S-27 / Basics of the Project Schedule / AIA Convention 1998 / 1
S-27 Designing the Project Schedule
Phillip G. Bernstein, AIACesar Pelli & Associates
Yale University School of Architecture
S-27 / Basics of the Project Schedule / AIA Convention / 2
Overview
• Project Management and Control
• Purposes and objectives of a successful
schedule
• Components
• Organizing Principles
• Implementation and tools
• Discussion
S-27 / Basics of the Project Schedule / AIA Convention / 3
1 - Project Management and Control
• Changing responsibilities
• Client expectations
• Control and coordination
• Project Dynamics
• Collaboration
S-27 / Basics of the Project Schedule / AIA Convention / 4
2 - Schedule Objectives
• Project goals
• Apparent tasks, responsibilities
• Hierarchy
• Flexibility
• Clarity
S-27 / Basics of the Project Schedule / AIA Convention / 5
3 - Core Elements
• Milestones - date drivers
• Deliverables - work product
• Tasks - steps to create deliverables by
milestones
S-27 / Basics of the Project Schedule / AIA Convention / 6
3 - Core Elements
Milestones
Tasks
Deliverables
100% DD Review DD Enhancements Owner Review / CD Start?
Aug Sep Oct Nov Dec Jan Feb Mar Apr May
10172431 7 142128 5 121926 2 9 162330 7 142128 4 111825 1 8 1522 1 8 152229 5 121926 3 10
Agency Meeting M MUSP Application (Book)
S Plan Document Submission B Background submission to GT by CP&A
Page 1 of 1
Prepared by Cesar Pelli & Associates - Version 4.0 (11/15/97)MUSP / Approvals SequenceP E R F O R M I N G S A R T S C E N T E R O F G R E A T E R M I A M I
Approval Element Notes
Revised Docs Walk-through
Palma walkthrough new plans
Large Scale Development Committee (LSDC)
2:00 PMCPA "road show" to PW, Zoning, FDOT
Urban Development Review Board (UDRB)
3:00 PM including model photos; CPA, BAL & R&Q
Historic Env Preservation Board (HEPB)
9/2 submit app; 9/5 submit plans.4:30 "Time Certain"; CPA & R&Q; include Sears progress
Zoning Board7:00 PM by R&Q/WA .4 sets walk-through "stamped" submitted by 9/2 (Palma)
Planning Advisory Board
7:00 PM by R&Q/WA
Public Works Review (tentative)
Exact mtg sequence TBD; attendees?
Replatting
Federal Department of Transportation (tentative)
Submission package includes plans, details. Schedule of meetings?
City Commission
FINAL Presentation by CP for permitting, including models; MUSP and street closure
S
12/16
S
8/19
Conf
9/18
LSDC Mtg
S
12/16 1/12
URDB Mtg
S
9/59/16
HEPP Mtg
2/13
Possible Sears Progress Review?
M
9/5
S
12/16 2/23
M
9/5
S
12/16 2/18
M
9/5
Tent Plat
S
1/12
Replat
1/27 2/18
Street Vacationwith Zoning
12/1
WO Issued
S
1/12
Plat Plan
1/26
City Conds
S
3/9
Final Plat
3/23
City Comms
S
4/6
FDOTPkg
S
9/15 10/9
AgencyRev
Comments S
11/19
Rev Pkg
S
12/16
FinalSubmit
1/18
FinalApproval
M
9/5
S
1/12 3/24
City CommMUSP
4/24
City CommReplat
Schedule13 - 3/11/1998 - 23:29:43
Complete
Complete UPDATE FOR SEARS WORKPLAN
S-27 / Basics of the Project Schedule / AIA Convention / 7
3 - Core Elements
ID Task Name
1 GSA Review - Package 1
2 VE Session
3 GSA On-Board Reviews
4 Consultant Coord Meetings
5 PACKAGE 2 SUBMISSION
6 Package 1 Refinements
7 HLW DD Additional Information
8 Package 2 Work Items
9 Exterior Perspectives
10 Public Corridors
11 Elevator Lobby
12 Toilet Rooms
13 Elevator Cabs
14 Cafeteria
15 Jury Assembly
16 Conf/Collections
17 Jury Rooms
6/14 7/4
6/25 6/28
7/8 7/23
7/297/11 7/187/2
6/14 7/8
6/14 6/27
6/25 7/15
7/1 7/19
6/14 6/27
7/8 7/19
6/25 7/15
6/25 7/15
6/25 7/15
7/8 7/19
