badin.
Objectives
The main objective of this intervention is to reverse the rising saline ground water level to
restore the productivity of degrading lands through replacing the pilfered tubewells, and
operationalizing the dysfunctional tubewells.
Output
The main output of the proposed intervention will be about 740 rehabilitated drainage
tubewells.
Outcome and Impact
It is expected that the proposed intervention will increase the overall farm productivity and
farm incomes by about five to ten percent in the overall project area.
Project Cost
The total cost of rehabilitating drainage tubewells is estimated at Rs.2,603 million, based on
current prevailing prices.
Project Viability
The indicative IFRR is estimated at 16.8 percent. However, given the past history of
vandalizing of removable parts, such as pumps, motors, electrical fittings, pole mounted
transformers, hook up connections, and LHT and HTL lines, and unauthorized diversion of
power for domestic use, it is apprehended that it is a very risky investment and not
sustainable.
Safeguards
The reduction in the water table will have a positive effect on the environment, and does not
require any resettlement.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
35
5.3.4 Pre-feasibility 4: Ghotki SCARP (Saline Zone)
Rationale
In the Ghotki saline zone area is spread over about 222 thousand ha out of which some 25
thousand ha is severely waterlogged, and the water table is about 3 feet from the surface. One
of the reasons for waterlogging is seepage from the canal system. The situation further
worsened soon after mid-1970 when the canals started receiving perennial supplies.
In 1994, a feasibility of a project covering the severely affected area was prepared by Agrar-
und-Hydrotechnik GMBH in association with NESPAK, commissioned by WAPDA. The
feasibility considered four alternatives: i) construction of surface drainage system for the
entire catchment area spread over 222 thousand ha, together with tile drainage system for 140
thousand ha; ii) provide tile subsurface and surface drainage only to the most affected 25
thousand ha, complemented by watercourse improvement program on 30 thousand ha; iii)
construction of surface drainage to 222 the entire catchment area and lining of the irrigation
network; iv) reversion to non-perennial system as originally designed. The feasibility
Consultants opted for the second option.
During the workshops the stakeholders expressed an urgent need to implement the proposed
salinity control and reclamation project, as the productivity of their lands is fast declining. As
suggested by the stakeholders, the Consultants have reviewed the feasibility to assess its
technical appropriateness and its viability at current prices.
It may please be noted that this Pre-feasibility is essentially a review of the feasibility
prepared by the earlier Consultants. The information on benefits and costs mentioned in the
feasibility has been updated for 2012 prices, assuming other parameters as same, and the rate
of return was re-estimated to assess if the viability parameters still hold.
Objectives
The following were the main objectives of the project, as mentioned in the feasibility
document, namely: were to: i) restore the designed cropping intensity and productivity by
lowering the water table; and ii) disposal of the drainage effluent in an environmental safe
manner.
Project Boundary
The project was expected to serve the canal irrigated area commanded by Ghotki canal
system in saline area.
Output
The main outputs mentioned in the feasibility report under review included: i) a grid of tile
drains serving the 25 thousand ha; ii) 900 km of surface drainage system; and iii) watercourse
improvement on area covering 30,000 ha.
Outcome and Impacts
As per feasibility report, the Project was expected to increase the cropping intensity to 120
percent from 93.5 percent during the then base year in the area where tile drainage is
provided. The project was expected to significantly increase the household income; and by
lowering the water table, would reverse the process of environment degradation.
Estimated Cost
Based on the current prices, the tile drainage and associated infrastructure would cost about
Rs.5.0 billion when updated for 2012 prices.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
36
The review suggests that proposed project prepared by the abovementioned Consultants is
unfeasible and hence it has been replaced by surface drainage network to evacuate the storm
water flows, and has been included in the prefeasibility 2 as one of the subproject.
Project Viability
While re-evaluating the feasibility, only the cost and benefits from the tile drainage and
associated infrastructure were taken into account, and the cost of OFWM improvement was
excluded. It is estimated that at current prices, the IFRR of the intervention would be around
10.9 percent, and hence is not a sound investment.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
37
5.3.5 Pre-feasibility 5: Privatization of FGW SCARP Tubewells
Introduction/Rationale
In Sindh, the SCARP tubewells were installed in the fresh water zones to combat the twin
menace of waterlogging and salinity. These tubewells significantly lowered the water table
and reclaimed the land in the fresh groundwater (FGW) zones, where installed. As intended,
with the availability of additional water for conjunctive use, the cropping intensity and
productivity in the zone of influence increased significantly. This also induced mushrooming
of private tubewells. However, the operational cost and maintenance of the SCARP tubewells
manifold surpassed the abiana/drainage cess collection, a heavy burden on the exchequer.
Moreover, the unauthorized power leakages further exasperated the financial burden. With
the passage of time, due to deferred maintenance, most of the tubewells, as reported by the
beneficiaries, are either nonoperational or dysfunctional. As early as 1980s, the government
decided to divest the public sector FGW SCARP tubewells, and offered the farmers to buy
and operate these as individuals or jointly as an irrigator groups.
In 2008, a feasibility of a project covering the FGW SCARPS areas was prepared by BM
Consultants (Ltd), commissioned by the IPD GoS. The feasibility indicates that proposed
divestment of FGW and support to the private sector to install smaller capacity tubewells.
Given the policy of the government vis-à-vis divesting of these tubewells a feasibility study
for transitioning theses tubewells was prepared in 1998. This study concluded that the
divestment will have high payoff and would reduce the financial burden on the constrained
O&M budget.
In the stakeholder workshops, the
beneficiary farmers voiced their
concern about reversal of
groundwater tale, and loss of
productivity, and desired that the
concerned agencies to take
corrective measures.
It may please be noted that this Pre-
feasibility is essentially a review of
the feasibility prepared by the
earlier Consultants. The information
on benefits and costs mentioned in
the feasibility has been update for
2012 prices, assuming other
parameters as same, and the rate of
return was re-estimated to assess if the viability parameters still hold.
Project Objectives
The objectives of the present study were: i) lowering of the water table to desired level to the
desired level; ii) enhance farm productivity through conjunctive use of the underground
water; iii) encourage and support small farmers groups to jointly own and manage tubewells
ensuring economy of scale; and iv) recover a portion of the capital investment and relieve the
public sector expenditure on O&M of the public sector FGWs.
Project Boundary
The project was to be located in the FGW corridors in Ghotki, Khairpur, Naushehro Feroze
(north Rohri), and Shaheed Benazirabad (South Rohri), Sanghar, and Mirpurkhas districts.
Figure 2: Utilization Factor for SCARP Division
05
101520253035
Uti
liza
tio
n F
acto
r, U
F (
%)
UTILIZATION FACTOR FOR SCARP DIVISIONS
STW PTW
Source: B.M.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
38
Output
A total of about 3,160 tubewells were to be divested in various districts. About 1,110
tubewells are in Ghotki area, followed by, 275 in Khairpur, 575 in Naushero Feroze, and
some 1,220 in Shaheed Benazirabad districts. In addition to this community mobilization and
financial support were to be provided to develop some 9,052 privately individually or jointly
owned tubewells.
Outcome and impact
The transition of SCARP tubewells to private sector would have relieved the government of
the substantial burden of subsidizing well water and providing vertical drainage. It was
expected that this would have improved the reliability of the water supply, and increased the
farm productivity and net farm income. This would have been in line with the poverty
reduction strategy of the government. With the financial support for fostering private tube
wells it was expected that the increase in the water table would be arrested.
Estimated cost
It is estimated that if the project is implemented, the revised cost of the six year project would
be about Rs. 8.3 billion in 2012 prices. The cost of private tubewells will be borne by the
farmers for which a credit line would be arranged.
Project Viability
The feasibility study finalized in 2009, submitted by the BMC consultants did not estimate
the IERR. The reassessment undertaken by present Consultants indicate an indicative IFRR
of about 13.3 percent. However, the sensitivity analysis suggests that the project is sensitive
to cost escalations, and reduction of benefits, and delays in the implementation, hence a risky
investment.
Safeguards
Initial review suggests that the project would have improved the environment and does not
indicate any negative environmental externalities that would need mitigation measures.
Similarly, it would not require any involuntary resettlement.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
39
5.3.6 Pre-feasibility 6: Second Line of Defense for Left Bank of Indus D/S Kotri
Introduction
Bunds along the Indus River in Sindh Province are breached during occurrence of large
floods, either: i) intentionally to protect vital structures, usually barrages, or ii) without
intention due to unfavorably high discharges and development of adverse hydraulic
conditions even though the bunds were well designed and constructed. The August 2010
breaching of the MS Bund, some 50 miles downstream from Kotri, afforded an opportunity
for the LBG/Indus team to investigate first hand possible reasons for a breach, effects of
resultant flooding that affected agriculture, commerce, populations, cities and villages, and
infrastructure including canals, roads, structures, homes and communications. The history of
breaching In this 50 mile long reach of the Indus River is manifested by the six loop bunds, a
system of spurs that extend one mile from the town of Belo to the Ranto Loop Bund and as
confirmed by the record of breaches listed in the Bund Manual.
The major benefit of construction of a second line of defense, providing an embankment
inland from the river along the entire 50 mile vulnerable area, would be disaster avoidance
through restriction flooding to areas, largely rural lands, along the existing bunds, should a
river bund breach.
Currently, neither the national nor the
provincial government has capacity to
fund or organize first responders to
simultaneously address the destruction
of the lives and livelihoods of tens of
thousands of persons across isolated
tracts of lands that have been flooded to
depths of 5 to 20 feet. This proposed
element of the regional plan addresses
this issue for a 50 mile reach of the river
that would be protected through
avoidance rather than periodic
inadequate costly response. Beyond this
initial project, a program that would
extend to the entire left bank and right
bank regions would greatly alleviate and possibly eliminate the disastrous effects of floods
along the Indus River in Sindh Province. The proposed works would have provided
protection from inundation to the communities in the left bank along the Pinyari feeder lower
and the Daro Branch.
Estimated Cost
It is estimated that the financial outlay of the proposed intervention would be about Rs. 2.0
billion.
Project Viability
The participants of the three AWB
workshops the opinion about its social acceptance was mixed. However, in the stakeholder
consultative workshops at the district level, the proposal was overwhelmingly rejected. It
validated the opinion of the communities along the proposed alignment. Given this, the
proposal is considered not socially acceptable. Also, given the exorbitant cost of intervention,
it does not seem to be an economically viable intervention. The stakeholders suggested that
instead the existing bunds should be rehabilitated and strengthened.
Figure 3: Three alternative costs
0
1
2
3
4
5
Bil
lio
n R
up
ees
ALTERNATIVES
Three Alternatives Cost
Alt 1 Alt 2 Alt 3
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
40
5.3.7 Pre-feasibility 7: Elevated Platforms for Flood Displaced Persons
Rationale
Water disasters including river flooding, overflow of drains from combined drainage water
and flood water discharge, and high water from coastal storms and storm surge frequently
inundate low lying areas of the delta and coastal areas of the Indus river in the left bank.
Given the flat terrain of the delta and the coastal, in the event of floods most communities are
marooned for considerable period, and have limited access to high grounds, except for roads,
canal and drain embankments, which are also under threat of failing.
As reported by the National Disaster Management Authority (NDMA) released on 28
November, 2011, about 30 thousand villages located in 520 union councils spread over 15
districts in the left bank of Indus were affected by monsoon rains of 2011. Out of which about
24 thousand villages in about 240 union councils were severely affected. The catastrophe
directly affected about 52 thousand population. The report also mentions that some 250
persons lost their lives, and 460 persons were injured. Also some 65 thousand livestock
succumbed to the floods in the seven most affected districts.
The floods completely destroyed 450 thousand houses, while 414 thousand houses were
partially damaged, rendering them shelter less, and sought refuge in the safer areas. Some of
them were shifted to government schools; whereas the majority of them constructed their
temporary shelters on road side berms, non-operational railway lines, and banks of the canals
and the drains. The stakeholders suggested that a suitable number of elevated platforms could
provide temporary shelter where they could shift in better living and hygienic conditions. It
was agreed that the Consultants will consider the possibility of constructing elevated
platforms to facilitate make-shift arrangements, where access to the social services is
possible. In addition to this the communities desired that the possibility of widening the
existing roads and bund sections to accommodate the displaced persons.
In countries experiencing similar flood hazard, introduction of elevated platforms has
provided relief to the affected communities. The elevated platforms provided about 40 square
meter (430 square foot) area for each household. In addition to this ten percent area will be
allocated for livestock and about 20 percent space for water and sanitation.
Each elevated platform will accommodate 16 to 20 households/families. It will also include ,
sixteen Two blocks of four wash rooms each are to be provided for 16 to 24 households, with
common wash room facilities, separate for men and women. A common area for livestock
will be located at the end of each platform. Space will also be reserved for NGO‘s and other
relief agencies at the entrance, along with the space for daily provisions.
Objectives
The main objective is to provide adequate hygienic make shift shelter to the flood displaced
population, till the normalcy returns. The purpose is to provide: i) temporary shelter for
human and livestock; ii) access to water and sanitation, uninterrupted education facilities to
children, and health facilities, and iii) access to relief and rehabilitation agencies.
Output
It is proposed that each year, for the next five years, about 1,000 elevated platforms,
accommodating 20 households each of about 5 to six family members, are constructed, and
about 1,000 running km of the roads and embankments are widened.
Impact and Outcome
The elevated shelter will improve the quality of life with safe hygienic conditions, and will
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
41
reduce the incidence of diseases, loss of livestock, and access to social services including
relief operations.
Estimated Project Cost
The consultants evaluated three
construction type options: i) type A - with
stone pitching and compaction; ii) type B -
without stone pitching and compaction;
and iii) type C - without stone pitching and
compaction with Murom. Similarly, three
sizes per household were considered,
namely, 400, 225, and 150 square foot
each for one family. A 400 square foot
with type A construction would cost about
Rs.60 thousand per household, while B
and C type construction would reduce the
cost by 50 percent, and 67 percent
respectively. Similarly, reduction in space
per household to 225 square foot would further
reduce the cost by 50 percent, while further reducing it to 150 square foot per household
would reduce the cost by to 67 percent in each type of construction. The Consultants
recommend that 20 household shelters complex should provide for 400 square foot of space
with type A construction for each household.
It is estimated that each shelter accommodating 20 household would cost about Rs.1.2
million, and the proposed 1,000 shelter complex would cost Rs.1.2 billion.
Proposed Implementation Arrangements
It is proposed that construction of elevated platforms is implemented by the PDMA, while
widening of road embankments is implemented by the roads department, while the district
administration assumes the responsibility of its upkeep and unauthorized occupation, when
not in use by the flood displaced person.
Project Sustainability
It is apprehended that the facilities, in particular the elevated platforms would have risk of
unauthorized occupation and other uses after the flood water recedes, particularly during
years when they are not required for sheltering flood displaced persons. During these periods
its maintenance and upkeep would be of low priority. During floods, even the illegal
occupants would require shelter and would be difficult to evict them on humanitarian
grounds, and might not be available to the flood displaced person influx; defeating the
purpose. This may require a prior evacuation and allotment plan and designation of
household with first right.
Figure 4: Cost of Elevated Platform
0 2000 4000 6000 8000
Option -1
Option -2
Option -3
Cost Per Person (PRs)
Cost of Elevated Platforms
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
42
5.3.8 Pre-feasibility 8: Rehabilitation of Coastal Wetlands
Rationale
In the left bank of Sindh, about 90 wetlands of varying sizes, serve as repository of wildlife,
flora and fauna, and biodiversity. The wetlands are important natural resource base of
economic importance. They provide livelihood opportunities, mainly fishing, for the local
communities. The coastal wet lands, particularly Sanhro and Mehro dhands - the Ramsar
sites, were recharged by flows from storm water runoff and surface drainage system in the
southern districts (Badin and Thatta). To avoid KPOD drainage effluent discharges into the
abovementioned two dhand complexes, a 42 km long tidal link canal was built to detour the
outfall into Shah Samando creek. In addition to this at Cholri dhand, a weir was constructed
to protect the dhands from excessive drainage flows and back flows into the tidal link during
high tide.
With the collapse of Cholri weir and breaches in the tidal link due to cyclone 2 A in 1999, the
salinity level of the dhands has been compromised due to back flows from the sea. With the
salinization of these dhands, the fish productivity capacity has been severely impaired. Also
during the low tides, the dhands drain out into the tidal link, causing sedimentation and
lowering the storage levels in the dhands.
The communities whose livelihood has been severely affected strongly expressed the need to
revive the dhands by arresting the seawater and KPOD drainage polluting the dhands. They
perceived that this would reinvigorate the livelihood opportunities for the communities
dependent on these dhands.
It is proposed that the dhand complex spread over 67 thousand acres be fortified with an
embankment, with a dead storage of 300 thousand acre feet, ensuring significant increase in
the fish production. The design of the embankment would also include a gated structure to
divert about 2,000 cusec of storm water flowing through the KPOD during high rainy season.
Objectives of the Project:
The main objective is to i) revive the dhands as a source of livelihood; ii) restore and improve
the ecosystem; through protecting the dhands from seawater and drainage effluent intrusion.
In addition to this seed of good quality local species of fish will be introduced in the dhands
to improve the quality and yield of the fish. The reed grasses will also be grown to create
better environment/habitat for the waterfowls and migratory birds.
Project Outputs
The following are the main outputs of the proposed intervention:
i. an embankment, about 500 meters from the tidal link extending all around the
dhands constructed to allow breathing space for the tidal water constructed;
ii. five gated structures at: i) RD minus 12 to block the backflows from sea; ii) at
upstream of RD minus to divert storm water flowing above the base flow level;
iii) at Karo Ghungro outfall, iv) at Guni Phuleli drain outfall, and v) at southern
side to regulate excess water in the dhand complex.
iii. fish seed of appropriate species introduced in the dhands.
The mangrove and local tree plantation in the space in between the bund and the tidal link
will protect its erosion from rains and tidal effects. This activity is included in a separate Pre-
feasibility, presented later in the report.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
43
Project Outcome and Impact
This intervention is expected to improve and revive to a larger extent the ecosystem of the
dhands and would enhance the household income of the communities that are dependent for
their livelihoods from these wetlands. The main outcome of the project includes:
i. about two thousand mt of fish produced annually;
ii. refuge to local water fowl, migratory birds;
iii. production of 5,000 thousand mt of fodder for livestock;
iv. improved ecosystem and better environment for the wild life and biodiversity;
v. irrigation supplies water from the dhands during water scarcity conditions.
The project will also provide employment to local communities, and would reduce the
poverty incidence to 50 percent from the current estimated level of 75 percent.
Project Cost estimates
The cost of the embankment around the dhands, the gated structure for incoming water from
KPOD, and the five outfall gated structures will approximately cost about Rs.8.4 billion.
Project Viability
Despite its enormous environment benefits, the project is not a financially or economically
justifiable proposition.
Safeguards
This is an environment friendly option to revive the badly degraded ecology of dhands, will
create employment opportunities for local communities, improve the salinity of dhands and
will help conserve valuable water resource presently wasted to the sea through drainage.
There are numerous social benefits including better livelihood opportunities, favorable
environment for migratory birds and fodder for livestock thus raising the socio-economic
wellbeing of the communities.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
44
5.3.9 Pre-feasibility 9: Protective Plantation of Mangroves in the Coastal Areas of the
Left Bank
Rationale
Thatta and Badin are the two major hazard-prone districts of Sindh. In the last four decades
cyclones, heavy rains, transport of hazardous industrial waste, inundation due to breaches in
LBOD system, further exasperated by the damage to tidal link and collapse of Cholri weir
causing seawater intrusion, resulted in several multidimensional issues. These hazards caused
salinization of farmland and water bodies and wetlands, including underground water
resources, resulting in the shrinkage of productive farm land, and loss of fish resources in the
delta and the coastal area. In addition, these impediments also had a negative impact on the
environment, ecology, and biodiversity. The situation has severely weakened the local
economy compromising the livelihoods of delta and coastal are communities. The
degradation process is furthering due to unchecked widening and extension of the creeks.
Mangroves serve as green wall screen and play a key role in combating natural and manmade
induced hazards in coastal areas. They act as first defense line against the onslaught of tidal
waves and protect the coastal areas from the seawater intrusion, and high surges of tides. The
extensive root system and the bushes retard the storm water runoff and support fish
spawning. Mangroves also provide fodder for animals, fuel wood, and small woods for roof
thatching material for the dependent communities.
The coastal communities strongly feel that the main issues are: i) erosion and degradation of
coastal productive land; ii) salinization of water bodies and dhands; iii) decline in fish
resource; v) and absence of mangroves as a source for fodder, fuel wood, and roofing
material, thereby constraining the livelihood opportunities.
This intervention will revitalize the mangrove plantation along the coast, a critical and
complex coastal ecosystem severely threatened due to over exploitation, constrained fresh
water flows, and disposal of industrial pollutants and drainage effluent. It will arrest the
seawater intrusion, increase fishing potential, improved access to fodder, fuel wood, roofing
material, and will be a source of livelihood for local communities. The establishment of
mangrove plantation is also in line with the CDM initiatives, and will act as carbon sink.
Project Objectives
The main purpose of the project is to i) to arrest seawater intrusion; ii) protection and
restoration of productivity of farm land and the water bodies; iii) ensure availability of
fodder, fuel wood, and roofing material to local communities and sustainable livelihoods; iv)
protect the ecosystem and act as carbon sink.
Provide protection to the coastline and the delta ecosystems ensuring sustainable livelihoods
to the local communities. The project has been so designed that it would create a biological
screen to protect the lower reaches of the drainage system, engineering structures, farmlands,
wetlands/water bodies and arrest coastline erosion and sea water intrusion. In addition, the
proposed intervention will support fish production, provide fuel wood and fodder to local
communities, and improve their livelihoods.
Project Location
The project will be located in coastal area of district Badin and Thatta district (left bank of
Indus), comprising of coastal Talukas (sub-districts) namely Badin and S.F Rahu of Badin
district and Jati and Shah Bander Talukas of Thatta district where potential areas/mudflats
will be identified.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
45
Project Outputs:
By the end of the 2017, the main outputs of the proposed intervention will accomplish:
i. 10,000 ha mangrove plantation on the blank mudflats in the frontage of sea and
backwater;
ii. 8,000 ha of plantation of mangrove belts along the wetlands and the tidal link;
iii. 5,000 ha planted with salt tolerant species in supra tidal zone and around the
perimeters of wetlands and dhands.
Project Outcome and Impact:
The main impact of the intervention will be:
iv. reduction in the coastal erosion and seawater intrusion and backwash, and further
degradation of fertile land;
v. enhanced fish production in the wetlands and dhands;
vi. reduction in damages from cyclones/tsunami;
vii. reclamation of productive lands in the coastal area;
viii. secured livelihood for the local communities; and
ix. improved environment through carbon development mechanism.
At the full development stage the annual production of wood is expected to be 10.90 mt with
an approximate value of Rs 24.6 million, and fodder with an approximate value of Rs. 6.20
million. In addition to this the green walling and arresting sea intrusion will reclaim about
137 thousand ha, with an annual value of farm production increased by about Rs.10,000 Per
ha. Similarly, the annual fish production will increase by two and a half thousand mt fetching
about Rs. 25 million to the communities.
Project Cost
The total estimated cost of the project is Rs.733 million. The estimated costs is based on
existing price structure and adopted from the ongoing mangrove rejuvenation projects, in the
coastal areas of Sindh. The estimated cost will be refined further if approved and selected for
detailed feasibility in the phase III of the study.
Project viability
The preliminary indicative IFRR is about 17.1 percent. The net value of present value of the
incremental benefits is expected to be Rs.409 million, with a benefit cost ratio of 1:1.5.
These estimates will be firmed up at the detailed feasibility stage, along with sensitivity
analysis.
Proposed Implementation Arrangements
The proposed project will have positive impacts on the social aspects of the society such as
poverty reduction, income distribution, employment generation, livelihood opportunities and
gender mainstreaming. With the development of this project and its execution through
integrated and participatory approaches the coastal people will be mobilized, organized and
act as executing team will get direct and indirect employment and sources of livelihood
which will ultimately alleviate poverty and distribute benefits equitably. Furthermore, the
communities will own the project. Women will also be involved in all the processes of the
project
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
46
The implementation period for the proposed intervention is five or seven years. The proposed
project will be implemented through participatory approach by involving all stakeholders
from project preparation, execution and benefit sharing. Due to participatory approach the
local communities will be involved from initial stages of project development, survey,
selection of sites, planting, maintenance, protection and distribution of benefits
The executing agency will be Sindh Coastal Development Authority (SCDA) and the Sindh
Forestry Department (SFD) is proposed to be responsible for the implementation. On the state
lands SFD will be responsible for the development and operational and management
arrangements, while on communal lands and around the wetland a public-private-partnership
arrangements will be established through NGOs and civil society organizations for
community mobilization.
Safeguards
The intervention is environment friendly and does not require any resettlement. The project
being developed under CDM will generate carbon credits which will be owned by the
Government and will be used for other CDM projects. Hence, the project has several
environmental benefits and is environment friendly project.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
47
5.3.10 Pre-feasibility 10: Use of Drainage Water for Forestation in the LBOD and Kotri
Areas
Introduction
Forest cover is an important source for timber, fire wood, fodder, and non-timber products. In
the riverine area, they also act as barrier to protect from banks erosion. Most stakeholders felt
that denuding of forest cover has impaired the availability of timber, forage, and other forest
products of economic importance, overall environment, and has depressed the income of
communities dependent on forests.
The stakeholders also suggested that the vast area that is out of cultivation due to limited
irrigation supplies, can be brought under forest cover, if additional irrigation supplies are
available. They proposed that the drainage effluent should be diverted, where possible, from
the adjacent drains to support establishing forests and or grazing lands, in conjunction with
the fresh water, on the public and private lands.
Conjunctive irrigation refers to mixing of irrigation and drainage waters to the areas for tree
plantations. The irrigation water will be sweet water and the drainage water will be saline
quality. In order to utilize drainage water for forestation both the waters will be mixed in
required quantities to reduce salinity level of brackish water to sustain tree growth
Project location
The proposed project will include two geographic areas namely i) LBOD command area
located in Shaheed Benazirabad, Sanghar and Mirpurkhas, and parts of Badin district; and ii)
Kotri Surface Drainage System located in Thatta and Badin districts.
Project Scope and objectives
The objectives of the project are to i) increase the livelihood of communities by utilizing the
culturable waste through establishing forests on the private and public lands; ii) releasing
pressure on the drainage system by offloading the drainage effluent; and iii) to improve
environment through carbon sequestration.
Project outputs
The expected outputs of the project include forest plantation on 5000 ha of private and public
lands. The project will raise nurseries of 15.0 million plants which will be supplied to
interested farmers on subsidized rates.
Project Outcome and Impact
At the full development stage annually about 25 thousand cft of wood, valued at Rs 295
million. It will provide employment to about 4,500 persons. Similarly the farming community
will be provided with forage for their livestock. In addition to this these forest will produce
non timber products. This would also reduce waterlogging and salinity in these lands
reclaiming their productivity. It would also generate income to Pakistan from carbon
sequestering. The details will be worked at the time of feasibility stage of the study in phase
III.
Project Cost Structure
Total cost of the project is estimated to be Rs. 225.0 million
Project Viability
The financial analysis was undertaken for all the production parameters i.e. grasses, fuel
wood, small construction wood and industrial wood, at an aggregated output level. The
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
48
project viability was assessed for the project as whole.
The overall IFRR for the project is 15.8 percent, while the NPV for the cost at 12 percent is
Rs.256 Million, and NPV for the incremental benefits is estimated Rs.346 million. The cost
benefit ratio of the project is 1:1.35 on overall basis.
Implementation arrangements
It is proposed that the FD executes and implement this intervention in coordination with the
IPD, SIDA. The FD will implement this on the forest lands, while it will provide support to
the private farm land owners with the support from NGOs for community mobilization.
Project Safeguards
The proposed project is environment friendly on the grounds that it will not have any adverse
impacts on any green infrastructure of the areas, will utilize the drainage water for growing
trees and crops, will improve degraded lands and increase their productivity and will improve
the physical and chemical structures of the degraded soils. This intervention does not involve
any resettlement issues.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
49
Coarse, 8%
Moderately
Coarse, 12%
Medium, 20%Moderately
Fine, 45%
Misc., 15%
Soil Texture 418,451 Acres
5.3.11 Pre-feasibility 11: Bio-saline Agriculture in Badin and Thatta Districts
Rationale
The drainage of effluent Kotri command area is carried through 18 major drainage systems.
These drainage systems are carrying drainage effluent into sea except for three drains which
are out falling into river Indus. One of these drainage systems Kadhan Pateji Outfall Drain
(KPOD) is connected to LBOD and Tidal Link for outfall into Sea. The total design discharge
capacity of the whole system on left bank is about 8,050 cusecs. The salinity level of the
drainage effluent is about 2 ds/m which is suitable to grow most crops on marginal lands.
The drainage effluent if used for bio saline agriculture, would supplement farm incomes, and
would release pressure on the main drainage system. Evidence from Pakistan and elsewhere
show that the salt tolerant crops (glycophytes) irrigated with the brackish water grown on
marginal lands has shown promise. These crops include salt tolerant varieties of wheat,
barley, oilseeds, cotton, and different vegetables.
The communities in the coastal area, particularly in the Badin district reported that since their
natural resource base has degraded, support is needed to increase their farm productivity. It
was suggested that if they are given access to the drainage water through public lift pumps,
they would be able to grow salt
tolerant crops.
In response to this, the
Consultants a Pre-feasibility was
prepared to support and introduce
bio-saline agriculture along the
drainage network.
Objectives
Following issues will be
addressed; i) reduction of
culturable waste, ii) arresting
further degradation and
desertification; iii) off load
pressure on the main drainage
system; iv) improve the
environment, and v) increase farm income.
Outputs
The main outputs will include: i) by the end of the 5 year project period, 625 community
based lift pumps will be installed, each supporting 200 acres; ii) distribution channels will be
laid out to deliver water to participating farmers.
Outcome and Impact
It is estimated that selected salt tolerant crops, grasses, and trees will be grown on about
125,000 acres, generating an annual net farm income of Rs.5,000 per acre per year. This will
not only increase the farming intensity, will also enhance the household income of
participating farmers, and will also provide additional employment to landless labor.
The proposed project will also have several indirect benefits, such as increased availability of
better nutrition to household members, will also help in the availability of fodder and forage
for the livestock, and would arrest further degradation of soils.
Figure 5: Soil textures in Thatta and Badin Districts
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
50
Proposed implementation arrangements:
Since the drains are flowing below the ground level the water at suitable points will be
pumped into purpose built channels along the drains. All the operations of the project will be
executed through participatory approach. The SIDA/IPD will procure and install the lift
pumps, and the community groups will operate and maintain the lift pumps. An NGO will
be engaged for community mobilization. The agriculture department will provide support for
soil testing and identification of appropriate crops and varieties.
Cost Structure
The total cost of intervention is estimated as Rs.2.4 billion. This includes cost of procurement
and installation of lift pumps at Rs.50,000 each, cost of laying out distribution system, land
clearance at Rs.10,000 per acre, and cost of community mobilization.
Economic Viability
The preliminary analysis suggests an indicative IFRR of 13.3 percent. Nonetheless, the
project has been designed based on the assumption that the hazardous effluent originating
from sugar mills and other sources discharged into the drains completely terminated, else the
drainage effluent is not usable for bio-saline agriculture, and farmers will be reluctant to use
this water. Hence if the drains are not kept free of the sugar mills effluent, the project has a
high risk of failure.
Safeguards
The proposed project is environment friendly as it will not have any adverse impacts on any
green infrastructure of the areas. Any salinity build up in the marginal soils due to application
of the saline drainage water would be washed off with the rain water flows. Moreover, only
those crops, grasses, and trees will be selected that help reduce soil salinity.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
51
Box 2: Profile of Chotiari
Reservoir
Length 7.8 miles
Width 9.6 miles
Surface 45,000 acres
Capacity 0.71 MAF
Live Storage 0.67 MAF
5.3.12 Pre-feasibility 12: Rehabilitation of Deh Akro II and Chotiari Wetland Complex
Introduction/Rationale
Wetlands are the storehouses of globally endangered biodiversity of flora and fauna because
of their extensive and rich food webs and biodiversity. It is also an import source of
livelihood for the wetland dependent communities. The wetlands are ecosystems that provide
goods and services that have an economic value, not only to the local population but for the
downstream beneficiaries. Within the study area, there are three inland wetland complexes.
They are i) Deh Akro II in Shaheed Benazirabad district; ii) Chotiari reservoir and wetlands
in Sanghar district; and iii) the coastal wetland complex in the Badin district.