5/26 6/2 6/9 6/16 6/23 6/30 7/7 7/14 7/21 7/28 8/4
June 1996 July 1996
S-27 / Basics of the Project Schedule / AIA Convention / 8
4 - Organizing Principles
• Timeframe(s)
• Hierarchy
• Flexibility
• Legibility
• Ease of Updates
S-27 / Basics of the Project Schedule / AIA Convention / 9
4 - Organizing Principles
1998March April May June July August September October November December
97/98 School Year 98 Recess 98/99 School Year
Project Task D Deliverable Formal ReviewMeeting at EWS
Page 1 of 1
Cesar Pelli & Associates / Albis Turlington ArchitectsCOMPREHENSIVE FACILITY MASTER PLAN - Proposed Workplan
Work Element
Reviews
Strategic Plan
Space Utilization
Building Needs
Master Plan
Data Collection CurriculumInterviews
FMAttributes
Curriculum ProgramExisting Conditions
FM Progress Review
Campus PlanningProgress Review
Bldg NeedsMP Pre-Final
Final Report Presentation to Board
4/1
Curriculum Recommendations
9/30
4/1
Survey
6/1
Land Use
6/22
D
7/1
Existing Conditions Survey
4/1
Collect Current Data
6/1
Attributes
6/19
4/1
Compile Electronic Backgrounds
7/1
4/1
Curriculum Analysis
5/31
(E) Curr Pgm
7/1
D
7/11
Curriculum Program
9/30
Bldg Use Opts
10/31
4/18
Exterior Docs
5/30 7/1
Ext Assess
7/30
D
9/30
FM Database
7/1
Life Safety/Accessibility
8/31
7/1
Systems Review
8/31
FM Database
9/30
D
10/31
Building Needs Assessment
4/1
Survey/Interview/Research
5/30 7/1
Planning Analysis
8/30
9/1
Campus Plan
9/30
9/1
Landscape Options
9/30
9/1
Growth Options
10/15
9/15
Building Concepts
10/15
10/15
Fin Recs
10/31
Report Production D
12/1
Final Report
S-27 / Basics of the Project Schedule / AIA Convention / 10
4 - Organizing Principles
ID Task Name Duration
1 Contract Negotiation 103 days
2 Notice To Proceed 0 wks
3 PROGRAM VERIFICATION 13 wks
8 AREA-WIDE MASTERPLAN (contract)25 wks
35 SCHEMATIC DESIGN 25 wks
41 DESIGN DEVELOPMENT 69.2 wks
59 CONSTRUCTION DOCUMENTS 51 wks
67 SEARS BUILDING 34 wks
83 Demo/Stabilization Construction18 wks
84 BASE PROJECT BID/NEGOTIATION12 wks
88 BUILDING CONSTRUCTION 169 wks
2/1
4/22
22 7/19
22 10/11AR
7/22 1/10SC
1/13 5/11DESIGN DE
1/13 1/4CONST
3/15 11/6SEA
11/9 3/12
1/5 3/29
3/30 6/24BUILDING CONSTRUCTION
1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007
S-27 / Basics of the Project Schedule / AIA Convention 1998 / 11
4 - Organizing Principles
ID Task Name
8 AREA-WIDE MASTERPLAN (contract)
9 Master Plan Analysis
10 Owner Review
11 SD NTP
12 Scoping Definition
13 Notice to Proceed - UDAP
14 UDAP (Option A)
21 UDAP (Option B)
22 Information Gathering
23 Conceptual Alternatives
24 Initial Plan Development
25 Final Plan Development
26 Review and Adjustments
27 Final Presentation
28 UDAP (Option C)
35 SCHEMATIC DESIGN
36 50% SD
37 Owner Review
38 100% SD
39 Owner Review
40 DD NTP
4/22 10/11AREA-WIDE MASTERPLAN (contract)
4/22 7/8
7/9 7/22
7/22
4/22 5/8
5/8
5/8 7/12UDAP (Option A)
5/8 8/30UDAP (Option B)
5/8 5/24
5/27 6/19
6/19 7/12
7/15 7/31
7/31 8/14
8/14 8/30
5/8 10/11UDAP (Option C)
7/22 1/10SCHEMATIC DESIGN
7/22 10/4
10/4
10/7 12/20
12/23 1/10
1/10
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr1996
S-27 / Basics of the Project Schedule / AIA Convention / 12
4 - Organizing Principles
ID Task Name Dur
1 PROJECT REVIEWS 125d
2 New Haven Meetings 1d
3 Miami Meetings 1d
4 User Meetings 1d
5 Special Presentations 1d
6 Owner SD Review 4w
7 ARCHITECTURE 105d
8 SD Notice to Proceed 0d
9 50 % Schematics 56d
10 Program Analysis 3w
11 Building Code / Zoning Analysis 5w
12 Blocking/Stacking Diagrams (1:50) 3w