Deh Akro II is also a wildlife sanctuary consisting of four major habitats; desert, wetland,
marsh and agricultural. It is a natural inland wetland ecosystem, which supports a variety of
rare and endangered wildlife species predominantly crocodiles. This area hosts a considerable
number of rare fauna. Many indigenous fish species are also found. During the last decade, a
persistent dry spell adversely affected the area. The Chotiari wetland complex extends over
20 thousand ha and includes about 36 lakes, of which five are freshwater and 31 brackish
water, fed by seepage from the Nara Canal and its Jamrao offshoot. This Pre-feasibility offers
a corrective intervention for Deh Akro II and Chotiari reservoir and associated wetlands. A
separate prefeasibility has been prepared and included in this document.
These wetlands are under threat due to lack of awareness
of its economic importance, and poor management. The
stakeholders during the consultative workshops reported
that in Deh Akro II the major issue is the shortage of
water required for the survival and growth of the wildlife
species. Most wetlands are water stressed causing serious
threat to the wildlife species available in these wetlands.
Ideally, the original water allocation for wetlands needs
to be restored in order to avoid the degradation process.
Notwithstanding the shortages in the irrigation supplies, a reasonable allocation needs to be
made to avoid continual damage to wetlands. The stakeholders suggest that supply of water
to head lakes through an underground pipe off taking from the Nara Canal, operating during
the peak flow months. In addition to this, the stakeholders suggested dredging of silted lakes
whose storage capacity has been reduced over time. Other issues include over growth of
predators, and indiscriminate hunting in this wetland complex.
In Chotiari Wetland Complex consist of: i) the Chotiari Reservoir; and ii) the Chotiari
Wetlands. The entire area is managed by the IPD for irrigation purposes. With the
construction of reservoir seepage has become a serious problem threatening its banks and
creating waterlogged conditions in the hinterland agriculture. During consultations many a
stakeholders considered the waterlogging due to seepage from the reservoir is a serious threat
to their livelihoods and emphasize its control.
The stakeholders concurred with the proposed solution of dig moats along the western and
southern embankments of the reservoir. These moats would intercept seepage water before
these can reach farmland areas. Alternatively, a grid of surface drains is laid to prevent the
topsoil from becoming waterlogged or even flooded.
A few participants of the workshops also suggested that there is an urgent need to prepare and
implement a regional wetland management strategy and an action plan. They also suggested
that a separate authority is established to manage the wetlands, and monitor the progress.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
52
Objectives
The principal objectives of the proposed intervention are:
i. revival of wetlands through assured supply of minimum requirement;
ii. increase farm productivity through control of seepage causing waterlogging;
iii. protection of biodiversity; and
iv. preparation of a regional wetland management strategy and action plan.
Outputs
The main outputs by the end of the plan period include:
i. by the end of 2014, a regional plan study is completed along with action plans for
all the wetlands in Sindh, and presented to policy makers for approval;
ii. by the end of 2014 the wetland authority is established;
iii. by the June 2015, about ten km long piped linkage between Nara canal and head
of the lake in Deh Akro II is constructed and operative;
iv. by 2015, dig moats or grid interceptor drain are in place along the Chotiari
reservoir complex;
v. communities mobilized and are effective in monitor illegal hunting.
It is anticipated that the interventions will increase the household income of the communities
dependent on the wetlands, particularly farmers through reclaiming of the waterlogged areas.
It will also improve the environment and create a rich habitat for reversing biodiversity
losses. This will also foster introduction of ecotourism.
Outcome and impact
The intervention will arrest the seepage to the lands adjoining the Chotiari lake restoring its
productivity, and improved habitat of the wetlands for wildlife and migratory birds.
Estimated Cost
The total estimated cost of the proposed project is Rs.40 million.
Economic Viability
As the main benefit is improvement of the environment, the intervention was not evaluated
for economic viability.
Proposed Implementation Arrangement
SIDA will be the executing agency, while Wild Life Department (WLD) will implement the
Deh Akro II restoration related interventions in collaboration with EPA and IUCN. The
Chotiari reservoir and wetland complex will be implemented by SIDA in collaboration with
WLD, EPA, and IUCN.
After initial studies have been launched and the necessary institutional and legislative
analysis have begun to produce their first results, an embryonic Regional Wetland
Management ―entity‖ will start taking shape. From thereon it should gradually assume more
and more responsibilities in the management of the wetland complexes.
Safeguards
The proposed solutions will not have any negative environmental issues. The proposed
intervention is environment friendly as it will not create any environmental problems but will
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
53
improve the existing environmental problem of waterlogging in the area. and wetland
complexes, The interventions may involve resettlement. This aspect will be addressed during
the detailed design stage, if selected.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
54
5.3.13 Pre-feasibility 13: Shrimp and Mud Crab Farming in Coastal Areas of Left Bank
Introduction
Coastal fishery is the mainstay of livelihoods of the coastal communities. During the last
three decades, fish productivity has dwindled due to sea intrusion, contamination of the
wetlands with drainage effluents, overfishing, and use of illegal nets. Further, due to recent
floods and damage to tidal link the seawater intrusion has altered the topography of area near
Zero point Badin and is suitable for shrimp and fin fish culture including crabs and lobster.
Mud crab (Scylla serrata) named Koko is very famous in taste in south East Asian countries.
At present so many parties are exporting crabs to European and Fareast Asian countries
which are on rise. The following species of crabs are exported in shape of crab meat, canned
and alive.
The stakeholders during the workshops expressed their predicament and suggested public
sector support to restore the fish potential and interventions to support the livelihoods in the
area. As the shrimp and mud crab farming is feasible and has potential in the area, and
communities with technical support can benefit from this enterprise.
The ponds can be built within the intertidal low lying areas, receiving tidal water into the
pond through gravity flow during high tide. The seed is available from the shrimp hatchery at
Hawks bay in Karachi, maintained by the Fisheries Department, GoS. Small size crabs can be
collected from sea mostly purchased from fishermen engaged in this trade.
Project location and boundaries
The project will be located in the coastal areas of Badin and left side of Thatta districts
comprising of Badin, Shaheed Fazil Rahu Talukas of Badin district and Jati, Shahbander and
Kharochan Talukas of Thatta district.
Project scope and objective
The main objective is to exploit the livelihood potential through introduction of the shrimp
and mud crab farming as a niche activity in the area.
Project Outputs
The project will help farmers to establish ten shrimp farms, and ten mud crab farms, in
Shahbander, Jati, Badin, and SF Rahu talukas.
Project Outcome
The proposed project will generate employment and will help in reducing poverty of landless
and unemployed.
Project Cost
Since it is a private sector project, would require a credit line of about Rs.123.5 million.
Project Viability
Fir the proposed enterprise, the estimated indicative IFRR is 12.8 percent.
Implementation Arrangements
The farms/ponds will be owned and managed by private enterprisers/farmers. Sindh Fisheries
Department will provide extension and advisory services.
Safeguards
This is an environmental friendly intervention as it will not create any adverse impacts on
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
55
flora and fauna, soil, water, land use, climate etc. The proposed project will be executed in
the mangrove areas, ensuring protect to the mangrove plantation, as due to increase in human
activity it is apprehended that the mangrove resource will be deteriorated on the cost of
shrimp farming. Resettlement is not required for this activity.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
56
5.3.14 Pre-feasibility 14: Brackish Water Fish Farming in LBOD Area
Introduction
The province of Sindh is blessed with all kind of water resources i.e. marine and brackish and
fresh water. Despite its potential, the growth of this subsector is constrained by lack of supply
of seed and knowledge base amongst the potential farmers. Thousands of acres of waste and
water logged land is available in the LBOD project area and surroundings which can be
converted into productive fish ponds, and is lying waste.
There is ample area and depressions in the command area of LBOD system which is un-
utilized due to salinity problem of the water available in the depressions. In such areas it is
not possible to grow fresh water fish. In addition, the LBOD drainage water is available in
ample quantity in the spinal, lateral and tertiary drains where brackish water fish could be
introduced and propagated. The fish seed is available from fish hatcheries and will be stocked
and grown in the fish ponds and will be stocked and grown in the fish ponds constructed
under the project.
The stakeholders expressed the need to support fisheries in the area to enhance income of the
communities located along the drainage network.
Project Area
The proposed project is suggested to be located in the districts of Shaheed Benazirabad,
Sanghar, Mirpurkhas, and Badin, along the drainage network.
Objectives
The objective of the proposed project is to introduce the brackish water fish along the
drainage network where the quality of water is brackish. The specific objectives of the
proposed project are as under:
Project outputs
A total of 80 ponds will be established, of which half will be the Tilapia noliticus and half for
the Lates calcarifer (Dangri). These will be divided between the four districts.
Outcome and Impact
With this the alternative opportunities for improved livelihood will enhance in the farming
community and ultimately the poverty will be alleviated. The proposed project is socially
acceptable as it will enhance job opportunities, reduce poverty, provide livelihood to the local
population and will increase economy of the people and the province. The project will
generate employment opportunities for rural people especially fishing and farming
communities during construction and execution phases and onwards. It will create direct and
indirect jobs for both men and women.
Cost structure
Since it is a private sector project, would require a credit line of about Rs.545 million.
Project Viability
The estimated IFRR of this activity is 13.2 percent. As this is a private sector activity, the
intervention, does not need allocation of funds, except.
Implementation Arrangements
The farms / ponds will be managed by land owners. Sindh Fisheries Department will provide
extension and advisory services.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
57
Safeguards
The proposed project will not create any environmental issue during its construction and
implementation phases but rather address the existing environmental issues such as water
logging and salinity, water quality aspects, degradation of agricultural lands, decline in fish
resources, and loss of biodiversity and decline in natural resources habitats. This is an
environmental friendly project as it will not create any adverse impacts on flora and fauna,
soil, water, land use, climate etc. The proposed project will be executed in the command
areas of LBOD system the care shall be taken to protect the existing wild vegetation of un-
economic value. In fact such un-economic and un-utilized lands will be made productive due
to introduction of brackish water fish.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
58
5.3.15 Pre feasibility 15: Establishment of Disaster Management Unit in SIDA
Introduction
Southern Sindh area has always been affected by floods due to high precipitation and lack of
drainage. It has been reported that the major events in recent history took place in 1959,
1961, 1962, 1964, 1970, 1976 and 1979 when the annual precipitation events were reported
to be within 203 mm to 609 mm. The Badin July 2003 precipitation (303.9 mm), which
caused major flooding and destruction, was estimated to have a 66 years return period. In
2011 on the 11th and 12th August the precipitation recorded in Badin added together was 297
mm which when looked as one 48 hours event the corresponding return period is near 100
years. Also, the highest ever monthly precipitation record in Badin was surpassed in August
2011 with 331 mm corresponding to more than 80 years return period. Moreover, if a 30
days period is observed from 10 August to 9 September 2011, Badin experienced 512 mm of
rainfall in one month.
The devastation experienced by the people of Sindh requires proper planning of the disaster.
It is implied within the Law in Sindh Province that, SIDA is to assume the flood management
activities within the command areas of its three AWBs and is responsible to the National
Disaster Management Agency.
This unit would develop, on a periodic basis, a strategy statement for improvement of
irrigation and drainage services, integrated water management including drinking water,
water distribution in times of drought, flood protection within its command and catchment
areas setting goals and objectives, formulating implementation policies and identifying
priority and other actions.
In addition to this would be responsible to issue flood warnings and warnings to all the
stakeholders that are likely to affected, if it has cause to believe that damage or harm shall
result from the use of any water flowing within its area of jurisdiction. The other functions
would include: i) monitoring of the disposal of toxic or noxious effluent safely and with
minimum pollution of water resources; ii) ensure repairs of flood protection works in the pre-
flood season; iii) review the plan for regulation of the canal supplies during the rainy season;
iv) ensure positioning of the machinery and materials near vulnerable points for emergency
repairs; and v) inspection of the vulnerable breaching of sections.
Objectives
The main objective of this study is to
implement a SIDA Disaster/ Crisis
Management Cell for preparing, training and
coordinating plans for emergency response
services in case of emergency situations and
disasters within SIDA‘s ordinance. The
Disaster Risk Management Cycle (Disaster
Cycle) consists of four phases:
Prevention/Mitigation and Preparedness in the
pre-disaster stage, and Response and
Rehabilitation/Reconstruction in post-disaster
stage.
Output
A Disaster Management will be established by 2014, and is functional. Standard operating
procedures or protocols will be developed to trigger timely flood protection and preparedness
Figure 6: Crises Management Cycle
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
59
measures in consultation with vulnerable communities in the pre-disaster stage, and response
and rehabilitation/reconstruction in post-disaster stage.
Impact and Outcome
The establishment of the Disaster Management Cell would i) develop the capacities of SIDA
to mitigate floods and droughts, particularly during calamities, such as breaches, floods or
extreme weather conditions such as cyclones, the SIDA shall have a coordinating role in
taking all necessary measures.
Estimated Project Cost
The estimated cost of the DMU is about ten million, with and annual operational expenditure
of Rs.20 million. The annual operating costs after the first year, once the Cell is fully
established, can be reduced as less number of staff will be required to operate the Cell.
Proposed Implementation Arrangements
The Sindh Water Management Act of 2002 assigns SIDA specific responsibilities related
with disaster management and related environmental issues. Therefore, SIDA has the
obligation to develop, on a periodic basis a strategy statement for improvement of irrigation
and drainage services, integrated water management, flood protection, prevention of sea
water intrusion, water distribution in times of drought and wetland management within its
command and catchment areas setting goals and objectives, formulating implementation
policies and identifying priority and other actions. It requires continued updating of
strategies for flood protection, prevention of sea water intrusion and drought management.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
60
"No nation can rise to the height of
glory unless your women are side by
side with you; we are victims of evil
customs. It is a crime against humanity
that our women are shut up within the
four walls of the houses as prisoners.
There is no sanction anywhere for the
deplorable condition in which our
women have to live." Mohammad Ali
Jinnah 1944
(US Library of Congress report
"Pakistan - A Country Study")
5.3.16 Pre feasibility 16: Gender Mainstreaming in Irrigation and Drainage
Introduction
Despite important role played by women in the
agriculture, and other economic activities, they are
generally perceived as beneficiaries, and not as
partners in the management of assets and resources,
and the development process. They are silent
bystanders in the planning, implementation and
operation stages of the development activities. They,
along with children are the first victims in disaster,
such as flood disasters. Moreover, the property rights
are not well defined and transparent.
The situation is not different vis-à-vis irrigation and
drainage subsectors. This is evident from their minimal presence in the water management
institutions, such as Water Users Associations (WUAs), FOs, AWBs. Here they are
represented by their male family members, as their guardians. Similarly, in the development
process their aspirations and problems, or their rights are not adequately represented or
articulated.
During the consultations at the village and district levels, the women participant showed their
dismay on the lack of their involvement, and absence of registering their apprehensions and
aspirations in the planning, implementation, and management of the irrigation and drainage
infrastructure, flood preparedness management, and desired an active role.
Current SIDA‘s framework advocates increased participation of women in the water
management reforms. Although SIDA has a gender policy, they need to draw a well laid out
way forward to ensure women participation in water management. Nevertheless, SIDA‘s has
made a considerable achievement in engaging women farmers and registering them as
members of the Water Course Association (WCA), FOs, and AWBs.
However, the limited women membership in the FOs does not indicate their active
involvement in the water management. Out of 383 FOs, only 146 have women representation,
but the overall participation of women in the FOs, and AWBs is less than one percent.
To main stream women participation in the water management, it is proposed that the Social
Cell organizes a five year gender sensitizing and training program to foster an active role in
the organizational and water management activities..
Objectives
To mainstream an active and representative women inclusion in the participatory water
management actives, and to sensitize all the line agencies dealing with the water management
and preparedness in flood management.
Project Output
The main outputs of the strengthening and training program are:
i. Gender mainstreaming strategy and action plan formulated and implemented;
ii. 60 staff of SIDA trained in gender mainstreaming;
iii. 90 field staff of AWBs trained in gender mainstreaming;
iv. 450 persons in line agencies in 15 districts trained for gender mainstreaming;
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
61
v. 500 field staff in AWBs trained in gender related conflict resolution and
negotiation skills;
vi. 1,400 members of the FOs trained in gender awareness of issues;
vii. 6,500 community members trained in flood preparedness;
viii. 9 campaigns at AWB level, 6 TV programs, 12 radio programs, and 12
newspapers supplements organized to disseminate information related to the
drainage issues.
Impact and Outcome
The training program would strengthen the capacity of the SIDA, AWBs, FOs, and rural
communities in ensuring active participation of the women in the management of irrigation
and drainage systems, and addressing gender concerns.
Estimated Project Cost
The estimated cost of training and awareness campaigns is estimated at about Rs.21 million.
Proposed Implementation Arrangements
It is proposed that a Social Cell of SIDA is entrusted to organize the trainings.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
62
5.4 Position Papers
5.4.1 Position Paper 1: Drainage Effluent Intrusion in the Ghotki Area from Southern
Punjab
During the stakeholder consultations concern was shown by the farmers in the Ghotki area
about the drainage effluent flowing in from the northern adjoining district of Rahim Yar
Khan, Punjab. The seepage from the evaporation ponds, draining out in the Ghotki area has
severely degraded considerable land creating marshy conditions. Significant cropped are has
been ruined into wasteland.
In Punjab, the evaporation ponds were constructed under the Salinity Control and
Reclamation Project (SCARP) VI for the disposal of the highly saline drainage effluent from
the irrigated areas of Rahim Yar Khan and Bahawalpur Districts. The gross area of the
Project is 11.46 Million acres (590,862 ha) out of which 1.267 Million acres (512,755 ha) are
culturable commanded by Punjnad and Abbasia Canals. SCARP VI comprise of 514
tubewells of varying capacity from 1.5 to 3 cusecs (43 to 85 lps) to lower and maintain the
water table over the area. In the first stage2, 391 tubewells were installed along four drains:
Abe-Hayat, Khanpur Main, and Manthar and, Pattan Manara. In the second stage 123
tubewells were installed along Tarukari Drain and the operation of the 514 tubewells started
in 1989.
Due to the lack of hydraulic head towards the Indus River the option to outfall into the River
was discarded and the option of saline drainage water disposal through evaporation ponds
along the fringe of the Cholistan Desert area was adopted in SCARP-VI scheme.
The evaporation ponds were developed taking advantage of the inter-dunal depressions and
old dhoras along the fringe of Cholistan Desert. The area is barren1 and without irrigation,
but used for animals grazing. The subsoil water has been reported as saline. Dykes were
provided between the dunes to shape up the ponds, which consist of series of elongated
reservoirs joined together by man-made connecting channels, converting them into a
contiguous series of ponds. Since commissioning of these evaporation ponds in 1989,
waterlogging and salinization have occurred in the adjacent lands.
To dispose the drainage effluent of the 514 deep drainage tubewells two series of ponds were
initially designed. Stage I with an initially designed area of 8,400 acres (3,400 ha) and Stage-
II also with an originally designed area of 24,600 acres (9,956 ha) to make a total of 33,000
acres (13,356 ha). However, in year 2001 the active pond area was in the range of only
13,000 acres (5,261ha).
The visits made by the Consultants to ground truth the situation observed that the intrusion if
unchecked and the negative externality arising from SCARP VI will further shrink the
productive land. This will deprive the farming communities in the affected areas of their
productive land, rendering them homeless, and even landless. The objective of the visit was
also to consult with the local communities to solicit a perceived solution to reclaim the
degraded lands.
Most stakeholders felt that the issue cannot be resolved unless the Punjab government shows
recognition of the problem and its mitigation. Various suggestions indicated i) replacement of
SGW tubewells with tile drainage in the SCARP- VI area; ii) installation of desalination plant
1IWASRI.Environmental impact of disposal of drainage effluent to evaporation ponds. M.N. Bhutta, M.F.K. Niazi,
N. Ahmed. Sep. 2003
2Proceedings of a roundtable meeting.IPTRID Secretariat - FAOLahore, Pakistan 10–11 November 2000
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
63
to desalinize the drainage effluent; iii) make provision of irrigation water from Rainee canal
to supply the channel which connects different ponds of the Rahimyar Khan SCARP project
area; and iv) provide tile drainage network system within the affected parts of Ghotki district.
Purpose of the Study
The main objective of the present study was to have an opinion on the issue by the Master
Plan Consultants, by visiting the area, conducting literature review and analyzing the
technical problems in an effort to contribute in the search for a common solution between the
Governments of Sindh and Punjab.
Main Points of the Analysis
IPTRID Secretariat referred to the
SCARP VI effluent as “It is clear
that the water is hazardous and
cannot be used for irrigation”.
The annual effluent inflows
entering the evaporation ponds
were originally estimated to be
487,000 acre-ft (601 Mm3). The
present expected annual discharge
into the ponds is of the order of
230,000 acre-ft (284 Mm3).
The original proposal suggested a
system of ponds gross area of
160,000 acres (64,752 ha). This evaporation area was latter on re-estimated to be 67,000
acres (27,115 ha) but, it was further reduced to about 13,000 acres (5,261 ha).
The volume of water that evaporates out of the series of ponds is between 35 to 40% of the
SCARP VI saline effluent that outfalls into the system of lagoons. Therefore, it is concluded
that the system of evaporation ponds has efficiencies of similar magnitude, 35 to 40%.
Conclusions and Recommendations
The water balance shows that the ponds are neither socially nor environmentally sustainable,
unless the volume of the incoming water from SCARP VI is reduced and/or, the evaporation
area (not the depth) of the ponds is increased to make them more efficient. The Provinces
should jointly seek for solutions of the problems caused by the effluents of SCARP VI
project to the people of the Ghotki affected area.
The relation Pond evaporation area/Saline inflow from SCARP VI is resumed at different
stages of the evaporation scheme as:
• Original design 0.33 acre/acre-ft
• Revised design 0.14 acre/acre-ft
• Actual 0.06 acre/acre-ft
The figures above clearly indicate that the implementation of the project diverted from its
original design or has not been fully implemented as per original plans. The surface area
provided is about one fifth of the initial estimate and, less than half the revised assessment.
Figure 7: Evaporation for Fresh and Saline Water Ponds
0
2
4
6
8
10
12
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
mm
/da
y
Evaporation from fresh and saline water ponds
Fresh W Saline W
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
64
The Consultants recommend implementing the relation Pond evaporation area/Saline inflow
from SCARP VI as per the revised design, as it should substantially increase the evaporation
and reduce the damaging infiltration effect. This should be done in the Punjab, at no cost to
the Sindh Province.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
65
5.4.2 Position Paper 2: Sugar Industry Effluent Treatment at Source
Introduction:
Of the 33 sugar mills in Sindh, 30 of them are located in the left bank of Indus. Sugarcane is
grown on about 250 thousand ha and annually produces about around thirteen million metric
tons annually. A sugar mill with 6,000 mt per day crushing capacity generates about 5,300 mt
of highly toxic effluent, which is mostly dumped into the canals, and the drainage network,
where available, without treatment. It is estimated that during the crushing season, these
sugar mills release about 160 thousand m3 per day.
The provincial EPA regulation requires that the sugar mills to process the generated effluent
within the sugar mills and should not be released out of sugar mills without treatment.
However, the restriction is not complied with due to lack of effective enforcement.
There are over 800 village settlements along the LBOD drains. During the water stress
periods, the polluted drainage water is pumped out by the farmers for supplementing
irrigating supplies. This toxic water not only adversely affects the soil but also causes high
mortality of fishes in the drains. This has reduced the availability of fish to the local
communities for their consumption. Whatever quantity of fish survives is consumed by the
communities, despite detrimental to their health. Also the toxic water is consumed by the
local livestock causing diseases, and higher toxicity in the dairy products. The polluted also
emits a strong foul smell, a menace for people residing along the drains. The level of toxicity
released is higher when
the effluent from sugar
mill distilleries is added.
Wastewater from sugar
mills is basically organic
with its high BOD rapidly
depletes available oxygen
supply when discharged
into water bodies
endangering fish and other
aquatic life. The high
BOD also creates septic
conditions, generating
foul-smelling hydrogen
sulfide, which in turn can
precipitate iron and any
dissolved salts, turning the
water black and highly toxic
for aquatic life. The smell
of the effluent is so irritating that people cannot breathe and sleep well. The polluted drain
water finds its way into the wetlands near coast like Nareri Dhand (a Ramsar Site) and the
dhand complex adjoining the KPOD. These dhands were the source of livelihood for
thousands of fishermen in the vicinity.
Analysis of effluent from sugar mills have depicted that the values of DO, BOD, COD and
TSS are higher than permitted by the WHO standards. Therefore, there is need to treat the
effluent prior to its disposal in water bodies or for use in agriculture.
Sindh province is already shortage of fresh surface water and its groundwater is mostly
saline. Therefore, it is very necessary that irrigation and drainage infrastructure are fully
Figure 8: Quantity of Sugar Mills Effluent Flows
- 2,000 4,000 6,000 8,000 10,000
Seri Sugar Mills
Tando M.Khan SMs
Shah Murad SMs +(Distillary)
Lar Sugar Mills
Dewan Budho Talpur …
Bawani SMs Talhar
Pangrio SMs
Khoski SMs
Army Welfare SMs Badin
Effluent (m3/day)
Sugar Industry Effluent 4-5 March 2011
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
66
protected from the disposal of untreated wastewater. Furthermore, necessary steps must be
taken for the recycling of available wastewater through primary treatment for use in
agricultural and industrial sectors.
USAB system for treatment of highly concentrated wastewater from agriculture industries is
increasingly popular and wastewater from sugar mills and distilleries can be treated for
significant reduction in pollution levels. Methane gas produced in USAB system can be used
as an energy source. This system is both technical and cost effective.
The overall advantage of establishing the treatment plants and ensuring disposal of the treated
effluent are manifold. These include:
i. The drainage system now completely polluted and with high levels of BOD, COD,
organic materials, toxic chemicals will be free from these pollutants and can
harbor fish and other biotic life.
ii. Communities now very much annoyed of the awful smell of the distillery effluent
will get rid of this problem.
iii. Livestock will be saved from toxic effects of chemicals
iv. The water of the drains will be utilized for bio-saline agriculture. This will
enhance production thereby increasing the income of the communities
v. Marine life now under the influence of the toxic effluents will be relieved of the
polluting effects of the drain water, and the fish catch will increase from both
inland and marine areas.
vi. Water fowl will be attracted by the slightly brackish drain water so the population
of migratory birds will increase.
The EPA should monitor that the sugar mills comply with the Environmental Protection Law
1997, and install the treatment plants in the vicinity of the mills so that the generated effluent
is of expected level, safe for other uses, such as conjunctive use of water, watering livestock,
and safe for the survival of fishes in the drains, and free from foul smell.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
67
5.4.3 Position Paper 3: Water Quality for Human Consumption
Introduction
In Sindh, especially in study area, there are many challenges to maintain the water quality
potable. These include adequate public sector investment in ensuring clean water supplies,
and ineffective compliance to check pollution of the fresh water resources.
The availability of safe and sweet drinking water has always been a major problem in the
coastal areas of both the districts of Badin and Thatta, where the underground water aquifers
is brackish, particularly close to the coast where seawater intrusion has worsened the
situation. The situation is even worse for the fisher folks living in and around the creeks.
They have to haul drinking water from significant distances, and for other requirements
depend on the brackish water.
Due to diversions of irrigation water at the various barrages has decreased the water
availability downstream of Kotri. The situation has been further exasperated by the release of
industrial pollutants and saline drainage effluent directly into the river. This has severely
impaired the quality of the water in
the river downstream of Kotri.
The coastal villages, other than
those living in the creek area,
depend on the irrigation channels
and minors for drinking water,
which is also stored in the ponds for
use when the supplies are low. As
the carrying capacity of the
irrigation system has been reduced
due to poor maintenance, the
availability of the drinking water is
constrained in the tail reaches.
This situation has been further
worsened due cyclones that
damaged the tail reaches of the
irrigation network, as close as 20
km from the coast. The Public
Health Engineering Department operated water supply system is mostly inoperative
salinization of aquifer. Following issues and problems need attention and its mitigation.
i. lack of awareness for safe drinking water amongst coastal communities;
ii. unchecked industrial pollution in the fresh water bodies above WHO standards;
iii. inadequate filtering and disinfecting arrangements in the public drinking water supply
installations;
iv. unchecked pollution from clothes washed in the irrigation channel,
v. unchecked pollution from animals bathing in the canal system;
vi. unacceptable level of salinity, fluoride and or arsenic contamination in the
underground water;
vii. unacceptable level of bacterial contamination.
Source: PCRWR, DRC, Tandojam
Figure 9: Arsenic Contamination in Badin District
0
50
100
150
200
250
0 ppb 1.5
ppb
10
ppb
25
ppb
50
ppb
>50
ppb
Nu
mb
er o
f S
am
ple
s
Arsenic Concentration (ppb)
Arsenic Found in Badin During Field Tests
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
68
Following are the recommendations to ensure access to safe water drinking supplies in the
rural communities:
i. construction of water filtering plants in the areas without access to safe drinking
water supplies;
ii. establish a water quality monitoring and surveillance system;
iii. promote appropriate technologies for rain water harvesting;
iv. effective monitoring for the compliance of treatment of effluent entering the
freshwater bodies;
v. introduction of low cost ―clay pitcher arsenic removal‖ method amongst the
communities dependent on underground water laden with arsenic contamination;
vi. introduction of low cost chemical treatment method amongst the communities;
dependent on underground water laden with fluorides;
vii. in study area, where the ground water is brackish & only source of drinking, the
Reverse Osmosis (RO) technology is a preferred option. This technology is now
available at affordable cost. For a small community, requiring 500 GPD of potable
water, the RO plant may cost up to Rs 400,000;
viii. the Environmental Protection Agencies (EPAs) may take the responsibility to
ensure that the water bodies are safe from pollution. It is further recommended
that the ―Integrated Water Management Committees‖ (IWMCs) may be formed by
the SIDA or irrigation department at canal level representing all the concerned
departments and NGOs to manage the water resources sustainably.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
69
6 PROPOSED REGIONAL PLAN STRATEGY AND RECOMMENDED INVESTMENT
PLAN
6.1 Proposed Regional Plan preparation Process
Understanding that a Master/Regional Plan is a proposed organizational strategy of a specific
territory, of a consented vision of a group of stakeholders that look at the development of the
territory in the long term and; in close coordination between the Consultants, SIDA and
partner NGOs; a consultative process which emphasizes the active participation of
stakeholders from each of the regions was designed and implemented. This allowed the direct
participation during the process of consultations through 35 workshops, visits to 231 villages
and the direct involvement of 9,077 participants. Among the stakeholders there were
government officials, community leaders, villagers, representatives of different institutions
and NGOs, universities and private sector.
The consultation process took place in two phases. A first phase of diagnosis, in which the
stakeholders defined the fundamental issues and problems they have to face in their daily
lives and a second phase, in which the stakeholders were consulted again to validate the
proposed strategies and determined the priority of each of the actions. With the interactive
sessions with the stakeholders, high priority interventions were identified, thus building from
a systemic approach achieving participatory consensus facilitated the Consultants to
formulate the proposed Master/Regional plan strategy. Figure 11 below presents the different
activities conducted in the preparation of the plan.
6.2 Proposed Regional Plan Strategy
As guided by the scope of work and terms of reference for the regional plan study for the left
bank of Indus, delta, and coastal areas, the Consultants propose a following strategy to
combat waterlogging and salinity and to ensure safe and timely disposal of drainage effluent,
and storm water into the sea and or natural depressions in the Thar desert.
Since last three decades, consequent to extreme weather changes, localized and widespread
riverine and storm water flooding has frequented the province of Sindh. The unprecedented
rains experienced in the year 2011 exposed the inadequacy and inability of the drainage
infrastructure to cope with the massive runoffs. This resulted in loss of life, substantial
damage to urban and rural property and infrastructure, public utilities and colossal loss of
agricultural crops and lands. The main causes were simultaneous heavy rains in most of the
drainage basins, deferred maintenance of the drainage network, encroachments of natural
waterways, trapping of water. Despite the construction of reservoirs and major investments in
flood protection, there is still a considerable flood hazard. It is estimated that the total losses
from floods were about Rs.454 billion, and about 500 lives lost.