13 Preliminary Plan Diagrams (1/32) 36d
14 Massing Approaches (1/32) 4w
15 100% Schematics 49d
16 Resolved Plan Diagrams (1/32) 3w
17 Refined Massing Approach 3w
18 Exterior Forms and Materials 3w
19 Large Scale SD Plans, Specs (1/16) 2w
20 Public Space Expression 2w
7/31 UDAP 8/27 Con Kickoff 9/24 Consult
8/9 CC 9/10 PACT/CC/PCC 10/7 CC,
9/10 10/7
7/22
7/22 8/9
7/31 9/4
7/29 8/16
8/19 10/7
9/10 10/7
10/8
10/8
10/8
7/14 7/21 7/28 8/4 8/11 8/18 8/25 9/1 9/8 9/15 9/22 9/29 10/6ul '96 Aug '96 Sep '96
S-27 / Basics of the Project Schedule / AIA Convention 1998 / 13
5 - Implementation
• Set project objectives
• Set information requirements
• Establish milestones, deliverables, tasks
• Establish hierarchy
• Develop task list
• Integrate schedule elements
S-27 / Basics of the Project Schedule / AIA Convention / 14
5 - Implementation
1998
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Page 1 of 1 3/11/98
Construction Documents
December January February March April May
6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30
Agency Meeting M MUSP Application (Book)
S Plan Document Submission Review Sequence
Page 1 of 1
Approval Element Notes
S-27 / Basics of the Project Schedule / AIA Convention / 15
5 - Implementation
1997 1998 1999 2000 2001 2002
2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Fees 69 245 56 0 6 4Construction Costs 0 3016 2594 0 325 195
Soft Costs 13 134 13 0 3 2Total Costs 83 3374 2092 0 339 203
0
482
964
1446
1928
2410
2892
3374Gross Fees
Construction Costs
Soft Costs
Total Costs
Page 1 of 2 3/11/1998
Prepared by Cesar Pelli & AssociatesPreliminary Cash Flow Projection - OPTION 7c (Garage)CAMPUS MASTER PLAN - 9711
SoftCosts*
ConstructionCosts
GrossFeesPhase
1055Schematic Design
1574Design Development
20122Construction Documents
9015Permitting
519Bidding and Negotiation
2085Construction Admin-Phases 1-4
510Construction Admin-Phase 5
3245Construction Phase 1
1465Construction Phase 2
678Construction Phase 3
222Construction Phase 4
11/16 12/16
12/16 3/10
3/10 7/17
6/8 9/1
7/27 10/1
10/1 6/24
9/1 3/14
10/1 1/7
1/7 4/1
4/1 5/27
5/27 6/24
*Soft costs are projected only.
D:\@DOCS\AIA\aia98\Cash Flow Master.ml5 - 3/11/199
S-27 / Basics of the Project Schedule / AIA Convention / 16
• Software
Power: Primavera, MS Project
Comfort: Suretrak, Timeline…
Recommended: Milestones, Etc. 5.0
• Hardware
Input: processors, screen resolution
Output: format, color, scale
5 - Implementation
S-27 / Basics of the Project Schedule / AIA Convention / 17
6 - Discussion
November December January10 17 24 1 8 15 22 29 5 12
Page 1 of 1 3/11/1998
Version 1.1DESIGN DEVELOPMENT ENHANCEMENTS Proposed WorkplanPerforming Arts Center of Greater Miami
Project Issue
Meetings / Reviews
Revised Architectural Design Development Documents
Engineering / Cost Estimating
Owner Reviews
11/18
InitialCoordination
11/24
InterimCoord (ACM)
12/1
InterimCoord (ACM)
12/8
Poss ARTEC/FDACoord Mtg
12/16
PACT DDRevision Review
1/5
Possible Cost/ReconcilReview Meeting
12/16 REVISED DDSUBMISSION
12/12
Printing/Collation
12/15 1/5
Team Cost Review
1/7
11/19
Preliminary Docs
Not for Distribution
12/2
Refined Docs
Not for Distribution
12/12
11/19
Prelim SKs
11/25
Final SKs
12/2
Refined SE Docs
12/11
Docs Due to CP&A
12/16
Cost Check
1/5
Draft Out
1/7
Final
1/12
Model Out
11/18
NTP Revisions(Complete)
12/16
Docs Rec'd
12/20
Comment Period
1/5
Final CommentsDue
1/5 1/12
NTP CDs
D:\@SCHEDS\9602mdpac\ddend5.ml5 - 3/11/1998 - 23:36:39 Cesar Pelli & Associates Inc - 9602