In developing the proposed regional plan strategy, the Consultants followed an extensive
stakeholder consultative approach, and organized consultative workshops at community,
district, and regional levels to register their perceptions about the drainage disposal related
issues and problems, and to solicit their perceived solutions and aspirations and identification
of priority interventions. The findings were disseminated widely through print and electronic
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
70
Stakeholder Consultative Process to Identify Issues, Problems and Solutions
Safe Disposal
of Surplus
Drainage
Effluent &
Storm Water
Rehabilitation
of Existing
Drainage
Infrastructure
Revival of
Natural
Waterways
Second Line
of Defense
d/s Kotri
Make Shift
Arrangements
for Flood
Displaced
Persons
Environment
Mitigation &
Arresting of
Sea Water
Intrusion
Inland
Wetland
Management
Mangroves
Plantation in
Coastal Area
Coastal
Wetland
Management
Conjunctive Use
of LBOD water
for Forestry
Livelihood
Strengthening
Develop Shrimp
and Mud Crab
Farms in Coastal
Zone
Introduction of
Brackish Water
Fish in LBOD
Catchment
Introduction of
Bio-Saline
Agriculture on
Marginal Lands
Institutional
Strengthening
& Capacity
Building
Crises
Management
Cell within
SIDA
Gender
Mainstreaming
Combating
Water-logging
and Salinity
Drainage
Infrastructure
in Non LBOD
Areas
Divestment of
FGW
Tubewells
Rehabilitation
of SGW
Tubewells
Regional Plan and Investment Priorities
media for wider awareness and feedback. Based on this, the prefeasibilities were prepared
and prioritized in consultation with stakeholders, and this lead to the formulation of regional
plan and action/implementation plan.
The five main pillars of the proposed strategy are:
1. Safe and timely disposal of surplus drainage effluent, and storm water flood.
2. Combating waterlogging and salinity in non-LBOD areas.
3. Environmental mitigation
4. Institutional Strengthening and capacity building of SIDA
5. Livelihood support to water hazard affected communities.
The graphic representation of the strategy is depicted in the following figure, followed by
brief explanation of rationale of the abovementioned five pillars of the strategy.
Figure 10: Strategy for Regional Plan for the Left Bank of Indus Delta and Coastal Zone
Reduction of Flood Damages
Increase in Agriculture Productivity
Reduction in Poverty
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
71
6.2.1 Pillars of the Strategy
1. Safe and timely disposal of surplus drainage effluent, storm water, and riverine
flood
The main reasons that exasperated the losses in 2011 include the lack of reduction of disposal
capacity of the drainage and flood protection system over time due to clogging of the system
due to deferred maintenance, relief cuts, unauthorized tampering of the system, and
constrictions due to physical infrastructure and encroachments. This warrants rehabilitation
of existing drainage structure and revival of natural waterways to relieve pressure on the
LBOD, and divert and harvest surplus storm water flows in the depressions in the desert
areas.
The main interventions/elements of the strategy include strengthening and rehabilitation of
the LBOD system, revival of natural waterways. These structures will ensure safe and timely
disposal of the storm water and avert the massive losses to the economy, if similar extreme
precipitation pattern re-occurs or persist.
The plight of the 2011 flood displaced persons suggest that the drainage system be
complemented with raised make shift shelters on higher grounds, and along the canal banks,
roadside, etc. to provide relief from marooning.
2. Combating waterlogging and salinity in non-LBOD areas
The increasing water table and the associated salinity in areas outside the LBOD catchment is
a tale tell for the declining farm productivity. The situation is precarious not only where there
is absence of drainage structures, but also in areas where existing saline and freshwater
drainage tubewells are nonoperational. The major reason is deferred maintenance and
vandalizing of the more than 50-60 percent of the tubewell machinery, and electrical hook up
system.
To control the water logging and salinity and to revive farm productivity, the need for
installing drainage system in the areas outside SCARP and LBOD, rehabilitation of the
nonfunctional tubewells, in the saline groundwater zones, and divestment of public sector
tubewells in the fresh groundwater areas and its replacement with a fostering program
development of private tubewells.
3. Environmental mitigation
The LBOD system had some unintended negative consequences, due to failure of the outfall
structures, mainly the collapse of Cholri weir, and tidal link, due to onslaught of the 1999
cyclone, and high tide trends. This led to intrusion of the seawater that degraded the
freshwater bodies and agricultural lands in the coastal areas, and to some extent in the lower
reaches of the LBOD system. This resulted in loss of farm productivity and salinization of the
freshwater bodies eroding the fish catch potential.
To arrest the seawater intrusion would require control structures in the lower reaches, and
biological screening through the plantation of mangroves and other salt tolerant species in the
potential coastal areas including around the tidal link and coastal wetland complex.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
72
In addition to this the inland and coastal wetlands also require attention to ensure
improvement of the local environment. Similarly, forest plantation will be established in
LBOD network areas and Kotri drainage system by using saline and fresh water in either
conjunctive of cyclic ways. This would serve as an instrument for improving the local
climate.
4. Institutional Strengthening and Capacity Building of SIDA
During the 2011 floods, SIDA played an important role in managing the disposal of the storm
water floods, and coordination with a vast array of agencies. The responsibility was not
commensurate with the available resources. It highlighted the need for creating a crisis
management cell with the SIDA, as a hub for coordination between agencies, and serve as
clearinghouse for the storm water flood related information system, including early warning
system, and rescue and relief operations. In addition to this, the women stakeholders felt that
most of the SIDA field staff is not adequately gender sensitive, and gender concerns need to
be mainstreamed for inclusive participatory irrigation management.
5. Livelihood support to rural communities
The livelihood of stakeholders, particularly those residing in the lower reaches of the LBOD
system, were adversely affected due to degradation of agricultural land due to seawater
encroachment and decrease in the fish production due to salinization of freshwater bodies.
This has rendered many household into economic deprivation. Stakeholders emphasized the
need for introducing appropriate income generating enterprises to gainfully engage the
unemployed persons. Following this exigent need, various income generating activities need
to be supported.
6.3 Screening, and Ranking of Proposed Interventions
A ranking procedure with the evaluation criteria for possible solutions, considering, costs,
economic returns, technical, social and environmental feasibility was developed and
submitted to SIDA and the PCMU for their comments and input. As mentioned above, the
method proposed contemplates five major criteria and a number of sub-attributes. These are:
i) social accessibility; ii) financial soundness; iii) environmental benefits; iv) socio-economic
impact; and; v) sustainability. The description and interpretation of each of the criterion and
sub-attributes is given in Volume II Annexure A.
Each of the sub-attribute identified by stakeholders for each of the interventions was
evaluated according to the expected impact. The impacts being positive or negative were
classified from none to very high in a scale that goes from 0 to +4 for the positive effects and
from 0 to -4 for the negative effects expected.
In the workshops of Phase-II, the stakeholders input were pursued as part of the evaluation
criteria for the ranking method. Input such as the social acceptability of specific schemes.
The details of the workshops are given in Volume IV of this report.
The ranking is calculated based on the statistical parameter known as ―standardization z‖
(also known as ―z score‖), which in statistics is defined as a standard score to express the
number of standard deviations an observation is above or below the mean. ―z‖ is a
dimensionless parameter calculated by subtracting the population mean (μ) from an
individual raw score (x) and then dividing the difference by the population standard deviation
(σ). This dimensionless value (z) allows us to combine the scores of the five different
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
73
components of the ranking process, regardless of the total possible points that each
component can achieve.
The score recorded for each of the sub-components is presented in Volume II, along with the
computation details of the addition and standardization of sub-components and each of the
five main components of the ranking method. In a first instance all components were
assigned the same ―weight‖ (W = 1). The results are presented in the table below:
Table 7: Ranking Based on Standardized Z scores
No Prefeasibility
W+ = 1
Total Rank
w+ z
*
1 Rehabilitation and improvement of LBOD drainage infrastructure 5.850 1
2 Revival of natural waterways to drain out storm water 4.842 2
9 Protective plantation of mangroves in the coastal areas of left bank 3.002 3
5 Privatization of FGW SCARP tubewells 2.302 4
3 Rehabilitation of LBOD and SCARP tubewells 2.156 5
15 Establishment of Disaster Management Cell in SIDA 0.769 6
11 Bio-saline agriculture in Badin and Thatta districts 0.325 7
12 Rehabilitation of Deh Akro II and Chotiari wetland complex 0.195 8
16 Gender mainstreaming in irrigation and drainage -0.748 9
10 Use of drainage water for forestation in the LBOD and Kotri areas -0.776 10
4 Ghotki SCARP (saline zone) -1.478 11
7 Elevated platforms for flood displaced persons -2.235 12
14 Brackish water fish farming in LBOD area -2.284 13
13 Shrimp and mud crab farming in coastal areas of left bank -3.007 14
8 Rehabilitation of coastal wetlands -3.404 15
6 Second line of defense for left bank of Indus d/s Kotri -5.509 16
* Standardized Index
+ Weight
Sensitivity analysis was also run increasing the weight of the social component in order to see
the effect on the ranking. The social component ―z‖ value was increased by 50% and the
other four components were left unchanged. The results show that the first seven schemes
continued to have the same ranking position.
6.4 Proposed Prioritizing and Sequencing of Interventions
6.4.1 First Priority Core Interventions
It is proposed that given the exigency of the intervention, and considering their quantifiable
and non-quantifiable benefits, five of the above pre feasibilities are recommended for
undertaking detailed feasibilities, as core projects of high priority. They include:
i. Rehabilitation and improvement of LBOD drainage infrastructure (ranked 1);
ii. Revival of natural waterways to drain out storm water (ranked 2);
iii. Protective plantation of mangroves in the coastal areas of left bank (ranked 3);
iv. Establishment of Disaster Management Cell in SIDA (ranked 6); and
v. Gender mainstreaming in Irrigation and Drainage (ranked 9).
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
74
The first two have direct bearing on the aversion of flood disaster, if the high rain events
relapse. They are expected to ensure timely and safe evacuation of storm water floods, and
would save colossal loss and damage to standing crops, livestock, private and public
properties and infrastructure, and more importantly human lives, and quality of life of rural
communities, and miseries thereof.
The third intervention will complement the safe outfall of the drainage effluent into the sea,
protect the outfall drainage infrastructure, and arrest and retard sea encroachment and
salinization of productive farm land and water bodies in the coastal areas. It would also
support livelihood of the coastal communities through restoration of fish potential.
Given the magnitude of the flooding risk and the inadequate capacity of the SIDA to cope
with the water disasters, may it be storm water flood or river floods, the need for creating a
vibrant and efficient Disaster Management Cell is overbearing, to coordinate the rescue,
relief, and rehabilitation work in conjunction with PDMA and other relevant agencies.
It is proposed that to ensure the role of women in the participatory water management
approach, the overarching mandate of SIDA, the social cell within SIDA also assumes the
responsibility of ensuring main streaming in the organization, and adopt the
recommendations of the pre-feasibility for the purpose which has been ranked nine in the
selection criteria mentioned above.
Although the ―Gender Mainstreaming in Irrigation and Drainage‖ sub-project was ranked at
9th place due to no assigned points for financial and environmental components, the
Consultant proposed the scheme for implementation due to numerous unquantifiable benefits
of investing in the development of human resources. Numerous studies and donor
organizations including the World Bank advocate for women‘s participation in various
programs to enhanced efficiency: ‗Women who are trained to manage and maintain
community water systems often perform better than men because they are less likely to
migrate, more accustomed to voluntary work, and better entrusted to administer funds
honestly‘ (World Bank 1992: 113). ‗Investing in women‘ has been critically described as
instrumentalist by scholars, noting how women have been taken on board insofar as they
could contribute to productivity objectives, yet sidestepping deliberate advances towards
achieving gender equality or transforming existing gender/power structures (Jackson 2000;
Cleaver 2003)‘. (Women and water management: an integrated approach‖, Dublin Principle
3, International Conference on Water and the Environment Development Issues for the 21st
Century, (Dublin, 1992., http://fiesta.bren.ucsb.edu/~idgec/papers/Babette_Resurreccion.pdf)
6.4.2 Second Priority Interventions
i. Privatization of FGW SCARP tubewells (ranked 4); and
ii. Rehabilitation of LBOD and SCARP tubewells (ranked 5).
The review of the feasibility for the divestment of FGW tubewells Project (prepared by
Consultants engaged by PID), was undertaken to reassess and evaluate its technical and
economic viability in the current situation suggests that the project is still viable.
Nonetheless, since the completion of the feasibility, the number of private tubewells has
surged, and the demand for additional tubewell should have declined. Therefore the emphasis
should be on divesting the existing public sector tubewell and facilitating the farmers to
develop their own tubewells.
Similarly, the pre-feasibility of rehabilitation of the dysfunctional and non-operative SGW
tubewells suggests that the investment will have a positive payoff. Notwithstanding its
benefits the sustainability of investment is in question. It is reported by the beneficiaries, and
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
75
observed by Consultants during the field visits, that more than 50 per cent of the tubewells
are closed, mostly due to vandalizing of the pumps, motors, electrical fixtures, PMT, LTL,
and HTL. The farmers apprehend that without safeguards for their protection, they would be
closed down before the objective of lowering the water table is achieved. Hence is a risky
investment.
Rather than reinventing the wheels, PC-Is, may be formulated by SIDA and PID within their
jurisdictions, using the current prices, and submit for approval to the relevant forum, subject
to availability of funds and if included in the development plans.
6.4.3 Third Priority Interventions
The following three projects, despite their technical feasibility, are marginally economic
viable, and the rate of returns are not robust, and seems sensitive to variations in costs and
benefits.
i. Bio-saline agriculture in Badin and Thatta districts (ranked 7);
ii. Use of drainage water for forestation in the LBOD and Kotri areas (ranked 10);
iii. Rehabilitation of Deh Akro II and Chotiari wetland complex (ranked 8).
The pre feasibilities of the first two abovementioned interventions suggest that the
investments has modest rate of returns, however are sensitive to changes in cost and benefit
structures. As these are directly relevant to the facilitating timely and safely disposal of the
storm waters, and also not within the preview and mandate of the SIDA or PID, should be
entrusted to the relevant agencies for its development into the respective development
programs i.e. (i) above to Agriculture Department and (ii) above to Sindh Forest Department.
The analysis of the prefeasibility for the Rehabilitation of Deh Akro II and Chotiari wetland
complex suggests that the main benefits is restoration of wildlife, and ecology of the
wetlands, with limited quantifiable benefits from intercepting seepage from the Chotiari lake
and preparation of a management plan for above wetlands.
It is recommended that the detail formulation and implementation of these interventions
should be entrusted to the relevant agencies i.e. Wildlife Department for Deh Akro II and
Irrigation Department for Chotiari. A co-ordinated effort will be required to implement these
interventions as for Deh Akro freshwater will be required from Nara Canal to revive the
dhandhs and for Chotiari Irrigation department and SIDA will be involved.
6.4.4 Interventions Not Recommended for Implementation
Following pre feasibilities were prepared and the analysis and it is recommended that they do
not merit further considerations, for reasons mentioned below. They proposed interventions
evaluated are:
i. Ghotki SCARP - saline zone, (ranked 11);
ii. Elevated platforms for flood displaced persons (ranked 12);
iii. Brackish water fish farming in LBOD area (ranked 13);
iv. Shrimp and mud crab farming in coastal areas of left bank (ranked 14);
v. Rehabilitation of coastal wetlands (ranked 15);
vi. Second line of defense for left bank of Indus d/s Kotri (ranked 16).
The review of feasibility of Ghotki SCARP (1994), prepared by the Consultants engaged by
WAPDA suggests that the proposed intervention is not economically viable now (price level
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
76
of 2012), and will have enormous negative environmental consequences, mitigation of which
will have high cost, which would further depress the economic viability. Moreover, the
prefeasibility for the revival of dhoras includes construction of surface drainage network to
flush out storm water flows from the Ghotki area.
The prefeasibility of the elevated platforms, prepared by the Consultants, suggest the
proposed intervention has a very high cost (about Rs.1.2 billion), and would provide refuge to
some 20,000 families or about 100 to 120 thousand souls. Moreover, it would be expensive to
maintain these elevated platforms when not use. In addition due the threat of unauthorized
occupation for other purposes, its sustainability is extremely unlikely. However, the widened
drainage banks and canals, and sections of roads, if widened and strengthened could be cost
effective, and will be accessible to a large number of flood displaced persons.
The prefeasibility of two interventions i.e. brackish water fish farming in LBOD area, and
Shrimp and mud crab farming in the coastal areas of left bank indicate that the interventions
have modest rate of return, but sensitive to changes in cost and prices. As the proposed
interventions are essentially a private sector activity, the Sindh Fisheries Department could
provide back up support to the interested potential fish farmers.
The prefeasibility of rehabilitation of coastal wetlands shows that intervention will not yield
enough returns to justify investment, will have high risk of failure due to cyclones of the
magnitude of 1999 cyclone 2A and will not be sustainable. In addition, the sugar mills
effluent laden water from Karo Ghungro and Guni Phuleli drains will kill the local fish
proposed to be promoted in dhand complex. Hence the intervention needs to be dropped for
further considerations.
Similarly, second line of defence intervention was found technically viable, but is not socially
acceptable. The communities along the proposed alignment vehemently opposed its
implementation, as it entails risk of flood disaster. Hence, it is recommended that this does
not warrant further considerations.
6.5 Implementation Chronogram
Two ten implementation chronograms were prepared. The first one considering all 16
identified solutions, including the unfeasible interventions according to the ranking
conducted. Occasionally some financially/economically unfeasible schemes can be chosen if
they are socially needed or because the country might have specific interests.
Two first priority interventions recommended by the Master/Regional Plan Consultants have
been questioned. SIDA instructed that no further work should be conducted in the study of
the Establishment of the Disaster Management Cell in SIDA, therefore the work already done
on it is reported along the other feasible schemes, but will not be included in Phase-III.
The Panel of Experts also expressed their dis-conformity about the high priority scheme
according to the Consultants criterion: Gender Mainstreaming in Irrigation and Drainage.
Therefore the work already done this particular intervention is reported along the other
feasible schemes, and will not be included in Phase-III, unless SIDA issues specific
instructions to do so.
The implementation chronogram including all sixteen schemes is presented below:
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
77
6.6 Implementation Strategy for the Rehabilitation and Improvement of LBOD
LBOD was originally designed for
a rainfall storm of 5 years return
period (Tr) magnitude, reported by
the World Bank in 2005, “…the
design criteria provided an
available capacity to drain 125 mm
rainfall of 5 days duration in a 5
days period.” The Master/Regional
Plan Consultants conducted a risk
analysis of this particular storm
magnitude and concluded that the
probability that an event of Tr = 5
years will happened within 3 years
period is 50%. This is the
equivalent to tossing a coin every
three years and hoping it will fall heads up.
As explained above, the original capacity of LBOD was limited, which –partially- explains
the recurrent flooding experienced by the people of the lower areas. The maintenance and
desilting practices of LBOD have increased the cross sectional area of the channel, increasing
its water removal and conveyance capacity.
As a result of the extraordinary rainfall recorded during 2011, a series of meetings with the
relevant institutions were held, where it was decided to prepare short and long term plans to
minimize the periodically recurring negative flooding effects and to increase the capacity of
the channel in order to be able to convey and dispose waters of significantly larger storms,
enlarging the recurrence period.
The total cost of the civil works have been worked out based on initial survey work,
discharge measurements during storm water flood of 2011 and adopting unit rates of existing
infrastructure in the Sindh Province. The budget details for the short and long term measures,
including miscellaneous support costs, such as the fees of the supervision consultants and
10 years Implementation Plan 1 2 3 4 5 6 7 8 9 10
Feasible Schemes
20
12
20
13
20
14
20
15
20
16
20
17
20
18
20
19
20
20
20
21
A First Priority Core Interventions
1 Rehabilitation and improvement of LBOD drainage infrastructure. 17,580
2 Revival of natural waterways to drain out storm water 43,565
3 Protective plantation of mangroves in the coastal areas of left bank 733
4 Establishment of Disaster Management Cell in SIDA (5 years plan) 108
5 Gender mainstreaming in irrigation and drainage (5 years plan) 420
Subtotal 62,406
B Second Priority Interventions
1 Privatization of FGW SCARP tubewells 8,290
2 Rehabilitation of LBOD and SCARP tubewells 2,603
Subtotal 10,893
C Third Priority Interventions
1 Bio-saline agriculture in Badin and Thatta districts 2,350
2 Use of drainage water for forestation in the LBOD and Kotri areas 225
3 Rehabilitation of Deh Akro II and Chotiari wetland complex 585
Subtotal 3,160
Grand Total 76,459
Investment
(Rs. Million)
-
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
Inves
tmen
t in
Mil
lion
Ru
pee
s
10 Year Investment Plan for Priority Scheme
With Base Cost With Price Contigency
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
78
others, are presented in detail in table 4. The total costs estimated for the civil works are
about Rs. 16.5 Billion and Rs. 1.2 Billion for miscellaneous expenditures, making a total of
about Rs.17.6 Billion.
6.6.1 Short Term Structural Measures
Following are the suggested short term measures for implementation in a period of 1to 3
years:
i. Raising Banks of Spinal Drainage to Free Board for storm level of 2011.
ii. Rehabilitation of Nawabshah (Shaheed Benazirabad) component of drainage
network.
iii. Rehabilitation of Sanghar component of drainage network.
iv. Rehabilitation of Mirpur Khas component of drainage network.
v. Rehabilitation of Badin component of drainage network.
vi. Rehabilitation of Fulleli Guni Drain.
vii. Rehabilitation of Karo Ghungro Drain.
viii. Rehabilitation of KPOD Outfall Drain.
ix. Rehabilitation of DPOD Drain.
x. Construction of inlets at sites of relief cuts.
xi. Reconstruction of damaged Water Course Crossings and Bridges.
xii. Raising of deck slabs of Submerged Bridges by 2 to 3 feet and also providing
additional water way by adding 1 to 2 spans through bypass culverts/bays.
xiii. Providing stone pitching upstream and downstream of all structures on Spinal,
KPOD and all Branch and Main drains in a length of 500 ft (200 ft upstream
and 200 ft downstream).
xiv. Rising of Banks of Main Drain/Branch Drain at outfall points by 3 to 4 ft in a
length of 10,000 ft to create surcharge storage.
6.6.2 Long Term Structural Measures
Following are the suggested long term measures for implementation in a period of 4 to 6
years:
i. Remodeling of LBOD Drainage Network for a return period of 20 years.
ii. Remodeling of KPOD to a discharge of 6,000 cs.
iii. Remodeling of LBOD Branch Drain to 2,000 cs.
iv. Remodeling of Main Mirpur Khas Main Drain.
v. Converting non inspection path of spinal/main and all branch drains as per IP.
vi. Construction of all weather Road from RD 159 of Spinal Drain to RD 815 of
Spinal Drain.
vii. Providing gated structures at outfall points of drains along KPOD.
viii. Providing pumping arrangement at outfall points of Badin drainage system.
ix. Construction of New Bridges/Water Course Aqueducts on LBOD system.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
79
x. Construction of additional Inlets to support On Farm drainage at field level.
xi. Off-loading of spinal drain discharge by a minimum of 3,000 cusecs into old
Dhoras/Dhands.
xii. Construction of Tidal Control Cross- Regulator at RD (-) 12 of KPOD.
xiii. Construction of Head Regulator at RD 159 of KPOD/DPOD.
xiv. Providing additional drainage culverts/causeway at crossing points of road
network.
6.6.3 LBOD rehabilitation construction chronogram
The construction activities are planned to be implemented in two phases. The reparation and
deferred maintenance works as short term activities to enhance the conveyance capacity of
the channel, aiming at protecting the population from the waters coming in the next monsoon
season and the long term undertakings to complete the works as per the design of the present
Consultancy Agreement. The gross chronogram of activities is presented below.
6.7 Implementation strategy for the revival of natural waterways to drain out storm
water
The 2011 unprecedented rainfall observed in Sindh was a wakeup call regarding the flooding
issues that the Province has been experiencing for a number of years. The floods experienced
in year 2011, revealed that the Left Bank area of Indus River has no outlet, except for LBOD,
which performed beyond its capacity. The water ponded for weeks despite the efforts of
SIDA, the Irrigation Department, the military and other authorities to dispose the rain water
off, because the natural waterways (dhoras) had been hindered by canals, drains, roads, and
encroachments of various types.
No Main Outputs
1. Restoration of Spinal Drain (RD 815 to 159) including Structure repair
2. Restoration of DPOD (RD127 to RD 5)
3. Restoration of KPOD (RD 159 to RD 0)
4. Restoration of LBOD branches, KPOD, and other drains
5. Restoration of Mirpurkhas component surface drains
6. Restoration of Sanghar component Surface drains
7. Restoration of Nawabshah component
8. Restoration of Fulleli Guni drainage system
9. Restoration of Karo Gungro drainage system
10. Remodeling of LBOD drainage system for a return period of 20 years
11. Remodeling of KPOD to discharge of 6,000 cfs;
12. Remodeling of Mirpur Khas Main Drain for Separation from Dhoro Puran.
13. Converting Non-Inspection Path (NIP) of Spinal/Main & all Branch drains to par with IP
14. Construction of All Weather Road from RD 159 RD 815 of Spinal Drain.
15. Providing Pumping arrangements at outfall points of Badin Drainage System
16. Construction of New Bridges +WC Aqueducts on LBOD System
17. Construction of new inlets to support of farm drainage
18. Construction of Tidal Control Regulator at RD minus 12 of KPOD
19. Construction of Head Regulator of KPOD RD 159
20. Ancillary works
21. Supervision Consultants
22. Construction of site offices and residential quarters
23. Procurement of boats and vehicles
24. Procurement of survey and scientific equipment
25. Procurement of radio communication system
26. Establishment of early warning system Cell
2019 2020
LBOD Proposed Gross Implementation Activities Chronograph Quarters and Years
2012 2013 2014 2015 2016 2017 2018
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
80
The conclusion after several meetings with the relevant authorities was that the natural
waterways (dhoras) had to be activated. Accordingly, the Master/Regional Plan Consultants
have developed and recommend the plan described below:
6.7.1 Suggested implementation plan for drainage in lower Sindh
In view of huge cost involved in the activation of natural waterways it is proposed that the
plan may be implemented in phases according to the availability of funds priority of works.
6.7.2 Top priority works before forth coming monsoon rains
i. Activation of dhoras on left side of LBOD Spinal Drain i.e. Hakro Dhoro,
Naro Dhoro and Pithoro Dhoro / Hiral Escape.
ii. Activation of full length of Dhoro Puran from Mirpurkhas to RD 110 of
DPOD including Mirpurkhas bypass.
iii. Separate outfall for Mirpurkhas Main Drain carrying highly polluted effluent,
into LBOD Spinal Drain.
iv. After separation of MMD, Dhoro Puran shall be routed to its natural path
under passing LBOD Spinal Drain.
v. Reconstruction of Dhoro Puran sections which have been utilized in the
alignment of LBOD Spinal Drain to provide clear passage to storm water.
vi. Construction of dhora bypasses proposed for Jhudo, Digri and Naukot towns.
6.7.3 Priority-2 works
i. Providing drainage to cutoff portions of Dhoro Puran on right side of LBOD
Spinal Drain and Mirpurkhas Main Drain by providing under passes / siphons
across Mirpurkhas Main Drain and LBOD Spinal Drain.
ii. Activation of Digri Dhoro, Sohni Dhoro and Bhai Khan Dhoro and connecting
them with Dhoro Puran by constructing under passes across Mirpurkhas Main
Drain and LBOD Spinal Drain.
iii. Construction of dhora bypasses proposed for Digri and Tando Ghulam Ali
towns.
6.7.4 Priority-3 works
i. Construction of adequate sized structures across the dhoras based on 20 years
return period. The construction of numerous structures can take longer time
and cannot be completed before monsoon 2012. As such, in the event of any
heavy rainfall in the monsoon 2012, relief cuts to roads with inadequate sized
culverts could be given to smoothly pass storm water. However, boats will be
required to facilitate local people on either side to cross the dhoras.
ii. Construction of drainage network including structures, proposed for the left
over areas of Umarkot, Digri, Tando Adam, Tando Allahyar and Tando
Ghulam Ali outside the catchment of LBOD system.
6.7.5 Activation of natural waterways chronogram
The construction activities are planned to be implemented in two phases or two terms. The
most important ones as short term activities to protect the population from the waters coming
in the next monsoon season and aiming at minimizing the potential flooding damages as soon
as it is possible to be implemented and, the long term undertakings to complete the works as
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
81
per the design of the present Consultancy Agreement. The gross chronogram of activities is
presented below.
6.7.6 Activation of Natural Waterways Investment Costs
The estimated indicative cost for the proposed activation of the dhoras is presented in table 6,
where besides the costs of the civil works, the costs related to the required supervision
consultants at 2% of the cost of the civil works were added, plus a gross estimate of the land
acquisition and resettlement activities.
6.8 Policy Issues
6.8.1 Deferred Maintenance
One of the reasons for the poor performance
of the existing drainage system has been
deferred maintenance and allocation of
budgets for the purpose. It is recommended
that adequate budget should be allocated to
ensure best practices and a watch dog
committee comprising of representatives
from the relevant AWBs, representatives of
the civil society, and SIDA and PID officials
to monitor the upkeep of the system.
6.8.2 Effective compliance of environmental protection laws
The discharge of toxic effluent from the sugar mills into the drainage system is a major cause
of concern expressed by the stakeholders. Apart from the foul smell it emits from the drains,
its toxicity is detrimental to aquatic life in the drains and the water bodies along the KPOD
and tidal link. This environmental hazard needs to be monitored and checked by the relevant
provincial agencies, particularly Environmental Protection Agency (EPA) in the province.
A review of the existing regulatory mechanism suggests that the sugar mills find it cheaper to
pay the fine, if imposed, than to invest in treating the effluent plant within the sugar mills. It
is rather an incentive to breach the compliance. It is recommended that following the
No Main OutputsStart
DateEnd Date
1Activation of dhoras, Puran up to Shakoord dhand, Sohni dhoro & Bhai Khan
dhoro and bypasses of Mirpurkhas, Jhuddo, Tando Ghulam Ali4/2012 6/2020
2Activation & Restoration of pocket drains along Hiral escape/ Pithoro Dhoro,
Hakro Dhoro & Naro (Nabisar) Dhoro i/c Naukot bypass4/2012 6/2020
3 Activation of Sarfaraz (Digri) Dhoro , including Digri bypasses 4/2012 6/2020
4 Excavation and revival of Pangrio, Kh‘ Gumbo & Roshanabad dhoras 7/2014 6/2020
5 Excavation and revival of Ghotki dhoras 7/2014 6/2020
6 Excavation and revival of Khairpur South dhoras 7/2014 6/2020
7 Construction of surface drains in T.Adam, T.AllahYar, T.M Khan and TG ALI
area
7/2014 6/2020
8 Construction of surface drains in Digri area 7/2014 6/2020
9 Construction of surface drains in Umerkot, Farash and Khipro area 7/2014 6/2020
10 Construction of surface drains in Ghotki area 7/2014 6/2020
11 Construction of surface drains in Khairpur South area 7/2014 6/2020
12 Construction of 3X Escapes on LBOD i/c Weirs and Link Channels 7/2014 6/2020
2017
Revival of Dhoras
Leftover Areas
LBOD Escapes
2018 2019 2020
Gross Chronogram of Activities for the Activation of natural Waterways (dhoras)
2012 2013 2014 2015 2016
0
20,000
40,000
60,000
80,000
100,000
Invest
men
t in
Mil
lio
n R
up
ees
10 Years Cummulative Investment for
Priority Schemes
With Base Cost With Price Contigency
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
82
‗pollutant to pay principle‘ the punitive default charge is enhanced to encourage the sugar
mills to refrain from dumping untreated effluent into the drainage or irrigation canals.
6.8.3 Cost Recovery Policy
The main benefit from the investment in rehabilitating, remodeling, the drainage system
including reviving of dhoras is to ensure safe disposal of the storm water (for storms of 20
years return period or less magnitude) and reduction of flood damages losses to all the sectors
of the economy (for larger storms). There is an urgent need for a policy to recover the capital
cost or at least the annual expenditure on operation and maintenance of the drainage system.
It is proposed that a pricing policy is articulated and formulated for enforcement of drainage
cess.
As the benefits of the drainage system improvements is not limited to the agriculture and
livestock sectors, it creates significant consumer surplus for the population in general, and
hence all the beneficiaries should contribute to the repayment of the capital and or operation
and maintenance cost, commensurate with share in the benefits. A study should be entrusted
to an economic research outfit and is financed by the Planning and Development Department
to estimate the benefits to different sectors and to assign a fair share to the direct and indirect
beneficiaries, considering the repayment capacity. The analysis should also recommend an
administratively easy mode of assessment and collection.
6.9 Summary Recommendations
The main objective of the Phase-II study was to i) identify structural and non-structural
solutions/options and interventions; ii) prepare pre feasibilities of the interventions selected
through stakeholder consultative process, detailing rationale, output, impact, along with
technical and economic viability, sustainability, and socially acceptability. Based on the
criteria developed the pre feasibilities have been ranked and prioritized. Following are the
recommendations for the consideration of SIDA, PID, and the GoS.
A. Core Projects be Selected as First Priority
The following pre feasibilities are recommended for formulating detailed feasibility during
the Phase-III.
i. rehabilitation and improvement of LBOD drainage infrastructure;
ii. revival of natural water ways (dhoras) to drain out the storm water;
iii. protective plantation of mangroves in the coastal areas of left bank;
iv. establishment of Disaster Management Cell in SIDA; and
v. gender mainstreaming in irrigation and drainage.
B. Preparation of PC Is for the Second Priority Projects
It is proposed that the following second priority interventions are considered for preparing
revised PC Is by the PID, and submitted for the approval of the GoS.
i. Privatization of FGW SCARP tubewells; and
ii. Rehabilitation of the LBOD and SCARP tubewells,
C. Projects to be Processed by the Relevant Line Departments
Following the third priority interventions should be entrusted the relevant line
agencies for further processing. These include:
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
83
i. Bio-saline agriculture in Badin and Thatta districts
ii. Use of drainage water for forestation in the LBOD and Kotri areas
iii. Rehabilitation of Deh Akro II and Chotiari wetland complex.
D. Projects Not Recommended for Further Pursuing
The analyses of six of the prefeasibility suggest that they do not merit considerations for
further pursuing, either they are unfeasible, or private sector activity, socially not acceptable,
and or risk of sustainability. They are:
i. Ghotki SCARP in saline zone (unfeasible);
ii. Rehabilitation of coastal wetlands (unfeasible);
iii. Elevated platforms for flood displaced persons (not sustainable); however
widened and strengthened drain and canal banks, and raised and widened section
of roads could be a cost effective alternative.
iv. Brackish water fish farming in LBOD area (feasible, but a private sector activity);
v. Shrimp and mud crab farming in coastal areas of left bank (feasible, but a private
sector activity); and
vi. Second line of defence for left bank of Indus d/s Kotri. (Socially not acceptable).
E. Non Structural Interventions/Pre Requisites
i. In addition to this, SIDA and PID should ensure that the irrigation canals are
closed at least one week before the rain warning.
ii. It is further recommended that before the ensuing monsoons, the heavy machinery
should be mobilized to vulnerable point on the drainage network by July 30 each
year,
iii. As it is anticipated that that the coming years will experience high level of
precipitation of about 2011 magnitude, SIDA/PID should ensure that the
information regarding expected floods and its intensity is widely and timely
disseminated, and coordinate with PDMA, district administrations, and relevant
NGOs for flood preparedness.
F. Effective Compliance and Enforcement of EPA regulations for Sugar mills.
i. The EPA should monitor that the sugar mills comply with the environmental
protection laws, and do not dump their untreated toxic effluent directly into the
water bodies including drains.
ii. EPA should also rationalize the fines on the sugar mills for non-compliance.
G. Initiation and Facilitation of Inter-Provincial Dialogue
To address the concerns expressed by the stakeholders located in the northern strip of Ghotki,
regarding the encroachment of saline effluent from SCARP VI adversely affecting the fertile
cropped lands, the environment water table and quality of ground water, SIDA needs to
initiate and facilitate an interprovincial dialogue, at the appropriate level. The Consultants
recommend implementing the project as per the original design.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
84
6.10 Indicative Financial Outlay of Master Plan
The indicative cost of interventions was estimated for all the pre-feasibilities using current
2012 prices. The base costs include a two per cent provision as physical contingency. Total
cost was also computed accounting for three per cent as price escalation for construction
industry.
It is estimated that the overall base cost of recommended and not recommended intervention
is about Rs.93.8 billion. With the provision of price contingency the total cost is about Rs.111
billion. Out of this, the estimated base cost of the recommended interventions is about
Rs.76.5 billion, and the total cost inclusive of price contingency is Rs.90.1 billion. It may be
noted, that the total cost includes 17.5 per cent as taxes, suggesting that the net financing
requirement will be reduced by about Rs.15.8 billion.
Following table summarises the financial outlay for the priority interventions. The detailed
year wise expenditure, both for base costs and with price contingency of 3 per cent is
presented in annex 1 and annex 2 respectively.
Table 8: Indicative Financial Outlay of Master Plan
Prefeasibility
Investment
(Rs. Million)a
A First Priority Core Interventions
1 Rehabilitation and improvement of LBOD drainage infrastructure b 17,580
2 Revival of natural waterways to drain out storm water b 43,565
3 Protective plantation of mangroves in the coastal areas of left bank 733
4 Establishment of Disaster Management Cell in SIDA 108
5 Gender mainstreaming in irrigation and drainage 420
Subtotal 62,406
B Second Priority Interventions
1 Privatization of FGW SCARP tubewells 8,290
2 Rehabilitation of LBOD and SCARP tubewells 2,603
Subtotal 10,893
C Third Priority Interventions
1 Bio-saline agriculture in Badin and Thatta districts 2,350
2 Use of drainage water for forestation in the LBOD and Kotri areas 225
3 Rehabilitation of Deh Akro II and Chotiari wetland complex 585
Subtotal 3,160
Total Base Cost of Intervention 76,459
Price contingency @ 3% yearly for construction sector escalation 24,434
Total Investment cost 90,083 a: These costs are base costs and include provision of 2 percent for unforeseen and physical contingency.
b: includes Rs.1,500 million and Rs.102 million cost to be incurred as emergency works
respectively for LBOD and Dhoras during April 2012 and 30 June 2012
6.11 Investment Chronogram
The two implementation alternatives were analyzed from the investment perspective, looking
at the annual and the cumulative budgets required for each alternative, putting special
emphasis on the first priority interventions, as these cover the main schemes, rehabilitation of
LBOD and revival of dhoras. The latter includes the investment of storm drainage provision
to the left over areas.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
85
The first priority interventions, recommended by the Master/Regional Plan Consultants
contemplate an annual maximum investment of nearly Rs. 7 Billion per year during eight
financial years. The annual investment required and the nine years cumulative investments
are presented in the chart.
The ten years investment plan for all sixteen schemes requires an average annual investment
of about Rs.5 Billion a year, concentrating most of the disbursement in the first nine years
due to the works to be carried out at the LBOD and dhoras. The peak investment obviously
falls in the first priority schemes and is of the order of Rs.9 Billion in year 2018, which
corresponds to the seventh year of the implementation component of the project. The
cumulated investment is about Rs.92.3 Billion. The details of the budget required and
chronogram are given in Annexure A of this chapter.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
86
Annex 1: Base Cost estimates of all Schemes
1 2 3 4 5 6 7 8 9 10 Total
A. First Priority Core Interventions
1. Rehabilitation and improvement of LBOD Drainage Infrastructure 1,568.0 2,670.0 1,834.0 1,918.0 1,918.0 1,918.0 1,918.0 1,918.0 1,918.0 - 17,580.0
2. Revival of natural waterways to drain out storm water 102.0 823.0 1,792.0 6,808.0 6,808.0 6,808.0 6,808.0 6,808.0 6,808.0 - 43,565.0
3. Protective plantation of mangroves in the coastal areas of the left bank - - 53.0 163.0 174.0 177.0 166.0 - - - 733.0
4. Establishment of disaster management cell in SIDA - - 30.0 20.0 20.0 19.0 19.0 - - - 108.0
5. Gender mainstreaming in irrigation and drainage - - 84.0 84.0 84.0 84.0 84.0 - - - 420.0
Subtotal 1,670.0 3,493.0 3,793.0 8,993.0 9,004.0 9,006.0 8,995.0 8,726.0 8,726.0 - 62,406.0
B. Second Priority Interventions
1. Privatization pf FGW SCARP tubewells - - - 1,658.0 1,658.0 1,658.0 1,658.0 1,658.0 - - 8,290.0
2. Rehabilitation of LBOD and SCARP tubewells - - - 520.6 520.6 520.6 520.6 520.6 - - 2,603.0
Subtotal - - - 2,178.6 2,178.6 2,178.6 2,178.6 2,178.6 - - 10,893.0
C. Third Priority Interventions
1. Bio-saline agriculture in Badin and Thatta districts - - - - - 190.0 540.0 540.0 540.0 540.0 2,350.0
2. Use of drainage water for forestation in the LBOD and Kotri areas - - - - - 45.0 45.0 45.0 45.0 45.0 225.0
3. Rehabilitation of Deh Akro II and Chotiari wetland complex - - - - - 195.0 195.0 195.0 - - 585.0
Subtotal - - - - - 430.0 780.0 780.0 585.0 585.0 3,160.0
Total Baseline Cost (Priority Interventions) 1,670.0 3,493.0 3,793.0 11,171.6 11,182.6 11,614.6 11,953.6 11,684.6 9,311.0 585.0 76,459.0
D. Not Recommended for Pusuing Further
1. Ghotki SCARP (Saline Zone) - - - - - 1,350.0 1,563.0 1,280.0 752.0 98.0 5,043.0
2. Elevated platforms for flood displaced persons - 200.0 200.0 200.0 200.0 200.0 200.0 - - - 1,200.0
3. Brackish water fish farming in LBOD area (credit line) - - - - - 109.0 109.0 109.0 109.0 109.0 545.0
4. Shrimp and mud carab farming in coastal areas of letft bank (credit line) - - - - - 24.8 24.8 24.8 24.8 24.8 124.0
5. Rehabilitation of coastal wetlands complex - - - - - 1,688.0 1,688.0 1,688.0 1,688.0 1,690.0 8,442.0
6. Second line of defense for left bank of Indus d/s Kotri - - - - 330.0 331.0 331.0 331.0 331.0 331.0 1,985.0
Subtotal - 200.0 200.0 200.0 530.0 3,702.8 3,915.8 3,432.8 2,904.8 2,252.8 17,339.0
Total Baseline Cost (Priority and non recommend interventions) 1,670.0 3,693.0 3,993.0 11,371.6 11,712.6 15,317.4 15,869.4 15,117.4 12,215.8 2,837.8 93,798.0
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
87
Annex 2: Cost estimates of all Schemes including Price Contingency
1 2 3 4 5 6 7 8 9 10 Total
A. First Priority Core Interventions
1. Rehabilitation and improvement of LBOD Drainage Infrastructure 1,591.5 2,791.4 1,974.9 2,127.3 2,191.1 2,256.8 2,324.5 2,394.3 2,466.1 - 20,117.9
2. Revival of natural waterways to drain out storm water 103.5 860.4 1,929.6 7,550.9 7,777.4 8,010.7 8,251.0 8,498.6 8,753.5 - 51,735.7
3. Protective plantation of mangroves in the coastal areas of the left bank - - 57.1 180.8 198.8 208.3 201.2 - - - 846.1
4. Establishment of disaster management cell in SIDA - - 32.3 22.2 22.8 22.4 23.0 - - - 122.7
5. Gender mainstreaming in irrigation and drainage - - 90.5 93.2 96.0 98.8 101.8 - - - 480.2
Subtotal 1,695.1 3,651.8 4,084.4 9,974.3 10,286.1 10,597.0 10,901.6 10,892.9 11,219.6 - 73,302.7
B. Second Priority Interventions
1. Privatization pf FGW SCARP tubewells - - - 1,838.9 1,894.1 1,950.9 2,009.4 2,069.7 - - 9,763.1
2. Rehabilitation of LBOD and SCARP tubewells - - - 577.4 594.7 612.6 630.9 649.9 - - 3,065.5
Subtotal - - - 2,416.3 2,488.8 2,563.5 2,640.4 2,719.6 - - 12,828.6
C. Third Priority Interventions
1. Bio-saline agriculture in Badin and Thatta districts - - - - - 223.6 654.5 674.1 694.3 715.1 2,961.6
2. Use of drainage water for forestation in the LBOD and Kotri areas - - - - - 52.9 54.5 56.2 57.9 59.6 281.1
3. Rehabilitation of Deh Akro II and Chotiari wetland complex - - - - - 229.4 236.3 243.4 - - 709.2
Subtotal - - - - - 506.0 945.3 973.7 752.2 774.7 3,951.9
Total Project Cost (Priority Interventions) 1,695.1 3,651.8 4,084.4 12,390.6 12,774.9 13,666.5 14,487.3 14,586.1 11,971.8 774.7 90,083.2
D. Nont Recommended for Pusuing Further
1. Ghotki SCARP (Saline Zone) - - - - - 1,588.5 1,894.3 1,597.9 966.9 129.8 6,177.3
2. Elevated platforms for flood displaced persons - 209.1 215.4 221.8 228.5 235.3 242.4 - - - 1,352.5
3. Brackish water fish farming in LBOD area (credit line) - - - - - 128.3 132.1 136.1 140.1 144.4 680.9
4. Shrimp and mud carab farming in coastal areas of letft bank (credit line) - - - - - 29.2 30.0 30.9 31.9 32.8 154.9
5. Rehabilitation of coastal wetlands complex - - - - - 1,986.2 2,045.8 2,107.2 2,170.4 2,238.1 10,547.7
6. Second line of defense for left bank of Indus d/s Kotri - - - - 377.0 389.5 401.2 413.2 425.6 438.4 2,444.8
Subtotal - 209.1 215.4 221.8 605.5 4,356.9 4,745.8 4,285.2 3,734.9 2,983.5 21,358.1
Total Project Cost (Priority and non recommend interventions) 1,695.1 3,860.8 4,299.7 12,612.4 13,380.4 18,023.4 19,233.1 18,871.4 15,706.7 3,758.2 111,441.3
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
88
Attachment 1
STAKEHOLDER CONSULTATION PROCESS
A central point in the preparation of the WSIP-I Regional Plan is preparation of the Plan in
consultations with communities and other major stakeholders. One of the key ―lessons
learnt” (see PAD, WB, 2007) has been to make participatory approaches to development
crucial to project design based on social considerations. Genuine participation and
involvement from the community and other relevant stakeholders, thus, is viewed as essential
throughout the planning and design process not only for this phase of the work but
throughout all four phases.
Therefore preparation of the Master Plan followed the consultative process at all stages of the
study, namely, identification of the issues and options and preparation of pre feasibilities, and
detail designing. The consultations with communities and other main stakeholders were
organized at multiple levels.
The main purpose of the workshop was to present solutions proposed during the consultations
with communities and stakeholders in the Phase-1, and to solicit additional suggestions and
solutions if any; and their endorsement of the proposed solutions, mainly to resolve issues
related to drainage, flooding, environment, natural resources, socio-economic and
institutional issues, and to prioritization the proposed interventions.
To ensure full and equal involvement of men and women of all ages, backgrounds and social
status, a wide range of stakeholders were invited to participate in the workshops in project
area based on fifteen districts of Sindh, three area water boards including national potential
stakeholders. Several interventions were proposed and presented to the stakeholders for the
identified problems related to drainage, flooding, environment, and socio-economic issues.
The main objective of this process of community consultations was to identify structural and
non-structural environment friendly solutions/interventions, ranking and detailed designing of
selected interventions. The solutions to the problems/issues identified during the phase I,
have been compiled, discussed, ranked and endorsed by the stakeholders at intensive Phase II
consultations.
Overall, the phase II consultations were comprised of the workshops organized at three levels
i.e.: i) twelve district level workshops; ii) three Area Water Board level workshops; and iii)
one national/regional level workshop.
The workshops at the district level were organized in the following districts: Ghotki, Sukkur
and Khaipur, Noushero Feroze, Shaheed Benazirabad, Mirpurkhas and Tando Allahyar,
Sanghar, Hyderabad and Matiary, Badin, Thatta, Tando Muhammad Khan, Tharparkar and
Umerkot. In addition, one workshop was organized for each of the three Area Water Boards
(Ghotki Feeder Canal AWB, Nara Canal AWB and Left Bank Canal AWB). The final wrap
up workshop was conducted in Karachi with participation of regional and national
stakeholders.
The participants included representations from the farmers, and line agencies, such as
departments of agriculture, livestock, fisheries, forestry, farmer organizations (FOs), Abadgar
Board, (AWBs), SIDA, civil society. Women were especially encouraged to participate.
These workshops were organized in coordination with fifteen local partner NGOs and
Consortium teams. Based on these consultations and stakeholders‘ suggestions, the
Consultants have formulated several interventions to mitigate the issues and problems mainly
pertaining to drainage, flooding, environment, natural resources, socio-economic and
institutional issues in the left bank of Indus, delta and coastal area. The stakeholders were
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
89
given the opportunity to discuss, endorse or reject those interventions with adding alternative
solutions according to their opinions.
In order to disseminate the preparation of master plan process, project fliers in local
languages were distributed prior to the community consultations. About 10,000 project
pamphlets each in Sindhi and English languages were distributed, along with 81 news
cuttings published in the local media in English, Urdu and Sindhi languages. In addition to
this, six TV programs about the preparation of the master plan and related issues were
organized local TV channels. In order to reach a wider community, a questionnaire to identify
problems and solutions was published in the Sindhi and English newspapers. The feedback
received from stakeholders indicates stakeholder‘s satisfaction and keen interest in the
participatory process. This also helped the consultants in understanding the perceptions and
aspirations of the stakeholders.
The total number of participants in the workshops held during the two phases was 9,077, of
which female participants were 2,455 (about 27 percent). Out of these women 229 were
women active in the professional fields.
In the district level workshops held during the second phase of the study, 1,442 stakeholders
were invited. Of them 1,014 (70 percent) participated in the workshop. Of those who attended,
twelve percent were women (121).
During and after the 2011 storm water floods, the social team visited each district in the
project area, assessed the situation and consulted with the flood affected communities. The
team visited 89 villages in fifteen project area districts and consulted with 1,740 persons in
order to assess the losses/damages of villages, crops destruction, people and livestock
affected, chicken and fish farms destroyed, diseases spread, government/private assistance
provided, source of income available etc. In each district, the team has a partner NGO that
gave us the first hand information about the situation on the ground, suggested villages and
communities to be visited and accompanied our team on each visit. Their work in affected
areas and information and help given to our team are indispensable.
The detailed description of the participatory process, and district wise representation and
participation, and proceedings of the workshops is presented in Volume IV of the Phase II
report.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
90
List of Documents Consulted
Abdul Aleem Chaudhry Ph.D. World Environment Day June 2010. Wetlands in Pakistan:
ACE and Halcrow, (2001) Technical Report No.30, Exploitation and regulations of fresh
groundwater, February 2001
Ajmal and Riazuddin Ansari.2008. Potential Use of Halophytes with Emphasis on Fodder
Production in Coastal Areas of Pakistan. Institute of Sustainable Halophyte
Utilization, University of Karachi.
Ali Hassan Shah, Khalid Hussain Gill & Najaf Iqbal Syed: Experience of Bio-Saline
Approach for Rehabilitation of Salt-Affected Lands in Pakistan. Pakistan Engineering
Congress, 71st Annual Session Proceedings. Paper 692
Amuda O.S. and Ibrahim A.O. 2006. Industrial wastewater treatment using natural material
as adsorbent. African Journal of Biotechnology Vol. 5 (16), pp. 1483-1487
Chandio, B.A. and M.K. Marri. 1988. Suitability of Interceptor Drains. International Seminar
on Hydrological Aspects of Drainage in Irrigated Areas. March 28-30, 1988. DRIP,
Tando Jam. Pakistan.
Cotruvo J et al. (2010) Desalination technology—Health and environmental impacts. Boca
Raton, Florida, IWA Publishing and CRC Press.
Economic Survey of Pakistan, 2007-08, www.scribd.com/doc/17055844
Edward P. Glenn, J. Jed Brown and James W. O‘Leary.1998. Irrigating Crops with Seawater.
Scientific American Inc.
EPA USA. 2004. Primer for Municipal Wastewater Treatment Systems.
FAO (2003) .Sindh Water Resources Management – Issues and Options ‗National Water
Policy (Draft), Ministry of Environment, Government of Pakistan
http://www.who.int/water_sanitation_health/hygiene/sanhygpromotoc.pdf
Gender Reforms Action Plan (GRAP) http://grap.gop.pk/
Gordon V. Johnson. Reclaiming Slick-Spots and Salty Soils. Division of Agricultural
Sciences and Natural Resources • Oklahoma State University.
http://www.osuextra.com
Government of Pakistan Millennium Development Goals Report 2005
http://un.org.pk/undp/publication/PMDGR05.pdf_Goal-3
http://www.irc.nl/page/8237. Waste stabilization ponds for wastewater treatment.
Indus for All Programm (April 2008) ‗Detailed Ecological Assessment Study Report‘ –WWF
Pakistan
Irrigation Department Government of Sindh (2011) Flood damages assessment report for
lower Sindh.
Irrigation Department Government of Sindh (2011) Master Plan for Improvement and
enhancement of storm water drainage system in left bank area of Sindh, ACE Ltd,
Karachi
IUCN. Economic Valuation of Wetlands. 1997. Ramsar Convention Bureau Gland,
Switzerland
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
91
J. R. Campos*, M. A. P. Reali, R. Rossetto and J. Sampaio 2009. A Wastewater Treatment
Plant Composed of UASB Reactors, Activated Sludge with DAF and UV
Disinfection, in Series. Water Practice & Technology Vol 4 No 1 © IWA Publishing.
James M. Ndung‘u. 2009. Economic Valuation of Ecosystem Services in the Shompole
Wetland, South Ewaso Ngiro River, Kenya. Power Point Presentation.
LBOD (1998) LBOD Stage I Project EMMP report
Leela Lyengar ,‖Technologies for fluoride Removal‖ http://www.samsamwater.com/library/
TP 40 _22_ Technologies_for_fluoride_removal.pdf
Lorene Lindsay (2004).Tech Brief • Chlorination, Fall 2004, Vol. 4, Issue 2
Luby. et. al.,). 2006. Combining drinking water treatment and hand washing for diarrhea
prevention, a cluster randomized controlled trial. Tropical Medicine and International
Health. Volume II No 4 PP 479-489.
Lwis Publishers. 2003. Hand Book of Water and Wastewater Treatment Operations. CRC
Press LLC
M. Ajmal Khan. 2007. Biosaline Agriculture in Pakistan. Department of Botany, University
of Karachi-75270, Pakistan.
M. Salequzzaman, S. M. Tariqul Islam, A. Tasnuva, M. A. Kashem And M. Mahedi Al
Masud. 2008. Environmental Impact of Sugar Industry - A Case Study on Kushtia
Sugar Mills in Bangladesh. j. innov.dev.strategy. 2(3): 31-35
M.H. Panhwar. Saline Agriculture snd Crops for Saline Soils and Water in Sindh.
Panhwar.com
M.Khan, U Kalsoom, T, Muhammad, M.Riaz and A.R. Khan. Characterization and
Treatment of Industrial Effluent from Sugar Industry. PCSIR Laboratories Peshawar
Mae-Wan Ho and Joe Cummins. 2009. Saline Agriculture to Feed and Fuel the World
http://www.i-sis.org.uk/full/SalineAgricultureFull.php
Magayane Machibya and Fredrick Mwanuzi. 2006. Effect of Low Quality Effluent from
Wastewater Stabilization Ponds to Receiving Bodies, Case of Kilombero Sugar Ponds
and Ruaha River, Tanzania. Int. J. Environ. Res. Public Health 2006, 3(2), 209-216
Memon M., et al., 2010. Drinking water quality assessment in Southern Sindh (Pakistan).
Environ Monit Assess Springer Science+Business Media B.V. 2010 (online
Publication)
Memon, A.R, 2004. ME Thesis on ‗Sugar Industry Effluent Analysis and its Impact on the
Local Environment‘ Musings: http://www.riazhaq.com/2009/03/water-scarce-
pakistan.html
N. Katerji. Productivity analysis of crops grown in saline environment: presentation of the
major research lines. Options Méditerranéennes Série B n. 36
National Commission on the Status of Women (NCSW). www.ncsw.gov.pk
National Drinking Water Policy (2009), Ministry of Environment, Government of Pakistan
National Environment Policy (2005), Ministry of Environment, Government of Pakistan
National Small Flows Clearinghouse West Virginia University. 1997. Lagoon system can
provide low cost wastewater treatment. Pipeline, Vol.8 No.2
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
92
NESPAK 1992. Fordwah Eastern Sadiqia (South) Phase-I Irrigation and Drainage Project,
PC-I PROFORMA. Lahore.
NESPAK-ACE-DMC 2009 Redesign og LBOD Stage-I Badin Area Drainage System.
Feasibility Report. WAPDA.
P.A. Hollington, Z. Hussain, MA Kahlown and M. Abdullah. 2001. Success stories in saline
agriculture in Pakistan: from research to production and development. BAC Saline
Agriculture Conference: March 19-21
Pakistan National policy for Development and Empowerment of women, March 2002,
www.quotaproject.org/CS/CS_Pakistan.pdf
Pak-SCEA (2006}.Pakistan Strategic Country Environmental Assessment Report.
PCRWR (2004), The Water Quality Report of the Pakistan Council for Research on Water
Resources
Rafique T., Naseem. S., Bhanger. M.I. and Usmani. T.H., ―Fluoride ion contamination in
ground water of Mithi sub-district, the Thar desert‖, Pakistan, Environ. Geol. 2007 (in
Press) DOI 10.1007/s00254-007-1167-y available on-line
Rashid Ahmad and M. H. Chang. 2002. Salinity Control and Environmental Protection
Through Halophytes. Journal of Drainage and Water Management, Vol.6(2)
RGNDWM (1993). Prevention and control of fluorosis. Vol. II. Water quality and
defluoridation techniques. New Delhi, India, Rajiv Gandhi National Drinking Water
Mission.
Riaz, H. (2009, March 21). World Water Day: Water Scarce Pakistan. Retrieved April 2009,
from Haq's Musings: http://www.riazhaq.com/2009/03/water-scarce-pakistan.html
S. Binu Kumari, A. Kavitha Kirubavathy and Rajammal Thirumalnesan. 2006. Suitability
and water quality criteria of an open drainage municipal sewage water at Coimbatore,
used for irrigation. Journal of Environmental Biology Triveni Enterprises, Lucknow
(India).
S. Lukman, J.A. Otun, A. Ismail, D.B. Adie, I.A. Oke2and U.A. Abubakar. 2010. Application of
Traditional & Modern Approaches to Waste Stabilization Pond Modelling & Design.
Department of Water Resources and Environmental Engineering, Ahmadu Bello University,
Zaria, Nigeria
Saleem Bashir, M., W. Wolters, and M.N. Bhutta. 1995. Effectiveness of Interceptor Drains
for Canal Seepage Recovery. In: Proceedings of the National Workshop on Drainage
Performance in Indus Plain and Future Strategies. (Volume III).
SDPI, Islamabad 2006. Study on Effluents from Selected Sugar Mills in Pakistan: Potential
Environmental, Health, and Economic Consequences of an Excessive Pollution Load.
SEPA (2002).‖Pilot Water Quality Monitoring‖ study report, sponsored by NDP WAPDA,
Hyderabad
Shah, M.T., and Danishwa,S. ―Potential fluoride contamination in drinking water of Naranji
area NWFP, Pakistan‖, Environ. Geochem. Health, 25, 475, 2003.
Shaheen Ashraf Shah, ‗Women and Masculine Domination in Water Institutions‘, Doctoral
Researcher on Women and Gender Studies, Department of Sociology, University of
Warwick, UK,
Shaheen Ashraf Shah, 2010, ‗Feminizing Water Institutions in Sindh, Pakistan‘, Hyderabad
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
93
Shun Dar Lin and C.C. Lee 2007. Water and Wastewater Calculations Manual. 2nd
Edition.
SIDA (2010) preparation of regional plan for the left bank of indus, delta and coastal zone
Volume I-IV, Louis Berger Group Inc and Indus Associated Consultants Ltd,
Hyderabad.
SIDA (Feb. 2003). ―Environmental Assessment of Sugar Industry in Sindh‖
SIDA (Jan. 2003). ―Sustainable Water Resources Management- issues and guidelines for
AWBs‖
Simi kaml, 2005, ‗Women and water, issues of entitlements, access and equity‘,
www.panipakistan.org.pk/
SODIS (2008). Solar Disinfection (SODIS) - CDC, January 2008)
SOE (2005). ‗State of the Environment Report 2005 (Draft)‘, Ministry of Environment,
Government of Pakistan
Sophie CHUETTE (2010), Team Leader ERU BHC French/Japanese/ Australian RC Dadu –
Sindh Pakistan floods operation(private Communication)
Souter PF, Cruckshank G.D., Tankerville M.Z. et al. 2003. Evaluation of a new water
treatment for point-of-use household applications to remove microorganisms and
arsenic from drinking water. Journal of Water and Health 1, 73-84
Sustainable Development Policy Institute, Nov 2007-July 2008, Pakistan: Country Gender
Profile http://www.jica.go.jp/activities/issues/gender/pdf/e08pak.pdf
Taej Mundkur, David Bakewell and Gabriel Chong 2009. Status of Waterbirds in Asia.
Wetlands International.
Tanwir, F., A. Saboor And Naima Nawaz 2003 Soil Salinity and the Livelihood Strategies of
Small Farmers: A Case Study in Faisalabad District, Punjab, Pakistan. Int. J. Agri.
Biol., Vol. 5, No. 4, 2003
Tech Brief, Development of Low-Cost Treatment Options for Arsenic Removal in Water
Treatment Facilities, Fall 2006, Vol. 6, Issue 3
The USAID and CDC (2009). ―Preventing Diarrheal Disease in Developing Countries :
Simple Options to Remove Turbidity ‖
http://www.usaid.gov/stories/pakistan/fp_pakistan_water.html
United Nations 2003. Waste-Water Treatment Technologies: A General Review.
US- EPA. 2006. Economic Benefits of Wetlands. U.S. EPA‘s website
USAID (2005). Press Release, USAID Announces Partnership with Procter and Gamble for
Pakistan Earthquake Survivors. October.
USAID / Pakistan Safe Drinking Water and Hygiene Promotion Project Page 5-7 - Technical
Review of POU and Community Water Treatment Technologies June 2008
W11, Threatened Birds of Indus Basin. Pakistan.
http://www.birdlife.org/action/science/species/asia_strategy/pdf_downloads/wetlands
W11.pdf
WAPDA (1994) Feasibility study SCARP Ghotki saline zone, final report volume I & II,
AHT Germany NESPAK Lahore, Pakistan.
SINDH WATER SECTOR IMPROVEMENT PHASE-I PROJECT
Preparation of Regional Plan for the Left Bank of Indus, Delta and Coastal Zone
94
WAPDA (2009) Feasibility study for redesign of LBOD Stage –I Badin area Drainage
system, NESPAK-ACE-DMC Joint venture (Volume-I, II)
WAPDA 1980. Lower Rechna Remaining Project Report (SCARP V). Volume I and II
WAPDA Project Planning Organization (N.Z.) Report N° 27. 106 B2 Gulberg III,
Lahore.
What is happening to them?
http://pecongress.org.pk/images/upload/books/Wetlands%20in%20Pakistan
WHO (2009). Scaling Up Household Water Treatment among Low-Income Populations
WHO (2011). Drinking-water from Desalination", WHO/HSE/WSH/11.03, World Health
Organization 2011
Wikipedia http://en.wikipedia.org/wiki/Water_supply_and_sanitation_in_Pakistan (modified
on 8 September 2011)
World Bank Report of the international panel of experts (2005)-Review of the performance
of the left bank outfall drain stage I, (DPOD, KPOD, Tidal Link and Cholrie weir).
World Bank, 1992. Staff Appraisal Report Pakistan Fordwah Eastern Sadiqia (South)
Irrigation and Drainage Project. South Asia Region, Country Department III,
Agriculture Operations Division. Report N° 10461-PAK.
World Bank, Oct. 2005, Pakistan Country Gender Assessment, Report No. 32244-PAK
http://repositorium.uni-osnabrueck.de/bitstream/urn:nbn:de:gbv:700-
2006053115/2/E-
Diss561_thesis.pdfhttp://siteresources.worldbank.org/PAKISTANEXTN/Resources/2
93051-1146639350561/CGA-Chapter-2.pdf Source:
(http://www3.weforum.org/docs/WEF_GenderGap_Report_2010.pdf, World
economic forum/ Gender Gap Report 2010/ country profile, pp 243
World Health Organization (2005) Sanitation and Hygiene Promotion: Programming
Guideline.
WWF (February 2007).Pakistan‘s waters at risk, water and health related issues in Pakistan
and key recommendations.
WWF Pakistan (2007-2012) Total Economic Valuation (TEV) of Ecosystems in the Indus
River Ecoregion. 2007.
WWI, Karachi (2011). Private communication